SlideShare a Scribd company logo
1
CALCULATING PHYSICAL PERCENT
COMPLETE FOR THE NES PROJECT USING
SCRUM AND ATLASSIAN STRUCTURES
Developing software using Scrum still needs the ability to determine
the Estimate to Complete (ETC), the Estimate at Completion (EAC), and
the Estimated Completion Data (ECD) when there is a fixed deliverable
date, a fixed budget for that software, and a minimal set of Features
and Capabilities on that date for that budget
Learning Objectives
§ Show how measuring Physical Percent Complete for
produced software is THE critical success factor for
integrating Performance Management with Agile
sofwtare development.
§ Show how to define Physical Percent Complete to
calculate Project Performance from the progress to
plan at the Sprint level.
§ Show why using Story Points do not provide
measures of physical percent complete beyond a
single Scrum team in a limited time window.
3
The question asked of every parent and
every software development project is …
Are We There Yet?
Looking for Simple Solutions to Questions?
They’re Aren’t Any …
The $20M Question ‒ How can we seamlessly integrate Scrum Development with
Project Performance Management measured in Dollars and Hours?
1. What Does DONE Look
Like?
2. How Do We Get to DONE?
3. Is There Enough Time,
Resources, And Money To
Get to DONE?
4. What Impediments Will Be
Encountered Along The
Way to DONE?
5. What Are The Units Of
Measure For Assessing
Progress Toward Done for
each Deliverable?
Let’s start with Immutable Principles
of Project Success with Five Easy
Questions …
Performance-Based Project Management®, Copyright © Glen B. Alleman, 2017, All Rights Reserved
QUESTIONS
We are successfully applying the Five Immutable Principals of Project
Success to Agile Programs if we …
1
… have a defined Mission, Vision, Capabilities, and High Level Technical and
Operational Requirements ‒ by which to create …
2
… a Product Roadmap for delivering these Capabilities and connecting the
Requirements and Release Plan for producing the needed outcomes to meet
this Roadmap ‒ and have …
3
… allocated enough Time, Money, and Resources to increase the probability of
the project’s success ‒ and we …
4
… know what Risks are in front of us and their plans for retirement or handling ‒
and we can …
5
… confirm progress to plan with measures of Physical Percent Complete for each
Deliverable in the Release Plan with confidence of “on or before the planned
time and “at or below” the planned cost. 6
10 Steps to an Integrated Agile and Performance
Management System Using Physical Percent Complete
Capabilities Defined
in Product Roadmap
Release Plan Defines Work
assigned to Sprints
Release Contains Features
in Sprint
Measure Physical
Percent Complete for
Each Feature
Perform Work IAW
Roadmap and Backlog
Physical Percent
Complete Defines
Progress
Adjust P&C for Technical
Performance
Measure
Use Past Performance to
Forecast Future
Performance
1
2
3
5
6 7
8
9
10
Work Sequence of
Features Defined in
Roadmap
4
9
Assess the capabilities being provided through the delivered Features
Fulfill the requirements through effort held in the Product Backlog
Produce deliverables from
Product Backlog
Planned Budget
Physical % Complete
WP’s produce deliverables
that fulfill requirements
Capabilities
topology defines
requirements flow
down
WP flow must describe the
increasing maturity of the
product or service
Producing the deliverables in the planned
sequence maintains the value stream to
the customer
Performance–Based Project Management®, Copyright © Glen B. Alleman, 2012 - 2017
8
10 Steps to Integrating Agile Development and Performance
Management System Using Physical Percent Complete
Principles to Integrate Agile with Project Performance Management in Order of Increasing Maturity
1 Capabilities drive system Features. All Features must be traceable to a capability.
Features and their Stories and Tasks identify technical and process deliverables.
Sprints contain the work activities used to produce the deliverables.
Product Roadmap arranges the Capabilities and their Features – risk adjusted – into activity
flow, from which Stories can be developed as the Basis of Estimate for the Sprint teams.
Work progress is measured as Physical Percent Complete against the planned progress at
time of the performance assessment.
Work Authorization (Backlog Grooming and Sprint Backlog) assures the sequence of Work
produce progress at the planned rate for the planned cost, with the planned product maturity at
each assessment point in the IMS.
Performance Measures describes the current performance and provides information about
future performance.
Conformance with Technical Performance Measures (TPM) adjusts Program Performance for
rework, quality, or delayed features, using Units of Measure meaningful to the decision makers.
Performance feedback from each Sprint and resulting Stories and Features, sequences the
Product Roadmap to reestablish an on–time, on–budget master schedule.
Future performance is based on the To Complete Performance Index (TCPI), Independent
Estimate At Complete (IEAC), and the adjusted work sequence.
9
Forecasting Future Performance needed to
successfully manage the project Starts with …
What Stories and Tasks did we plan to produce?
Where are we now? (Physical Percent Complete)
What Stories and Tasks have been completed
now?
Produced = Planned × Physical Percent
Complete
Determining where we are now.
Is determined with a simple calculation
A Popular Bumper Sticker
in Boulder, Colorado (my
