EMERYVILLE
CENTER OF INNOVATION
MARCH 4, 2020
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G000
EMERYVILLE CENTER OF INNOVATIONFlad Project Number
BMR CAMPUS VISION19396-05
PROJECT DESCRIPTION PROJECT TEAM SHEET INDEX
LOCATION MAP
VICINITY MAP
LAND USE PROGRAM
The proposed FDP area includes approximately 6.31
acres situated at the intersection of Hollis and Stanford
Streets, and Horton and 53rd Streets in Emeryville,
California. The FDP proposes to develop the area of
Buildings 1, 2, 3, 13 and 14 identified in Figure 2-5 of the
PDP, to accommodate research, development and small-
scale manufacturing, production-scale manufacturing,
administration, and mechanical and utility spaces. The
building and landscaping design are intended to establish
the Emeryville Center of Innovation as a cohesive, modern
life science campus for the 21st century.
PROJECT DESCRIPTION
The proposed project consists of two new buildings, B1 and
B2/3 totaling approximately 561,000 square feet that will
complete the Hollis Street frontage between 53rd Street and
Stanford Avenue, along with a parking structure, B13/14,
facing Horton Street that will accommodate the parking
necessary to support the existing and new building space.
The project components are summarized as follows:
Building	Approx Size	 # of Occupied Floors
B1	 300,000 SF	 11
B2/3	 261,000 SF	 7
B13/14	 2,018Cars	 9 levels, including grade and 	
			roof
This proposed construction complies with the “Minimum
Project” as defined in Section 2.2.3 of the PDP.
The initial building construction will consist of the
building shell and core space, to include the full building
structure, building exterior facades, roof level equipment
screening, interior stairs and elevators, and primary
utility distribution risers. The initial construction may also
include the building entry lobbies, toilet cores on one or
more floor levels, and primary mechanical equipment.
Specific functions throughout the buildings will be
determined by the building tenants as a part of the future
tenant improvements construction.
BUILDING DESCRIPTIONS
Building B1 consists of a new 11-story, approximately
300,000 SF tower designed to accommodate research
and development laboratories and associated office
and support space on all levels. The First Floor level will
incorporate the primary building entry, tenant spaces
facing the streets, courtyard and plaza, and entries to the
building loading dock and service areas. Floors 2 through
10 will be designed to accommodate flexible laboratory
OWNER
Biomed Realty
17190 Bernardo Center Drive
San Diego, CA 92128
(858) 485.9840
ARCHITECT
FLAD Architects
650 California Street
17th Floor
San Francisco, CA 94108
(415) 398.1600
PARKING DESIGN
International Parking Design
560 14th Street
Suite #300
Oakland, CA 94612
(510) 473.0300
LAND USE COUNSEL
Perkins Coie
505 Howard Street
Suite 1000
San Francisco, CA 94105
(415) 344.7117
CIVIL ENGINEER
BKF Engineers
150 California Street
Suite 600
San Francisco, CA 94111
(415) 930.7949
GEOTECHNICAL ENGINEER
LANGAN
135 Main Street
Suite 1500
San Francisco, CA 94105
(415) 955.5200
LANDSCAPE ARCHITECT
BIONIC
833 Market Street
Suite 601
San Francisco, CA 94103
(415) 206.0648
12/12/19
02/10/20
03/04/20
11/04/19
and associated office and support space on all levels, and
the 11th floor will be designed as a “sky box” space that
can accommodate either administrative, conference or
research space. The potential for a rooftop terrace space
will be incorporated to take advantage of the views from
this premier location. The building roof areas will be utilized
for mechanical equipment, including boilers, chillers, air
handling units and exhaust fans.
Building B2/3 consists of a new 7-story, approximately
261,000 SF building designed to accommodate research
and development laboratories and associated office
and support space on all levels. The First Floor level will
incorporate the primary building entry, tenant spaces
facing Hollis Street and the courtyard, and entries to the
building loading dock and service areas. Floors 2 through
7 will be designed to accommodate flexible laboratory
and associated office and support space on all levels.
The building roof areas will be utilized for mechanical
equipment, including boilers, chillers, air handling units
and exhaust fans. The street liner for will contain building
support functions such conferencing and meeting rooms,
training and education facilities, and so on. Retail functions
will also be provided on building 2/3.
Building B13/14 consists of a dedicated parking structure
with vehicle parking on 9 levels, including the grade level
and roof level. Provisions will be made for incorporation of
electric vehicle charging as appropriate. This building is
anticipated to accommodate small occupied space for an
Emergency Operations Center or other retail use including
possible provision for a small office to accommodate a
parking staff.
BUILDING FACADES
The building B1 and B2/3 facade will consist of a
combination of materials that are respectful and compatible
with the architecture of existing Building 4, while also
updating the appearance of these new buildings to
meet new sustainability objectives, indoor environmental
standards, energy performance, and marketplace
expectations. The lower levels of the proposed buildings
B1 and B2/3 will incorporate glass and terracotta or
brick masonry materials that relate strongly to the local
Emeryville history, current context and adjacent Building
4 design. The middle levels of the buildings will consist of
glass and metal trim that provide excellent light and views
to and from the building interior. Opaque areas will be
addressed with a combination of shadowbox (spandrels)
panels and/or metal infill panels, to add interest and
variation to the facade. The upper levels and mechanical
screens will consist of a combination of opaque glass
panels and metal screen materials or terracotta to conceal
the rooftop equipment and exhaust risers.
Sheet Index
G000	 Data Sheet
G001	 BMR Campus Vision
G002	 BMR Campus Vision - Axonometric
G003	 Existing Conditions Within PDP Area
G004	 Existing Conditions Within PDP Area On BMR Properties
G005	 Existing Site Photos
G006	 PDP Boundary and Site Plan*
G007	 PDP Boundary And Site Plan - Showing BMR Properties
G008	 PDP Boundary And Site Plan - Showing BMR FDP Boundary
G009	 BMR Proposed FDP Scope
G010	 BMR FDP - Frontage & Setbacks
G011	 BMR FDP - Open Space
G012	 BMR FDP - Building Heights
G013	 BMR FDP - Vehicular Circulation & Service Access
G014	 BMR FDP - Pedestrian Circulation
G015	 BMR FDP - Emergency Vehicle Access
G016	 BMR FDP - Bicycle Circulation
G017	 BMR FDP - Bicycle Circulation At B13/14
G018	 Project Images - Southwest View At Hollis And Stanford Streets -B1
G019	 Building Plans - B1
G020	 Building Images, Hollis Street Elevation - B1
G021	 Project Images - Southwest View At Hollis Street - B2/3
G022	 Building Plans - B2/3
G023	 Building Images, Hollis Street Elevation - B2/3
G024	 Building Images, Southeast View at Horton Street - B13/14
G025	 Building Images, Southeast View at Horton Street - B13/14
G026	 Building Plans - B13/14 (Parking)
G027	 Building Images, Horton Street Elevation - B13/14
G028	 Shadow Studies
G029	 PDP Conformance - Overall Massing
G030	 PDP Conformance - Hollis Street Setbacks
G031	 PDP Conformance - Hollis Street Height Limits
G032	 PDP Conformance - Hollis Street Building Massing
G033	 PDP Conformance - Horton Street Building Massing
G034	 PDP Conformance - PDP Setbacks
G035	 PDP Conformance - PDP & Proposed FDP Setback Comparison
L001	 Context Of FDP Boundary
L002	 Landscape Illustrative Plan B1 & B2/3
L003	 Project Image - Chiron Way Shared Street Looking North
L004	 Project Image - Plaza Looking South
L005	 Project Image - Plaza Looking North
L006	 Project Image - Paseo Looking Toward Chiron Way
L007	 Material Palette & Precedents
L008	 Materials Plan B1 & B2/3
L009	 Preliminary Plant Palette & Precedents
L010	 Preliminary Tree Palette & Precedents
L011	 Planting Areas B1 & B2/3
L012	 Hydrozone B1 & B2/3
L013	 Landscape Sections: (Chiron Way)
L014	 Landscape Sections: (Chiron Way)
L015	 Landscape Sections: (Chiron Way)
L016	 Landscape Sections: (Hollis Street, Stanford Avenue)
L017	 Landscape Sections: (Hollis Street, Stanford Avenue)
L018	 Landscape Sections: (Entry Garden Section, Paseo Section)
L019	 Landscape Sections: (Plaza)
Data Sheet
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
25’0’ 50’ 100’
B2/3
24'
HORTON STREET
(Public Street)
HORTON STREET “FORMERLY LANDREGAN ST”(Public Street)
53RDSTREET
(PublicStreet)
CHIRON WAY “FORMERLY HOLDEN ST”
(Publicly-Accessible Private Street)
HOLLIS STREET
(Public Street)
HOLLIS STREET
(Public Street)
PELADEAU STREET
(Public Street)
STANFORD
AVENUE
(PublicStreet)
FUTUREPEDESTRIANBRIDGEBRIDGEACCESS
EASEMENT
NON-BUILDABLE
EASEMENT
B1
B4
(E)
B7
(E)
B8B
(FUTURE BUILDING)
B8A
(FUTURE BUILDING)
PDU
(E)
R
(E)
Q
(E)
N
(E)
H
(E)
12A
(E)
CMF
(E)
F
(E)
E
(E)
D
(E)
B13/14
B2/3
Non Buildable Easement**
Grifols-Owned Properties
Overall PDP Boundary*
BMR-Owned Properties
Grifols-Owned BuildingA0A
BMR-Owned BuildingA0A
Existing Building(E)
GRIFOLS-OWNED
PROPERTIES
GRIFOLS-OWNED
PROPERTIES
BMR-OWNED
PROPERTIES
BMR-OWNED
PROPERTIES
BMR-OWNED
PROPERTIES
GRIFOLS-OWNED
PROPERTIES
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G001
BMR Campus Vision
*Per Preliminary Development Plan Figure 2-5 & 2-6
**Per 2018 ALTA/NSPS Land Title Survey
HORTON STREET “FORMERLY LANDREGAN ST”
HORTON STREET
HOLLIS STREET
HOLLIS STREET
PELADEAU STREET
STANFORDAVENUE
FUTURE SHERWIN WILLIAMS
DEVELOPMENT
B8B
(FUTURE BUILDING)
B8A
(FUTURE BUILDING)
D
(E)
R
(E)
Q
(E)
PDU
(E)
H
(E) 12A
(E)
CMF
(E)
B1
B2/3
B7
(E)
B4
(E)
B13/14
F
(E)
N
(E)
E
(E)
Overall PDP Boundary*
BMR-Owned Properties**
BMR-Owned BuildingA0A
Grifols-Owned BuildingA0A
Existing Building(E)
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G002
BMR Campus Vision - Axonometric
*Per Preliminary Development Plan Figure 2-5 & 2-6
**Per 2018 ALTA/NSPS Land Title Survey
Overall PDP Boundary*
Grifols-Owned Building
BMR-Owned Building
A0A
A0A
12AH
R
Q
N
PDU
G T
B7
B4
E
D
CMF
F
0’ 25’ 50’ 100’
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G003
Existing Conditions Within PDP Area
*Per Preliminary Development Plan Figure 2-5 & 2-6
Overall PDP Boundary*
BMR-Owned Properties**
Non BMR-Owned Properties**
PDU
G T
B7
B4
BMR-OWNED
PROPERTIES
BMR-OWNED
PROPERTIES
BMR-OWNED
PROPERTIES
0’ 25’ 50’ 100’
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G004
Existing Conditions Within PDP Area On BMR Properties
*Per Preliminary Development Plan Figure 2-5 & 2-6
** Per 2018 ALTA/NSPS Land Title Survey
map.
1000 ft
N
➤➤
N
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G005
Existing Site Photos
1
6
3
2
5
4
1
54
2
3
6
Overall PDP Boundary*
Proposed PDP Buildings*
Horton Street
Hollis Street
Holden Street
53rdStreet
45thStreet
StanfordStreetExtension
Horton Street Bypass
B4
B8B9B10B11D B7A
CMF
B7B
B6
B5
B3
B2
PDU B12B B12AB13B14B
B14A
B1
0’ 25’ 50’ 100’
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G006
PDP Boundary and Site Plan*
*Per Preliminary Development Plan Figure 2-5 & 2-6
Overall PDP Boundary*
Proposed PDP Buildings*
BMR-Owned Properties**
HORTON STREET
HOLLIS STREET
HOLDEN STREET
53RDSTREET
45THSTREET
STANFORD
STREETEXTENSION
HORTON STREET BYPASS
B4
B8B9B10B11D B7A
CMF
B7B
B6
B5
B3
B2
PDU B12B B12AB13B14B
B14A
B1
BMR-OWNED
PROPERTIES
BMR-OWNED
PROPERTIES
BMR-OWNED
PROPERTIES
0’ 25’ 50’ 100’
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G007
*Per Preliminary Development Plan Figure 2-5 & 2-6
PDP Boundary And Site Plan - Showing BMR Properties
Overall PDP Boundary*
BMR FDP Scope Extents
Proposed PDP Buildings*
53RDSTREET
HORTON STREET
HOLLIS STREET
HOLDEN STREET
45THSTREET
STANFORD
STREETEXTENSION
HORTON STREET BYPASS
B4
B8B9B10B11D B7A
CMF
B7B
B6
B5
B3
B2
PDU B12B B12AB13B14B
B14A
B1
0’ 25’ 50’ 100’
PROPOSED
FDP AREA
PROPOSED
FDP AREA
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G008
*Per Preliminary Development Plan Figure 2-5 & 2-6
PDP Boundary And Site Plan - Showing BMR FDP Boundary
25’0’ 50’ 100’
Overall PDP Boundary*
BMR FDP Boundary
Grifols-Owned BuildingA0A
BMR-Owned BuildingA0A
Existing Building(E)
HORTON STREET
HORTON STREET “FORMERLY LANDREGAN ST”
FUTUREPEDESTRIANBRIDGE
53RDSTREET
HOLLIS STREET
HOLLIS STREET
PELADEAU STREET
STANFORD
AVENUE
CHIRON WAY “FORMERLY HOLDEN ST”
(Publicly-Accessible Private Street)
B1
B4
(E)
B7
(E)
G
(E)
T
(E)
PDU
(E)
B13/14
R
(E)
Q
(E)
N
(E)
H
(E)
12A
(E)
CMF
(E)
F
(E)
E
(E)
D
(E)
B2/3
REMOVING EXISTING
SECURITY GATES
PROPOSED
FDP AREA
REMOVING EXISTING
SECURITY GATES
PROPOSED
FDP AREA
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G009
BMR Proposed FDP Scope
*Per Preliminary Development Plan Figure 2-5 & 2-6
25’0’ 50’ 100’
Overall PDP Boundary*
BMR FDP Boundary
Grifols-Owned BuildingA0A
BMR-Owned BuildingA0A
Existing Building(E)
50'
22'
45'
77'
30'
26'26'
32'
12'
47'
50'
50'
20'
14'
18'
35'
HORTON STREET
HORTON STREET “FORMERLY LANDREGAN ST”
53RDSTREET
HOLLIS STREET
HOLLIS STREET
PELADEAU STREET
STANFORDAVENUE
FUTUREPEDESTRIANBRIDGE
CHIRON WAY “FORMERLY HOLDEN ST”
(Publicly-Accessible Private Street)
B1
B2/3
B4
(E)
PDU
(E)
R
(E)
Q
(E)
N
(E)
H
(E)
12A
(E)
CMF
(E)
F
(E)
E
(E)
D
(E)
B13/14
G
(E)
T
(E)
B7
(E)
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G010
BMR FDP - Frontage & Setbacks
*Per Preliminary Development Plan Figure 2-5 & 2-6
25’0’ 50’ 100’
Overall PDP Boundary*
BMR FDP Boundary
Open Space
Grifols-Owned BuildingA0A
BMR-Owned BuildingA0A
Service
HORTON STREET
HORTON STREET “FORMERLY LANDREGAN ST”
53RDSTREET
HOLLIS STREET
HOLLIS STREET
PELADEAU STREET
STANFORD
AVENUE
SERVICE
FUTUREPEDESTRIANBRIDGE
CHIRON WAY “FORMERLY HOLDEN ST”
(Publicly-Accessible Private Street)
B4
(E)
B7
(E)
G
(E)
T
(E)
PDU
(E)
B13/14 H
(E)
12A
(E)
CMF
(E)
F
(E)
R
(E)
Q
(E)
N
(E)
E
(E)
D
(E)
B2/3
B1
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G011
BMR FDP - Open Space
*Per Preliminary Development Plan Figure 2-5, 2-6, 2-30
25’0’ 50’ 100’
Overall PDP Boundary*
BMR FDP Boundary
Grifols-Owned BuildingA0A
BMR-Owned BuildingA0A
Existing Building(E)
HORTON STREET
HORTON STREET “FORMERLY LANDREGAN ST”
53RDSTREET
HOLLIS STREET
HOLLIS STREET
PELADEAU STREET
STANFORD
AVENUE
FUTUREPEDESTRIANBRIDGE
CHIRON WAY “FORMERLY HOLDEN ST”
(Publicly-Accessible Private Street)
