SlideShare a Scribd company logo
1 of 15
About Organisation-
• Simplex infrastructure Ltd. is a diversified company established in 1924
and executing projects in several sectors like
• Transport, energy & power,mining, buildings, marine, real estate etc.
• Simplex is one of the construction leaders in India for nearly 90 years
executing projects with consistent quality assurance ,cost control and
adherence to milestones in a safe environment as per the customer
requirements. It promotes the culture of sharing rich and varied
experience with staff members ,as also with clients and thereby
benefits and helps the growth of the construction fraternity and
society at large.
• The company has been closely associated with the country
infrastructure buildings with over 2600 completed projects spanning
almost all the gamut construction industry.
Name of block No. Of floor in each
block
No. Of flat on each floor No. Of column in each
block
Plinth beam top level
(M)
BLOCK A(NO.1) G+10 THREE 52 99.000
BLOCK B (NO.2) G+10 TWO 39 99.500
BLOCK C (NO.3) G+10 TWO 36 99.500
BLOCK D (NO.4) G+11 FOUR 61 99.500
BLOCK E (NO.5) G+11 FOUR 65 100.000
BLOCK F ( NO.6) G+10 TWO 33 100.000
BLOCK G (NO.7) G+10 TWO 46 100.000
Total no. Of block-7
Total no. Of flat- 198
PRODUCTION OF CONCERETE
PRODUCTION PROCESS-
RAW MATERIALS –
Cement-PPC(Portland pozzolana cement) is using in this
project because it produces less heat of hydration and offers
greater resistance to the attack of aggressive water than
ordinary Portland cement.
Aggregate-
1. Coarse aggregate-20mm and 10mm size coarse aggregate are
using in concrete.
2. Fine aggregate –sand is used as fine aggregate which is finer than
4.75mm sieve size and grade of sand is well.
Water - Water used for mixing and curing should be clean and free
from injurious amounts of oils, acids, alkalis, salts, sugar, organic
materials or other substances that may be deleterious to concrete or
steel. Portable water is generally considered satisfactory for mixing
concrete.
Admixtures – SNF (sulphonated naphthalene-formaldehyde
condensates) is used as admixture. It is superplasticizer admixtures
which increases settling time of concrete and workability.
BATCHING AND MIXING –
• Weigh batching is using in batching
plant for making concrete. It produces
0.50 M3 concrete in one batch.
• Mixing is essential for the production
of uniform concrete. The mixing should
ensure that the mass becomes
homogeneous, uniform in colour and
consistency.
• Mixing time is 25 sec for each batch.
Placing of concrete in column
COMPACTION–
Compaction of concrete is the process adopted for expelling the
entrapped air from the concrete .If the air is not removed fully,the
concrete loses strength considerably.60mm needle vibrator of 1.5kv or
3kv is using at site for compaction of concrete in column and surface
vibrator is using for compaction of concrete in slab.
CURING-
The curing can be considered as creation of a favourable environment
during the early period for uninterrupted hydration. Water curing is
using for slabs, beams , masonry work and membrane curing or curing
compound is using for curing of columns and outer face of beams for
conservation of water.
BUILDING MATERIALS –
• BRICK
• CLC BLOCK
• CEMENT
• SAND
• COARSE AGGREGATE
• STEEL
Testing for brick
Dimension Test- A set of twenty brick are laying in a raw
then measure it’s length ,width and height one by one
and brick is okay if the avg. dimension of one brick is
230x110x75mm.
Efflorescence Test-In this, brick is submersed in 1” water
for 48 hours and brick is said to be okay if efflorescence
is less than 50% of total surface.
Testing for cement –
Field testing-
• Open the bag and there should not be any visible lumps.
• The colour of the cement should normally be greenish grey.
• Take a pinch of cement and feel between the fingers. It
