The document summarizes Toyota's Production System (TPS) and the seven types of "muda" or waste. It defines muda as any activity that does not add value from the customer's perspective. The seven types of muda are overproduction, waiting, transportation, processing itself, inventory, unnecessary motion, and defects. The document provides examples and causes of each type of muda, and explains how eliminating muda can help reduce costs and increase profits through just-in-time production and continuous improvement. The overall goal of TPS is to minimize lead time and eliminate all sources of muda.
Custom Molds, Inc. is a father-son business that began focusing on molds and later expanded into plastic parts production. It faces issues with longer production times than promised and defective products due to bottlenecks. The document analyzes the mold and parts production processes and recommends reconfiguring machines and workflows between departments, especially mold fabrication, parts fabrication, and testing, to better match current needs and reduce inefficiencies. It also recommends the office focus orders on what can be completed on time and streamline design processes.
Custom Molds, Inc. was founded in 1987 and manufactures custom molds and plastic parts. It has expanded over the years to include additional production processes. The changing market environment requires evaluating whether to focus on molds or parts production. Recommendations include concentrating specialized machines and workers depending on the production type, moving the testing area for improved efficiency, and coordinating order placement based on completion ability. In conclusion, market needs and financial effects must be considered for business changes.
1) Saivs provides sand casting, machining, and inspection processes with an ability to cast over 20,000 tons annually.
2) They use CNC machining centers, lathes, mills, drills and other equipment to machine parts to a tolerance of 0.02-0.03mm.
3) Saivs has quality management systems to inspect materials, perform tests, and ensure product quality meets standards.
As of September 2012 a spool manufacturer was required to supply 23,300 Spools by Jun 2013
Based on the current run-rate of 197 spools per week the spools manufacturer is forecasted to complete the full order of 23,300 Spools in Apr 2014, an estimated 10 months behind schedule
As the spool manufacturer was on the critical path for the LNG construction project, the delayed spools were a critical risk to first-gas target date
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS Julian Kalac P.Eng
The document provides 12 examples of Lean Six Sigma projects that resulted in cost savings through process improvements. The first example describes a project that increased production capacity of HVAC duct elbows by designing a one-man cell to run three semi-automatic machines simultaneously, achieving annual savings of $472k. Another project reduced robot welding setup time from 38 minutes to zero by designing modular fixtures, achieving annual savings of $650k. A third project converted batch production to continuous flow, increasing shift capacity by 82% and eliminating the need for overtime.
5 - Day Kaizen Event focusing on AR Changeover to:
- Lead time reduction
- Cycle time reduction
- Improve workflow
- WIP reduction
- Improve ergonomics, housekeeping & safety
- Clear SOPs & training materials
Achieved
- 81% Lead time reduction
- 37% Cycle time reduction
- 80% WIP reduction
Cangzhou Haoxing Hardware Manufacturing Co., Ltd is a leading Chinese manufacturer of stainless steel pipe fittings, valves, and quick couplings. The company is located in Cangzhou, Hebei province near major ports for convenient transportation. Haoxing offers a wide range of stainless steel products in grades 304, 316, 316L, and 316Ti to various standards. It has casting and machining production capabilities of 40 and 65 tons per month respectively. Haoxing prides itself on quality control throughout the entire production process from material input to final inspection before shipping. It aims to provide long-term business relationships with customers through competitive pricing, excellent communication, and a focus on continuous improvement.
The document summarizes Toyota's Production System (TPS) and the seven types of "muda" or waste. It defines muda as any activity that does not add value from the customer's perspective. The seven types of muda are overproduction, waiting, transportation, processing itself, inventory, unnecessary motion, and defects. The document provides examples and causes of each type of muda, and explains how eliminating muda can help reduce costs and increase profits through just-in-time production and continuous improvement. The overall goal of TPS is to minimize lead time and eliminate all sources of muda.
Custom Molds, Inc. is a father-son business that began focusing on molds and later expanded into plastic parts production. It faces issues with longer production times than promised and defective products due to bottlenecks. The document analyzes the mold and parts production processes and recommends reconfiguring machines and workflows between departments, especially mold fabrication, parts fabrication, and testing, to better match current needs and reduce inefficiencies. It also recommends the office focus orders on what can be completed on time and streamline design processes.
Custom Molds, Inc. was founded in 1987 and manufactures custom molds and plastic parts. It has expanded over the years to include additional production processes. The changing market environment requires evaluating whether to focus on molds or parts production. Recommendations include concentrating specialized machines and workers depending on the production type, moving the testing area for improved efficiency, and coordinating order placement based on completion ability. In conclusion, market needs and financial effects must be considered for business changes.
1) Saivs provides sand casting, machining, and inspection processes with an ability to cast over 20,000 tons annually.
2) They use CNC machining centers, lathes, mills, drills and other equipment to machine parts to a tolerance of 0.02-0.03mm.
3) Saivs has quality management systems to inspect materials, perform tests, and ensure product quality meets standards.
