SlideShare a Scribd company logo
MESC 2014 Presentation 
Tim Masse, Principal, BerryDunn 
Bill Brown, Principal, BerryDunn 
Contracting Best Practices 
berrydunn.com | GAIN CONTROL
• What if…. 
• “Not So Good” Practices 
• “Smart” Practices and Best 
Practices 
2 
Discussion Overview
• … all the states were mandated to undertake 60-70 new 
large-scale projects all at once with the exact same go-live 
dates? 
• … minimum funding for the projects was $5B, with many 
of the projects ranging in costs from $50M to $300M? 
• … must build systems that largely have never been built 
before for state governments? 
• … must build necessary systems and implement them in 
12 to 18 months on average? 
3 
What if
4 
“Not So Good” Practices
5 
Requests for Proposals (RFP) 
• The RFP document typically becomes the foundation 
for, and part of the final contract along with vendor 
response and written communications 
• Inadequate RFPs typically leads to bad contracts 
• RFPs not being used 
• Rushed procurements, contract development, and 
review processes due to mandated deadlines
Project Management vs. Contract Management 
6 
• Lack of project funding results in Project Manager 
serving as Contract Manager 
• Combined project management and contract 
management processes and personnel reduces project 
controls and “checks and balances” 
• Contract management is a discipline, good project 
managers aren’t necessarily good contract managers 
• Contract negotiation skills and experience are needed
• Greater reliance on sole source contracts to meet 
mandated legislative deadlines. Sole source contracts 
traditionally have been established for “emergency” 
procurements 
• Project and system requirements are often not well 
specified 
• Typically does not provide best value to the state compared 
to competitive procurements 
• Generally does not support federal Code of Federal 
Regulations (CFRs) for system procurements 
7 
Sole Source Contracts
8 
Waterfall vs. Agile 
Software Development Life Cycle (SDLC) 
• Traditional waterfall SDLC based projects typically tie 
payments to completion of major project phases; 
requirements, design, development, testing, training 
• Agile SDLC combines phases into software release 
“sprints” based on predetermined dates or duration 
• Payments tied to “sprint” completion is challenging when 
percent of functions delivered in each sprint is unknown 
until it is completed
9 
Pre-qualification Contracts and SOWs 
• States establish blanket contracts to streamline and 
expedite IT procurements 
• Allows agencies to more quickly request a statement of 
work (SOW) from select number of prequalified firms 
• SOWs too often lack detail and specificity in requirements 
which can cause problems later in project life cycle
10 
Accounting and Reporting Complexity 
• Multiple funding sources for a project 
• Complexity is unavoidable, but is a constant challenge 
to project reporting 
• Risks of overly complex or simplistic reporting process 
• Obtaining data, summarizing information and reporting 
results
11 
Project (Dis)Incentives 
Vendors not being paid in approximate 
correlation with their costs start losing resources 
and may perform worse 
Adversarial relationship with vendor, not a 
partner
12 
“Smart” Practices & Best Practices
13 
Deliverables and Milestones 
• Deliverables should not be the same as Milestones 
• In large scale projects deliverables should roll into 
milestones, and milestone payments are made when all 
associated deliverables are accepted 
• Smaller projects can tie payments directly to 
acceptance of deliverables. Depending on project 
duration, 10 deliverables or less
14 
Approving Invoices 
• Establish milestone and payment schedule that 
correlates with vendor project costs 
• Plan for, and require project hold back 
• Hold backs range from 5% to 25% 
• Establish invoice format and process up front in RFP 
• Performance bonds, penalty provisions, service levels
15 
Financial Management 
• Determine financial reporting needs as early as possible, 
so that data collection procedures can be designed 
accordingly 
• Determine key metrics and level of detail for each level of 
financial reporting, with focus on decision makers needs. 
• Distinguish reporting needs for compliance from those for 
decision making
16 
Cost Allocation 
• Determine granularity required for compliance and 
funding purposes, leaving flexibility to adapt to project 
changes 
• Align cost allocation methodology with existing project 
progress measurements and metrics 
• Give explicit consideration to balancing the risk of 
insufficient justification with that of burdensome 
complexity in the design
17 
Contract Terms & Conditions and RFPs 
• Put required contract terms and conditions into RFP 
• Provide for question and response process 
• Update terms and conditions to final and require all 
RFP respondents to comply with final version 
• Utilize federal CFRs for contract management 
processes in your projects 
• Provide timely and adequate contract review process 
by involving and communicating with reviewers early
18 
Dedicated Contract Managers 
• Dedicate a Contract Manager to your projects. Request 
funding for both state and vendor Contract Management staff 
• Contract Managers do not necessarily need to be full-time on 
the project 
• Contract Managers are usually not legal experts, therefore, 
ensure you provide your Contract Manager with adequate 
and timely legal support 
• Not CPAs either, ensure Contract Manager has adequate 
financial management and cost allocation support
19 
Integrate Contract Manager into Projects 
Contract Manager 
meet regularly with 
PMs and CMs 
Contract Manager 
works with Project 
Change Control 
Process 
Project Manager 
should send 
approvals for 
Deliverables 
Contract Manager 
should send 
approvals for 
Milestones
20 
Scalability 
• Create contracting practices that make sense 
for the contract size 
• PMOs typically scale project management 
methodologies based on project size 
• Establish scalable contracting practices for 
$1M, $10M, $50M, $100M+ projects for 
example
21 
Change Control 
• Reserve minimum of 10% contingency fund for project 
change orders, scale based on nature of project 
• Establish effective change control project processes from 
project inception 
• Spec out, review, and approve change orders in two to six 
weeks 
• Establish policy up front for “work at risk”
THANK YOU - QUESTIONS 
22 
Bill Brown, CPA, CFE, MAFF 
Principal, BerryDunn 
bbrown@berrydunn.com 
Tim Masse, MBA 
Principal, BerryDunn 
tmasse@berrydunn.com

