CASE HISTORY
DOHA RED LINE NORTH
-
CONTROL IN EXECUTION OF SYSTEM PERFORMANCE OF
CONNECTION AND GASKET
Emissione Data Approvazione Progetto Rev.
S. LUPI 27/10/2014 G. BOMBEN DOHA RED LINE NORTH 1
CASE HISTORY
INTRODUCTION
Fama Spa is an Italian company operating since 1988 in design, certification,
manufacture of products for precast lining of tunnels.
Fama Spa is specialized in the development of sealing systems and a wide
range of accessories for the connection, lifting and anchoring systems for
the construction of tunnels with TBM.
For the excavation of the Red Line North di DOHA, FAMA SpA provided
gaskets and connection systems.
To complete a strategic path that began with the design and continued with
the certification through laboratory tests, with a campaign of
measurements, it was possible to document the performance of these
products in exercise.
CASE HISTORY
DOHA METRO RED LINE NORTH
DESIGN OF THE LINING
- UNIVERSAL RING 6+1
- KEY 1/3 OTHER SEGMENT
- EX. DIAMETER 6.770 mm
- IN. DIAMETER 6.170 mm
- THICKNESS OF CONCRETE 300 mm
- LENGTH OF CONCRETE 1.500 mm
- ANCHORED GASKET 26 x 17 mm
WITH HIDROPHYLIC STRIP
- 19 CONNECTORS FOR RING
(3 FOR EACH SEGMENT , 1 FOR THE KEY)
- GUIDE BAR AND BOLT ON THE RADIAL
JOINT
CASE HISTORY
EPDM SEALING GASKET
- UG027A
- ANCHORED GASKET 26 x 17 mm WITH
HIDROPHYLIC STRIP
- PRESSURE REQUIRED TO CONTRACT
 10 bar
 GAP 5 mm
 OFFSET 10 mm
CASE HISTORY
CONNECTION SYSTEM
- SMARTBLOCK 90-160/300-60
- PULL OUT 90 KN
- SHEAR STRENGTH 160 KN
- LENGTH 300 mm
- DIAMETER OF CENTERING 60 mm
CASE HISTORY
1. We want to calculate the current state of misalignment and separation of the joints between the
segments in the gallery;
2. The relief is performed with the use of two measurement gauges: one for the depth, with which
recalculate the offsets and one for the width of the slots for the recalculation of the gap;
3. The joints are first classified according to the orientation angle to the progress of the excavation;
4. Usually the relief is performed on a continuous succession of five joints, reached by the operator
that runs through the tunnel by foot. In case of severe anomalies the relief can be conducted on the
entire ring with the aid of suitable lifting equipment. The measuring block 5 of joints may, at the
operator's discretion, be repeated several times;
5. The sequence of measurements, if necessary, can be performed on the right side and on the left side
of the tunnel with reference to the direction of advance of the excavation;
6. May be conducted in the presence of detections punctual infiltration of water, in order to evaluate if
this is generated by an excessive misalignment, or spreading of the coupling or, finally, from other
causes;
7. If necessary measurements can be performed on the blocks, facing the opposite of progress to
compare with those initial misalignment stabilized along the tunnel.
PROCEDURE FOR DETECTION GAP AND OFFSET BETWEEN
THE JOINTS IN CONCRETE INTO THE TUNNEL
CASE HISTORY
PROCEDURE FOR DETECTION GAP AND OFFSET BETWEEN THE
JOINTS IN CONCRETE INTO THE TUNNEL
The measurements of gap and offset are performed at approximately 20
mm from the T joint, where the deviations from nominal are maximums.
MEASUREMENTS
OF GAP
MEASUREMENTS
OF GAP
CASE HISTORY
PROCEDURE FOR DETECTION GAP AND OFFSET BETWEEN
THE JOINTS IN CONCRETE
In the diagrams below are identified types of angles between segments of a
same ring adjacent each other refer to the direction of excavation.
CASE HISTORY
PRESENTATION OF RESULTS
MEASURES OF GAP IN THE CIRCUMFERENTIAL JOINTS
CASE HISTORY
PRESENTATION OF RESULTS
MEASURES OF GAP IN THE LONGITUDINAL JOINTS
CASE HISTORY
PRESENTATION OF RESULTS
MEASURES OF OFFSET IN THE CIRCUMFERENTIAL JOINTS
CASE HISTORY
PRESENTATION OF RESULTS
MEASURES OF OFFSET IN THE LONGITUDINAL JOINTS
CASE HISTORY
PRESENTATION OF RESULTS
PICTURES OF THE TUNNEL
CASE HISTORY
ANALYSIS OF THE RESULTS
ASSESSMENT OF THE EFFICIENCY OF THE CONNECTION SYSTEM
There have been 294 measurements of gap and offset.
The average weigth gain of the gap is 0.4 mm, the offset of 1.4 mm.
The requirements of the specifications of the Doha Metro Red Line North provide
a mounting tolerance of 5 mm on the opening of the joint (gap) and 10 mm on
the misalignment of the joint (offset). The connection system SmartBlock
allowed a mounting error is much lower than expected.
The connection system SmartBlock has minimized the effect of the divergence of
the longitudinal and circumferential joints generated by the thrust of the gasket.
The performance of the pull-out and shear of the SmartBlock are suited to the
conditions of employment, ensuring the correct dimensioning of the system.
CASE HISTORY
ANALYSIS OF THE RESULTS
ASSESSMENT OF THE EFFICIENCY OF THE SEALING GASKET
The gallery of the DOHA METRO RED LINE NORTH is dry.
The gasket sealing UG027A has been tested at the University Tor Vergata for
the hydraulic performance requirements in the specifications of the project
Doha Metro Red Line North.
The gasket UG022A requires a load of 45 KN/m for its complete compression
facilitating, in fact, the permanence of the closed joint.
The geometry of UG022A well balanced between width and height and
angles conformed to the geometry of the concrete allow, during assembly of
the ring, to remain in its seat.

