The document provides information about construction of the Chaplin Station for the Eglinton Crosstown LRT project. Key details include:
- Construction will begin in fall 2016 and occur in 4 stages over approximately 20 months, requiring temporary traffic changes and bus stop relocations.
- Utilities will be relocated, followed by installation of support of excavation and construction of the station box underground.
- The station will have entrances at Chaplin Crescent and Eglinton Avenue. Design concepts aim for accessibility, natural light, and integration with the community.
- Traffic mitigation measures will include temporarily closing Gilgorm Road and relaxing turn restrictions on nearby streets.
The document provides information about construction of the Mount Pleasant Station for the Eglinton Crosstown LRT project. Key details include:
- Construction will begin in fall 2016 and involve supporting excavation, utility relocation, and installing a concrete roof slab to allow work under the roadway.
- The station will be built using a modified cut-and-cover method to minimize road disruption. It will feature a main entrance preserving a heritage facade and a secondary entrance.
- Temporary traffic and pedestrian changes like road closures and sidewalk restrictions will be needed during construction stages from 2016-2017. Nearby TTC bus stops will also be relocated.
- Safety is the top priority, and the project
The document provides information about the construction of the Caledonia Station for the Eglinton Crosstown LRT project in Toronto. Key details include:
- Construction began in March 2016 at the Keelesdale station and Caledonia station construction will involve installing supports, excavating, and building the underground structure from 2016-2017.
- The station will be built using a "cut-and-cover" method where the area is excavated and covered with a concrete roof allowing work below. Safety is the top priority during construction.
- When complete in 2020, the new modern LRT line will be 19km long with 25 stations, connecting communities along Eglinton Avenue.
Fairbank and Oakwood stations open house Crosstown TO
The document provides information about upcoming open houses for the Fairbank and Oakwood stations on the Eglinton Crosstown LRT project. It discusses safety as the top priority during construction and provides background on the project. Details are given on how the underground stations will be constructed, including using cut-and-cover and mined methods. specifics are outlined about the construction process and timelines for Fairbank station, including traffic and pedestrian impacts during utility relocation and shoring. Design concepts and features of Fairbank and Oakwood stations are also summarized.
The document provides information about safety protocols and the construction of the Eglinton Crosstown LRT project. It discusses safety as the top priority and outlines roles and responsibilities. It then summarizes that the project involves building a 19km LRT route with 15 underground stations and 10 surface stops to connect communities along Eglinton Avenue. It highlights some key aspects of the construction process for Leaside station, including using both cut-and-cover and mined methods with sequential excavation.
This document provides information about construction of the Laird Station for the Eglinton Crosstown LRT project in Toronto. It discusses that Laird Station will be built using the mined method known as Sequential Excavation Method. This involves installing support around the station entrances for 12 months, then excavating inside in segments over about 44 months total. During construction there will be lane and sidewalk closures near the station that will impact traffic and pedestrians. The document outlines the construction timeline and expected impacts at Laird Station.
Leaside Station Open House - March 2017Crosstown TO
The document provides information about the construction of the Eglinton Crosstown LRT line in Toronto. It discusses the background and players involved in the project, details about what is being built including its route and features, safety and accessibility considerations, construction methods and timelines, and community benefits initiatives. The specific section on Leaside station provides renderings and details plans for its construction including utility relocations, shoring work, and expected timelines and impacts through 2017.
The document provides information about construction of the Forest Hill station for the Eglinton Crosstown LRT project. Safety is the top priority during construction. The station will be built using a top-down construction method over approximately 15 months. This will involve installing supports, excavating, and rebuilding the road above. The station design includes two entrances, an outdoor bike area, and retail space. Construction will require some sidewalk and lane closures.
This document provides information about an open house for the Mount Dennis & West Portal areas of the Eglinton Crosstown LRT project in Toronto. It discusses construction plans and timelines for the Mount Dennis station, which will use a modified cut and cover method, and relocate an existing building. It also outlines safety protocols for the project and provides design details and renderings of the proposed Mount Dennis station, bus facility, entrances, and plaza. Additionally, it discusses the elevated guideway and west portal that will connect to the underground portion of the line at Mount Dennis station.
The document provides information about construction of the Mount Pleasant Station for the Eglinton Crosstown LRT project. Key details include:
- Construction will begin in fall 2016 and involve supporting excavation, utility relocation, and installing a concrete roof slab to allow work under the roadway.
- The station will be built using a modified cut-and-cover method to minimize road disruption. It will feature a main entrance preserving a heritage facade and a secondary entrance.
- Temporary traffic and pedestrian changes like road closures and sidewalk restrictions will be needed during construction stages from 2016-2017. Nearby TTC bus stops will also be relocated.
- Safety is the top priority, and the project
The document provides information about the construction of the Caledonia Station for the Eglinton Crosstown LRT project in Toronto. Key details include:
- Construction began in March 2016 at the Keelesdale station and Caledonia station construction will involve installing supports, excavating, and building the underground structure from 2016-2017.
- The station will be built using a "cut-and-cover" method where the area is excavated and covered with a concrete roof allowing work below. Safety is the top priority during construction.
- When complete in 2020, the new modern LRT line will be 19km long with 25 stations, connecting communities along Eglinton Avenue.
Fairbank and Oakwood stations open house Crosstown TO
The document provides information about upcoming open houses for the Fairbank and Oakwood stations on the Eglinton Crosstown LRT project. It discusses safety as the top priority during construction and provides background on the project. Details are given on how the underground stations will be constructed, including using cut-and-cover and mined methods. specifics are outlined about the construction process and timelines for Fairbank station, including traffic and pedestrian impacts during utility relocation and shoring. Design concepts and features of Fairbank and Oakwood stations are also summarized.
The document provides information about safety protocols and the construction of the Eglinton Crosstown LRT project. It discusses safety as the top priority and outlines roles and responsibilities. It then summarizes that the project involves building a 19km LRT route with 15 underground stations and 10 surface stops to connect communities along Eglinton Avenue. It highlights some key aspects of the construction process for Leaside station, including using both cut-and-cover and mined methods with sequential excavation.
This document provides information about construction of the Laird Station for the Eglinton Crosstown LRT project in Toronto. It discusses that Laird Station will be built using the mined method known as Sequential Excavation Method. This involves installing support around the station entrances for 12 months, then excavating inside in segments over about 44 months total. During construction there will be lane and sidewalk closures near the station that will impact traffic and pedestrians. The document outlines the construction timeline and expected impacts at Laird Station.
Leaside Station Open House - March 2017Crosstown TO
The document provides information about the construction of the Eglinton Crosstown LRT line in Toronto. It discusses the background and players involved in the project, details about what is being built including its route and features, safety and accessibility considerations, construction methods and timelines, and community benefits initiatives. The specific section on Leaside station provides renderings and details plans for its construction including utility relocations, shoring work, and expected timelines and impacts through 2017.
The document provides information about construction of the Forest Hill station for the Eglinton Crosstown LRT project. Safety is the top priority during construction. The station will be built using a top-down construction method over approximately 15 months. This will involve installing supports, excavating, and rebuilding the road above. The station design includes two entrances, an outdoor bike area, and retail space. Construction will require some sidewalk and lane closures.
This document provides information about an open house for the Mount Dennis & West Portal areas of the Eglinton Crosstown LRT project in Toronto. It discusses construction plans and timelines for the Mount Dennis station, which will use a modified cut and cover method, and relocate an existing building. It also outlines safety protocols for the project and provides design details and renderings of the proposed Mount Dennis station, bus facility, entrances, and plaza. Additionally, it discusses the elevated guideway and west portal that will connect to the underground portion of the line at Mount Dennis station.
The document provides information about the construction of the Eglinton Crosstown LRT project in Toronto, including details about safety procedures, the construction process for underground stations using cut-and-cover and mined methods, plans for the Science Centre station, and efforts to minimize impacts on traffic and keep the community informed and benefitted through employment opportunities. Key aspects of the project include building 19 km of light rail track, 15 underground stations, a maintenance facility, and links to other transit lines while prioritizing safety, accessibility, and community engagement.