should give a smooth and not a gitty feeling.
• Take a handful of cement and throw it on a bucket full of
water,the particle should float for some time before they
sink.
Testing of Coarse Aggregate –
Toughness test or impact value test for 10mm aggregate-
The aggregate impact value gives relative measure of the resistance of
an aggregate to sudden shock or impact. The test sample consists of
aggregate passing through 12.5mm and retained on 10mm I.S. sieve.
Then the aggregate dried in an oven for a period of four hours at a
temperature of 100oC and cooled. The whole sample is filled into a
cylindrical steel cup firmly fixed on the base of the machine. A hammer
weighing about 14 kg is raise about to a height of 380mm above the
upper surface of the aggregate in the cup and allowed to fall freely on
the aggregate. Then the test sample subjected to a total 15 such blows
each being delivered at an interval of not less than one second. The
crushed aggregate is removed from the cup and whole of it is sieved on
2.36mm I.S.sieve. 3
-
BRICK MASONRY – It is using in
partition wall of flat in this project.
Layout out of brick masonry is
occurring with the help of thread
and plumb bob. Between two brick
layer we are providing 10 to 12 mm
cement mortar (1:6).According to
my calculation for masonry work
electrical substation, there is 383
bricks and thickness of mortar is
16mm in 1 m3 work And in
partition wall of block 4 ,there is
415 bricks in 1m3 and 10mm
mortar.
WALL FINISHING- For wall finishing
we provided 12mm thick cement
mortar layer and 2-3mm pop layer.
For strong bonding and strong
cohesion we used cement slurry
before plastering. Skill labour require
for plastering. For plastering finishing
we used planner of different -2 sizes
6ft,8ft and c/s is 70x40mm.
FLOOR FINISHING- for floor finishing we provided 40mm mortar (1:5) and 10mm
thick tiles. Digital glazed vitrified tiles are using in the project. The size of tile is
800x800mm.
SKIRTING -tiles are provided at the bottom of the wall is known as skirting.
100mm skirting are providing in this project.
TRAP –is a device which is
used to prevent sewer gases
from entering the building.
The traps are located below
or within a plumbing fixture
and retain some amount of
water. The retaining water
creates a water seal which
stops foul gases going back
to the building from drain
pipes. Therefore all
plumbing fixtures such as
sinks, washbasin, bathtubs
and toilets are equipped
with traps.
P-TRAP
Q-TRAP
CONCLUSION
The main aim of studies within this project was to investigate how a structure is constructed
within its desired properties. We get knowledge about the basic & advanced techniques
of building construction as well as saw the challenges which a civil engineer have to face
during construction i.e. labour problems, cost management, environmental challenges etc. We
cleared our many doubts regarding building construction. We had seen dewatering system at
project site for construction which is not used at our state anymore, so it was a new thing for
us.
Although are subjects more important for technicians, in the project we have been Studied
some mechanic or electro-mechanic machinery such as the ready mix plant because basic
knowledge about their working is important for an engineer but also because was the
opportunity to see and understand them. Overhaul it must be said that the construction
methods and quality control on a highway Project needs a very good coordination and
large quantities of man power, equipment and funds.
During the period of two month all the company staff helped us a lot to provide all the
information about any query. So we are grateful to all the staff of Simplex Infrastructures ltd. ,
as well as we are so thankful to our Civil Engineering Department for their kind support.

