Commissioning for Better
Buildings
Nicholas A. Chazapis
Commissioning Consultant
Revised Version
Better Buildings
• Better Project Management
• Better Design
• Better Construction
• Better Occupancy
• Better Renovation
• Better Reconstruction
Better Buildings
• Project Management:
– Owner’s Requirements
– Feasibility study
– Appoint Architects and Engineers
– Certification Environmental Credit Bodies.
Better Buildings
• A/E Design:
– Building Program
– Basis of Design
– Applications Engineering
Better Buildings
• Building Construction:
– Specifications
– Time schedule
– Costs
Better Buildings
• Building Occupancy:
– Seasonal Tests
– Occupants Questionnaire
– Complaints Analysis.
Better Buildings
• Building Renovation:
– New innovative automatic controls
– Internet of Things
– Continuous Commissioning
Better Buildings
• Building Reconstruction:
– As built drawings updated for years.
– Assets / Equipment Maintenance Archive.
– Operations and Maintenance Costs Archive.
Commissioning for Better
Buildings
Useful Colors of Project Management
Better Buildings Workforce Guidelines
• The U.S. Department of Energy (DOE) and the
National Institute of Building Sciences
(Institute) through its Commercial Workforce
Credentialing Council (CWCC) have worked
with industry stakeholders to develop
voluntary national guidelines aimed at
improving the quality and consistency of
commercial building workforce credentials for
four key energy-related jobs.
Better Buildings Workforce (BBWG)
• The Commercial Building Energy Auditor is an
energy solutions professional who assesses
building systems and site conditions; analyzes
and evaluates equipment and energy usage;
and recommends strategies to optimize
building resource utilization
Better Buildings Workforce (BBWG)
• The Building Commissioning (Cx) Professional
is an individual who leads, plans, coordinates
and manages a commissioning team to
implement commissioning processes in new
and existing buildings.
Better Buildings Workforce (BBWG)
• An Energy Manager is responsible for
managing and continually improving energy
performance in commercial buildings by
establishing and maintaining an energy
program management system that supports
the mission and goals of the organization.
Better Buildings Workforce (BBWG)
• The Building Operations Professional manages
the maintenance and operation of building
systems and installed equipment, and
performs general maintenance to maintain
the building's operability, optimize building
performance, and ensure the comfort,
productivity and safety of the building
occupants.
Better Buildings: Future Buildings
Better Buildings: Future Buildings
Better Buildings: Future Buildings
Better Buildings: Future Buildings
Commissioning for Better Buildings in the Future
Commissioning for Better
Buildings in the Future.
End of Presentation
More info: leader@commissioning.gr

Chazapis cx for better buildings rev

  • 1.
    Commissioning for Better Buildings NicholasA. Chazapis Commissioning Consultant Revised Version
  • 2.
    Better Buildings • BetterProject Management • Better Design • Better Construction • Better Occupancy • Better Renovation • Better Reconstruction
  • 3.
    Better Buildings • ProjectManagement: – Owner’s Requirements – Feasibility study – Appoint Architects and Engineers – Certification Environmental Credit Bodies.
  • 4.
    Better Buildings • A/EDesign: – Building Program – Basis of Design – Applications Engineering
  • 5.
    Better Buildings • BuildingConstruction: – Specifications – Time schedule – Costs
  • 6.
    Better Buildings • BuildingOccupancy: – Seasonal Tests – Occupants Questionnaire – Complaints Analysis.
  • 7.
    Better Buildings • BuildingRenovation: – New innovative automatic controls – Internet of Things – Continuous Commissioning
  • 8.
    Better Buildings • BuildingReconstruction: – As built drawings updated for years. – Assets / Equipment Maintenance Archive. – Operations and Maintenance Costs Archive.
  • 9.
    Commissioning for Better Buildings UsefulColors of Project Management
  • 10.
    Better Buildings WorkforceGuidelines • The U.S. Department of Energy (DOE) and the National Institute of Building Sciences (Institute) through its Commercial Workforce Credentialing Council (CWCC) have worked with industry stakeholders to develop voluntary national guidelines aimed at improving the quality and consistency of commercial building workforce credentials for four key energy-related jobs.
  • 11.
    Better Buildings Workforce(BBWG) • The Commercial Building Energy Auditor is an energy solutions professional who assesses building systems and site conditions; analyzes and evaluates equipment and energy usage; and recommends strategies to optimize building resource utilization
  • 12.
    Better Buildings Workforce(BBWG) • The Building Commissioning (Cx) Professional is an individual who leads, plans, coordinates and manages a commissioning team to implement commissioning processes in new and existing buildings.
  • 13.
    Better Buildings Workforce(BBWG) • An Energy Manager is responsible for managing and continually improving energy performance in commercial buildings by establishing and maintaining an energy program management system that supports the mission and goals of the organization.
  • 14.
    Better Buildings Workforce(BBWG) • The Building Operations Professional manages the maintenance and operation of building systems and installed equipment, and performs general maintenance to maintain the building's operability, optimize building performance, and ensure the comfort, productivity and safety of the building occupants.
  • 15.
  • 16.
  • 17.
  • 18.
    Better Buildings: FutureBuildings Commissioning for Better Buildings in the Future
  • 19.
    Commissioning for Better Buildingsin the Future. End of Presentation More info: leader@commissioning.gr