The document summarizes plans for the Keelesdale Station Open House regarding the Eglinton Crosstown LRT project. It discusses that the project aims to address traffic congestion problems in the GTHA. Construction of Keelesdale Station will use a cut-and-cover method, requiring excavation of the area and installation of support structures. During construction, there will be lane reductions, sidewalk closures, and parking removals to stage work zones. The open house provided details on station design, construction timelines and impacts to traffic, pedestrians and transit stops.
Cedarvale station open house for website final2Crosstown TO
The document discusses construction plans and timelines for the Cedarvale Station on the Eglinton Crosstown LRT project in Toronto. It provides details on safety protocols, construction methods like cut-and-cover, and expected staging over the next few years including road closures and utility relocations to accommodate station building. Community benefits and engagement efforts are also highlighted.
The document discusses plans for constructing Avenue Station on the Eglinton Crosstown LRT project, including:
- Avenue Station will be one of the longest underground stations at 400 meters due to its crossover track structure.
- Metrolinx proposes temporarily using part of the North Toronto Memorial Community Centre lands for construction staging and laydown areas.
- Several traffic and parking mitigation alternatives are discussed to address impacts during construction, including retaining some parking on Eglinton Avenue.
The document provides information about construction of the Forest Hill station for the Eglinton Crosstown LRT project in Toronto. Safety is the top priority during construction. The station will be built using a cut-and-cover method, requiring excavation below the road that will later be reinstated. Construction will occur in stages from 2016-2017, with traffic and pedestrian changes implemented to accommodate work zones. The station design includes entrances, a bike parking area, and potential retail space. Nearby roads will be used as haul routes during excavation and shoring stages.
Avenue station open house presentation Crosstown TO
The document discusses plans to build the Eglinton Crosstown LRT in Toronto to address traffic congestion problems, including constructing a 19 km light rail line with 25 stations from Weston Road to Kennedy Station. It describes the different station construction methods being used, provides design concepts and features of the stations, and outlines the construction process and community updates for the Avenue Station.
The document provides information about an open house for the Eglinton Crosstown LRT project, including details on safety procedures, construction of underground stations using cut-and-cover methods, expected impacts such as road and sidewalk closures during utility relocation and shoring work, and renderings of the planned Eglinton station design and integration with the existing TTC subway line. Temporary bus stop relocations and routing changes are also outlined to accommodate construction stages over the next 4 years.
Mount Dennis Station and EMSF Open House - March 2017Crosstown TO
The document provides details about the construction of the Eglinton Crosstown LRT project in Toronto. It discusses the background and players involved in the project, as well as details about building the 19-kilometer light rail line which includes 15 underground stations and 10 surface stops. Safety is the top priority during construction. Community benefits and business support programs are being implemented to help local residents and businesses impacted by construction. Regular updates are encouraged by following Crosstown social media channels or visiting one of their local project offices.
Chaplin Station Open House Feb 24 and 27 describes the construction work happening in the Eglinton and Chaplin area for the Eglinton Crosstown project.
Surface Section and Kennedy Station Open House - April 2017Crosstown TO
- The document provides details about the construction of the Eglinton Crosstown LRT project in Toronto. It discusses the history and planning of the project, describes what is being built including underground stations, surface stops and interchange stations, and outlines the construction approach and timelines. Safety, accessibility, and minimizing environmental impact are priorities. The summary highlights construction is underway at all underground stations, with utility relocations and supporting excavations in progress or planned for 2017 at interchange stations like Kennedy. Surface stop road widening and utility work will also begin in 2017.
Crosstown business opportunties and info session presentationCrosstown TO
Crosslinx Transit Solutions (CTS) held an information session to share details about business opportunities for the Eglinton Crosstown LRT project. CTS will design, build, finance, and maintain the light rail line and its 25 stations over 30 years. The project is divided into six construction segments that will be built between 2015 and 2021. CTS is committed to supporting local economic development and hiring through employment, procurement, and community investment. They encouraged local businesses to learn more about contracting opportunities by registering on their website.
Caledonia Station, West Portal and Elevated Guideway Open HouseCrosstown TO
The document provides information on the construction of the Eglinton Crosstown LRT project in Toronto, including:
- An overview of Metrolinx and their regional transportation plan which included the Eglinton Crosstown LRT.
- Details on the 19km LRT route, including 15 underground stations, surface stops, maintenance facility, and links to other transit lines.
- An emphasis on safety as the top priority during construction.
- Renderings and descriptions of station designs and their accessibility, environmental, and sustainability features.
- Explanations of the cut-and-cover and mined tunnel construction methods being used.
- Updates on construction progress in 2017, including tunnel excav
The document provides information about the Eglinton Crosstown LRT project in Toronto. It discusses the need for improved transit due to traffic congestion, outlines Metrolinx's mandate to plan and build transit projects, and provides details about the construction of the Eglinton Crosstown line. Specifically, it will be a 19km light rail line running mostly underground with 25 stations. Construction is underway using different methods and will continue through 2019, with impacts to traffic and pedestrians along Eglinton Avenue.
The document provides information about the construction of the Eglinton Crosstown LRT project in Toronto, including:
- Metrolinx is the agency overseeing regional transportation in the Greater Toronto area, including a $50 billion, 25-year plan.
- The 19-km Eglinton Crosstown LRT will have 15 underground stations, 10 surface stops, a maintenance facility, and links to other transit lines.
- Safety is the top priority during construction, which uses cut-and-cover and mined methods to excavate station areas.
- Upcoming work at the Avenue Station in 2017 includes installing support structures, dewatering wells, and mitigating utilities like sewer lining.
The document provides information about the construction of the Eglinton Crosstown LRT project in Toronto. It discusses Metrolinx's regional transportation plan, the project details such as the 19km route and 25 stations (9 underground, 10 surface), safety and accessibility features, construction methods like cut-and-cover and sequential excavation mining, and community benefits like a youth-led mural at Laird station. Updates on construction progress in 2016-2017 are also outlined.
Former Kodak Lands Update - November 19, 2015Crosstown TO
This document provides an overview of Metrolinx's current plan for the former Kodak lands located near Mount Dennis Station. It discusses 9 guiding principles for the redevelopment, including maximizing development potential while minimizing the footprint of the Eglinton Maintenance and Storage Facility. The plan proposes a phased approach to intensification and identifies areas that could accommodate additional uses in the future. It also emphasizes connecting the site to nearby green spaces, employment lands, and communities through improved transportation and pedestrian infrastructure. Heritage buildings will be conserved and integrated into any new development.
Mount Dennis Mobility Hub Update and Station Design ReviewCrosstown TO
Metrolinx invites you to view an updated presentation for the Mount Dennis Mobility Hub Workshop. The purpose for the presentation is to present a preliminary station design concept and a series of more refined concepts for how the lands around the station could develop over time. Have your say at thecrosstown.ca.
Fairbank & Oakwood Stations Open House - April 2017Crosstown TO
The document provides information about the construction of the Eglinton Crosstown LRT project in Toronto, including:
- Metrolinx is overseeing the $50 billion regional transportation plan to integrate transit in the Toronto area.
- The 19km Eglinton Crosstown LRT will run underground and above ground with 25 stations, and is scheduled to open in 2022.
- The document focuses on construction plans and impacts around the Fairbank Station, including traffic staging plans from 2017-2018 to allow excavation and shoring work. Haul routes are identified to transport material on and off site.
Kennedy Station Design Update Meeting PresentationCrosstown TO
Metrolinx invites you to attend a meeting for information on the preliminary station and stop designs for the Eglinton Crosstown project. Specifically, the station design concept for the Crosstown Kennedy Station, including the mobility hub study, will be presented. As well, the surface stop design concepts and surface alignment from Bermondsey to Kennedy will be available for review.
Leaside - Laird Construction Liaison Committee Meeting - June 2017Crosstown TO
The document provides updates on construction progress and plans for the Crosstown LRT's Leaside and Laird stations. At Leaside Station, support of excavation work is underway and will continue through 2017. Laird Station is being built using sequential excavation mining, with mining operations starting at the secondary entrance and expected to continue through late 2019. Both stations will require ongoing utility relocations and traffic management as construction advances throughout 2017.
