This project evaluated alternative low-cost waterproofing materials for small construction sites in Northern Province, Sri Lanka. Three cement-fevicol mix tanks and three lime-fevicol mix tanks were constructed and subjected to ponding, durability and bonding tests. Results found the lime-fevicol mix tanks performed better with minimal leakage observed and a protective lime layer forming on the water surface over three days, indicating potential as an effective and affordable waterproofing solution. Cost analysis found the lime-fevicol mix cost Rs. 690 per square meter compared to over Rs. 1,000 for standard materials, suggesting it can help encourage waterproofing in small northern constructions.
Presentation by Sallie Houston on slurry seal mix design for the CalAPA Spring Asphalt Pavement Conference & Equipment Expo, April 20-21, 2016, in Ontario, CA.
Presentation on Slurry Seals by Lance Allen of Pacific Emulsions at the CalAPA Los Angeles Regional Technical Committee meeting Jan. 7, 2015 in Santa Ana
Presentation by Sallie Houston on slurry seal mix design for the CalAPA Spring Asphalt Pavement Conference & Equipment Expo, April 20-21, 2016, in Ontario, CA.
Presentation on Slurry Seals by Lance Allen of Pacific Emulsions at the CalAPA Los Angeles Regional Technical Committee meeting Jan. 7, 2015 in Santa Ana
This report examines the properties of wet self- compacting concrete to determine if the properties meet the specification or not, more focus in this test was to determine the workability and flow ability of self-compacting concrete through different tests.
A summer training presentation on Highway material and soil testing.
In this presentation along with the entire test procedure readings and images of apparatus are used for better understanding.
The experiments are presented in a creative manner.
This test method is used to determine the time of setting of the cement by VICAT
needle apparatus.
The knowledge of the setting time of the cement is always helpful in deciding the time duration
to mix, transport, place and compact the concrete effectively.
We always prefer a larger initial setting time so that we can mix, transport and place the
concrete easily. According to ASTM specifications, the initial setting time shall not be less
than 45 min but in the field we prefer an initial setting time not less than 90 min.
A smaller value of the final setting time is always preferred in order to avoid large expenditures
on the formwork. According to most of the specifications, the final setting time shall not be
greater than 10hrs and shall not be less than (90 + 1.2 x (initial setting time)) min.
The basic aim is to find out the water content required to produce a cement paste of standard consistency as specified by the IS: 4031 (Part 4) – 1988. The principle is that standard consistency of cement is that consistency at which the Vicat plunger penetrates to a point 5-7mm from the bottom of Vicat mould.
Detailed working of each equipments, formulas and calculations. Easy to understand. Very helpful for those students who face difficulty in making lab reports
This report examines the properties of wet self- compacting concrete to determine if the properties meet the specification or not, more focus in this test was to determine the workability and flow ability of self-compacting concrete through different tests.
A summer training presentation on Highway material and soil testing.
In this presentation along with the entire test procedure readings and images of apparatus are used for better understanding.
The experiments are presented in a creative manner.
This test method is used to determine the time of setting of the cement by VICAT
needle apparatus.
The knowledge of the setting time of the cement is always helpful in deciding the time duration
to mix, transport, place and compact the concrete effectively.
We always prefer a larger initial setting time so that we can mix, transport and place the
concrete easily. According to ASTM specifications, the initial setting time shall not be less
than 45 min but in the field we prefer an initial setting time not less than 90 min.
A smaller value of the final setting time is always preferred in order to avoid large expenditures
on the formwork. According to most of the specifications, the final setting time shall not be
greater than 10hrs and shall not be less than (90 + 1.2 x (initial setting time)) min.
The basic aim is to find out the water content required to produce a cement paste of standard consistency as specified by the IS: 4031 (Part 4) – 1988. The principle is that standard consistency of cement is that consistency at which the Vicat plunger penetrates to a point 5-7mm from the bottom of Vicat mould.
Detailed working of each equipments, formulas and calculations. Easy to understand. Very helpful for those students who face difficulty in making lab reports
The report is being made on the experience of 3 weeks office training.
briefly describes the quality tests of Fine and Coarse aggregates .
