Welcome to Crossrail
Opportunites
Dafydd Hughes
Head of Construction
Welsh Government
Steven Kay & Simon Pain
Crossrail
CROSSRAIL
MOVING LONDON FORWARD
Steven Kay
Central Area Delivery Director
Simon Pain
Principal Programme Supply Chain Manager
Header here max 30 charactersCrossrail Route
Header here max 30 characters
Overall, 90% complete
Tunnelling completed in East London and
Docklands
Short video
Final westbound section to Farringdon
Then onto systems, fit out, M & E …
Tunnelling is almost complete
Header here max 30 charactersCrossrail: delivering a railway
13 14 15 16 17 182012
Railway Systems
Stations
Rolling Stock & Depot
NR Surface Works
TestandCommission
TrialOperation
Crossrail TOC
Civils and
Tunnelling
Property
Acquisition
OSD & Urban Realm
Header here max 30 charactersCrossrail benefits
£42bn+
24
14,000 people
24 trains per hour
200 million journeys per year
Header here max 30 charactersCentral stations
Tottenham Court Road Station
Header here max 30 charactersRolling stock
Header here max 30 characters
2014
379 Apprentices
8,565 enrolled at TUCA
10,000+ employed on the project
746 workers previously unemployed
All figures are running totals bar “employed on project”
Skills development
Header here max 30 charactersWallasea Island 2016
Header here max 30 characters
What the Crossrail
Supply Chain looks like,
How you can improve
your chances of getting
into it.
Crossrail Supply Chain
Header here max 30 charactersOpportunities on Crossrail
Header here max 30 charactersCrossrail in Wales
• Over £20m awarded in Wales
• £12m Neath area
• £8m Newport and Cardiff
• Reinforcement bars
• Piling
• Props
• Structural steel
Identifying the opportunities
19
Header here max 30 charactersEnergy saving technologies
Energy Technology Products List
Enhanced Capital Allowances
https://etl.decc.gov.uk
Be prepared
Existing Networks
Website and guidance - www.Crossrail.co.uk
www.CompeteFor.com
Header here max 30 characters
Thank you
SteveKay@crossrail.co.uk simonPain@crossrail.co.uk
Simon Poulter & Oliver Thompson Smith
Laing O’Rourke
© Laing O’Rourke 2014, all rights reserved.25
Crossrail Event
2014 - St David’s Hotel Ewloe
© Laing O’Rourke 2014, all rights reserved.26
© Laing O’Rourke 2014, all rights reserved.27
© Laing O’Rourke 2014, all rights reserved.28
© Laing O’Rourke 2014, all rights reserved.29
© Laing O’Rourke 2014, all rights reserved.30 © Laing O’Rourke 2014, all rights reserved.30
The Laing O’Rourke /
Crossrail Projects
© Laing O’Rourke 2014, all rights reserved.31
The Projects:
C502 Liverpool Street
C422 Tottenham Court Road
C520 Custom House
Crossrail Event- St David’s Hotel Ewloe
© Laing O’Rourke 2014, all rights reserved.32
C502 – Liverpool
Street Station
© Laing O’Rourke 2014, all rights reserved.33
Liverpool Street: Plan View
Liverpool Street Mainline
Station
Broadgate THBlomfield Box
Moorgate TH Moorgate Station
Moorgate Shaft
LU Liverpool Street Station
Crossrail Platforms
Crossrail Event- St David’s Hotel Ewloe
© Laing O’Rourke 2014, all rights reserved.34
C502
2014
Structural Steelwork
Scaffolding
Screeds & Render
2015
Dry lining
FF&E Works
Decoration
Landscaping
Commissioning
Sub-Mains Cabling Pulling
Thermal Insulation
Trace Heating
Distribution Boards
Fire Stopping
Crossrail Event- St David’s Hotel Ewloe
© Laing O’Rourke 2014, all rights reserved.35
Supply Chain Summit 2014 - Bristol
C422 – Tottenham
Court Road
© Laing O’Rourke 2014, all rights reserved.36
Western Ticket Hall
(WTH)
Dean Street Box
Westbound
CRL Tunnel
Eastbound
CRL Tunnel
Central Line
Centre Point
Goslett Yard
Box (GYB)
Northern Line
Crossrail Event- St David’s Hotel Ewloe
© Laing O’Rourke 2014, all rights reserved.37
C422
2014
Scaffolding
Screeds & Render
General Metalwork
2015
Soft Floor Finishes
Epoxy Flooring
Decoration
Thermal Insulation
Distribution Boards
Durasteel Cladding
Luminaries
Dampers - Smoke
2016
Landscaping
Road Surfacing
Crossrail Event- St David’s Hotel Ewloe
© Laing O’Rourke 2014, all rights reserved.38
C520 – Custom
House
© Laing O’Rourke 2014, all rights reserved.39
C520
2014
Soft Landscaping
Commissioning Management
2015
Hard Landscaping
FF&E
Signage & Totems
Electric Panel Heaters
Small Transformer
Chlorination – Water Treatment
Crossrail Event- St David’s Hotel Ewloe
© Laing O’Rourke 2014, all rights reserved.40 © Laing O’Rourke 2014, all rights reserved.40
Becoming Part of the
Supply Chain
© Laing O’Rourke 2014, all rights reserved.41
LO’R
Preferred
Supply
Chain
Partner
Financial
Appraisal (D&B
Report)
Financial
Capacity
Checks
Health & Safety
Checks (SSIP)
Past
Performance
Data
On Site
Subcontractor
Questionnaire
(where
applicable)
Asite Pre-
Qualification
(Tiered Supply
Chain)
Crossrail Event- St David’s Hotel Ewloe
© Laing O’Rourke 2014, all rights reserved.42
✓
X
Supplier Turnover (£) Total Package Value April 13 - March 14 % of t/o April 14 - March 15 % of t/o April 15 - March 16 % of t/o
£ 12,654,248.00 £ 2,271,202.30 £245,535.38 2% £1,104,909.23 9% £920,757.69 7%
£ 3,133,000.00 £ 2,271,202.30 £245,535.38 8% £1,104,909.23 35% £920,757.69 29%
£ 2,479,595.00 £ 2,271,202.30 £245,535.38 10% £1,104,909.23 45% £920,757.69 37%
£ 955,188.00 £ 2,271,202.30 £245,535.38 26% £1,104,909.23 116% £920,757.69 96%
£ 8,859,045.00 £ 2,271,202.30 £245,535.38 3% £1,104,909.23 12% £920,757.69 10%
FINANCIAL ACCREDITATION
© Laing O’Rourke 2014, all rights reserved.43
Crossrail Event- St David’s Hotel Ewloe
© Laing O’Rourke 2014, all rights reserved.44
Crossrail Event- St David’s Hotel Ewloe
© Laing O’Rourke 2014, all rights reserved.45 © Laing O’Rourke 2014, all rights reserved.45
What is Responsible
Procurement?
© Laing O’Rourke 2014, all rights reserved.46
Crossrail Event- St David’s Hotel Ewloe
The Greater London Authority defines Responsible Procurement as:
“The purchase of goods, works and services in a socially and
environmentally responsible way that delivers value for money and
benefits to the contracting authority and to London”
© Laing O’Rourke 2014, all rights reserved.47
Crossrail Event- St David’s Hotel Ewloe
Workforce
welfare
Workforce
welfare
Environmental
Sustainability
Environmental
Sustainability
Ethical Sourcing
Ethical Sourcing
Skills
and
employment
Skills
and
employment
Community
Benefits
Community
Benefits
Supplier
Diversity
Supplier
Diversity
Fair
Employment
Fair
Employment
Responsible
Procurement
Responsible
ProcurementClimate change,
pollution and
natural resource
management.
London Living Wage
(LLW) and working
conditions.
Supply chain
diversity and
equality.
Community
initiatives e.g.
tackling crime and
disorder.
Training and
employment
opportunities &
meeting skills
shortage.
Ensuring
standards of
labour
conditions and
human rights in
the supply chain.
Union
representation
and worker’s
rights.
Workforce
welfare
Workforce
welfare
Environmental
Sustainability
Environmental
Sustainability
Ethical Sourcing
Ethical Sourcing
Skills
and
employment
Skills
and
employment
Community
Benefits
Community
Benefits
Supplier
Diversity
Supplier
Diversity
Fair
Employment
Fair
Employment
Responsible
Procurement
Responsible
Procurement
Workforce
welfare
Workforce
welfare
Environmental
Sustainability
Environmental
Sustainability
Ethical Sourcing
Ethical Sourcing
Skills
and
employment
Skills
and
employment
Community
Benefits
Community
Benefits
Supplier
Diversity
Supplier
Diversity
Fair
Employment
Fair
Employment
Responsible
Procurement
Responsible
ProcurementClimate change,
pollution and
natural resource
management.
London Living Wage
(LLW) and working
conditions.
Supply chain
diversity and
equality.
Community
initiatives e.g.
tackling crime and
disorder.
Training and
employment
opportunities &
meeting skills
shortage.
Ensuring
standards of
labour
conditions and
human rights in
the supply chain.
Union
representation
and worker’s
rights.
Seven Themes Under the Crossrail RP Policy
© Laing O’Rourke 2014, all rights reserved.48 © Laing O’Rourke 2014, all rights reserved.48
Laing O’Rourke’s Use
of CompeteFor
© Laing O’Rourke 2014, all rights reserved.49
Summary of Custom House to Date
25No. Existing planned opportunities advertised on CompeteFor with a combined value of approx.
£5.6million.
198No. Companies registered an interest on CompeteFor for these opportunities.
100No. Of these companies were shortlisted.
31No. Were recommended to be invited to tender for one or more of the 19No. opportunities.
7No. Of which were previously unknown to Laing O’Rourke
19No. Opportunities of the 25No. advertised have now been awarded.
6No. Awarded to a company from CompeteFor for have a combined value of £2,373,625.38
Crossrail Event- St David’s Hotel Ewloe
© Laing O’Rourke 2014, all rights reserved.50
Compete For
• Compete For Tailored Questionnaire
• Answers Scored
• Anonymous Long list turned Top Eight Shortlist
Potential Tender
Schedule
• Compete For Shortlist
• LO’R Tiered Supply Chain
• Past Performance, SSIP, Building Confidence, DNBi, Capacity Modelling
Approved Tender
List
• Approved Tender List issued to Crossrail
Crossrail Event- St David’s Hotel Ewloe
© Laing O’Rourke 2014, all rights reserved.51
Simon Tayor
Costain-Skanska
Simon Taylor
Costain-Skanska Environmental Manager
CSJV Working in Collaboration with
Crossrail
Moving London Forward
Fisher Street
Paddington
Eleanor Street and
Mile End Park
Stepney Green
and Limmo
Bond Street
CSJV Projects
C360 Eleanor Street and Mile End Park
Summary of Scope
Mile End shaft – 10m dia. 30m deep shaft constructed using PC
segments and Sprayed Concrete Lining (SCL)
Eleanor Street shaft – 16.4m dia. 36m deep shaft constructed using
PC segments and SCL
Status
95% of supply chain packages are procured
Packages left to go...
Headhouse Construction - £1.4M (Jan 15)
Landscaping - £0.4M (Jan 15)
Construction starts (July 15 – Feb 16)
12/3/2014 58
C412 Bond Street
Summary of Scope
Connecting shaft and tunnels from street level to main running
tunnels
Status
All supply chain packages are yet to be procured
Works start early to mid 2015
Secondary Linings
Roofing
Cladding
Fixtures and fittings
Hard Landscaping
C405 Paddington
Summary of scope
Underground Box construction to form station at running tunnels with
fit out
Status
Supply chain packages are yet to be procured
All to be procured between now and Feb 2015
Cladding (Metal and bwk)
Roofing (Kalzip)
Car Park
Fit out (Carpet and curtains)
Fixtures and fittings
Street furniture and hard landscaping
Limmo
Peninsular
Fisher Street
Stepney Green
C335 Shaft Fit Out and Headhouses
Summary of scope
Shaft fit out and headhouse construction – Currently Tendering
Status
Nil packages procured to date
Work starts Jan 2016
Cladding (Metal and bespoke blockwork)
Piling
Reinforced Concrete.
Brick and Block (shaft and head house internals)
Roofing
Fit out (painting, louvres, doors etc)
Fixtures and fittings
Architectural Metalwork
Street furniture, soft and hard landscaping
Chris Corkhill & Georgina Wright
BAM Ferrovial Kier JV
& Shane Gill, NG Bailey
Chris Corkhill + Georgia Wright+ Shane Gill
Procurement Manager + Quantity Surveyor + Buyer
C435 Farringdon Station
BFK JV: Project Overview and Future
Opportunities
BFK Joint Venture
Kier Group Plc
Kier Construction Ltd
Royal BAM nv
Wayss & Freytag
Ingenieurbau AG BAM Nuttall Ltd
Grupo Ferrovial SA
Ferrovial Agroman SA
Ferrovial Agroman UK Ltd
Joint Venture Board
Richard Reddell Luis Amorim
Principle Members
Sean JefferyAdrian Savory Karl Goose
Ian Pegram
Western Tunnels and Stations
About the BFK contracts
 C300: two 6.2 km tunnel drives between Royal Oak and
Farringdon
 C410: construct early access shafts and sprayed concrete