Cedarvale Station Open House - March 2017Crosstown TO
The document provides information about the construction of the Eglinton Crosstown LRT line in Toronto. It discusses the background and players involved in the project, details about what is being built including key features and design approaches, how construction is taking place through methods like tunnel boring and cut-and-cover stations, community benefits and business support programs, and timelines and expected activities over 2017 at the Cedarvale station site. Safety, accessibility, environment and sustainability considerations are also outlined.
The document provides information about the construction of the Eglinton Crosstown LRT project in Toronto, including details about safety procedures, the construction process for underground stations using cut-and-cover and mined methods, plans for the Science Centre station, and efforts to minimize impacts on traffic and keep the community informed and benefitted through employment opportunities. Key aspects of the project include building 19 km of light rail track, 15 underground stations, a maintenance facility, and links to other transit lines while prioritizing safety, accessibility, and community engagement.
The document summarizes plans for the Keelesdale Station Open House regarding the Eglinton Crosstown LRT project. It discusses that the project aims to address traffic congestion problems in the GTHA. Construction of Keelesdale Station will use a cut-and-cover method, requiring excavation of the area and installation of support structures. During construction, there will be lane reductions, sidewalk closures, and parking removals to stage work zones. The open house provided details on station design, construction timelines and impacts to traffic, pedestrians and transit stops.
Cedarvale station open house for website final2Crosstown TO
The document discusses construction plans and timelines for the Cedarvale Station on the Eglinton Crosstown LRT project in Toronto. It provides details on safety protocols, construction methods like cut-and-cover, and expected staging over the next few years including road closures and utility relocations to accommodate station building. Community benefits and engagement efforts are also highlighted.
The document discusses plans for constructing Avenue Station on the Eglinton Crosstown LRT project, including:
- Avenue Station will be one of the longest underground stations at 400 meters due to its crossover track structure.
- Metrolinx proposes temporarily using part of the North Toronto Memorial Community Centre lands for construction staging and laydown areas.
- Several traffic and parking mitigation alternatives are discussed to address impacts during construction, including retaining some parking on Eglinton Avenue.
The document provides information about construction of the Forest Hill station for the Eglinton Crosstown LRT project in Toronto. Safety is the top priority during construction. The station will be built using a cut-and-cover method, requiring excavation below the road that will later be reinstated. Construction will occur in stages from 2016-2017, with traffic and pedestrian changes implemented to accommodate work zones. The station design includes entrances, a bike parking area, and potential retail space. Nearby roads will be used as haul routes during excavation and shoring stages.
Avenue station open house presentation Crosstown TO
The document discusses plans to build the Eglinton Crosstown LRT in Toronto to address traffic congestion problems, including constructing a 19 km light rail line with 25 stations from Weston Road to Kennedy Station. It describes the different station construction methods being used, provides design concepts and features of the stations, and outlines the construction process and community updates for the Avenue Station.
The document provides information about an open house for the Eglinton Crosstown LRT project, including details on safety procedures, construction of underground stations using cut-and-cover methods, expected impacts such as road and sidewalk closures during utility relocation and shoring work, and renderings of the planned Eglinton station design and integration with the existing TTC subway line. Temporary bus stop relocations and routing changes are also outlined to accommodate construction stages over the next 4 years.
Mount Dennis Station and EMSF Open House - March 2017Crosstown TO
The document provides details about the construction of the Eglinton Crosstown LRT project in Toronto. It discusses the background and players involved in the project, as well as details about building the 19-kilometer light rail line which includes 15 underground stations and 10 surface stops. Safety is the top priority during construction. Community benefits and business support programs are being implemented to help local residents and businesses impacted by construction. Regular updates are encouraged by following Crosstown social media channels or visiting one of their local project offices.
Chaplin Station Open House Feb 24 and 27 describes the construction work happening in the Eglinton and Chaplin area for the Eglinton Crosstown project.
Surface Section and Kennedy Station Open House - April 2017Crosstown TO
- The document provides details about the construction of the Eglinton Crosstown LRT project in Toronto. It discusses the history and planning of the project, describes what is being built including underground stations, surface stops and interchange stations, and outlines the construction approach and timelines. Safety, accessibility, and minimizing environmental impact are priorities. The summary highlights construction is underway at all underground stations, with utility relocations and supporting excavations in progress or planned for 2017 at interchange stations like Kennedy. Surface stop road widening and utility work will also begin in 2017.
Crosstown business opportunties and info session presentationCrosstown TO
Crosslinx Transit Solutions (CTS) held an information session to share details about business opportunities for the Eglinton Crosstown LRT project. CTS will design, build, finance, and maintain the light rail line and its 25 stations over 30 years. The project is divided into six construction segments that will be built between 2015 and 2021. CTS is committed to supporting local economic development and hiring through employment, procurement, and community investment. They encouraged local businesses to learn more about contracting opportunities by registering on their website.
Caledonia Station, West Portal and Elevated Guideway Open HouseCrosstown TO
The document provides information on the construction of the Eglinton Crosstown LRT project in Toronto, including:
- An overview of Metrolinx and their regional transportation plan which included the Eglinton Crosstown LRT.
- Details on the 19km LRT route, including 15 underground stations, surface stops, maintenance facility, and links to other transit lines.
- An emphasis on safety as the top priority during construction.
- Renderings and descriptions of station designs and their accessibility, environmental, and sustainability features.
- Explanations of the cut-and-cover and mined tunnel construction methods being used.
- Updates on construction progress in 2017, including tunnel excav
The document provides information about the Eglinton Crosstown LRT project in Toronto. It discusses the need for improved transit due to traffic congestion, outlines Metrolinx's mandate to plan and build transit projects, and provides details about the construction of the Eglinton Crosstown line. Specifically, it will be a 19km light rail line running mostly underground with 25 stations. Construction is underway using different methods and will continue through 2019, with impacts to traffic and pedestrians along Eglinton Avenue.
The document provides information about the construction of the Eglinton Crosstown LRT project in Toronto, including:
- Metrolinx is the agency overseeing regional transportation in the Greater Toronto area, including a $50 billion, 25-year plan.
- The 19-km Eglinton Crosstown LRT will have 15 underground stations, 10 surface stops, a maintenance facility, and links to other transit lines.
- Safety is the top priority during construction, which uses cut-and-cover and mined methods to excavate station areas.
- Upcoming work at the Avenue Station in 2017 includes installing support structures, dewatering wells, and mitigating utilities like sewer lining.
The document provides information about the construction of the Eglinton Crosstown LRT project in Toronto. It discusses Metrolinx's regional transportation plan, the project details such as the 19km route and 25 stations (9 underground, 10 surface), safety and accessibility features, construction methods like cut-and-cover and sequential excavation mining, and community benefits like a youth-led mural at Laird station. Updates on construction progress in 2016-2017 are also outlined.
Former Kodak Lands Update - November 19, 2015Crosstown TO
This document provides an overview of Metrolinx's current plan for the former Kodak lands located near Mount Dennis Station. It discusses 9 guiding principles for the redevelopment, including maximizing development potential while minimizing the footprint of the Eglinton Maintenance and Storage Facility. The plan proposes a phased approach to intensification and identifies areas that could accommodate additional uses in the future. It also emphasizes connecting the site to nearby green spaces, employment lands, and communities through improved transportation and pedestrian infrastructure. Heritage buildings will be conserved and integrated into any new development.
Mount Dennis Mobility Hub Update and Station Design ReviewCrosstown TO
Metrolinx invites you to view an updated presentation for the Mount Dennis Mobility Hub Workshop. The purpose for the presentation is to present a preliminary station design concept and a series of more refined concepts for how the lands around the station could develop over time. Have your say at thecrosstown.ca.
Fairbank & Oakwood Stations Open House - April 2017Crosstown TO
The document provides information about the construction of the Eglinton Crosstown LRT project in Toronto, including:
- Metrolinx is overseeing the $50 billion regional transportation plan to integrate transit in the Toronto area.
- The 19km Eglinton Crosstown LRT will run underground and above ground with 25 stations, and is scheduled to open in 2022.
- The document focuses on construction plans and impacts around the Fairbank Station, including traffic staging plans from 2017-2018 to allow excavation and shoring work. Haul routes are identified to transport material on and off site.