Complete calculation of concrete mix design is included with solved numerical equations.
Cement, water and admixtures quality test is not performed because the contractor purchase it from other chemical and cement manufacturer company.
The Use Of Permeable Concrete For Ground Water RechargeIJERA Editor
In order to develop Smart Cities in India, we need to develop smart technologies and smart construction materials. Permeable concrete an innovative material is environment friendly and a smart material which can be used for construction of several structures. In India, the ground water table is decreasing at a faster rate due to reduction in ground water recharge. These days, the vegetation cover is replaced by infrastructure hence the water gets very less opportunity to infiltrate itself into the soil. If the permeable concrete which has a high porosity is used for the construction of pavements, walking tracks, parking lots, well lining, etc. then it can reduce the runoff from the site and help in the ground water recharge. Such type of smart materials will play an important role for Indian conditions where government is putting lot of efforts to implement ground water recharging techniques. During the research work, the runoff for a particular storm was calculated for a bitumen pavement on a sloping ground. Later after studying the various topographical features, the traffic intensity and the rainfall for that particular area, the concrete was designed and tested for the different proportion and thus the mix design for the permeable concrete was finalized based upon its permeability and strength characteristics. Later by using this permeable concrete the infiltration and runoff for the same storm was compared and studied. The research paper will thus give an account of the properties of permeable concrete where it can be used over an existing road.
This guidebook, consisting of Building Schedule Rates, Highway Schedule Rates, Irrigation Schedule Rates and Material Testing of 2020 were scaned by Vj, under the guidance of Deputy Chief Secretary Engineering Services, Northern Province.
Immunizing Image Classifiers Against Localized Adversary Attacksgerogepatton
This paper addresses the vulnerability of deep learning models, particularly convolutional neural networks
(CNN)s, to adversarial attacks and presents a proactive training technique designed to counter them. We
introduce a novel volumization algorithm, which transforms 2D images into 3D volumetric representations.
When combined with 3D convolution and deep curriculum learning optimization (CLO), itsignificantly improves
the immunity of models against localized universal attacks by up to 40%. We evaluate our proposed approach
using contemporary CNN architectures and the modified Canadian Institute for Advanced Research (CIFAR-10
and CIFAR-100) and ImageNet Large Scale Visual Recognition Challenge (ILSVRC12) datasets, showcasing
accuracy improvements over previous techniques. The results indicate that the combination of the volumetric
input and curriculum learning holds significant promise for mitigating adversarial attacks without necessitating
adversary training.
Cosmetic shop management system project report.pdfKamal Acharya
Buying new cosmetic products is difficult. It can even be scary for those who have sensitive skin and are prone to skin trouble. The information needed to alleviate this problem is on the back of each product, but it's thought to interpret those ingredient lists unless you have a background in chemistry.
Instead of buying and hoping for the best, we can use data science to help us predict which products may be good fits for us. It includes various function programs to do the above mentioned tasks.
Data file handling has been effectively used in the program.
The automated cosmetic shop management system should deal with the automation of general workflow and administration process of the shop. The main processes of the system focus on customer's request where the system is able to search the most appropriate products and deliver it to the customers. It should help the employees to quickly identify the list of cosmetic product that have reached the minimum quantity and also keep a track of expired date for each cosmetic product. It should help the employees to find the rack number in which the product is placed.It is also Faster and more efficient way.
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSveerababupersonal22
It consists of cw radar and fmcw radar ,range measurement,if amplifier and fmcw altimeterThe CW radar operates using continuous wave transmission, while the FMCW radar employs frequency-modulated continuous wave technology. Range measurement is a crucial aspect of radar systems, providing information about the distance to a target. The IF amplifier plays a key role in signal processing, amplifying intermediate frequency signals for further analysis. The FMCW altimeter utilizes frequency-modulated continuous wave technology to accurately measure altitude above a reference point.
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
HEAP SORT ILLUSTRATED WITH HEAPIFY, BUILD HEAP FOR DYNAMIC ARRAYS.
Heap sort is a comparison-based sorting technique based on Binary Heap data structure. It is similar to the selection sort where we first find the minimum element and place the minimum element at the beginning. Repeat the same process for the remaining elements.