home town), says
Measures of Physical Percent
Complete are required to assess
progress to plan in presence of
uncertainty.
Trouble is, it’s not true.
— J. R. R. Tolkien
We need a target to steer
toward, and we need
measures of progress toward
that target.
That target is a statistically
random number, so estimates
of the target and progress to
the target are needed.
Those estimates must be in
units meaningful to the
decision makers.
Measuring Physical Percent Complete …
§ Product Effectiveness ‒ a measure of success that
are closely related to the achievements of the
operational objectives evaluated in the operational
environment, under a specific set of conditions. †
§ Product Performance ‒ a physical or functional
attribute relating to the system operation, measured
or estimated under specific conditions. †
Means Compliance With Planned Attributes Of Each
Deliverable Defined as Exit Criteria in the User Story
Physical Percent Complete requires measures meaningful to the decision makers.
Effectiveness and Performance are the starting point.
Measuring Physical Percent Complete …
§ Key Performance Parameters ‒ a capability and
characteristic so significant that failure to meet them
can be cause for reevaluation, reassessing, or
replanning of the project.
§ Technical Performance Measures ‒ an attribute that
determine how well a system or system element is
satisfying or expected to satisfy a technical
requirement or goal.
Means Compliance With Planned Attributes Of Each
Deliverable (Exit Criteria)
Performance Measures Start at the Task Level for
each Story in the Sprint
§ For work Started, what is TO DO
compared to Planned?
§ Physical Percent Complete at the Task Level
o (Planned Estimate ‒ TO DO) / Planned Estimate
§ For Story S70 ‒ Purchase Your Items
o (26 hrs ‒ 16 hrs) / 26 hrs = 38%
o Task S70 has 2 Story Points assigned to it for 26 hours
Task S73 has 3 Story Points and 8 hours
o Story Points can be used to prioritize but not measure
14
Project Performance Measures at the Release
Level
Capability
Feature (1-6)
18%
Feature (7-9)
18%
Feature (10-12)
28%
Feature (13-22)
36%
Release 1 Release 2 Release 3
The Bright Line
Physical Percent Complete (P%C) for the Capability
assessed at the end of each Release.
Release 1 = Capability 18% Complete
Release 2 = Capability 64% Complete
Release 3 = Capability 100% Complete
Project
Performance
Reporting
Agile Team
Reporting
Summing Physical Percent Complete from Tasks and Stories
to Features to Release.
Physical Percent Complete …
§ The Project Performance completion criteria must be based on technical
performance, the quality of work must be verified, and criteria must be
defined clearly and unambiguously.
§ The PO/PM ensures that this process measures quality and technical
maturity of technical work products instead of the quantity of work
performed.
§ In Agile Physical Percent Complete means Working Software at the end of
every Sprint.
§ The challenge in Agile is to account for deferred capabilities ‒ moved to
the next Sprint or Release ‒ and moving Budget to follow them.
§ But in Agile, Budget is flat spread connected with the labor assigned to
each Sprint that implements the Features.
… means compliance with planned Technical
Performance of Deliverable
Story Points are NOT a Meaningful
Measure of Physical Percent Complete
https://www.mountaingoatsoftware.com/blog/its-effort-not-complexity
In Agile,
Story Point-based
measures are
about the Relative
effort the work will
take, not the actual
effort or duration
Let’s Pause for an Interlude to Address the
Cardinal and Ordinal Estimating Problem
§ When we use a measure of something we
need to know if it is Cardinal or Ordinal.
§ Ordinal measures tell us the relative
difference between items.
– Uncle Scrooge is relatively rich
compared to Huey, Dewey, and Louie
is an Ordinal measure.
§ Cardinal measures are numbers that say how many of something there are,
they are counting numbers ‒ one, two, three, four, five.
§ Uncle Scrooge has $1,250,000,000 dollars of Gold
§ In Project Performance Management we use Cardinal numbers, measured in
Dollars, Hours, Technical Performance compliance.
§ Story Points are NOT a unit of measure used in Project Performance
Management.
Ordinal versus Cardinal is a critical understanding for success of Physical Percent Complete.
A Caution for using Story Points to Measure Progress
Beyond a Single Feature from a Single Team
Ordinal
numbers ONLY
have meaning
for their current
use ‒ unless
calibrated to a
reference that
does not
change over
time
Without Calibrated values, the numbers have no meaning when collected at higher levels of the
program ‒ Features and Capabilities.
Ordinal Story Points cannot be the basis of PV higher
than a single Feature developed by a single team
Feature 1
Story 1
Story 2
Story 3
Story 4
Story 5
Story 6
Team 1’s
Uncalibrated
Ordinal SP
estimates
Feature n
Team 2’s
Uncalibrated
Ordinal SP
estimates
∑ F1(SP) ∑ Fn(SP)
Release 1 ∑ of SP’s
• • •
§ At the Story level,
relative effort defines
individual estimates.
§ At the Feature level,
lower level SP’s don’t
have the same unit of
measure in the way
Dollars do.
§ When Features
summed to the
Release, relative
measures do not
provide basis of
Physical Percent
Complete.
These are Not the same units of measure
between Features – Uncalibrated SP’s
Story 1
Story 2
Story 3
Story 4
Story 5
Story 6• • •
Using Ordinal (uncalibrated values) outside the domain of agreement prevents comparison of
progress to plan. My Story Points aren’t Your Story Points.