More Related Content

Viewers also liked

Fr case history doha linea red line north - misura gap ed offset
Fr case history   doha linea red line north - misura gap ed offsetFr case history   doha linea red line north - misura gap ed offset
Fr case history doha linea red line north - misura gap ed offset
stefanolupifamaspa
 
Case history doha linea red line north - misura gap ed offset rev 1
Case history   doha linea red line north - misura gap ed offset rev 1Case history   doha linea red line north - misura gap ed offset rev 1
Case history doha linea red line north - misura gap ed offset rev 1
stefanolupifamaspa
 
Case history milano linea m4 tratta expo rev.1
Case history   milano linea m4 tratta expo rev.1Case history   milano linea m4 tratta expo rev.1
Case history milano linea m4 tratta expo rev.1
stefanolupifamaspa
 
Case history doha linie red line north - ted. rev 1
Case history   doha linie red line north - ted. rev 1Case history   doha linie red line north - ted. rev 1
Case history doha linie red line north - ted. rev 1
stefanolupifamaspa
 
Presentazione guarnizione ancorata UG027A
Presentazione guarnizione ancorata UG027APresentazione guarnizione ancorata UG027A
Presentazione guarnizione ancorata UG027A
stefanolupifamaspa
 
Guarnizione ancorata ug027 a def_fr
Guarnizione ancorata ug027 a def_frGuarnizione ancorata ug027 a def_fr
Guarnizione ancorata ug027 a def_fr
stefanolupifamaspa
 
Anchored rubber gasket UG027A presentation
Anchored rubber gasket UG027A presentationAnchored rubber gasket UG027A presentation
Anchored rubber gasket UG027A presentation
stefanolupifamaspa
 

Viewers also liked (7)

Fr case history doha linea red line north - misura gap ed offset
Fr case history   doha linea red line north - misura gap ed offsetFr case history   doha linea red line north - misura gap ed offset
Fr case history doha linea red line north - misura gap ed offset
 
Case history doha linea red line north - misura gap ed offset rev 1
Case history   doha linea red line north - misura gap ed offset rev 1Case history   doha linea red line north - misura gap ed offset rev 1
Case history doha linea red line north - misura gap ed offset rev 1
 
Case history milano linea m4 tratta expo rev.1
Case history   milano linea m4 tratta expo rev.1Case history   milano linea m4 tratta expo rev.1
Case history milano linea m4 tratta expo rev.1
 
Case history doha linie red line north - ted. rev 1
Case history   doha linie red line north - ted. rev 1Case history   doha linie red line north - ted. rev 1
Case history doha linie red line north - ted. rev 1
 
Presentazione guarnizione ancorata UG027A
Presentazione guarnizione ancorata UG027APresentazione guarnizione ancorata UG027A
Presentazione guarnizione ancorata UG027A
 
Guarnizione ancorata ug027 a def_fr
Guarnizione ancorata ug027 a def_frGuarnizione ancorata ug027 a def_fr
Guarnizione ancorata ug027 a def_fr
 