+194'
Top Of Screen
+178'
Top Of Roof
Structure
+162'
Top Of Roof
Structure
+178'
Top Of Screen
+130'
Top Of Screen
+106'-3''
Top Of Mech
+82'-6''
Top Of Roof
Structure
+114'
Top Of Roof
Structure
+90'-2''
Top Of Roof
Structure
B4
(E)
B7
(E)
G
(E)
T
(E)
PDU
(E)
B13/14 H
(E)
12A
(E)
CMF
(E)
F
(E)
R
(E)
Q
(E)
N
(E)
E
(E)
D
(E)
B2/3
B1
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G012
BMR FDP - Building Heights
*Per Preliminary Development Plan Figure 2-5 & 2-6
25’0’ 50’ 100’
Overall PDP Boundary*
BMR FDP Boundary
Service Vehicle Access
Building Entrance Location
Loading Entrance Location
Parking Entrance Location
Vehicular Circulation
BMR-Owned BuildingA0A
Non BMR-Owned BuildingA0A
Loading Zone
Commercial StructuredParking Short Term Loading/Drop-Off
B4
(E)
B7
(E)
G
(E)
T
(E)
PDU
(E)
B13/14 H
(E)
12A
(E)
CMF
(E)
F
(E)
R
(E)
Q
(E)
N
(E)
E
(E)
D
(E)
B2/3
B1
CURB CUT
CURB CUT
REMOVING EXISTING
SECURITY GATES
REMOVING EXISTING
SECURITY GATES
HORTON STREET
HORTON STREET “FORMERLY LANDREGAN ST”
53RDSTREET
HOLLIS STREET
HOLLIS STREET
PELADEAU STREET
STANFORD
AVENUE
FUTUREPEDESTRIANBRIDGE
CHIRON WAY “FORMERLY HOLDEN ST”
(Publicly-Accessible Private Street)
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G013
BMR FDP - Vehicular Circulation & Service Access
*Per Preliminary Development Plan Figure 2-5 & 2-6
25’0’ 50’ 100’
Overall PDP Boundary*
BMR FDP Boundary
Building Entrance Location
Pedestrian Circulation
through Arcade
Private Elevator
Public Park
Crosswalk zone Pedestrian Circulation
BMR-Owned BuildingA0A
Non BMR-Owned BuildingA0A
Proposed Greenway**
B4
(E)
B7
(E)
G
(E)
T
(E)
PDU
(E)
B13/14 H
(E)
12A
(E)
CMF
(E)
F
(E)
R
(E)
Q
(E)
N
(E)
E
(E)
D
(E)
B2/3
B1
REMOVING EXISTING
SECURITY GATES
REMOVING EXISTING
SECURITY GATES
HORTON STREET
HORTON STREET “FORMERLY LANDREGAN ST”
53RDSTREET
HOLLIS STREET
HOLLIS STREET
PELADEAU STREET
STANFORD
AVENUE
FUTUREPEDESTRIANBRIDGE
CHIRON WAY “FORMERLY HOLDEN ST”
(Publicly-Accessible Private Street)
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G014
BMR FDP - Pedestrian Circulation
*Per Preliminary Development Plan Figure 2-5 & 2-6
**Per 2016 General Plan, Figure 4-1
25’0’ 50’ 100’
Overall PDP Boundary*
BMR FDP Boundary
E.V.A. Route
Emergency Vehicle
Vehicular Circulation
BMR-Owned BuildingA0A
Non BMR-Owned Building
Existing Fire Hydrant To Remain
A0A
B4
(E)
B7
(E)
G
(E)
T
(E)
PDU
(E)
B13/14 H
(E)
12A
(E)
CMF
(E)
F
(E)
R
(E)
Q
(E)
N
(E)
E
(E)
D
(E)
B2/3
B1
HORTON STREET
HORTON STREET “FORMERLY LANDREGAN ST”
53RDSTREET
HOLLIS STREET
HOLLIS STREET
PELADEAU STREET
STANFORD
AVENUE
FUTUREPEDESTRIANBRIDGE
CHIRON WAY “FORMERLY HOLDEN ST”
(Publicly-Accessible Private Street)
150'150'
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G015
BMR FDP - Emergency Vehicle Access
*Per Preliminary Development Plan Figure 2-5 & 2-6
25’0’ 50’ 100’
Overall PDP Boundary*
BMR FDP Boundary
Bicycle Circulation
Bike Boulevard**
BMR-Owned BuildingA0A
Non BMR-Owned BuildingA0A
Existing Building(E)
Building Entrance Location
Long Term Bicycle StorageShort Term Bicycle Storage
B4
(E)
B7
(E)
G
(E)
T
(E)
PDU
(E)
R
(E)
Q
(E)
N
(E)
H
(E)
12A
(E)
CMF
(E)
F
(E)
E
(E)
D
(E)
B13/14
B2/3
B1
REMOVING EXISTING
SECURITY GATES
REMOVING EXISTING
SECURITY GATES
HORTON STREET
HORTON STREET “FORMERLY LANDREGAN ST”
53RDSTREET
HOLLIS STREET
HOLLIS STREET
PELADEAU STREET
STANFORD
AVENUE
FUTUREPEDESTRIANBRIDGE
CHIRON WAY “FORMERLY HOLDEN ST”
(Publicly-Accessible Private Street)
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G016
BMR FDP - Bicycle Circulation
*Per Preliminary Development Plan Figure 2-5 & 2-6
**Per 2016 General Plan, Figure 3-6
SEE SHEET G017
53rdSTREET
Garage Entrance
Proposed Separation Pylons
Proposed Conflict Striping
Proposed Bike Lane
Existing Sharrows
Existing Separation Pylons
Existing Bike Lane
BICYCLES
SAFETY
MEASURES
2
1
B13/14
21
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G017
BMR FDP - Bicycle Circulation At B13/14
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G018
Project Images - Southwest View At Hollis And Stanford Streets -B1
GLAZED MECHANICAL
SCREEN WALL
TERRACOTTA, GFRC, OR MASONRY
CLADDING PANELS
TERRACOTTA, GFRC, OR MASONRY
PANEL RAINSCREEN
LOW-IRON HIGH PERFORMANCE
INSULATED GLAZING UNITS
HIGH PERFORMANCE INSULATED
GLAZING UNITS
STANFORDAVENUE
HOLLIS STREET
CHIRON WAY
0 32 FT 64 FT
50'-6"
53'-0"
19'-0"
42'-0"
LEVEL 1
STANFORDAVENUE
HOLLIS STREET
19'-0"
50'-6"
53'-0"
205'-0"
136'-0"
213'-9"
APPROX.
APPROX.
APPROX.
0’ 16’ 32’ 64’
BMR Emeryville Master Plan, Area Summary DRAFT
BUILDING SQUARE FEET, GSF TABLE-2: PARKING PROVIDED, CAR COUNT HEIGHT LIMITS
floor B1 B2/3 B8 A B4 B8 B Subtotal-1 floor B 13 Subtotal 75' ht limit 90' ht limit 125' Ht limit225' ht limit
11 17,000 11 178
10 30,000 10 162 130'-175'
9 30,000 9 146
8 30,000 8 94,738 PH(132) 130
7 30,000 18,594 7 94,738 114 114 90-130'
6 27,000 32,000 18,594 6 94,738 PH(98) 98 98
5 27,000 35,000 23,117 23,558 5 94,738 82 82 82
4 27,000 35,000 24,547 23,558 4 94,738 66 66 66 66
3 26,000 35,000 24,547 24,416 3 94,738 50 50 50 50
2 28,000 32,000 24,547 24,416 2 94,738 34 34 34 34
1 28,000 31,000 23,107 285,000 23,861 1 94,738 18 18 18 18
Area 300,000 200,000 119,865 285,000 156,997 1,061,862 Area 757,900 757,900
Rounding 3 3 3 3 3 3 Cars 2,309 2,309
300,000 200,000 119,000 285,000 156,000 1,061,000 Surface 38 2,347
TABLE-3: Proposed Parking
Building Area, sqft 1,061,862 1,061,862
Parking per 1000 GSF 1.55 2
Car Count 1,646 2,124
Note-1 : PH = 18'-0", Ground floor = 18'-0", Typical Floor = 16'-0"
Note-2 : Car Count Assumes 325 GSF per stall
7,500 GSF
11,000
GSF AVG
18,000
GSF AVG
MECHANICAL
BUILDING SUPPORT
R&D COLLABORATION
R&D OFFICE
R&D SUPPORT
R&D LAB
AMENITY
ROOF TERRACE
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G019
Building Plans - B1
LEVEL 1 FLOOR PLAN
1
TYPICAL FLOOR PLAN
2
ROOF PLAN
3
LEGEND
LOBBY
November 4, 2019 BMR EMERYVILLE CENTER OF INNOVATION
Building Images, Elevation - B1
A210
Building B1 East Elevation
ROOF
106'-3"106'-3"
ROOF
90'-3"
level 7
74'-3"
level 6
57'-6"
level 5
41'-6"
level 4
25'-6"
level 3
12'-9"
level 2
0'-0"
level 1
90'-3"
level 7
74'-3"
level 6
57'-6"
level 5
41'-6"
level 4
25'-6"
level 3
12'-9"
level 2
0'-0"
level 1
84'-4"
0'-0"
level 1
level 4
level 2
11'-4"
level 3
21'-6"
31'-8"
level 5
41'-10"
level 6
level 7
Roof
72'-4"
52'-0"
62'-2"
198'-0"
Top of Screen
Roof
178'-0"
level 11
162'-0"
146'-0"
level 10
130'-0"
level 9
level 8
level 7
114'-0"
98'-0"
82'-0"
level 6
level 5
66'-0"
50'-0"
level 4
34'-0"
level 3
0'-0"
level 1
18'-0"
level 2
Roof
98'-0"
82'-0"
level 6
level 5
66'-0"
50'-0"
level 4
34'-0"
level 3
0'-0"
level 1
18'-0"
level 2
114'-0"
Top of Screen
Top of Core Top of Core
level 2
18'-0"
level 1
0'-0"
level 3
34'-0"
level 4
50'-0"
66'-0"
level 5
level 6
82'-0"
98'-0"
Roof
level 2
18'-0"
level 1
0'-0"
level 3
34'-0"
level 4
50'-0"
66'-0"
level 5
level 6
82'-0"
98'-0"
114'-0"
level 7
level 8
level 9
130'-0"
level 10
146'-0"
162'-0"
level 11
178'-0"
Roof
62'-2"
52'-0"
72'-4"
Roof
level 7
level 6
41'-10"
level 5
31'-8"
21'-6"
level 3
11'-4"
level 2
level 4
level 1
0'-0"
84'-4"
level 1
0'-0"
level 2
12'-9"
level 3
25'-6"
level 4
41'-6"
level 5
57'-6"
level 6
74'-3"
level 7
90'-3"
level 1
0'-0"
level 2
12'-9"
level 3
25'-6"
level 4
41'-6"
level 5
57'-6"
level 6
74'-3"
level 7
90'-3"
ROOF
106'-3" 106'-3"
ROOF
Top of Screen
114'-0"
Top of Screen
194'-0"
0’ 16’ 32’ 64’
November 4, 2019 BMR EMERYVILLE CENTER OF INNOVATION
Building Images, Elevation - B1
A210
Building B2/3 East Elevation
ROOF
106'-3"106'-3"
ROOF
90'-3"
level 7
74'-3"
level 6
57'-6"
level 5
41'-6"
level 4
25'-6"
level 3
12'-9"
level 2
0'-0"
level 1
90'-3"
level 7
74'-3"
level 6
57'-6"
level 5
41'-6"
level 4
25'-6"
level 3
12'-9"
level 2
0'-0"
level 1
84'-4"
0'-0"
level 1
level 4
level 2
11'-4"
level 3
21'-6"
31'-8"
level 5
41'-10"
level 6
level 7
Roof
72'-4"
52'-0"
62'-2"
198'-0"
Top of Screen
Roof
178'-0"
level 11
162'-0"
146'-0"
level 10
130'-0"
level 9
level 8
level 7
114'-0"
98'-0"
82'-0"
level 6
level 5
66'-0"
50'-0"
level 4
34'-0"
level 3
0'-0"
level 1
18'-0"
level 2
Roof
98'-0"
82'-0"
level 6
level 5
66'-0"
50'-0"
level 4
34'-0"
level 3
0'-0"
level 1
18'-0"
level 2
114'-0"
Top of Screen
Top of Core
level 3
62'-2"
21'-6"
94'-6"
31'-8"
level 5
Top of Screen
Roof
level 8
41'-10"
Roof
level 7
level 6
98'-0"
114'-0"
130'-0"
0'-0"
level 1
82'-0"
level 6
level 5
66'-0"
50'-0"
level 4
level 4
34'-0"
level 7
level 3
0'-0"
level 1
18'-0"
level 2
72'-4"
level 2
11'-4"
52'-0"
Top of Core
82'-6"
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G020
Building Images, Hollis Street Elevation - B1
GLAZED MECHANICAL
SCREEN WALL
HIGH PERFORMANCE
INSULATED GLAZING UNITS
LOW-IRON HIGH PERFORMANCE
INSULATED GLAZING UNITS
TERRACOTTA, GFRC, OR MASONRY
PANEL RAINSCREEN
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G021
Project Images - Southwest View At Hollis Street - B2/3
TERRACOTTA, GFRC, OR
MASONRY SCREEN WALL
TERRACOTTA, GFRC, OR
MASONRY CLADDING
PANELS
TERRACOTTA, GFRC, OR
MASONRY PANEL
RAINSCREEN
LOW-IRON HIGH
PERFORMANCE
INSULATED GLAZING UNITS
HIGH PERFORMANCE
INSULATED GLAZING
UNITS
47'-0"
HOLLIS STREET
CHIRON WAY
30'-0"
0 32 FT 64 FT
30'-0"
45'-0"
LEVEL 1
39,392 sq ft
182'-0"
128'-6"
134'-0"
118'-6"
0 32 FT 64 FT
APPROX.
APPROX.
APPROX.
APPROX.
LEVEL 3-5 (TYPICAL) - NEW OPTION
64 FT32 FT0
LEVEL 7 (MECHANICAL)
0’ 16’ 32’ 64’
BMR Emeryville Master Plan, Area Summary DRAFT
BUILDING SQUARE FEET, GSF TABLE-2: PARKING PROVIDED, CAR COUNT HEIGHT LIMITS
floor B1 B2/3 B8 A B4 B8 B Subtotal-1 floor B 13 Subtotal 75' ht limit 90' ht limit 125' Ht limit225' ht limit
11 17,000 11 178
10 30,000 10 162 130'-175'
9 30,000 9 146
8 30,000 8 94,738 PH(132) 130
7 30,000 18,594 7 94,738 114 114 90-130'
6 27,000 32,000 18,594 6 94,738 PH(98) 98 98
5 27,000 35,000 23,117 23,558 5 94,738 82 82 82
4 27,000 35,000 24,547 23,558 4 94,738 66 66 66 66
3 26,000 35,000 24,547 24,416 3 94,738 50 50 50 50
2 28,000 32,000 24,547 24,416 2 94,738 34 34 34 34
1 28,000 31,000 23,107 285,000 23,861 1 94,738 18 18 18 18
Area 300,000 200,000 119,865 285,000 156,997 1,061,862 Area 757,900 757,900
Rounding 3 3 3 3 3 3 Cars 2,309 2,309
300,000 200,000 119,000 285,000 156,000 1,061,000 Surface 38 2,347
TABLE-3: Proposed Parking
Building Area, sqft 1,061,862 1,061,862
Parking per 1000 GSF 1.55 2
Car Count 1,646 2,124
Note-1 : PH = 18'-0", Ground floor = 18'-0", Typical Floor = 16'-0"
Note-2 : Car Count Assumes 325 GSF per stall
7,500 GSF
11,000
GSF AVG
18,000
GSF AVG
B1 B2/3 B8 A B4 B8 B Subtotal-1 floor B 13 Subtotal 75' ht limit 90' ht limit 125' Ht limit225' ht limit
14 226 175-225'
13 210
12 194
17,564 11 178
29,243 10 162 130'-175'
29,243 9 146
29,243 8 94,738 PH(132) 130
29,243 34,200 34,200 18,594 7 94,738 114 114 90-130'
26,867 36,800 36,800 18,594 6 94,738 PH(98) 98 98
26,867 36,800 36,800 23,117 23,558 5 94,738 82 82 82
26,867 36,800 36,800 24,547 23,558 4 94,738 66 66 66 66
25,543 36,800 36,800 24,547 24,416 3 94,738 50 50 50 50
27,541 40,600 40,600 24,547 24,416 2 94,738 34 34 34 34
27,541 39,300 39,300 23,107 285,000 23,861 1 94,738 18 18 18 18
295,762 261,300 119,865 285,000 156,997 1,118,924 Area 757,900 757,900
g 3 2 3 3 3 3 Cars 2,309 2,309
2,332
295,000 261,300 261,300 119,000 285,000 156,000 1,118,000 Surface 38 2,347
: Proposed Parking
Building Area, sqft 1,118,924 1,118,924
Parking per 1000 GSF 1.55 2
Car Count 1,734 2,238
PH = 18'-0", Ground floor = 18'-0", Typical Floor = 16'-0"
Car Count Assumes 325 GSF per stall
7,500 GSF
AVG
11,000
GSF AVG
18,000
GSF AVG
STANFORDAVENUE
HOLLIS STREET
19'-0"
50'-6"
53'-0"
meryville Master Plan, Area Summary DRAFT
SUMMARY
1: BUILDING SQUARE FEET, GSF TABLE-2: PARKING PROVIDED, CAR COUNT HEIGHT LIMITS
B1 B2/3 B8 A B4 B8 B Subtotal-1 floor B 13 Subtotal 75' ht limit 90' ht limit 125' Ht limit225' ht limit
14 226 175-225'
13 210
12 194
17,564 11 178
29,243 10 162 130'-175'
29,243 9 146
29,243 8 94,738 PH(132) 130
29,243 34,200 34,200 18,594 7 94,738 114 114 90-130'
26,867 36,800 36,800 18,594 6 94,738 PH(98) 98 98
26,867 36,800 36,800 23,117 23,558 5 94,738 82 82 82
26,867 36,800 36,800 24,547 23,558 4 94,738 66 66 66 66
25,543 36,800 36,800 24,547 24,416 3 94,738 50 50 50 50
27,541 40,600 40,600 24,547 24,416 2 94,738 34 34 34 34
27,541 39,300 39,300 23,107 285,000 23,861 1 94,738 18 18 18 18
295,762 261,300 119,865 285,000 156,997 1,118,924 Area 757,900 757,900
ng 3 2 3 3 3 3 Cars 2,309 2,309
2,332
295,000 261,300 261,300 119,000 285,000 156,000 1,118,000 Surface 38 2,347
3: Proposed Parking
Building Area, sqft 1,118,924 1,118,924
Parking per 1000 GSF 1.55 2
Car Count 1,734 2,238
: PH = 18'-0", Ground floor = 18'-0", Typical Floor = 16'-0"
: Car Count Assumes 325 GSF per stall
7,500 GSF
AVG
11,000
GSF AVG
18,000
GSF AVG
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G022
Building Plans - B2/3
LEVEL 1 FLOOR PLAN
1
ROOF PLAN
3
TYPICAL FLOOR PLAN
2
LEGEND
MECHANICAL
BUILDING SUPPORT
R&D COLLABORATION
R&D OFFICE
R&D SUPPORT
R&D LAB
AMENITY
ROOF TERRACE
LOBBY
November 4, 2019 BMR EMERYVILLE CENTER OF INNOVATION
Building Images, Elevation - B1
A210
Building B2/3 East Elevation
ROOF
106'-3"106'-3"
ROOF
90'-3"
level 7
74'-3"
level 6
57'-6"
level 5
41'-6"
level 4
25'-6"
level 3
12'-9"
level 2
0'-0"
level 1
90'-3"
level 7
74'-3"
level 6
57'-6"
level 5
41'-6"
level 4
25'-6"
level 3
12'-9"
level 2
0'-0"
level 1
84'-4"
0'-0"
level 1
level 4
level 2
11'-4"
level 3
21'-6"
31'-8"
level 5
41'-10"
level 6
level 7
Roof
72'-4"
52'-0"
62'-2"
198'-0"
Top of Screen
Roof
178'-0"
level 11
162'-0"
146'-0"
level 10
130'-0"
level 9
level 8
level 7
114'-0"
98'-0"
82'-0"
level 6
level 5
66'-0"
50'-0"
level 4
34'-0"
level 3
0'-0"
level 1
18'-0"
level 2
Roof
98'-0"
82'-0"
level 6
level 5
66'-0"
50'-0"
level 4
34'-0"
level 3
0'-0"
level 1
18'-0"
level 2
114'-0"
Top of Screen
Top of Core
level 3
62'-2"
21'-6"
94'-6"
31'-8"
level 5
Top of Screen
Roof
level 8
41'-10"
Roof
level 7
level 6
98'-0"
114'-0"
130'-0"
0'-0"
level 1
82'-0"
level 6
level 5
66'-0"
50'-0"
level 4
level 4
34'-0"
level 7
level 3
0'-0"
level 1
18'-0"
level 2
72'-4"
level 2
11'-4"
52'-0"
Top of Core
82'-6"
November 4, 2019 BMR EMERYVILLE CENTER OF INNOVATION
Building Images, Elevation - B1
A210
Building B2/3 East Elevation
ROOF
106'-3"106'-3"
ROOF
90'-3"
level 7
74'-3"
level 6
57'-6"
level 5
41'-6"
level 4
25'-6"
level 3
12'-9"
level 2
0'-0"
level 1
90'-3"
level 7
74'-3"
level 6
57'-6"
level 5
41'-6"
level 4
25'-6"
level 3
12'-9"
level 2