More Related Content

What's hot

Mukesh ppt
Mukesh pptMukesh ppt
Mukesh pptHJ Sims
 
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTUVATSAL PATEL
 
Gravel Roads - The Economic Backbone of the State
Gravel Roads - The Economic Backbone of the StateGravel Roads - The Economic Backbone of the State
Gravel Roads - The Economic Backbone of the StateUGPTI
 
Design of special pavements as per IRC SP 20
Design of special pavements as per IRC SP 20Design of special pavements as per IRC SP 20
Design of special pavements as per IRC SP 20GOVERNMENT POLYTECHNIC
 
Cold mix bituminous plant
Cold mix bituminous plantCold mix bituminous plant
Cold mix bituminous plantpradip dangar
 
Dense Bituminous macadam
Dense Bituminous macadamDense Bituminous macadam
Dense Bituminous macadampradip dangar
 
Pavement materials in Road Construction
Pavement materials in Road ConstructionPavement materials in Road Construction
Pavement materials in Road Constructionsrinivas2036
 
DELHI-AGRA ROAD PROJECT
DELHI-AGRA ROAD PROJECTDELHI-AGRA ROAD PROJECT
DELHI-AGRA ROAD PROJECTGLA University
 
cement road construction in the rural areas
cement road construction in the rural areas cement road construction in the rural areas
cement road construction in the rural areas Anshul Shakya
 
Construction of flexible pavements
Construction of flexible pavementsConstruction of flexible pavements
Construction of flexible pavementspradip dangar
 
Construction of flexible pavement in brief.
Construction of flexible pavement in brief.Construction of flexible pavement in brief.
Construction of flexible pavement in brief.AJINKYA THAKRE
 
Chapter3 road pavement
Chapter3 road pavementChapter3 road pavement
Chapter3 road pavementpokjak80
 
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICEHIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY CONSTRUCTION MATERIAL & PRACTICEFresher Thinking
 
Lec 09 Pavement Design (Transportation Engineering)
Lec 09 Pavement Design (Transportation Engineering) Lec 09 Pavement Design (Transportation Engineering)
Lec 09 Pavement Design (Transportation Engineering) Hossam Shafiq I
 
Maintenance of unsurfaced roads, wbm roads
Maintenance of unsurfaced roads, wbm roadsMaintenance of unsurfaced roads, wbm roads
Maintenance of unsurfaced roads, wbm roadsDhrubajyoti Majumdar
 
Pavement materials and testing
Pavement materials and testingPavement materials and testing
Pavement materials and testingArchana Shagoti
 
presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)alamrintu
 

What's hot (20)

Mukesh ppt
Mukesh pptMukesh ppt
Mukesh ppt
 
Bituminous pavement
Bituminous pavementBituminous pavement
Bituminous pavement
 
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
 
Gravel Roads - The Economic Backbone of the State
Gravel Roads - The Economic Backbone of the StateGravel Roads - The Economic Backbone of the State
Gravel Roads - The Economic Backbone of the State
 
Civil Engineering
Civil EngineeringCivil Engineering
Civil Engineering
 
Design of special pavements as per IRC SP 20
Design of special pavements as per IRC SP 20Design of special pavements as per IRC SP 20
Design of special pavements as per IRC SP 20
 
Cold mix bituminous plant
Cold mix bituminous plantCold mix bituminous plant
Cold mix bituminous plant
 
Unit 4
Unit 4Unit 4
Unit 4
 
Dense Bituminous macadam
Dense Bituminous macadamDense Bituminous macadam
Dense Bituminous macadam
 
Pavement materials in Road Construction
Pavement materials in Road ConstructionPavement materials in Road Construction
Pavement materials in Road Construction
 
DELHI-AGRA ROAD PROJECT
DELHI-AGRA ROAD PROJECTDELHI-AGRA ROAD PROJECT
DELHI-AGRA ROAD PROJECT
 
cement road construction in the rural areas
cement road construction in the rural areas cement road construction in the rural areas
cement road construction in the rural areas
 
Construction of flexible pavements
Construction of flexible pavementsConstruction of flexible pavements
Construction of flexible pavements
 
Construction of flexible pavement in brief.
Construction of flexible pavement in brief.Construction of flexible pavement in brief.
Construction of flexible pavement in brief.
 
Chapter3 road pavement
Chapter3 road pavementChapter3 road pavement
Chapter3 road pavement
 
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICEHIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
 
Lec 09 Pavement Design (Transportation Engineering)
Lec 09 Pavement Design (Transportation Engineering) Lec 09 Pavement Design (Transportation Engineering)
Lec 09 Pavement Design (Transportation Engineering)
 
Maintenance of unsurfaced roads, wbm roads
Maintenance of unsurfaced roads, wbm roadsMaintenance of unsurfaced roads, wbm roads
Maintenance of unsurfaced roads, wbm roads
 
Pavement materials and testing
Pavement materials and testingPavement materials and testing
Pavement materials and testing
 
presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)
 