More Related Content

What's hot

Download-manuals-general-procurement-manua ll-(hp-ii)[1][1]
 Download-manuals-general-procurement-manua ll-(hp-ii)[1][1] Download-manuals-general-procurement-manua ll-(hp-ii)[1][1]
Download-manuals-general-procurement-manua ll-(hp-ii)[1][1]hydrologywebsite1
 
CQF Risk Brochure
CQF Risk BrochureCQF Risk Brochure
CQF Risk Brochure
cberr
 
Non-Profit Grant Management
Non-Profit Grant ManagementNon-Profit Grant Management
Non-Profit Grant Management
Texas ACE
 
LSC Technology Initiative Grant Conference 2015 | Session Materials - Managin...
LSC Technology Initiative Grant Conference 2015 | Session Materials - Managin...LSC Technology Initiative Grant Conference 2015 | Session Materials - Managin...
LSC Technology Initiative Grant Conference 2015 | Session Materials - Managin...
Legal Services Corporation
 
PROJECT STORYBOARD: Reducing Purchase Order Lead Time by 33% Using Lean Six S...
PROJECT STORYBOARD: Reducing Purchase Order Lead Time by 33% Using Lean Six S...PROJECT STORYBOARD: Reducing Purchase Order Lead Time by 33% Using Lean Six S...
PROJECT STORYBOARD: Reducing Purchase Order Lead Time by 33% Using Lean Six S...
GoLeanSixSigma.com
 
Dynamic Changes Occurring: OMB's Uniform Grant Guidance
Dynamic Changes Occurring: OMB's Uniform Grant GuidanceDynamic Changes Occurring: OMB's Uniform Grant Guidance
Dynamic Changes Occurring: OMB's Uniform Grant Guidance
StreamLinkSoftware
 
Structuring Software Sales Transactions for Optimal Revenue Recognition
Structuring Software Sales Transactions for Optimal Revenue RecognitionStructuring Software Sales Transactions for Optimal Revenue Recognition
Structuring Software Sales Transactions for Optimal Revenue Recognition
Tensoft, Inc.
 