0'-0"
level 1
84'-4"
0'-0"
level 1
level 4
level 2
11'-4"
level 3
21'-6"
31'-8"
level 5
41'-10"
level 6
level 7
Roof
72'-4"
52'-0"
62'-2"
198'-0"
Top of Screen
Roof
178'-0"
level 11
162'-0"
146'-0"
level 10
130'-0"
level 9
level 8
level 7
114'-0"
98'-0"
82'-0"
level 6
level 5
66'-0"
50'-0"
level 4
34'-0"
level 3
0'-0"
level 1
18'-0"
level 2
Roof
98'-0"
82'-0"
level 6
level 5
66'-0"
50'-0"
level 4
34'-0"
level 3
0'-0"
level 1
18'-0"
level 2
114'-0"
Top of Screen
Top of Core
level 3
62'-2"
21'-6"
94'-6"
31'-8"
level 5
Top of Screen
Roof
level 8
41'-10"
Roof
level 7
level 6
98'-0"
114'-0"
130'-0"
0'-0"
level 1
82'-0"
level 6
level 5
66'-0"
50'-0"
level 4
level 4
34'-0"
level 7
level 3
0'-0"
level 1
18'-0"
level 2
72'-4"
level 2
11'-4"
52'-0"
Top of Core
82'-6"
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G023
Building Images, Hollis Street Elevation - B2/3
0’ 16’ 32’ 64’
TERRACOTTA, GFRC, OR
MASONRY SCREEN WALL
HIGH PERFORMANCE
INSULATED GLAZING UNITS
LOW-IRON HIGH PERFORMANCE
INSULATED GLAZING UNITS
TERRACOTTA, v, OR MASONRY
PANEL RAINSCREEN
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G024
Building Images, Southeast View at Horton Street - B13/14
*Per South Bayfront Pedestrian Bicycle Bridge Project Overview, Emeryville City Council Meeting May 21, 2019
TO BRIDGE
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G025
Building Images, Southeast View at Horton Street - B13/14
PAINTED METAL PANEL
SYSTEM
EXPOSED CONCRETE
PAINTED PERFORATED
METAL SCREEN
SYSTEM
PAINTED METAL
GUARDRAIL
APPROX.170'-0"
44'-0"62'-0"
APPROX.180'-0"
62'-0"
248'-0"97'-0"
APPROX. 488'-0"
156'-0"
RAMP DN
RAMP UP
RAMP UP
RAMP DN
0 32 FT 64 FT
LEVEL 2-8 (TYPICAL)
245 SPACES
242'-0"
26'-0"26'-0"
10'-0"
10'-0"
150'-0"
150'-0"
240'-0"
FUTURE SHERWIN WILLIAMS DEVELOPMENT
PDUEASEMENT
HORTON STREET
RAMP UP
RAMP UP
TOSOUTHBAYFRONTBRIDGE
EOC
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G026
Building Plans - B13/14 (Parking)
LEVEL 1 FLOOR PLAN
1 * TBD
**
LONGTERM
BICYCLESTORAGE
TYPICAL FLOOR PLAN
2
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G027
Building Images, Horton Street Elevation - B13/14
level 3
62'-2"
21'-6"
94'-6"
31'-8"
level 5
Top of Screen
Roof
level 8
41'-10"
Roof
level 7
level 6
98'-0"
114'-0"
130'-0"
0'-0"
level 1
82'-0"
level 6
level 5
66'-0"
50'-0"
level 4
level 4
34'-0"
level 7
level 3
0'-0"
level 1
18'-0"
level 2
72'-4"
level 2
11'-4"
52'-0"
Top of Core
82'-6"
PAINTED PERFORATED METAL
SCREEN SYSTEM
EXPOSED CONCRETE
PAINTED METAL PANEL SYSTEM
PAINTED METAL GUARDRAIL
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G028
Shadow Studies
BMR PHASE 1 - WINTER SOLSTICE (DECEMBER 21) - 3PMPDP - WINTER SOLSTICE (DECEMBER 21) - 3PM
BMR PHASE 1 - WINTER SOLSTICE (DECEMBER 21) - 9AM
Note: No significant shading impact to adjacent new or proposed housing developments.
PDP - WINTER SOLSTICE (DECEMBER 21) - 9AM
HORTON STREET “FORMERLY LANDREGAN ST”
HORTON STREET
HOLLIS STREET
HOLLIS STREET
PELADEAU STREET
STANFORDAVENUE
HOLLIS STREET
STANFORDAVENUE
HOLLIS STREET
160'-0''
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G029
PDP Conformance - Overall Massing
Preliminary Design Plan
BMR Campus Vision
A tower of 225 ft will be allowed on the Building 1 site
The tower portion of the building is set back from Hollis Street by at least 160’ at the juncture of
Buildings 1 and 2 and from Stanford Avenue by 5-45 ft
The bulk of the tower shall diminish towards the top between 130 & 175 ft with a floor plate average
of 11,000 gross square feet
The proposed tower height is approximately 178 ft to the roof level, which is 47 ft less than the
allowable maximum height of 225 ft
With the revised street alignment of Holden Street (now Chiron Way), the required tower portion
setback (160 ft from Hollis Street) is no longer possible given the separate property ownership of the
parcel west of Chiron Way at Stanford Ave.
Typical floor plate size is approximately 29,000 SF, which is at the lower end of market-dictated floor
plate size for contemporary class-A institutional life science buildings. 11,000 GSF is not a viable floor
plate for contemporary life-science industry.
Street Arcade
Building Mass At Street Frontage
Street Arcade
Building Mass At Street Frontage
Levels Height* PDP Allowable Area*
1-6 0'-90' No Maximum
7-9 90'-130' Average 18,000 GSF
10 130'-145' Average 11,000 GSF
11 145’-160’ Average 11,000 GSF
12 160’-175’ Average 11,000 GSF
13-15 175-225 Average 7,500 GSF
Levels Height PDP Allowable Area* BMR Area
1-6 0'-90' No Maximum 28,000 GSF
7-9 90'-130' Average 18,000 GSF 30,000 GSF
10 130'-145' Average 11,000 GSF 30,000 GSF
11 145’-160’ Average 11,000 GSF 17,000 GSF
12 160’-175’ Average 11,000 GSF -
13-15 175-225 Average 7,500 GSF -
*Per Preliminary Development Plan Exhibit 5 & Appendix B
1
1
1
1
2
2
2
2
3
3
3
3
HORTON STREET “FORMERLY LANDREGAN ST”
HORTON STREET
HOLLIS STREET
HOLLIS STREET
PELADEAU STREET
STANFORDAVENUE
22'-0''
52'-0''
20'-0''
50'-0''
47'-0''
45'-0''
HOLLIS STREET
STANFORDAVENUE
45'-0''
55'-0''
75'-0''
50'-0''
50'-0''
45'-0''
5'-0''
80'-0''
160'-0''
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G030
BMR Campus Vision
PDP Conformance - Hollis Street Setbacks
Street Arcade
Building Mass At Street Frontage
Street Arcade
Building Mass At Street Frontage
Preliminary Design Plan
HORTON STREET “FORMERLY LANDREGAN ST”
HORTON STREET
HOLLIS STREET
HOLLIS STREET
PELADEAU STREET
STANFORDAVENUE
FUTURE BUILDING
FUTURE BUILDING
+194'
Top of Screen
+178'
Roof
+82'-6''
+94'-6” +94'-6”
+94'-6”
+178'
Top of Screen
+162'
Roof
+130'
Top of Screen
+114'
Roof
+114'
Roof
+34'
Roof
+98'
Roof
+162'
Roof
HOLLIS STREET
HOLLIS STREET
STANFORDAVENUE
+245'
+225'
+175'
+200'
+150'
+130'
+65'
+65'
+75'
+75'
+90'
+110'
+110'
+110'
+90'
+90'
+75'
+75'
+75'
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G031
PDP Conformance - Hollis Street Height Limits
Preliminary Design Plan
BMR Campus Vision
PROPOSED DESIGN
RELOCATED PDP MASSING
Hollis St
PDP
StanfordAve
Hollis St
StanfordAve
Hollis St
StanfordAve
PDP
VS. PROPOSED
+90’
+245’
+225’
+178’
Roof
+114’
0’ 25’ 50’ 100’0’ 25’ 50’ 100’
RELOCATED PDP MASSING
RELOCATED MASSING IN PROPOSED DESIGN
SCOPE
PDP ENTITLEMENT
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G032
PDP Conformance - Hollis Street Building Massing
Horton St
Horton St
Horton St
PROPOSED DESIGNPDP
RELOCATED PDP MASSING
+82’-6” +75’
PDP
VS. PROPOSED
0’ 25’ 50’ 100’0’ 25’ 50’ 100’
RELOCATED PDP MASSING
RELOCATED PDP MASSING IN PROPOSED DESIGN
SCOPE
PDP
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G033
PDP Conformance - Horton Street Building Massing
25’0’ 50’ 100’
Overall PDP Boundary*
Colonnade**
Grifols-Owned BuildingA0A
BMR-Owned Building
1995 PDP Massing*
A0A
PDP Proposed Service
Access***
50'
12'
55'
≤ 55% OVERALL
ENCROACHMENT
B3
≤ 55% OVERALL
ENCROACHMENT
B2
≤ 25% OVERALL
ENCROACHMENT
B1
75'
12'
5'
50'
160' MIN
TOWER SETBACK
12' 80'
45'
HORTON STREET
HORTON STREET BYPASS
HORTON STREET “FORMERLY LANDREGAN ST”
53RDSTREET
CHIRON WAY “FORMERLY HOLDEN ST”
HOLLIS STREET
SERVICE ACCESS
HOLLIS STREET
PELADEAU STREET
STANFORD
AVENUE
CHIRON WAY ALIGNMENT
B4 B3 B2 B1
B13 PDU B12B B12A
CMF
B6B7A
B8B9
B5
B10B11D
B7B
B14A
B14B
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G034
PDP Conformance - PDP Setbacks
*Per Preliminary Development Plan Figure 2-5 & 2-6
**Per Preliminary Development Plan Figure 2-21
***Per Preliminary Development Plan Exhibit 3
25’0’ 50’ 100’
Overall PDP Boundary*Grifols-Owned BuildingA0A
BMR-Owned Building
1995 PDP Massing*
A0A
Proposed FDP Massing
Relocated PDP Massing
Relocated Massing in
Proposed Design
FDP Service Access
Non-BMR Owned Properties
HORTON STREET
HORTON STREET “FORMERLY LANDREGAN ST”
53RDSTREET
CHIRON WAY “FORMERLY HOLDEN ST”
HOLLIS STREET
HOLLIS STREET
PELADEAU STREET
STANFORD
AVENUE
FUTUREPEDESTRIANBRIDGE
EXISTING CHIRON WAY
ALIGNMENT
47'
50'
20'
45'
160' MIN
TOWER SETBACK
60'
B4
(E)
B3
PROPOSED B2/3
PROPOSED B13/14
PROPOSED B1
B2
B1
B7
(E)
G
(E)
T
(E)
PDU
(E)
B13B14A
B14B
H
(E)
12A
(E)
CMF
(E)
F
(E)
R
(E)
Q
(E)
N
(E)
E
(E)
D
(E)
NON-BMR OWNED
PROPERTIES
NON-BMR OWNED
PROPERTIES
NON-BMR OWNED
PROPERTIES
March 4, 2020 EMERYVILLE CENTER OF INNOVATION G035
PDP Conformance - PDP & Proposed FDP Setback Comparison
*Per Preliminary Development Plan Figure 2-5 & 2-6
**Per Preliminary Development Plan Exhibit 3
March 4, 2020 EMERYVILLE CENTER OF INNOVATION L001
Context Of FDP Boundary
FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-002
Landscape Illustrative Plan B1 & B2/3
1’’=60’
FDP Boundary
53rdStreet
Chiron Way
Hollis Street
StanfordAvenue
B4
B2/3
B1
March 4, 2020 EMERYVILLE CENTER OF INNOVATION L002
Landscape Illustrative Plan B1 & B2/3
FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-003
Project Image - Chiron Way Shared Street Looking North
March 4, 2020 EMERYVILLE CENTER OF INNOVATION L003
Project Image - Chiron Way Shared Street Looking North
FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-004
Project Image - Plaza Looking South
March 4, 2020 EMERYVILLE CENTER OF INNOVATION L004
Project Image - Plaza Looking South
FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-005
Project Image - Plaza Looking North
March 4, 2020 EMERYVILLE CENTER OF INNOVATION L005
Project Image - Plaza Looking North
FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-006
Project Image - Paseo Looking Toward Chiron Way
March 4, 2020 EMERYVILLE CENTER OF INNOVATION L006
Project Image - Paseo Looking Toward Chiron Way
FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-007
Metal Walkway
Shade Structure / Pavilion
Paving
Built-In Furnishings
Moveable Furnishings
Built-In Furnishings
Materials Palette & Precedents
March 4, 2020 EMERYVILLE CENTER OF INNOVATION L007
Material Palette & Precedents
FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-008
(AC) Asphaltic Concrete (CUP) Concrete Unit Pavers -
Profile B
Tactile Warning Surfacing
(CIP) Cast In Place Concrete -
Profile A
Bike Rack
Metal - Type A
(CUP) Concrete Unit Pavers -
Profile A
Materials Plan B1 & B2/3
FDP Boundary
1’’=60’
LEGEND SCHEDULE
53rdStreet
Chiron Way
Hollis Street
StanfordAvenue
B4
B2/3
B1
March 4, 2020 EMERYVILLE CENTER OF INNOVATION L008
Materials Plan B1 & B2/3
March 4, 2020 EMERYVILLE CENTER OF INNOVATION L009
Preliminary Plant Palette & Precedents
March 4, 2020 EMERYVILLE CENTER OF INNOVATION L010
Preliminary Tree Palette & Precedents
FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-011
Planting Areas B1 & B2/3
1’’=60’
Planting - Type A
(Streetscape)
Planting - Type C
(Meadow)
Tree (Proposed)
Tree Box Size 36’’
Planting - Type B
(Shade)
Bio-Retention Planter Tree (Proposed)
Tree Box Size 24’’
Planting - Type D
(Pollinator)
FDP Boundary
LEGEND SCHEDULE
Tree (Proposed)
Tree Box Size 60’’
53rdStreet
Chiron Way
Hollis Street
StanfordAvenue
B4
B2/3
B1
March 4, 2020 EMERYVILLE CENTER OF INNOVATION L011
Planting Areas B1 & B2/3
FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-012
Hydrozone B1 & B2/3
Wucols - Very Low
Wucols - Low
1’’=60’
FDP Boundary
LEGEND SCHEDULE
53rdStreet
Chiron Way
Hollis Street
StanfordAvenue
B4
B2/3
B1
March 4, 2020 EMERYVILLE CENTER OF INNOVATION L012
Hydrozone B1 & B2/3
0 8 16 24 FT
FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-013
Landscape Sections: (Chiron Way)
B4 SIDEWALK SIDEWALK SIDEWALK
PLANTING
AREA
PLANTING
AREA
6’ 11’ 13’4’ 20’ 26’ 6’ 6’6’ 6’
SHARED ZONE SHARED ZONE
EXISTING
OPEN SPACE SIDEWALK BUILDING F (E)
Section A Section B
A B
PL PL
FDP Boundary
Property Line
BIO-RETENTION PLANTER
FDPFDP
March 4, 2020 EMERYVILLE CENTER OF INNOVATION L013
Landscape Sections: (Chiron Way)
0 8 16 24 FT
FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-014
Landscape Sections: (Chiron Way)
Section C Section D
C D
PLANTING
AREA PLAZA
6’ (VARIES) 17’ (VARIES) 3’ 20’ 12’3’
SHARED ZONE SIDEWALK BUILDING F (E)
TRUNCATED DOMESTRUNCATED DOMES TRUNCATED DOMES
PLAZA
PLANTING
AREA
3’ 26’10’ 6’ 6’
SHARED ZONE SIDEWALK BUILDING F (E)
LOADING/
DROP OFF
ZONE
PLPL FDPFDP
FDP Boundary
Property Line
March 4, 2020 EMERYVILLE CENTER OF INNOVATION L014
Landscape Sections: (Chiron Way)
0 8 16 24 FT
FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-015
Landscape Sections: (Chiron Way)
B1 LOADING B1 SIDEWALK SIDEWALK
6’ 3’14’ 20’ 20’3’ 6’ 3’ 6’
LOADING DOCK SHARED ZONE SHARED ZONEGRIFOLDS YARDSIDEWALK GRIFOLDS YARD
TRUNCATED DOMES
Section E Section F
EF
PL PL FDPFDP
TRUNCATED DOMES TRUNCATED DOMES
FDP Boundary
Property Line
March 4, 2020 EMERYVILLE CENTER OF INNOVATION L015
Landscape Sections: (Chiron Way)
0 8 16 24 FT
FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-016
Landscape Sections (Hollis Street, Standford Avenue)
G H
Section G Section H
B2/3 B2/3BIO-RETENTION PLANTER SIDEWALK BUILDING ENTRY
21’-9” (VARIES) 13’ (VARIES) 40’-7” (VARIES)5’-7”(VARIES) 5’-7”(VARIES) 10’
SHADE
GARDEN
PLANTING
AREA
PLANTING
AREAHOLLIS STREET
ROW ROW
HOLLIS STREET
PL PL FDPFDP
FDP Boundary
Property Line
March 4, 2020 EMERYVILLE CENTER OF INNOVATION L016
Landscape Sections: (Hollis Street, Stanford Avenue)
0 8 16 24 FT
FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-017
Landscape Sections (Hollis Street, Standford Avenue)
Section I Section J
I J
B1
BUILDING ENTRY
(METAL BRIDGE) BUILDING ENTRY
18’ (VARIES) 42’-9”37’-7” (VARIES) 12’ 10’ 17’-5” (VARIES)
PLANTING AREA (POLLINATOR) PLANTING AREA
HOLLIS
STREET
LOADING/
DROP OFF
ZONESIDEWALK
STANFORD
AVENUE
PL PLFDP FDP
FDP Boundary
Property Line
March 4, 2020 EMERYVILLE CENTER OF INNOVATION L017
Landscape Sections: (Hollis Street, Stanford Avenue)
0 8 16 24 FT
FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-018
Landscape Sections (Entry Garden Section, Paseo Section)
K
L
B1BIO-RETENTION PLANTER METAL BRIDGE PLANTING AREA (POLLINATOR)
38’-6” (varies) 15’-5” (varies) 24’-11” (varies) 8’-3” (varies) 7’(varies) 12’-7” (varies)
B2/3SHADE GARDEN
SHADE
GARDEN PASEO
Section K Section L
FDP
FDP Boundary
March 4, 2020 EMERYVILLE CENTER OF INNOVATION L018
Landscape Sections: (Entry Garden Section, Paseo Section)
36 FT
0 8 16 FT
0 12 24
FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-019
Landscape Sections (Plaza)
M
N
Section M
Section N
FDP PL
PL
FDP Boundary
Property Line
36 FT
0 8 16 FT
0 12 24
FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-019
Landscape Sections (Plaza)
M
N
Section M
Section N
FDP PL
PL
FDP Boundary
Property Line
March 4, 2020 EMERYVILLE CENTER OF INNOVATION L019
Landscape Sections: (Plaza)