Kennedy Station Design Update Meeting PresentationCrosstown TO
Metrolinx invites you to attend a meeting for information on the preliminary station and stop designs for the Eglinton Crosstown project. Specifically, the station design concept for the Crosstown Kennedy Station, including the mobility hub study, will be presented. As well, the surface stop design concepts and surface alignment from Bermondsey to Kennedy will be available for review.
Leaside - Laird Construction Liaison Committee Meeting - June 2017Crosstown TO
The document provides updates on construction progress and plans for the Crosstown LRT's Leaside and Laird stations. At Leaside Station, support of excavation work is underway and will continue through 2017. Laird Station is being built using sequential excavation mining, with mining operations starting at the secondary entrance and expected to continue through late 2019. Both stations will require ongoing utility relocations and traffic management as construction advances throughout 2017.
Cedarvale Station Open House - March 2017Crosstown TO
The document provides information about the construction of the Eglinton Crosstown LRT line in Toronto. It discusses the background and players involved in the project, details about what is being built including key features and design approaches, how construction is taking place through methods like tunnel boring and cut-and-cover stations, community benefits and business support programs, and timelines and expected activities over 2017 at the Cedarvale station site. Safety, accessibility, environment and sustainability considerations are also outlined.
Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017Crosstown TO
The document provides updates on construction progress at the Avenue Station and Chaplin Station sites for the Eglinton Crosstown LRT project, including that piling and excavation are underway at Avenue Station and will continue through 2017, while piling and utility relocation work are ongoing at Chaplin Station through the spring of 2017 as part of the initial construction stage. Aerial renderings and construction progress photos of both sites are also included.
Western Works Construction Liaison Committee Meeting - September 2017Crosstown TO
The document provides updates on ongoing construction works for the Crosstown LRT project in September 2017, including:
1) Works at the Maintenance and Storage Facility, Mount Dennis Station, the railway corridor, West Portal and elevated guideway, Keelesdale Station, and Caledonia Station.
2) Details on concrete pouring for the LRT tunnel invert and fit out, including delivery, laying of rebar, and pouring in stages.
3) Notices of works including pile driving and road/sidewalk closures at specific locations.
Cedarvale - Forest Hill Construction Liaison Committee Meeting - June 2017Crosstown TO
The document provides construction updates for the Cedarvale and Forest Hill stations of the Eglinton Crosstown project.
For Cedarvale station, utilities relocation is ongoing, tunnel concrete pouring is in progress, shoring for an entrance is underway, and traffic changes are scheduled for mid-July.
For Forest Hill station, demolition, utilities relocation, and piling work have been completed. Upcoming work includes continuing piling, excavation, and starting piling at the main and secondary entrances over the summer. The document includes renderings and photos of progress.
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Crosstown TO
This document provides updates on construction activities at the Avenue Station and Chaplin Station sites for the Crosstown LRT project in Q2 and Q3 of 2017.
For Avenue Station, excavation and monitoring installations will continue in Q2 and Q3, with utilities work and sound wall installations also planned. Dewatering systems will be operating by Q4.
For Chaplin Station, piling will continue at entrances and the station box through Q3. Utilities relocation and traffic staging are also outlined. Concept diagrams show the planned layouts of both stations. Progress photos depict current construction stages.
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Crosstown TO
The document provides an update on construction of the Crosstown LRT project in Toronto, specifically focusing on the West At-Grade section from Brentcliffe to Victoria Park and the Science Centre Station. It summarizes that preparatory works are underway at both locations, including geotechnical investigations, utility relocations and tree protection. At Brentcliffe, piling for support of excavation is nearly complete. At Science Centre Station, piling is underway and existing traffic staging has been installed to support upcoming works like piling, utility relocation and road widening. Renderings of stations along the West At-Grade section and of the Science Centre Station are also included.
Science Centre Station and West At-Grade Surface Stops Open House - November ...Crosstown TO
The document provides information about the Crosstown LRT project's Science Centre Station and surface stops. It summarizes that the project includes an underground station with links to other transit lines, a maintenance facility, and surface stops along a 19km route. It discusses safety as the top priority and highlights design principles, environmental sustainability initiatives, and community outreach efforts like employment opportunities and public art projects. Renderings depict planned station and stop designs.
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017Crosstown TO
The document provides updates on construction activities at the Avenue and Chaplin stations for the Crosstown LRT project in Q2 and Q3 of 2017. At Avenue station, excavation is underway at the main and secondary entrances and will continue level by level with supporting structures installed. Dewatering wells and utilities work including sewer lining and water main replacement will also take place. At Chaplin station, piling will continue at the tertiary and southeast areas and the pedestrian detour will be rerouted. Concept designs and progress photos are also included.
Forest Hill Station Open House - June 2017Crosstown TO
The document provides information about the construction of the Eglinton Crosstown LRT project in Toronto. It discusses Metrolinx's regional transportation plan, the project details including a 19km LRT route with underground and surface stations, and safety and accessibility features. It outlines the construction methods using cut-and-cover and mined tunnels. It highlights 2017 construction milestones and provides renderings and progress updates for the Forest Hill station.
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Crosstown TO
The document provides updates on construction progress at the Fairbank and Oakwood stations for the Crosstown LRT. At Fairbank Station, support of excavation using a top-down method is underway and will take 1.5 years to complete. Updates provided include piling, utilities relocation, and traffic staging. At Oakwood Station, support of excavation is complete at the entrances and excavation within the station box is proceeding using the sequential excavation method. Near-term work at Oakwood includes excavation, geotechnical instrumentation, crane assembly, and service connections requiring some overnight work. Progress photos document the current states of construction.
Western Works - Construction Liaison Committee Meeting - May 2017Crosstown TO
The document provides an overview and progress update of the Eglinton Crosstown LRT project. Key points discussed include the maintenance and storage facility, Mount Dennis Station, tunnel construction, and progress at Keelesdale and Caledonia stations. Updates on concrete pouring in the tunnels and foundation work at various sites are also provided.
Cedarvale - Forest Hill Construction Liaison Committee Meeting - May 2017Crosstown TO
The document provides construction updates for the Cedarvale and Forest Hill stations of the Eglinton Crosstown project. For Cedarvale station, monitoring installations are complete, utility relocations are underway, tunnel concrete pouring is ongoing, and shoring works will begin in June. For Forest Hill station, demolition, geotechnical work, and utility relocations are complete, piling on the southwest side is finished, and future work includes continued piling and excavation. Renderings of the proposed stations are also included.
Eglinton Station Open House - March 2017Crosstown TO
The document provides information about the construction of the Eglinton Crosstown LRT line in Toronto. It discusses the background and players involved in the project, details about what is being built including its route and features, safety and accessibility considerations, and environmental and sustainability efforts. It also outlines the construction approach and methods, as well as summaries of work completed in 2016 and anticipated milestones and impacts for 2017, such as utility relocations and support of excavation at station sites like Eglinton station. Community benefits and ways to stay updated on the project are also mentioned.
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Crosstown TO
1) The Crosstown LRT will be a 19-kilometre light rail line running east-west across Toronto, with 15 underground stations and 10 surface stops.
2) Construction involves distinct phases including preliminary works, utility relocations, tunnel excavation, station construction, track installation, and testing.
3) Recent progress includes completing tunnel construction, ongoing station construction activities, and beginning excavation of station boxes in 2017. Upcoming milestones are excavating 1 million tons of material and advancing utility relocations and guideway installation.
Leaside - Laird Construction Liaison Committee Meeting - July 2017Crosstown TO
Construction updates were provided for the Leaside and Laird stations of the Crosstown LRT. For Leaside station in Q3 2017, support of excavation will continue in stages and water main investigations will expose portions of a main near Bayview Ave. Overnight line painting of crosswalks is planned for July. At Laird station, mining operations will continue at the main and secondary entrances in Q3 with dewatering and concrete pouring also underway. Sewer lining work may result in odours near maintenance holes on Eglinton Ave E between Sutherland Dr and Brentcliffe Rd.
