SlideShare a Scribd company logo
1 of 13
Download to read offline
RockSat-C 2012
LRR
Launch Readiness Review
Zero Tilt
Frostburg State University
Kaetie Combs, Francisco Diaz , Sean Hughes, Jared Hughes, Andrew
Huntley, Subhasis Ghosh, Mayowa Ogundipe, Derek Val-Addo,
Michael Stevenson, Shaun O’Donnell, Ian Cuddahee, Michael Young,
David Wall, Adam Rexroad, Raymod Azenadaga, M. Eltayeb, Tyler
Lemmert
Date
RockSat-C 2012
LRR
User Notes
•  Mission Statement: Zero Tilt’s goal is to
provide, for the first time, a stable
environment throughout the flight of a
Sounding Rocket via two concurrent
objectives:
– Tilt correction system
– Despun platform system
RockSat-C 2012
LRR
Final Payload
• Show off payload!
– Pictures of the payload
– Pictures of team with the
payload
3
RockSat-C 2012
LRR
4
Final Payload
RockSat-C 2012
LRR
5
Final Payload
RockSat-C 2012
LRR
User Guide Compliance
6
Requirement Payload Requirement Status
Mass allotment: 10 LB 6.5 LB (plenty of room for
balancing)
OK
Volume allotment: Half Canister OK
The payload’s center of gravity
(CG):
In 1”X1”X1” envelope of
centroid (or in area designated
for sharing teams?
5.5 cm
(height is
11.5) can
be
adjusted
still
Activation met under requirement:
(either 1.SYS.1 or 1.SYS.2)
SYS.1 Tested?
YES
Structure mounts: Top and bottom bulkheads. No
mounts to sides of cans.
Bottom
Sharing: Fully developed? YES?
For reference: 1.SYS.1 is the early activation line
1.SYS.2 is the RBF/g-switch activation line
RockSat-C 2012
LRR
Integration Plan and Procedure
•  Where are you for integration?
•  Integrated the system
–  95% complete
• Two mounts for the accel. (tomorrow)
• Balancing (tomorrow)
–  What did you learn from integrating for tests?
• Be careful about all details
• Make sure to color code wires
•  Is your procedure complete and written?
–  Yes, system mounts on “Silver
Cake” (integrated system) make procedure
simple
7
RockSat-C 2012
LRR
Integration Plan and Procedure
– Do you have any concerns? What will you do
to mitigate these?
• Mounting holes as in the drawings we received
8
RockSat-C 2012
LRR
Testing Results
• Any updates on testing?
– Testing both systems
• Does you payload activate properly?
– Yes
• Does your payload fulfill the mission
requirements?
– Yes
9
RockSat-C 2012
LRR
Level of Readiness
•  This is the most important part of the
presentation!
•  Are you ready? 98%
•  What is ready?
–  New modified and compact voltage regulator
•  Is anything not ready?
–  Balancing and mounts
• Easy fix by tomorrow
–  Why? How will you make them ready?
• Machining delays
• Machinist is reporting completion by tomorrow
10
RockSat-C 2012
LRR
Level of Readiness
• Action items between now and June
15th?
– What will you do with the things that aren’t
ready?
• Complete mounts and balancing
• Perform more tests on rocket emulation system
11
RockSat-C 2012
LRR
Check-In Inspections
• Are there any remaining questions
about check-in?
• Have you tried it yet?
– Yes
– Were there any issues?
– No
12
RockSat-C 2012
LRR
Final Questions
• Do you have any questions about how
this week will go?
– Any environmental test day questions?
– Any integration day questions?
– Any launch day questions?
– Food questions?
– Pony questions?
– Bill’s questions?
13

More Related Content

Viewers also liked

Sanjoy - Aftersales Automotive parts
Sanjoy -  Aftersales  Automotive partsSanjoy -  Aftersales  Automotive parts
Sanjoy - Aftersales Automotive parts
Sanjoy Roy Choudhury
 

Viewers also liked (10)

пошта майдану
пошта майданупошта майдану
пошта майдану
 
RESUME - Copy
RESUME - CopyRESUME - Copy
RESUME - Copy
 
Resume
ResumeResume
Resume
 
Sanjoy - Aftersales Automotive parts
Sanjoy -  Aftersales  Automotive partsSanjoy -  Aftersales  Automotive parts
Sanjoy - Aftersales Automotive parts
 
Enterprise Risk Management:from Resistance to Resilience
Enterprise Risk Management:from Resistance to ResilienceEnterprise Risk Management:from Resistance to Resilience
Enterprise Risk Management:from Resistance to Resilience
 
地図会社がゲームアプリを作って思ったこと
地図会社がゲームアプリを作って思ったこと地図会社がゲームアプリを作って思ったこと
地図会社がゲームアプリを作って思ったこと
 
ICO_Ebook (1)
ICO_Ebook (1)ICO_Ebook (1)
ICO_Ebook (1)
 
