More Related Content Similar to Crossrail Suppy Chain Engagement Seminar 2013 - Simon Poulter, Laing O'Rourke - Crossrail Projects (20) More from Invest Northern Ireland (20) Crossrail Suppy Chain Engagement Seminar 2013 - Simon Poulter, Laing O'Rourke - Crossrail Projects2. 2
Make your main title for each page in
the body of the text – 24pt Arial bold
• Second level copy runs from this point, please type over this paragraph to create text on your pages
• Third level – Use the guides on this page for lining up copy and pictures
• Fourth level
• Fifth level
© Laing O’Rourke 2012, all rights reserved
3. 3
Make your main title for each page in
the body of the text – 24pt Arial bold
• Second level copy runs from this point, please type over this paragraph to create text on your pages
• Third level – Use the guides on this page for lining up copy and pictures
• Fourth level
• Fifth level
© Laing O’Rourke 2012, all rights reserved
4. 44 © Laing O’Rourke 2012, all rights reserved
So what are the Laing O’Rourke Crossrail Opportunities?
5. 55 © Laing O’Rourke 2012, all rights reserved
The Projects:
C502 Liverpool Street
C422 Tottenham Court Road
C520 Custom House
6. 66
‘Three Projects. One Team.’
Supply Chain opportunities within the one team model.
© Laing O’Rourke 2012, all rights reserved
Projects
C422 C502 C520
2013
Noise & Vibration Monitoring
Precast Concrete Works
Substructure Works
Reinforcement
Superstructure Works
2014
Cladding
Structural Steelwork
Metal Doors
Glazed Canopy
M & E Works
2015
Drylining
FF&E Works
Decoration
Landscaping
Commissioning
8. 88
Broadgate Ticket Hall including
the Link Passageway AP8
Moorgate work includes:
• Moorgate Ticket Hall
• Highwalk access at Moorfields
• Completion of Moor House Draft relief ventilation shaft
Blomfield Box
Moorgate Shaft work includes:
• Moorgate Shaft internal structure
• Stabilisation and monitoring of 8 Moorfield & 87
Moorgate
Finsbury work includes:
• Finsbury Circus access shaft
• Finsbury Circus Gardens
Tunnel work includes:
• Internal Structure
• Fit-out, test and commissioning
Project Overview
9. 99
C502 – Liverpool Street Station
Construction Programme
© Laing O’Rourke 2012, all rights reserved
Year Construction Programme
2012
Project Start Up
30.04.12 Start Date
OCI Design & Validation
Aug 12 Commence first work site – BBX ventilation shaft
2013
Design & Procurement
Blomfield box piling and substructures
Dec 2013 start Broadgate worksite
Arup design stage F
Procurement phase (most packages let in 2013)
2014
Substructures / structures
Blomfield box substructures
Broadgate piling and substructures
August 2014 - Moorgate ticket hall works commence – Demolition / structures
Dec Tunnel works site starts
2015
Structures & Envelope
Blomfield box structures complete / Envelope and fit out starts
Broadgate Ticket hall structures complete / waterproofing
Moorgate Ticket hall – structures
July – Moorgate shaft worksite starts
Tunnel structures & fit out starts
2016
Fit Out
Services & fit out underway to all worksites
2017
Complete fit and commission
Fit out completed to all worksites by mid 2017
Testing & Commissioning phase
2018
Integrated commissioning & pre operation activities
System wide commissioning
Operational readiness
Handover activities
Aug 2018 completion
11. 1111
Project overview
© Laing O’Rourke 2012, all rights reserved
Western Ticket Hall
(WTH)
Dean Street Box Centre Point
Central Line
Goslett Yard
Box (GYB)
Eastbound
CRL Tunnel
Westbound
CRL Tunnel
Northern Line
12. 1212
C422 – Tottenham Court Road
Construction Programme
© Laing O’Rourke 2012, all rights reserved
Year Construction Programme
2012
Project Start Up
16.07.12 Start date
OCI Design & Validation
2013
Design & Procurement
WSP design stage F
Procurement phase
2014
Substructures / structures
Completion of WSP Design / Design Acceptances/ Gate 3 Sign Offs
Conclusion of Package Procurement
Western Ticket Hall (WTH) Structures