Anchored rubber gasket UG027A presentation
Anchored rubber gasket UG027A presentationAnchored rubber gasket UG027A presentation
Anchored rubber gasket UG027A presentation
 

Similar to Case history doha linea red line north en

Case history doha linea red line north en
Case history   doha linea red line north enCase history   doha linea red line north en
Case history doha linea red line north en
stefanolupifamaspa
 
A model support plan for underground coal mines , under regulation 123 of the...
A model support plan for underground coal mines , under regulation 123 of the...A model support plan for underground coal mines , under regulation 123 of the...
A model support plan for underground coal mines , under regulation 123 of the...
nasina balasubrahmayam
 
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
IRJET Journal
 
Pipeline Construct.pptx
Pipeline Construct.pptxPipeline Construct.pptx
Pipeline Construct.pptx
ssuserfc98db
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
Loay Ghazaleh MBA, BSc Civil Eng.
 
ADITYA IS-4984.pptx
ADITYA IS-4984.pptxADITYA IS-4984.pptx
11.01.04 Trench Drains
11.01.04    Trench  Drains11.01.04    Trench  Drains
11.01.04 Trench Drains
TheJoyceAgencyInc
 
SPC HDPE BROCHURE NEW
SPC HDPE BROCHURE NEWSPC HDPE BROCHURE NEW
SPC HDPE BROCHURE NEW
Lia Collatz
 
Mill & Kiln Gear Asset Management
Mill & Kiln Gear Asset ManagementMill & Kiln Gear Asset Management
Mill & Kiln Gear Asset Management
Global Physical Asset Management
 
Boiler Operation and Maintenance Experiences
Boiler Operation and Maintenance ExperiencesBoiler Operation and Maintenance Experiences
Boiler Operation and Maintenance Experiences
National Productivity Council, Hyderabad, India
 
Analysis of 8 path meter diagnostics
Analysis of 8 path meter diagnosticsAnalysis of 8 path meter diagnostics
Analysis of 8 path meter diagnostics
Gregor Brown
 
A Complete Guide on Directional Boring
A Complete Guide on Directional BoringA Complete Guide on Directional Boring
A Complete Guide on Directional Boring
We-Bore-It
 
Hydraulic catalogue
Hydraulic catalogueHydraulic catalogue
Hydraulic catalogue
Ramesh Chalise
 
Ptc magmeter manual
Ptc magmeter manualPtc magmeter manual
Ptc magmeter manual
PTRANSANDCONTROLS
 
Effect of height of triangular siil on the performance of stilling basin model
Effect of height of triangular siil on the performance of stilling basin modelEffect of height of triangular siil on the performance of stilling basin model
Effect of height of triangular siil on the performance of stilling basin model
eSAT Publishing House
 
Fire Safety (Common Design Issues) .pptx
Fire Safety (Common Design Issues) .pptxFire Safety (Common Design Issues) .pptx
Fire Safety (Common Design Issues) .pptx
Rafat30
 
Flexible Ducts
Flexible DuctsFlexible Ducts
Flexible Ducts
Mostafa Al Wakeel
 
Design and Fabrication of an In-Pipe Inspection Robot
Design and Fabrication of an In-Pipe Inspection RobotDesign and Fabrication of an In-Pipe Inspection Robot
Design and Fabrication of an In-Pipe Inspection Robot
paperpublications3
 
804 query-short-spools-support
804 query-short-spools-support804 query-short-spools-support
804 query-short-spools-support
Alaa Altaie
 
An Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAn Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara Sea
Ali Osman Öncel
 

Similar to Case history doha linea red line north en (20)

Case history doha linea red line north en
Case history   doha linea red line north enCase history   doha linea red line north en
Case history doha linea red line north en
 
A model support plan for underground coal mines , under regulation 123 of the...
A model support plan for underground coal mines , under regulation 123 of the...A model support plan for underground coal mines , under regulation 123 of the...
A model support plan for underground coal mines , under regulation 123 of the...
 