2015-06-25 Trending Topics in Employee Benefit Plans
2015-06-25 Trending Topics in Employee Benefit Plans2015-06-25 Trending Topics in Employee Benefit Plans
2015-06-25 Trending Topics in Employee Benefit PlansRaffa Learning Community
 
The Vendor Selection Guide - How to on Assessing Vendor Viability
The Vendor Selection Guide - How to on Assessing Vendor ViabilityThe Vendor Selection Guide - How to on Assessing Vendor Viability
The Vendor Selection Guide - How to on Assessing Vendor Viability
Proformative, Inc.
 
Sage Grant Management Webinar
Sage Grant Management Webinar Sage Grant Management Webinar
Sage Grant Management Webinar
Abila
 
Project scope management22
Project scope management22Project scope management22
Project scope management22
Amrendra kumar
 
Project Implementation
Project ImplementationProject Implementation
Project Implementation
Shidin Divakar
 
Project cycle
Project cycleProject cycle
Project cycle
Tilak Raj Chaulagai
 
Project Integration
Project IntegrationProject Integration
Project IntegrationTechNoleGirl
 
Developer's Forum - RSTF Update Final Report
Developer's Forum - RSTF Update Final ReportDeveloper's Forum - RSTF Update Final Report
Developer's Forum - RSTF Update Final Report
Scott Skraban, MPA, CH-ERIM
 
ClearTrial: Your Partner for Greater Efficiency in Clinical Operations and Ou...
ClearTrial: Your Partner for Greater Efficiency in Clinical Operations and Ou...ClearTrial: Your Partner for Greater Efficiency in Clinical Operations and Ou...
ClearTrial: Your Partner for Greater Efficiency in Clinical Operations and Ou...nfitzmaurice
 
Primavera.
Primavera.Primavera.
Primavera.
rajlaxmipardeshi
 
Agile Is Not Fragile
Agile Is Not FragileAgile Is Not Fragile
Agile Is Not Fragile
Sunil Mundra
 

What's hot (20)

Download-manuals-general-procurement-manua ll-(hp-ii)[1][1]
 Download-manuals-general-procurement-manua ll-(hp-ii)[1][1] Download-manuals-general-procurement-manua ll-(hp-ii)[1][1]
Download-manuals-general-procurement-manua ll-(hp-ii)[1][1]
 
CQF Risk Brochure
CQF Risk BrochureCQF Risk Brochure
CQF Risk Brochure
 
Non-Profit Grant Management
Non-Profit Grant ManagementNon-Profit Grant Management
Non-Profit Grant Management
 
LSC Technology Initiative Grant Conference 2015 | Session Materials - Managin...
LSC Technology Initiative Grant Conference 2015 | Session Materials - Managin...LSC Technology Initiative Grant Conference 2015 | Session Materials - Managin...
LSC Technology Initiative Grant Conference 2015 | Session Materials - Managin...
 
PROJECT STORYBOARD: Reducing Purchase Order Lead Time by 33% Using Lean Six S...
PROJECT STORYBOARD: Reducing Purchase Order Lead Time by 33% Using Lean Six S...PROJECT STORYBOARD: Reducing Purchase Order Lead Time by 33% Using Lean Six S...
PROJECT STORYBOARD: Reducing Purchase Order Lead Time by 33% Using Lean Six S...
 
Dynamic Changes Occurring: OMB's Uniform Grant Guidance
Dynamic Changes Occurring: OMB's Uniform Grant GuidanceDynamic Changes Occurring: OMB's Uniform Grant Guidance
Dynamic Changes Occurring: OMB's Uniform Grant Guidance
 
Structuring Software Sales Transactions for Optimal Revenue Recognition
Structuring Software Sales Transactions for Optimal Revenue RecognitionStructuring Software Sales Transactions for Optimal Revenue Recognition
Structuring Software Sales Transactions for Optimal Revenue Recognition
 
IPM (INTEGRATED PROJECT MANAGEMENT) Rev 1
IPM (INTEGRATED PROJECT MANAGEMENT) Rev 1IPM (INTEGRATED PROJECT MANAGEMENT) Rev 1
IPM (INTEGRATED PROJECT MANAGEMENT) Rev 1
 