More Related Content

What's hot

Ever growing amman, jordan_urban expansion social polarisation and contempora...
Ever growing amman, jordan_urban expansion social polarisation and contempora...Ever growing amman, jordan_urban expansion social polarisation and contempora...
Ever growing amman, jordan_urban expansion social polarisation and contempora...
Dania Abdel-aziz
 
Denver art museum_ Daniel Libeskind
Denver art museum_ Daniel LibeskindDenver art museum_ Daniel Libeskind
Denver art museum_ Daniel Libeskind
Composicio 3 Tarda
 
Biomimetic architecture
Biomimetic architectureBiomimetic architecture
Biomimetic architecture
nada khaled
 
Mahidnra World City, Jaipur
Mahidnra World City, JaipurMahidnra World City, Jaipur
Mahidnra World City, Jaipur
Konark Realspace Pvt. Ltd.
 
THE EDGE, Amsterdam
THE EDGE, AmsterdamTHE EDGE, Amsterdam
THE EDGE, Amsterdam
JazibAhmed7
 
Matrimandir
MatrimandirMatrimandir
Matrimandir
Manipal University
 
Tadao ando
Tadao andoTadao ando
Tadao ando
Soumya Bhatia
 
Vernacular architecture of Nalwar Yadgir district
Vernacular architecture of Nalwar Yadgir districtVernacular architecture of Nalwar Yadgir district
Vernacular architecture of Nalwar Yadgir district
Tanzil Faraz
 
Building Technology 1 Construction Solutions Report
Building Technology 1 Construction Solutions ReportBuilding Technology 1 Construction Solutions Report
Building Technology 1 Construction Solutions Report
douglasloon
 
harar architecture re
harar architecture reharar architecture re
harar architecture re
anteneh mezgebu
 
Sustainable Office Buildings
Sustainable Office BuildingsSustainable Office Buildings
Sustainable Office Buildings
Rohan Narvekar
 
Historic Re-enactment With Modern Interpretation (Thesis Report)
Historic Re-enactment With Modern Interpretation (Thesis Report)Historic Re-enactment With Modern Interpretation (Thesis Report)
Historic Re-enactment With Modern Interpretation (Thesis Report)
Divya Bhaskara
 
النظم الانشائية structure systems.pdf
النظم الانشائية structure systems.pdfالنظم الانشائية structure systems.pdf
النظم الانشائية structure systems.pdf
SohirShoky
 
Raj rewal
Raj rewal Raj rewal
Raj rewal
Ankush Bharti
 
Church of light
 Church of light   Church of light
Church of light
Simran Rattan
 
Jordanian vernacular architecture
Jordanian vernacular architecture Jordanian vernacular architecture
Jordanian vernacular architecture
Dania Abdel-aziz
 
Harvard University
Harvard UniversityHarvard University
Harvard University
Akash Matthew
 
BedZED1
BedZED1BedZED1
Folded plates
Folded platesFolded plates
Folded plates
Rohan Narvekar
 
RAJ REWAL WORKS
RAJ REWAL WORKSRAJ REWAL WORKS
RAJ REWAL WORKS
Chaitanya Satpute
 

What's hot (20)

Ever growing amman, jordan_urban expansion social polarisation and contempora...
Ever growing amman, jordan_urban expansion social polarisation and contempora...Ever growing amman, jordan_urban expansion social polarisation and contempora...
Ever growing amman, jordan_urban expansion social polarisation and contempora...
 
Denver art museum_ Daniel Libeskind
Denver art museum_ Daniel LibeskindDenver art museum_ Daniel Libeskind
Denver art museum_ Daniel Libeskind
 
Biomimetic architecture
Biomimetic architectureBiomimetic architecture
Biomimetic architecture
 
Mahidnra World City, Jaipur
Mahidnra World City, JaipurMahidnra World City, Jaipur
Mahidnra World City, Jaipur
 
THE EDGE, Amsterdam
THE EDGE, AmsterdamTHE EDGE, Amsterdam
THE EDGE, Amsterdam
 
Matrimandir
MatrimandirMatrimandir
Matrimandir
 
Tadao ando
Tadao andoTadao ando
Tadao ando
 
Vernacular architecture of Nalwar Yadgir district
Vernacular architecture of Nalwar Yadgir districtVernacular architecture of Nalwar Yadgir district
Vernacular architecture of Nalwar Yadgir district
 
Building Technology 1 Construction Solutions Report
Building Technology 1 Construction Solutions ReportBuilding Technology 1 Construction Solutions Report
Building Technology 1 Construction Solutions Report
 
harar architecture re
harar architecture reharar architecture re
harar architecture re
 
Sustainable Office Buildings
Sustainable Office BuildingsSustainable Office Buildings
Sustainable Office Buildings
 
Historic Re-enactment With Modern Interpretation (Thesis Report)
Historic Re-enactment With Modern Interpretation (Thesis Report)Historic Re-enactment With Modern Interpretation (Thesis Report)
Historic Re-enactment With Modern Interpretation (Thesis Report)
 
النظم الانشائية structure systems.pdf
النظم الانشائية structure systems.pdfالنظم الانشائية structure systems.pdf
النظم الانشائية structure systems.pdf
 
Raj rewal
Raj rewal Raj rewal
Raj rewal
 
Church of light
 Church of light   Church of light
Church of light
 
Jordanian vernacular architecture
Jordanian vernacular architecture Jordanian vernacular architecture
Jordanian vernacular architecture
 
Harvard University
Harvard UniversityHarvard University
Harvard University
 
BedZED1
BedZED1BedZED1
BedZED1
 
Folded plates
Folded platesFolded plates
Folded plates
 
RAJ REWAL WORKS
RAJ REWAL WORKSRAJ REWAL WORKS
RAJ REWAL WORKS
 

Similar to Biomed realty-emeryville-center-innovation

DESIGN STUDIO III ARCP 301R. Belton, AIA, NOMA, CSI Associates.docx
DESIGN STUDIO III ARCP 301R. Belton, AIA, NOMA, CSI Associates.docxDESIGN STUDIO III ARCP 301R. Belton, AIA, NOMA, CSI Associates.docx
DESIGN STUDIO III ARCP 301R. Belton, AIA, NOMA, CSI Associates.docx
carolinef5
 
Linkedin
LinkedinLinkedin
Oberoi Hotel
Oberoi HotelOberoi Hotel
Oberoi Hotel
Scott Campbell
 
CMAA OHare and Midway International Airports Capital Improvement Program
CMAA OHare and Midway International Airports Capital Improvement ProgramCMAA OHare and Midway International Airports Capital Improvement Program
CMAA OHare and Midway International Airports Capital Improvement Program
Ausrine Rakauskaite
 
Singular Projects Gibraltar
Singular Projects GibraltarSingular Projects Gibraltar
Singular Projects Gibraltar
Manuel Cabello de Alba
 
Brouches of Jaypee Green
Brouches of Jaypee GreenBrouches of Jaypee Green
Brouches of Jaypee Green
Rakesh Agarwal
 
ExtremePita-Cover
ExtremePita-CoverExtremePita-Cover
ExtremePita-Cover
Stephen Bryce Liebert, AIA
 
Town planning report northroad 20121210 a
Town planning report northroad 20121210 aTown planning report northroad 20121210 a
Town planning report northroad 20121210 a
Anne Kim
 
Singular Projects Gibraltar
Singular Projects GibraltarSingular Projects Gibraltar
Singular Projects Gibraltar
Manuel Cabello de Alba
 
City of orlando db colonial ped overpass technical
City of orlando db colonial ped overpass   technicalCity of orlando db colonial ped overpass   technical
City of orlando db colonial ped overpass technical
Brendan O'Connor
 
Building economics final assignment report
Building economics final assignment reportBuilding economics final assignment report
Building economics final assignment report
lucaschinsheng
 
Item # 6 - 820 Cambridge Oval
Item # 6 - 820 Cambridge OvalItem # 6 - 820 Cambridge Oval
Item # 6 - 820 Cambridge Oval
ahcitycouncil
 
Jll Presentation Cpa And Bohler Arch And Laser Scanning
Jll Presentation Cpa And Bohler Arch And Laser ScanningJll Presentation Cpa And Bohler Arch And Laser Scanning
Jll Presentation Cpa And Bohler Arch And Laser Scanning
RICHBUTKUS
 
Public Safety Headquarters
Public Safety HeadquartersPublic Safety Headquarters
Public Safety Headquarters
Fairfax County
 
James Ingle's Technology Portfolio
James Ingle's Technology PortfolioJames Ingle's Technology Portfolio
James Ingle's Technology Portfolio
James Ingle
 
Resume_SOl_2016
Resume_SOl_2016Resume_SOl_2016
Resume_SOl_2016
Sean O' Leary
 
Resume_SOl_2016
Resume_SOl_2016Resume_SOl_2016
Resume_SOl_2016
Sean O' Leary
 
Resume sol_2016
Resume sol_2016Resume sol_2016
Resume sol_2016
Sean O' Leary
 
Pipes and Plaits in Ark Mode Design V2 and V3 Glass Warehouse and Title
Pipes and Plaits in Ark Mode Design V2 and V3 Glass Warehouse and TitlePipes and Plaits in Ark Mode Design V2 and V3 Glass Warehouse and Title
Pipes and Plaits in Ark Mode Design V2 and V3 Glass Warehouse and Title
Brij Consulting, LLC
 
Industry Model Answers
Industry Model AnswersIndustry Model Answers
Industry Model Answers
neilgood
 

Similar to Biomed realty-emeryville-center-innovation (20)

DESIGN STUDIO III ARCP 301R. Belton, AIA, NOMA, CSI Associates.docx
DESIGN STUDIO III ARCP 301R. Belton, AIA, NOMA, CSI Associates.docxDESIGN STUDIO III ARCP 301R. Belton, AIA, NOMA, CSI Associates.docx
DESIGN STUDIO III ARCP 301R. Belton, AIA, NOMA, CSI Associates.docx
 
Linkedin
LinkedinLinkedin
Linkedin
 
Oberoi Hotel
Oberoi HotelOberoi Hotel
Oberoi Hotel
 
CMAA OHare and Midway International Airports Capital Improvement Program
CMAA OHare and Midway International Airports Capital Improvement ProgramCMAA OHare and Midway International Airports Capital Improvement Program
CMAA OHare and Midway International Airports Capital Improvement Program
 
Singular Projects Gibraltar
Singular Projects GibraltarSingular Projects Gibraltar
Singular Projects Gibraltar
 
Brouches of Jaypee Green
Brouches of Jaypee GreenBrouches of Jaypee Green
Brouches of Jaypee Green
 
ExtremePita-Cover
ExtremePita-CoverExtremePita-Cover
ExtremePita-Cover
 
Town planning report northroad 20121210 a
Town planning report northroad 20121210 aTown planning report northroad 20121210 a
Town planning report northroad 20121210 a
 
Singular Projects Gibraltar
Singular Projects GibraltarSingular Projects Gibraltar
Singular Projects Gibraltar
 
City of orlando db colonial ped overpass technical
City of orlando db colonial ped overpass   technicalCity of orlando db colonial ped overpass   technical
City of orlando db colonial ped overpass technical
 
Building economics final assignment report
Building economics final assignment reportBuilding economics final assignment report
Building economics final assignment report
 
Item # 6 - 820 Cambridge Oval
Item # 6 - 820 Cambridge OvalItem # 6 - 820 Cambridge Oval
Item # 6 - 820 Cambridge Oval
 
Jll Presentation Cpa And Bohler Arch And Laser Scanning
Jll Presentation Cpa And Bohler Arch And Laser ScanningJll Presentation Cpa And Bohler Arch And Laser Scanning
Jll Presentation Cpa And Bohler Arch And Laser Scanning
 
Public Safety Headquarters
Public Safety HeadquartersPublic Safety Headquarters
Public Safety Headquarters
 
James Ingle's Technology Portfolio
James Ingle's Technology PortfolioJames Ingle's Technology Portfolio
James Ingle's Technology Portfolio
 
Resume_SOl_2016
Resume_SOl_2016Resume_SOl_2016
Resume_SOl_2016
 
Resume_SOl_2016
Resume_SOl_2016Resume_SOl_2016
Resume_SOl_2016
 
Resume sol_2016
Resume sol_2016Resume sol_2016
Resume sol_2016
 
Pipes and Plaits in Ark Mode Design V2 and V3 Glass Warehouse and Title
Pipes and Plaits in Ark Mode Design V2 and V3 Glass Warehouse and TitlePipes and Plaits in Ark Mode Design V2 and V3 Glass Warehouse and Title
Pipes and Plaits in Ark Mode Design V2 and V3 Glass Warehouse and Title
 
Industry Model Answers
Industry Model AnswersIndustry Model Answers
Industry Model Answers
 

More from E'ville Eye

legal-Complaint-emery-unified-assault.pdf
legal-Complaint-emery-unified-assault.pdflegal-Complaint-emery-unified-assault.pdf
legal-Complaint-emery-unified-assault.pdf
E'ville Eye
 
EUSD Superintendent Goals 2021-2023.pdf
EUSD Superintendent Goals 2021-2023.pdfEUSD Superintendent Goals 2021-2023.pdf
EUSD Superintendent Goals 2021-2023.pdf
E'ville Eye
 
SeaWallsMap-UPDATE.pdf
SeaWallsMap-UPDATE.pdfSeaWallsMap-UPDATE.pdf
SeaWallsMap-UPDATE.pdf
E'ville Eye
 
EGR-WOAK_BART_Preso_1024.pdf
EGR-WOAK_BART_Preso_1024.pdfEGR-WOAK_BART_Preso_1024.pdf
EGR-WOAK_BART_Preso_1024.pdf
E'ville Eye
 
City of Emeryville 2023-2031 Housing Element [Public Draft]
City of Emeryville 2023-2031 Housing Element [Public Draft]City of Emeryville 2023-2031 Housing Element [Public Draft]
City of Emeryville 2023-2031 Housing Element [Public Draft]
E'ville Eye
 
Wood Street Engagement Sessions FAQ.pdf
Wood Street Engagement Sessions FAQ.pdfWood Street Engagement Sessions FAQ.pdf
Wood Street Engagement Sessions FAQ.pdf
E'ville Eye
 
Item 9.2 bay street emeryville grocery store staff report
Item 9.2 bay street emeryville grocery store staff reportItem 9.2 bay street emeryville grocery store staff report
Item 9.2 bay street emeryville grocery store staff report
E'ville Eye
 
2021 Emeryville Special Election Petition
2021 Emeryville Special Election Petition2021 Emeryville Special Election Petition
2021 Emeryville Special Election Petition
E'ville Eye
 
Wdwg press packet
Wdwg press packetWdwg press packet
Wdwg press packet
E'ville Eye
 
8 6 updated_reopeningschoolsdata_0
8 6 updated_reopeningschoolsdata_08 6 updated_reopeningschoolsdata_0
8 6 updated_reopeningschoolsdata_0
E'ville Eye
 
History and Innovation in Emeryville
History and Innovation in EmeryvilleHistory and Innovation in Emeryville
History and Innovation in Emeryville
E'ville Eye
 
Onni deemed withdrawn letter 07 22-20
Onni deemed withdrawn letter 07 22-20Onni deemed withdrawn letter 07 22-20
Onni deemed withdrawn letter 07 22-20
E'ville Eye
 
Item 7.1 art center study session
Item 7.1   art center study sessionItem 7.1   art center study session
Item 7.1 art center study session
E'ville Eye
 
Lpas rcs-3600-san-pablo
Lpas rcs-3600-san-pabloLpas rcs-3600-san-pablo
Lpas rcs-3600-san-pablo
E'ville Eye
 