Commence Goslett Yard Box (GYB) Structures
July - Tunnel site works starts
2015
Structures & Envelope
WTH & GYB Envelope Works
WTH Fitout
WTH and GYB systemwide installation to vent shafts
GYB Fitout
2016
Fit Out
Services & fit out underway to all worksites
Systemwide access to equipment rooms
2017
Complete fit and commission
Fit out complete to all WTH and GYB by early 2017
Testing & Commissioning phase
2018
Integrated commissioning & pre operation activities
Fit out complete to all platforms and tunnels by early 2018
System wide commissioning
Operational readiness
Handover activities
Aug 2018 completion
15. 1515
C520 – Custom House
Procurement Programme
© Laing O’Rourke 2012, all rights reserved
Year Construction Programme
2012
Project Start Up
28th September 2012 Start date
OCI Design & Validation
2013
Design, Procurement Substructure & Superstructure
All design works
March 2013 – Piling works
June 2013 – Substructure
September 2013 – Superstructure
Ramboll design stage F
Procurement phase (majority of packages let in 2013)
2014
Superstructure, Fit-out and M&E works
April 2014 – ExCeL bridge installation
August 2014 – Commence station entrance
Dec Tunnel works site starts
2015
Internal Finishes works
April 2015 – DLR Bridge works
April 2015 – Commission Station Entrance
May 2015 – Remove temporary bridge
May 2015 – Hand Over
2016
Crossrail works
Station Wide Services
2017 No Laing O’Rourke works
2018 Integrated commissioning on permanent services
16. 1616 © Laing O’Rourke 2012, all rights reserved
LO’R
Crossrail
Preferred
Supply Chain
Partner
Financial
Appraisal (D&B
Report)
Financial
Capacity
Checks
Health & Safety
Checks (SSIP
& Building
Confidence)
Past
Performance
Data
Subcontractor
Questionnaire
Compete For
How to become a LO’R Crossrail supply chain partner?
17. 1717 © Laing O’Rourke 2012, all rights reserved
✓
X
Supplier Turnover (£) Total Package Value April 13 - March 14 % of t/o April 14 - March 15 % of t/o April 15 - March 16 % of t/o
£ 12,654,248.00 £ 2,271,202.30 £245,535.38 2% £1,104,909.23 9% £920,757.69 7%
£ 3,133,000.00 £ 2,271,202.30 £245,535.38 8% £1,104,909.23 35% £920,757.69 29%
£ 2,479,595.00 £ 2,271,202.30 £245,535.38 10% £1,104,909.23 45% £920,757.69 37%
£ 955,188.00 £ 2,271,202.30 £245,535.38 26% £1,104,909.23 116% £920,757.69 96%
£ 8,859,045.00 £ 2,271,202.30 £245,535.38 3% £1,104,909.23 12% £920,757.69 10%
18. 1818 © Laing O’Rourke 2012, all rights reserved
“Our mission is to act as an umbrella organisation to
facilitate mutual recognition between health and safety pre-
qualification schemes wherever it is practicable to do so"
Within SSIP there are:
• 39 Registered Members
• 7 Affiliate Members
• 3 Co-opted Members
Delivering trusted, meaningful connections
Achilles BuildingConfidence is and online accreditation standard used
by 19 buyer organisations and over 1,500 suppliers in the UK
construction sector.
20. 2020 © Laing O’Rourke 2012, all rights reserved
Question: Please confirm if you were to sub-contract any works specifically for this scheme,
that you would comply with the Crossrail requirements to source potential subcontractors
through CompeteFor
Project
Title
Valued Opportunities on
Compete For
C502 £ 20,930,758.92
C422 £ 5,215,021.00
C520 £ 2,751,326.00
21. 2121 © Laing O’Rourke 2012, all rights reserved
Compete For
• Compete For Tailored Questionnaire
• Answers Scored
• Anonymous Long list turned Top Eight Shortlist
Potential Tender
Schedule
• Compete For Shortlist
• LO’R Tiered Supply Chain
• Past Performance, SSIP, Building Confidence, DNBi, Capacity Modelling
Approved Tender
List
• Approved Tender List issued to Crossrail
23. © Laing O’Rourke 2012, all rights reserved.
No part of this presentation may be reproduced, stored on a retrieval system, disclosed or transmitted, in any form or by any
means, electronic, mechanical, photocopying, recording or otherwise, without prior permission of the copyright owner.
Thank You