2015-06-25 Trending Topics in Employee Benefit Plans
2015-06-25 Trending Topics in Employee Benefit Plans2015-06-25 Trending Topics in Employee Benefit Plans
2015-06-25 Trending Topics in Employee Benefit Plans
 
The Vendor Selection Guide - How to on Assessing Vendor Viability
The Vendor Selection Guide - How to on Assessing Vendor ViabilityThe Vendor Selection Guide - How to on Assessing Vendor Viability
The Vendor Selection Guide - How to on Assessing Vendor Viability
 
Sage Grant Management Webinar
Sage Grant Management Webinar Sage Grant Management Webinar
Sage Grant Management Webinar
 
Project scope management22
Project scope management22Project scope management22
Project scope management22
 
Project Implementation
Project ImplementationProject Implementation
Project Implementation
 
Project cycle
Project cycleProject cycle
Project cycle
 
Dc ops
Dc opsDc ops
Dc ops
 
Project Integration
Project IntegrationProject Integration
Project Integration
 
Developer's Forum - RSTF Update Final Report
Developer's Forum - RSTF Update Final ReportDeveloper's Forum - RSTF Update Final Report
Developer's Forum - RSTF Update Final Report
 
ClearTrial: Your Partner for Greater Efficiency in Clinical Operations and Ou...
ClearTrial: Your Partner for Greater Efficiency in Clinical Operations and Ou...ClearTrial: Your Partner for Greater Efficiency in Clinical Operations and Ou...
ClearTrial: Your Partner for Greater Efficiency in Clinical Operations and Ou...
 
Primavera.
Primavera.Primavera.
Primavera.
 
Agile Is Not Fragile
Agile Is Not FragileAgile Is Not Fragile
Agile Is Not Fragile
 

Viewers also liked

пошта майдану
пошта майданупошта майдану
пошта майдану
Людмила Квадріціус
 
Resume
ResumeResume
Resume
SANJAY JHA
 
Sanjoy - Aftersales Automotive parts
Sanjoy -  Aftersales  Automotive partsSanjoy -  Aftersales  Automotive parts
Sanjoy - Aftersales Automotive partsSanjoy Roy Choudhury
 
Enterprise Risk Management:from Resistance to Resilience
Enterprise Risk Management:from Resistance to ResilienceEnterprise Risk Management:from Resistance to Resilience
Enterprise Risk Management:from Resistance to Resilience
William H. (Bill) Brown, CPA, MAFF, CFE
 
地図会社がゲームアプリを作って思ったこと
地図会社がゲームアプリを作って思ったこと地図会社がゲームアプリを作って思ったこと
地図会社がゲームアプリを作って思ったこと
incrementp.corp
 
образи на картинах
образи на картинахобрази на картинах
образи на картинах
Людмила Квадріціус
 
Process Measurement - BPM Roundtable QLD
Process Measurement - BPM Roundtable QLDProcess Measurement - BPM Roundtable QLD
Process Measurement - BPM Roundtable QLD
Leonardo Consulting
 

Viewers also liked (11)

LRR_Frostburg_RSC2012
LRR_Frostburg_RSC2012LRR_Frostburg_RSC2012
LRR_Frostburg_RSC2012
 
RESUME - Copy
RESUME - CopyRESUME - Copy
RESUME - Copy
 
пошта майдану
пошта майданупошта майдану
пошта майдану
 
Resume
ResumeResume
Resume
 
Sanjoy - Aftersales Automotive parts
Sanjoy -  Aftersales  Automotive partsSanjoy -  Aftersales  Automotive parts
Sanjoy - Aftersales Automotive parts
 
Enterprise Risk Management:from Resistance to Resilience
Enterprise Risk Management:from Resistance to ResilienceEnterprise Risk Management:from Resistance to Resilience
Enterprise Risk Management:from Resistance to Resilience
 
地図会社がゲームアプリを作って思ったこと
地図会社がゲームアプリを作って思ったこと地図会社がゲームアプリを作って思ったこと
地図会社がゲームアプリを作って思ったこと
 
ICO_Ebook (1)
ICO_Ebook (1)ICO_Ebook (1)
ICO_Ebook (1)
 
образи на картинах
образи на картинахобрази на картинах
образи на картинах
 
Process Measurement - BPM Roundtable QLD
Process Measurement - BPM Roundtable QLDProcess Measurement - BPM Roundtable QLD
Process Measurement - BPM Roundtable QLD
 
Psychomotor domain
Psychomotor domainPsychomotor domain
Psychomotor domain
 

Similar to Contracting Best Practices - MESC 2014

Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...
Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...
Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...
Loay Ghazaleh MBA, BSc Civil Eng.
 