3. 1 - Introduction
Water proofing is very necessary in the surface which are in touch with water. If
we don’t do the waterproofing, the leakage and absorption of water more
harmful to the surface.
Nowadays waterproofing materials are available in markets but rate is very high.
Although in the higher constructions they use but in the small construction site
and small contractors In villages they want to avoid spend lot of money for the
water proofing work in nothern province and other areas also.
AIM AND OBJECTIVES
•To reduce cost for waterproof material in construction
•To find out the suitable alternative materials which are easily available for
water proofing
•To encourage waterproofing work in small construction work too
4. Master seal
K 11
Fair mate
Water guard liquid
standard water
proofing materials
ALTERNATIVE MATERIAL
SELECTION
Fevicol adhesive
O.P.C Cement / lime
Water
We decided these following alternative
materials for water proofing
Generally These Materials Are Used
For Waterproofing work
5. 2 - Literature Review
Mr.Rymond (2000) reported on water proofing materials usage and
alternative material selection for waterproofing. In his paper, he reported
standard waterproofing materials has ability to make molecules layer on
pores of surface to reduce the permeability. Above ability should be
when the selection of alternative material for waterproofing.
Mr.Prudip (2006) carried out some studies on waterproofing. By the
introduction of suitable alternative material, can reach the lower cost with
best quality expectation for waterproofing.
Any suggestions to the alternative material didn’t proceed yet. They
only recommended the require characteristic to the alternative
material selection. We choose the alternative materials to satisfy
their statement.
6. 3 - Comparison
STANDARD MATERIAL
(master seal 540)
ALTANATIVE
MATERIAL
Cost Per 𝑚2
(SLS) High Low
Durability Minimum 10 Years (On Process)
Availability Depend on market Easily Available
Colour White Gray and White
Flexibility Easy Easy
Safety Measures High Low
7. 4 – Progress Chart
ITEM
June July
05
06
07
08
09
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
01
02
03
04
05
06
07
08
09
10
11
12
13
14
15
Material Tools Arrangement
Construction Of Tanks
Curing Of Tanks
Allow To Dry
Water Pouring
Leakage Identify
Allow To Dry
1st Coat Water Proof Apply
2nd Coat Water Proof Apply
Water Pouring
Observation
8. 5 - Methodology
The waterproof material divided in two part. first part A in liquid stage then second part B in
powder stage. The identified the suitable substitutes materials for waterproof.
part A : Fevicol, Margo Adhesive, Tar
Part B : Cement, Lime, Mud,
Identification Of Substituent Material
Availability Of Substituent Material
Above mentioned materials are available in northern province widely. So can get materials
required manner.
Finally we decided to use the fevicol adhesive as part A and cement or lime
as part B with required amount pure water for the testing.
9. Material Arrangement
Material Total Quantity
Bricks 240 Nos
Sand ( River Sand ) 2 bags ( 50 kg )
Cement ( Nippon ) 16 kg
Lime 4 kg
Fevicol ( Synthetic Resin Adhesive ) 1 kg
Water ( Pure Water ) Required amount
11. 1. CONSTRUCTION WORK OF TANKS
• Materials were bought and Tools were arranged.
then those were transported to our work site
• Impurities and other large particles were removed
from Fine aggregate ( Sand ) by sieve, Working place
was cleaned
• Cement sand Mortar was mixed thoroughly in ratio 1:5 for brick construction
• Polythene sheet was placed over the surface to avoid
bonding between the surface and mortar, Then tank
bed was prepared in 15 mm thickness and size of 400
mm X 400 mm, Then brick construction was started
by stretcher bond on the above bed size in height of
450 mm with the brick thickness 100 mm.
12. • When do the construction we had to maintain the internal surface as smooth for
easy apply of material.
• Checked the alignment of tanks by using plumb bop, level bar and sprit level.
Internal right angle were maintained using setsquare, tank top was leveled by
mortar
• Well curing was done to the tanks for 3 days. Tanks were named as I, II, III, IV, V,
VI.