As of September 2012 a spool manufacturer was required to supply 23,300 Spools by Jun 2013
Based on the current run-rate of 197 spools per week the spools manufacturer is forecasted to complete the full order of 23,300 Spools in Apr 2014, an estimated 10 months behind schedule
As the spool manufacturer was on the critical path for the LNG construction project, the delayed spools were a critical risk to first-gas target date
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS Julian Kalac P.Eng
The document provides 12 examples of Lean Six Sigma projects that resulted in cost savings through process improvements. The first example describes a project that increased production capacity of HVAC duct elbows by designing a one-man cell to run three semi-automatic machines simultaneously, achieving annual savings of $472k. Another project reduced robot welding setup time from 38 minutes to zero by designing modular fixtures, achieving annual savings of $650k. A third project converted batch production to continuous flow, increasing shift capacity by 82% and eliminating the need for overtime.
5 - Day Kaizen Event focusing on AR Changeover to:
- Lead time reduction
- Cycle time reduction
- Improve workflow
- WIP reduction
- Improve ergonomics, housekeeping & safety
- Clear SOPs & training materials
Achieved
- 81% Lead time reduction
- 37% Cycle time reduction
- 80% WIP reduction
Cangzhou Haoxing Hardware Manufacturing Co., Ltd is a leading Chinese manufacturer of stainless steel pipe fittings, valves, and quick couplings. The company is located in Cangzhou, Hebei province near major ports for convenient transportation. Haoxing offers a wide range of stainless steel products in grades 304, 316, 316L, and 316Ti to various standards. It has casting and machining production capabilities of 40 and 65 tons per month respectively. Haoxing prides itself on quality control throughout the entire production process from material input to final inspection before shipping. It aims to provide long-term business relationships with customers through competitive pricing, excellent communication, and a focus on continuous improvement.
summary of 16 Lean Six Sigma improvement projects in manufacturing, bio-manufacturing, supply chain
including 2 machine safeguarding . Total savings over $8Mil
H&M , BIG W Groups Requirements for Quality SystemMithun Kar
The purpose of any retailer/ buyer
company requirements for quality
system is to provide supplies,
guidelines & requirements in order to
reach and sustain a good qualities level
in products
This document contains a summary of Poonam Dole's work experience and qualifications. It details her experience as a warehouse assistant and production assembly technician for Ecotech Industries Pvt Ltd since 2014, where she performed tasks like receiving, storing, and shipping goods and assembling air quality monitoring systems. It also outlines her 2011 apprenticeship with Mahindra Two Wheeler where she built and tested fuel tanks. The summary highlights her technical and academic qualifications which include an ITI certification in fitting and degrees from Dr. Harisingh Gour University.
This presentation are taking about the major points for the main keys of quality to control the MEP Activities, which is so important to any starting of any project.
This document provides information about a new compact universal testing machine for small spring compression from FEC, an ISO 9001 certified company. The machine has a maximum load capacity of 100 kg and maximum testing length of 100-600 mm. It has features like peak hold, digital or scale elongation measurement, motorized up and down movement, safety switches, overload protection and is designed for easy operation. The machine can be used to test springs, nonwovens, fabrics, yarns and other small products.
The document discusses the costs of poor quality, which are estimated to be 20-30% of production costs. There are four main categories of costs: prevention costs aim to reduce defects, appraisal costs identify defects before customers, internal failure costs arise from defects found during production, and external failure costs occur after products reach customers, such as warranty repairs. As quality increases, prevention costs rise while appraisal, internal, and external failure costs decrease.
1. Addtech is a Swedish group with 1400 employees and annual turnover of $675 million with branches in several countries including Denmark and China.
2. Their Qingdao branch has 250 employees and $50 million annual turnover, providing sealing and vibration isolation solutions from suppliers as well as custom elastomer products.
3. Their mission is to improve customers' competitiveness by supplying technical and commercial polymeric solutions that improve product performance.
The document provides an agenda for a workshop on effective shop floor organization for small furniture manufacturers. The workshop covers topics like effective layout options, process flow and organization, safety standards, basic equipment maintenance, and preventing electrical hazards. It emphasizes organizing the production space through proper layout and process flow, and maintaining the organization through the "5S" methodology of sorting, setting in order, shining, standardizing, and sustaining cleanliness and order over time. The overall goal is to help small businesses improve efficiency, safety, and productivity through an organized and well-maintained workshop environment.
Quality control of mould making at bluestar mould group Huy Bui Van
Bluestar Mould follows prevention-oriented philosophy before starting a new project. Special Review Team consists of Engineering Department, Manufacturing Department, Project Department, Quality Control Department and Purchasing Department adopt mould flow analysis, experience summary of similar projects and precaution potential problems of customers’ requirements, thereby to ensure the product quality effectively.
Riyadh Plastic Factories is a leading plastics company in Saudi Arabia with over 30 years of experience. They specialize in shrink film production using the latest machinery. Their largest machine can produce up to 20,000 kg per day. They offer mass production capabilities on short notice. Riyadh Plastic Factories also provides quality assurance through strict quality control testing from raw materials to finished goods. Their quality control lab can test for tensile strength, shrinkage, and melt flow. They have logistics capabilities to deliver products anywhere in Saudi Arabia through their fleet of trucks.