2013-06-13 Government Contractors Project Management Systems
2013-06-13 Government Contractors Project Management Systems2013-06-13 Government Contractors Project Management Systems
2013-06-13 Government Contractors Project Management Systems
Raffa Learning Community
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract Admin
Chris Carson
 
LN I - PPT.pptx
LN I - PPT.pptxLN I - PPT.pptx
LN I - PPT.pptx
AronHailesellasieAbr
 
DPBCapitalOutlayPPT_832015
DPBCapitalOutlayPPT_832015DPBCapitalOutlayPPT_832015
DPBCapitalOutlayPPT_832015Liliana Judge
 
EY-power-and-utilities-maturity-model-and-architecture
EY-power-and-utilities-maturity-model-and-architectureEY-power-and-utilities-maturity-model-and-architecture
EY-power-and-utilities-maturity-model-and-architectureChristopher Matthews
 
INAAU Project Management for Telecommunications Professionals
INAAU Project Management for Telecommunications ProfessionalsINAAU Project Management for Telecommunications Professionals
INAAU Project Management for Telecommunications Professionals
Rory McKenna
 
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for TrainersPMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
Ready to Train
 
CDM_2015_no_speaker_notes.pptx
CDM_2015_no_speaker_notes.pptxCDM_2015_no_speaker_notes.pptx
CDM_2015_no_speaker_notes.pptx
ssuserb5044d
 
Project: Monitoring
Project: Monitoring Project: Monitoring
Project: Monitoring
Mfb Firoz
 
0.Commercial Management slides _Lvl3.pdf
0.Commercial Management slides _Lvl3.pdf0.Commercial Management slides _Lvl3.pdf
0.Commercial Management slides _Lvl3.pdf
RahulSamadhiya2
 
Project Scope Management in IT Project and Software Project
Project Scope Management in IT Project and Software ProjectProject Scope Management in IT Project and Software Project
Project Scope Management in IT Project and Software Project
HengSovannarith
 
SOLAR Project-Finance-Nigeria-Case-Studies.pptx
SOLAR Project-Finance-Nigeria-Case-Studies.pptxSOLAR Project-Finance-Nigeria-Case-Studies.pptx
SOLAR Project-Finance-Nigeria-Case-Studies.pptx
DNTPOWER
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptx
ssuser5fc1e7
 
Rymer Resume Complete Master 0915
Rymer Resume Complete Master 0915Rymer Resume Complete Master 0915
Rymer Resume Complete Master 0915Robert Rymer
 
Using Project Management to Improve ROI Day 1 Event
Using Project Management to Improve ROI  Day 1 EventUsing Project Management to Improve ROI  Day 1 Event
Using Project Management to Improve ROI Day 1 Event
Ed Kozak
 
Mn dot bidding and estimating 4 16-13
Mn dot bidding and estimating 4 16-13Mn dot bidding and estimating 4 16-13
Mn dot bidding and estimating 4 16-13
jpeabody
 
Balancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBalancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBrown Smith Wallace
 
Deltek Vision User Group – Nv 2017
Deltek Vision User Group – Nv 2017Deltek Vision User Group – Nv 2017
Deltek Vision User Group – Nv 2017
BCS ProSoft
 

Similar to Contracting Best Practices - MESC 2014 (20)

Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...
Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...
Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...
 