Tejada retirement notice
Tejada retirement noticeTejada retirement notice
Tejada retirement notice
E'ville Eye
 
Fy 2019 21 mid-cycle budget review 5-14-2020
Fy 2019 21 mid-cycle budget review 5-14-2020Fy 2019 21 mid-cycle budget review 5-14-2020
Fy 2019 21 mid-cycle budget review 5-14-2020
E'ville Eye
 
2020.03.19 covid-19 emergency rental assistance program
2020.03.19   covid-19 emergency rental assistance program2020.03.19   covid-19 emergency rental assistance program
2020.03.19 covid-19 emergency rental assistance program
E'ville Eye
 
Dec 3 2019 cc meeting proposed sales tax measure
Dec 3 2019 cc meeting   proposed sales tax measureDec 3 2019 cc meeting   proposed sales tax measure
Dec 3 2019 cc meeting proposed sales tax measure
E'ville Eye
 
Ac fr ogdxe1o77gyvrw6rruvtw7lusdahpeh-u_k0fz0g0qzdx80n9wtveg4_p2c17d1b-r2m4zv...
Ac fr ogdxe1o77gyvrw6rruvtw7lusdahpeh-u_k0fz0g0qzdx80n9wtveg4_p2c17d1b-r2m4zv...Ac fr ogdxe1o77gyvrw6rruvtw7lusdahpeh-u_k0fz0g0qzdx80n9wtveg4_p2c17d1b-r2m4zv...
Ac fr ogdxe1o77gyvrw6rruvtw7lusdahpeh-u_k0fz0g0qzdx80n9wtveg4_p2c17d1b-r2m4zv...
E'ville Eye
 
2010 10 14_bay_bridge_report_v5_d
2010 10 14_bay_bridge_report_v5_d2010 10 14_bay_bridge_report_v5_d
2010 10 14_bay_bridge_report_v5_d
E'ville Eye
 

More from E'ville Eye (20)

legal-Complaint-emery-unified-assault.pdf
legal-Complaint-emery-unified-assault.pdflegal-Complaint-emery-unified-assault.pdf
legal-Complaint-emery-unified-assault.pdf
 
EUSD Superintendent Goals 2021-2023.pdf
EUSD Superintendent Goals 2021-2023.pdfEUSD Superintendent Goals 2021-2023.pdf
EUSD Superintendent Goals 2021-2023.pdf
 
SeaWallsMap-UPDATE.pdf
SeaWallsMap-UPDATE.pdfSeaWallsMap-UPDATE.pdf
SeaWallsMap-UPDATE.pdf
 
EGR-WOAK_BART_Preso_1024.pdf
EGR-WOAK_BART_Preso_1024.pdfEGR-WOAK_BART_Preso_1024.pdf
EGR-WOAK_BART_Preso_1024.pdf
 
City of Emeryville 2023-2031 Housing Element [Public Draft]
City of Emeryville 2023-2031 Housing Element [Public Draft]City of Emeryville 2023-2031 Housing Element [Public Draft]
City of Emeryville 2023-2031 Housing Element [Public Draft]
 
Wood Street Engagement Sessions FAQ.pdf
Wood Street Engagement Sessions FAQ.pdfWood Street Engagement Sessions FAQ.pdf
Wood Street Engagement Sessions FAQ.pdf
 
Item 9.2 bay street emeryville grocery store staff report
Item 9.2 bay street emeryville grocery store staff reportItem 9.2 bay street emeryville grocery store staff report
Item 9.2 bay street emeryville grocery store staff report
 
2021 Emeryville Special Election Petition
2021 Emeryville Special Election Petition2021 Emeryville Special Election Petition
2021 Emeryville Special Election Petition
 
Wdwg press packet
Wdwg press packetWdwg press packet
Wdwg press packet
 
8 6 updated_reopeningschoolsdata_0
8 6 updated_reopeningschoolsdata_08 6 updated_reopeningschoolsdata_0
8 6 updated_reopeningschoolsdata_0
 
History and Innovation in Emeryville
History and Innovation in EmeryvilleHistory and Innovation in Emeryville
History and Innovation in Emeryville
 
Onni deemed withdrawn letter 07 22-20
Onni deemed withdrawn letter 07 22-20Onni deemed withdrawn letter 07 22-20
Onni deemed withdrawn letter 07 22-20
 
Item 7.1 art center study session
Item 7.1   art center study sessionItem 7.1   art center study session
Item 7.1 art center study session
 
Lpas rcs-3600-san-pablo
Lpas rcs-3600-san-pabloLpas rcs-3600-san-pablo
Lpas rcs-3600-san-pablo
 
Tejada retirement notice
Tejada retirement noticeTejada retirement notice
Tejada retirement notice
 
Fy 2019 21 mid-cycle budget review 5-14-2020
Fy 2019 21 mid-cycle budget review 5-14-2020Fy 2019 21 mid-cycle budget review 5-14-2020
Fy 2019 21 mid-cycle budget review 5-14-2020
 
2020.03.19 covid-19 emergency rental assistance program
2020.03.19   covid-19 emergency rental assistance program2020.03.19   covid-19 emergency rental assistance program
2020.03.19 covid-19 emergency rental assistance program
 
Dec 3 2019 cc meeting proposed sales tax measure
Dec 3 2019 cc meeting   proposed sales tax measureDec 3 2019 cc meeting   proposed sales tax measure
Dec 3 2019 cc meeting proposed sales tax measure
 
Ac fr ogdxe1o77gyvrw6rruvtw7lusdahpeh-u_k0fz0g0qzdx80n9wtveg4_p2c17d1b-r2m4zv...
Ac fr ogdxe1o77gyvrw6rruvtw7lusdahpeh-u_k0fz0g0qzdx80n9wtveg4_p2c17d1b-r2m4zv...Ac fr ogdxe1o77gyvrw6rruvtw7lusdahpeh-u_k0fz0g0qzdx80n9wtveg4_p2c17d1b-r2m4zv...
Ac fr ogdxe1o77gyvrw6rruvtw7lusdahpeh-u_k0fz0g0qzdx80n9wtveg4_p2c17d1b-r2m4zv...
 
2010 10 14_bay_bridge_report_v5_d
2010 10 14_bay_bridge_report_v5_d2010 10 14_bay_bridge_report_v5_d
2010 10 14_bay_bridge_report_v5_d
 

Recently uploaded

PPT Item # 5 - 318 Tuxedo Ave. (sign. review)
PPT Item # 5 - 318 Tuxedo Ave. (sign. review)PPT Item # 5 - 318 Tuxedo Ave. (sign. review)
PPT Item # 5 - 318 Tuxedo Ave. (sign. review)
ahcitycouncil
 
2024: The FAR - Federal Acquisition Regulations, Part 42
2024: The FAR - Federal Acquisition Regulations, Part 422024: The FAR - Federal Acquisition Regulations, Part 42
2024: The FAR - Federal Acquisition Regulations, Part 42
JSchaus & Associates
 
How To Cultivate Community Affinity Throughout The Generosity Journey
How To Cultivate Community Affinity Throughout The Generosity JourneyHow To Cultivate Community Affinity Throughout The Generosity Journey
How To Cultivate Community Affinity Throughout The Generosity Journey
Aggregage
 
G7 Apulia Leaders Communique, June 2024 (1).pdf
G7 Apulia Leaders Communique, June 2024 (1).pdfG7 Apulia Leaders Communique, June 2024 (1).pdf
G7 Apulia Leaders Communique, June 2024 (1).pdf
Energy for One World
 
Border towns and spaces of (in)visibility.pdf
Border towns and spaces of (in)visibility.pdfBorder towns and spaces of (in)visibility.pdf
Border towns and spaces of (in)visibility.pdf
Scalabrini Institute for Human Mobility in Africa
 
原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样
原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样
原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样
3woawyyl
 
TRUE BOOK OF LIFE 1.15 OF TRUE JESUS CHRIST
TRUE BOOK OF LIFE 1.15 OF TRUE JESUS CHRISTTRUE BOOK OF LIFE 1.15 OF TRUE JESUS CHRIST
TRUE BOOK OF LIFE 1.15 OF TRUE JESUS CHRIST
Cheong Man Keong
 
在线办理(西班牙UPV毕业证书)瓦伦西亚理工大学毕业证毕业完成信一模一样
在线办理(西班牙UPV毕业证书)瓦伦西亚理工大学毕业证毕业完成信一模一样在线办理(西班牙UPV毕业证书)瓦伦西亚理工大学毕业证毕业完成信一模一样
在线办理(西班牙UPV毕业证书)瓦伦西亚理工大学毕业证毕业完成信一模一样
dj1cx4ex
 
karnataka housing board schemes . all schemes
karnataka housing board schemes . all schemeskarnataka housing board schemes . all schemes
karnataka housing board schemes . all schemes
narinav14
 
在线办理(英国UEA毕业证书)东英格利亚大学毕业证成绩单一模一样
在线办理(英国UEA毕业证书)东英格利亚大学毕业证成绩单一模一样在线办理(英国UEA毕业证书)东英格利亚大学毕业证成绩单一模一样
在线办理(英国UEA毕业证书)东英格利亚大学毕业证成绩单一模一样
3woawyyl
 
原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样
原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样
原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样
ii2sh2v
 
一比一原版英国阿伯丁大学毕业证(AU毕业证书)学历如何办理
一比一原版英国阿伯丁大学毕业证(AU毕业证书)学历如何办理一比一原版英国阿伯丁大学毕业证(AU毕业证书)学历如何办理
一比一原版英国阿伯丁大学毕业证(AU毕业证书)学历如何办理
afsebu
 
Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019
Partito democratico
 
一比一原版(Adelaide毕业证)阿德莱德大学毕业证如何办理
一比一原版(Adelaide毕业证)阿德莱德大学毕业证如何办理一比一原版(Adelaide毕业证)阿德莱德大学毕业证如何办理
一比一原版(Adelaide毕业证)阿德莱德大学毕业证如何办理
teeaszt
 
Indira awas yojana housing scheme renamed as PMAY
Indira awas yojana housing scheme renamed as PMAYIndira awas yojana housing scheme renamed as PMAY
Indira awas yojana housing scheme renamed as PMAY
narinav14
 
快速办理(Bristol毕业证书)布里斯托大学毕业证Offer一模一样
快速办理(Bristol毕业证书)布里斯托大学毕业证Offer一模一样快速办理(Bristol毕业证书)布里斯托大学毕业证Offer一模一样
快速办理(Bristol毕业证书)布里斯托大学毕业证Offer一模一样
3woawyyl
 
G7 Apulia Leaders Communique, 14th June 2024
G7 Apulia Leaders Communique, 14th June 2024G7 Apulia Leaders Communique, 14th June 2024
G7 Apulia Leaders Communique, 14th June 2024
Energy for One World
 
PPT Item # 4 - 434 College Blvd. (sign. review)
PPT Item # 4 - 434 College Blvd. (sign. review)PPT Item # 4 - 434 College Blvd. (sign. review)
PPT Item # 4 - 434 College Blvd. (sign. review)
ahcitycouncil
 
Item # 10 -- Historical Presv. Districts
Item # 10 -- Historical Presv. DistrictsItem # 10 -- Historical Presv. Districts
Item # 10 -- Historical Presv. Districts
ahcitycouncil
 
2024: The FAR - Federal Acquisition Regulations, Part 40
2024: The FAR - Federal Acquisition Regulations, Part 402024: The FAR - Federal Acquisition Regulations, Part 40
2024: The FAR - Federal Acquisition Regulations, Part 40
JSchaus & Associates
 

Recently uploaded (20)

PPT Item # 5 - 318 Tuxedo Ave. (sign. review)
PPT Item # 5 - 318 Tuxedo Ave. (sign. review)PPT Item # 5 - 318 Tuxedo Ave. (sign. review)
PPT Item # 5 - 318 Tuxedo Ave. (sign. review)
 
2024: The FAR - Federal Acquisition Regulations, Part 42
2024: The FAR - Federal Acquisition Regulations, Part 422024: The FAR - Federal Acquisition Regulations, Part 42
2024: The FAR - Federal Acquisition Regulations, Part 42
 
How To Cultivate Community Affinity Throughout The Generosity Journey
How To Cultivate Community Affinity Throughout The Generosity JourneyHow To Cultivate Community Affinity Throughout The Generosity Journey
How To Cultivate Community Affinity Throughout The Generosity Journey
 
G7 Apulia Leaders Communique, June 2024 (1).pdf
G7 Apulia Leaders Communique, June 2024 (1).pdfG7 Apulia Leaders Communique, June 2024 (1).pdf
G7 Apulia Leaders Communique, June 2024 (1).pdf
 
Border towns and spaces of (in)visibility.pdf
Border towns and spaces of (in)visibility.pdfBorder towns and spaces of (in)visibility.pdf
Border towns and spaces of (in)visibility.pdf
 
原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样
原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样
原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样
 
TRUE BOOK OF LIFE 1.15 OF TRUE JESUS CHRIST
TRUE BOOK OF LIFE 1.15 OF TRUE JESUS CHRISTTRUE BOOK OF LIFE 1.15 OF TRUE JESUS CHRIST
TRUE BOOK OF LIFE 1.15 OF TRUE JESUS CHRIST
 
在线办理(西班牙UPV毕业证书)瓦伦西亚理工大学毕业证毕业完成信一模一样
在线办理(西班牙UPV毕业证书)瓦伦西亚理工大学毕业证毕业完成信一模一样在线办理(西班牙UPV毕业证书)瓦伦西亚理工大学毕业证毕业完成信一模一样
在线办理(西班牙UPV毕业证书)瓦伦西亚理工大学毕业证毕业完成信一模一样
 
karnataka housing board schemes . all schemes
karnataka housing board schemes . all schemeskarnataka housing board schemes . all schemes
karnataka housing board schemes . all schemes
 
在线办理(英国UEA毕业证书)东英格利亚大学毕业证成绩单一模一样
在线办理(英国UEA毕业证书)东英格利亚大学毕业证成绩单一模一样在线办理(英国UEA毕业证书)东英格利亚大学毕业证成绩单一模一样
在线办理(英国UEA毕业证书)东英格利亚大学毕业证成绩单一模一样
 
原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样
原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样
原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样
 
一比一原版英国阿伯丁大学毕业证(AU毕业证书)学历如何办理
一比一原版英国阿伯丁大学毕业证(AU毕业证书)学历如何办理一比一原版英国阿伯丁大学毕业证(AU毕业证书)学历如何办理
一比一原版英国阿伯丁大学毕业证(AU毕业证书)学历如何办理
 
Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019
 
一比一原版(Adelaide毕业证)阿德莱德大学毕业证如何办理
一比一原版(Adelaide毕业证)阿德莱德大学毕业证如何办理一比一原版(Adelaide毕业证)阿德莱德大学毕业证如何办理
一比一原版(Adelaide毕业证)阿德莱德大学毕业证如何办理
 
Indira awas yojana housing scheme renamed as PMAY
Indira awas yojana housing scheme renamed as PMAYIndira awas yojana housing scheme renamed as PMAY
Indira awas yojana housing scheme renamed as PMAY
 
快速办理(Bristol毕业证书)布里斯托大学毕业证Offer一模一样
快速办理(Bristol毕业证书)布里斯托大学毕业证Offer一模一样快速办理(Bristol毕业证书)布里斯托大学毕业证Offer一模一样
快速办理(Bristol毕业证书)布里斯托大学毕业证Offer一模一样
 
G7 Apulia Leaders Communique, 14th June 2024
G7 Apulia Leaders Communique, 14th June 2024G7 Apulia Leaders Communique, 14th June 2024
G7 Apulia Leaders Communique, 14th June 2024
 
PPT Item # 4 - 434 College Blvd. (sign. review)
PPT Item # 4 - 434 College Blvd. (sign. review)PPT Item # 4 - 434 College Blvd. (sign. review)
PPT Item # 4 - 434 College Blvd. (sign. review)
 
Item # 10 -- Historical Presv. Districts
Item # 10 -- Historical Presv. DistrictsItem # 10 -- Historical Presv. Districts
Item # 10 -- Historical Presv. Districts
 
2024: The FAR - Federal Acquisition Regulations, Part 40
2024: The FAR - Federal Acquisition Regulations, Part 402024: The FAR - Federal Acquisition Regulations, Part 40
2024: The FAR - Federal Acquisition Regulations, Part 40
 