13. 2. IDENTIFY THE LEAKAGE
For our water proofing test, firstly we had to ensure the leakage in the tanks. Then
only we can find out the possibility of our proceeded alternative water proof
material to reduce the leakage amount
After the curing the tanks were allowed to fully dry (for easy to identify the
leakages). Then Water fully filled into the tanks when filling the we had to fill
without any spill of water on the tank’s external surface.
Tank open area was covered tightly to prevent the evaporation, field
temperature was measured
observations were recorded
14. 3. SURFACE PREPARATION
CEMENT : FEVICOL : WATER = 3 : 1 : 2
LIME : FEVICOL : WATER = 3 : 1.5 : 2
4. MIXING OF WATER PROOF MATERIALS
Remaining water in the tank was removed and tanks
were allowed to dry
The internal surfaces of every tanks were cleaned and fillet
application was done to all corners with cement : sand
motor
We analyzed with our coordinator to select the possible mixing ratio of the water
proof materials and decided the following ratio by volume
15. 4. APPLICATION
First 3 tanks were applied with cement fevicol mix (tank I, tank II and tank III)
Other tanks ( tank IV, tank V and tank VI ) were applied with lime fevicol mix
Application of mix was done to cover whole area smoothly with two coat of
application by
vertical apply horizontal apply
16. 6 - Cost Analysis
In the planning stage of a project or work, we have to choose in economical way
with higher quality to reach success. When we proceed a alternative material for
standard one, checking and analyzing in cost vice is help to recommendation of the
proceeded material.
17. Description unit Rate Quantity Amount(Rs)
Material
Cement (Nippon) bag 900 0.08 72
Fevicol (Adhesive) kg 580 0.5 290
Wastage - 10% 36.20
Labour
Skill Labour hr 200 0.75 150
Unskill Labour hr 150 1.25 187.50
Tools and machineries 10% 33.75
Overhead and profit - 14% 107.72
Total Amount 877.17
Analyzing for cement fevicol application( 𝑚2
)
• Applied area = ((230x435x4)+(230x230)) x 3
= 1.359 m2
• Cost for 1.359 m2 = Rs 877.17
• So, Cost for 1 m2 = 877.17/1.359 = Rs 645.45
= Rs 646.00
18. Analyzing for Lime fevicol application(𝑚2
)
Description unit Rate Quantity Amount
Material
Lime bag 900 0.13 120
Fevicol (Synthetic Resin
Adhesive)
kg 580 0.5 290
Wastage 10% 41
Labour
Skill labour hr 200 0.75 150
Unskill labour hr 150 1.25 187.50
Tools and machineries 10% 33.75
Overhead and profit - 14% 115.11
Total Amount 937.36
• Applied area = ((230x435x4)+(230x230)) x 3
= 1.359 m2
• Cost for 1.359 m2 = Rs 937.36
• So, Cost for 1 m2 = 937.36/1.359 = Rs 689.74
= Rs.690.00
19. Analyzing the Alternative material with Standard
Description Unit Amount
Water proofing treatment by using flexible Polymer cement
slurry according to manufacturer's specifications. ( Master
seal 540 or equivalent approved product including
preparation of surface) (Rate from BSR-2016)
𝑚2 Rs 1,187.00
Water proofing treatment by using
Cement : fevicol : water mix in ratio of 3 : 1 : 2
𝑚2 Rs 646.00
Water proofing treatment by using
Lime : fevicol : water mix in ratio of 3 : 1.5 : 2
𝑚2
Rs.690.00
20. 7 - Tests Carried Out
Ponding test
To identify the water leakage through the water proof applied
surface
Bonding test
To ensure the bonding between applied material and surface
Durability test
To determine the expecting life time without failure
21. Testing procedure
PONDING TEST
The tank were ensure free from moisture (to early
identify the leakages after water filling)
Water fully filled into the tanks (fill the water carefully
into the tanks without any spill of water to the outside)
Open areas of every tanks were covered tightly by using
regiforms to avoid the evaporation, field temperature was
measured.
22. DURABILITY TEST
Durability is a Maximum life time of a material without losing of property. We
checked Durability of applied material with time duration.