lining works for Bond Street and Tottenham Court Road station
tunnels
 C435:construct tunnels, platforms, ticket hall and station
concourse at Farringdon
Tunnels
Twin 7.1m diameter tunnel
drives, Royal Oak to
Farringdon(Contract C300)
SCL station tunnels, shafts and
compensation grouting at Bond
Street and Tottenham Court Road
Stations (Contract C410)
Tunnel Boring Machine (TBM)
Tunnel Boring Machine (TBM)
Tunnel Boring Machine (TBM)
Tunnel Boring Machine (TBM)
Before & now
Prep for System Wide contract
Ready for System Wide contract
Farringdon – feel the vibes ...
Removal
Phyllis and Ada
First ring started 05 May 2012
6,861m of Westbound tunnel
4,675 rings
Last ring complete 14:30hrs Tues 07 Oct 2013
Phyllis – under Smithfield Market in perpetuity
Phyllis and Ada
Ada was named after Ada Lovelace who was Lord Byron’s
only daughter Ada
6,861m of Eastbound tunnel
4,658 rings
Last ring complete 19:15hrs Fri 24 Jan 2014
Ada – under Charterhouse Square in perpetuity
Party time – last ring ....
The Long Walk Home ......
The day after the party
C410 Bond St Station Tunnels
C410 Bond St Station Tunnels
C410 Bond Street WTH
Underground
Yes - its in the right place
Preparing to spray
Spray shotcrete
Underground
Hanover Square - magic
Bond Street WTH
C410 Tottenham Ct Road Station
Tunnels
Tottenham Court Road from above
Ground level
below
… and more
Excavated material to Northfleet
Offload at Northfleet
Northfleet
Shipped to Wallasea
Northfleet – the last ship!
Farringdon – 150 years old LU station
Farringdon – Thomas the Tank Engine
Summary - Farringdon
Key facts
Project overview
Procurement progress
Opportunities
Route to Market
108
What’s in it for me?
109
How can I respond?
Farringdon – Key Facts
£250m+ NEC3 Option C (Target)
Completion - 2018
Main Works (next slide)
Over Site Development (by others)
Main Works
1) Tunnel
widening &
connecting
passages
2) Civils &
Structural
3) Building – 2nr
ticket halls & 2
Platform fit out
4) M & E – NG
Bailey
Farringdon Station – Overview
Farringdon Station - Western Ticket Hall
Farringdon Progress –WTH Civils phase
Farringdon Station - Eastern Ticket Hall
Farringdon Progress – ETH Civils phase
Farringdon Progress – ETH Civils phase
Farringdon Progress – Platform tunnels
Farringdon Station - Platform
119
C435 Farringdon Station
Georgia Wright
Graduate QS
Farringdon – Progress
Civil & structural works
Most packages let
Self delivery mainly
Outstanding packages - Barbican Bridge
M&E
NG Bailey - let as partner
Shane elaborate
Build & Fit-Out
Platforms: April 2015
Ticket Halls: October 2015
Farringdon – Build & Fit-Out - Progress
Package Status Value Key facts
Lifts Let £7.0m 10nr
Escalators Let £3.2m 11nr
Cladding GRC (tunnels) Let £5.9m c.7,000m2
Precast APSE ceiling Let £0.7m c.500m2
Structural Steel Final Ts+Cs £5.5m c.2,200t
Cladding, Glazing & Curtain walling Advertised £6.0m
Farringdon – Opportunities (Imminent)
Package Key facts Enquiry Date Site Start
Masonry (Brick, Block &
Windposts)
27,000m2 Nov 2014 Sept 2015
Precast Stairs Sep 2014 Jun 2015
PES (Platform Edge Screen) 520m Sep 2014 Sept 2015
Farringdon – Opportunities (Future)
Package Advert Date Site Start
Waterproofing Aug 2015 May 2016
Builders Work (Fire Stopping, Core Drill etc.) Aug 2015 May 2016
Metalwork (architectural - balustrades, handrails) Jul 2015 April 2016
Drylining, partitions, ceilings, render & plaster Jul 2015 Oct 2015
Screeding Dec 2014 Oct 2015
Floor Tiling (terrazo / granazzo) Mar 2015 Nov 2015
Soft Floor Finishes Mar 2015 Dec 2015
Painting & Decorating Jul 2015 Oct 2015
Doors & Gates Feb 2015 Mar 2016
Platform Nosing GFRP Reinforcement Mar 2015 Sept 2015
Farringdon – Supplier Opportunities
Miscellaneous – late 2015 onwards
Signage & wayfinding (framework of 3 due Jan 15)
Furniture, fixtures and fittings
Sanitaryware
Ceramic wall tiling
Raised access flooring
Temporary scaffold
Hoist
Fire alarms
Route to market - Farringdon
Compete For (www.competefor.com)
Current supply chain (JV companies)
(BAM, Ferrovial, Kier)
Supplier events
126
C435 Farringdon Station M&E
Shane Gill
NG Bailey Buyer
Supply
Fans
Pipework & Fittings
Fire Smoke Dampers &
Panels
AHU’s
ACU’s
Pumps, Booster Sets &
Pressurisation Units
Attenuation
Valves
Sanitary Ware
Grilles/Diffusers/Louvres
Water Heaters
Supply & Install
Ductwork Installations
Pipework Insulation
Chillers
Sump Pumps
Ventilation Commissioning
Trace Heating and Leak
Detection
Water Treatment
MEP – Mechanical, Electrical & Public Health
Mechanical
≈ £150k
≈ £60k
≈ 6k
≈ £800k
≈ £235k
≈ 10k
≈ 20k
Supply
Cable & Cable Accessories
Lighting
Switchgear LV
Wiring Accessories
Busbar
Automatic Transfer Switches
Fixings & Brackets
Steel Conduit
Earthing and Lightning
Protection
Lamps & Tubes
Loose Switchgear
Supply & Install
Fire Alarm System
Alarm, Security &
Communication
Plant Handling & Craneage
Earthing & Lightning Protection
MEP – Mechanical, Electrical & Public Health
Electrical
≈ £560k
≈ £364k
≈ 5k
≈ £430k
≈ £420k
≈ 75k
≈ 240k
≈ £130k
≈ £77k
≈ £50k
Farringdon – MEP Opportunities
How to find out more about the MEP opportunities
• CompeteFor
• Send an email with the details mentioned below and I will return an
email of expected enquiry date and an indication of when it will be
posted on CompeteFor:
• Name of Package
• Turnover
• Approvals/Accreditation Obtained (LU/CRL/ISO/BS EN etc.)
• shane.gill@ngbailey.co.uk
www.teambfk.co.uk
Helen Bass & Gareth Evans
Alstom Costain JV
25-Nov-2014
CROSSRAIL
- 8 sub-surface stations
- 1 surface station
21 km of twin-bore railway through London
Track
C610
C644
C650
OHLE
Mechanical,
Electrical
& Public
Health
Logistics
System
Integration
£
350m
Started April 13
Completion
3/8/18
 Long Welded Rail
 Derailment containment
 Lubricants
 Standard Track Slab
 High Attenuation Sleepers
 Ballasted Track
 Sleepers incl. fastenings.
 Direct Fix Fastenings
 Floating Track Slab
 Switches & Crossings
 Concrete
 Elastomeric Springs
 Reinforcement cages
 Mesh reinforcement
 Drainage channels
High Atténuation Sleepers
Top Down Construction
Innovative N&V solutions
 Cable laying
 Tunnel walkways
 Tunnel Ventilation Steelwork
 Attenuators
 Ventilation Control Systems
 Variable Speed Drives
 Cable Management Systems
 Cross passages doors
 Signage
 REB
 Tunnel fire mains
 Tunnel lighting & Power Panels
 Low Voltage distribution within tunnels
 Tunnel ventilation system
 Tunnel drainage pumping system
 Miscellaneous metal works
 Temporary Communications
 Temporary Ventilation
 Gas Monitoring
 Personnel Monitoring
 Asset Tagging and Tracking
 Temporary Power and Lighting
 Temporary Drainage
 Fire Main
 Connaught Tunnel – De-watering
 Copper Cable
 Transformers
 Autotransformers
 Re-locatable Equipment Buildings
 EMC Management
 Noise & Vibration Modelling
 Gas Insulated Switchgear
 Outdoor switchgear – Circuit Breakers
 Outdoor switchgear – Disconnectors
 Protection and Control
 Civil Engineering packages – Foundations
Provision of two railhead facilities
Plumstead and Westbourne Park / Royal Oak Portal
 Material storage, handling and lay-down areas
 Track, M&E and OHLE - materials depot providing safe storage
 Mobile gantry cranes
 Aggregate sheds, plant and equipment depots
 Multi-purpose Gantry’s
 Heavy Traction Loco’s
 Mid-size Traction Loco’s
 Chute Wagons
 Wagons
 Welfare Wagons
Plant and Equipment used to distribute people, materials and
equipment
 Concrete Shuttles
 Unimogs
 Rail Road Vehicles
 MEWP’s
 Cable winders
 Cable pulling equipment
Multi Purpose Gantry
Power Cube
Adam Compton
CompeteFor
CompeteFor
Opening the supply chain to
Local and SME Suppliers
Adam Compton
Key Accounts Manager
www.competefor.com
CompeteFor – What we do
• UK wide supply chain portal, designed to open major supply chains
• Deliver sustainable and measurable economic growth
• Community Benefits
• Enable local and SME business to take advantage of these B2B opportunities
Introduction
• Online portal to advertise supply chain opportunities from major projects
• Service created for the London 2012 Olympic and Paralympic Games, to match Buyers with
Suppliers, encouraging equality and transparency
• Commitment from Major Buying Programmes to procure responsibly
• CompeteFor has expanded beyond its original remit, to incorporate additional supply chains:-
– Crossrail
– Thames Tideway Tunnel
– Transport for London
– SWIP
– SOREC
– HS2
CompeteFor Key Objectives
• Delivering Transparency
• Local and SME Engagement
• Driving Innovation and Value
• Enablement and Capacity Building
• Supplier Diversity
• Supply Chain Visibility
Opening Supply Chains
Crossrail and CompeteFor
• Crossrail is a large and complex project offering a wide range of business
opportunities across many sectors
• Crossrail have adopted CompeteFor to help ensure that these opportunities are
opened up to the widest possible market
• Crossrail’s contractors are required to advertise all appropriate opportunities on
CompeteFor, to drive innovation in the supply chain
• Over 2,112 Crossrail and Supply Chain opportunities posted to date on
CompeteFor
Current Opportunities
Current Opportunities
Opportunities posted in the previous fortnight:
•C502 Liverpool Street Station - WP2525 Broadgate Temporary Steel Propping
and Decking
•C422 Tottenham Court Road - General Metalwork - GBP 251k to 500k
•C435 Farringdon Station - Package S155 – Back of House Screeding and Floor
Finishes
Future opportunities
• Bombardier have secured the Rolling Stock contract with Crossrail (circa
£1 billion) and are opening up their supply chain, by publishing their
contract requirements onto CompeteFor.
• Particular contract opportunities include:-
– Battery Systems
– Audio Communications
– Passenger Door Systems
– Control Equipment
• Woolwich Station – Balfour Beatty Group:-
– Currently being trained in the use of CompeteFor
– A diverse range of opportunities will soon be posted to the service
Buyer Benefits
• Enables capacity building and competition
throughout the Supply Chain
• Buyers visibility of an innovative and diverse
supplier community
• An intuitive and robust set of tools for optimising
value from the supply chain.
• Automatic scoring of Supplier responses, reducing
time for buyers
• Supports Corporate Social Responsibility and
community benefits
• Encourages compliance and supply chain
community engagement
Register
Create Notice
Evaluate
Shortlist
Supply Chain
Award
Supplier Benefits
• CompeteFor provides awareness of business
opportunities across a variety of sectors and
industries
• Suppliers can promote themselves via their
CompeteFor Business Profile
• Standardised information is stored within
suppliers profiles, making responding to
opportunities a quicker process.
• Sector specific email alerts advising suppliers of
relevant contract opportunities
Register
Business profile
Business ready
Self Certified
Supply Chain
Opportunities
Our Partners
Users
Successes
• Over 16,500 contract opportunities posted
• Almost £3 billion contracts awarded
• 75% of all contracts posted have been awarded to SMEs
• 90% of opportunities have come from private sector buying organisations
Summary
• Taking forward the legacy of the London 2012 games
• Continued support from key infrastructure projects, such as Crossrail
• National solution for UK wide supply chain development
• Supporting sustainable and responsible procurement
• Join our growing and thriving community at:-
www.competefor.com
www.competefor.com
0845 217 7804
Adam Compton
Tel: 07904995679
adam.compton@competefor.com
Key Accounts Manager
Thank you
Come along to the next Construction
Futures Wales Event on the
11th December in Bangor