The 7 wastes of production are overproduction, wait time, transportation waste, processing waste, motion/movement waste, inventory waste, and defects waste. Each waste results in unnecessary time, costs, and resources. Eliminating these wastes would allow companies to produce only what is needed, when it is needed, with no unnecessary steps or movement in the production process.
One day maybe you wonder whether or not your home contains asbestos. As we know, asbestos-containing material (ACM) is widely used in 1980s and mostly can be found in roofing wall sheeting, floor sheeting, fencing, eaves, insulation and hot water systems.
Real lean transition case for a clothing company english daha-iyisini-yapabil...Utkan Uluçay, MSc., CDDP
The document outlines a company's process to reduce inventory levels and lead times by redesigning their production process. A task team conducted an analysis which showed high inventory levels and long lead times. They proposed improvements like reducing the number of production steps, decreasing movement between operations, and implementing a flow line system. This led to lower inventory levels and manufacturing time, increased flexibility, and higher profits. The changes established a more efficient customer-focused manufacturing process.
Total Solution Industries is a global manufacturing solutions provider headquartered in Raleigh, NC that was founded in 1987. It has manufacturing facilities in Shenzhen, China and provides services including injection molding, compression molding, casting, and stamping dies to customers in industries such as medical devices. The company utilizes a proprietary project management portal and state-of-the-art manufacturing technologies to deliver high quality molds on time at a competitive price through seamless global communications between its teams and customers.
This was our group assignment this august, we really enjoyed it and had some good ideas about the production engineering as well as operation management. Thought you would like to have a glimpse...
Engaged in offering wide range of Paper Mill Machinery, Packaging and Corrugation products such as Consistency And Level Control ( For Paper Mills Only ), Freeness Tester ( For Paper Mills Only ), Hand Sheet Former PAP 3053 ( For Paper Mills Only ), Head Box ( For Paper Mills Only ), Beating & Freeness Tester-Schopper Reigler, Beating & Freeness Tester Schopper Reigler Type, Beating & Freeness Tester-Canadian Type, Hand Sheet Former ( For Paper Mills Only ), Bod Incubator, Environmental Chamber, Laboratory Oven, Muffle Furnace.
The document discusses cylinder blocks used in press machines. Cylinder blocks must withstand high pressures and stresses without defects. They are made of materials like ZG45 by selecting molds and simulating the casting process. The blocks have been widely used in metallurgy, chemical, and construction industries in China and exported to other countries. They provide stable performance, simple technology, and low air viscosity. The manufacturer offers cost-effective production, fast delivery, and customer support.
Berry Long is seeking employment as a journeyman industrial pipefitter with experience installing, assembling, and troubleshooting piping systems. He has over 10 years of experience in pipefitting, construction assisting, and maintenance roles. His background includes certified pipefitting skills, military service as an infantry soldier and rifle team leader, and ongoing education to become a maintenance technician. He is skilled in areas such as pipe preparation, welding, hydraulic systems, and safety compliance.
Case Studies it is sbout honfs dfsdfsdjlfksldkfjTeproQC
The document outlines six supplier case studies: 1) Problem Solving, 2) In-House Training System, 3) Dies/Mold Preventive Maintenance, 4) Process Audits, 5) PDCA (Plan-Do-Check-Act), and 6) Process Design/Concept. Each case study provides examples of how the supplier addressed a particular issue or process using a structured approach like a fishbone diagram, training plan, preventative maintenance checks, process audits, PDCA cycles, or design concepts. The case studies are meant to demonstrate the supplier's commitment to continuous improvement through problem solving techniques.
Presentation given at SPE section meeting held at Hennepin Technical College March 29, 2016. Covers why injection molding training is so important, best practices for injection molding training and case studies from Paulson injection molding customers and scientific molding training
This document summarizes a Six Sigma Green Belt project conducted from September 2012 to January 2013 to reduce scrap from contamination in tubes at Extruder #1 and #2. The project team measured attributes, conducted an affinity diagram and cause-and-effect diagram to identify potential causes. Hypotheses were tested through demonstration of causes. Improvements were made to materials, methods, machines and validated through metrics tracking.
summary of 16 Lean Six Sigma improvement projects in manufacturing, bio-manufacturing, supply chain
including 2 machine safeguarding . Total savings over $8Mil
H&M , BIG W Groups Requirements for Quality SystemMithun Kar
The purpose of any retailer/ buyer
company requirements for quality
system is to provide supplies,
guidelines & requirements in order to
reach and sustain a good qualities level
in products
This document contains a summary of Poonam Dole's work experience and qualifications. It details her experience as a warehouse assistant and production assembly technician for Ecotech Industries Pvt Ltd since 2014, where she performed tasks like receiving, storing, and shipping goods and assembling air quality monitoring systems. It also outlines her 2011 apprenticeship with Mahindra Two Wheeler where she built and tested fuel tanks. The summary highlights her technical and academic qualifications which include an ITI certification in fitting and degrees from Dr. Harisingh Gour University.