• Ability of water reserve
compare the first and last day leakage amount (water
depth). From the different, we can expect the durability of material.
• Colour change
Colour change affects the durability of materials. Inspected
any colour changes in the surface and water in the tanks with the time period.
BONDING TEST
Test carried out by visual observation. Observed any changes arise in the
material applied surface in the regular time period.
23. 8- Observations
In the tank I,II,III there is no significant change in colour but in tank IV,V,VI
able to identify the floating white (lime) layer on the water surface with
minimum leakage.
VISUAL OBSERVATIONS
In the tanks IV,V,VI there is a ‘ scaly ’ formed in the
white surface but in the tanks I,II,III there no change
in the applied surface.
24. Date Time
Depth of water level from tank top ( mm )
Tank I Tank II Tank III Tank IV Tank V Tank VI
12th June
11.00 a.m. 36 42 29 43 26 31
3.00 p.m. 58 57 48 52 42 38
7.00 p.m. 75 88 70 69 51 47
13th June
7.00 a.m. 118 126 107 119 89 73
11.00 a.m. 128 137 116 134 98 86
3.00 p.m. 134 142 122 148 109 93
14th June 7.00 a.m. 152 166 149 180 127 107
Location : Ariyalai Water pouring Date : 12 June 2017
Temperature : 31℃ Water pouring time : 7.00 a.m
1. WATER LEAKAGE (TIME BASE FOR 3 DAYS) –BEFORE WATER PROOFING
25.
26. Location : Ariyalai Water pouring Date : 19 June 2017
Avg.Temperature : 30℃ Water pouring time : 7.00 a.m
Date Time
Depth of water level from tank top ( mm )
Cement Fevicol mix Lime Fevicol Mix
Tank I Tank II Tank III Tank IV Tank V Tank VI
20th June
11.00 a.m - - - - - -
3.00 p.m - - - - - -
7.00 p.m - - - Approx. 2 - -
21st June
7.00 a.m - Approx. 2 - Approx. 2 Approx. 2 Approx. 2
11.00 a.m Approx. 2 Approx. 3 - Approx. 3 Approx. 3 Approx. 3
3.00 p.m Approx. 3 Approx. 3 Approx. 3 Approx. 3 Approx. 3 Approx. 3
22nd June 7.00 a.m Approx. 3 Approx. 4 Approx. 3 Approx. 4 Approx. 3 Approx. 4
2. WATER LEAKAGE (TIME BASE FOR 3 DAYS) - AFTER WATER PROOFING
27. Depth of water level from tank top ( mm )
Cement Fevicol mix Lime Fevicol Mix
Date Tank I Tank II Tank III Tank IV Tank V Tank VI
23rd June 3 5 4 6 4 4
25th June 5 8 6 9 11 10
27th June 8 12 10 15 17 16
29th June 11 15 13 21 19 21
1st July 15 17 17 25 23 27
3rd July 18 20 21 29 29 35
5th July 22 24 25 34 34 38
7th July 26 29 28 38 40 42
9th July 28 30 31 42 44 47
11th July 30 32 33 49 49 51
13th July 32 33 34 54 52 53
15th July 33 34 35 57 55 56
3. FIND OUT AVERAGE LEAKAGE PER 2 DAY - AFTER WATER PROOFING
28. Depth of water level from tank top ( mm )
Cement Fevicol mix Lime Fevicol Mix
Date Tank I Tank II Tank III Tank IV Tank V Tank VI
17th July 32 35 36 58 56 58