More Related Content

Viewers also liked

Junta General Accionistas 2012 (Español)
Junta General Accionistas 2012 (Español)Junta General Accionistas 2012 (Español)
Junta General Accionistas 2012 (Español)
Ferrovial
 
Resultados enero-junio 2013
Resultados enero-junio 2013Resultados enero-junio 2013
Resultados enero-junio 2013
Ferrovial
 
Ferrovial Servicios Birmingham Ciudad Inteligente
Ferrovial Servicios Birmingham Ciudad InteligenteFerrovial Servicios Birmingham Ciudad Inteligente
Ferrovial Servicios Birmingham Ciudad Inteligente
Ferrovial
 
Executive summary 2013 | Resumen Ejecutivo 2013
Executive summary 2013 | Resumen Ejecutivo 2013Executive summary 2013 | Resumen Ejecutivo 2013
Executive summary 2013 | Resumen Ejecutivo 2013Ferrovial
 
Ferrovial Financial Results Jan Dec 2015
Ferrovial Financial Results Jan Dec 2015Ferrovial Financial Results Jan Dec 2015
Ferrovial Financial Results Jan Dec 2015
Ferrovial
 
Ferrovial Investors Presentation Jan Dec 2014 | Presentación Inversores Ene D...
Ferrovial Investors Presentation Jan Dec 2014 | Presentación Inversores Ene D...Ferrovial Investors Presentation Jan Dec 2014 | Presentación Inversores Ene D...
Ferrovial Investors Presentation Jan Dec 2014 | Presentación Inversores Ene D...
Ferrovial
 
Executive Summary: January-June 2014 Results
Executive Summary: January-June 2014 ResultsExecutive Summary: January-June 2014 Results
Executive Summary: January-June 2014 Results
Ferrovial
 
Investors Presentation 2012 | Presentación Inversores 2012
Investors Presentation 2012 | Presentación Inversores 2012Investors Presentation 2012 | Presentación Inversores 2012
Investors Presentation 2012 | Presentación Inversores 2012Ferrovial
 
Ferrovial Financial Results Jan Jun 2015
Ferrovial Financial Results Jan Jun 2015Ferrovial Financial Results Jan Jun 2015
Ferrovial Financial Results Jan Jun 2015
Ferrovial
 
Ferrovial: Investor Presentation Jan Jun 2014 | Presentación Inversores Ene J...
Ferrovial: Investor Presentation Jan Jun 2014 | Presentación Inversores Ene J...Ferrovial: Investor Presentation Jan Jun 2014 | Presentación Inversores Ene J...
Ferrovial: Investor Presentation Jan Jun 2014 | Presentación Inversores Ene J...
Ferrovial
 
January-September results 2013
January-September results 2013January-September results 2013
January-September results 2013
Ferrovial
 
Ferrovial 2010 Results Presentation
Ferrovial 2010 Results PresentationFerrovial 2010 Results Presentation
Ferrovial 2010 Results Presentation
Ferrovial
 