Similar to Simplex Infrastructure's Construction Methods and Quality Standards

Module-1_INTRODUCTION TO CIVIL ENGINEERING AND CIVIL ENGINEERING MATERIALS.pptx
Module-1_INTRODUCTION TO CIVIL ENGINEERING AND CIVIL ENGINEERING MATERIALS.pptxModule-1_INTRODUCTION TO CIVIL ENGINEERING AND CIVIL ENGINEERING MATERIALS.pptx
Module-1_INTRODUCTION TO CIVIL ENGINEERING AND CIVIL ENGINEERING MATERIALS.pptxSilasChaudhari
 
Building materials, Basic civil engineering ,unit-1
Building materials, Basic civil engineering ,unit-1Building materials, Basic civil engineering ,unit-1
Building materials, Basic civil engineering ,unit-1Parimal Jha
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptxHimanshumangal12
 
Cement Plastering procedure
Cement Plastering procedureCement Plastering procedure
Cement Plastering procedureSyed Javed
 
Lowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure servicesLowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure servicesAr Jitendra
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxARUNKUMARC39
 
Building materials pdf
Building materials pdfBuilding materials pdf
Building materials pdfSaqib Imran
 
capstoe PPT FINAL GLAX G.S.pptx
capstoe PPT FINAL GLAX G.S.pptxcapstoe PPT FINAL GLAX G.S.pptx
capstoe PPT FINAL GLAX G.S.pptxYogitaSalunke1
 
Gangaram yadav ppt road con....
Gangaram yadav ppt road con....Gangaram yadav ppt road con....
Gangaram yadav ppt road con....RaazYadav6
 
IRJET - Effect of Silica Fume on Properties of Concrete
IRJET -  	  Effect of Silica Fume on Properties of ConcreteIRJET -  	  Effect of Silica Fume on Properties of Concrete
IRJET - Effect of Silica Fume on Properties of ConcreteIRJET Journal
 
Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)A Makwana
 
Strength Characteristics of Concrete Produced by Replacing Fine Aggregates wi...
Strength Characteristics of Concrete Produced by Replacing Fine Aggregates wi...Strength Characteristics of Concrete Produced by Replacing Fine Aggregates wi...
Strength Characteristics of Concrete Produced by Replacing Fine Aggregates wi...IRJET Journal
 

Similar to Simplex Infrastructure's Construction Methods and Quality Standards (20)

Module-1_INTRODUCTION TO CIVIL ENGINEERING AND CIVIL ENGINEERING MATERIALS.pptx
Module-1_INTRODUCTION TO CIVIL ENGINEERING AND CIVIL ENGINEERING MATERIALS.pptxModule-1_INTRODUCTION TO CIVIL ENGINEERING AND CIVIL ENGINEERING MATERIALS.pptx
Module-1_INTRODUCTION TO CIVIL ENGINEERING AND CIVIL ENGINEERING MATERIALS.pptx
 
Building materials, Basic civil engineering ,unit-1
Building materials, Basic civil engineering ,unit-1Building materials, Basic civil engineering ,unit-1
Building materials, Basic civil engineering ,unit-1
 
Abhishek presentation.pptx
Abhishek presentation.pptxAbhishek presentation.pptx
Abhishek presentation.pptx
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
 
Concrete pdf
Concrete pdfConcrete pdf
Concrete pdf
 
Cement Plastering procedure
Cement Plastering procedureCement Plastering procedure
Cement Plastering procedure
 
Is 456 codal provisions
Is 456 codal provisionsIs 456 codal provisions
Is 456 codal provisions
 
Lowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure servicesLowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure services
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptx
 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
 
Building materials pdf
Building materials pdfBuilding materials pdf
Building materials pdf
 
capstoe PPT FINAL GLAX G.S.pptx
capstoe PPT FINAL GLAX G.S.pptxcapstoe PPT FINAL GLAX G.S.pptx
capstoe PPT FINAL GLAX G.S.pptx
 
Cement.pptx
Cement.pptxCement.pptx
Cement.pptx
 
Gangaram yadav ppt road con....
Gangaram yadav ppt road con....Gangaram yadav ppt road con....
Gangaram yadav ppt road con....
 
