5. NEW POLICE HEADQUARTERS
CITY OF COLLEGE STATION
CITY COUNCIL REVIEW | OCTOBER 02, 2017
INITIAL PROGRAM SIZE: 79,000 SF
BUDGET OVERVIEW
PROJECT BUDGET: $28.00 MILLION
SD PHASE SIZE: 85,650 SF
INITIAL SD ESTIMATE: $34.60 MILLION *
CURRENT SIZE: 74,815 SF
CURRENT ESTIMATE: $27.94 MILLION *
* Cost Estimate Includes:
Borrow pit fill, furnishing & equipment, information technology, security, back-
up generators, landscape budget, consultant design fees, design and owner
contingencies
PROJECT BUDGET
6. NEW POLICE HEADQUARTERS
CITY OF COLLEGE STATION
CITY COUNCIL REVIEW | OCTOBER 02, 2017
• Clarified masonry selection (cost/sf)
• Clarified flooring selections (cost/sf)
• Clarified perimeter fence material
• Relocated mechanical yard (closer to building)
• Reduced site paving quantity
• Removed Jail
• Reduce Square Footage by 10,835 (including Jail removal)
• Simplified annex building form
• Simplified entrance lobby form
SCOPE & BUDGET RECONCILIATION
PROJECT BUDGET
11. NEW POLICE HEADQUARTERS
CITY OF COLLEGE STATION
CITY COUNCIL REVIEW | OCTOBER 02, 2017
ALTERNATE FACADE OPTION | MATERIAL CONCEPTS
12. NEW POLICE HEADQUARTERS
CITY OF COLLEGE STATION
CITY COUNCIL REVIEW | OCTOBER 02, 2017
ALTERNATE FACADE OPTION | AERIAL PERSPECTIVE - NORTHEAST CORNER
13. NEW POLICE HEADQUARTERS
CITY OF COLLEGE STATION
CITY COUNCIL REVIEW | OCTOBER 02, 2017
ALTERNATE FACADE OPTION | PERSPECTIVE - CORNER VIEW
16. NEW POLICE HEADQUARTERS
CITY OF COLLEGE STATION
CITY COUNCIL REVIEW | OCTOBER 02, 2017
AERIAL PERSPECTIVE - NORTHEAST CORNER
17. NEW POLICE HEADQUARTERS
CITY OF COLLEGE STATION
CITY COUNCIL REVIEW | OCTOBER 02, 2017
PERSPECTIVE - CORNER VIEW
18. NEW POLICE HEADQUARTERS
CITY OF COLLEGE STATION
CITY COUNCIL REVIEW | OCTOBER 02, 2017
ALTERNATE FACADE OPTION | PERSPECTIVE - KRENEK TAP VIEW
19. NEW POLICE HEADQUARTERS
CITY OF COLLEGE STATION
CITY COUNCIL REVIEW | OCTOBER 02, 2017
ALTERNATE FACADE OPTION | PERSPECTIVE - MAIN BUILDING ENTRANCE
20. CITY COUNCIL REVIEW | OCTOBER 02, 2017
NEW POLICE HEADQUARTERS
CITY OF COLLEGE STATIONCITY MONUMENT SIGNS
21. NEW POLICE HEADQUARTERS
CITY OF COLLEGE STATION
CITY COUNCIL REVIEW | OCTOBER 02, 2017
SITE PLAN SURVERY AND ANALYSIS
22. CITY COUNCIL REVIEW | OCTOBER 02, 2017
NEW POLICE HEADQUARTERS
CITY OF COLLEGE STATION
SEASONAL SOLAR STUDY - FALLSEASONAL SOLAR STUDY - SUMMER
SEASONAL SOLAR STUDY - SPRINGSEASONAL SOLAR STUDY - WINTER
SITE SOLAR ANALYSIS
23. NEW POLICE HEADQUARTERS
CITY OF COLLEGE STATION
CITY COUNCIL REVIEW | OCTOBER 02, 2017
GLASS TECHNOLOGY AND BUILDING ORIENTATION ANALYSIS
Low Emissivity Glass: Emissivity measures the ability to radiate energy and the lower
the emissivity the less heat is transferred in or out.
Louvers and
Overhangs
diffuse light
and heat
from entering
the building.
Sun Position
• The best quality of indirect light is
always from the North
• The worst is direct light and heat from
the South
• The building is situated on the sight to
where the majority of glazing is facing
North-northwest
Low-E Glass Section Site Solar Diagram
BENEFITS OF GLASS
Summer
Keeps interiors
cooler in warmer
months
Blocks majority long
wave solar heat
energy
Winter
Keeps interiors
warmer in cooler
months
In the winter interior
radiant heat is kept
reflected back inside
Seasonal Glass Preformance Work Place Benefit
• Increase in Natural daylight puts less
stress on artificial lighting which in turn
reduces energy usage
• Increase in productivity and well-being
• Reduces likelihood of fatigue, headache,
lack of concentration, and eye strain.
• 73% of Office Works found daylight
Desirable.
• Views to the outdoors with change in
daylight conditions are necessary for
metal stimulation
• Open floor plan as well as plenty of
windows communicates to employees
the open and inviting nature of the
business.
• Increase in productivity and well-being
• Decrease in absenteeism
• Decrease in employee turnover
Low-E
Coating
Argon Glass
Blend
Outside
Inside
Majority of
visible light passes
through year round.
Majority of
summer heat is
reflected outside.
Heat
Majority of
harmful UV Rays
are reflected
year round.
Light
24. NEW POLICE HEADQUARTERS
CITY OF COLLEGE STATION
CITY COUNCIL REVIEW | OCTOBER 02, 2017
SCHEDULE:
IF PROCEED WITH CURRENT FORM AND FLOOR PLAN:
Design Development (DD): 11/13/2017
Design Development Cost Estimate: 12/04/2017
Issue for Permit: 02/05/2018
Issue for Competitive Sealed Proposal: 04/02/2018
Start Construction: 07/02/2018
IF CHANGE OF AESTHETIC, FORM, AND FLOOR PLAN:
Determination of Design Direction (6 months): 03/05/2018
Finalize Design Aesthetic /Floor Plan (2 months): 05/01/2018
Produce Document and Select Contractor (9 months): 02/04/2019
Start Construction: 02/04/2019
9MONTHS
DESIGN DIRECTION