More Related Content

What's hot

Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
Glen Alleman
 
Building a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingBuilding a Credible Performance Measurement Baseling
Building a Credible Performance Measurement Baseling
Glen Alleman
 
5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess
Glen Alleman
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOE
Glen Alleman
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master schedule
Glen Alleman
 
PGCS 2019 Master Class Integrating SE with PPM
PGCS 2019 Master Class Integrating SE with PPMPGCS 2019 Master Class Integrating SE with PPM
PGCS 2019 Master Class Integrating SE with PPM
Glen Alleman
 
Credible Plans, Integrated Reporting, and Control Systems
Credible Plans, Integrated Reporting, and Control SystemsCredible Plans, Integrated Reporting, and Control Systems
Credible Plans, Integrated Reporting, and Control Systems
Glen Alleman
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbook
Glen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
Glen Alleman
 
Build an integrated master plan and integrated master
Build an integrated master plan and integrated masterBuild an integrated master plan and integrated master
Build an integrated master plan and integrated master
Glen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
Glen Alleman
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
Glen Alleman
 
Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement Baseline
Glen Alleman
 
A credible pmb is the window to program
A credible pmb is the window to programA credible pmb is the window to program
A credible pmb is the window to program
Glen Alleman
 
Control Account Manager Short Course
Control Account Manager Short CourseControl Account Manager Short Course
Control Account Manager Short Course
Glen Alleman
 
EDM/PDM Implementation
EDM/PDM ImplementationEDM/PDM Implementation
EDM/PDM Implementation
Glen Alleman
 
Estimating and Reporting Agile Projects
Estimating and Reporting Agile ProjectsEstimating and Reporting Agile Projects
Estimating and Reporting Agile Projects
Glen Alleman
 