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
 
Pipeline Construct.pptx
Pipeline Construct.pptxPipeline Construct.pptx
Pipeline Construct.pptx
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
 
ADITYA IS-4984.pptx
ADITYA IS-4984.pptxADITYA IS-4984.pptx
ADITYA IS-4984.pptx
 
11.01.04 Trench Drains
11.01.04    Trench  Drains11.01.04    Trench  Drains
11.01.04 Trench Drains
 
SPC HDPE BROCHURE NEW
SPC HDPE BROCHURE NEWSPC HDPE BROCHURE NEW
SPC HDPE BROCHURE NEW
 
Mill & Kiln Gear Asset Management
Mill & Kiln Gear Asset ManagementMill & Kiln Gear Asset Management
Mill & Kiln Gear Asset Management
 
Boiler Operation and Maintenance Experiences
Boiler Operation and Maintenance ExperiencesBoiler Operation and Maintenance Experiences
Boiler Operation and Maintenance Experiences
 
Analysis of 8 path meter diagnostics
Analysis of 8 path meter diagnosticsAnalysis of 8 path meter diagnostics
Analysis of 8 path meter diagnostics
 
A Complete Guide on Directional Boring
A Complete Guide on Directional BoringA Complete Guide on Directional Boring
A Complete Guide on Directional Boring
 
Hydraulic catalogue
Hydraulic catalogueHydraulic catalogue
Hydraulic catalogue
 
Ptc magmeter manual
Ptc magmeter manualPtc magmeter manual
Ptc magmeter manual
 
Effect of height of triangular siil on the performance of stilling basin model
Effect of height of triangular siil on the performance of stilling basin modelEffect of height of triangular siil on the performance of stilling basin model
Effect of height of triangular siil on the performance of stilling basin model
 
Fire Safety (Common Design Issues) .pptx
Fire Safety (Common Design Issues) .pptxFire Safety (Common Design Issues) .pptx
Fire Safety (Common Design Issues) .pptx
 
Flexible Ducts
Flexible DuctsFlexible Ducts
Flexible Ducts
 
Design and Fabrication of an In-Pipe Inspection Robot
Design and Fabrication of an In-Pipe Inspection RobotDesign and Fabrication of an In-Pipe Inspection Robot
Design and Fabrication of an In-Pipe Inspection Robot
 
804 query-short-spools-support
804 query-short-spools-support804 query-short-spools-support
804 query-short-spools-support
 
An Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAn Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara Sea
 

More from stefanolupifamaspa

Case history doha linea red line north en
Case history   doha linea red line north enCase history   doha linea red line north en
Case history doha linea red line north en
stefanolupifamaspa
 
Anchored rubber gasket UG027A english
Anchored rubber gasket UG027A englishAnchored rubber gasket UG027A english
Anchored rubber gasket UG027A english
stefanolupifamaspa
 
Fama presentazione aziendale slim en
Fama presentazione aziendale slim enFama presentazione aziendale slim en
Fama presentazione aziendale slim en
stefanolupifamaspa
 
Guarnizione ancorata UG027A francese
Guarnizione ancorata UG027A franceseGuarnizione ancorata UG027A francese
Guarnizione ancorata UG027A francese
stefanolupifamaspa
 
Fama presentazione aziendale slim fr
Fama presentazione aziendale slim frFama presentazione aziendale slim fr
Fama presentazione aziendale slim fr
stefanolupifamaspa
 
Verankerte Dichtung UG027A
Verankerte Dichtung UG027A Verankerte Dichtung UG027A
Verankerte Dichtung UG027A
stefanolupifamaspa
 
Case history mailand linie m4 strecke expo
Case history   mailand linie m4 strecke expoCase history   mailand linie m4 strecke expo
Case history mailand linie m4 strecke expo
stefanolupifamaspa
 
Fama presentazione aziendale slim ted
Fama presentazione aziendale slim tedFama presentazione aziendale slim ted
Fama presentazione aziendale slim ted
stefanolupifamaspa
 
Fama presentazione aziendale slim en
Fama presentazione aziendale slim enFama presentazione aziendale slim en
Fama presentazione aziendale slim en
stefanolupifamaspa
 
Fama presentazione aziendale slim
Fama presentazione aziendale slim Fama presentazione aziendale slim
Fama presentazione aziendale slim
stefanolupifamaspa
 

More from stefanolupifamaspa (10)

Case history doha linea red line north en
Case history   doha linea red line north enCase history   doha linea red line north en
Case history doha linea red line north en
 
Anchored rubber gasket UG027A english
Anchored rubber gasket UG027A englishAnchored rubber gasket UG027A english
Anchored rubber gasket UG027A english
 
Fama presentazione aziendale slim en
Fama presentazione aziendale slim enFama presentazione aziendale slim en
Fama presentazione aziendale slim en
 
Guarnizione ancorata UG027A francese
Guarnizione ancorata UG027A franceseGuarnizione ancorata UG027A francese
Guarnizione ancorata UG027A francese
 