Biomed realty-emeryville-center-innovation

  • 2.
  • 3. March 4, 2020 EMERYVILLE CENTER OF INNOVATION G000 EMERYVILLE CENTER OF INNOVATIONFlad Project Number BMR CAMPUS VISION19396-05 PROJECT DESCRIPTION PROJECT TEAM SHEET INDEX LOCATION MAP VICINITY MAP LAND USE PROGRAM The proposed FDP area includes approximately 6.31 acres situated at the intersection of Hollis and Stanford Streets, and Horton and 53rd Streets in Emeryville, California. The FDP proposes to develop the area of Buildings 1, 2, 3, 13 and 14 identified in Figure 2-5 of the PDP, to accommodate research, development and small- scale manufacturing, production-scale manufacturing, administration, and mechanical and utility spaces. The building and landscaping design are intended to establish the Emeryville Center of Innovation as a cohesive, modern life science campus for the 21st century. PROJECT DESCRIPTION The proposed project consists of two new buildings, B1 and B2/3 totaling approximately 561,000 square feet that will complete the Hollis Street frontage between 53rd Street and Stanford Avenue, along with a parking structure, B13/14, facing Horton Street that will accommodate the parking necessary to support the existing and new building space. The project components are summarized as follows: Building Approx Size # of Occupied Floors B1 300,000 SF 11 B2/3 261,000 SF 7 B13/14 2,018Cars 9 levels, including grade and roof This proposed construction complies with the “Minimum Project” as defined in Section 2.2.3 of the PDP. The initial building construction will consist of the building shell and core space, to include the full building structure, building exterior facades, roof level equipment screening, interior stairs and elevators, and primary utility distribution risers. The initial construction may also include the building entry lobbies, toilet cores on one or more floor levels, and primary mechanical equipment. Specific functions throughout the buildings will be determined by the building tenants as a part of the future tenant improvements construction. BUILDING DESCRIPTIONS Building B1 consists of a new 11-story, approximately 300,000 SF tower designed to accommodate research and development laboratories and associated office and support space on all levels. The First Floor level will incorporate the primary building entry, tenant spaces facing the streets, courtyard and plaza, and entries to the building loading dock and service areas. Floors 2 through 10 will be designed to accommodate flexible laboratory OWNER Biomed Realty 17190 Bernardo Center Drive San Diego, CA 92128 (858) 485.9840 ARCHITECT FLAD Architects 650 California Street 17th Floor San Francisco, CA 94108 (415) 398.1600 PARKING DESIGN International Parking Design 560 14th Street Suite #300 Oakland, CA 94612 (510) 473.0300 LAND USE COUNSEL Perkins Coie 505 Howard Street Suite 1000 San Francisco, CA 94105 (415) 344.7117 CIVIL ENGINEER BKF Engineers 150 California Street Suite 600 San Francisco, CA 94111 (415) 930.7949 GEOTECHNICAL ENGINEER LANGAN 135 Main Street Suite 1500 San Francisco, CA 94105 (415) 955.5200 LANDSCAPE ARCHITECT BIONIC 833 Market Street Suite 601 San Francisco, CA 94103 (415) 206.0648 12/12/19 02/10/20 03/04/20 11/04/19 and associated office and support space on all levels, and the 11th floor will be designed as a “sky box” space that can accommodate either administrative, conference or research space. The potential for a rooftop terrace space will be incorporated to take advantage of the views from this premier location. The building roof areas will be utilized for mechanical equipment, including boilers, chillers, air handling units and exhaust fans. Building B2/3 consists of a new 7-story, approximately 261,000 SF building designed to accommodate research and development laboratories and associated office and support space on all levels. The First Floor level will incorporate the primary building entry, tenant spaces facing Hollis Street and the courtyard, and entries to the building loading dock and service areas. Floors 2 through 7 will be designed to accommodate flexible laboratory and associated office and support space on all levels. The building roof areas will be utilized for mechanical equipment, including boilers, chillers, air handling units and exhaust fans. The street liner for will contain building support functions such conferencing and meeting rooms, training and education facilities, and so on. Retail functions will also be provided on building 2/3. Building B13/14 consists of a dedicated parking structure with vehicle parking on 9 levels, including the grade level and roof level. Provisions will be made for incorporation of electric vehicle charging as appropriate. This building is anticipated to accommodate small occupied space for an Emergency Operations Center or other retail use including possible provision for a small office to accommodate a parking staff. BUILDING FACADES The building B1 and B2/3 facade will consist of a combination of materials that are respectful and compatible with the architecture of existing Building 4, while also updating the appearance of these new buildings to meet new sustainability objectives, indoor environmental standards, energy performance, and marketplace expectations. The lower levels of the proposed buildings B1 and B2/3 will incorporate glass and terracotta or brick masonry materials that relate strongly to the local Emeryville history, current context and adjacent Building 4 design. The middle levels of the buildings will consist of glass and metal trim that provide excellent light and views to and from the building interior. Opaque areas will be addressed with a combination of shadowbox (spandrels) panels and/or metal infill panels, to add interest and variation to the facade. The upper levels and mechanical screens will consist of a combination of opaque glass panels and metal screen materials or terracotta to conceal the rooftop equipment and exhaust risers. Sheet Index G000 Data Sheet G001 BMR Campus Vision G002 BMR Campus Vision - Axonometric G003 Existing Conditions Within PDP Area G004 Existing Conditions Within PDP Area On BMR Properties G005 Existing Site Photos G006 PDP Boundary and Site Plan* G007 PDP Boundary And Site Plan - Showing BMR Properties G008 PDP Boundary And Site Plan - Showing BMR FDP Boundary G009 BMR Proposed FDP Scope G010 BMR FDP - Frontage & Setbacks G011 BMR FDP - Open Space G012 BMR FDP - Building Heights G013 BMR FDP - Vehicular Circulation & Service Access G014 BMR FDP - Pedestrian Circulation G015 BMR FDP - Emergency Vehicle Access G016 BMR FDP - Bicycle Circulation G017 BMR FDP - Bicycle Circulation At B13/14 G018 Project Images - Southwest View At Hollis And Stanford Streets -B1 G019 Building Plans - B1 G020 Building Images, Hollis Street Elevation - B1 G021 Project Images - Southwest View At Hollis Street - B2/3 G022 Building Plans - B2/3 G023 Building Images, Hollis Street Elevation - B2/3 G024 Building Images, Southeast View at Horton Street - B13/14 G025 Building Images, Southeast View at Horton Street - B13/14 G026 Building Plans - B13/14 (Parking) G027 Building Images, Horton Street Elevation - B13/14 G028 Shadow Studies G029 PDP Conformance - Overall Massing G030 PDP Conformance - Hollis Street Setbacks G031 PDP Conformance - Hollis Street Height Limits G032 PDP Conformance - Hollis Street Building Massing G033 PDP Conformance - Horton Street Building Massing G034 PDP Conformance - PDP Setbacks G035 PDP Conformance - PDP & Proposed FDP Setback Comparison L001 Context Of FDP Boundary L002 Landscape Illustrative Plan B1 & B2/3 L003 Project Image - Chiron Way Shared Street Looking North L004 Project Image - Plaza Looking South L005 Project Image - Plaza Looking North L006 Project Image - Paseo Looking Toward Chiron Way L007 Material Palette & Precedents L008 Materials Plan B1 & B2/3 L009 Preliminary Plant Palette & Precedents L010 Preliminary Tree Palette & Precedents L011 Planting Areas B1 & B2/3 L012 Hydrozone B1 & B2/3 L013 Landscape Sections: (Chiron Way) L014 Landscape Sections: (Chiron Way) L015 Landscape Sections: (Chiron Way) L016 Landscape Sections: (Hollis Street, Stanford Avenue) L017 Landscape Sections: (Hollis Street, Stanford Avenue) L018 Landscape Sections: (Entry Garden Section, Paseo Section) L019 Landscape Sections: (Plaza) Data Sheet X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X
  • 4. 25’0’ 50’ 100’ B2/3 24' HORTON STREET (Public Street) HORTON STREET “FORMERLY LANDREGAN ST”(Public Street) 53RDSTREET (PublicStreet) CHIRON WAY “FORMERLY HOLDEN ST” (Publicly-Accessible Private Street) HOLLIS STREET (Public Street) HOLLIS STREET (Public Street) PELADEAU STREET (Public Street) STANFORD AVENUE (PublicStreet) FUTUREPEDESTRIANBRIDGEBRIDGEACCESS EASEMENT NON-BUILDABLE EASEMENT B1 B4 (E) B7 (E) B8B (FUTURE BUILDING) B8A (FUTURE BUILDING) PDU (E) R (E) Q (E) N (E) H (E) 12A (E) CMF (E) F (E) E (E) D (E) B13/14 B2/3 Non Buildable Easement** Grifols-Owned Properties Overall PDP Boundary* BMR-Owned Properties Grifols-Owned BuildingA0A BMR-Owned BuildingA0A Existing Building(E) GRIFOLS-OWNED PROPERTIES GRIFOLS-OWNED PROPERTIES BMR-OWNED PROPERTIES BMR-OWNED PROPERTIES BMR-OWNED PROPERTIES GRIFOLS-OWNED PROPERTIES March 4, 2020 EMERYVILLE CENTER OF INNOVATION G001 BMR Campus Vision *Per Preliminary Development Plan Figure 2-5 & 2-6 **Per 2018 ALTA/NSPS Land Title Survey
  • 5. HORTON STREET “FORMERLY LANDREGAN ST” HORTON STREET HOLLIS STREET HOLLIS STREET PELADEAU STREET STANFORDAVENUE FUTURE SHERWIN WILLIAMS DEVELOPMENT B8B (FUTURE BUILDING) B8A (FUTURE BUILDING) D (E) R (E) Q (E) PDU (E) H (E) 12A (E) CMF (E) B1 B2/3 B7 (E) B4 (E) B13/14 F (E) N (E) E (E) Overall PDP Boundary* BMR-Owned Properties** BMR-Owned BuildingA0A Grifols-Owned BuildingA0A Existing Building(E) March 4, 2020 EMERYVILLE CENTER OF INNOVATION G002 BMR Campus Vision - Axonometric *Per Preliminary Development Plan Figure 2-5 & 2-6 **Per 2018 ALTA/NSPS Land Title Survey
  • 6. Overall PDP Boundary* Grifols-Owned Building BMR-Owned Building A0A A0A 12AH R Q N PDU G T B7 B4 E D CMF F 0’ 25’ 50’ 100’ March 4, 2020 EMERYVILLE CENTER OF INNOVATION G003 Existing Conditions Within PDP Area *Per Preliminary Development Plan Figure 2-5 & 2-6
  • 7. Overall PDP Boundary* BMR-Owned Properties** Non BMR-Owned Properties** PDU G T B7 B4 BMR-OWNED PROPERTIES BMR-OWNED PROPERTIES BMR-OWNED PROPERTIES 0’ 25’ 50’ 100’ March 4, 2020 EMERYVILLE CENTER OF INNOVATION G004 Existing Conditions Within PDP Area On BMR Properties *Per Preliminary Development Plan Figure 2-5 & 2-6 ** Per 2018 ALTA/NSPS Land Title Survey
  • 8. map. 1000 ft N ➤➤ N March 4, 2020 EMERYVILLE CENTER OF INNOVATION G005 Existing Site Photos 1 6 3 2 5 4 1 54 2 3 6
  • 9. Overall PDP Boundary* Proposed PDP Buildings* Horton Street Hollis Street Holden Street 53rdStreet 45thStreet StanfordStreetExtension Horton Street Bypass B4 B8B9B10B11D B7A CMF B7B B6 B5 B3 B2 PDU B12B B12AB13B14B B14A B1 0’ 25’ 50’ 100’ March 4, 2020 EMERYVILLE CENTER OF INNOVATION G006 PDP Boundary and Site Plan* *Per Preliminary Development Plan Figure 2-5 & 2-6
  • 10. Overall PDP Boundary* Proposed PDP Buildings* BMR-Owned Properties** HORTON STREET HOLLIS STREET HOLDEN STREET 53RDSTREET 45THSTREET STANFORD STREETEXTENSION HORTON STREET BYPASS B4 B8B9B10B11D B7A CMF B7B B6 B5 B3 B2 PDU B12B B12AB13B14B B14A B1 BMR-OWNED PROPERTIES BMR-OWNED PROPERTIES BMR-OWNED PROPERTIES 0’ 25’ 50’ 100’ March 4, 2020 EMERYVILLE CENTER OF INNOVATION G007 *Per Preliminary Development Plan Figure 2-5 & 2-6 PDP Boundary And Site Plan - Showing BMR Properties
  • 11. Overall PDP Boundary* BMR FDP Scope Extents Proposed PDP Buildings* 53RDSTREET HORTON STREET HOLLIS STREET HOLDEN STREET 45THSTREET STANFORD STREETEXTENSION HORTON STREET BYPASS B4 B8B9B10B11D B7A CMF B7B B6 B5 B3 B2 PDU B12B B12AB13B14B B14A B1 0’ 25’ 50’ 100’ PROPOSED FDP AREA PROPOSED FDP AREA March 4, 2020 EMERYVILLE CENTER OF INNOVATION G008 *Per Preliminary Development Plan Figure 2-5 & 2-6 PDP Boundary And Site Plan - Showing BMR FDP Boundary
  • 12. 25’0’ 50’ 100’ Overall PDP Boundary* BMR FDP Boundary Grifols-Owned BuildingA0A BMR-Owned BuildingA0A Existing Building(E) HORTON STREET HORTON STREET “FORMERLY LANDREGAN ST” FUTUREPEDESTRIANBRIDGE 53RDSTREET HOLLIS STREET HOLLIS STREET PELADEAU STREET STANFORD AVENUE CHIRON WAY “FORMERLY HOLDEN ST” (Publicly-Accessible Private Street) B1 B4 (E) B7 (E) G (E) T (E) PDU (E) B13/14 R (E) Q (E) N (E) H (E) 12A (E) CMF (E) F (E) E (E) D (E) B2/3 REMOVING EXISTING SECURITY GATES PROPOSED FDP AREA REMOVING EXISTING SECURITY GATES PROPOSED FDP AREA March 4, 2020 EMERYVILLE CENTER OF INNOVATION G009 BMR Proposed FDP Scope *Per Preliminary Development Plan Figure 2-5 & 2-6
  • 13. 25’0’ 50’ 100’ Overall PDP Boundary* BMR FDP Boundary Grifols-Owned BuildingA0A BMR-Owned BuildingA0A Existing Building(E) 50' 22' 45' 77' 30' 26'26' 32' 12' 47' 50' 50' 20' 14' 18' 35' HORTON STREET HORTON STREET “FORMERLY LANDREGAN ST” 53RDSTREET HOLLIS STREET HOLLIS STREET PELADEAU STREET STANFORDAVENUE FUTUREPEDESTRIANBRIDGE CHIRON WAY “FORMERLY HOLDEN ST” (Publicly-Accessible Private Street) B1 B2/3 B4 (E) PDU (E) R (E) Q (E) N (E) H (E) 12A (E) CMF (E) F (E) E (E) D (E) B13/14 G (E) T (E) B7 (E) March 4, 2020 EMERYVILLE CENTER OF INNOVATION G010 BMR FDP - Frontage & Setbacks *Per Preliminary Development Plan Figure 2-5 & 2-6
  • 14. 25’0’ 50’ 100’ Overall PDP Boundary* BMR FDP Boundary Open Space Grifols-Owned BuildingA0A BMR-Owned BuildingA0A Service HORTON STREET HORTON STREET “FORMERLY LANDREGAN ST” 53RDSTREET HOLLIS STREET HOLLIS STREET PELADEAU STREET STANFORD AVENUE SERVICE FUTUREPEDESTRIANBRIDGE CHIRON WAY “FORMERLY HOLDEN ST” (Publicly-Accessible Private Street) B4 (E) B7 (E) G (E) T (E) PDU (E) B13/14 H (E) 12A (E) CMF (E) F (E) R (E) Q (E) N (E) E (E) D (E) B2/3 B1 March 4, 2020 EMERYVILLE CENTER OF INNOVATION G011 BMR FDP - Open Space *Per Preliminary Development Plan Figure 2-5, 2-6, 2-30
  • 15. 25’0’ 50’ 100’ Overall PDP Boundary* BMR FDP Boundary Grifols-Owned BuildingA0A BMR-Owned BuildingA0A Existing Building(E) HORTON STREET HORTON STREET “FORMERLY LANDREGAN ST” 53RDSTREET HOLLIS STREET HOLLIS STREET PELADEAU STREET STANFORD AVENUE FUTUREPEDESTRIANBRIDGE CHIRON WAY “FORMERLY HOLDEN ST” (Publicly-Accessible Private Street) +194' Top Of Screen +178' Top Of Roof Structure +162' Top Of Roof Structure +178' Top Of Screen +130' Top Of Screen +106'-3'' Top Of Mech +82'-6'' Top Of Roof Structure +114' Top Of Roof Structure +90'-2'' Top Of Roof Structure B4 (E) B7 (E) G (E) T (E) PDU (E) B13/14 H (E) 12A (E) CMF (E) F (E) R (E) Q (E) N (E) E (E) D (E) B2/3 B1 March 4, 2020 EMERYVILLE CENTER OF INNOVATION G012 BMR FDP - Building Heights *Per Preliminary Development Plan Figure 2-5 & 2-6