Earned value, XP and government contracts
Earned value, XP and government contractsEarned value, XP and government contracts
Earned value, XP and government contracts
Glen Alleman
 
Lifecycle
LifecycleLifecycle
Lifecycle
Glen Alleman
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project management
Glen Alleman
 

What's hot (20)

Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Building a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingBuilding a Credible Performance Measurement Baseling
Building a Credible Performance Measurement Baseling
 
5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOE
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master schedule
 
PGCS 2019 Master Class Integrating SE with PPM
PGCS 2019 Master Class Integrating SE with PPMPGCS 2019 Master Class Integrating SE with PPM
PGCS 2019 Master Class Integrating SE with PPM
 
Credible Plans, Integrated Reporting, and Control Systems
Credible Plans, Integrated Reporting, and Control SystemsCredible Plans, Integrated Reporting, and Control Systems
Credible Plans, Integrated Reporting, and Control Systems
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbook
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Build an integrated master plan and integrated master
Build an integrated master plan and integrated masterBuild an integrated master plan and integrated master
Build an integrated master plan and integrated master
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement Baseline
 
A credible pmb is the window to program
A credible pmb is the window to programA credible pmb is the window to program
A credible pmb is the window to program
 
Control Account Manager Short Course
Control Account Manager Short CourseControl Account Manager Short Course
Control Account Manager Short Course
 
EDM/PDM Implementation
EDM/PDM ImplementationEDM/PDM Implementation
EDM/PDM Implementation
 
Estimating and Reporting Agile Projects
Estimating and Reporting Agile ProjectsEstimating and Reporting Agile Projects
Estimating and Reporting Agile Projects
 
Earned value, XP and government contracts
Earned value, XP and government contractsEarned value, XP and government contracts
Earned value, XP and government contracts
 
Lifecycle
LifecycleLifecycle
Lifecycle
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project management
 

Similar to Calculating Physical Percent Complete on Agile Projects

Alleman ps03 - physical percent complete (v2)
Alleman   ps03 - physical percent complete (v2)Alleman   ps03 - physical percent complete (v2)
Alleman ps03 - physical percent complete (v2)
Glen Alleman
 
How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)
Glen Alleman
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value Management
Glen Alleman
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value Management
Glen Alleman
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
Glen Alleman
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environment
Glen Alleman
 
The Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentThe Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software Development
Glen Alleman
 
Five Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessFive Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation Success
Glen Alleman
 
Ev+agile=success
Ev+agile=successEv+agile=success
Ev+agile=success
Glen Alleman
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...
Glen Alleman
 
Capabilities Based Planning
Capabilities Based PlanningCapabilities Based Planning
Capabilities Based Planning
Glen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
Glen Alleman
 
Physical Percent Complete for Agile Projects
Physical Percent Complete for Agile ProjectsPhysical Percent Complete for Agile Projects
Physical Percent Complete for Agile Projects
Glen Alleman
 
EVM+Agile the darkside
EVM+Agile the darksideEVM+Agile the darkside
EVM+Agile the darkside
Glen Alleman
 
Assessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIAssessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPI
Glen Alleman
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
ignitetribes
 
Slides chapters 24-25
Slides chapters 24-25Slides chapters 24-25
Slides chapters 24-25
Priyanka Shetty
 
Dev ops metrics
Dev ops metricsDev ops metrics
Dev ops metrics
Shivagami Gugan
 
The Synergistic Nature of PI Objectives
The Synergistic Nature of PI ObjectivesThe Synergistic Nature of PI Objectives
The Synergistic Nature of PI Objectives
Charlene Cuenca
 

Similar to Calculating Physical Percent Complete on Agile Projects (20)

Alleman ps03 - physical percent complete (v2)
Alleman   ps03 - physical percent complete (v2)Alleman   ps03 - physical percent complete (v2)
Alleman ps03 - physical percent complete (v2)
 
How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value Management
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value Management
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environment
 
The Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentThe Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software Development
 
Five Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessFive Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation Success
 
Ev+agile=success
Ev+agile=successEv+agile=success
Ev+agile=success
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...
 