2013-06-13 Government Contractors Project Management Systems
2013-06-13 Government Contractors Project Management Systems2013-06-13 Government Contractors Project Management Systems
2013-06-13 Government Contractors Project Management Systems
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract Admin
 
LN I - PPT.pptx
LN I - PPT.pptxLN I - PPT.pptx
LN I - PPT.pptx
 
DPBCapitalOutlayPPT_832015
DPBCapitalOutlayPPT_832015DPBCapitalOutlayPPT_832015
DPBCapitalOutlayPPT_832015
 
EY-power-and-utilities-maturity-model-and-architecture
EY-power-and-utilities-maturity-model-and-architectureEY-power-and-utilities-maturity-model-and-architecture
EY-power-and-utilities-maturity-model-and-architecture
 
INAAU Project Management for Telecommunications Professionals
INAAU Project Management for Telecommunications ProfessionalsINAAU Project Management for Telecommunications Professionals
INAAU Project Management for Telecommunications Professionals
 
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for TrainersPMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
 
AGC Webinar
AGC WebinarAGC Webinar
AGC Webinar
 
CDM_2015_no_speaker_notes.pptx
CDM_2015_no_speaker_notes.pptxCDM_2015_no_speaker_notes.pptx
CDM_2015_no_speaker_notes.pptx
 
Project: Monitoring
Project: Monitoring Project: Monitoring
Project: Monitoring
 
0.Commercial Management slides _Lvl3.pdf
0.Commercial Management slides _Lvl3.pdf0.Commercial Management slides _Lvl3.pdf
0.Commercial Management slides _Lvl3.pdf
 
Project Scope Management in IT Project and Software Project
Project Scope Management in IT Project and Software ProjectProject Scope Management in IT Project and Software Project
Project Scope Management in IT Project and Software Project
 
SOLAR Project-Finance-Nigeria-Case-Studies.pptx
SOLAR Project-Finance-Nigeria-Case-Studies.pptxSOLAR Project-Finance-Nigeria-Case-Studies.pptx
SOLAR Project-Finance-Nigeria-Case-Studies.pptx
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptx
 
Rymer Resume Complete Master 0915
Rymer Resume Complete Master 0915Rymer Resume Complete Master 0915
Rymer Resume Complete Master 0915
 
Using Project Management to Improve ROI Day 1 Event
Using Project Management to Improve ROI  Day 1 EventUsing Project Management to Improve ROI  Day 1 Event
Using Project Management to Improve ROI Day 1 Event
 
Mn dot bidding and estimating 4 16-13
Mn dot bidding and estimating 4 16-13Mn dot bidding and estimating 4 16-13
Mn dot bidding and estimating 4 16-13
 
Balancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBalancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction Projects
 
Deltek Vision User Group – Nv 2017
Deltek Vision User Group – Nv 2017Deltek Vision User Group – Nv 2017
Deltek Vision User Group – Nv 2017
 

