1. Introduction
1) Lessons leant form the Hiroshima severe Rain disaster (2018), Hurricane Katrina
in US (2005) and Flooding in Thailand (2011/2013), City Flood is one of the
most critical issues with safety and Business Continuity. Actually, the provability
of City Flood is much higher than earthquakes. And it could happen in Tokyo
Metropolitan area.
2) Same as the other disaster, reviewing with Hazard Maps to make a plan can
minimize the impacts from the disaster because most of the actual disaster
happened in the high risk area suggested on the Hazard Map.
3) City Flood mainly consists of Flooding from rivers (Gaisui - hanran) and
Flooding from inland waters (Naisui - hanran) caused by Severe Weather
and Typhoon which became more serious due to the global warming. On the top
of that High Tide are also increasing City Flood Risk as those block draining
system.
4) Unfortunately more than 99.9% of disaster related information/news in Japan is
still made in Japanese language only or takes time for make English translation.
So I will pick useful information both Japanese and English up for you.
5) During the presentation, I will introduce “Pre-Evacuation” and “Home BCP” to
minimize risk for your families and partners.
© Copyright Barclays 2018 (all rights reserved)
3 | <BCCJ Risk Seminar 2018> | <4 October 2018>
1) To introduce basic knowledge with City Flood
2) To review high risk area in Kanto region and Tokyo
3) To know more about Hazard Maps
4) To share sample impact Analysis
5) To introduce Barclays’ Home BCP
6) To show useful information source
2. Purpose of this presentation
© Copyright Barclays 2018 (all rights reserved)
4 | <BCCJ Risk Seminar 2018> | <4 October 2018>
Basic Knowledge with
Tokyo City Flood
© Copyright Barclays 2018 (all rights reserved)
5 | <BCCJ Risk Seminar 2018> | <4 October 2018>
3. History of Tokyo City Flood
Tokyo Metropolitan Government:
http://www.kensetsu.metro.tokyo.jp/suiga
i_kiroku/kako.htm
Tokyo City Flood: From 2000 to 2015, we had 104 City Floods in Tokyo and total of 661ha (13
times bigger than Tokyo Disney land) were damaged.
2011 – 2015 (27 Times 285ha were damaged 2006 – 2010 (31 Times 81ha were damaged
2000 – 2005 (46 Times 295ha were damaged
© Copyright Barclays 2018 (all rights reserved)
6 | <BCCJ Risk Seminar 2018> | <4 October 2018>
Dams
Rivers
4. City Flood and Water Draining System
Ministry of Land, Infrastructure, Transport
and Tourism:
http://www.pref.shimane.lg.jp/kasen/kando
gawa/kankyo.data/shitsumidamugaiyo.pdf
④ Capacity of
Dams
⑤ Capacity of
rivers
Ministry of Land, Infrastructure,
Transport and Tourism:
https://www.kkr.mlit.go.jp/yamato/ab
out/glossary/18.html
Ministry of Land, Infrastructure,
Transport and Tourism:
http://www.skr.mlit.go.jp/nakagawa/
disaster-prev/eq/tsunami-type.html
⑦ Strong Wind
push water back
Sea
1) Major factor of City Flood
① Heavy Rain in the Mountain
② Heavy Rain in the City
③ High Tide
2) Sub factor of City Flood
④ Capacity of Dams
⑤ Capacity of Rivers
⑥ Capacity of Water Draining System
⑦ Strong Wind of Typhoon
⑧ Low Pressure of Typhoon
⑨ Tide by Moon
Flooding from rivers
② Heavy Rain in the City
“City Flood happens when the Water Draining System fail to work due to the over capacity”
③ High Tide
① Heavy Rain in the Mountain
⑥ Over capacity of Draining system push
water back to the residential area
Flooding from inland water
Okayama City:
http://www.city.okayama.jp/gesui/keikakucyousei/keikakucyo
usei_00114.html
⑧ Low
Pressure
sucking
water up
⑨ Tide by Moon
© Copyright Barclays 2018 (all rights reserved)
7 | <BCCJ Risk Seminar 2018> | <4 October 2018>
5. About Typhoon
1) 15 out of 78 Typhoons (19.2%) gave impact with Tokyo Metropolitan Area in the last 3 years
(as of 1 Oct 2018).
2) Sea surface temperature is 1 to 2 degrees Celsius higher than 2017 around Japan which
makes Typhoon bigger and stronger (as of 1 Oct 2018). For example Typhoon 24 (Trami) had
11m high tide/waves as well as heavy rain and strong wind.
Weather news: http://weathernews.jp/
JMA:
https://www.data.jma.go.jp/kaiyou/data/db/kaikyo/daily/sst_HQ.html
Sea surface temperature deference Height of waves with Typhoon Trami
© Copyright Barclays 2018 (all rights reserved)
8 | <BCCJ Risk Seminar 2018> | <4 October 2018>
6. Flooding from the Rivers
1) There are 3 rivers
(Tone River, Ara
River and Tama River)
which make a flood in
Tokyo Metropolitan
area.
2) Especially between
Tone River and Ara
River as well the East
side of Tokyo are high
risk area of Flooding
from the Rivers
3) We should monitor the
heavy rain situation not
only in Tokyo but also
in the upper reaches of
those rivers because
tons of water will come
to Tokyo Metropolitan
area in a few hours
Yahoo Japan: https://typhoon.yahoo.co.jp/weather/river/
© Copyright Barclays 2018 (all rights reserved)
9 | <BCCJ Risk Seminar 2018> | <4 October 2018>
Potential High risk area
around Tokyo
© Copyright Barclays 2018 (all rights reserved)
10 | <BCCJ Risk Seminar 2018> | <4 October 2018>
7. Review Kanto district Land history
Asia Air Survey Co.,Ltd :
http://www.ajiko.co.jp/yomimono/imamura03.html
1) Seafront (6,000 years ago)
 6m adjusted Map shows the ancient seafront. Blue area mainly
consists of the soft soil and sand as it was under the water 6,000
years ago. Dry land is far smaller than today.
 Particularly Area stated Red Ovals (Zone 1 and Zone 2) have high
risk with flooding and Liquefactions risk.
6m adjusted Map
(Seafront of 6,000 years ago)
2
2) Eastward diversion of Tone River (400 years ago)
 About 400 years ago, Tokugawa shogun decided diverting Tone-
river from Zone 1 to Zone 2 to create a dry land in the east side of
Edo (Tokyo) . This is a reason why East Tokyo is low land.
Imperial Household Agency
http://www.kunaicho.go.jp/okotoba/02/koen/koen-h18az-mizuforum4th-e.html
© Copyright Barclays 2018 (all rights reserved)
11 | <BCCJ Risk Seminar 2018> | <4 October 2018>
8 Review Tokyo Altitude Overview
Geographical Information Authority of Japan: http://www.gsi.go.jp/common/000061694.pdf
1) West side of 23
Wards
 West side of Keihin-
Tohoku line are so-called
‘Yamanote’ and mostly 20-
40m from the sea level.
 This area is based on the
hard soil.
2) East side of 23
Wards
 East side of Keihin-
Tohoku line are so-called
‘Shitamachi’ and mostly
less than 5m from the sea
level.
 This area is based on the
soft soil as it was below sea
level thus having risk with
liquefactions and flooding
compare with ‘Yamanote’.
© Copyright Barclays 2018 (all rights reserved)
12 | <BCCJ Risk Seminar 2018> | <4 October 2018>
City Flood Hazard Map
© Copyright Barclays 2018 (all rights reserved)
13 | <BCCJ Risk Seminar 2018> | <4 October 2018>
9. Hazard Maps
1) Hazard Maps are very useful information source with the natural
disaster such as Flooding, Tsunami and Liquefaction as well as
the public support you may use such as the public evacuation
place.
2) Tokyo Metropolitan Government and each City Hall of 23 Wards
have Hazard Maps. I strongly recommend you to download or
have it from the City Hall of your home, school of your kids and
your working place. And understand risk with those places.
3) Then please have a discussion with your family or partner where
you should live and where you to evacuate.
4) This is the first step of the Solution Development.
© Copyright Barclays 2018 (all rights reserved)
14 | <BCCJ Risk Seminar 2018> | <4 October 2018>
10. Case Study
– Why we should know about Hazard Maps
High Risk Area of
Flood Hazard
Map
Actual
Flooding area
Mainichi News: https://mainichi.jp/articles/20180714/k00/00m/040/217000c
In the Hiroshima disaster 2018, actual
Flooding area is almost same as the High
Risk Area of Flood Hazard Map.
Asahi News
https://www.asahi.com/articles/ASL7956K2L79PTIL02N.h
tml
© Copyright Barclays 2018 (all rights reserved)
15 | <BCCJ Risk Seminar 2018> | <4 October 2018>
11. Minato-ku: Flood Hazard Map
Minato- Ku: https://www.city.minato.tokyo.jp/dobokukeikaku/bosai-anzen/bosai/shinsui/hazard-map/documents/omote-eigo.pdf
1) Some areas in Minato-ku have 0.50-1.0m Flood
risk when heavy rain exceeded sewer system and
river drainage capacity.
2) It is important for you to discuss with your family or
partner about Flood risk around your house, kids’
school and identify evacuation place and how to get
there safely.
3) Though your house is safe to stay, you should keep
sufficient stock of foods and water as well as special
kit with toilet. Also you should consider electric power
supply will be damaged by flooding.
© Copyright Barclays 2018 (all rights reserved)
16 | <BCCJ Risk Seminar 2018> | <4 October 2018>
5 minutes QA Session 1/3
© Copyright Barclays 2018 (all rights reserved)
17 | <BCCJ Risk Seminar 2018> | <4 October 2018>
Sample Impact Analysis
© Copyright Barclays 2018 (all rights reserved)
18 | <BCCJ Risk Seminar 2018> | <4 October 2018>
12. Flood risk and Public Transportations 1/2
Special committee in Cabinet office Japan
http://www.bousai.go.jp/kaigirep/chuobou/senmon/daikibosuigai/index.html
1) In 2010, Special Committee in Cabinet
Office Japan reported with the impact of
Tokyo City Flood caused by Ara-River
over flow. Some solutions were
implemented after this report to minimize
impacts.
2) According to the report, once Ara-
River flood happens, plenty of water
comes into Tokyo Metro (under ground)
and make it go under water in 12 - 24
hours
Japan Meteorological Agency:
https://www.jma.go.jp/jma/kishou/know/tenki_chuui/tenki
_chuui_p3.html