Chaplin Station Open House - March 2017Crosstown TO
The document provides information about the construction of the Eglinton Crosstown LRT project in Toronto. It discusses the background and players involved in the project, details about what is being built including key features and design approaches. It also covers topics like safety, accessibility, environment and sustainability measures, and descriptions of the construction process and methods being used. Updates are provided on construction progress and milestones. Information is also given about community benefits initiatives and how people can stay updated on the project.
Science Centre Station Open House - June 2017Crosstown TO
The document provides information about the construction of the Eglinton Crosstown LRT project in Toronto. It discusses Metrolinx's regional transportation plan, the project players and their roles, details about the light rail transit line including its route and features, construction methods like cut-and-cover and mining, project timelines and milestones for 2017, and community benefits programs related to employment, procurement, and investment.
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Crosstown TO
Construction is underway on the Crosstown LRT project, including at Kennedy Station. Crews will use a cut-and-cover construction method at Kennedy Station, which will involve utility relocations, installing support of excavation including piles and shoring, and excavating the site. In 2017, crews will relocate utilities and roads, demolish the existing north entrance, and begin support of excavation work, which may cause noise, vibration and dust. The project will build 15 underground stations along a 19-kilometre LRT route to improve transit connections in Toronto.
Cedarvale & Forest Hill Stations Construction Liaison Committee Meeting - Sep...Crosstown TO
The document provides construction updates for the Cedarvale and Forest Hill stations on the Eglinton Crosstown LRT project. At Cedarvale Station, excavation of the east entrance is ongoing along with utility relocation works and shoring. Upcoming work includes the South Allen Road Diversion and backfill of a crossover. At Forest Hill Station, ongoing work includes piling at the station box, entrance areas, and utility relocation, with a focus on completing the roof slab over the coming months.
Central Open House (Chaplin Station to Leaside Station) - spring 2018Crosstown TO
Metrolinx is building the Eglinton Crosstown LRT, a 19km light rail line running east-west through Toronto. The project includes 25 stations, many of which are undergoing construction using cut-and-cover or mined methods. Over $30 billion is being invested in transit expansion across the Greater Toronto and Hamilton Area as part of Metrolinx's regional transportation plan. Community engagement efforts include informing residents about construction progress, traffic changes, and programs to support local businesses and provide employment opportunities.
Community Information Meeting of parkette design plan at Fairbank StationCrosstown TO
Metrolinx is building the Eglinton Crosstown LRT, a 19-kilometer light rail line running east-west through Toronto. Construction is underway on the Fairbank Station, with support of excavation and utility relocation currently taking place. Future plans for the station include exterior plazas and landscaping improvements to benefit the local community. Community engagement efforts have focused on employment, apprenticeships, and public art programs.
East Open House - East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station...Crosstown TO
Metrolinx was created in 2006 to improve transportation coordination across the Greater Toronto and Hamilton Area (GTHA). Metrolinx has invested over $30 billion in new transit infrastructure projects according to its Regional Transportation Plan, including new light rail, bus rapid transit, and GO Transit expansion projects. One such project is the Eglinton Crosstown LRT, which will include 25 underground and surface stations along a 19km route, connecting to other transit lines and improving transportation across the busy Eglinton corridor.
The document provides information about a public meeting to discuss plans for 6 new SmartTrack stations and 2 new GO stations in Toronto. It includes an overview of the proposed station concepts and the transit project assessment process that will evaluate environmental impacts. Schematic designs are presented for 5 of the stations - Finch-Kennedy, Lawrence-Kennedy, Gerrard-Carlaw, East Harbour, and Bloor-Lansdowne. Key considerations for station design like integration with other transit lines, accessibility, and community impacts are discussed. Feedback from the public meeting will help inform the planning and design of the new stations.
Kennedy Station and East At-Grade Section Open House - December 2017Crosstown TO
The document provides information about the Eglinton Crosstown LRT project being built by Metrolinx and Crosslinx Transit Solutions. It discusses plans to build a 19-kilometre light rail line along Eglinton Avenue in Toronto, including 15 underground stations and 10 surface stops. It outlines safety measures and design principles for the project. It also discusses community benefits programs and upcoming construction activities at various stations and surface stops along the route in 2017-2018.
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Crosstown TO
This document provides information about Metrolinx's Crosstown LRT project, including:
- A description of the key aspects being built, such as underground and surface stations, maintenance facility, and route.
- An emphasis on safety as the top priority during construction.
- Details about the project's design principles and focus on sustainability, environment, and community benefits.
- Expected construction milestones and activities in 2017-2018 for various sections, including tunnel fit out, stations, and elevated guideways.
- Plans to minimize impacts on local businesses and support the community during construction.
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Crosstown TO
The document provides information on Metrolinx's Draft 2041 Regional Transportation Plan and details about the Crosstown LRT project in Toronto. Key points include:
- Metrolinx is updating its Regional Transportation Plan and is seeking public input on the Draft 2041 Plan.
- The Crosstown LRT will be a 19-kilometer light rail line with 25 stations, running mostly underground in Toronto.
- Construction updates are provided for 2017-2018, including tunneling work, track installation, and station construction at sites like Mount Dennis.
- Community benefits of the project include employment opportunities, support for social enterprises and local businesses, and community improvements.
The document summarizes Metrolinx's regional transportation plan and the Eglinton Crosstown LRT project. Key points include:
- Metrolinx is investing over $30 billion in rapid transit infrastructure across the Greater Toronto and Hamilton Area, including expanding GO Transit service, building new light rail and bus rapid transit lines.
- The Eglinton Crosstown LRT will be a 19km light rail line with 25 stations, costing over $5.3 billion. Construction updates are provided for several stations.
- Safety, design excellence, environmental sustainability, and community benefits are priorities of the project.
This document provides a summary of infrastructure investments and construction updates in the city of Ottawa for Fall 2016. It discusses the O-Train Confederation Line LRT construction, OC Transpo fall service changes, and various road construction and renewal projects. Traffic impacts are expected to be high around the downtown core due to LRT station construction and other projects. Tips are provided to help residents plan trips and commute during the busy construction season.
The Eglinton Crosstown LRT project is now over 75% complete, with three stations largely finished and over 85% of track installed. Work continues on the project through 2020 and 2021, including installing remaining track and overhead wires, completing stations, and road restoration works. The constructor is committed to community benefits like hiring from disadvantaged groups and supporting local businesses. Safety measures are in place like masks, screening, and testing to allow construction to continue as an essential service during the COVID-19 pandemic.
OPDC revised draft Local Plan presentation - TransportAlexandra Dobson
The document summarizes the revised draft Local Plan for the Old Oak and Park Royal area, which focuses on transport policies and supporting studies. It includes 9 transport policies addressing roads, walking, cycling, parking, rail, buses, freight, construction, and transport assessments. Key transport projects are described such as the new Old Oak Common station integrated with HS2, Elizabeth line and other rail lines. Supporting studies are outlined covering topics like bus strategy, parking, and delivery of pedestrian and cycling infrastructure. Public consultation on the plan is open through September 2017.
Western Works CLC - January 17, 2023.pdfCrosstown TO
The document provides updates on construction progress for the Eglinton Crosstown LRT project. It summarizes work completed in December 2022 and ongoing work at Caledonia Station, Keelesdale Station, and Mount Dennis Station. It also discusses track installation in the rail corridor, testing of light rail vehicles at the Eglinton Maintenance and Storage Facility, and lane reductions planned for heat trace installation works. Construction and testing activities are expected to continue through early 2023 and into 2023.
The document provides updates on construction activities for the Eglinton Crosstown LRT. Work is ongoing at Caledonia, Keelesdale, and Mount Dennis stations, and in the rail corridor, and will continue through spring 2023. This includes finishing works, system testing, and commissioning of trains. Lane reductions will occur between Weston Rd and Black Creek Dr in March for heat trace installation works. LRVs are being tested on the mainline in preparation for passenger service.
The document provides updates on construction progress for the Eglinton Crosstown LRT project, including at Leaside and Laird stations. At Leaside Station, architectural finishes, mechanical and electrical works are underway with station box and entrance construction expected to be complete in spring 2023. At Laird Station, similar finishing works are ongoing with the main and secondary entrances projected to be finished in early 2023. Utility works and asphalt restoration requiring periodic lane closures on Eglinton Avenue are also outlined.