Capabilities Based Planning
Capabilities Based PlanningCapabilities Based Planning
Capabilities Based Planning
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Physical Percent Complete for Agile Projects
Physical Percent Complete for Agile ProjectsPhysical Percent Complete for Agile Projects
Physical Percent Complete for Agile Projects
 
EVM+Agile the darkside
EVM+Agile the darksideEVM+Agile the darkside
EVM+Agile the darkside
 
Assessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIAssessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPI
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
Slides chapters 24-25
Slides chapters 24-25Slides chapters 24-25
Slides chapters 24-25
 
Dev ops metrics
Dev ops metricsDev ops metrics
Dev ops metrics
 
The Synergistic Nature of PI Objectives
The Synergistic Nature of PI ObjectivesThe Synergistic Nature of PI Objectives
The Synergistic Nature of PI Objectives
 

More from Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
Glen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
Glen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
Glen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
Glen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
Glen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
Glen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
Glen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
Glen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
Glen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
Glen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
Glen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
Glen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
Glen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
Glen Alleman
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
Glen Alleman
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project manager
Glen Alleman
 
Paradigm of agile project management (update)
Paradigm of agile project management (update)Paradigm of agile project management (update)
Paradigm of agile project management (update)
Glen Alleman
 

More from Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project manager
 
Paradigm of agile project management (update)
Paradigm of agile project management (update)Paradigm of agile project management (update)
Paradigm of agile project management (update)
 

Recently uploaded

FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
Prayukth K V
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
BookNet Canada
 
Search and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical FuturesSearch and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical Futures
Bhaskar Mitra
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Product School
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
UiPathCommunity
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Inflectra
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
Guy Korland
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Jeffrey Haguewood
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...
Elena Simperl
 
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptxIOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
Abida Shariff
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
Product School
 
How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...
Product School
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
Laura Byrne
 
Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
Elena Simperl
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance
 
Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
Safe Software
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
DianaGray10
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
DianaGray10
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Tobias Schneck
 

Recently uploaded (20)

FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
 
Search and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical FuturesSearch and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical Futures
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...
 
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptxIOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
 