Fama presentazione aziendale slim fr
Fama presentazione aziendale slim frFama presentazione aziendale slim fr
Fama presentazione aziendale slim fr
 
Verankerte Dichtung UG027A
Verankerte Dichtung UG027A Verankerte Dichtung UG027A
Verankerte Dichtung UG027A
 
Case history mailand linie m4 strecke expo
Case history   mailand linie m4 strecke expoCase history   mailand linie m4 strecke expo
Case history mailand linie m4 strecke expo
 
Fama presentazione aziendale slim ted
Fama presentazione aziendale slim tedFama presentazione aziendale slim ted
Fama presentazione aziendale slim ted
 
Fama presentazione aziendale slim en
Fama presentazione aziendale slim enFama presentazione aziendale slim en
Fama presentazione aziendale slim en
 
Fama presentazione aziendale slim
Fama presentazione aziendale slim Fama presentazione aziendale slim
Fama presentazione aziendale slim
 

Recently uploaded

Kinetic studies on malachite green dye adsorption from aqueous solutions by A...
Kinetic studies on malachite green dye adsorption from aqueous solutions by A...Kinetic studies on malachite green dye adsorption from aqueous solutions by A...
Kinetic studies on malachite green dye adsorption from aqueous solutions by A...
Open Access Research Paper
 
Global Climate Change and global warming
Global Climate Change and global warmingGlobal Climate Change and global warming
Global Climate Change and global warming
ballkicker20
 
Overview of the Global Peatlands Assessment
Overview of the Global Peatlands AssessmentOverview of the Global Peatlands Assessment
Overview of the Global Peatlands Assessment
Global Landscapes Forum (GLF)
 
Enhanced action and stakeholder engagement for sustainable peatland management
Enhanced action and stakeholder engagement for sustainable peatland managementEnhanced action and stakeholder engagement for sustainable peatland management
Enhanced action and stakeholder engagement for sustainable peatland management
Global Landscapes Forum (GLF)
 
Improving the Management of Peatlands and the Capacities of Stakeholders in I...
Improving the Management of Peatlands and the Capacities of Stakeholders in I...Improving the Management of Peatlands and the Capacities of Stakeholders in I...
Improving the Management of Peatlands and the Capacities of Stakeholders in I...
Global Landscapes Forum (GLF)
 
Microbial characterisation and identification, and potability of River Kuywa ...
Microbial characterisation and identification, and potability of River Kuywa ...Microbial characterisation and identification, and potability of River Kuywa ...
Microbial characterisation and identification, and potability of River Kuywa ...
Open Access Research Paper
 
Recycling and Disposal on SWM Raymond Einyu pptx
Recycling and Disposal on SWM Raymond Einyu pptxRecycling and Disposal on SWM Raymond Einyu pptx
Recycling and Disposal on SWM Raymond Einyu pptx
RayLetai1
 
原版制作(Newcastle毕业证书)纽卡斯尔大学毕业证在读证明一模一样
原版制作(Newcastle毕业证书)纽卡斯尔大学毕业证在读证明一模一样原版制作(Newcastle毕业证书)纽卡斯尔大学毕业证在读证明一模一样
原版制作(Newcastle毕业证书)纽卡斯尔大学毕业证在读证明一模一样
p2npnqp
 
Climate Change All over the World .pptx
Climate Change All over the World  .pptxClimate Change All over the World  .pptx
Climate Change All over the World .pptx
sairaanwer024
 
ENVIRONMENT~ Renewable Energy Sources and their future prospects.
ENVIRONMENT~ Renewable Energy Sources and their future prospects.ENVIRONMENT~ Renewable Energy Sources and their future prospects.
ENVIRONMENT~ Renewable Energy Sources and their future prospects.
tiwarimanvi3129
 
Promoting Multilateral Cooperation for Sustainable Peatland management
Promoting Multilateral Cooperation for Sustainable Peatland managementPromoting Multilateral Cooperation for Sustainable Peatland management
Promoting Multilateral Cooperation for Sustainable Peatland management
Global Landscapes Forum (GLF)
 
Improving the viability of probiotics by encapsulation methods for developmen...
Improving the viability of probiotics by encapsulation methods for developmen...Improving the viability of probiotics by encapsulation methods for developmen...
Improving the viability of probiotics by encapsulation methods for developmen...
Open Access Research Paper
 
world-environment-day-2024-240601103559-14f4c0b4.pptx
world-environment-day-2024-240601103559-14f4c0b4.pptxworld-environment-day-2024-240601103559-14f4c0b4.pptx
world-environment-day-2024-240601103559-14f4c0b4.pptx
mfasna35
 