19th July 33 36 37 59 57 60
21st July 34 38 40 61 58 64
23rd July 35 39 41 62 60 68
25th July 36 40 42 66 64 71
27th July 38 42 43 69 67 75
29th July 41 43 45 71 72 78
31st July 42 45 46 74 76 81
2nd August 44 47 48 78 80 85
4th August 45 48 51 81 83 89
6th August 47 51 53 85 87 95
CONTINUE ……
29. 9. Calculations
Date Time
Depth of water level from tank top ( mm )
Tank I Tank II Tank III Average Tank IV Tank V Tank VI Average
12th June
11.00 a.m. 36 42 29 35.7 43 26 31 33.3
3.00 p.m. 58 57 48 54.3 52 42 38 44.0
7.00 p.m. 75 88 70 77.7 69 51 47 55.7
13th June
7.00 a.m. 118 126 107 117.0 119 89 73 93.7
11.00 a.m. 128 137 116 127.0 134 98 86 106.0
3.00 p.m. 134 142 122 132.7 148 109 93 116.7
14th June 7.00 a.m. 152 166 149 155.7 180 127 107 138.0
1. FIND OUT AVERAGE LEAKAGE - BEFORE WATER PROOFING
30. Date
Time
Depth of water level from tank top ( mm )
Cement Fevicol mix Lime Fevicol Mix
Tank I Tank II Tank III Average Tank IV Tank V Tank VI Average
20th
June
11.00 a.m - - - 0 - - - 0
3.00 p.m - - - 0 - - - 0
7.00 p.m - - - 0 Approx. 2 - - 0.6
21st
June
7.00 a.m - Approx. 2 - 0.6 Approx. 2 Approx. 2 Approx. 2 2
11.00 a.m Approx. 2 Approx. 3 - 1.6 Approx. 3 Approx. 3 Approx. 3 3
3.00 p.m Approx. 3 Approx. 3 Approx. 3 3 Approx. 3 Approx. 3 Approx. 3 3
22nd
June
7.00 a.m Approx. 3 Approx. 4 Approx. 3 3.3 Approx. 4 Approx. 3 Approx. 4 3.6
2. FIND OUT AVERAGE LEAKAGE (TIME BASE FOR 3 DAYS) - AFTER WATER PROOFING
31. Date
Depth of water level from tank top ( mm )
Cement Fevicol mix Lime Fevicol Mix
Tank I Tank II Tank III Average Tank IV Tank V Tank VI Average
23rd June 3 5 4 4.0 6 4 4 4.7
25th June 5 8 6 6.3 9 11 10 10.0
27th June 8 12 10 10.0 15 17 16 16.0
29th June 11 15 13 13.0 21 19 21 20.3
1st July 15 17 17 16.3 25 23 27 25.0
3rd July 18 20 21 19.7 29 29 35 31.0
5th July 22 24 25 23.7 34 34 38 35.3
7th July 26 29 28 27.7 38 40 42 40.0
9th July 28 30 31 29.7 42 44 47 44.3
11th July 30 32 33 31.7 49 49 51 49.7
13th July 32 33 34 33.0 54 52 53 53.0
15th July 33 34 35 34.0 57 55 56 56.0
3. FIND OUT AVERAGE LEAKAGE PER 2 DAY - AFTER WATER PROOFING
32. Date
Depth of water level from tank top ( mm )
Cement Fevicol mix Lime Fevicol Mix
Tank I Tank II Tank III Average Tank IV Tank V Tank VI Average
17th July 32 35 36 34.3 58 56 58 57.3
19th July 33 36 37 35.3 59 57 60 58.7
21st July 34 38 40 37.3 61 58 64 61.0
23rd July 35 39 41 38.3 62 60 68 63.3
25th July 36 40 42 39.3 66 64 71 67.0
27th July 38 42 43 41.0 69 67 75 70.3
29th July 41 43 45 43.0 71 72 78 73.7
31st July 42 45 46 44.3 74 76 81 77.0
2nd August 44 47 48 46.3 78 80 85 81.0
4th August 45 48 51 48.0 81 83 89 84.3
6th August 47 51 53 50.3 85 87 95 89.0
CONTINUE ….