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project. It notes that work will continue through spring 2023 at Eglinton Station to finish architectural details, mechanical, electrical and testing. It also provides details on construction progress photos and updates for Mount Pleasant Station, including ongoing work on the station box and entrances through spring 2023. Traffic impacts are noted at both locations through late May 2023 for line painting and other works.
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
The document provides updates on construction progress for the Eglinton Crosstown LRT Chaplin Station and Avenue Station. For Chaplin Station, work is underway on the station entrances, station box, and Chaplin Parkette through Spring 2023. For Avenue Station, construction is ongoing on the station box, main and secondary entrances, and Eglinton Avenue streetscape through Summer 2023. Traffic configurations and lane closures are also outlined.
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project from Brentcliffe Road to O'Connor Drive. It notes that vehicle testing is ongoing from Brentcliffe to Kennedy, and that landscaping will continue through the summer. It also summarizes specific utility works, platform works, traffic restrictions and closures taking place between April and May 2023 at various locations along the route. Photos show examples of construction progress such as Presto machine installations and work at Aga Khan Park Station.
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxCrosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project from Pharmacy Station to Kennedy Station. It notes that vehicle testing and landscaping work will continue through spring 2023 between Brentcliffe and Kennedy stations. Between O'Connor and Ionview stops, traffic sign installation and line painting will take place through late spring. Sidewalk repairs are scheduled along Eglinton Ave East from mid-March 2023. Testing and commissioning activities are ongoing at Kennedy Station and will continue into early 2023. GO train platform service at Kennedy Station will shift east through 2023 with accessibility shuttle services provided.
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCrosstown TO
The document provides an update on construction activities for the Eglinton Crosstown LRT project from Pharmacy Station to Kennedy Station. It summarizes that testing and commissioning of light rail vehicles is ongoing between Brentcliffe Road and Kennedy Road through 2023. It also outlines ongoing construction and finishing work at multiple stations along the route including O'Connor, Pharmacy, Golden Mile, Birchmount, Ionview and Kennedy stations. Temporary traffic and pedestrian configurations are in place at 1995 Eglinton Avenue East and Kennedy Station during construction activities.
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
The document provides updates on construction progress for different sections of the Eglinton Crosstown LRT project. Section One details work between Brentcliffe Portal to Sunnybrook Park Stop including vehicle testing, noise barrier removal, landscaping and utility works. Section Two details work from Aga Khan Park & Museum Stop to O'Connor Stop including vehicle testing, station finishes, and upcoming watermain restoration works. Science Centre Station work includes finishing activities and ongoing traffic configuration. Photos show ongoing signage, electrical and landscaping work throughout the alignment.
Chaplin-Avenue CLC - March 1, 2023.pptxCrosstown TO
The document provides updates on construction progress for the Chaplin Station and Avenue Station of the Eglinton Crosstown LRT. For Chaplin Station, work is underway on the station entrances, station box, and Chaplin Parkette through Spring 2023, with periodic lane closures on Chaplin Cres. For Avenue Station, construction is ongoing on the station box, entrances, and Eglinton Avenue streetscape/cycle track between Avenue Rd and Duplex Ave, with the traffic configuration shifting and lane reductions expected by March 2, 2023. Periodic lane and sidewalk closures as well as pedestrian rerouting will occur.
Leaside-Laird CLC - March 13, 2023.pdfCrosstown TO
The document provides updates on construction progress for the Eglinton Crosstown LRT project. It summarizes work happening at Leaside Station, including finishing the station box, main entrance, and secondary entrance through spring 2023. It also summarizes work at Laird Station, including main and secondary entrance construction through early 2023. Utility and road work is occurring through spring 2023 at both stations.
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
The document provides updates on construction progress for different sections of the Eglinton Crosstown LRT project. Section One details work happening from Brentcliffe Portal to Sunnybrook Park Stop, including vehicle testing, noise barrier removal, landscaping, and overnight utility works. Section Two details work from Aga Khan Park & Museum Stop to O'Connor Stop, including vehicle testing, landscaping, station finishes, and upcoming watermain restoration works. Science Centre Station work includes finishing activities and ongoing traffic configuration. Photos show ongoing signage, electrical, and landscaping works.
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfCrosstown TO
The document provides updates on construction activities for the Eglinton Crosstown LRT project. It acknowledges that the project is taking place on Indigenous land and discusses the importance of reconciliation. It then details construction timelines and plans for the Eglinton and Mount Pleasant stations, including extended work hours, entrance construction, traffic shifts, and anticipated completion dates in spring 2023. Photos show progress on the station structures and entrances.
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
The document provides updates on construction progress at the Chaplin Station and Avenue Station sites of the Eglinton Crosstown LRT. At Chaplin Station, work is underway on the main, secondary, and tertiary entrances through December 2022, along with station box construction and road closures. At Avenue Station, station box construction and work on the main and secondary entrances is progressing through December 2022, along with Eglinton Avenue streetscape and cycle track construction between Eastbourne and Duplex Avenues. Construction photos depict ongoing work.
Chaplin-Avenue CLC - January 11 2023 (002).pptxCrosstown TO
The document provides updates on construction progress for the Chaplin Station and Avenue Station of the Eglinton Crosstown LRT. For Chaplin Station, construction of the main, secondary and tertiary entrances and Chaplin Parkette are underway through Spring 2023. Station box construction and intersection reinstatement at Chaplin Cres and Eglinton Ave are also progressing. For Avenue Station, station box construction, main and secondary entrance construction, and Eglinton Avenue streetscape work are underway through Spring 2023, with a traffic configuration change expected in early February 2023. Construction photos depict progress at station boxes, entrances and connections to local trails.
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
This is a meeting invite for the Brentcliffe-Victoria Park CLC (Construction Liaison Committee) Monthly Meeting, covering the Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan, Wynford, Sloane and O’ Connor Stops.
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfCrosstown TO
The document provides updates on construction progress for the Eglinton Crosstown LRT project. It discusses ongoing work at Eglinton Station including extended hours for station box construction and main entrance construction. It also discusses ongoing work at Mount Pleasant Station including station box construction and main and secondary entrance construction. Traffic configuration changes at Mount Pleasant are also noted as completed. Construction progress photos of station box work are included.
Leaside-Laird CLC - January 9, 2023.pdfCrosstown TO
The document provides updates on construction progress at the Eglinton Crosstown LRT Leaside and Laird stations. At Leaside Station, work is underway on the station box, main entrance, secondary entrance, and utility and road works, with sidewalk restoration planned for January 9-11, 2023. At Laird Station, work continues on the main entrance, secondary entrance, and station box, with sidewalk restoration and monitoring well decommissioning requiring periodic lane reductions into early-mid 2023. Photos show ongoing construction and finishing works at both stations.
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
Construction updates for the following locations/stops: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan Park & Museum, Wynford, Sloane and O'Connor.
AHMR is an interdisciplinary peer-reviewed online journal created to encourage and facilitate the study of all aspects (socio-economic, political, legislative and developmental) of Human Mobility in Africa. Through the publication of original research, policy discussions and evidence research papers AHMR provides a comprehensive forum devoted exclusively to the analysis of contemporaneous trends, migration patterns and some of the most important migration-related issues.
Food safety, prepare for the unexpected - So what can be done in order to be ready to address food safety, food Consumers, food producers and manufacturers, food transporters, food businesses, food retailers can ...
Jennifer Schaus and Associates hosts a complimentary webinar series on The FAR in 2024. Join the webinars on Wednesdays and Fridays at noon, eastern.
Recordings are on YouTube and the company website.
https://www.youtube.com/@jenniferschaus/videos
10. Safety First – Our #1 Priority
• Always have a site specific safety plan and site specific emergency plan.
• Ensure pre-work hazard assessments are complete and understood.
• Ensure job hazards analyses are complete and understood.
• Identify and report unsafe behaviour and coach each other to make improvements.
• Do everything possible to protect themselves, co-workers and members of the
public
• Stop work if the safety of themselves, co-workers and members of the public
cannot be assured
• Be prepared and equipped to work safely.