Evolving Lifecycles with High Resolution Site Characterization (HRSC) and 3-D...
Evolving Lifecycles with High Resolution Site Characterization (HRSC) and 3-D...Evolving Lifecycles with High Resolution Site Characterization (HRSC) and 3-D...
Evolving Lifecycles with High Resolution Site Characterization (HRSC) and 3-D...
Joshua Orris
 
Global Peatlands Map and Hotspot Explanation Atlas
Global Peatlands Map and Hotspot Explanation AtlasGlobal Peatlands Map and Hotspot Explanation Atlas
Global Peatlands Map and Hotspot Explanation Atlas
Global Landscapes Forum (GLF)
 
Wildlife-AnIntroduction.pdf so that you know more about our environment
Wildlife-AnIntroduction.pdf so that you know more about our environmentWildlife-AnIntroduction.pdf so that you know more about our environment
Wildlife-AnIntroduction.pdf so that you know more about our environment
amishajha2407
 
Epcon is One of the World's leading Manufacturing Companies.
Epcon is One of the World's leading Manufacturing Companies.Epcon is One of the World's leading Manufacturing Companies.
Epcon is One of the World's leading Manufacturing Companies.
EpconLP
 
Peatlands of Latin America and the Caribbean
Peatlands of Latin America and the CaribbeanPeatlands of Latin America and the Caribbean
Peatlands of Latin America and the Caribbean
Global Landscapes Forum (GLF)
 
在线办理(lboro毕业证书)拉夫堡大学毕业证学历证书一模一样
在线办理(lboro毕业证书)拉夫堡大学毕业证学历证书一模一样在线办理(lboro毕业证书)拉夫堡大学毕业证学历证书一模一样
在线办理(lboro毕业证书)拉夫堡大学毕业证学历证书一模一样
pjq9n1lk
 
Optimizing Post Remediation Groundwater Performance with Enhanced Microbiolog...
Optimizing Post Remediation Groundwater Performance with Enhanced Microbiolog...Optimizing Post Remediation Groundwater Performance with Enhanced Microbiolog...
Optimizing Post Remediation Groundwater Performance with Enhanced Microbiolog...
Joshua Orris
 

Recently uploaded (20)

Kinetic studies on malachite green dye adsorption from aqueous solutions by A...
Kinetic studies on malachite green dye adsorption from aqueous solutions by A...Kinetic studies on malachite green dye adsorption from aqueous solutions by A...
Kinetic studies on malachite green dye adsorption from aqueous solutions by A...
 
Global Climate Change and global warming
Global Climate Change and global warmingGlobal Climate Change and global warming
Global Climate Change and global warming
 
Overview of the Global Peatlands Assessment
Overview of the Global Peatlands AssessmentOverview of the Global Peatlands Assessment
Overview of the Global Peatlands Assessment
 
Enhanced action and stakeholder engagement for sustainable peatland management
Enhanced action and stakeholder engagement for sustainable peatland managementEnhanced action and stakeholder engagement for sustainable peatland management
Enhanced action and stakeholder engagement for sustainable peatland management
 
Improving the Management of Peatlands and the Capacities of Stakeholders in I...
Improving the Management of Peatlands and the Capacities of Stakeholders in I...Improving the Management of Peatlands and the Capacities of Stakeholders in I...
Improving the Management of Peatlands and the Capacities of Stakeholders in I...
 
Microbial characterisation and identification, and potability of River Kuywa ...
Microbial characterisation and identification, and potability of River Kuywa ...Microbial characterisation and identification, and potability of River Kuywa ...
Microbial characterisation and identification, and potability of River Kuywa ...
 
Recycling and Disposal on SWM Raymond Einyu pptx
Recycling and Disposal on SWM Raymond Einyu pptxRecycling and Disposal on SWM Raymond Einyu pptx
Recycling and Disposal on SWM Raymond Einyu pptx
 
原版制作(Newcastle毕业证书)纽卡斯尔大学毕业证在读证明一模一样
原版制作(Newcastle毕业证书)纽卡斯尔大学毕业证在读证明一模一样原版制作(Newcastle毕业证书)纽卡斯尔大学毕业证在读证明一模一样
原版制作(Newcastle毕业证书)纽卡斯尔大学毕业证在读证明一模一样
 
Climate Change All over the World .pptx
Climate Change All over the World  .pptxClimate Change All over the World  .pptx
Climate Change All over the World .pptx
 
ENVIRONMENT~ Renewable Energy Sources and their future prospects.
ENVIRONMENT~ Renewable Energy Sources and their future prospects.ENVIRONMENT~ Renewable Energy Sources and their future prospects.
ENVIRONMENT~ Renewable Energy Sources and their future prospects.
 