33. Calculation for Durability Test
CEMENT FEVICOL TANKS :
Total leakages for 48 days = last leakage Avg.reading – First leakage Avg.reading
Total leakages for 48 days = 50.3 – 4.0
= 46.3 mm
LIME FEVICOL TANKS :
Total leakages for 48 days = 89.0 – 4.7
= 84.3 mm
leakages amount = 46.3/48
= 0.95 mm/day
leakages amount = 84.3/48
= 1.75 mm/day
34. 10 - Graphing
0
20
40
60
80
100
120
140
160
180
0 10 20 30 40 50 60
Leakage(mm)
Time (hr)
1. WATER LEAKAGE (TIME BASE FOR 3 DAYS) –BEFORE WATER PROOFING
0
20
40
60
80
100
120
140
160
0 10 20 30 40 50 60
Leakage(mm)
Time (hr)
Average leakage of Tank – I , II , III Average leakage of Tank – IV , V , VI
35. -0.5
0
0.5
1
1.5
2
2.5
3
3.5
0 10 20 30 40 50 60
Leakage(mm)
Time (hr)
2. WATER LEAKAGE (TIME BASE FOR 3 DAYS) –AFTER WATER PROOFING
-0.5
0
0.5
1
1.5
2
2.5
3
3.5
4
0 10 20 30 40 50 60
Leakage(mm) Time (hr)
Average leakage of Tank – I , II , III Average leakage of Tank – IV , V , VI
36. 0
10
20
30
40
50
60
0 10 20 30 40 50 60
Leakage(mm)
Time (day)
3. WATER LEAKAGE (PER 2 DAY) –AFTER WATER PROOFING
0
10
20
30
40
50
60
70
80
90
100
0 10 20 30 40 50 60
Leakage(mm)
Time (day)
Average leakage of Tank – I , II , III Average leakage of Tank – IV , V , VI
37. 11 - Comparing And Analyzing
-20
0
20
40
60
80
100
120
140
160
180
0 10 20 30 40 50 60
Leakage(mm)
Time (hr)
BEFORE
AFTER
1. AVERAGE WATER LEAKAGE BEFORE AND AFTER OF WATER PROOFING TO
CEMENT FEVICOL MIX
38. -20
0
20
40
60
80
100
120
140
160
0 10 20 30 40 50 60
Leakage(mm)
Time (hr)
BEFORE
AFTER
2. AVERAGE WATER LEAKAGE BEFORE AND AFTER OF WATER PROOFING TO LIME
FEVICOL MIX
39. 0
10
20
30
40
50
60
70
80
90
100
0 10 20 30 40 50 60
Leakage(mm)
Time (Day)
CEMENT
LIME
3. AVERAGE WATER LEAKAGE BETWEEN LIME FEVICOL MIX AND CEMENT
FEVICOL MIX
40. 12 - Result
From Ponding Test
When analyzing before and after waterproofing, the amount of leakage
reduced large amount by the application
When comparing the cement fevicol application and lime fevicol application,
cement fevicol mix application showed less amount of leakage than lime
fevicol mix application. So, cement fevicol mix application showed better
application method for waterproofing
From Bonding Test
We identified white floating on the water surface and scaly formation on the
applied surface on lime fevicol mix applied tanks. It showed less bonding
property on the lime fevicol application method. But there is no significant
change identified cement fevicol mix application. It showed, better bonding
property then lime fevicol application
41. Cement fevicol application method showed less amount of leakage per day. So
cement fevicol application method is durable than lime fevicol application
From Durability Test
Cement fevicol mix Lime fevicol mix
0.95 mm/day 1.75 mm/day
From cost analysis
Description Unit Amount
Water proofing treatment (Rate from BSR-2016) 𝑚2
Rs 1,187.00
Water proofing treatment by using Cement : fevicol : water
mix
𝑚2
Rs 646.00
Water proofing treatment by using Lime : fevicol : water mix 𝑚2
Rs.690.00
42. Lime fevicol mix application method cost is higher than cement fevicol mix
application method, but quality and durability is less compare with other
By comparing the cost of BSR and cement fevicol mix rate, cement fevicol
application became nearly half of the BSR. Comparatively cement fevicol
application is economical but we have to think about the quality and
durability.
43. 13 – Conclusion And Recommendation
From our observation, we observed some leakage on the tanks through the
cement fevicol mix application because we used brick construction. Which
tank surface was constructed by brick work. If we apply to block work or
concreted surface the leakage maybe reduce
By increase the fevicol ratio in the mix the result of bonding test, ponding
test and durability test maybe show better.
For our testing tanks we didn’t apply Plastering work to the surface. If we
apply the waterproof with plastering surface the effectiveness of alternative
waterproofing maybe increase.