This presentation are taking about the major points for the main keys of quality to control the MEP Activities, which is so important to any starting of any project.
This document provides information about a new compact universal testing machine for small spring compression from FEC, an ISO 9001 certified company. The machine has a maximum load capacity of 100 kg and maximum testing length of 100-600 mm. It has features like peak hold, digital or scale elongation measurement, motorized up and down movement, safety switches, overload protection and is designed for easy operation. The machine can be used to test springs, nonwovens, fabrics, yarns and other small products.
The document discusses the costs of poor quality, which are estimated to be 20-30% of production costs. There are four main categories of costs: prevention costs aim to reduce defects, appraisal costs identify defects before customers, internal failure costs arise from defects found during production, and external failure costs occur after products reach customers, such as warranty repairs. As quality increases, prevention costs rise while appraisal, internal, and external failure costs decrease.
1. Addtech is a Swedish group with 1400 employees and annual turnover of $675 million with branches in several countries including Denmark and China.
2. Their Qingdao branch has 250 employees and $50 million annual turnover, providing sealing and vibration isolation solutions from suppliers as well as custom elastomer products.
3. Their mission is to improve customers' competitiveness by supplying technical and commercial polymeric solutions that improve product performance.
The document provides an agenda for a workshop on effective shop floor organization for small furniture manufacturers. The workshop covers topics like effective layout options, process flow and organization, safety standards, basic equipment maintenance, and preventing electrical hazards. It emphasizes organizing the production space through proper layout and process flow, and maintaining the organization through the "5S" methodology of sorting, setting in order, shining, standardizing, and sustaining cleanliness and order over time. The overall goal is to help small businesses improve efficiency, safety, and productivity through an organized and well-maintained workshop environment.
Quality control of mould making at bluestar mould group Huy Bui Van
Bluestar Mould follows prevention-oriented philosophy before starting a new project. Special Review Team consists of Engineering Department, Manufacturing Department, Project Department, Quality Control Department and Purchasing Department adopt mould flow analysis, experience summary of similar projects and precaution potential problems of customers’ requirements, thereby to ensure the product quality effectively.
Riyadh Plastic Factories is a leading plastics company in Saudi Arabia with over 30 years of experience. They specialize in shrink film production using the latest machinery. Their largest machine can produce up to 20,000 kg per day. They offer mass production capabilities on short notice. Riyadh Plastic Factories also provides quality assurance through strict quality control testing from raw materials to finished goods. Their quality control lab can test for tensile strength, shrinkage, and melt flow. They have logistics capabilities to deliver products anywhere in Saudi Arabia through their fleet of trucks.
The 7 wastes of production are overproduction, wait time, transportation waste, processing waste, motion/movement waste, inventory waste, and defects waste. Each waste results in unnecessary time, costs, and resources. Eliminating these wastes would allow companies to produce only what is needed, when it is needed, with no unnecessary steps or movement in the production process.
One day maybe you wonder whether or not your home contains asbestos. As we know, asbestos-containing material (ACM) is widely used in 1980s and mostly can be found in roofing wall sheeting, floor sheeting, fencing, eaves, insulation and hot water systems.
Real lean transition case for a clothing company english daha-iyisini-yapabil...Utkan Uluçay, MSc., CDDP
The document outlines a company's process to reduce inventory levels and lead times by redesigning their production process. A task team conducted an analysis which showed high inventory levels and long lead times. They proposed improvements like reducing the number of production steps, decreasing movement between operations, and implementing a flow line system. This led to lower inventory levels and manufacturing time, increased flexibility, and higher profits. The changes established a more efficient customer-focused manufacturing process.
Total Solution Industries is a global manufacturing solutions provider headquartered in Raleigh, NC that was founded in 1987. It has manufacturing facilities in Shenzhen, China and provides services including injection molding, compression molding, casting, and stamping dies to customers in industries such as medical devices. The company utilizes a proprietary project management portal and state-of-the-art manufacturing technologies to deliver high quality molds on time at a competitive price through seamless global communications between its teams and customers.
This was our group assignment this august, we really enjoyed it and had some good ideas about the production engineering as well as operation management. Thought you would like to have a glimpse...
Engaged in offering wide range of Paper Mill Machinery, Packaging and Corrugation products such as Consistency And Level Control ( For Paper Mills Only ), Freeness Tester ( For Paper Mills Only ), Hand Sheet Former PAP 3053 ( For Paper Mills Only ), Head Box ( For Paper Mills Only ), Beating & Freeness Tester-Schopper Reigler, Beating & Freeness Tester Schopper Reigler Type, Beating & Freeness Tester-Canadian Type, Hand Sheet Former ( For Paper Mills Only ), Bod Incubator, Environmental Chamber, Laboratory Oven, Muffle Furnace.