January-March 2013 results
January-March 2013 resultsJanuary-March 2013 results
January-March 2013 results
Ferrovial
 
Manual contra el despilfarro
Manual contra el despilfarroManual contra el despilfarro
Manual contra el despilfarro
Ferrovial
 
Investors Presentation 2013 | Presentación Inversores 2013
Investors Presentation 2013 | Presentación Inversores 2013Investors Presentation 2013 | Presentación Inversores 2013
Investors Presentation 2013 | Presentación Inversores 2013Ferrovial
 
Planteamiento de Cespa en la gestión de residuos vegetales de invernadero
Planteamiento de Cespa en la gestión de residuos vegetales de invernaderoPlanteamiento de Cespa en la gestión de residuos vegetales de invernadero
Planteamiento de Cespa en la gestión de residuos vegetales de invernadero
Ferrovial
 
Resultados enero - diciembre 2012
Resultados enero - diciembre 2012Resultados enero - diciembre 2012
Resultados enero - diciembre 2012
Ferrovial
 
January-December results 2013
January-December results 2013January-December results 2013
January-December results 2013
Ferrovial
 
Ferrovial Executive Summary Jan Dec 2014
Ferrovial Executive Summary Jan Dec 2014Ferrovial Executive Summary Jan Dec 2014
Ferrovial Executive Summary Jan Dec 2014
Ferrovial
 
Ferrovial Financial Results Jan-Sep 2014
Ferrovial Financial Results Jan-Sep 2014Ferrovial Financial Results Jan-Sep 2014
Ferrovial Financial Results Jan-Sep 2014
Ferrovial
 

Viewers also liked (20)

Junta General Accionistas 2012 (Español)
Junta General Accionistas 2012 (Español)Junta General Accionistas 2012 (Español)
Junta General Accionistas 2012 (Español)
 
Resultados enero-junio 2013
Resultados enero-junio 2013Resultados enero-junio 2013
Resultados enero-junio 2013
 
Ferrovial Servicios Birmingham Ciudad Inteligente
Ferrovial Servicios Birmingham Ciudad InteligenteFerrovial Servicios Birmingham Ciudad Inteligente
Ferrovial Servicios Birmingham Ciudad Inteligente
 
Executive summary 2013 | Resumen Ejecutivo 2013
Executive summary 2013 | Resumen Ejecutivo 2013Executive summary 2013 | Resumen Ejecutivo 2013
Executive summary 2013 | Resumen Ejecutivo 2013
 
Ferrovial Financial Results Jan Dec 2015
Ferrovial Financial Results Jan Dec 2015Ferrovial Financial Results Jan Dec 2015
Ferrovial Financial Results Jan Dec 2015
 
Ferrovial Investors Presentation Jan Dec 2014 | Presentación Inversores Ene D...
Ferrovial Investors Presentation Jan Dec 2014 | Presentación Inversores Ene D...Ferrovial Investors Presentation Jan Dec 2014 | Presentación Inversores Ene D...
Ferrovial Investors Presentation Jan Dec 2014 | Presentación Inversores Ene D...
 
Executive Summary: January-June 2014 Results
Executive Summary: January-June 2014 ResultsExecutive Summary: January-June 2014 Results
Executive Summary: January-June 2014 Results
 
Investors Presentation 2012 | Presentación Inversores 2012
Investors Presentation 2012 | Presentación Inversores 2012Investors Presentation 2012 | Presentación Inversores 2012
Investors Presentation 2012 | Presentación Inversores 2012
 
Ferrovial Financial Results Jan Jun 2015
Ferrovial Financial Results Jan Jun 2015Ferrovial Financial Results Jan Jun 2015
Ferrovial Financial Results Jan Jun 2015
 
Ferrovial: Investor Presentation Jan Jun 2014 | Presentación Inversores Ene J...
Ferrovial: Investor Presentation Jan Jun 2014 | Presentación Inversores Ene J...Ferrovial: Investor Presentation Jan Jun 2014 | Presentación Inversores Ene J...
Ferrovial: Investor Presentation Jan Jun 2014 | Presentación Inversores Ene J...
 
January-September results 2013
January-September results 2013January-September results 2013
January-September results 2013
 
Ferrovial 2010 Results Presentation
Ferrovial 2010 Results PresentationFerrovial 2010 Results Presentation
Ferrovial 2010 Results Presentation
 
January-March 2013 results
January-March 2013 resultsJanuary-March 2013 results
January-March 2013 results
 
Manual contra el despilfarro
Manual contra el despilfarroManual contra el despilfarro
Manual contra el despilfarro
 
Investors Presentation 2013 | Presentación Inversores 2013
Investors Presentation 2013 | Presentación Inversores 2013Investors Presentation 2013 | Presentación Inversores 2013
Investors Presentation 2013 | Presentación Inversores 2013
 
Planteamiento de Cespa en la gestión de residuos vegetales de invernadero
Planteamiento de Cespa en la gestión de residuos vegetales de invernaderoPlanteamiento de Cespa en la gestión de residuos vegetales de invernadero
Planteamiento de Cespa en la gestión de residuos vegetales de invernadero
 
Resultados enero - diciembre 2012
Resultados enero - diciembre 2012Resultados enero - diciembre 2012
Resultados enero - diciembre 2012
 
January-December results 2013
January-December results 2013January-December results 2013
January-December results 2013
 
Ferrovial Executive Summary Jan Dec 2014
Ferrovial Executive Summary Jan Dec 2014Ferrovial Executive Summary Jan Dec 2014
Ferrovial Executive Summary Jan Dec 2014
 
Ferrovial Financial Results Jan-Sep 2014
Ferrovial Financial Results Jan-Sep 2014Ferrovial Financial Results Jan-Sep 2014
Ferrovial Financial Results Jan-Sep 2014
 

Similar to Construction Futures Wales - CrossRail Event

Crossrail Suppy Chain Engagement Seminar 2013 - Simon Poulter, Laing O'Rourke...
Crossrail Suppy Chain Engagement Seminar 2013 - Simon Poulter, Laing O'Rourke...Crossrail Suppy Chain Engagement Seminar 2013 - Simon Poulter, Laing O'Rourke...
Crossrail Suppy Chain Engagement Seminar 2013 - Simon Poulter, Laing O'Rourke...Invest Northern Ireland
 
Moving London Forward - Crossrail
Moving London Forward - Crossrail Moving London Forward - Crossrail
Moving London Forward - Crossrail
Ibrahim Al-Hudhaif
 
Severfield Capital Markets Day 2015
Severfield Capital Markets Day 2015Severfield Capital Markets Day 2015
Severfield Capital Markets Day 2015
Company Spotlight
 
Judge 3D Summary Projects
Judge 3D Summary ProjectsJudge 3D Summary Projects
Judge 3D Summary ProjectsJohn Judge
 
UK Group at OTC brochure 2017
UK Group at OTC brochure 2017UK Group at OTC brochure 2017
UK Group at OTC brochure 2017
Raelene Rifkind
 
Fbe manchester energy event nov 2015
Fbe manchester energy event nov 2015Fbe manchester energy event nov 2015
Fbe manchester energy event nov 2015
FBE Manchester
 
London Residential Breakfast Briefing 2015 | Estates Gazette
London Residential Breakfast Briefing 2015 | Estates GazetteLondon Residential Breakfast Briefing 2015 | Estates Gazette
London Residential Breakfast Briefing 2015 | Estates Gazette
estatesgazette.com, RBI
 
WEC Group Ltd at a glance - 2016
WEC Group Ltd at a glance - 2016WEC Group Ltd at a glance - 2016
WEC Group Ltd at a glance - 2016
Jean-Yves Dziki
 
Bank station upgrade presentation 9th June 2014
Bank station upgrade presentation 9th June 2014Bank station upgrade presentation 9th June 2014
Bank station upgrade presentation 9th June 2014
Association for Project Management
 
Richard James
Richard JamesRichard James
Richard JamesOEP
 
Peter Hearn & Lionel Shelley, Plymouth CC - Viability in Plymouth
Peter Hearn & Lionel Shelley, Plymouth CC - Viability in PlymouthPeter Hearn & Lionel Shelley, Plymouth CC - Viability in Plymouth
Peter Hearn & Lionel Shelley, Plymouth CC - Viability in Plymouth
PAS_Team
 
Cable Laying Pulling Equipment Low High Voltage Cables - Catalogue
Cable Laying Pulling Equipment Low High Voltage Cables - CatalogueCable Laying Pulling Equipment Low High Voltage Cables - Catalogue
Cable Laying Pulling Equipment Low High Voltage Cables - Catalogue
Thorne & Derrick International
 
SEB Cable Pulling & Laying Equipment Catalogue
SEB Cable Pulling & Laying Equipment CatalogueSEB Cable Pulling & Laying Equipment Catalogue
SEB Cable Pulling & Laying Equipment Catalogue
Thorne & Derrick International
 
Cable Pulling & Laying Equipment for Street Lighting
Cable Pulling & Laying Equipment for Street LightingCable Pulling & Laying Equipment for Street Lighting
Cable Pulling & Laying Equipment for Street Lighting
Thorne & Derrick International
 
SEB - Cable Pulling & Cable Laying Equipment For Low & High Voltage Cables In...
SEB - Cable Pulling & Cable Laying Equipment For Low & High Voltage Cables In...SEB - Cable Pulling & Cable Laying Equipment For Low & High Voltage Cables In...
SEB - Cable Pulling & Cable Laying Equipment For Low & High Voltage Cables In...
Thorne & Derrick International
 