  • 16. 25’0’ 50’ 100’ Overall PDP Boundary* BMR FDP Boundary Service Vehicle Access Building Entrance Location Loading Entrance Location Parking Entrance Location Vehicular Circulation BMR-Owned BuildingA0A Non BMR-Owned BuildingA0A Loading Zone Commercial StructuredParking Short Term Loading/Drop-Off B4 (E) B7 (E) G (E) T (E) PDU (E) B13/14 H (E) 12A (E) CMF (E) F (E) R (E) Q (E) N (E) E (E) D (E) B2/3 B1 CURB CUT CURB CUT REMOVING EXISTING SECURITY GATES REMOVING EXISTING SECURITY GATES HORTON STREET HORTON STREET “FORMERLY LANDREGAN ST” 53RDSTREET HOLLIS STREET HOLLIS STREET PELADEAU STREET STANFORD AVENUE FUTUREPEDESTRIANBRIDGE CHIRON WAY “FORMERLY HOLDEN ST” (Publicly-Accessible Private Street) March 4, 2020 EMERYVILLE CENTER OF INNOVATION G013 BMR FDP - Vehicular Circulation & Service Access *Per Preliminary Development Plan Figure 2-5 & 2-6
  • 17. 25’0’ 50’ 100’ Overall PDP Boundary* BMR FDP Boundary Building Entrance Location Pedestrian Circulation through Arcade Private Elevator Public Park Crosswalk zone Pedestrian Circulation BMR-Owned BuildingA0A Non BMR-Owned BuildingA0A Proposed Greenway** B4 (E) B7 (E) G (E) T (E) PDU (E) B13/14 H (E) 12A (E) CMF (E) F (E) R (E) Q (E) N (E) E (E) D (E) B2/3 B1 REMOVING EXISTING SECURITY GATES REMOVING EXISTING SECURITY GATES HORTON STREET HORTON STREET “FORMERLY LANDREGAN ST” 53RDSTREET HOLLIS STREET HOLLIS STREET PELADEAU STREET STANFORD AVENUE FUTUREPEDESTRIANBRIDGE CHIRON WAY “FORMERLY HOLDEN ST” (Publicly-Accessible Private Street) March 4, 2020 EMERYVILLE CENTER OF INNOVATION G014 BMR FDP - Pedestrian Circulation *Per Preliminary Development Plan Figure 2-5 & 2-6 **Per 2016 General Plan, Figure 4-1
  • 18. 25’0’ 50’ 100’ Overall PDP Boundary* BMR FDP Boundary E.V.A. Route Emergency Vehicle Vehicular Circulation BMR-Owned BuildingA0A Non BMR-Owned Building Existing Fire Hydrant To Remain A0A B4 (E) B7 (E) G (E) T (E) PDU (E) B13/14 H (E) 12A (E) CMF (E) F (E) R (E) Q (E) N (E) E (E) D (E) B2/3 B1 HORTON STREET HORTON STREET “FORMERLY LANDREGAN ST” 53RDSTREET HOLLIS STREET HOLLIS STREET PELADEAU STREET STANFORD AVENUE FUTUREPEDESTRIANBRIDGE CHIRON WAY “FORMERLY HOLDEN ST” (Publicly-Accessible Private Street) 150'150' March 4, 2020 EMERYVILLE CENTER OF INNOVATION G015 BMR FDP - Emergency Vehicle Access *Per Preliminary Development Plan Figure 2-5 & 2-6
  • 19. 25’0’ 50’ 100’ Overall PDP Boundary* BMR FDP Boundary Bicycle Circulation Bike Boulevard** BMR-Owned BuildingA0A Non BMR-Owned BuildingA0A Existing Building(E) Building Entrance Location Long Term Bicycle StorageShort Term Bicycle Storage B4 (E) B7 (E) G (E) T (E) PDU (E) R (E) Q (E) N (E) H (E) 12A (E) CMF (E) F (E) E (E) D (E) B13/14 B2/3 B1 REMOVING EXISTING SECURITY GATES REMOVING EXISTING SECURITY GATES HORTON STREET HORTON STREET “FORMERLY LANDREGAN ST” 53RDSTREET HOLLIS STREET HOLLIS STREET PELADEAU STREET STANFORD AVENUE FUTUREPEDESTRIANBRIDGE CHIRON WAY “FORMERLY HOLDEN ST” (Publicly-Accessible Private Street) March 4, 2020 EMERYVILLE CENTER OF INNOVATION G016 BMR FDP - Bicycle Circulation *Per Preliminary Development Plan Figure 2-5 & 2-6 **Per 2016 General Plan, Figure 3-6 SEE SHEET G017
  • 20. 53rdSTREET Garage Entrance Proposed Separation Pylons Proposed Conflict Striping Proposed Bike Lane Existing Sharrows Existing Separation Pylons Existing Bike Lane BICYCLES SAFETY MEASURES 2 1 B13/14 21 March 4, 2020 EMERYVILLE CENTER OF INNOVATION G017 BMR FDP - Bicycle Circulation At B13/14
  • 21. March 4, 2020 EMERYVILLE CENTER OF INNOVATION G018 Project Images - Southwest View At Hollis And Stanford Streets -B1 GLAZED MECHANICAL SCREEN WALL TERRACOTTA, GFRC, OR MASONRY CLADDING PANELS TERRACOTTA, GFRC, OR MASONRY PANEL RAINSCREEN LOW-IRON HIGH PERFORMANCE INSULATED GLAZING UNITS HIGH PERFORMANCE INSULATED GLAZING UNITS
  • 22. STANFORDAVENUE HOLLIS STREET CHIRON WAY 0 32 FT 64 FT 50'-6" 53'-0" 19'-0" 42'-0" LEVEL 1 STANFORDAVENUE HOLLIS STREET 19'-0" 50'-6" 53'-0" 205'-0" 136'-0" 213'-9" APPROX. APPROX. APPROX. 0’ 16’ 32’ 64’ BMR Emeryville Master Plan, Area Summary DRAFT BUILDING SQUARE FEET, GSF TABLE-2: PARKING PROVIDED, CAR COUNT HEIGHT LIMITS floor B1 B2/3 B8 A B4 B8 B Subtotal-1 floor B 13 Subtotal 75' ht limit 90' ht limit 125' Ht limit225' ht limit 11 17,000 11 178 10 30,000 10 162 130'-175' 9 30,000 9 146 8 30,000 8 94,738 PH(132) 130 7 30,000 18,594 7 94,738 114 114 90-130' 6 27,000 32,000 18,594 6 94,738 PH(98) 98 98 5 27,000 35,000 23,117 23,558 5 94,738 82 82 82 4 27,000 35,000 24,547 23,558 4 94,738 66 66 66 66 3 26,000 35,000 24,547 24,416 3 94,738 50 50 50 50 2 28,000 32,000 24,547 24,416 2 94,738 34 34 34 34 1 28,000 31,000 23,107 285,000 23,861 1 94,738 18 18 18 18 Area 300,000 200,000 119,865 285,000 156,997 1,061,862 Area 757,900 757,900 Rounding 3 3 3 3 3 3 Cars 2,309 2,309 300,000 200,000 119,000 285,000 156,000 1,061,000 Surface 38 2,347 TABLE-3: Proposed Parking Building Area, sqft 1,061,862 1,061,862 Parking per 1000 GSF 1.55 2 Car Count 1,646 2,124 Note-1 : PH = 18'-0", Ground floor = 18'-0", Typical Floor = 16'-0" Note-2 : Car Count Assumes 325 GSF per stall 7,500 GSF 11,000 GSF AVG 18,000 GSF AVG MECHANICAL BUILDING SUPPORT R&D COLLABORATION R&D OFFICE R&D SUPPORT R&D LAB AMENITY ROOF TERRACE March 4, 2020 EMERYVILLE CENTER OF INNOVATION G019 Building Plans - B1 LEVEL 1 FLOOR PLAN 1 TYPICAL FLOOR PLAN 2 ROOF PLAN 3 LEGEND LOBBY
  • 23. November 4, 2019 BMR EMERYVILLE CENTER OF INNOVATION Building Images, Elevation - B1 A210 Building B1 East Elevation ROOF 106'-3"106'-3" ROOF 90'-3" level 7 74'-3" level 6 57'-6" level 5 41'-6" level 4 25'-6" level 3 12'-9" level 2 0'-0" level 1 90'-3" level 7 74'-3" level 6 57'-6" level 5 41'-6" level 4 25'-6" level 3 12'-9" level 2 0'-0" level 1 84'-4" 0'-0" level 1 level 4 level 2 11'-4" level 3 21'-6" 31'-8" level 5 41'-10" level 6 level 7 Roof 72'-4" 52'-0" 62'-2" 198'-0" Top of Screen Roof 178'-0" level 11 162'-0" 146'-0" level 10 130'-0" level 9 level 8 level 7 114'-0" 98'-0" 82'-0" level 6 level 5 66'-0" 50'-0" level 4 34'-0" level 3 0'-0" level 1 18'-0" level 2 Roof 98'-0" 82'-0" level 6 level 5 66'-0" 50'-0" level 4 34'-0" level 3 0'-0" level 1 18'-0" level 2 114'-0" Top of Screen Top of Core Top of Core level 2 18'-0" level 1 0'-0" level 3 34'-0" level 4 50'-0" 66'-0" level 5 level 6 82'-0" 98'-0" Roof level 2 18'-0" level 1 0'-0" level 3 34'-0" level 4 50'-0" 66'-0" level 5 level 6 82'-0" 98'-0" 114'-0" level 7 level 8 level 9 130'-0" level 10 146'-0" 162'-0" level 11 178'-0" Roof 62'-2" 52'-0" 72'-4" Roof level 7 level 6 41'-10" level 5 31'-8" 21'-6" level 3 11'-4" level 2 level 4 level 1 0'-0" 84'-4" level 1 0'-0" level 2 12'-9" level 3 25'-6" level 4 41'-6" level 5 57'-6" level 6 74'-3" level 7 90'-3" level 1 0'-0" level 2 12'-9" level 3 25'-6" level 4 41'-6" level 5 57'-6" level 6 74'-3" level 7 90'-3" ROOF 106'-3" 106'-3" ROOF Top of Screen 114'-0" Top of Screen 194'-0" 0’ 16’ 32’ 64’ November 4, 2019 BMR EMERYVILLE CENTER OF INNOVATION Building Images, Elevation - B1 A210 Building B2/3 East Elevation ROOF 106'-3"106'-3" ROOF 90'-3" level 7 74'-3" level 6 57'-6" level 5 41'-6" level 4 25'-6" level 3 12'-9" level 2 0'-0" level 1 90'-3" level 7 74'-3" level 6 57'-6" level 5 41'-6" level 4 25'-6" level 3 12'-9" level 2 0'-0" level 1 84'-4" 0'-0" level 1 level 4 level 2 11'-4" level 3 21'-6" 31'-8" level 5 41'-10" level 6 level 7 Roof 72'-4" 52'-0" 62'-2" 198'-0" Top of Screen Roof 178'-0" level 11 162'-0" 146'-0" level 10 130'-0" level 9 level 8 level 7 114'-0" 98'-0" 82'-0" level 6 level 5 66'-0" 50'-0" level 4 34'-0" level 3 0'-0" level 1 18'-0" level 2 Roof 98'-0" 82'-0" level 6 level 5 66'-0" 50'-0" level 4 34'-0" level 3 0'-0" level 1 18'-0" level 2 114'-0" Top of Screen Top of Core level 3 62'-2" 21'-6" 94'-6" 31'-8" level 5 Top of Screen Roof level 8 41'-10" Roof level 7 level 6 98'-0" 114'-0" 130'-0" 0'-0" level 1 82'-0" level 6 level 5 66'-0" 50'-0" level 4 level 4 34'-0" level 7 level 3 0'-0" level 1 18'-0" level 2 72'-4" level 2 11'-4" 52'-0" Top of Core 82'-6" March 4, 2020 EMERYVILLE CENTER OF INNOVATION G020 Building Images, Hollis Street Elevation - B1 GLAZED MECHANICAL SCREEN WALL HIGH PERFORMANCE INSULATED GLAZING UNITS LOW-IRON HIGH PERFORMANCE INSULATED GLAZING UNITS TERRACOTTA, GFRC, OR MASONRY PANEL RAINSCREEN
  • 24. March 4, 2020 EMERYVILLE CENTER OF INNOVATION G021 Project Images - Southwest View At Hollis Street - B2/3 TERRACOTTA, GFRC, OR MASONRY SCREEN WALL TERRACOTTA, GFRC, OR MASONRY CLADDING PANELS TERRACOTTA, GFRC, OR MASONRY PANEL RAINSCREEN LOW-IRON HIGH PERFORMANCE INSULATED GLAZING UNITS HIGH PERFORMANCE INSULATED GLAZING UNITS
  • 25. 47'-0" HOLLIS STREET CHIRON WAY 30'-0" 0 32 FT 64 FT 30'-0" 45'-0" LEVEL 1 39,392 sq ft 182'-0" 128'-6" 134'-0" 118'-6" 0 32 FT 64 FT APPROX. APPROX. APPROX. APPROX. LEVEL 3-5 (TYPICAL) - NEW OPTION 64 FT32 FT0 LEVEL 7 (MECHANICAL) 0’ 16’ 32’ 64’ BMR Emeryville Master Plan, Area Summary DRAFT BUILDING SQUARE FEET, GSF TABLE-2: PARKING PROVIDED, CAR COUNT HEIGHT LIMITS floor B1 B2/3 B8 A B4 B8 B Subtotal-1 floor B 13 Subtotal 75' ht limit 90' ht limit 125' Ht limit225' ht limit 11 17,000 11 178 10 30,000 10 162 130'-175' 9 30,000 9 146 8 30,000 8 94,738 PH(132) 130 7 30,000 18,594 7 94,738 114 114 90-130' 6 27,000 32,000 18,594 6 94,738 PH(98) 98 98 5 27,000 35,000 23,117 23,558 5 94,738 82 82 82 4 27,000 35,000 24,547 23,558 4 94,738 66 66 66 66 3 26,000 35,000 24,547 24,416 3 94,738 50 50 50 50 2 28,000 32,000 24,547 24,416 2 94,738 34 34 34 34 1 28,000 31,000 23,107 285,000 23,861 1 94,738 18 18 18 18 Area 300,000 200,000 119,865 285,000 156,997 1,061,862 Area 757,900 757,900 Rounding 3 3 3 3 3 3 Cars 2,309 2,309 300,000 200,000 119,000 285,000 156,000 1,061,000 Surface 38 2,347 TABLE-3: Proposed Parking Building Area, sqft 1,061,862 1,061,862 Parking per 1000 GSF 1.55 2 Car Count 1,646 2,124 Note-1 : PH = 18'-0", Ground floor = 18'-0", Typical Floor = 16'-0" Note-2 : Car Count Assumes 325 GSF per stall 7,500 GSF 11,000 GSF AVG 18,000 GSF AVG B1 B2/3 B8 A B4 B8 B Subtotal-1 floor B 13 Subtotal 75' ht limit 90' ht limit 125' Ht limit225' ht limit 14 226 175-225' 13 210 12 194 17,564 11 178 29,243 10 162 130'-175' 29,243 9 146 29,243 8 94,738 PH(132) 130 29,243 34,200 34,200 18,594 7 94,738 114 114 90-130' 26,867 36,800 36,800 18,594 6 94,738 PH(98) 98 98 26,867 36,800 36,800 23,117 23,558 5 94,738 82 82 82 26,867 36,800 36,800 24,547 23,558 4 94,738 66 66 66 66 25,543 36,800 36,800 24,547 24,416 3 94,738 50 50 50 50 27,541 40,600 40,600 24,547 24,416 2 94,738 34 34 34 34 27,541 39,300 39,300 23,107 285,000 23,861 1 94,738 18 18 18 18 295,762 261,300 119,865 285,000 156,997 1,118,924 Area 757,900 757,900 g 3 2 3 3 3 3 Cars 2,309 2,309 2,332 295,000 261,300 261,300 119,000 285,000 156,000 1,118,000 Surface 38 2,347 : Proposed Parking Building Area, sqft 1,118,924 1,118,924 Parking per 1000 GSF 1.55 2 Car Count 1,734 2,238 PH = 18'-0", Ground floor = 18'-0", Typical Floor = 16'-0" Car Count Assumes 325 GSF per stall 7,500 GSF AVG 11,000 GSF AVG 18,000 GSF AVG STANFORDAVENUE HOLLIS STREET 19'-0" 50'-6" 53'-0" meryville Master Plan, Area Summary DRAFT SUMMARY 1: BUILDING SQUARE FEET, GSF TABLE-2: PARKING PROVIDED, CAR COUNT HEIGHT LIMITS B1 B2/3 B8 A B4 B8 B Subtotal-1 floor B 13 Subtotal 75' ht limit 90' ht limit 125' Ht limit225' ht limit 14 226 175-225' 13 210 12 194 17,564 11 178 29,243 10 162 130'-175' 29,243 9 146 29,243 8 94,738 PH(132) 130 29,243 34,200 34,200 18,594 7 94,738 114 114 90-130' 26,867 36,800 36,800 18,594 6 94,738 PH(98) 98 98 26,867 36,800 36,800 23,117 23,558 5 94,738 82 82 82 26,867 36,800 36,800 24,547 23,558 4 94,738 66 66 66 66 25,543 36,800 36,800 24,547 24,416 3 94,738 50 50 50 50 27,541 40,600 40,600 24,547 24,416 2 94,738 34 34 34 34 27,541 39,300 39,300 23,107 285,000 23,861 1 94,738 18 18 18 18 295,762 261,300 119,865 285,000 156,997 1,118,924 Area 757,900 757,900 ng 3 2 3 3 3 3 Cars 2,309 2,309 2,332 295,000 261,300 261,300 119,000 285,000 156,000 1,118,000 Surface 38 2,347 3: Proposed Parking Building Area, sqft 1,118,924 1,118,924 Parking per 1000 GSF 1.55 2 Car Count 1,734 2,238 : PH = 18'-0", Ground floor = 18'-0", Typical Floor = 16'-0" : Car Count Assumes 325 GSF per stall 7,500 GSF AVG 11,000 GSF AVG 18,000 GSF AVG March 4, 2020 EMERYVILLE CENTER OF INNOVATION G022 Building Plans - B2/3 LEVEL 1 FLOOR PLAN 1 ROOF PLAN 3 TYPICAL FLOOR PLAN 2 LEGEND MECHANICAL BUILDING SUPPORT R&D COLLABORATION R&D OFFICE R&D SUPPORT R&D LAB AMENITY ROOF TERRACE LOBBY
  • 26. November 4, 2019 BMR EMERYVILLE CENTER OF INNOVATION Building Images, Elevation - B1 A210 Building B2/3 East Elevation ROOF 106'-3"106'-3" ROOF 90'-3" level 7 74'-3" level 6 57'-6" level 5 41'-6" level 4 25'-6" level 3 12'-9" level 2 0'-0" level 1 90'-3" level 7 74'-3" level 6 57'-6" level 5 41'-6" level 4 25'-6" level 3 12'-9" level 2 0'-0" level 1 84'-4" 0'-0" level 1 level 4 level 2 11'-4" level 3 21'-6" 31'-8" level 5 41'-10" level 6 level 7 Roof 72'-4" 52'-0" 62'-2" 198'-0" Top of Screen Roof 178'-0" level 11 162'-0" 146'-0" level 10 130'-0" level 9 level 8 level 7 114'-0" 98'-0" 82'-0" level 6 level 5 66'-0" 50'-0" level 4 34'-0" level 3 0'-0" level 1 18'-0" level 2 Roof 98'-0" 82'-0" level 6 level 5 66'-0" 50'-0" level 4 34'-0" level 3 0'-0" level 1 18'-0" level 2 114'-0" Top of Screen Top of Core level 3 62'-2" 21'-6" 94'-6" 31'-8" level 5 Top of Screen Roof level 8 41'-10" Roof level 7 level 6 98'-0" 114'-0" 130'-0" 0'-0" level 1 82'-0" level 6 level 5 66'-0" 50'-0" level 4 level 4 34'-0" level 7 level 3 0'-0" level 1 18'-0" level 2 72'-4" level 2 11'-4" 52'-0" Top of Core 82'-6" November 4, 2019 BMR EMERYVILLE CENTER OF INNOVATION Building Images, Elevation - B1 A210 Building B2/3 East Elevation ROOF 106'-3"106'-3" ROOF 90'-3" level 7 74'-3" level 6 57'-6" level 5 41'-6" level 4 25'-6" level 3 12'-9" level 2 0'-0" level 1 90'-3" level 7 74'-3" level 6 57'-6" level 5 41'-6" level 4 25'-6" level 3 12'-9" level 2 0'-0" level 1 84'-4" 0'-0" level 1 level 4 level 2 11'-4" level 3 21'-6" 31'-8" level 5 41'-10" level 6 level 7 Roof 72'-4" 52'-0" 62'-2" 198'-0" Top of Screen Roof 178'-0" level 11 162'-0" 146'-0" level 10 130'-0" level 9 level 8 level 7 114'-0" 98'-0" 82'-0" level 6 level 5 66'-0" 50'-0" level 4 34'-0" level 3 0'-0" level 1 18'-0" level 2 Roof 98'-0" 82'-0" level 6 level 5 66'-0" 50'-0" level 4 34'-0" level 3 0'-0" level 1 18'-0" level 2 114'-0" Top of Screen Top of Core level 3 62'-2" 21'-6" 94'-6" 31'-8" level 5 Top of Screen Roof level 8 41'-10" Roof level 7 level 6 98'-0" 114'-0" 130'-0" 0'-0" level 1 82'-0" level 6 level 5 66'-0" 50'-0" level 4 level 4 34'-0" level 7 level 3 0'-0" level 1 18'-0" level 2 72'-4" level 2 11'-4" 52'-0" Top of Core 82'-6" March 4, 2020 EMERYVILLE CENTER OF INNOVATION G023 Building Images, Hollis Street Elevation - B2/3 0’ 16’ 32’ 64’ TERRACOTTA, GFRC, OR MASONRY SCREEN WALL HIGH PERFORMANCE INSULATED GLAZING UNITS LOW-IRON HIGH PERFORMANCE INSULATED GLAZING UNITS TERRACOTTA, v, OR MASONRY PANEL RAINSCREEN