Contracting Best Practices - MESC 2014

  • 1. MESC 2014 Presentation Tim Masse, Principal, BerryDunn Bill Brown, Principal, BerryDunn Contracting Best Practices berrydunn.com | GAIN CONTROL
  • 2. • What if…. • “Not So Good” Practices • “Smart” Practices and Best Practices 2 Discussion Overview
  • 3. • … all the states were mandated to undertake 60-70 new large-scale projects all at once with the exact same go-live dates? • … minimum funding for the projects was $5B, with many of the projects ranging in costs from $50M to $300M? • … must build systems that largely have never been built before for state governments? • … must build necessary systems and implement them in 12 to 18 months on average? 3 What if
  • 4. 4 “Not So Good” Practices
  • 5. 5 Requests for Proposals (RFP) • The RFP document typically becomes the foundation for, and part of the final contract along with vendor response and written communications • Inadequate RFPs typically leads to bad contracts • RFPs not being used • Rushed procurements, contract development, and review processes due to mandated deadlines
  • 6. Project Management vs. Contract Management 6 • Lack of project funding results in Project Manager serving as Contract Manager • Combined project management and contract management processes and personnel reduces project controls and “checks and balances” • Contract management is a discipline, good project managers aren’t necessarily good contract managers • Contract negotiation skills and experience are needed
  • 7. • Greater reliance on sole source contracts to meet mandated legislative deadlines. Sole source contracts traditionally have been established for “emergency” procurements • Project and system requirements are often not well specified • Typically does not provide best value to the state compared to competitive procurements • Generally does not support federal Code of Federal Regulations (CFRs) for system procurements 7 Sole Source Contracts
  • 8. 8 Waterfall vs. Agile Software Development Life Cycle (SDLC) • Traditional waterfall SDLC based projects typically tie payments to completion of major project phases; requirements, design, development, testing, training • Agile SDLC combines phases into software release “sprints” based on predetermined dates or duration • Payments tied to “sprint” completion is challenging when percent of functions delivered in each sprint is unknown until it is completed
  • 9. 9 Pre-qualification Contracts and SOWs • States establish blanket contracts to streamline and expedite IT procurements • Allows agencies to more quickly request a statement of work (SOW) from select number of prequalified firms • SOWs too often lack detail and specificity in requirements which can cause problems later in project life cycle
  • 10. 10 Accounting and Reporting Complexity • Multiple funding sources for a project • Complexity is unavoidable, but is a constant challenge to project reporting • Risks of overly complex or simplistic reporting process • Obtaining data, summarizing information and reporting results
  • 11. 11 Project (Dis)Incentives Vendors not being paid in approximate correlation with their costs start losing resources and may perform worse Adversarial relationship with vendor, not a partner
  • 12. 12 “Smart” Practices & Best Practices
  • 13. 13 Deliverables and Milestones • Deliverables should not be the same as Milestones • In large scale projects deliverables should roll into milestones, and milestone payments are made when all associated deliverables are accepted • Smaller projects can tie payments directly to acceptance of deliverables. Depending on project duration, 10 deliverables or less
  • 14. 14 Approving Invoices • Establish milestone and payment schedule that correlates with vendor project costs • Plan for, and require project hold back • Hold backs range from 5% to 25% • Establish invoice format and process up front in RFP • Performance bonds, penalty provisions, service levels
  • 15. 15 Financial Management • Determine financial reporting needs as early as possible, so that data collection procedures can be designed accordingly • Determine key metrics and level of detail for each level of financial reporting, with focus on decision makers needs. • Distinguish reporting needs for compliance from those for decision making
  • 16. 16 Cost Allocation • Determine granularity required for compliance and funding purposes, leaving flexibility to adapt to project changes • Align cost allocation methodology with existing project progress measurements and metrics • Give explicit consideration to balancing the risk of insufficient justification with that of burdensome complexity in the design
  • 17. 17 Contract Terms & Conditions and RFPs • Put required contract terms and conditions into RFP • Provide for question and response process • Update terms and conditions to final and require all RFP respondents to comply with final version • Utilize federal CFRs for contract management processes in your projects • Provide timely and adequate contract review process by involving and communicating with reviewers early
  • 18. 18 Dedicated Contract Managers • Dedicate a Contract Manager to your projects. Request funding for both state and vendor Contract Management staff • Contract Managers do not necessarily need to be full-time on the project • Contract Managers are usually not legal experts, therefore, ensure you provide your Contract Manager with adequate and timely legal support • Not CPAs either, ensure Contract Manager has adequate financial management and cost allocation support
  • 19. 19 Integrate Contract Manager into Projects Contract Manager meet regularly with PMs and CMs Contract Manager works with Project Change Control Process Project Manager should send approvals for Deliverables Contract Manager should send approvals for Milestones
  • 20. 20 Scalability • Create contracting practices that make sense for the contract size • PMOs typically scale project management methodologies based on project size • Establish scalable contracting practices for $1M, $10M, $50M, $100M+ projects for example
  • 21. 21 Change Control • Reserve minimum of 10% contingency fund for project change orders, scale based on nature of project • Establish effective change control project processes from project inception • Spec out, review, and approve change orders in two to six weeks • Establish policy up front for “work at risk”
  • 22. THANK YOU - QUESTIONS 22 Bill Brown, CPA, CFE, MAFF Principal, BerryDunn bbrown@berrydunn.com Tim Masse, MBA Principal, BerryDunn tmasse@berrydunn.com