How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
 
Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
 
Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
 

Calculating Physical Percent Complete on Agile Projects

  • 1. 1 CALCULATING PHYSICAL PERCENT COMPLETE FOR THE NES PROJECT USING SCRUM AND ATLASSIAN STRUCTURES Developing software using Scrum still needs the ability to determine the Estimate to Complete (ETC), the Estimate at Completion (EAC), and the Estimated Completion Data (ECD) when there is a fixed deliverable date, a fixed budget for that software, and a minimal set of Features and Capabilities on that date for that budget
  • 2. Learning Objectives § Show how measuring Physical Percent Complete for produced software is THE critical success factor for integrating Performance Management with Agile sofwtare development. § Show how to define Physical Percent Complete to calculate Project Performance from the progress to plan at the Sprint level. § Show why using Story Points do not provide measures of physical percent complete beyond a single Scrum team in a limited time window.
  • 3. 3 The question asked of every parent and every software development project is … Are We There Yet?
  • 4. Looking for Simple Solutions to Questions? They’re Aren’t Any … The $20M Question ‒ How can we seamlessly integrate Scrum Development with Project Performance Management measured in Dollars and Hours?
  • 5. 1. What Does DONE Look Like? 2. How Do We Get to DONE? 3. Is There Enough Time, Resources, And Money To Get to DONE? 4. What Impediments Will Be Encountered Along The Way to DONE? 5. What Are The Units Of Measure For Assessing Progress Toward Done for each Deliverable? Let’s start with Immutable Principles of Project Success with Five Easy Questions … Performance-Based Project Management®, Copyright © Glen B. Alleman, 2017, All Rights Reserved QUESTIONS
  • 6. We are successfully applying the Five Immutable Principals of Project Success to Agile Programs if we … 1 … have a defined Mission, Vision, Capabilities, and High Level Technical and Operational Requirements ‒ by which to create … 2 … a Product Roadmap for delivering these Capabilities and connecting the Requirements and Release Plan for producing the needed outcomes to meet this Roadmap ‒ and have … 3 … allocated enough Time, Money, and Resources to increase the probability of the project’s success ‒ and we … 4 … know what Risks are in front of us and their plans for retirement or handling ‒ and we can … 5 … confirm progress to plan with measures of Physical Percent Complete for each Deliverable in the Release Plan with confidence of “on or before the planned time and “at or below” the planned cost. 6
  • 7. 10 Steps to an Integrated Agile and Performance Management System Using Physical Percent Complete Capabilities Defined in Product Roadmap Release Plan Defines Work assigned to Sprints Release Contains Features in Sprint Measure Physical Percent Complete for Each Feature Perform Work IAW Roadmap and Backlog Physical Percent Complete Defines Progress Adjust P&C for Technical Performance Measure Use Past Performance to Forecast Future Performance 1 2 3 5 6 7 8 9 10 Work Sequence of Features Defined in Roadmap 4 9 Assess the capabilities being provided through the delivered Features Fulfill the requirements through effort held in the Product Backlog Produce deliverables from Product Backlog Planned Budget Physical % Complete WP’s produce deliverables that fulfill requirements Capabilities topology defines requirements flow down WP flow must describe the increasing maturity of the product or service Producing the deliverables in the planned sequence maintains the value stream to the customer Performance–Based Project Management®, Copyright © Glen B. Alleman, 2012 - 2017
  • 8. 8 10 Steps to Integrating Agile Development and Performance Management System Using Physical Percent Complete Principles to Integrate Agile with Project Performance Management in Order of Increasing Maturity 1 Capabilities drive system Features. All Features must be traceable to a capability. Features and their Stories and Tasks identify technical and process deliverables. Sprints contain the work activities used to produce the deliverables. Product Roadmap arranges the Capabilities and their Features – risk adjusted – into activity flow, from which Stories can be developed as the Basis of Estimate for the Sprint teams. Work progress is measured as Physical Percent Complete against the planned progress at time of the performance assessment. Work Authorization (Backlog Grooming and Sprint Backlog) assures the sequence of Work produce progress at the planned rate for the planned cost, with the planned product maturity at each assessment point in the IMS. Performance Measures describes the current performance and provides information about future performance. Conformance with Technical Performance Measures (TPM) adjusts Program Performance for rework, quality, or delayed features, using Units of Measure meaningful to the decision makers. Performance feedback from each Sprint and resulting Stories and Features, sequences the Product Roadmap to reestablish an on–time, on–budget master schedule. Future performance is based on the To Complete Performance Index (TCPI), Independent Estimate At Complete (IEAC), and the adjusted work sequence.
  • 9. 9 Forecasting Future Performance needed to successfully manage the project Starts with … What Stories and Tasks did we plan to produce? Where are we now? (Physical Percent Complete) What Stories and Tasks have been completed now? Produced = Planned × Physical Percent Complete Determining where we are now. Is determined with a simple calculation