The document discusses cylinder blocks used in press machines. Cylinder blocks must withstand high pressures and stresses without defects. They are made of materials like ZG45 by selecting molds and simulating the casting process. The blocks have been widely used in metallurgy, chemical, and construction industries in China and exported to other countries. They provide stable performance, simple technology, and low air viscosity. The manufacturer offers cost-effective production, fast delivery, and customer support.
Berry Long is seeking employment as a journeyman industrial pipefitter with experience installing, assembling, and troubleshooting piping systems. He has over 10 years of experience in pipefitting, construction assisting, and maintenance roles. His background includes certified pipefitting skills, military service as an infantry soldier and rifle team leader, and ongoing education to become a maintenance technician. He is skilled in areas such as pipe preparation, welding, hydraulic systems, and safety compliance.
Case Studies it is sbout honfs dfsdfsdjlfksldkfjTeproQC
The document outlines six supplier case studies: 1) Problem Solving, 2) In-House Training System, 3) Dies/Mold Preventive Maintenance, 4) Process Audits, 5) PDCA (Plan-Do-Check-Act), and 6) Process Design/Concept. Each case study provides examples of how the supplier addressed a particular issue or process using a structured approach like a fishbone diagram, training plan, preventative maintenance checks, process audits, PDCA cycles, or design concepts. The case studies are meant to demonstrate the supplier's commitment to continuous improvement through problem solving techniques.
Presentation given at SPE section meeting held at Hennepin Technical College March 29, 2016. Covers why injection molding training is so important, best practices for injection molding training and case studies from Paulson injection molding customers and scientific molding training
This document summarizes a Six Sigma Green Belt project conducted from September 2012 to January 2013 to reduce scrap from contamination in tubes at Extruder #1 and #2. The project team measured attributes, conducted an affinity diagram and cause-and-effect diagram to identify potential causes. Hypotheses were tested through demonstration of causes. Improvements were made to materials, methods, machines and validated through metrics tracking.
- The factory tour report summarizes Stephen's visit to Taizhou Xiang Yu Machinery Co., Ltd. to investigate issues with hardness in their manufactured parts.
- Testing with a calibrated hardness tester showed that the parts met the required hardness specifications after heat treatment, indicating the previous failure was likely due to using an uncalibrated tester.
- Suggestions were provided to the manufacturer to appoint a quality manager, keep thorough inspection records, calibrate measuring tools, and double check tools before use to prevent future issues.
The curriculum vitae is for Mr. N. Karthick, who has over 5 years of experience in quality assurance, quality control, and non-destructive testing. He has a diploma in mechanical engineering and is skilled in AutoCAD, PRO-E, Solidworks, and Microsoft operating systems. His experience includes positions as a maintenance engineer, tool room in charge, quality control engineer, and quality development engineer. He has qualifications in non-destructive testing techniques including radiography, penetrant testing, and visual testing.
Bubai Mondal is seeking assignments in production, quality control, production planning, product development, process development and improvement, or technical support. He has over 5 years of experience in manufacturing and technical support. He is proficient in laboratory infrastructure, product development, process optimization, quality control, and troubleshooting analytical equipment. He has strong problem solving, analytical, and organizational skills. Currently he works as a Quality Officer at Precision Plastic Products LLC in Dubai, where he manages people, demonstrates quality procedures, conducts audits and documentation, and handles customer complaints.
Manufacturing involves transforming raw materials into finished goods through various processes. The key steps in manufacturing include prefabrication, welding, painting, assembly, testing, finishing and delivery. Manufacturing processes can be classified as casting, forming and machining. Implementing lean manufacturing principles such as reducing waste, batch sizes and inventories can improve productivity, quality and reduce costs. The 5S methodology is a common starting point that involves sorting, simplifying, sweeping, standardizing and sustaining work areas to increase organization and efficiency.
Presentation made to MD&M MN Conference in 2006 by Tom Misik, VP Sales Belco Packaging Systems, Inc.
Equipment Considerations For Thermoformed Tray Sealing On Shuttle Style Heat Sealers
Improvement strategy by using ML and TM. A case study for solving cracking i...q-Maxim
1. The case study aimed to reduce cracking in steel castings produced via sand casting by optimizing process parameters.
2. In Phase 1, exploratory data analysis of over 6500 records identified furnace number, tap temperature, ladle temperature, and chemistry variables like C and Ni as most influential on cracking.
3. Linear regression and LASSO regression confirmed these findings and shortlisted key variables to focus on in subsequent experimentation and optimization.
Scott Phipps started in the mold making industry in 1978 and now owns United Tool and Mold (UTM), which operates from three locations in South Carolina and Alabama. UTM specializes in mold repair and has experience supporting molders globally. Phipps emphasizes the importance of communication, preventative maintenance planning, understanding the entire molding process, and paying attention to details when diagnosing and solving molding issues. He also discusses the challenges of finding skilled employees with diverse experience.
The document provides information about The Delta Composite Knitting Ind. Ltd., a knit composite dyeing industry in Bangladesh. It was established in 1998 and has expanded over time to include 19 dyeing machines across two floors. It produces knitted fabrics from cotton, polyester, and blends. While the facilities and machinery allow for production, the document notes the drainage system and effluent treatment need improvement to be more environmentally sustainable.