© Copyright Barclays 2018 (all rights reserved)
19 | <BCCJ Risk Seminar 2018> | <4 October 2018>
13. Flood risk and Public Transportations 2/2
Special committee in Cabinet office Japan
http://www.bousai.go.jp/kaigirep/chuobou/senmon/daikibosuigai/pdf/090123_shiryo_8.pdf
According to the worst scenario with Ara-River Flood, most of the stations of Tozai-line and
Hibiya-line goes under water in 15 hours (stated Red arrows) . Same situation will be
happened other Metro lines as well.
© Copyright Barclays 2018 (all rights reserved)
20 | <BCCJ Risk Seminar 2018> | <4 October 2018>
14. What happens after the City Flood
Special committee in Cabinet office Japan http://www.bousai.go.jp/kaigirep/chuobou/senmon/daikibosuigai/index.html
Main Issues are as follows;
 Sewage and dirty / polluted water
 Distributions / Supply Chain for food and water etc.
 Health and safety
Referring to the cases with the flood in Thailand and Hurricane Katrina in US, those bad
situation lasts more than a month and not easy to restore infrastructures such as public
transportation mainly due to the dirty water and debris.
© Copyright Barclays 2018 (all rights reserved)
21 | <BCCJ Risk Seminar 2018> | <4 October 2018>
Solution Development
© Copyright Barclays 2018 (all rights reserved)
22 | <BCCJ Risk Seminar 2018> | <4 October 2018>
15. Let’s think about Family and Partner’s
safety
1) Japanese Government well prepared prevention plan with City Flood
however it is better you to know the high risk area and potential
evacuation route.
2) One of the purposes of creating Home BCP (will be explained in detail on
the following slides) is improving your Family and Partner’s safety.
3) If you live in the area where you have less risk with Flooding, Liquefaction,
Earthquake or Fire etc., your Family and Partner can save time with
evacuation when disaster happens and much safer than living in the high
risk area suggested on the Hazard Map. Same as the school of your kids.
4) Moving to the less risk area before disaster makes sense. This is the
concept so-called ‘Pre-Evacuation’.
5) Now you know that high risk area, you can make a choice;
 Nice view vs. Family and Partner’s Safety
 Conferrable Commute vs. Family and Partner’s Safety
© Copyright Barclays 2018 (all rights reserved)
23 | <BCCJ Risk Seminar 2018> | <4 October 2018>
Sample Solution Development
- Home BCP -
© Copyright Barclays 2018 (all rights reserved)
24 | <BCCJ Risk Seminar 2018> | <4 October 2018>
16. Home BCP
1) Why we should have Home BCP
 Home BCP was developed in Barclays Japan to support having survival plans for employees’
Family and Partner.
 Employee cannot work for the company during the disaster without confirming safety of
Family and Partner, thus company must support 1) Risk Awareness, 2) Creating Plan and 3)
improving it.
2) Home BCP consists of Home BCP Pocket Card and a guide for emergency stock
 Contents of BCP Pocket Card
 Communication (Contact information)
 Daytime location
 Medical information
 Meeting point (Assembly point)
 Pick up plan for kids
 Embassy information and other information
 Emergency Stock (Must have)
 Food
 Water (Drinking Water and Other Water)
 Toilet
© Copyright Barclays 2018 (all rights reserved)
25 | <BCCJ Risk Seminar 2018> | <4 October 2018>
17. Home BCP: Sample Contents of Home BCP
Assembly Points
 Discuss The Primary
Assembly Point with your
Family as Mobile will be down
within 30 minutes
 Discuss about the
Secondary Assembly Point
too.
 Decide on communication
methodology if the Family
cannot meet (for example
messaging boards)
School Info
 Confirm teacher's landline telephone number, e-mail address and mobile number
 Confirm procedures to have your children picked up if both parents will be unavailable
 Confirm procedures if nobody will be available to pick up your children
Communication
 Mobile phone and e-mail:
Convenient, but availability
may be limited following a
disaster
 Landline: Advisable to have
one as they are much more
stable than mobile lines
 Social networks: are
generally good but you
should take the age of your
children into account
Daytime location Medical Information
Embassy Information
© Copyright Barclays 2018 (all rights reserved)
26 | <BCCJ Risk Seminar 2018> | <4 October 2018>
18. About an emergency stock
Water、Food and Toilet are must have emergency stock items
Basic requirements with emergency stock used be 3-5 days but considered with Flood risk, lifeline and
distribution lines will be malfunctioned for 2 – 4 weeks
 Drinking Water
 On average 1 person needs 2L/day(Resulting 1 family with 2 kids needs 112L in 2 weeks)
(Adult needs 50cc /1kg (weight), baby needs 150cc / 1kg and child needs 100cc / 1kg)
 Tap water can be used in 3 days. After that reused it to Bath or Washing machine
 Other Water(washing body and closes etc)
 Drinking water and Other water should be managed separately
 Dish must be covered by wrap to save water
 Food
 Pre-cooked food is recommended
 High calorie food and good balanced food should be selected
 Toilet
 Cover the toilet in your home by the special plastic bag
© Copyright Barclays 2018 (all rights reserved)
27 | <BCCJ Risk Seminar 2018> | <4 October 2018>
5 minutes QA Session 2/3
© Copyright Barclays 2018 (all rights reserved)
28 | <BCCJ Risk Seminar 2018> | <4 October 2018>
Appendix
© Copyright Barclays 2018 (all rights reserved)
29 | <BCCJ Risk Seminar 2018> | <4 October 2018>
A-1. Sample Emergency Stock - Food
<Basic Points to be considered with >
 Should be Pre-cooked
 Should contain a High calorie
 Should be with Long life
 Should not be too Hot or Spicy
 Should be with a Good natural balance
 Dish should be covered by a Wrap
Amazon https://www.amazon.co.jp/
© Copyright Barclays 2018 (all rights reserved)
30 | <BCCJ Risk Seminar 2018> | <4 October 2018>
A-2. Sample Emergency Stock - Drinking Water
< Basic Points to be considered with >
1) Drinking Water
 2L per person a day
 Long Life Pet bottle
 Water server is good to use (12L per bottle)
 Tap water can be used for drinking (3 days )
http://www.city.nerima.tokyo.jp/kusei/koho/oshirase/sinsai_tai
o/kumioki.files/kumioki.pdf
Good to have A filter for emergency
2) Other Water
 Should keep clean water in a bathtub (150L) for everything
except for Drinking and Cooking
Amazon https://www.amazon.co.jp/
© Copyright Barclays 2018 (all rights reserved)
31 | <BCCJ Risk Seminar 2018> | <4 October 2018>
A-3. Sample Emergency Stock - Goods for toilet
< Basic Points to be considered with >
1) Can not use water to flash
2) We should;
 Use existing toilet with plastic bag
 Use those with deodorizer
 Do not forget buying Toilet paper and Wet tissue
 Covered it by Another plastic bag for disposal
Amazon https://www.amazon.co.jp/
© Copyright Barclays 2018 (all rights reserved)
32 | <BCCJ Risk Seminar 2018> | <4 October 2018>
A-4. Useful Information Source
1) Disaster Preparedness Tokyo (Tokyo Metropolitan Government)
 Japanese: http://www.bousai.metro.tokyo.jp/index.html
 English: http://www.bousai.metro.tokyo.jp/english/index.html
2) Earthquake Survival Manual
 Japanese/English: http://www.myanmar-embassy-tokyo.net/eq/eq-survival-manual.pdf
3) Assistance for Foreigners at Times of Disaster Q & A Manual by Tokyo
International Communication Committee
 English: http://www.tokyo-icc.jp/information/pdf/qa_en.pdf
4) Disaster Management in Japan
 Japanese / English: http://www.bousai.go.jp/1info/pdf/saigaipanf_e.pdf
© Copyright Barclays 2018 (all rights reserved)
33 | <BCCJ Risk Seminar 2018> | <4 October 2018>
A-5. Going home support
Tokyo Metropolitan Government http://map.bousai.metro.tokyo.jp/en/pc/
There is a website to support you to go back to your house during the disaster
© Copyright Barclays 2018 (all rights reserved)
34 | <BCCJ Risk Seminar 2018> | <4 October 2018>
A-6. Fire Hazard (Earthquake)
Tokyo Metropolitan Government: http://www.toshiseibi.metro.tokyo.jp/bosai/chousa_6/download/kikendo.pdf?1802
1) Tokyo Metropolitan
Government announced about
Fire Hazard risk.
2) Though this is based on the
scenario analysis with
Earthquake, we could see the
area where Fire can be
occurred and not easy to work
for Firefighters.
3) We could see many
Wooden made houses are
close to each other and road
width
© Copyright Barclays 2018 (all rights reserved)
35 | <BCCJ Risk Seminar 2018> | <4 October 2018>
A-7. Traffic Restrictions (Earthquake)
Tokyo Metropolitan Police Department: http://www.keishicho.metro.tokyo.jp/kurashi/saigai/shinsai_kisei/kisei/index.files/english_270309.pdf
1) Tokyo Metropolitan
Police Department
announced that they
enforce City Block when
the big earthquake
happens in Tokyo.
2) In side of Kannana ring
road and Key/Major road
such as Route 20 are
controlled and authorized
emergency vehicles only.
3) Please take this into
account and it will be
affected your evacuation
plan.
© Copyright Barclays 2018 (all rights reserved)
36 | <BCCJ Risk Seminar 2018> | <4 October 2018>
A-8. Intensity of Typhoon
Note that the definition of "typhoon" is different between the Japanese standard and the international
http://agora.ex.nii.ac.jp/digital-typhoon/help/unit.html.en
© Copyright Barclays 2018 (all rights reserved)
37 | <BCCJ Risk Seminar 2018> | <4 October 2018>
A-9. Weather Warning /Advisory
JMA: http://www.jma.go.jp/jma/en/Emergency_Warning/examples_of_responses.png
© Copyright Barclays 2018 (all rights reserved)
38 | <BCCJ Risk Seminar 2018> | <4 October 2018>
Closing QA Session 3/3