  • 27. March 4, 2020 EMERYVILLE CENTER OF INNOVATION G024 Building Images, Southeast View at Horton Street - B13/14 *Per South Bayfront Pedestrian Bicycle Bridge Project Overview, Emeryville City Council Meeting May 21, 2019 TO BRIDGE
  • 28. March 4, 2020 EMERYVILLE CENTER OF INNOVATION G025 Building Images, Southeast View at Horton Street - B13/14 PAINTED METAL PANEL SYSTEM EXPOSED CONCRETE PAINTED PERFORATED METAL SCREEN SYSTEM PAINTED METAL GUARDRAIL
  • 29. APPROX.170'-0" 44'-0"62'-0" APPROX.180'-0" 62'-0" 248'-0"97'-0" APPROX. 488'-0" 156'-0" RAMP DN RAMP UP RAMP UP RAMP DN 0 32 FT 64 FT LEVEL 2-8 (TYPICAL) 245 SPACES 242'-0" 26'-0"26'-0" 10'-0" 10'-0" 150'-0" 150'-0" 240'-0" FUTURE SHERWIN WILLIAMS DEVELOPMENT PDUEASEMENT HORTON STREET RAMP UP RAMP UP TOSOUTHBAYFRONTBRIDGE EOC March 4, 2020 EMERYVILLE CENTER OF INNOVATION G026 Building Plans - B13/14 (Parking) LEVEL 1 FLOOR PLAN 1 * TBD ** LONGTERM BICYCLESTORAGE TYPICAL FLOOR PLAN 2
  • 30. March 4, 2020 EMERYVILLE CENTER OF INNOVATION G027 Building Images, Horton Street Elevation - B13/14 level 3 62'-2" 21'-6" 94'-6" 31'-8" level 5 Top of Screen Roof level 8 41'-10" Roof level 7 level 6 98'-0" 114'-0" 130'-0" 0'-0" level 1 82'-0" level 6 level 5 66'-0" 50'-0" level 4 level 4 34'-0" level 7 level 3 0'-0" level 1 18'-0" level 2 72'-4" level 2 11'-4" 52'-0" Top of Core 82'-6" PAINTED PERFORATED METAL SCREEN SYSTEM EXPOSED CONCRETE PAINTED METAL PANEL SYSTEM PAINTED METAL GUARDRAIL
  • 31. March 4, 2020 EMERYVILLE CENTER OF INNOVATION G028 Shadow Studies BMR PHASE 1 - WINTER SOLSTICE (DECEMBER 21) - 3PMPDP - WINTER SOLSTICE (DECEMBER 21) - 3PM BMR PHASE 1 - WINTER SOLSTICE (DECEMBER 21) - 9AM Note: No significant shading impact to adjacent new or proposed housing developments. PDP - WINTER SOLSTICE (DECEMBER 21) - 9AM
  • 32. HORTON STREET “FORMERLY LANDREGAN ST” HORTON STREET HOLLIS STREET HOLLIS STREET PELADEAU STREET STANFORDAVENUE HOLLIS STREET STANFORDAVENUE HOLLIS STREET 160'-0'' March 4, 2020 EMERYVILLE CENTER OF INNOVATION G029 PDP Conformance - Overall Massing Preliminary Design Plan BMR Campus Vision A tower of 225 ft will be allowed on the Building 1 site The tower portion of the building is set back from Hollis Street by at least 160’ at the juncture of Buildings 1 and 2 and from Stanford Avenue by 5-45 ft The bulk of the tower shall diminish towards the top between 130 & 175 ft with a floor plate average of 11,000 gross square feet The proposed tower height is approximately 178 ft to the roof level, which is 47 ft less than the allowable maximum height of 225 ft With the revised street alignment of Holden Street (now Chiron Way), the required tower portion setback (160 ft from Hollis Street) is no longer possible given the separate property ownership of the parcel west of Chiron Way at Stanford Ave. Typical floor plate size is approximately 29,000 SF, which is at the lower end of market-dictated floor plate size for contemporary class-A institutional life science buildings. 11,000 GSF is not a viable floor plate for contemporary life-science industry. Street Arcade Building Mass At Street Frontage Street Arcade Building Mass At Street Frontage Levels Height* PDP Allowable Area* 1-6 0'-90' No Maximum 7-9 90'-130' Average 18,000 GSF 10 130'-145' Average 11,000 GSF 11 145’-160’ Average 11,000 GSF 12 160’-175’ Average 11,000 GSF 13-15 175-225 Average 7,500 GSF Levels Height PDP Allowable Area* BMR Area 1-6 0'-90' No Maximum 28,000 GSF 7-9 90'-130' Average 18,000 GSF 30,000 GSF 10 130'-145' Average 11,000 GSF 30,000 GSF 11 145’-160’ Average 11,000 GSF 17,000 GSF 12 160’-175’ Average 11,000 GSF - 13-15 175-225 Average 7,500 GSF - *Per Preliminary Development Plan Exhibit 5 & Appendix B 1 1 1 1 2 2 2 2 3 3 3 3
  • 33. HORTON STREET “FORMERLY LANDREGAN ST” HORTON STREET HOLLIS STREET HOLLIS STREET PELADEAU STREET STANFORDAVENUE 22'-0'' 52'-0'' 20'-0'' 50'-0'' 47'-0'' 45'-0'' HOLLIS STREET STANFORDAVENUE 45'-0'' 55'-0'' 75'-0'' 50'-0'' 50'-0'' 45'-0'' 5'-0'' 80'-0'' 160'-0'' March 4, 2020 EMERYVILLE CENTER OF INNOVATION G030 BMR Campus Vision PDP Conformance - Hollis Street Setbacks Street Arcade Building Mass At Street Frontage Street Arcade Building Mass At Street Frontage Preliminary Design Plan
  • 34. HORTON STREET “FORMERLY LANDREGAN ST” HORTON STREET HOLLIS STREET HOLLIS STREET PELADEAU STREET STANFORDAVENUE FUTURE BUILDING FUTURE BUILDING +194' Top of Screen +178' Roof +82'-6'' +94'-6” +94'-6” +94'-6” +178' Top of Screen +162' Roof +130' Top of Screen +114' Roof +114' Roof +34' Roof +98' Roof +162' Roof HOLLIS STREET HOLLIS STREET STANFORDAVENUE +245' +225' +175' +200' +150' +130' +65' +65' +75' +75' +90' +110' +110' +110' +90' +90' +75' +75' +75' March 4, 2020 EMERYVILLE CENTER OF INNOVATION G031 PDP Conformance - Hollis Street Height Limits Preliminary Design Plan BMR Campus Vision
  • 35. PROPOSED DESIGN RELOCATED PDP MASSING Hollis St PDP StanfordAve Hollis St StanfordAve Hollis St StanfordAve PDP VS. PROPOSED +90’ +245’ +225’ +178’ Roof +114’ 0’ 25’ 50’ 100’0’ 25’ 50’ 100’ RELOCATED PDP MASSING RELOCATED MASSING IN PROPOSED DESIGN SCOPE PDP ENTITLEMENT March 4, 2020 EMERYVILLE CENTER OF INNOVATION G032 PDP Conformance - Hollis Street Building Massing
  • 36. Horton St Horton St Horton St PROPOSED DESIGNPDP RELOCATED PDP MASSING +82’-6” +75’ PDP VS. PROPOSED 0’ 25’ 50’ 100’0’ 25’ 50’ 100’ RELOCATED PDP MASSING RELOCATED PDP MASSING IN PROPOSED DESIGN SCOPE PDP March 4, 2020 EMERYVILLE CENTER OF INNOVATION G033 PDP Conformance - Horton Street Building Massing
  • 37. 25’0’ 50’ 100’ Overall PDP Boundary* Colonnade** Grifols-Owned BuildingA0A BMR-Owned Building 1995 PDP Massing* A0A PDP Proposed Service Access*** 50' 12' 55' ≤ 55% OVERALL ENCROACHMENT B3 ≤ 55% OVERALL ENCROACHMENT B2 ≤ 25% OVERALL ENCROACHMENT B1 75' 12' 5' 50' 160' MIN TOWER SETBACK 12' 80' 45' HORTON STREET HORTON STREET BYPASS HORTON STREET “FORMERLY LANDREGAN ST” 53RDSTREET CHIRON WAY “FORMERLY HOLDEN ST” HOLLIS STREET SERVICE ACCESS HOLLIS STREET PELADEAU STREET STANFORD AVENUE CHIRON WAY ALIGNMENT B4 B3 B2 B1 B13 PDU B12B B12A CMF B6B7A B8B9 B5 B10B11D B7B B14A B14B March 4, 2020 EMERYVILLE CENTER OF INNOVATION G034 PDP Conformance - PDP Setbacks *Per Preliminary Development Plan Figure 2-5 & 2-6 **Per Preliminary Development Plan Figure 2-21 ***Per Preliminary Development Plan Exhibit 3
  • 38. 25’0’ 50’ 100’ Overall PDP Boundary*Grifols-Owned BuildingA0A BMR-Owned Building 1995 PDP Massing* A0A Proposed FDP Massing Relocated PDP Massing Relocated Massing in Proposed Design FDP Service Access Non-BMR Owned Properties HORTON STREET HORTON STREET “FORMERLY LANDREGAN ST” 53RDSTREET CHIRON WAY “FORMERLY HOLDEN ST” HOLLIS STREET HOLLIS STREET PELADEAU STREET STANFORD AVENUE FUTUREPEDESTRIANBRIDGE EXISTING CHIRON WAY ALIGNMENT 47' 50' 20' 45' 160' MIN TOWER SETBACK 60' B4 (E) B3 PROPOSED B2/3 PROPOSED B13/14 PROPOSED B1 B2 B1 B7 (E) G (E) T (E) PDU (E) B13B14A B14B H (E) 12A (E) CMF (E) F (E) R (E) Q (E) N (E) E (E) D (E) NON-BMR OWNED PROPERTIES NON-BMR OWNED PROPERTIES NON-BMR OWNED PROPERTIES March 4, 2020 EMERYVILLE CENTER OF INNOVATION G035 PDP Conformance - PDP & Proposed FDP Setback Comparison *Per Preliminary Development Plan Figure 2-5 & 2-6 **Per Preliminary Development Plan Exhibit 3
  • 39. March 4, 2020 EMERYVILLE CENTER OF INNOVATION L001 Context Of FDP Boundary
  • 40. FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-002 Landscape Illustrative Plan B1 & B2/3 1’’=60’ FDP Boundary 53rdStreet Chiron Way Hollis Street StanfordAvenue B4 B2/3 B1 March 4, 2020 EMERYVILLE CENTER OF INNOVATION L002 Landscape Illustrative Plan B1 & B2/3
  • 41. FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-003 Project Image - Chiron Way Shared Street Looking North March 4, 2020 EMERYVILLE CENTER OF INNOVATION L003 Project Image - Chiron Way Shared Street Looking North
  • 42. FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-004 Project Image - Plaza Looking South March 4, 2020 EMERYVILLE CENTER OF INNOVATION L004 Project Image - Plaza Looking South
  • 43. FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-005 Project Image - Plaza Looking North March 4, 2020 EMERYVILLE CENTER OF INNOVATION L005 Project Image - Plaza Looking North
  • 44. FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-006 Project Image - Paseo Looking Toward Chiron Way March 4, 2020 EMERYVILLE CENTER OF INNOVATION L006 Project Image - Paseo Looking Toward Chiron Way
  • 45. FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-007 Metal Walkway Shade Structure / Pavilion Paving Built-In Furnishings Moveable Furnishings Built-In Furnishings Materials Palette & Precedents March 4, 2020 EMERYVILLE CENTER OF INNOVATION L007 Material Palette & Precedents
  • 46. FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-008 (AC) Asphaltic Concrete (CUP) Concrete Unit Pavers - Profile B Tactile Warning Surfacing (CIP) Cast In Place Concrete - Profile A Bike Rack Metal - Type A (CUP) Concrete Unit Pavers - Profile A Materials Plan B1 & B2/3 FDP Boundary 1’’=60’ LEGEND SCHEDULE 53rdStreet Chiron Way Hollis Street StanfordAvenue B4 B2/3 B1 March 4, 2020 EMERYVILLE CENTER OF INNOVATION L008 Materials Plan B1 & B2/3
  • 47. March 4, 2020 EMERYVILLE CENTER OF INNOVATION L009 Preliminary Plant Palette & Precedents
  • 48. March 4, 2020 EMERYVILLE CENTER OF INNOVATION L010 Preliminary Tree Palette & Precedents
  • 49. FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-011 Planting Areas B1 & B2/3 1’’=60’ Planting - Type A (Streetscape) Planting - Type C (Meadow) Tree (Proposed) Tree Box Size 36’’ Planting - Type B (Shade) Bio-Retention Planter Tree (Proposed) Tree Box Size 24’’ Planting - Type D (Pollinator) FDP Boundary LEGEND SCHEDULE Tree (Proposed) Tree Box Size 60’’ 53rdStreet Chiron Way Hollis Street StanfordAvenue B4 B2/3 B1 March 4, 2020 EMERYVILLE CENTER OF INNOVATION L011 Planting Areas B1 & B2/3
  • 50. FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-012 Hydrozone B1 & B2/3 Wucols - Very Low Wucols - Low 1’’=60’ FDP Boundary LEGEND SCHEDULE 53rdStreet Chiron Way Hollis Street StanfordAvenue B4 B2/3 B1 March 4, 2020 EMERYVILLE CENTER OF INNOVATION L012 Hydrozone B1 & B2/3
  • 51. 0 8 16 24 FT FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-013 Landscape Sections: (Chiron Way) B4 SIDEWALK SIDEWALK SIDEWALK PLANTING AREA PLANTING AREA 6’ 11’ 13’4’ 20’ 26’ 6’ 6’6’ 6’ SHARED ZONE SHARED ZONE EXISTING OPEN SPACE SIDEWALK BUILDING F (E) Section A Section B A B PL PL FDP Boundary Property Line BIO-RETENTION PLANTER FDPFDP March 4, 2020 EMERYVILLE CENTER OF INNOVATION L013 Landscape Sections: (Chiron Way)
  • 52. 0 8 16 24 FT FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-014 Landscape Sections: (Chiron Way) Section C Section D C D PLANTING AREA PLAZA 6’ (VARIES) 17’ (VARIES) 3’ 20’ 12’3’ SHARED ZONE SIDEWALK BUILDING F (E) TRUNCATED DOMESTRUNCATED DOMES TRUNCATED DOMES PLAZA PLANTING AREA 3’ 26’10’ 6’ 6’ SHARED ZONE SIDEWALK BUILDING F (E) LOADING/ DROP OFF ZONE PLPL FDPFDP FDP Boundary Property Line March 4, 2020 EMERYVILLE CENTER OF INNOVATION L014 Landscape Sections: (Chiron Way)
  • 53. 0 8 16 24 FT FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-015 Landscape Sections: (Chiron Way) B1 LOADING B1 SIDEWALK SIDEWALK 6’ 3’14’ 20’ 20’3’ 6’ 3’ 6’ LOADING DOCK SHARED ZONE SHARED ZONEGRIFOLDS YARDSIDEWALK GRIFOLDS YARD TRUNCATED DOMES Section E Section F EF PL PL FDPFDP TRUNCATED DOMES TRUNCATED DOMES FDP Boundary Property Line March 4, 2020 EMERYVILLE CENTER OF INNOVATION L015 Landscape Sections: (Chiron Way)
  • 54. 0 8 16 24 FT FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-016 Landscape Sections (Hollis Street, Standford Avenue) G H Section G Section H B2/3 B2/3BIO-RETENTION PLANTER SIDEWALK BUILDING ENTRY 21’-9” (VARIES) 13’ (VARIES) 40’-7” (VARIES)5’-7”(VARIES) 5’-7”(VARIES) 10’ SHADE GARDEN PLANTING AREA PLANTING AREAHOLLIS STREET ROW ROW HOLLIS STREET PL PL FDPFDP FDP Boundary Property Line March 4, 2020 EMERYVILLE CENTER OF INNOVATION L016 Landscape Sections: (Hollis Street, Stanford Avenue)
  • 55. 0 8 16 24 FT FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-017 Landscape Sections (Hollis Street, Standford Avenue) Section I Section J I J B1 BUILDING ENTRY (METAL BRIDGE) BUILDING ENTRY 18’ (VARIES) 42’-9”37’-7” (VARIES) 12’ 10’ 17’-5” (VARIES) PLANTING AREA (POLLINATOR) PLANTING AREA HOLLIS STREET LOADING/ DROP OFF ZONESIDEWALK STANFORD AVENUE PL PLFDP FDP FDP Boundary Property Line March 4, 2020 EMERYVILLE CENTER OF INNOVATION L017 Landscape Sections: (Hollis Street, Stanford Avenue)
  • 56. 0 8 16 24 FT FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-018 Landscape Sections (Entry Garden Section, Paseo Section) K L B1BIO-RETENTION PLANTER METAL BRIDGE PLANTING AREA (POLLINATOR) 38’-6” (varies) 15’-5” (varies) 24’-11” (varies) 8’-3” (varies) 7’(varies) 12’-7” (varies) B2/3SHADE GARDEN SHADE GARDEN PASEO Section K Section L FDP FDP Boundary March 4, 2020 EMERYVILLE CENTER OF INNOVATION L018 Landscape Sections: (Entry Garden Section, Paseo Section)
  • 57. 36 FT 0 8 16 FT 0 12 24 FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-019 Landscape Sections (Plaza) M N Section M Section N FDP PL PL FDP Boundary Property Line 36 FT 0 8 16 FT 0 12 24 FEBRUARY 10, 2020 EMERYVILLE CENTER OF INNOVATION L-019 Landscape Sections (Plaza) M N Section M Section N FDP PL PL FDP Boundary Property Line March 4, 2020 EMERYVILLE CENTER OF INNOVATION L019 Landscape Sections: (Plaza)