This document discusses the implementation of statistical process control (SPC) techniques at an automotive rubber parts manufacturing firm in India. It focuses on applying SPC to their production of shocker seals, which previously had an unacceptably high rejection rate of over 9%. Common defects causing shocker seal rejections are identified. Recommendations are provided to address defects, such as improving vacuum, temperature control, and inspection processes. SPC X-bar and R charts are created using data from 400 samples to monitor the diameter of shocker seals. No data points fell outside the control limits, indicating process capability was improved beyond requirements. In conclusion, applying SPC helped reduce rework costs and improve process efficiency.
In any SME manufacturing organizations, one of the major causes for low plant utilization is changeover loss.In this presentation, using SMED methodology, step by step process is given to reduce the changeover loss.Also shared the real examples of changeover loss reduction in various manufacturing industries using SMED concept.Hope this is useful for any organization struggling with low plant utilisation due to changeover loss..
This document provides a summary of a seminar report on the implementation of Industry 4.0 at Tega Industries in Dahej, Gujarat, India. Tega Industries established in 1976 and is a global leader in wear resistant products for mining and materials handling. The report outlines Tega's production process, including fabrication, blasting and painting, rubber mixing in the banburry, blank production, and pressing. It identifies key performance indicators to monitor in Phase 1 of implementing Industry 4.0. This includes implementing barcode and digital systems to track production and ensure quality. The report also analyzes utilization of blasting machines and safety issues to address, such as in the banburry and boiler areas.
The document summarizes work to automate leak testing of food storage containers. Key points:
- The project aims to develop a testing apparatus to improve on the current manual leak testing procedure and free up technician time.
- The proposed apparatus would rotate containers filled with water and use infrared sensors to detect and count any drips, standardizing the test.
- Testing showed the apparatus results correlated with manual tests and did not affect container seals. It was estimated to save over $6,000 annually in technician time.
- Future work may include automating lid attachment, more rigorous testing plans, and minimizing human error to increase confidence in results.
The document contains rules and guidelines for workplace conduct, safety procedures, potential emergencies, hazardous and non-hazardous materials, standard work processes, machine operating procedures, product and process characteristics to control, and plans for daily preventive maintenance and visual controls. Disciplinary actions are outlined for issues like absenteeism, idleness, leaving early, safety violations, and drug or alcohol use.
uality is one of the most important management principles for any organization regardless of industry. This is particularly true for the pharmaceutical sector: maintaining quality product standards is essential for the prevention and treatment of numerous medical disorders.
Although the pharmaceutical industry has been around for centuries, in recent years we have experienced an increase in the number of drugs being launched in the market. As a result of this increase, the need for quality assurance and quality control measures has risen. For instance, drug manufacturers must follow strict guidelines to get their drugs approved by the FDA (Food and Drug Administration) in the United States. Such guidelines include requirements for testing, manufacturing, labelling, packaging, storing and distributing pharmaceuticals.
Quality Management
Quality management is a crucial component of any successful organization as it ensures that products and services are produced and distributed consistently and effectively.
Good Manufacturing Practice (GMP) is the element of quality management that ensures goods are produced and controlled according to the quality standards of their intended use and that they meet the requirements specified by the marketing authorization or product specification. Additionally, it ensures that manufactured goods are safe, of high quality, and effective. For pharmaceutical companies, GMP entails the monitoring of procedures, apparatuses, employees, and environments.
Quality planning, quality control, and quality assurance are all important aspects of quality management too. We’ll look at what quality management is, why it’s important, and the main components and principles of quality management in this article.
Quality planning
Quality planning refers to the process of defining the quality requirements and standards of a product or service and identifying the resources needed to meet such requirements and standards. The planning phase is the first stage in establishing a good quality management system. It is in this phase that companies define their baseline quality objectives. Once goals have been set, organizations must determine what is required to achieve these objectives and what procedures should be implemented to ensure their success. During this stage of the quality management process, it is important to keep in mind the following considerations:
The organization’s definition of success
How often procedures and processes will be evaluated for improvement
If the stakeholders have any quality-related priorities, goals, or ambitions
If there are any legal procedures or standards that must be followed in order to achieve the desired quality level
Quality Control
Quality control is the next step in the quality management process. At this stage, companies assess through physical inspection and testing whether their plan is achievable.
1. This document provides information on the finishing process and organizational structure of Fariha Knit Tex Ltd, including job descriptions for managers and supervisors.
2. It outlines the finishing process flow chart and lists the required and existing positions in the dyeing and finishing section, with variances.
3. The job responsibilities of key managers - the AGM, two senior managers, and three assistant managers - are described in detail, focusing on production planning and monitoring, quality control, and ensuring on-time delivery.