© Copyright Barclays 2018 (all rights reserved)
39 | <BCCJ Risk Seminar 2018> | <4 October 2018>
Disclaimer 1/5
© Copyright Barclays 2018 (all rights reserved)
BARCLAYS This communication has been prepared by Barclays.
“Barclays” means any entity within the Barclays Group of companies, where “Barclays Group”
means Barclays Bank PLC, Barclays PLC and any of their subsidiaries, affiliates, ultimate holding
company and any subsidiaries or affiliates of such holding company.
CONFLICT OF
INTERESTS
BARCLAYS IS A FULL SERVICE INVESTMENT BANK. In the normal course of offering
investment banking products and services to clients, Barclays may act in several capacities
(including issuer, market maker and/or liquidity provider, underwriter, distributor, index sponsor,
swap counterparty and calculation agent) simultaneously with respect to a Product, giving rise to
potential conflict of interests which may impact the performance of a Product.
NOT RESEARCH This document is not a product of the Barclays Research department. Any views expressed may
differ from those of Barclays Research.
BARCLAYS
POSITIONS
Barclays may at any time acquire, hold or dispose of long or short positions (including hedging
and trading positions) and trade or otherwise effect transactions for their own account or the
account of their customers in the products referred to herein which may impact the performance
of a Product.
PRIVATE
INFORMATION
BARCLAYS MAY HAVE PRIVATE INFORMATION ABOUT ANY PRODUCT AND/OR THE
UNDERLYING ASSETS REFERENCED BY THE PRODUCT. It is not obligated to disclose any
such information to you.
FOR
INFORMATION
ONLY
THIS DOCUMENT IS PROVIDED FOR INFORMATION PURPOSES ONLY AND IS SUBJECT TO
CHANGE. IT IS INDICATIVE ONLY AND IS NOT BINDING.
40 | <BCCJ Risk Seminar 2018> | <4 October 2018>
Disclaimer 2/5
© Copyright Barclays 2018 (all rights reserved)
NO OFFER Barclays is not offering to sell or seeking to buy any Product or enter into any transaction. Any
offer or entry into any transaction requires Barclays’ subsequent formal agreement which will be
subject to internal approvals and execution of binding transaction documents.
NO LIABILITY Neither Barclays nor any of its directors, officers, employees, representatives or agents, accepts
any liability whatsoever for any direct, indirect or consequential losses (in contract, tort or
otherwise) arising from the use of this document or its contents or reliance on the information
contained herein, except to the extent this would be prohibited by law or regulation.
NO ADVICE Barclays is acting solely as principal and not as fiduciary. Barclays does not provide, and has not
provided, any investment advice or personal recommendation to you in relation to the
transaction and/or any related securities described herein and is not responsible for providing or
arranging for the provision of any general financial, strategic or specialist advice, including legal,
regulatory, accounting, model auditing or taxation advice or services or any other services in
relation to the transaction and/or any related securities described herein. Accordingly Barclays is
under no obligation to, and shall not, determine the suitability for you of the transaction
described herein. You must determine, on your own behalf or through independent professional
advice, the merits, terms, conditions and risks of the transaction described herein.
THIRD PARTY
INFORMATION
Barclays is not responsible for information stated to be obtained or derived from third party
sources or statistical services.
DISTRIBUTION All laws and regulations in any relevant jurisdiction(s) must be complied with when offering,
marketing or selling a Product or distributing offering materials.
PAST
PERFORMANCE
Any past or simulated past performance including back-testing, modelling or scenario analysis
contained in this document is no indication as to future performance.
No representation is made as to the accuracy of the assumptions made within, or completeness
of, any modelling, scenario analysis or back-testing.
41 | <BCCJ Risk Seminar 2018> | <4 October 2018>
Disclaimer 3/5
© Copyright Barclays 2018 (all rights reserved)
OPINIONS SUBJECT
TO CHANGE
All opinions and estimates are given as of the date hereof and are subject to change. The
value of any investment may also fluctuate as a result of market changes. Barclays is not
obliged to inform the recipients of this document of any change to such opinions or estimates.
NOT FOR RETAIL This document is being directed at persons who are professionals and is not intended for retail
customer use.
REGULATORY
DISCLOSURE
Information relating to an investment may be disclosed when required by regulators or other
authorities, including tax authorities.
TAX DISCLOSURE All discussions and any related materials relating to the tax treatment or tax structure of any
transactions described in this document (including any attachments) may be disclosed without
limitation. This authorisation of tax disclosure supersedes anything to the contrary contained
in this document or otherwise communicated.
CONFIDENTIAL This document is confidential and is for the benefit and internal use of the recipient for the
purpose of considering the securities/transaction described herein, and no part of it may be
reproduced, distributed or transmitted without the prior written permission of Barclays.
ABOUT BARCLAYS Barclays offers premier investment banking products and services to its clients through
Barclays Bank PLC. Barclays Bank PLC is authorised by the Prudential Regulation Authority
and regulated by the Financial Conduct Authority and the Prudential Regulation Authority and
is a member of the London Stock Exchange. Barclays Bank PLC is registered in England No.
1026167 with its registered office at 1 Churchill Place, London E14 5HP.
Barclays Securities Japan Limited is a joint-stock company incorporated in Japan with
registered office of 6-10-1, Roppongi, Minato-ku, Tokyo 106-6131, Japan. It is a subsidiary
of Barclays Bank PLC and a financial instruments firm regulated by the Financial Services
Agency of Japan. Registered Number: Kanto Zaimukyokucho (kinsho) No. 143.
42 | <BCCJ Risk Seminar 2018> | <4 October 2018>
COPYRIGHT © Copyright Barclays 2018 (all rights reserved).
MATTERS TO BE
INDICATED IN
ADVERTISEMENT,
ETC.
Barclays Securities Japan Limited is a financial instruments business operator (kinyushohin
torihikigyosha) regulated by the Financial Services Agency of Japan. Registered Number:
Kanto Zaimukyokucho (kinsho) No. 143. It is a member of the Japan Securities Dealers
Association, the Financial Futures Association of Japan and Type II Financial Instruments
Firms Association.
This event given by Barclays may have the purpose to solicit the execution of financial
instrument transactions with Barclays. When you enter into transactions involving financial
instruments sold by Barclays, you may be required to pay charges, fees or expenses for each
financial instrument. You may also be required, by prior agreement with Barclays, to deposit
margin and/or other cash guarantee (“Cash Guarantee”), depending on the type of
transaction, such as derivative and margin transactions, that you enter into with Barclays.
For certain transactions, the notional amount of the transaction may exceed the amount of
Cash Guarantee (i.e., the ratio of the notional amount of transaction compared to the amount
of Cash Guarantee cannot be calculated in advance, since the specific terms of the transaction
may not have yet been determined). PLEASE BE AWARE OF THE RISK THAT YOU MAY
INCUR LOSSES IN CONNECTION WITH YOUR INVESTMENT CAUSED BY VARIOUS
FACTORS INCLUDING, WITHOUT LIMITATION, FLUCTUATIONS IN THE INTEREST
RATES, CURRENCY VALUES, OR PRICES OR OTHER INDICES IN THE FINANCIAL
INSTRUMENT MARKET AND THAT YOUR POSSIBLE LOSSES MAY EXCEED THE AMOUNT
OF CASH GUARANTEE YOU HAVE DEPOSITED BECAUSE OF SUCH FACTORS.
Disclaimer 4/5
© Copyright Barclays 2018 (all rights reserved)
43 | <BCCJ Risk Seminar 2018> | <4 October 2018>
Disclaimer 5/5
© Copyright Barclays 2018 (all rights reserved)
In relation to over-the-counter derivative transactions, the indicative price for purchasing
financial instruments from Barclays will differ from that for selling financial instruments. In
addition, there is a risk that you may lose your principal or that you may incur losses
exceeding the amount of your original investment in connection with the sale or other
transactions involving financial instruments which you enter into with Barclays because of a
change in the business or creditworthiness of the person engaging in such sale or such
other transactions involving financial instruments or any other person. There is also a risk
that there may be a limitation period in which to exercise any right that is derived from
such sale or such other transactions involving financial instruments or in which contracts
relating to the sale or entry into other transactions involving such financial instruments may
be cancelled.
Please read carefully the documents which have been delivered to you prior to the
execution of any agreement, prospectus and other marketing materials and be aware that
the fees and commissions which are payable and the risks involved may differ depending on
the type of financial instrument, as mentioned above.
44 | <BCCJ Risk Seminar 2018> | <4 October 2018>
Thank you very much
© Copyright Barclays 2018 (all rights reserved)