We train and direct staff to:
11. Construction of the
Eglinton Crosstown LRT Line
Background
• In September 2008, Metrolinx
launched a regional transportation
plan – a 25-year, $50 billion plan -- to
coordinate and integrate transportation
and transit in the Greater Toronto Area
• In 2010, City of Toronto approved the
project to build the Eglinton Crosstown
from Weston Road in the west to
Kennedy Station in the east.
• Following a competitive process,
Crosslinx Transit Solutions (CTS) was
awarded a contract in July 2015 to
design, build, finance, and maintain
the Eglinton Crosstown Light Rail
Transit (LRT).
Benefits of P3s:
• The Crosstown is being delivered using a public
private partnership model called Alternative
Financing and Procurement (AFP).
• It was procured as one design-build-finance-
maintain project to minimize integration risk –
historically, a factor for project cost overruns
under traditional models.
• Under the AFP model, CTS assumes most
project risks, including:
design, project management and sub-
contractor coordination
increases in construction material prices
and labour costs
schedule and project completion delays
maintenance and lifecycle replacement of
materials within the stations and stops,
rails, control systems, and vehicles
13. What are we building – a new modern LRT
• 15 underground stations and 10 surface stops
• A maintenance and storage facility
• A 19-kilometre route separated from regular traffic
• Communications system
• Links to 54 bus routes, three subway stations, GO Transit, and a new UP Express station
15. Design Approach: Design from City to Object
15
S i m p l i c i t y
I conog ra phy
Transparency
Ur b a n i t y
Simplicity and elegance of the design solution at all scales,
from the city to the object;
Iconography of the architectural elements to create a unique
and highly recognizable signature on Eglinton Avenue, from
the slanted portal celebrating kinetic movement, to the
profiled wing delineating shelters and waiting areas;
Transparency of the entrances and through the station to magnify
the presence of natural light, to enact as a way-finding strategy
and to uplift the passenger’s experience;
Urbanity of the signature layers from landscape to architecture,
to underline the genius loci and contextualize the stations and
stops within the civic scale of the avenue.
17. 17
Clarity and Simplicity of Architectural
Expression
Street Level – Contextual &
Inviting
An International Signature
for Toronto
Entrance – Bright & Secure
Concourse – Simple &
Pristine
Concourse – Transparent &
Open
Platform – Spacious &
Animated
18. Crosstown Design Approach
Features
• About half of the 19 km line is
tunneled
• Stations and stops are about 0.6 km
apart
• Features will include:
• time arrival information
• safe access for people walking
and biking to the station
• clear route maps, seating, bike
parking
Design Approach
Comply with nine design principles developed
by City of Toronto and Metrolinx.
• Provide a legacy for generations to come.
• Have natural lighting during the day and well-lit
entrances at night.
• Have safe, clean, intuitive wayfinding at
all the stations and stops.
• Put passengers first.
• Provide visible entrances, bicycle facilities and
sustainable practices to ensure all stations
comply with Toronto Green Standard Tier.
• Landscaped entrances, including planters with
trees and ornamental grasses.
• Public plazas and retail components at some
stations.
• Clean and minimalist space at platform level.
• Accessible to passengers with disabilities,
strollers, and bicycles.
19. Accessibility for All
Station and stops are designed to support ease of access and use by persons with
differing levels of mobility, sight, hearing, sensory and cognitive abilities. The project site
and facilities are designed to be universally accessible including satisfying the
requirements of Accessibility for Ontarians with Disabilities Act (AODA) and applicable
City of Toronto Guidelines, Ontario Building Code (OBC) and Canadian Standards
Association (CSA) Standards. Some of these features include:
• Barrier‐free path from the entrance level to the station platform level
• Tactile warning strips and tactile walking surface indicators
• Signage system with tactile indicators
• Passenger Assistance Intercom (PAI)
• Low floor Light Rail Vehicle (LRV) with designated wheelchair locations
• Nominal gap from platform edge to LRV entry
• Automated visual and audible stop announcements
• On-street and off-street paratransit passenger pick-up/drop-off
20. • The underground stations run
between Weston Road in the west to
Laird Street in the east.
• Construction began at Keelesdale
station, located at Keele Street /
Trethewey Drive and Eglinton Avenue
in March 2016.
• Installing support of excavation is the first step in
constructing an underground station.
• All underground stations will be brand
new, including the three LRT
interchange stations connecting to
other transit modes.
• Most of the underground stations will be
in construction by the end of 2016.
What to expect in 2016
– Start of Stations Construction
21. How we’re building: Cut-and-Cover Stations
Chaplin
Locations: Keelesdale (Keele), Caledonia, Fairbank (Dufferin), Forest Hill
(Bathurst), Chaplin, Mount Pleasant, Leaside (Bayview), Science Centre
23. • There are three
interchange stations.
• Interchange stations
will allow transit
riders to connect to
other transit modes,
such as TTC, GO
and the UP Express.
• The three
interchange stations
will be built with the
‘Cut and Cover’
method.
How we’re building – Interchange Stations
Subway Station Longitudinal Section
Locations: Cedarvale (Allen), Eglinton (Yonge), Kennedy
24. How we’re building Chaplin Station -
Construction Overview
Distinct phases of construction:
• Preparatory works
• Utility relocations
• Support of excavation (shoring)
• Roof slab construction
• Road restoration
• Deep excavation
• Underground station construction
• Track work and systems installation
• Station structure construction
• Traction power system
• Signalling system
• Testing and commissioning
25. How we’re building Chaplin Station –
Preparatory Works
Since fall 2015, CTS has been preparing the line for underground stations
and stops construction.
Preparatory activities:
• Pre-construction surveys and seismic testing
• Assess soil condition and measure water levels
• Locate and mark underground utilities
• Clearing/grubbing of shrubs/trees in the future station area
• Demolish existing buildings and infrastructure in the future station area
• Remove street furniture
(i.e. benches, bus shelters, planters, garbage bins)
26. • A modified version of the cut-and-cover method,
whereby following support of excavation, a
concrete roof slab is constructed and placed over
top of the excavated area, the roadway is restored
and work continues safely below ground
• The station roof slab is used to support utilities and
the roadway
• Benefits include reduction in road disruption
(compared to tradition method), increased utility
stability and improved safety and working
conditions
How we’re building Chaplin Station – Station
Construction
27. Reinstate Roadway
• A concrete roof slab will be
constructed over top of the
excavated area, utilities will be
buried, and the roadway will be
reinstated above the roof slab.
Excavation
• Once the roadway is reinstated,
crews will work safely beneath the
roadway to construct the station box,
build the platform and install rail
infrastructure.
Architectural & Building Work
• Construction of the station entrance
structures will begin in 2018.