Total Quality Management (TQM) is a management approach focused on customer satisfaction by ensuring quality in all business processes. TQM involves management commitment, employee empowerment, and continuous improvement. The key aspects of TQM include determining customer demands, designing products and processes to meet those demands, tracking results to guide improvements, and quality control at all stages from raw materials to final inspection. TQM aims for zero defects through techniques like statistical process control, ISO standards, and management systems.
Dongguan Juyan Silicone Technology Co., Ltd is a Chinese manufacturer of silicone products established in 2001 that specializes in developing, manufacturing, and selling rubber and silicone products. The company has over 6,500 square meters of factory space with advanced machinery and quality inspection equipment. Key sections of the factory include engineering, production, quality assurance, and customer service. Juyan focuses on cake molds, ice trays, kitchen utensils, and other silicone household items. It prides itself on technical expertise, a talented workforce, and an ISO-certified quality management system to ensure high product quality and customer satisfaction.
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....Lacey Max
“After being the most listed dog breed in the United States for 31
years in a row, the Labrador Retriever has dropped to second place
in the American Kennel Club's annual survey of the country's most
popular canines. The French Bulldog is the new top dog in the
United States as of 2022. The stylish puppy has ascended the
rankings in rapid time despite having health concerns and limited
color choices.”
Digital Marketing with a Focus on Sustainabilitysssourabhsharma
Digital Marketing best practices including influencer marketing, content creators, and omnichannel marketing for Sustainable Brands at the Sustainable Cosmetics Summit 2024 in New York
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Final ank Satta Matka Dpbos Final ank Satta Matta Matka 143 Kalyan Matka Guessing Final Matka Final ank Today Matka 420 Satta Batta Satta 143 Kalyan Chart Main Bazar Chart vip Matka Guessing Dpboss 143 Guessing Kalyan night
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challengesHolger Mueller
Holger Mueller of Constellation Research shares his key takeaways from SAP's Sapphire confernece, held in Orlando, June 3rd till 5th 2024, in the Orange Convention Center.
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...APCO
The Radar reflects input from APCO’s teams located around the world. It distils a host of interconnected events and trends into insights to inform operational and strategic decisions. Issues covered in this edition include:
IMPACT Silver is a pure silver zinc producer with over $260 million in revenue since 2008 and a large 100% owned 210km Mexico land package - 2024 catalysts includes new 14% grade zinc Plomosas mine and 20,000m of fully funded exploration drilling.
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...Aleksey Savkin
The Strategy Implementation System offers a structured approach to translating stakeholder needs into actionable strategies using high-level and low-level scorecards. It involves stakeholder analysis, strategy decomposition, adoption of strategic frameworks like Balanced Scorecard or OKR, and alignment of goals, initiatives, and KPIs.
Key Components:
- Stakeholder Analysis
- Strategy Decomposition
- Adoption of Business Frameworks
- Goal Setting
- Initiatives and Action Plans
- KPIs and Performance Metrics
- Learning and Adaptation
- Alignment and Cascading of Scorecards
Benefits:
- Systematic strategy formulation and execution.
- Framework flexibility and automation.
- Enhanced alignment and strategic focus across the organization.
Company Valuation webinar series - Tuesday, 4 June 2024FelixPerez547899
This session provided an update as to the latest valuation data in the UK and then delved into a discussion on the upcoming election and the impacts on valuation. We finished, as always with a Q&A
At Techbox Square, in Singapore, we're not just creative web designers and developers, we're the driving force behind your brand identity. Contact us today.
3 Simple Steps To Buy Verified Payoneer Account In 2024SEOSMMEARTH
Buy Verified Payoneer Account: Quick and Secure Way to Receive Payments
Buy Verified Payoneer Account With 100% secure documents, [ USA, UK, CA ]. Are you looking for a reliable and safe way to receive payments online? Then you need buy verified Payoneer account ! Payoneer is a global payment platform that allows businesses and individuals to send and receive money in over 200 countries.
If You Want To More Information just Contact Now:
Skype: SEOSMMEARTH
Telegram: @seosmmearth
Gmail: seosmmearth@gmail.com
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...my Pandit
Dive into the steadfast world of the Taurus Zodiac Sign. Discover the grounded, stable, and logical nature of Taurus individuals, and explore their key personality traits, important dates, and horoscope insights. Learn how the determination and patience of the Taurus sign make them the rock-steady achievers and anchors of the zodiac.
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf46adnanshahzad
How to Start Up a Company: A Step-by-Step Guide Starting a company is an exciting adventure that combines creativity, strategy, and hard work. It can seem overwhelming at first, but with the right guidance, anyone can transform a great idea into a successful business. Let's dive into how to start up a company, from the initial spark of an idea to securing funding and launching your startup.
Introduction
Have you ever dreamed of turning your innovative idea into a thriving business? Starting a company involves numerous steps and decisions, but don't worry—we're here to help. Whether you're exploring how to start a startup company or wondering how to start up a small business, this guide will walk you through the process, step by step.