More Related Content

Similar to Barclays Disaster Preparedness Presentation | BCCJ

The challenge in the recovery process and solutions for the future, Takuya ITO
The challenge in the recovery process and solutions for the future, Takuya ITOThe challenge in the recovery process and solutions for the future, Takuya ITO
The challenge in the recovery process and solutions for the future, Takuya ITOGlobal Risk Forum GRFDavos
 
Economic Loss Accounting in Japan, Tomoyuki Okada MLIT
Economic Loss Accounting in Japan, Tomoyuki Okada MLIT Economic Loss Accounting in Japan, Tomoyuki Okada MLIT
Economic Loss Accounting in Japan, Tomoyuki Okada MLIT OECD Governance
 
Statistics FOR Business - Special Project (Example #2).docx
Statistics FOR Business - Special Project (Example #2).docxStatistics FOR Business - Special Project (Example #2).docx
Statistics FOR Business - Special Project (Example #2).docxrafaelaj1
 
Experiences From The Tohoku Disaster In Japan And Stakeholder Perceptions On ...
Experiences From The Tohoku Disaster In Japan And Stakeholder Perceptions On ...Experiences From The Tohoku Disaster In Japan And Stakeholder Perceptions On ...
Experiences From The Tohoku Disaster In Japan And Stakeholder Perceptions On ...Prabhakar SVRK
 
Japan KE4CAP Session 1_may 11p
Japan KE4CAP Session 1_may 11pJapan KE4CAP Session 1_may 11p
Japan KE4CAP Session 1_may 11pweADAPT
 
Cases of Disaster Prevention Activities in Japan
Cases of Disaster Prevention Activities in JapanCases of Disaster Prevention Activities in Japan
Cases of Disaster Prevention Activities in JapanNopphawanTamkuan
 
2011 12-15 -report_to_spc_acm_final
2011 12-15 -report_to_spc_acm_final2011 12-15 -report_to_spc_acm_final
2011 12-15 -report_to_spc_acm_finalNaoise
 
Side Event - Climate Science for Policy - WMO Statement on the State of the G...
Side Event - Climate Science for Policy - WMO Statement on the State of the G...Side Event - Climate Science for Policy - WMO Statement on the State of the G...
Side Event - Climate Science for Policy - WMO Statement on the State of the G...ipcc-media
 
IRJET- Flood Risk Assessment in Uyo Urban, Nigeria using Geospatial Tools
IRJET- Flood Risk Assessment in Uyo Urban, Nigeria using Geospatial ToolsIRJET- Flood Risk Assessment in Uyo Urban, Nigeria using Geospatial Tools
IRJET- Flood Risk Assessment in Uyo Urban, Nigeria using Geospatial ToolsIRJET Journal
 
News 03 (en)
News 03 (en)News 03 (en)
News 03 (en)otakio
 
The adoption of roof catchment rainwater harvesting and major water sources i...
The adoption of roof catchment rainwater harvesting and major water sources i...The adoption of roof catchment rainwater harvesting and major water sources i...
The adoption of roof catchment rainwater harvesting and major water sources i...oircjournals
 
IRJET - A Case Study On Flood Risk Management
IRJET - A Case Study On Flood Risk ManagementIRJET - A Case Study On Flood Risk Management
IRJET - A Case Study On Flood Risk ManagementIRJET Journal
 
IRJET- Development Control Regulation Strategies for Disaster Management- Cas...
IRJET- Development Control Regulation Strategies for Disaster Management- Cas...IRJET- Development Control Regulation Strategies for Disaster Management- Cas...
IRJET- Development Control Regulation Strategies for Disaster Management- Cas...IRJET Journal
 
Tipaimukh dam & Bangladesh- M Shahriar Sonet
Tipaimukh dam & Bangladesh- M Shahriar SonetTipaimukh dam & Bangladesh- M Shahriar Sonet
Tipaimukh dam & Bangladesh- M Shahriar SonetM Shahriar Sonet
 
Water Pollution and Environmental Management Measures
Water Pollution and Environmental Management MeasuresWater Pollution and Environmental Management Measures
Water Pollution and Environmental Management MeasuresMohamedIrsha
 
Session 6: Scene-setting-Mainstreaming resilience in projects - Sophie Lavaud...
Session 6: Scene-setting-Mainstreaming resilience in projects - Sophie Lavaud...Session 6: Scene-setting-Mainstreaming resilience in projects - Sophie Lavaud...
Session 6: Scene-setting-Mainstreaming resilience in projects - Sophie Lavaud...OECD Environment
 

Similar to Barclays Disaster Preparedness Presentation | BCCJ (20)

The challenge in the recovery process and solutions for the future, Takuya ITO
The challenge in the recovery process and solutions for the future, Takuya ITOThe challenge in the recovery process and solutions for the future, Takuya ITO
The challenge in the recovery process and solutions for the future, Takuya ITO
 