How we’re building Chaplin Station – Station
Construction (cont’d)
34. Chaplin Station Unique Design Concepts
• Main station entrance is located at the northeast
corner of Chaplin Crescent and Eglinton Avenue
West
• Secondary station entrance is located at the
southwest corner
• Tertiary station entrance is located east of Chaplin
Crescent on Eglinton Avenue West, adjacent the
former Toronto Fire Hall
• The main and secondary station entrances provide
a gateway to the Chaplin Parkette and Kay
Gardiner Beltline Trail, respectfully
• 32 sheltered and unsheltered bike parking spots
located at the main and secondary station
entrances
35. Chaplin Station Tunnel Ventilation System
• Hosts the station’s Tunnel Ventilation System (TVS)
• Designed to extract and control smoke from tunnels and stations in the
event of a fire
• Controls excessive air velocities and air pressure transients
• Removes heat and controls air temperature during operations
• Supplies outdoor air ventilation and facilitates contaminant removal
• Chaplin Station TVS is comprised of station fans, electrical equipment,
tunnel ventilation control panels, supervisory control and data acquisition
(SCADA) interface, and Tunnel Ventilation Fire Command Post
• The tunnel ventilation grates are located at grade, 12 meters west of the
main station entrance
36. Chaplin Station Construction Lookahead
(2016 – 2017)
Fall 2016
• Continue installation of monitoring points
• Continue relocation of telecommunication (Bell) lines (6 weeks)
• Demolition of 641 Eglinton Avenue West (Toronto Fire Hall) to make way for the future tertiary station
entrance (8 weeks)
• Relocation and reconfiguration of traffic poles and signals throughout intersection to accommodate
construction staging (1 week)
• Start of support of excavation (shoring) of the main station entrance (8 weeks)
• Relocation of aerial hydro to temporary poles and underground duct bank (6 weeks)
• Relocation of a watermain on the north and south sides of Eglinton Avenue West (6 weeks)
• Replacement and relocation of a sanitary sewer on Eglinton Avenue West between Gilgorm Road and
Latimer Avenue (5 weeks)
December 2016
• Expected start of long-term shoring in the roadway, beginning on the north side of Eglinton Ave W (4
months)
37. Traffic and Pedestrian Changes
• To accommodate utilities relocation and support of excavation
(SOE) construction stages, temporary traffic changes, such as
road closures, lane reductions, turn restrictions, pedestrian
rerouting and bus stop relocations may be in effect
• Additionally, changes to existing traffic conditions, such as
relaxation of turn restrictions or additional restrictions, may be
enacted in development with local elected officials, traffic
engineers and the local community
38. Chaplin Station Construction Stages
Stage Activity Duration
Target Start
Date
1
Utilities
Relocation;
Shoring
8 months Fall 2016
2
Utilities
Relocation;
Shoring
2 months Spring 2017
3 Shoring 8 months Summer 2017
4 Shoring 2 months Fall 2017
39. Bell Utilities Relocation – Current Staging Plan
Began August 29 (7 weeks)
8 WEEK LANE
CLOSURE AND
PEDESTRIAN
REROUTING
44. Summary of Traffic Changes for Chaplin Station
Stage Traffic Changes
Associated
Activities
Approx.
Start Date
Approx.
Duration
1
• Close Gilgorm Rd at Eglinton Ave W
• Convert Gilgorm Rd to a two-way street
• Restrict access to Eglinton Ave W from southbound Latimer Ave
• Restrict left turns onto Latimer Avenue from eastbound Eglinton
Ave W
Utilities
Relocation and
shoring Fall 2016 35 weeks
2
Continue Stage 1 configuration, plus:
• Restrict north and southbound left turns
• Restrict westbound right turn
• Restore access to Eglinton Ave W from southbound Latimer Ave
Utilities
Relocation and
shoring
Spring
2017
Eight (8)
weeks
3
Continue Stage 2 configuration, plus:
• Restore westbound right turn
• Restrict northbound right turn
• Restrict eastbound left turn
Shoring
Summer
2017
23 weeks
4
Continue Stage 3 configuration, plus:
• Restore southbound left turn
Shoring Winter
2018
Four (4)
weeks
45. Summary of Pedestrian Changes for
Chaplin Station
Stage 1
• Relocate north and south crosswalks further north and south,
respectively
Stage 2
• Relocate east crosswalk further east
Stage 3
• Restrict north-south crossing on the west side of Chaplin Crescent
• Relocate east crosswalk further west
• Implement temporary signalized crosswalk and traffic signal east of
Russel Hill Rd and Eglinton Ave W
Stage 4
• Relocate west and east crosswalks further west and east,
respectively
Temporary
Crosswalk
46. Proposed Closure of Gilgorm Rd and
Mitigation
Why?
• Location of station box obstructs access to
Eglinton Ave W during construction stages 1
and 2
• To prevent unsafe traffic movements and
congestion during all stages
Mitigation
• Convert Gilgorm Rd from a one-way to a two-
way street to facilitate entry and egress for
local traffic
Duration
• Approximately 20 months, beginning fall 2016
47. Turn Restrictions and Proposed Mitigation
Why?
• Insufficient turn radius due to location of station box
• To prevent traffic congestion during construction stages
1 through 4
Mitigation
• Temporarily relax peak hour turn restrictions on nearby
local streets to facilitate alternative route access to east
and westbound Eglinton Ave W, including Latimer Ave,
Castlewood Ave, Heddington Ave and Sheilds Ave at
Roselawn Ave
Duration
• For approximately 20 months
RELAX PEAK
HOUR TURN
RESTRICTIONS
(7:00 – 9:00 AM)
48. Advanced Signage
• Advanced signage will be placed
along Eglinton Ave W and cross
streets to inform motorists and
pedestrians of traffic changes at the
intersection
• At Chaplin Station, advanced
signage will be placed as far north
as Spadina Rd, as far south as
Russel Hill Rd, as far east as
Heddington Ave and as far west as
Spadina Rd
49. Bus Stop Relocations
Five (5) TTC bus stops at the four corners of Eglinton Avenue West and Chaplin Crescent will
be relocated throughout various stages of utilities relocation and shoring.
• The northwest stop will be relocated approximately 20 m to the north
• The northeast stop at Chaplin Crescent will be relocated approximately 72 m to the north
• The northeast stop at Gilgorm Road will be relocated approximately 140 m to the east
• The southwest stop will be relocated approximately 40 m to the south
• The southeast stop will be relocated approximately 120 m to the east
The stops service the following TTC bus routes:
• #32/332 Eglinton Avenue West – West
• #32/332 Eglinton Avenue West – East
• #33 Forest Hill – South
• #14 Glencairn – East
Please look for signage informing passengers of the new temporary stop locations.
50. TTC Bus Stop Relocation Map
Relocate 20m
north
Relocate 72m
north
Relocate 140m
east
Relocate 120m
east
Relocate 40m
south
51. TTC Bus Stop Relocation Map
• To accommodate construction staging
at Chaplin Station, TTC bus route #33
now travels in reverse direction, from
north of Eglinton Ave W, Chaplin
Cres, Roselawn Ave and Bathurst St
• Beginning in October 2016, a detour
along Mayfair Ave to Shallmar Blvd, is
proposed for TTC Bus Route #33 to
accommodate construction staging at
Forest Hill Station (at Bathurst St)
• The duration of the proposed detour
is approximately 15 months
52. Experience Eglinton
Advertising and marketing initiatives, ranging
from subway and local newspapers advertisements,
to postcards, coupon booklets and flyers all focused
on encouraging residents in the neighbourhood
to shop locally.
Support for Businesses – Shop Local
53. Community Benefits
Commit to Social Procurement and Local Investment
to maximize business opportunities along the project corridor.
Visit CTS’ website www.crosslinxtransit.ca for updated postings.
The Eglinton Crosstown LRT is the first time a Community Benefits Framework
has been included as part of a major infrastructure project in Ontario.
Partner with Local Workforce Agencies
to recruit candidates from the project corridor and from
historically disadvantaged communities.
Work with Subcontractors
to maximize opportunities for apprentices.
Laird Station will be an underground station located at the intersection of Laird Drive and Eglinton Avenue East. The station will also be a turnback station and will have special trackwork for LRT operations.
A turnback station allows trains to change directions. The special trackwork allows a train to be stored between the tracks. For example, a disabled train could be stored there so it does not disrupt service.
The main, fully accessible entrance will be located at the southwest corner of Eglinton Avenue and Laird Drive. This entrance will also include a station plaza and retail spaces at street level. The secondary entrance will be located south of Eglinton Avenue East, just east of Laird Drive.
There will be on-street connections to TTC buses, and 60 outdoor bicycle parking spaces.
Laird Station will be an underground station located at the intersection of Laird Drive and Eglinton Avenue East. The station will also be a turnback station and will have special trackwork for LRT operations.
A turnback station allows trains to change directions. The special trackwork allows a train to be stored between the tracks. For example, a disabled train could be stored there so it does not disrupt service.
The main, fully accessible entrance will be located at the southwest corner of Eglinton Avenue and Laird Drive. This entrance will also include a station plaza and retail spaces at street level. The secondary entrance will be located south of Eglinton Avenue East, just east of Laird Drive.
There will be on-street connections to TTC buses, and 60 outdoor bicycle parking spaces.
June 1, 2016
Utilities relocation
Removal of one hydro pole on south west corner
Relocation of light poles along Laird Drive and on the south side of Eglinton Avenue East
Two long-term one
lane closures anticipated, one at the main shaft and another
at the secondary shaft. Four sidewalk closures are
anticipated; all other sidewalks will be maintained along with
business accesses. One bus stop relocations as per Stage 1
will continue to be maintained.