  • 10. A Popular Bumper Sticker in Boulder, Colorado (my home town), says Measures of Physical Percent Complete are required to assess progress to plan in presence of uncertainty. Trouble is, it’s not true. — J. R. R. Tolkien We need a target to steer toward, and we need measures of progress toward that target. That target is a statistically random number, so estimates of the target and progress to the target are needed. Those estimates must be in units meaningful to the decision makers.
  • 11. Measuring Physical Percent Complete … § Product Effectiveness ‒ a measure of success that are closely related to the achievements of the operational objectives evaluated in the operational environment, under a specific set of conditions. † § Product Performance ‒ a physical or functional attribute relating to the system operation, measured or estimated under specific conditions. † Means Compliance With Planned Attributes Of Each Deliverable Defined as Exit Criteria in the User Story Physical Percent Complete requires measures meaningful to the decision makers. Effectiveness and Performance are the starting point.
  • 12. Measuring Physical Percent Complete … § Key Performance Parameters ‒ a capability and characteristic so significant that failure to meet them can be cause for reevaluation, reassessing, or replanning of the project. § Technical Performance Measures ‒ an attribute that determine how well a system or system element is satisfying or expected to satisfy a technical requirement or goal. Means Compliance With Planned Attributes Of Each Deliverable (Exit Criteria)
  • 13. Performance Measures Start at the Task Level for each Story in the Sprint § For work Started, what is TO DO compared to Planned? § Physical Percent Complete at the Task Level o (Planned Estimate ‒ TO DO) / Planned Estimate § For Story S70 ‒ Purchase Your Items o (26 hrs ‒ 16 hrs) / 26 hrs = 38% o Task S70 has 2 Story Points assigned to it for 26 hours Task S73 has 3 Story Points and 8 hours o Story Points can be used to prioritize but not measure
  • 14. 14 Project Performance Measures at the Release Level Capability Feature (1-6) 18% Feature (7-9) 18% Feature (10-12) 28% Feature (13-22) 36% Release 1 Release 2 Release 3 The Bright Line Physical Percent Complete (P%C) for the Capability assessed at the end of each Release. Release 1 = Capability 18% Complete Release 2 = Capability 64% Complete Release 3 = Capability 100% Complete Project Performance Reporting Agile Team Reporting Summing Physical Percent Complete from Tasks and Stories to Features to Release.
  • 15. Physical Percent Complete … § The Project Performance completion criteria must be based on technical performance, the quality of work must be verified, and criteria must be defined clearly and unambiguously. § The PO/PM ensures that this process measures quality and technical maturity of technical work products instead of the quantity of work performed. § In Agile Physical Percent Complete means Working Software at the end of every Sprint. § The challenge in Agile is to account for deferred capabilities ‒ moved to the next Sprint or Release ‒ and moving Budget to follow them. § But in Agile, Budget is flat spread connected with the labor assigned to each Sprint that implements the Features. … means compliance with planned Technical Performance of Deliverable
  • 16. Story Points are NOT a Meaningful Measure of Physical Percent Complete https://www.mountaingoatsoftware.com/blog/its-effort-not-complexity In Agile, Story Point-based measures are about the Relative effort the work will take, not the actual effort or duration
  • 17. Let’s Pause for an Interlude to Address the Cardinal and Ordinal Estimating Problem § When we use a measure of something we need to know if it is Cardinal or Ordinal. § Ordinal measures tell us the relative difference between items. – Uncle Scrooge is relatively rich compared to Huey, Dewey, and Louie is an Ordinal measure. § Cardinal measures are numbers that say how many of something there are, they are counting numbers ‒ one, two, three, four, five. § Uncle Scrooge has $1,250,000,000 dollars of Gold § In Project Performance Management we use Cardinal numbers, measured in Dollars, Hours, Technical Performance compliance. § Story Points are NOT a unit of measure used in Project Performance Management. Ordinal versus Cardinal is a critical understanding for success of Physical Percent Complete.
  • 18. A Caution for using Story Points to Measure Progress Beyond a Single Feature from a Single Team Ordinal numbers ONLY have meaning for their current use ‒ unless calibrated to a reference that does not change over time Without Calibrated values, the numbers have no meaning when collected at higher levels of the program ‒ Features and Capabilities.
  • 19. Ordinal Story Points cannot be the basis of PV higher than a single Feature developed by a single team Feature 1 Story 1 Story 2 Story 3 Story 4 Story 5 Story 6 Team 1’s Uncalibrated Ordinal SP estimates Feature n Team 2’s Uncalibrated Ordinal SP estimates ∑ F1(SP) ∑ Fn(SP) Release 1 ∑ of SP’s • • • § At the Story level, relative effort defines individual estimates. § At the Feature level, lower level SP’s don’t have the same unit of measure in the way Dollars do. § When Features summed to the Release, relative measures do not provide basis of Physical Percent Complete. These are Not the same units of measure between Features – Uncalibrated SP’s Story 1 Story 2 Story 3 Story 4 Story 5 Story 6• • • Using Ordinal (uncalibrated values) outside the domain of agreement prevents comparison of progress to plan. My Story Points aren’t Your Story Points.