Disaster Mitigation Social Resilience: From Humans to Infrastructure
Disaster Mitigation Social Resilience: From Humans to InfrastructureDisaster Mitigation Social Resilience: From Humans to Infrastructure
Disaster Mitigation Social Resilience: From Humans to Infrastructure
 
Economic Loss Accounting in Japan, Tomoyuki Okada MLIT
Economic Loss Accounting in Japan, Tomoyuki Okada MLIT Economic Loss Accounting in Japan, Tomoyuki Okada MLIT
Economic Loss Accounting in Japan, Tomoyuki Okada MLIT
 
Statistics FOR Business - Special Project (Example #2).docx
Statistics FOR Business - Special Project (Example #2).docxStatistics FOR Business - Special Project (Example #2).docx
Statistics FOR Business - Special Project (Example #2).docx
 
Thesis
ThesisThesis
Thesis
 
Experiences From The Tohoku Disaster In Japan And Stakeholder Perceptions On ...
Experiences From The Tohoku Disaster In Japan And Stakeholder Perceptions On ...Experiences From The Tohoku Disaster In Japan And Stakeholder Perceptions On ...
Experiences From The Tohoku Disaster In Japan And Stakeholder Perceptions On ...
 
Japan KE4CAP Session 1_may 11p
Japan KE4CAP Session 1_may 11pJapan KE4CAP Session 1_may 11p
Japan KE4CAP Session 1_may 11p
 
Cases of Disaster Prevention Activities in Japan
Cases of Disaster Prevention Activities in JapanCases of Disaster Prevention Activities in Japan
Cases of Disaster Prevention Activities in Japan
 
2011 12-15 -report_to_spc_acm_final
2011 12-15 -report_to_spc_acm_final2011 12-15 -report_to_spc_acm_final
2011 12-15 -report_to_spc_acm_final
 
Side Event - Climate Science for Policy - WMO Statement on the State of the G...
Side Event - Climate Science for Policy - WMO Statement on the State of the G...Side Event - Climate Science for Policy - WMO Statement on the State of the G...
Side Event - Climate Science for Policy - WMO Statement on the State of the G...
 
IRJET- Flood Risk Assessment in Uyo Urban, Nigeria using Geospatial Tools
IRJET- Flood Risk Assessment in Uyo Urban, Nigeria using Geospatial ToolsIRJET- Flood Risk Assessment in Uyo Urban, Nigeria using Geospatial Tools
IRJET- Flood Risk Assessment in Uyo Urban, Nigeria using Geospatial Tools
 
News 03 (en)
News 03 (en)News 03 (en)
News 03 (en)
 
The adoption of roof catchment rainwater harvesting and major water sources i...
The adoption of roof catchment rainwater harvesting and major water sources i...The adoption of roof catchment rainwater harvesting and major water sources i...
The adoption of roof catchment rainwater harvesting and major water sources i...
 
IRJET - A Case Study On Flood Risk Management
IRJET - A Case Study On Flood Risk ManagementIRJET - A Case Study On Flood Risk Management
IRJET - A Case Study On Flood Risk Management
 
Slums down the drain
Slums down the drainSlums down the drain
Slums down the drain
 
IRJET- Development Control Regulation Strategies for Disaster Management- Cas...
IRJET- Development Control Regulation Strategies for Disaster Management- Cas...IRJET- Development Control Regulation Strategies for Disaster Management- Cas...
IRJET- Development Control Regulation Strategies for Disaster Management- Cas...
 
Tipaimukh dam & Bangladesh- M Shahriar Sonet
Tipaimukh dam & Bangladesh- M Shahriar SonetTipaimukh dam & Bangladesh- M Shahriar Sonet
Tipaimukh dam & Bangladesh- M Shahriar Sonet
 
Water Pollution and Environmental Management Measures
Water Pollution and Environmental Management MeasuresWater Pollution and Environmental Management Measures
Water Pollution and Environmental Management Measures
 
Session 6: Scene-setting-Mainstreaming resilience in projects - Sophie Lavaud...
Session 6: Scene-setting-Mainstreaming resilience in projects - Sophie Lavaud...Session 6: Scene-setting-Mainstreaming resilience in projects - Sophie Lavaud...
Session 6: Scene-setting-Mainstreaming resilience in projects - Sophie Lavaud...
 
Taenichek..pptx
Taenichek..pptxTaenichek..pptx
Taenichek..pptx
 

Recently uploaded

Contoh Aksi Nyata Refleksi Diri ( NUR ).pdf
Contoh Aksi Nyata Refleksi Diri ( NUR ).pdfContoh Aksi Nyata Refleksi Diri ( NUR ).pdf
Contoh Aksi Nyata Refleksi Diri ( NUR ).pdfcupulin
 
AIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.pptAIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.pptNishitharanjan Rout
 
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽中 央社
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxannathomasp01
 
e-Sealing at EADTU by Kamakshi Rajagopal
e-Sealing at EADTU by Kamakshi Rajagopale-Sealing at EADTU by Kamakshi Rajagopal
e-Sealing at EADTU by Kamakshi RajagopalEADTU
 
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...Nguyen Thanh Tu Collection
 
Andreas Schleicher presents at the launch of What does child empowerment mean...
Andreas Schleicher presents at the launch of What does child empowerment mean...Andreas Schleicher presents at the launch of What does child empowerment mean...
Andreas Schleicher presents at the launch of What does child empowerment mean...EduSkills OECD
 
Rich Dad Poor Dad ( PDFDrive.com )--.pdf
Rich Dad Poor Dad ( PDFDrive.com )--.pdfRich Dad Poor Dad ( PDFDrive.com )--.pdf
Rich Dad Poor Dad ( PDFDrive.com )--.pdfJerry Chew
 
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptx
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptxAnalyzing and resolving a communication crisis in Dhaka textiles LTD.pptx
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptxLimon Prince
 
How to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptxHow to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptxCeline George
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSAnaAcapella
 
How To Create Editable Tree View in Odoo 17
How To Create Editable Tree View in Odoo 17How To Create Editable Tree View in Odoo 17
How To Create Editable Tree View in Odoo 17Celine George
 
會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文
會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文
會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文中 央社
 
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...Nguyen Thanh Tu Collection
 
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...EADTU
 
UChicago CMSC 23320 - The Best Commit Messages of 2024
UChicago CMSC 23320 - The Best Commit Messages of 2024UChicago CMSC 23320 - The Best Commit Messages of 2024
UChicago CMSC 23320 - The Best Commit Messages of 2024Borja Sotomayor
 

Recently uploaded (20)

Contoh Aksi Nyata Refleksi Diri ( NUR ).pdf
Contoh Aksi Nyata Refleksi Diri ( NUR ).pdfContoh Aksi Nyata Refleksi Diri ( NUR ).pdf
Contoh Aksi Nyata Refleksi Diri ( NUR ).pdf
 
AIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.pptAIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.ppt
 
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 
e-Sealing at EADTU by Kamakshi Rajagopal
e-Sealing at EADTU by Kamakshi Rajagopale-Sealing at EADTU by Kamakshi Rajagopal
e-Sealing at EADTU by Kamakshi Rajagopal
 
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
 
Including Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdfIncluding Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdf
 
Andreas Schleicher presents at the launch of What does child empowerment mean...
Andreas Schleicher presents at the launch of What does child empowerment mean...Andreas Schleicher presents at the launch of What does child empowerment mean...
Andreas Schleicher presents at the launch of What does child empowerment mean...
 
Rich Dad Poor Dad ( PDFDrive.com )--.pdf
Rich Dad Poor Dad ( PDFDrive.com )--.pdfRich Dad Poor Dad ( PDFDrive.com )--.pdf
Rich Dad Poor Dad ( PDFDrive.com )--.pdf
 
ESSENTIAL of (CS/IT/IS) class 07 (Networks)
ESSENTIAL of (CS/IT/IS) class 07 (Networks)ESSENTIAL of (CS/IT/IS) class 07 (Networks)
ESSENTIAL of (CS/IT/IS) class 07 (Networks)
 
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptx
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptxAnalyzing and resolving a communication crisis in Dhaka textiles LTD.pptx
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptx
 
How to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptxHow to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptx
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
 
How To Create Editable Tree View in Odoo 17
How To Create Editable Tree View in Odoo 17How To Create Editable Tree View in Odoo 17
How To Create Editable Tree View in Odoo 17
 
VAMOS CUIDAR DO NOSSO PLANETA! .
VAMOS CUIDAR DO NOSSO PLANETA!                    .VAMOS CUIDAR DO NOSSO PLANETA!                    .
VAMOS CUIDAR DO NOSSO PLANETA! .
 
OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...
 
會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文
會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文
會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文會考英文
 
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...
ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH FORM 50 CÂU TRẮC NGHI...
 
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
 
UChicago CMSC 23320 - The Best Commit Messages of 2024
UChicago CMSC 23320 - The Best Commit Messages of 2024UChicago CMSC 23320 - The Best Commit Messages of 2024
UChicago CMSC 23320 - The Best Commit Messages of 2024
 

Barclays Disaster Preparedness Presentation | BCCJ

  • 1. BCCJ Risk Seminar - City Flood and Water Hazard Risk- Version Final_D 4 October 2018 Yasutake Sayanagi Barclays Japan Group Resilience
  • 2. 2 | <BCCJ Risk Seminar 2018> | <4 October 2018> 1. Introduction 1) Lessons leant form the Hiroshima severe Rain disaster (2018), Hurricane Katrina in US (2005) and Flooding in Thailand (2011/2013), City Flood is one of the most critical issues with safety and Business Continuity. Actually, the provability of City Flood is much higher than earthquakes. And it could happen in Tokyo Metropolitan area. 2) Same as the other disaster, reviewing with Hazard Maps to make a plan can minimize the impacts from the disaster because most of the actual disaster happened in the high risk area suggested on the Hazard Map. 3) City Flood mainly consists of Flooding from rivers (Gaisui - hanran) and Flooding from inland waters (Naisui - hanran) caused by Severe Weather and Typhoon which became more serious due to the global warming. On the top of that High Tide are also increasing City Flood Risk as those block draining system. 4) Unfortunately more than 99.9% of disaster related information/news in Japan is still made in Japanese language only or takes time for make English translation. So I will pick useful information both Japanese and English up for you. 5) During the presentation, I will introduce “Pre-Evacuation” and “Home BCP” to minimize risk for your families and partners. © Copyright Barclays 2018 (all rights reserved)
  • 3. 3 | <BCCJ Risk Seminar 2018> | <4 October 2018> 1) To introduce basic knowledge with City Flood 2) To review high risk area in Kanto region and Tokyo 3) To know more about Hazard Maps 4) To share sample impact Analysis 5) To introduce Barclays’ Home BCP 6) To show useful information source 2. Purpose of this presentation © Copyright Barclays 2018 (all rights reserved)
  • 4. 4 | <BCCJ Risk Seminar 2018> | <4 October 2018> Basic Knowledge with Tokyo City Flood © Copyright Barclays 2018 (all rights reserved)
  • 5. 5 | <BCCJ Risk Seminar 2018> | <4 October 2018> 3. History of Tokyo City Flood Tokyo Metropolitan Government: http://www.kensetsu.metro.tokyo.jp/suiga i_kiroku/kako.htm Tokyo City Flood: From 2000 to 2015, we had 104 City Floods in Tokyo and total of 661ha (13 times bigger than Tokyo Disney land) were damaged. 2011 – 2015 (27 Times 285ha were damaged 2006 – 2010 (31 Times 81ha were damaged 2000 – 2005 (46 Times 295ha were damaged © Copyright Barclays 2018 (all rights reserved)
  • 6. 6 | <BCCJ Risk Seminar 2018> | <4 October 2018> Dams Rivers 4. City Flood and Water Draining System Ministry of Land, Infrastructure, Transport and Tourism: http://www.pref.shimane.lg.jp/kasen/kando gawa/kankyo.data/shitsumidamugaiyo.pdf ④ Capacity of Dams ⑤ Capacity of rivers Ministry of Land, Infrastructure, Transport and Tourism: https://www.kkr.mlit.go.jp/yamato/ab out/glossary/18.html Ministry of Land, Infrastructure, Transport and Tourism: http://www.skr.mlit.go.jp/nakagawa/ disaster-prev/eq/tsunami-type.html ⑦ Strong Wind push water back Sea 1) Major factor of City Flood ① Heavy Rain in the Mountain ② Heavy Rain in the City ③ High Tide 2) Sub factor of City Flood ④ Capacity of Dams ⑤ Capacity of Rivers ⑥ Capacity of Water Draining System ⑦ Strong Wind of Typhoon ⑧ Low Pressure of Typhoon ⑨ Tide by Moon Flooding from rivers ② Heavy Rain in the City “City Flood happens when the Water Draining System fail to work due to the over capacity” ③ High Tide ① Heavy Rain in the Mountain ⑥ Over capacity of Draining system push water back to the residential area Flooding from inland water Okayama City: http://www.city.okayama.jp/gesui/keikakucyousei/keikakucyo usei_00114.html ⑧ Low Pressure sucking water up ⑨ Tide by Moon © Copyright Barclays 2018 (all rights reserved)
  • 7. 7 | <BCCJ Risk Seminar 2018> | <4 October 2018> 5. About Typhoon 1) 15 out of 78 Typhoons (19.2%) gave impact with Tokyo Metropolitan Area in the last 3 years (as of 1 Oct 2018). 2) Sea surface temperature is 1 to 2 degrees Celsius higher than 2017 around Japan which makes Typhoon bigger and stronger (as of 1 Oct 2018). For example Typhoon 24 (Trami) had 11m high tide/waves as well as heavy rain and strong wind. Weather news: http://weathernews.jp/ JMA: https://www.data.jma.go.jp/kaiyou/data/db/kaikyo/daily/sst_HQ.html Sea surface temperature deference Height of waves with Typhoon Trami © Copyright Barclays 2018 (all rights reserved)
  • 8. 8 | <BCCJ Risk Seminar 2018> | <4 October 2018> 6. Flooding from the Rivers 1) There are 3 rivers (Tone River, Ara River and Tama River) which make a flood in Tokyo Metropolitan area. 2) Especially between Tone River and Ara River as well the East side of Tokyo are high risk area of Flooding from the Rivers 3) We should monitor the heavy rain situation not only in Tokyo but also in the upper reaches of those rivers because tons of water will come to Tokyo Metropolitan area in a few hours Yahoo Japan: https://typhoon.yahoo.co.jp/weather/river/ © Copyright Barclays 2018 (all rights reserved)
  • 9. 9 | <BCCJ Risk Seminar 2018> | <4 October 2018> Potential High risk area around Tokyo © Copyright Barclays 2018 (all rights reserved)
  • 10. 10 | <BCCJ Risk Seminar 2018> | <4 October 2018> 7. Review Kanto district Land history Asia Air Survey Co.,Ltd : http://www.ajiko.co.jp/yomimono/imamura03.html 1) Seafront (6,000 years ago)  6m adjusted Map shows the ancient seafront. Blue area mainly consists of the soft soil and sand as it was under the water 6,000 years ago. Dry land is far smaller than today.  Particularly Area stated Red Ovals (Zone 1 and Zone 2) have high risk with flooding and Liquefactions risk. 6m adjusted Map (Seafront of 6,000 years ago) 2 2) Eastward diversion of Tone River (400 years ago)  About 400 years ago, Tokugawa shogun decided diverting Tone- river from Zone 1 to Zone 2 to create a dry land in the east side of Edo (Tokyo) . This is a reason why East Tokyo is low land. Imperial Household Agency http://www.kunaicho.go.jp/okotoba/02/koen/koen-h18az-mizuforum4th-e.html © Copyright Barclays 2018 (all rights reserved)
  • 11. 11 | <BCCJ Risk Seminar 2018> | <4 October 2018> 8 Review Tokyo Altitude Overview Geographical Information Authority of Japan: http://www.gsi.go.jp/common/000061694.pdf 1) West side of 23 Wards  West side of Keihin- Tohoku line are so-called ‘Yamanote’ and mostly 20- 40m from the sea level.  This area is based on the hard soil. 2) East side of 23 Wards  East side of Keihin- Tohoku line are so-called ‘Shitamachi’ and mostly less than 5m from the sea level.  This area is based on the soft soil as it was below sea level thus having risk with liquefactions and flooding compare with ‘Yamanote’. © Copyright Barclays 2018 (all rights reserved)
  • 12. 12 | <BCCJ Risk Seminar 2018> | <4 October 2018> City Flood Hazard Map © Copyright Barclays 2018 (all rights reserved)
  • 13. 13 | <BCCJ Risk Seminar 2018> | <4 October 2018> 9. Hazard Maps 1) Hazard Maps are very useful information source with the natural disaster such as Flooding, Tsunami and Liquefaction as well as the public support you may use such as the public evacuation place. 2) Tokyo Metropolitan Government and each City Hall of 23 Wards have Hazard Maps. I strongly recommend you to download or have it from the City Hall of your home, school of your kids and your working place. And understand risk with those places. 3) Then please have a discussion with your family or partner where you should live and where you to evacuate. 4) This is the first step of the Solution Development. © Copyright Barclays 2018 (all rights reserved)