IRJET - Effect of Silica Fume on Properties of Concrete
IRJET -  	  Effect of Silica Fume on Properties of ConcreteIRJET -  	  Effect of Silica Fume on Properties of Concrete
IRJET - Effect of Silica Fume on Properties of Concrete
 
Getting the construction right
Getting the construction rightGetting the construction right
Getting the construction right
 
Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)
 
Suraj presentation.pptx
Suraj presentation.pptxSuraj presentation.pptx
Suraj presentation.pptx
 
4
44
4
 
Strength Characteristics of Concrete Produced by Replacing Fine Aggregates wi...
Strength Characteristics of Concrete Produced by Replacing Fine Aggregates wi...Strength Characteristics of Concrete Produced by Replacing Fine Aggregates wi...
Strength Characteristics of Concrete Produced by Replacing Fine Aggregates wi...
 

Recently uploaded

BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
Micromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersMicromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersChitralekhaTherkar
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
PSYCHIATRIC History collection FORMAT.pptx
PSYCHIATRIC   History collection FORMAT.pptxPSYCHIATRIC   History collection FORMAT.pptx
PSYCHIATRIC History collection FORMAT.pptxPoojaSen20
 

Recently uploaded (20)

BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
Micromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersMicromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of Powders
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
PSYCHIATRIC History collection FORMAT.pptx
PSYCHIATRIC   History collection FORMAT.pptxPSYCHIATRIC   History collection FORMAT.pptx
PSYCHIATRIC History collection FORMAT.pptx
 