KOM Presentation STN-N Conductor_rev 2
KOM Presentation STN-N Conductor_rev 2KOM Presentation STN-N Conductor_rev 2
KOM Presentation STN-N Conductor_rev 2Brian Quan (Minh)
 
Delivering Transformation - Place Making in North Lincolnshire
Delivering Transformation - Place Making in North LincolnshireDelivering Transformation - Place Making in North Lincolnshire
Delivering Transformation - Place Making in North Lincolnshire
PAS_Team
 
Amal modular yard rev03 20150921 -pdf
Amal modular yard rev03 20150921 -pdfAmal modular yard rev03 20150921 -pdf
Amal modular yard rev03 20150921 -pdf
Tiago Alvarez
 
Crossrail Suppy Chain Engagement Seminar 2013 - Terry Morgan, Martin Rowark, ...
Crossrail Suppy Chain Engagement Seminar 2013 - Terry Morgan, Martin Rowark, ...Crossrail Suppy Chain Engagement Seminar 2013 - Terry Morgan, Martin Rowark, ...
Crossrail Suppy Chain Engagement Seminar 2013 - Terry Morgan, Martin Rowark, ...
Invest Northern Ireland
 

Similar to Construction Futures Wales - CrossRail Event (20)

Crossrail Suppy Chain Engagement Seminar 2013 - Simon Poulter, Laing O'Rourke...
Crossrail Suppy Chain Engagement Seminar 2013 - Simon Poulter, Laing O'Rourke...Crossrail Suppy Chain Engagement Seminar 2013 - Simon Poulter, Laing O'Rourke...
Crossrail Suppy Chain Engagement Seminar 2013 - Simon Poulter, Laing O'Rourke...
 
Moving London Forward - Crossrail
Moving London Forward - Crossrail Moving London Forward - Crossrail
Moving London Forward - Crossrail
 
Severfield Capital Markets Day 2015
Severfield Capital Markets Day 2015Severfield Capital Markets Day 2015
Severfield Capital Markets Day 2015
 
Judge 3D Summary Projects
Judge 3D Summary ProjectsJudge 3D Summary Projects
Judge 3D Summary Projects
 
UK Group at OTC brochure 2017
UK Group at OTC brochure 2017UK Group at OTC brochure 2017
UK Group at OTC brochure 2017
 
Fbe manchester energy event nov 2015
Fbe manchester energy event nov 2015Fbe manchester energy event nov 2015
Fbe manchester energy event nov 2015
 
London Residential Breakfast Briefing 2015 | Estates Gazette
London Residential Breakfast Briefing 2015 | Estates GazetteLondon Residential Breakfast Briefing 2015 | Estates Gazette
London Residential Breakfast Briefing 2015 | Estates Gazette
 
WEC Group Ltd at a glance - 2016
WEC Group Ltd at a glance - 2016WEC Group Ltd at a glance - 2016
WEC Group Ltd at a glance - 2016
 
Bank station upgrade presentation 9th June 2014
Bank station upgrade presentation 9th June 2014Bank station upgrade presentation 9th June 2014
Bank station upgrade presentation 9th June 2014
 
Richard James
Richard JamesRichard James
Richard James
 
Peter Hearn & Lionel Shelley, Plymouth CC - Viability in Plymouth
Peter Hearn & Lionel Shelley, Plymouth CC - Viability in PlymouthPeter Hearn & Lionel Shelley, Plymouth CC - Viability in Plymouth
Peter Hearn & Lionel Shelley, Plymouth CC - Viability in Plymouth
 
Cable Laying Pulling Equipment Low High Voltage Cables - Catalogue
Cable Laying Pulling Equipment Low High Voltage Cables - CatalogueCable Laying Pulling Equipment Low High Voltage Cables - Catalogue
Cable Laying Pulling Equipment Low High Voltage Cables - Catalogue
 
SEB Cable Pulling & Laying Equipment Catalogue
SEB Cable Pulling & Laying Equipment CatalogueSEB Cable Pulling & Laying Equipment Catalogue
SEB Cable Pulling & Laying Equipment Catalogue
 
Cable Pulling & Laying Equipment for Street Lighting
Cable Pulling & Laying Equipment for Street LightingCable Pulling & Laying Equipment for Street Lighting
Cable Pulling & Laying Equipment for Street Lighting
 
SEB - Cable Pulling & Cable Laying Equipment For Low & High Voltage Cables In...
SEB - Cable Pulling & Cable Laying Equipment For Low & High Voltage Cables In...SEB - Cable Pulling & Cable Laying Equipment For Low & High Voltage Cables In...
SEB - Cable Pulling & Cable Laying Equipment For Low & High Voltage Cables In...
 
Alistair_Gower_CV 1
Alistair_Gower_CV 1Alistair_Gower_CV 1
Alistair_Gower_CV 1
 
KOM Presentation STN-N Conductor_rev 2
KOM Presentation STN-N Conductor_rev 2KOM Presentation STN-N Conductor_rev 2
KOM Presentation STN-N Conductor_rev 2
 
Delivering Transformation - Place Making in North Lincolnshire
Delivering Transformation - Place Making in North LincolnshireDelivering Transformation - Place Making in North Lincolnshire
Delivering Transformation - Place Making in North Lincolnshire
 
Amal modular yard rev03 20150921 -pdf
Amal modular yard rev03 20150921 -pdfAmal modular yard rev03 20150921 -pdf
Amal modular yard rev03 20150921 -pdf
 
Crossrail Suppy Chain Engagement Seminar 2013 - Terry Morgan, Martin Rowark, ...
Crossrail Suppy Chain Engagement Seminar 2013 - Terry Morgan, Martin Rowark, ...Crossrail Suppy Chain Engagement Seminar 2013 - Terry Morgan, Martin Rowark, ...
Crossrail Suppy Chain Engagement Seminar 2013 - Terry Morgan, Martin Rowark, ...
 

More from Rae Davies

Construction Futures Wales - Mental Health in Construction HHW
Construction Futures Wales - Mental Health in Construction HHWConstruction Futures Wales - Mental Health in Construction HHW
Construction Futures Wales - Mental Health in Construction HHW
Rae Davies
 
Construction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank AccountsConstruction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank Accounts
Rae Davies
 
Construction Futures Wales Project Bank Accounts - November 2018
Construction Futures Wales Project Bank Accounts  - November 2018Construction Futures Wales Project Bank Accounts  - November 2018
Construction Futures Wales Project Bank Accounts - November 2018
Rae Davies
 
Construction Futures Wales - Mental health in the Workplace
Construction Futures Wales - Mental health in the WorkplaceConstruction Futures Wales - Mental health in the Workplace
Construction Futures Wales - Mental health in the Workplace
Rae Davies
 
Construction Futures Wales & Wales Nuclear Forum - React to Nuclear Event
Construction Futures Wales & Wales Nuclear Forum - React to Nuclear EventConstruction Futures Wales & Wales Nuclear Forum - React to Nuclear Event
Construction Futures Wales & Wales Nuclear Forum - React to Nuclear Event
Rae Davies
 
Construction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank AccountsConstruction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank Accounts
Rae Davies
 
Construction Futures Wales - Digitalisation Workshop
Construction Futures Wales - Digitalisation WorkshopConstruction Futures Wales - Digitalisation Workshop
Construction Futures Wales - Digitalisation Workshop
Rae Davies
 
Construction Futures Wales - Succession Planning Workshop
Construction Futures Wales - Succession Planning WorkshopConstruction Futures Wales - Succession Planning Workshop
Construction Futures Wales - Succession Planning Workshop
Rae Davies
 
Construction Futures Wales - Supply Chain Development Workshop
Construction Futures Wales - Supply Chain Development WorkshopConstruction Futures Wales - Supply Chain Development Workshop
Construction Futures Wales - Supply Chain Development Workshop
Rae Davies
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Rae Davies
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Rae Davies
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
Rae Davies
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview Workshop
Rae Davies
 
CFW Managing your Cash-flow
CFW Managing your Cash-flowCFW Managing your Cash-flow
CFW Managing your Cash-flow
Rae Davies
 
CFW An Introduction to Building Information Modelling
CFW An Introduction to Building Information Modelling CFW An Introduction to Building Information Modelling
CFW An Introduction to Building Information Modelling
Rae Davies
 
Construction Futures Wales Workplace Health Workshop - Case Studies - Public ...
Construction Futures Wales Workplace Health Workshop - Case Studies - Public ...Construction Futures Wales Workplace Health Workshop - Case Studies - Public ...
Construction Futures Wales Workplace Health Workshop - Case Studies - Public ...
Rae Davies
 
Construction Futures Wales Workplace Health Workshop - Fit For Work - Paul Kirk
Construction Futures Wales Workplace Health Workshop - Fit For Work - Paul KirkConstruction Futures Wales Workplace Health Workshop - Fit For Work - Paul Kirk
Construction Futures Wales Workplace Health Workshop - Fit For Work - Paul Kirk
Rae Davies
 
CFW Workplace Health Workshop North & South Wales Oct 2016 - Morgan Sindall, ...
CFW Workplace Health Workshop North & South Wales Oct 2016 - Morgan Sindall, ...CFW Workplace Health Workshop North & South Wales Oct 2016 - Morgan Sindall, ...
CFW Workplace Health Workshop North & South Wales Oct 2016 - Morgan Sindall, ...
Rae Davies
 
CFW Procurement Workshop October 2016
CFW Procurement Workshop October 2016CFW Procurement Workshop October 2016
CFW Procurement Workshop October 2016
Rae Davies
 
RWE Mynydd y Gwair Supply Chain Event - Construction Futures Wales / Paul Wintle
RWE Mynydd y Gwair Supply Chain Event - Construction Futures Wales / Paul WintleRWE Mynydd y Gwair Supply Chain Event - Construction Futures Wales / Paul Wintle
RWE Mynydd y Gwair Supply Chain Event - Construction Futures Wales / Paul Wintle
Rae Davies
 