Promoting Multilateral Cooperation for Sustainable Peatland management
Promoting Multilateral Cooperation for Sustainable Peatland managementPromoting Multilateral Cooperation for Sustainable Peatland management
Promoting Multilateral Cooperation for Sustainable Peatland management
 
Improving the viability of probiotics by encapsulation methods for developmen...
Improving the viability of probiotics by encapsulation methods for developmen...Improving the viability of probiotics by encapsulation methods for developmen...
Improving the viability of probiotics by encapsulation methods for developmen...
 
world-environment-day-2024-240601103559-14f4c0b4.pptx
world-environment-day-2024-240601103559-14f4c0b4.pptxworld-environment-day-2024-240601103559-14f4c0b4.pptx
world-environment-day-2024-240601103559-14f4c0b4.pptx
 
Evolving Lifecycles with High Resolution Site Characterization (HRSC) and 3-D...
Evolving Lifecycles with High Resolution Site Characterization (HRSC) and 3-D...Evolving Lifecycles with High Resolution Site Characterization (HRSC) and 3-D...
Evolving Lifecycles with High Resolution Site Characterization (HRSC) and 3-D...
 
Global Peatlands Map and Hotspot Explanation Atlas
Global Peatlands Map and Hotspot Explanation AtlasGlobal Peatlands Map and Hotspot Explanation Atlas
Global Peatlands Map and Hotspot Explanation Atlas
 
Wildlife-AnIntroduction.pdf so that you know more about our environment
Wildlife-AnIntroduction.pdf so that you know more about our environmentWildlife-AnIntroduction.pdf so that you know more about our environment
Wildlife-AnIntroduction.pdf so that you know more about our environment
 
Epcon is One of the World's leading Manufacturing Companies.
Epcon is One of the World's leading Manufacturing Companies.Epcon is One of the World's leading Manufacturing Companies.
Epcon is One of the World's leading Manufacturing Companies.
 
Peatlands of Latin America and the Caribbean
Peatlands of Latin America and the CaribbeanPeatlands of Latin America and the Caribbean
Peatlands of Latin America and the Caribbean
 
在线办理(lboro毕业证书)拉夫堡大学毕业证学历证书一模一样
在线办理(lboro毕业证书)拉夫堡大学毕业证学历证书一模一样在线办理(lboro毕业证书)拉夫堡大学毕业证学历证书一模一样
在线办理(lboro毕业证书)拉夫堡大学毕业证学历证书一模一样
 
Optimizing Post Remediation Groundwater Performance with Enhanced Microbiolog...
Optimizing Post Remediation Groundwater Performance with Enhanced Microbiolog...Optimizing Post Remediation Groundwater Performance with Enhanced Microbiolog...
Optimizing Post Remediation Groundwater Performance with Enhanced Microbiolog...
 