Simplex Infrastructure's Construction Methods and Quality Standards

  • 1. About Organisation- • Simplex infrastructure Ltd. is a diversified company established in 1924 and executing projects in several sectors like • Transport, energy & power,mining, buildings, marine, real estate etc. • Simplex is one of the construction leaders in India for nearly 90 years executing projects with consistent quality assurance ,cost control and adherence to milestones in a safe environment as per the customer requirements. It promotes the culture of sharing rich and varied experience with staff members ,as also with clients and thereby benefits and helps the growth of the construction fraternity and society at large. • The company has been closely associated with the country infrastructure buildings with over 2600 completed projects spanning almost all the gamut construction industry.
  • 2. Name of block No. Of floor in each block No. Of flat on each floor No. Of column in each block Plinth beam top level (M) BLOCK A(NO.1) G+10 THREE 52 99.000 BLOCK B (NO.2) G+10 TWO 39 99.500 BLOCK C (NO.3) G+10 TWO 36 99.500 BLOCK D (NO.4) G+11 FOUR 61 99.500 BLOCK E (NO.5) G+11 FOUR 65 100.000 BLOCK F ( NO.6) G+10 TWO 33 100.000 BLOCK G (NO.7) G+10 TWO 46 100.000 Total no. Of block-7 Total no. Of flat- 198
  • 3. PRODUCTION OF CONCERETE PRODUCTION PROCESS- RAW MATERIALS – Cement-PPC(Portland pozzolana cement) is using in this project because it produces less heat of hydration and offers greater resistance to the attack of aggressive water than ordinary Portland cement.
  • 4. Aggregate- 1. Coarse aggregate-20mm and 10mm size coarse aggregate are using in concrete. 2. Fine aggregate –sand is used as fine aggregate which is finer than 4.75mm sieve size and grade of sand is well. Water - Water used for mixing and curing should be clean and free from injurious amounts of oils, acids, alkalis, salts, sugar, organic materials or other substances that may be deleterious to concrete or steel. Portable water is generally considered satisfactory for mixing concrete. Admixtures – SNF (sulphonated naphthalene-formaldehyde condensates) is used as admixture. It is superplasticizer admixtures which increases settling time of concrete and workability.
  • 5. BATCHING AND MIXING – • Weigh batching is using in batching plant for making concrete. It produces 0.50 M3 concrete in one batch. • Mixing is essential for the production of uniform concrete. The mixing should ensure that the mass becomes homogeneous, uniform in colour and consistency. • Mixing time is 25 sec for each batch. Placing of concrete in column
  • 6. COMPACTION– Compaction of concrete is the process adopted for expelling the entrapped air from the concrete .If the air is not removed fully,the concrete loses strength considerably.60mm needle vibrator of 1.5kv or 3kv is using at site for compaction of concrete in column and surface vibrator is using for compaction of concrete in slab.
  • 7. CURING- The curing can be considered as creation of a favourable environment during the early period for uninterrupted hydration. Water curing is using for slabs, beams , masonry work and membrane curing or curing compound is using for curing of columns and outer face of beams for conservation of water.
  • 8. BUILDING MATERIALS – • BRICK • CLC BLOCK • CEMENT • SAND • COARSE AGGREGATE • STEEL
  • 9. Testing for brick Dimension Test- A set of twenty brick are laying in a raw then measure it’s length ,width and height one by one and brick is okay if the avg. dimension of one brick is 230x110x75mm. Efflorescence Test-In this, brick is submersed in 1” water for 48 hours and brick is said to be okay if efflorescence is less than 50% of total surface.
  • 10. Testing for cement – Field testing- • Open the bag and there should not be any visible lumps. • The colour of the cement should normally be greenish grey. • Take a pinch of cement and feel between the fingers. It should give a smooth and not a gitty feeling. • Take a handful of cement and throw it on a bucket full of water,the particle should float for some time before they sink.
  • 11. Testing of Coarse Aggregate – Toughness test or impact value test for 10mm aggregate- The aggregate impact value gives relative measure of the resistance of an aggregate to sudden shock or impact. The test sample consists of aggregate passing through 12.5mm and retained on 10mm I.S. sieve. Then the aggregate dried in an oven for a period of four hours at a temperature of 100oC and cooled. The whole sample is filled into a cylindrical steel cup firmly fixed on the base of the machine. A hammer weighing about 14 kg is raise about to a height of 380mm above the upper surface of the aggregate in the cup and allowed to fall freely on the aggregate. Then the test sample subjected to a total 15 such blows each being delivered at an interval of not less than one second. The crushed aggregate is removed from the cup and whole of it is sieved on 2.36mm I.S.sieve. 3 -
  • 12. BRICK MASONRY – It is using in partition wall of flat in this project. Layout out of brick masonry is occurring with the help of thread and plumb bob. Between two brick layer we are providing 10 to 12 mm cement mortar (1:6).According to my calculation for masonry work electrical substation, there is 383 bricks and thickness of mortar is 16mm in 1 m3 work And in partition wall of block 4 ,there is 415 bricks in 1m3 and 10mm mortar.
  • 13. WALL FINISHING- For wall finishing we provided 12mm thick cement mortar layer and 2-3mm pop layer. For strong bonding and strong cohesion we used cement slurry before plastering. Skill labour require for plastering. For plastering finishing we used planner of different -2 sizes 6ft,8ft and c/s is 70x40mm. FLOOR FINISHING- for floor finishing we provided 40mm mortar (1:5) and 10mm thick tiles. Digital glazed vitrified tiles are using in the project. The size of tile is 800x800mm. SKIRTING -tiles are provided at the bottom of the wall is known as skirting. 100mm skirting are providing in this project.
  • 14. TRAP –is a device which is used to prevent sewer gases from entering the building. The traps are located below or within a plumbing fixture and retain some amount of water. The retaining water creates a water seal which stops foul gases going back to the building from drain pipes. Therefore all plumbing fixtures such as sinks, washbasin, bathtubs and toilets are equipped with traps. P-TRAP Q-TRAP
  • 15. CONCLUSION The main aim of studies within this project was to investigate how a structure is constructed within its desired properties. We get knowledge about the basic & advanced techniques of building construction as well as saw the challenges which a civil engineer have to face during construction i.e. labour problems, cost management, environmental challenges etc. We cleared our many doubts regarding building construction. We had seen dewatering system at project site for construction which is not used at our state anymore, so it was a new thing for us. Although are subjects more important for technicians, in the project we have been Studied some mechanic or electro-mechanic machinery such as the ready mix plant because basic knowledge about their working is important for an engineer but also because was the opportunity to see and understand them. Overhaul it must be said that the construction methods and quality control on a highway Project needs a very good coordination and large quantities of man power, equipment and funds. During the period of two month all the company staff helped us a lot to provide all the information about any query. So we are grateful to all the staff of Simplex Infrastructures ltd. , as well as we are so thankful to our Civil Engineering Department for their kind support.