More from Rae Davies (20)

Construction Futures Wales - Mental Health in Construction HHW
Construction Futures Wales - Mental Health in Construction HHWConstruction Futures Wales - Mental Health in Construction HHW
Construction Futures Wales - Mental Health in Construction HHW
 
Construction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank AccountsConstruction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank Accounts
 
Construction Futures Wales Project Bank Accounts - November 2018
Construction Futures Wales Project Bank Accounts  - November 2018Construction Futures Wales Project Bank Accounts  - November 2018
Construction Futures Wales Project Bank Accounts - November 2018
 
Construction Futures Wales - Mental health in the Workplace
Construction Futures Wales - Mental health in the WorkplaceConstruction Futures Wales - Mental health in the Workplace
Construction Futures Wales - Mental health in the Workplace
 
Construction Futures Wales & Wales Nuclear Forum - React to Nuclear Event
Construction Futures Wales & Wales Nuclear Forum - React to Nuclear EventConstruction Futures Wales & Wales Nuclear Forum - React to Nuclear Event
Construction Futures Wales & Wales Nuclear Forum - React to Nuclear Event
 
Construction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank AccountsConstruction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank Accounts
 
Construction Futures Wales - Digitalisation Workshop
Construction Futures Wales - Digitalisation WorkshopConstruction Futures Wales - Digitalisation Workshop
Construction Futures Wales - Digitalisation Workshop
 
Construction Futures Wales - Succession Planning Workshop
Construction Futures Wales - Succession Planning WorkshopConstruction Futures Wales - Succession Planning Workshop
Construction Futures Wales - Succession Planning Workshop
 
Construction Futures Wales - Supply Chain Development Workshop
Construction Futures Wales - Supply Chain Development WorkshopConstruction Futures Wales - Supply Chain Development Workshop
Construction Futures Wales - Supply Chain Development Workshop
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview Workshop
 
CFW Managing your Cash-flow
CFW Managing your Cash-flowCFW Managing your Cash-flow
CFW Managing your Cash-flow
 
CFW An Introduction to Building Information Modelling
CFW An Introduction to Building Information Modelling CFW An Introduction to Building Information Modelling
CFW An Introduction to Building Information Modelling
 
Construction Futures Wales Workplace Health Workshop - Case Studies - Public ...
Construction Futures Wales Workplace Health Workshop - Case Studies - Public ...Construction Futures Wales Workplace Health Workshop - Case Studies - Public ...
Construction Futures Wales Workplace Health Workshop - Case Studies - Public ...
 
Construction Futures Wales Workplace Health Workshop - Fit For Work - Paul Kirk
Construction Futures Wales Workplace Health Workshop - Fit For Work - Paul KirkConstruction Futures Wales Workplace Health Workshop - Fit For Work - Paul Kirk
Construction Futures Wales Workplace Health Workshop - Fit For Work - Paul Kirk
 
CFW Workplace Health Workshop North & South Wales Oct 2016 - Morgan Sindall, ...
CFW Workplace Health Workshop North & South Wales Oct 2016 - Morgan Sindall, ...CFW Workplace Health Workshop North & South Wales Oct 2016 - Morgan Sindall, ...
CFW Workplace Health Workshop North & South Wales Oct 2016 - Morgan Sindall, ...
 
CFW Procurement Workshop October 2016
CFW Procurement Workshop October 2016CFW Procurement Workshop October 2016
CFW Procurement Workshop October 2016
 
RWE Mynydd y Gwair Supply Chain Event - Construction Futures Wales / Paul Wintle
RWE Mynydd y Gwair Supply Chain Event - Construction Futures Wales / Paul WintleRWE Mynydd y Gwair Supply Chain Event - Construction Futures Wales / Paul Wintle
RWE Mynydd y Gwair Supply Chain Event - Construction Futures Wales / Paul Wintle
 

Recently uploaded

ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 

Recently uploaded (20)

ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 

Construction Futures Wales - CrossRail Event

  • 2. Dafydd Hughes Head of Construction Welsh Government
  • 3. Steven Kay & Simon Pain Crossrail
  • 4. CROSSRAIL MOVING LONDON FORWARD Steven Kay Central Area Delivery Director Simon Pain Principal Programme Supply Chain Manager
  • 5. Header here max 30 charactersCrossrail Route
  • 6. Header here max 30 characters Overall, 90% complete Tunnelling completed in East London and Docklands Short video Final westbound section to Farringdon Then onto systems, fit out, M & E … Tunnelling is almost complete
  • 7. Header here max 30 charactersCrossrail: delivering a railway 13 14 15 16 17 182012 Railway Systems Stations Rolling Stock & Depot NR Surface Works TestandCommission TrialOperation Crossrail TOC Civils and Tunnelling Property Acquisition OSD & Urban Realm
  • 8. Header here max 30 charactersCrossrail benefits £42bn+ 24 14,000 people 24 trains per hour 200 million journeys per year
  • 9. Header here max 30 charactersCentral stations
  • 11. Header here max 30 charactersRolling stock
  • 12. Header here max 30 characters 2014 379 Apprentices 8,565 enrolled at TUCA 10,000+ employed on the project 746 workers previously unemployed All figures are running totals bar “employed on project” Skills development
  • 13. Header here max 30 charactersWallasea Island 2016
  • 14. Header here max 30 characters What the Crossrail Supply Chain looks like, How you can improve your chances of getting into it. Crossrail Supply Chain
  • 15. Header here max 30 charactersOpportunities on Crossrail
  • 16. Header here max 30 charactersCrossrail in Wales • Over £20m awarded in Wales • £12m Neath area • £8m Newport and Cardiff • Reinforcement bars • Piling • Props • Structural steel
  • 18. Header here max 30 charactersEnergy saving technologies Energy Technology Products List Enhanced Capital Allowances https://etl.decc.gov.uk Be prepared
  • 20. Website and guidance - www.Crossrail.co.uk www.CompeteFor.com
  • 21. Header here max 30 characters Thank you SteveKay@crossrail.co.uk simonPain@crossrail.co.uk
  • 22. Simon Poulter & Oliver Thompson Smith Laing O’Rourke
  • 23. © Laing O’Rourke 2014, all rights reserved.25 Crossrail Event 2014 - St David’s Hotel Ewloe
  • 24. © Laing O’Rourke 2014, all rights reserved.26
  • 25. © Laing O’Rourke 2014, all rights reserved.27
  • 26. © Laing O’Rourke 2014, all rights reserved.28
  • 27. © Laing O’Rourke 2014, all rights reserved.29
  • 28. © Laing O’Rourke 2014, all rights reserved.30 © Laing O’Rourke 2014, all rights reserved.30 The Laing O’Rourke / Crossrail Projects
  • 29. © Laing O’Rourke 2014, all rights reserved.31 The Projects: C502 Liverpool Street C422 Tottenham Court Road C520 Custom House Crossrail Event- St David’s Hotel Ewloe
  • 30. © Laing O’Rourke 2014, all rights reserved.32 C502 – Liverpool Street Station
  • 31. © Laing O’Rourke 2014, all rights reserved.33 Liverpool Street: Plan View Liverpool Street Mainline Station Broadgate THBlomfield Box Moorgate TH Moorgate Station Moorgate Shaft LU Liverpool Street Station Crossrail Platforms Crossrail Event- St David’s Hotel Ewloe
  • 32. © Laing O’Rourke 2014, all rights reserved.34 C502 2014 Structural Steelwork Scaffolding Screeds & Render 2015 Dry lining FF&E Works Decoration Landscaping Commissioning Sub-Mains Cabling Pulling Thermal Insulation Trace Heating Distribution Boards Fire Stopping Crossrail Event- St David’s Hotel Ewloe
  • 33. © Laing O’Rourke 2014, all rights reserved.35 Supply Chain Summit 2014 - Bristol C422 – Tottenham Court Road
  • 34. © Laing O’Rourke 2014, all rights reserved.36 Western Ticket Hall (WTH) Dean Street Box Westbound CRL Tunnel Eastbound CRL Tunnel Central Line Centre Point Goslett Yard Box (GYB) Northern Line Crossrail Event- St David’s Hotel Ewloe
  • 35. © Laing O’Rourke 2014, all rights reserved.37 C422 2014 Scaffolding Screeds & Render General Metalwork 2015 Soft Floor Finishes Epoxy Flooring Decoration Thermal Insulation Distribution Boards Durasteel Cladding Luminaries Dampers - Smoke 2016 Landscaping Road Surfacing Crossrail Event- St David’s Hotel Ewloe
  • 36. © Laing O’Rourke 2014, all rights reserved.38 C520 – Custom House
  • 37. © Laing O’Rourke 2014, all rights reserved.39 C520 2014 Soft Landscaping Commissioning Management 2015 Hard Landscaping FF&E Signage & Totems Electric Panel Heaters Small Transformer Chlorination – Water Treatment Crossrail Event- St David’s Hotel Ewloe
  • 38. © Laing O’Rourke 2014, all rights reserved.40 © Laing O’Rourke 2014, all rights reserved.40 Becoming Part of the Supply Chain
  • 39. © Laing O’Rourke 2014, all rights reserved.41 LO’R Preferred Supply Chain Partner Financial Appraisal (D&B Report) Financial Capacity Checks Health & Safety Checks (SSIP) Past Performance Data On Site Subcontractor Questionnaire (where applicable) Asite Pre- Qualification (Tiered Supply Chain) Crossrail Event- St David’s Hotel Ewloe
  • 40. © Laing O’Rourke 2014, all rights reserved.42 ✓ X Supplier Turnover (£) Total Package Value April 13 - March 14 % of t/o April 14 - March 15 % of t/o April 15 - March 16 % of t/o £ 12,654,248.00 £ 2,271,202.30 £245,535.38 2% £1,104,909.23 9% £920,757.69 7% £ 3,133,000.00 £ 2,271,202.30 £245,535.38 8% £1,104,909.23 35% £920,757.69 29% £ 2,479,595.00 £ 2,271,202.30 £245,535.38 10% £1,104,909.23 45% £920,757.69 37% £ 955,188.00 £ 2,271,202.30 £245,535.38 26% £1,104,909.23 116% £920,757.69 96% £ 8,859,045.00 £ 2,271,202.30 £245,535.38 3% £1,104,909.23 12% £920,757.69 10% FINANCIAL ACCREDITATION
  • 41. © Laing O’Rourke 2014, all rights reserved.43 Crossrail Event- St David’s Hotel Ewloe
  • 42. © Laing O’Rourke 2014, all rights reserved.44 Crossrail Event- St David’s Hotel Ewloe
  • 43. © Laing O’Rourke 2014, all rights reserved.45 © Laing O’Rourke 2014, all rights reserved.45 What is Responsible Procurement?
  • 44. © Laing O’Rourke 2014, all rights reserved.46 Crossrail Event- St David’s Hotel Ewloe The Greater London Authority defines Responsible Procurement as: “The purchase of goods, works and services in a socially and environmentally responsible way that delivers value for money and benefits to the contracting authority and to London”
  • 45. © Laing O’Rourke 2014, all rights reserved.47 Crossrail Event- St David’s Hotel Ewloe Workforce welfare Workforce welfare Environmental Sustainability Environmental Sustainability Ethical Sourcing Ethical Sourcing Skills and employment Skills and employment Community Benefits Community Benefits Supplier Diversity Supplier Diversity Fair Employment Fair Employment Responsible Procurement Responsible ProcurementClimate change, pollution and natural resource management. London Living Wage (LLW) and working conditions. Supply chain diversity and equality. Community initiatives e.g. tackling crime and disorder. Training and employment opportunities & meeting skills shortage. Ensuring standards of labour conditions and human rights in the supply chain. Union representation and worker’s rights. Workforce welfare Workforce welfare Environmental Sustainability Environmental Sustainability Ethical Sourcing Ethical Sourcing Skills and employment Skills and employment Community Benefits Community Benefits Supplier Diversity Supplier Diversity Fair Employment Fair Employment Responsible Procurement Responsible Procurement Workforce welfare Workforce welfare Environmental Sustainability Environmental Sustainability Ethical Sourcing Ethical Sourcing Skills and employment Skills and employment Community Benefits Community Benefits Supplier Diversity Supplier Diversity Fair Employment Fair Employment Responsible Procurement Responsible ProcurementClimate change, pollution and natural resource management. London Living Wage (LLW) and working conditions. Supply chain diversity and equality. Community initiatives e.g. tackling crime and disorder. Training and employment opportunities & meeting skills shortage. Ensuring standards of labour conditions and human rights in the supply chain. Union representation and worker’s rights. Seven Themes Under the Crossrail RP Policy
  • 46. © Laing O’Rourke 2014, all rights reserved.48 © Laing O’Rourke 2014, all rights reserved.48 Laing O’Rourke’s Use of CompeteFor
  • 47. © Laing O’Rourke 2014, all rights reserved.49 Summary of Custom House to Date 25No. Existing planned opportunities advertised on CompeteFor with a combined value of approx. £5.6million. 198No. Companies registered an interest on CompeteFor for these opportunities. 100No. Of these companies were shortlisted. 31No. Were recommended to be invited to tender for one or more of the 19No. opportunities. 7No. Of which were previously unknown to Laing O’Rourke 19No. Opportunities of the 25No. advertised have now been awarded. 6No. Awarded to a company from CompeteFor for have a combined value of £2,373,625.38 Crossrail Event- St David’s Hotel Ewloe
  • 48. © Laing O’Rourke 2014, all rights reserved.50 Compete For • Compete For Tailored Questionnaire • Answers Scored • Anonymous Long list turned Top Eight Shortlist Potential Tender Schedule • Compete For Shortlist • LO’R Tiered Supply Chain • Past Performance, SSIP, Building Confidence, DNBi, Capacity Modelling Approved Tender List • Approved Tender List issued to Crossrail Crossrail Event- St David’s Hotel Ewloe
  • 49. © Laing O’Rourke 2014, all rights reserved.51
  • 51. Simon Taylor Costain-Skanska Environmental Manager CSJV Working in Collaboration with Crossrail
  • 53. Fisher Street Paddington Eleanor Street and Mile End Park Stepney Green and Limmo Bond Street CSJV Projects
  • 54. C360 Eleanor Street and Mile End Park
  • 55. Summary of Scope Mile End shaft – 10m dia. 30m deep shaft constructed using PC segments and Sprayed Concrete Lining (SCL) Eleanor Street shaft – 16.4m dia. 36m deep shaft constructed using PC segments and SCL Status 95% of supply chain packages are procured Packages left to go... Headhouse Construction - £1.4M (Jan 15) Landscaping - £0.4M (Jan 15) Construction starts (July 15 – Feb 16)
  • 58. Summary of Scope Connecting shaft and tunnels from street level to main running tunnels Status All supply chain packages are yet to be procured Works start early to mid 2015 Secondary Linings Roofing Cladding Fixtures and fittings Hard Landscaping
  • 60. Summary of scope Underground Box construction to form station at running tunnels with fit out Status Supply chain packages are yet to be procured All to be procured between now and Feb 2015 Cladding (Metal and bwk) Roofing (Kalzip) Car Park Fit out (Carpet and curtains) Fixtures and fittings Street furniture and hard landscaping
  • 62. Summary of scope Shaft fit out and headhouse construction – Currently Tendering Status Nil packages procured to date Work starts Jan 2016 Cladding (Metal and bespoke blockwork) Piling Reinforced Concrete. Brick and Block (shaft and head house internals) Roofing Fit out (painting, louvres, doors etc) Fixtures and fittings Architectural Metalwork Street furniture, soft and hard landscaping
  • 63. Chris Corkhill & Georgina Wright BAM Ferrovial Kier JV & Shane Gill, NG Bailey
  • 64. Chris Corkhill + Georgia Wright+ Shane Gill Procurement Manager + Quantity Surveyor + Buyer C435 Farringdon Station BFK JV: Project Overview and Future Opportunities
  • 65. BFK Joint Venture Kier Group Plc Kier Construction Ltd Royal BAM nv Wayss & Freytag Ingenieurbau AG BAM Nuttall Ltd Grupo Ferrovial SA Ferrovial Agroman SA Ferrovial Agroman UK Ltd Joint Venture Board Richard Reddell Luis Amorim Principle Members Sean JefferyAdrian Savory Karl Goose Ian Pegram