образи на картинах
образи на картинахобрази на картинах
образи на картинах
 
Process Measurement - BPM Roundtable QLD
Process Measurement - BPM Roundtable QLDProcess Measurement - BPM Roundtable QLD
Process Measurement - BPM Roundtable QLD
 
Psychomotor domain
Psychomotor domainPsychomotor domain
Psychomotor domain
 

Similar to LRR_Frostburg_RSC2012

Tech Days 2015: User Presentation Vermont Technical College
Tech Days 2015: User Presentation Vermont Technical CollegeTech Days 2015: User Presentation Vermont Technical College
Tech Days 2015: User Presentation Vermont Technical College
AdaCore
 
Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...
Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...
Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...
Dave Callen
 
637124main staehle presentation
637124main staehle presentation637124main staehle presentation
637124main staehle presentation
Clifford Stone
 
Inter approach to_spaceprogmgmt
Inter approach to_spaceprogmgmtInter approach to_spaceprogmgmt
Inter approach to_spaceprogmgmt
NASAPMC
 
COTS lessons learned_2013_nov13
COTS lessons learned_2013_nov13COTS lessons learned_2013_nov13
COTS lessons learned_2013_nov13
Dmitry Tseitlin
 
COTS_lessons learned_2013_nov_13
COTS_lessons learned_2013_nov_13COTS_lessons learned_2013_nov_13
COTS_lessons learned_2013_nov_13
Dmitry Tseitlin
 
IGARSS 2011 - RCM, The Making of (AC) (Short).ppt
IGARSS 2011 - RCM, The Making of (AC) (Short).pptIGARSS 2011 - RCM, The Making of (AC) (Short).ppt
IGARSS 2011 - RCM, The Making of (AC) (Short).ppt
grssieee
 
Cots lessons learned_2013_nov13
Cots lessons learned_2013_nov13Cots lessons learned_2013_nov13
Cots lessons learned_2013_nov13
Dmitry Tseitlin
 
Raa.ftc.ev.in flightwifi
Raa.ftc.ev.in flightwifiRaa.ftc.ev.in flightwifi
Raa.ftc.ev.in flightwifi
dmcclatc
 
Mars CubeSat Telecom Relay Constellation_JPL Final
Mars CubeSat Telecom Relay Constellation_JPL FinalMars CubeSat Telecom Relay Constellation_JPL Final
Mars CubeSat Telecom Relay Constellation_JPL Final
Rohan Deshmukh
 
FINALTeam5 SPDRSAT Final Report
FINALTeam5 SPDRSAT Final ReportFINALTeam5 SPDRSAT Final Report
FINALTeam5 SPDRSAT Final Report
Jeffrey Lehrer
 

Similar to LRR_Frostburg_RSC2012 (20)

Tech Days 2015: User Presentation Vermont Technical College
Tech Days 2015: User Presentation Vermont Technical CollegeTech Days 2015: User Presentation Vermont Technical College
Tech Days 2015: User Presentation Vermont Technical College
 
Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...
Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...
Briefing - The Atlast V Aft Bulkhead Carrier Update - Past Missions, Upcoming...
 
637124main staehle presentation
637124main staehle presentation637124main staehle presentation
637124main staehle presentation
 
Inter approach to_spaceprogmgmt
Inter approach to_spaceprogmgmtInter approach to_spaceprogmgmt
Inter approach to_spaceprogmgmt
 
COTS lessons learned_2013_nov13
COTS lessons learned_2013_nov13COTS lessons learned_2013_nov13
COTS lessons learned_2013_nov13
 
COTS_lessons learned_2013_nov_13
COTS_lessons learned_2013_nov_13COTS_lessons learned_2013_nov_13
COTS_lessons learned_2013_nov_13
 
AMBER and Kepler GPUs
AMBER and Kepler GPUsAMBER and Kepler GPUs
AMBER and Kepler GPUs
 
ISU storage First Draft 1
ISU storage First Draft 1ISU storage First Draft 1
ISU storage First Draft 1
 
Integrating Laser Scan Data into FEA Model to Perform Level 3 FFS
Integrating Laser Scan Data into FEA Model to Perform Level 3 FFSIntegrating Laser Scan Data into FEA Model to Perform Level 3 FFS
Integrating Laser Scan Data into FEA Model to Perform Level 3 FFS
 
Robotic Refueling Mission
Robotic Refueling MissionRobotic Refueling Mission
Robotic Refueling Mission
 
IGARSS 2011 - RCM, The Making of (AC) (Short).ppt
IGARSS 2011 - RCM, The Making of (AC) (Short).pptIGARSS 2011 - RCM, The Making of (AC) (Short).ppt
IGARSS 2011 - RCM, The Making of (AC) (Short).ppt
 
ETL GISSUB
ETL GISSUBETL GISSUB
ETL GISSUB
 
Cots lessons learned_2013_nov13
Cots lessons learned_2013_nov13Cots lessons learned_2013_nov13
Cots lessons learned_2013_nov13
 
Flight Readiness Review Presentation for Project A.R.E.S.
Flight Readiness Review Presentation for Project A.R.E.S.Flight Readiness Review Presentation for Project A.R.E.S.
Flight Readiness Review Presentation for Project A.R.E.S.
 