Best practices for project execution and deliveryCLIVE MINCHIN
A select set of project management best practices to keep your project on-track, on-cost and aligned to scope. Many firms have don't have the necessary skills, diligence, methods and oversight of their projects; this leads to slippage, higher costs and longer timeframes. Often firms have a history of projects that simply failed to move the needle. These best practices will help your firm avoid these pitfalls but they require fortitude to apply.
1. 10/30/2017 Six Sigma Black Belt
Larry Whitmarsh Ph.D.
Master Lean, Six Sigma, Statistical Engineering
Primary Consultant Statistical Engineering
1-248-880-1534
www.linkedin.com/in/dr-larry-whitmarsh-63076b10 whitmarsh.l@att.net
2.
3. Lid guide
Y's =
Outputs/
Results Y1 Rec Plastic Y1
Convey to
Dryer Y1
Load Molding
Machine Y1 Molding machine Y1
In Process
Inspection Y1 Final Inspection
Critical
Operator
dominate Move Molding machine Process inspection Final Inspection
Process
Steps
Incoming
material
Drying time Move to machine Settings, warm-up
Bend test and size
every 100 parts
both cavities
Instructions
In any problem solving it is key to understand the entire process. I have found over the years
it is best done with Business Process Performance. First taught to me by PPG while problem solving
a major painting process located in Monterrey Mexico.
I have listed the Ys in this case as the steps in the process. I have always used the PFMEA to
gain the suppliers knowledge of their process. In most cases I find the PFMEA only reveals the
very basic steps. In one instance with a Die Caster the whole PFMEA relied on weekly CMM layouts
and no in-process inspection. When I asked the General Manager how this could happen he stated
“it comes from Japan like that”. Needless to say this changed very quickly.
4. Process
Steps
Incoming
material
Drying time Move to machine Settings, warm-up
Bend test and size
every 100 parts
both cavities
Instructions
X's =
Controls/
Inputs X1
Certification
review X1
Ensure
quality
inspected
material X1 Proper fill level, X1
Machine warn up
time X1 No brittleness X1 Special instructions
X2
Understand
limits X2
Pour into
dryer. X2 Correct color X2 Proper ID size
X3
Blind
sampling to
supplier X3
Establish
proper
settings and
time . X3 Purge barrel X3
Visual
characteristics
X3
Assure
virgin
Material X4
Run set up parts
until process is
capable. Hold and
release.
X4
Special reaction
instructions
X4
Identify
acceptable
or reject X5
First piece
inspection and
approval to run
The above was a plastic molding process. The part was failing in the field, at the time I got involved 4 users
had been struck in the head by the part failing. The real critical problem was; there were thousand’s more
in warehouses waiting to be shipped to the final customers.
The Xs are the FMEA instructions
DFMEA
PFMEA
Cause and Effect Dia.
Six Sigma
5. N's=
Noise/
Variatio
n N1
Supplier of
material N1 Dryers N1 Machine warm up N1 Run machine N1 Process Inspection N1 Final Insp
N2
Understand
process N2
Understand
settings, on
machine, hi
and lo limit
lights N2 Barrel purge N1
Inspect every 100
parts N2
Develop plan for
insp. At process N2
Develop random
sampling plan
N3
More
knowledge
of material N3
Can
material be
dried too
much N3 Machine settings N2
Operator reaction
plan N3
Manufacture
measure tool N3
assure no need to
look for short shot
due to warm up.
N4
Determine
critical info
from certs. N4
High and low limits
of material in
feeder N3
Mold angle too
sharp 90 degree
tool maker to
change to 45
degrees N4
Utilize test tool
N5
Gain
knowledge
from
supplier of
drying
concerns
and heat
setting. N5
Inspection approval
to run
N5
Training
N6
No regrind
and
material in
dryer is
destroyed
after run N6
Destroy set up
parts
The N's are the team brainstorming
opportunities. In this case you can
see 6 items in yellow directly
contributed to the failure. I have
Expanded this to use LEAN
calculations.
6.
7. 7
4
First notified; June 29, 2010 contained to assembly plant
2nd incident; July 17th by distribution center internal
3rd Incident; July 19th by External distribution
4th Incident; July 20 Reports from customers
Clips found internally were shatter not just cracked.
Comments;
• Supplier had no knowledge why the part was failing. Material being used is the same
• 1500 pounds when this job 1st started up 07.2007. 1st clue
Next steps;
• Review supplier process for clues
• Visit polymer supplier for clues
• Determine proper material and handling
• Brainstorm all significant and important items in the process
• Control all items in process
• Perform 8 hour production run with improve product and track Win numbers
The team was starting
to worry that the age of
the plastic might cause
the material properties
to degrade
8. It is mandatory that you can measure what
you are working on. In this case we used a
die maker rule and tapped in into the sleeve
until the plastic broke. Not especially
repeatable nor especially accurate but for
our study was just what the doctor ordered.
9.
10.
11. 1.
2.
Number 1. the part from the mold before
any rework of the mold. Notice all the air
bubbles. Gating was at 90 degrees causing
turbulence during injection.
Number 2. Ground gate to 45 degrees which
eliminated the turbulence, no air bubble
present.