  • 67. About the BFK contracts  C300: two 6.2 km tunnel drives between Royal Oak and Farringdon  C410: construct early access shafts and sprayed concrete lining works for Bond Street and Tottenham Court Road station tunnels  C435:construct tunnels, platforms, ticket hall and station concourse at Farringdon
  • 68. Tunnels Twin 7.1m diameter tunnel drives, Royal Oak to Farringdon(Contract C300) SCL station tunnels, shafts and compensation grouting at Bond Street and Tottenham Court Road Stations (Contract C410)
  • 74. Prep for System Wide contract
  • 75. Ready for System Wide contract
  • 76. Farringdon – feel the vibes ...
  • 78. Phyllis and Ada First ring started 05 May 2012 6,861m of Westbound tunnel 4,675 rings Last ring complete 14:30hrs Tues 07 Oct 2013 Phyllis – under Smithfield Market in perpetuity
  • 79. Phyllis and Ada Ada was named after Ada Lovelace who was Lord Byron’s only daughter Ada 6,861m of Eastbound tunnel 4,658 rings Last ring complete 19:15hrs Fri 24 Jan 2014 Ada – under Charterhouse Square in perpetuity
  • 80. Party time – last ring ....
  • 81. The Long Walk Home ......
  • 82. The day after the party
  • 83. C410 Bond St Station Tunnels
  • 84. C410 Bond St Station Tunnels
  • 87. Yes - its in the right place
  • 93. C410 Tottenham Ct Road Station Tunnels
  • 94. Tottenham Court Road from above
  • 96. below
  • 98. Excavated material to Northfleet
  • 102. Northfleet – the last ship!
  • 103. Farringdon – 150 years old LU station
  • 104. Farringdon – Thomas the Tank Engine
  • 105. Summary - Farringdon Key facts Project overview Procurement progress Opportunities Route to Market
  • 106. 108 What’s in it for me?
  • 107. 109 How can I respond?
  • 108. Farringdon – Key Facts £250m+ NEC3 Option C (Target) Completion - 2018 Main Works (next slide) Over Site Development (by others)
  • 109. Main Works 1) Tunnel widening & connecting passages 2) Civils & Structural 3) Building – 2nr ticket halls & 2 Platform fit out 4) M & E – NG Bailey Farringdon Station – Overview
  • 110. Farringdon Station - Western Ticket Hall
  • 111. Farringdon Progress –WTH Civils phase
  • 112. Farringdon Station - Eastern Ticket Hall
  • 113. Farringdon Progress – ETH Civils phase
  • 114. Farringdon Progress – ETH Civils phase
  • 115. Farringdon Progress – Platform tunnels
  • 116. Farringdon Station - Platform
  • 117. 119 C435 Farringdon Station Georgia Wright Graduate QS
  • 118. Farringdon – Progress Civil & structural works Most packages let Self delivery mainly Outstanding packages - Barbican Bridge M&E NG Bailey - let as partner Shane elaborate Build & Fit-Out Platforms: April 2015 Ticket Halls: October 2015
  • 119. Farringdon – Build & Fit-Out - Progress Package Status Value Key facts Lifts Let £7.0m 10nr Escalators Let £3.2m 11nr Cladding GRC (tunnels) Let £5.9m c.7,000m2 Precast APSE ceiling Let £0.7m c.500m2 Structural Steel Final Ts+Cs £5.5m c.2,200t Cladding, Glazing & Curtain walling Advertised £6.0m
  • 120. Farringdon – Opportunities (Imminent) Package Key facts Enquiry Date Site Start Masonry (Brick, Block & Windposts) 27,000m2 Nov 2014 Sept 2015 Precast Stairs Sep 2014 Jun 2015 PES (Platform Edge Screen) 520m Sep 2014 Sept 2015
  • 121. Farringdon – Opportunities (Future) Package Advert Date Site Start Waterproofing Aug 2015 May 2016 Builders Work (Fire Stopping, Core Drill etc.) Aug 2015 May 2016 Metalwork (architectural - balustrades, handrails) Jul 2015 April 2016 Drylining, partitions, ceilings, render & plaster Jul 2015 Oct 2015 Screeding Dec 2014 Oct 2015 Floor Tiling (terrazo / granazzo) Mar 2015 Nov 2015 Soft Floor Finishes Mar 2015 Dec 2015 Painting & Decorating Jul 2015 Oct 2015 Doors & Gates Feb 2015 Mar 2016 Platform Nosing GFRP Reinforcement Mar 2015 Sept 2015
  • 122. Farringdon – Supplier Opportunities Miscellaneous – late 2015 onwards Signage & wayfinding (framework of 3 due Jan 15) Furniture, fixtures and fittings Sanitaryware Ceramic wall tiling Raised access flooring Temporary scaffold Hoist Fire alarms
  • 123. Route to market - Farringdon Compete For (www.competefor.com) Current supply chain (JV companies) (BAM, Ferrovial, Kier) Supplier events
  • 124. 126 C435 Farringdon Station M&E Shane Gill NG Bailey Buyer
  • 125. Supply Fans Pipework & Fittings Fire Smoke Dampers & Panels AHU’s ACU’s Pumps, Booster Sets & Pressurisation Units Attenuation Valves Sanitary Ware Grilles/Diffusers/Louvres Water Heaters Supply & Install Ductwork Installations Pipework Insulation Chillers Sump Pumps Ventilation Commissioning Trace Heating and Leak Detection Water Treatment MEP – Mechanical, Electrical & Public Health Mechanical ≈ £150k ≈ £60k ≈ 6k ≈ £800k ≈ £235k ≈ 10k ≈ 20k
  • 126. Supply Cable & Cable Accessories Lighting Switchgear LV Wiring Accessories Busbar Automatic Transfer Switches Fixings & Brackets Steel Conduit Earthing and Lightning Protection Lamps & Tubes Loose Switchgear Supply & Install Fire Alarm System Alarm, Security & Communication Plant Handling & Craneage Earthing & Lightning Protection MEP – Mechanical, Electrical & Public Health Electrical ≈ £560k ≈ £364k ≈ 5k ≈ £430k ≈ £420k ≈ 75k ≈ 240k ≈ £130k ≈ £77k ≈ £50k
  • 127. Farringdon – MEP Opportunities How to find out more about the MEP opportunities • CompeteFor • Send an email with the details mentioned below and I will return an email of expected enquiry date and an indication of when it will be posted on CompeteFor: • Name of Package • Turnover • Approvals/Accreditation Obtained (LU/CRL/ISO/BS EN etc.) • shane.gill@ngbailey.co.uk
  • 129. Helen Bass & Gareth Evans Alstom Costain JV
  • 131. CROSSRAIL - 8 sub-surface stations - 1 surface station 21 km of twin-bore railway through London
  • 133.  Long Welded Rail  Derailment containment  Lubricants  Standard Track Slab  High Attenuation Sleepers  Ballasted Track  Sleepers incl. fastenings.  Direct Fix Fastenings  Floating Track Slab  Switches & Crossings  Concrete  Elastomeric Springs  Reinforcement cages  Mesh reinforcement  Drainage channels
  • 134. High Atténuation Sleepers Top Down Construction Innovative N&V solutions
  • 135.
  • 136.
  • 137.  Cable laying  Tunnel walkways  Tunnel Ventilation Steelwork  Attenuators  Ventilation Control Systems  Variable Speed Drives  Cable Management Systems  Cross passages doors  Signage  REB  Tunnel fire mains  Tunnel lighting & Power Panels  Low Voltage distribution within tunnels  Tunnel ventilation system  Tunnel drainage pumping system  Miscellaneous metal works
  • 138.
  • 139.  Temporary Communications  Temporary Ventilation  Gas Monitoring  Personnel Monitoring  Asset Tagging and Tracking  Temporary Power and Lighting  Temporary Drainage  Fire Main  Connaught Tunnel – De-watering
  • 140.
  • 141.  Copper Cable  Transformers  Autotransformers  Re-locatable Equipment Buildings  EMC Management  Noise & Vibration Modelling  Gas Insulated Switchgear  Outdoor switchgear – Circuit Breakers  Outdoor switchgear – Disconnectors  Protection and Control  Civil Engineering packages – Foundations
  • 142. Provision of two railhead facilities Plumstead and Westbourne Park / Royal Oak Portal
  • 143.  Material storage, handling and lay-down areas  Track, M&E and OHLE - materials depot providing safe storage  Mobile gantry cranes  Aggregate sheds, plant and equipment depots
  • 144.  Multi-purpose Gantry’s  Heavy Traction Loco’s  Mid-size Traction Loco’s  Chute Wagons  Wagons  Welfare Wagons Plant and Equipment used to distribute people, materials and equipment  Concrete Shuttles  Unimogs  Rail Road Vehicles  MEWP’s  Cable winders  Cable pulling equipment
  • 145.
  • 148.
  • 149.
  • 150.
  • 152. CompeteFor Opening the supply chain to Local and SME Suppliers Adam Compton Key Accounts Manager www.competefor.com
  • 153. CompeteFor – What we do • UK wide supply chain portal, designed to open major supply chains • Deliver sustainable and measurable economic growth • Community Benefits • Enable local and SME business to take advantage of these B2B opportunities
  • 154. Introduction • Online portal to advertise supply chain opportunities from major projects • Service created for the London 2012 Olympic and Paralympic Games, to match Buyers with Suppliers, encouraging equality and transparency • Commitment from Major Buying Programmes to procure responsibly • CompeteFor has expanded beyond its original remit, to incorporate additional supply chains:- – Crossrail – Thames Tideway Tunnel – Transport for London – SWIP – SOREC – HS2
  • 155. CompeteFor Key Objectives • Delivering Transparency • Local and SME Engagement • Driving Innovation and Value • Enablement and Capacity Building • Supplier Diversity • Supply Chain Visibility
  • 157. Crossrail and CompeteFor • Crossrail is a large and complex project offering a wide range of business opportunities across many sectors • Crossrail have adopted CompeteFor to help ensure that these opportunities are opened up to the widest possible market • Crossrail’s contractors are required to advertise all appropriate opportunities on CompeteFor, to drive innovation in the supply chain • Over 2,112 Crossrail and Supply Chain opportunities posted to date on CompeteFor
  • 159. Current Opportunities Opportunities posted in the previous fortnight: •C502 Liverpool Street Station - WP2525 Broadgate Temporary Steel Propping and Decking •C422 Tottenham Court Road - General Metalwork - GBP 251k to 500k •C435 Farringdon Station - Package S155 – Back of House Screeding and Floor Finishes
  • 160. Future opportunities • Bombardier have secured the Rolling Stock contract with Crossrail (circa £1 billion) and are opening up their supply chain, by publishing their contract requirements onto CompeteFor. • Particular contract opportunities include:- – Battery Systems – Audio Communications – Passenger Door Systems – Control Equipment • Woolwich Station – Balfour Beatty Group:- – Currently being trained in the use of CompeteFor – A diverse range of opportunities will soon be posted to the service
  • 161. Buyer Benefits • Enables capacity building and competition throughout the Supply Chain • Buyers visibility of an innovative and diverse supplier community • An intuitive and robust set of tools for optimising value from the supply chain. • Automatic scoring of Supplier responses, reducing time for buyers • Supports Corporate Social Responsibility and community benefits • Encourages compliance and supply chain community engagement Register Create Notice Evaluate Shortlist Supply Chain Award
  • 162. Supplier Benefits • CompeteFor provides awareness of business opportunities across a variety of sectors and industries • Suppliers can promote themselves via their CompeteFor Business Profile • Standardised information is stored within suppliers profiles, making responding to opportunities a quicker process. • Sector specific email alerts advising suppliers of relevant contract opportunities Register Business profile Business ready Self Certified Supply Chain Opportunities
  • 164. Users
  • 165. Successes • Over 16,500 contract opportunities posted • Almost £3 billion contracts awarded • 75% of all contracts posted have been awarded to SMEs • 90% of opportunities have come from private sector buying organisations
  • 166. Summary • Taking forward the legacy of the London 2012 games • Continued support from key infrastructure projects, such as Crossrail • National solution for UK wide supply chain development • Supporting sustainable and responsible procurement • Join our growing and thriving community at:- www.competefor.com
  • 167. www.competefor.com 0845 217 7804 Adam Compton Tel: 07904995679 adam.compton@competefor.com Key Accounts Manager
  • 168. Thank you Come along to the next Construction Futures Wales Event on the 11th December in Bangor