Timing and Design Closure in Physical Design Flows
Timing and Design Closure in Physical Design Flows Timing and Design Closure in Physical Design Flows
Timing and Design Closure in Physical Design Flows
 
Raa.ftc.ev.in flightwifi
Raa.ftc.ev.in flightwifiRaa.ftc.ev.in flightwifi
Raa.ftc.ev.in flightwifi
 
Mars CubeSat Telecom Relay Constellation_JPL Final
Mars CubeSat Telecom Relay Constellation_JPL FinalMars CubeSat Telecom Relay Constellation_JPL Final
Mars CubeSat Telecom Relay Constellation_JPL Final
 
Srr Payload Team Consept 2
Srr Payload Team Consept 2Srr Payload Team Consept 2
Srr Payload Team Consept 2
 
Multibeam Advisory Committee - 2016 UNOLS FIC Meeting
Multibeam Advisory Committee - 2016 UNOLS FIC MeetingMultibeam Advisory Committee - 2016 UNOLS FIC Meeting
Multibeam Advisory Committee - 2016 UNOLS FIC Meeting
 
FINALTeam5 SPDRSAT Final Report
FINALTeam5 SPDRSAT Final ReportFINALTeam5 SPDRSAT Final Report
FINALTeam5 SPDRSAT Final Report
 

LRR_Frostburg_RSC2012

  • 1. RockSat-C 2012 LRR Launch Readiness Review Zero Tilt Frostburg State University Kaetie Combs, Francisco Diaz , Sean Hughes, Jared Hughes, Andrew Huntley, Subhasis Ghosh, Mayowa Ogundipe, Derek Val-Addo, Michael Stevenson, Shaun O’Donnell, Ian Cuddahee, Michael Young, David Wall, Adam Rexroad, Raymod Azenadaga, M. Eltayeb, Tyler Lemmert Date
  • 2. RockSat-C 2012 LRR User Notes •  Mission Statement: Zero Tilt’s goal is to provide, for the first time, a stable environment throughout the flight of a Sounding Rocket via two concurrent objectives: – Tilt correction system – Despun platform system
  • 3. RockSat-C 2012 LRR Final Payload • Show off payload! – Pictures of the payload – Pictures of team with the payload 3
  • 6. RockSat-C 2012 LRR User Guide Compliance 6 Requirement Payload Requirement Status Mass allotment: 10 LB 6.5 LB (plenty of room for balancing) OK Volume allotment: Half Canister OK The payload’s center of gravity (CG): In 1”X1”X1” envelope of centroid (or in area designated for sharing teams? 5.5 cm (height is 11.5) can be adjusted still Activation met under requirement: (either 1.SYS.1 or 1.SYS.2) SYS.1 Tested? YES Structure mounts: Top and bottom bulkheads. No mounts to sides of cans. Bottom Sharing: Fully developed? YES? For reference: 1.SYS.1 is the early activation line 1.SYS.2 is the RBF/g-switch activation line
  • 7. RockSat-C 2012 LRR Integration Plan and Procedure •  Where are you for integration? •  Integrated the system –  95% complete • Two mounts for the accel. (tomorrow) • Balancing (tomorrow) –  What did you learn from integrating for tests? • Be careful about all details • Make sure to color code wires •  Is your procedure complete and written? –  Yes, system mounts on “Silver Cake” (integrated system) make procedure simple 7
  • 8. RockSat-C 2012 LRR Integration Plan and Procedure – Do you have any concerns? What will you do to mitigate these? • Mounting holes as in the drawings we received 8
  • 9. RockSat-C 2012 LRR Testing Results • Any updates on testing? – Testing both systems • Does you payload activate properly? – Yes • Does your payload fulfill the mission requirements? – Yes 9
  • 10. RockSat-C 2012 LRR Level of Readiness •  This is the most important part of the presentation! •  Are you ready? 98% •  What is ready? –  New modified and compact voltage regulator •  Is anything not ready? –  Balancing and mounts • Easy fix by tomorrow –  Why? How will you make them ready? • Machining delays • Machinist is reporting completion by tomorrow 10
  • 11. RockSat-C 2012 LRR Level of Readiness • Action items between now and June 15th? – What will you do with the things that aren’t ready? • Complete mounts and balancing • Perform more tests on rocket emulation system 11
  • 12. RockSat-C 2012 LRR Check-In Inspections • Are there any remaining questions about check-in? • Have you tried it yet? – Yes – Were there any issues? – No 12
  • 13. RockSat-C 2012 LRR Final Questions • Do you have any questions about how this week will go? – Any environmental test day questions? – Any integration day questions? – Any launch day questions? – Food questions? – Pony questions? – Bill’s questions? 13