Case history doha linea red line north en

  • 1. CASE HISTORY DOHA RED LINE NORTH - CONTROL IN EXECUTION OF SYSTEM PERFORMANCE OF CONNECTION AND GASKET Emissione Data Approvazione Progetto Rev. S. LUPI 27/10/2014 G. BOMBEN DOHA RED LINE NORTH 1
  • 2. CASE HISTORY INTRODUCTION Fama Spa is an Italian company operating since 1988 in design, certification, manufacture of products for precast lining of tunnels. Fama Spa is specialized in the development of sealing systems and a wide range of accessories for the connection, lifting and anchoring systems for the construction of tunnels with TBM. For the excavation of the Red Line North di DOHA, FAMA SpA provided gaskets and connection systems. To complete a strategic path that began with the design and continued with the certification through laboratory tests, with a campaign of measurements, it was possible to document the performance of these products in exercise.
  • 3. CASE HISTORY DOHA METRO RED LINE NORTH DESIGN OF THE LINING - UNIVERSAL RING 6+1 - KEY 1/3 OTHER SEGMENT - EX. DIAMETER 6.770 mm - IN. DIAMETER 6.170 mm - THICKNESS OF CONCRETE 300 mm - LENGTH OF CONCRETE 1.500 mm - ANCHORED GASKET 26 x 17 mm WITH HIDROPHYLIC STRIP - 19 CONNECTORS FOR RING (3 FOR EACH SEGMENT , 1 FOR THE KEY) - GUIDE BAR AND BOLT ON THE RADIAL JOINT
  • 4. CASE HISTORY EPDM SEALING GASKET - UG027A - ANCHORED GASKET 26 x 17 mm WITH HIDROPHYLIC STRIP - PRESSURE REQUIRED TO CONTRACT  10 bar  GAP 5 mm  OFFSET 10 mm
  • 5. CASE HISTORY CONNECTION SYSTEM - SMARTBLOCK 90-160/300-60 - PULL OUT 90 KN - SHEAR STRENGTH 160 KN - LENGTH 300 mm - DIAMETER OF CENTERING 60 mm
  • 6. CASE HISTORY 1. We want to calculate the current state of misalignment and separation of the joints between the segments in the gallery; 2. The relief is performed with the use of two measurement gauges: one for the depth, with which recalculate the offsets and one for the width of the slots for the recalculation of the gap; 3. The joints are first classified according to the orientation angle to the progress of the excavation; 4. Usually the relief is performed on a continuous succession of five joints, reached by the operator that runs through the tunnel by foot. In case of severe anomalies the relief can be conducted on the entire ring with the aid of suitable lifting equipment. The measuring block 5 of joints may, at the operator's discretion, be repeated several times; 5. The sequence of measurements, if necessary, can be performed on the right side and on the left side of the tunnel with reference to the direction of advance of the excavation; 6. May be conducted in the presence of detections punctual infiltration of water, in order to evaluate if this is generated by an excessive misalignment, or spreading of the coupling or, finally, from other causes; 7. If necessary measurements can be performed on the blocks, facing the opposite of progress to compare with those initial misalignment stabilized along the tunnel. PROCEDURE FOR DETECTION GAP AND OFFSET BETWEEN THE JOINTS IN CONCRETE INTO THE TUNNEL
  • 7. CASE HISTORY PROCEDURE FOR DETECTION GAP AND OFFSET BETWEEN THE JOINTS IN CONCRETE INTO THE TUNNEL The measurements of gap and offset are performed at approximately 20 mm from the T joint, where the deviations from nominal are maximums. MEASUREMENTS OF GAP MEASUREMENTS OF GAP
  • 8. CASE HISTORY PROCEDURE FOR DETECTION GAP AND OFFSET BETWEEN THE JOINTS IN CONCRETE In the diagrams below are identified types of angles between segments of a same ring adjacent each other refer to the direction of excavation.
  • 9. CASE HISTORY PRESENTATION OF RESULTS MEASURES OF GAP IN THE CIRCUMFERENTIAL JOINTS
  • 10. CASE HISTORY PRESENTATION OF RESULTS MEASURES OF GAP IN THE LONGITUDINAL JOINTS
  • 11. CASE HISTORY PRESENTATION OF RESULTS MEASURES OF OFFSET IN THE CIRCUMFERENTIAL JOINTS
  • 12. CASE HISTORY PRESENTATION OF RESULTS MEASURES OF OFFSET IN THE LONGITUDINAL JOINTS
  • 13. CASE HISTORY PRESENTATION OF RESULTS PICTURES OF THE TUNNEL
  • 14. CASE HISTORY ANALYSIS OF THE RESULTS ASSESSMENT OF THE EFFICIENCY OF THE CONNECTION SYSTEM There have been 294 measurements of gap and offset. The average weigth gain of the gap is 0.4 mm, the offset of 1.4 mm. The requirements of the specifications of the Doha Metro Red Line North provide a mounting tolerance of 5 mm on the opening of the joint (gap) and 10 mm on the misalignment of the joint (offset). The connection system SmartBlock allowed a mounting error is much lower than expected. The connection system SmartBlock has minimized the effect of the divergence of the longitudinal and circumferential joints generated by the thrust of the gasket. The performance of the pull-out and shear of the SmartBlock are suited to the conditions of employment, ensuring the correct dimensioning of the system.
  • 15. CASE HISTORY ANALYSIS OF THE RESULTS ASSESSMENT OF THE EFFICIENCY OF THE SEALING GASKET The gallery of the DOHA METRO RED LINE NORTH is dry. The gasket sealing UG027A has been tested at the University Tor Vergata for the hydraulic performance requirements in the specifications of the project Doha Metro Red Line North. The gasket UG022A requires a load of 45 KN/m for its complete compression facilitating, in fact, the permanence of the closed joint. The geometry of UG022A well balanced between width and height and angles conformed to the geometry of the concrete allow, during assembly of the ring, to remain in its seat.