  • 14. 14 | <BCCJ Risk Seminar 2018> | <4 October 2018> 10. Case Study – Why we should know about Hazard Maps High Risk Area of Flood Hazard Map Actual Flooding area Mainichi News: https://mainichi.jp/articles/20180714/k00/00m/040/217000c In the Hiroshima disaster 2018, actual Flooding area is almost same as the High Risk Area of Flood Hazard Map. Asahi News https://www.asahi.com/articles/ASL7956K2L79PTIL02N.h tml © Copyright Barclays 2018 (all rights reserved)
  • 15. 15 | <BCCJ Risk Seminar 2018> | <4 October 2018> 11. Minato-ku: Flood Hazard Map Minato- Ku: https://www.city.minato.tokyo.jp/dobokukeikaku/bosai-anzen/bosai/shinsui/hazard-map/documents/omote-eigo.pdf 1) Some areas in Minato-ku have 0.50-1.0m Flood risk when heavy rain exceeded sewer system and river drainage capacity. 2) It is important for you to discuss with your family or partner about Flood risk around your house, kids’ school and identify evacuation place and how to get there safely. 3) Though your house is safe to stay, you should keep sufficient stock of foods and water as well as special kit with toilet. Also you should consider electric power supply will be damaged by flooding. © Copyright Barclays 2018 (all rights reserved)
  • 16. 16 | <BCCJ Risk Seminar 2018> | <4 October 2018> 5 minutes QA Session 1/3 © Copyright Barclays 2018 (all rights reserved)
  • 17. 17 | <BCCJ Risk Seminar 2018> | <4 October 2018> Sample Impact Analysis © Copyright Barclays 2018 (all rights reserved)
  • 18. 18 | <BCCJ Risk Seminar 2018> | <4 October 2018> 12. Flood risk and Public Transportations 1/2 Special committee in Cabinet office Japan http://www.bousai.go.jp/kaigirep/chuobou/senmon/daikibosuigai/index.html 1) In 2010, Special Committee in Cabinet Office Japan reported with the impact of Tokyo City Flood caused by Ara-River over flow. Some solutions were implemented after this report to minimize impacts. 2) According to the report, once Ara- River flood happens, plenty of water comes into Tokyo Metro (under ground) and make it go under water in 12 - 24 hours Japan Meteorological Agency: https://www.jma.go.jp/jma/kishou/know/tenki_chuui/tenki _chuui_p3.html © Copyright Barclays 2018 (all rights reserved)
  • 19. 19 | <BCCJ Risk Seminar 2018> | <4 October 2018> 13. Flood risk and Public Transportations 2/2 Special committee in Cabinet office Japan http://www.bousai.go.jp/kaigirep/chuobou/senmon/daikibosuigai/pdf/090123_shiryo_8.pdf According to the worst scenario with Ara-River Flood, most of the stations of Tozai-line and Hibiya-line goes under water in 15 hours (stated Red arrows) . Same situation will be happened other Metro lines as well. © Copyright Barclays 2018 (all rights reserved)
  • 20. 20 | <BCCJ Risk Seminar 2018> | <4 October 2018> 14. What happens after the City Flood Special committee in Cabinet office Japan http://www.bousai.go.jp/kaigirep/chuobou/senmon/daikibosuigai/index.html Main Issues are as follows;  Sewage and dirty / polluted water  Distributions / Supply Chain for food and water etc.  Health and safety Referring to the cases with the flood in Thailand and Hurricane Katrina in US, those bad situation lasts more than a month and not easy to restore infrastructures such as public transportation mainly due to the dirty water and debris. © Copyright Barclays 2018 (all rights reserved)
  • 21. 21 | <BCCJ Risk Seminar 2018> | <4 October 2018> Solution Development © Copyright Barclays 2018 (all rights reserved)
  • 22. 22 | <BCCJ Risk Seminar 2018> | <4 October 2018> 15. Let’s think about Family and Partner’s safety 1) Japanese Government well prepared prevention plan with City Flood however it is better you to know the high risk area and potential evacuation route. 2) One of the purposes of creating Home BCP (will be explained in detail on the following slides) is improving your Family and Partner’s safety. 3) If you live in the area where you have less risk with Flooding, Liquefaction, Earthquake or Fire etc., your Family and Partner can save time with evacuation when disaster happens and much safer than living in the high risk area suggested on the Hazard Map. Same as the school of your kids. 4) Moving to the less risk area before disaster makes sense. This is the concept so-called ‘Pre-Evacuation’. 5) Now you know that high risk area, you can make a choice;  Nice view vs. Family and Partner’s Safety  Conferrable Commute vs. Family and Partner’s Safety © Copyright Barclays 2018 (all rights reserved)
  • 23. 23 | <BCCJ Risk Seminar 2018> | <4 October 2018> Sample Solution Development - Home BCP - © Copyright Barclays 2018 (all rights reserved)
  • 24. 24 | <BCCJ Risk Seminar 2018> | <4 October 2018> 16. Home BCP 1) Why we should have Home BCP  Home BCP was developed in Barclays Japan to support having survival plans for employees’ Family and Partner.  Employee cannot work for the company during the disaster without confirming safety of Family and Partner, thus company must support 1) Risk Awareness, 2) Creating Plan and 3) improving it. 2) Home BCP consists of Home BCP Pocket Card and a guide for emergency stock  Contents of BCP Pocket Card  Communication (Contact information)  Daytime location  Medical information  Meeting point (Assembly point)  Pick up plan for kids  Embassy information and other information  Emergency Stock (Must have)  Food  Water (Drinking Water and Other Water)  Toilet © Copyright Barclays 2018 (all rights reserved)
  • 25. 25 | <BCCJ Risk Seminar 2018> | <4 October 2018> 17. Home BCP: Sample Contents of Home BCP Assembly Points  Discuss The Primary Assembly Point with your Family as Mobile will be down within 30 minutes  Discuss about the Secondary Assembly Point too.  Decide on communication methodology if the Family cannot meet (for example messaging boards) School Info  Confirm teacher's landline telephone number, e-mail address and mobile number  Confirm procedures to have your children picked up if both parents will be unavailable  Confirm procedures if nobody will be available to pick up your children Communication  Mobile phone and e-mail: Convenient, but availability may be limited following a disaster  Landline: Advisable to have one as they are much more stable than mobile lines  Social networks: are generally good but you should take the age of your children into account Daytime location Medical Information Embassy Information © Copyright Barclays 2018 (all rights reserved)
  • 26. 26 | <BCCJ Risk Seminar 2018> | <4 October 2018> 18. About an emergency stock Water、Food and Toilet are must have emergency stock items Basic requirements with emergency stock used be 3-5 days but considered with Flood risk, lifeline and distribution lines will be malfunctioned for 2 – 4 weeks  Drinking Water  On average 1 person needs 2L/day(Resulting 1 family with 2 kids needs 112L in 2 weeks) (Adult needs 50cc /1kg (weight), baby needs 150cc / 1kg and child needs 100cc / 1kg)  Tap water can be used in 3 days. After that reused it to Bath or Washing machine  Other Water(washing body and closes etc)  Drinking water and Other water should be managed separately  Dish must be covered by wrap to save water  Food  Pre-cooked food is recommended  High calorie food and good balanced food should be selected  Toilet  Cover the toilet in your home by the special plastic bag © Copyright Barclays 2018 (all rights reserved)
  • 27. 27 | <BCCJ Risk Seminar 2018> | <4 October 2018> 5 minutes QA Session 2/3 © Copyright Barclays 2018 (all rights reserved)
  • 28. 28 | <BCCJ Risk Seminar 2018> | <4 October 2018> Appendix © Copyright Barclays 2018 (all rights reserved)
  • 29. 29 | <BCCJ Risk Seminar 2018> | <4 October 2018> A-1. Sample Emergency Stock - Food <Basic Points to be considered with >  Should be Pre-cooked  Should contain a High calorie  Should be with Long life  Should not be too Hot or Spicy  Should be with a Good natural balance  Dish should be covered by a Wrap Amazon https://www.amazon.co.jp/ © Copyright Barclays 2018 (all rights reserved)
  • 30. 30 | <BCCJ Risk Seminar 2018> | <4 October 2018> A-2. Sample Emergency Stock - Drinking Water < Basic Points to be considered with > 1) Drinking Water  2L per person a day  Long Life Pet bottle  Water server is good to use (12L per bottle)  Tap water can be used for drinking (3 days ) http://www.city.nerima.tokyo.jp/kusei/koho/oshirase/sinsai_tai o/kumioki.files/kumioki.pdf Good to have A filter for emergency 2) Other Water  Should keep clean water in a bathtub (150L) for everything except for Drinking and Cooking Amazon https://www.amazon.co.jp/ © Copyright Barclays 2018 (all rights reserved)
  • 31. 31 | <BCCJ Risk Seminar 2018> | <4 October 2018> A-3. Sample Emergency Stock - Goods for toilet < Basic Points to be considered with > 1) Can not use water to flash 2) We should;  Use existing toilet with plastic bag  Use those with deodorizer  Do not forget buying Toilet paper and Wet tissue  Covered it by Another plastic bag for disposal Amazon https://www.amazon.co.jp/ © Copyright Barclays 2018 (all rights reserved)
  • 32. 32 | <BCCJ Risk Seminar 2018> | <4 October 2018> A-4. Useful Information Source 1) Disaster Preparedness Tokyo (Tokyo Metropolitan Government)  Japanese: http://www.bousai.metro.tokyo.jp/index.html  English: http://www.bousai.metro.tokyo.jp/english/index.html 2) Earthquake Survival Manual  Japanese/English: http://www.myanmar-embassy-tokyo.net/eq/eq-survival-manual.pdf 3) Assistance for Foreigners at Times of Disaster Q & A Manual by Tokyo International Communication Committee  English: http://www.tokyo-icc.jp/information/pdf/qa_en.pdf 4) Disaster Management in Japan  Japanese / English: http://www.bousai.go.jp/1info/pdf/saigaipanf_e.pdf © Copyright Barclays 2018 (all rights reserved)
  • 33. 33 | <BCCJ Risk Seminar 2018> | <4 October 2018> A-5. Going home support Tokyo Metropolitan Government http://map.bousai.metro.tokyo.jp/en/pc/ There is a website to support you to go back to your house during the disaster © Copyright Barclays 2018 (all rights reserved)
  • 34. 34 | <BCCJ Risk Seminar 2018> | <4 October 2018> A-6. Fire Hazard (Earthquake) Tokyo Metropolitan Government: http://www.toshiseibi.metro.tokyo.jp/bosai/chousa_6/download/kikendo.pdf?1802 1) Tokyo Metropolitan Government announced about Fire Hazard risk. 2) Though this is based on the scenario analysis with Earthquake, we could see the area where Fire can be occurred and not easy to work for Firefighters. 3) We could see many Wooden made houses are close to each other and road width © Copyright Barclays 2018 (all rights reserved)
  • 35. 35 | <BCCJ Risk Seminar 2018> | <4 October 2018> A-7. Traffic Restrictions (Earthquake) Tokyo Metropolitan Police Department: http://www.keishicho.metro.tokyo.jp/kurashi/saigai/shinsai_kisei/kisei/index.files/english_270309.pdf 1) Tokyo Metropolitan Police Department announced that they enforce City Block when the big earthquake happens in Tokyo. 2) In side of Kannana ring road and Key/Major road such as Route 20 are controlled and authorized emergency vehicles only. 3) Please take this into account and it will be affected your evacuation plan. © Copyright Barclays 2018 (all rights reserved)
  • 36. 36 | <BCCJ Risk Seminar 2018> | <4 October 2018> A-8. Intensity of Typhoon Note that the definition of "typhoon" is different between the Japanese standard and the international http://agora.ex.nii.ac.jp/digital-typhoon/help/unit.html.en © Copyright Barclays 2018 (all rights reserved)
  • 37. 37 | <BCCJ Risk Seminar 2018> | <4 October 2018> A-9. Weather Warning /Advisory JMA: http://www.jma.go.jp/jma/en/Emergency_Warning/examples_of_responses.png © Copyright Barclays 2018 (all rights reserved)
  • 38. 38 | <BCCJ Risk Seminar 2018> | <4 October 2018> Closing QA Session 3/3 © Copyright Barclays 2018 (all rights reserved)
  • 39. 39 | <BCCJ Risk Seminar 2018> | <4 October 2018> Disclaimer 1/5 © Copyright Barclays 2018 (all rights reserved) BARCLAYS This communication has been prepared by Barclays. “Barclays” means any entity within the Barclays Group of companies, where “Barclays Group” means Barclays Bank PLC, Barclays PLC and any of their subsidiaries, affiliates, ultimate holding company and any subsidiaries or affiliates of such holding company. CONFLICT OF INTERESTS BARCLAYS IS A FULL SERVICE INVESTMENT BANK. In the normal course of offering investment banking products and services to clients, Barclays may act in several capacities (including issuer, market maker and/or liquidity provider, underwriter, distributor, index sponsor, swap counterparty and calculation agent) simultaneously with respect to a Product, giving rise to potential conflict of interests which may impact the performance of a Product. NOT RESEARCH This document is not a product of the Barclays Research department. Any views expressed may differ from those of Barclays Research. BARCLAYS POSITIONS Barclays may at any time acquire, hold or dispose of long or short positions (including hedging and trading positions) and trade or otherwise effect transactions for their own account or the account of their customers in the products referred to herein which may impact the performance of a Product. PRIVATE INFORMATION BARCLAYS MAY HAVE PRIVATE INFORMATION ABOUT ANY PRODUCT AND/OR THE UNDERLYING ASSETS REFERENCED BY THE PRODUCT. It is not obligated to disclose any such information to you. FOR INFORMATION ONLY THIS DOCUMENT IS PROVIDED FOR INFORMATION PURPOSES ONLY AND IS SUBJECT TO CHANGE. IT IS INDICATIVE ONLY AND IS NOT BINDING.
  • 40. 40 | <BCCJ Risk Seminar 2018> | <4 October 2018> Disclaimer 2/5 © Copyright Barclays 2018 (all rights reserved) NO OFFER Barclays is not offering to sell or seeking to buy any Product or enter into any transaction. Any offer or entry into any transaction requires Barclays’ subsequent formal agreement which will be subject to internal approvals and execution of binding transaction documents. NO LIABILITY Neither Barclays nor any of its directors, officers, employees, representatives or agents, accepts any liability whatsoever for any direct, indirect or consequential losses (in contract, tort or otherwise) arising from the use of this document or its contents or reliance on the information contained herein, except to the extent this would be prohibited by law or regulation. NO ADVICE Barclays is acting solely as principal and not as fiduciary. Barclays does not provide, and has not provided, any investment advice or personal recommendation to you in relation to the transaction and/or any related securities described herein and is not responsible for providing or arranging for the provision of any general financial, strategic or specialist advice, including legal, regulatory, accounting, model auditing or taxation advice or services or any other services in relation to the transaction and/or any related securities described herein. Accordingly Barclays is under no obligation to, and shall not, determine the suitability for you of the transaction described herein. You must determine, on your own behalf or through independent professional advice, the merits, terms, conditions and risks of the transaction described herein. THIRD PARTY INFORMATION Barclays is not responsible for information stated to be obtained or derived from third party sources or statistical services. DISTRIBUTION All laws and regulations in any relevant jurisdiction(s) must be complied with when offering, marketing or selling a Product or distributing offering materials. PAST PERFORMANCE Any past or simulated past performance including back-testing, modelling or scenario analysis contained in this document is no indication as to future performance. No representation is made as to the accuracy of the assumptions made within, or completeness of, any modelling, scenario analysis or back-testing.
  • 41. 41 | <BCCJ Risk Seminar 2018> | <4 October 2018> Disclaimer 3/5 © Copyright Barclays 2018 (all rights reserved) OPINIONS SUBJECT TO CHANGE All opinions and estimates are given as of the date hereof and are subject to change. The value of any investment may also fluctuate as a result of market changes. Barclays is not obliged to inform the recipients of this document of any change to such opinions or estimates. NOT FOR RETAIL This document is being directed at persons who are professionals and is not intended for retail customer use. REGULATORY DISCLOSURE Information relating to an investment may be disclosed when required by regulators or other authorities, including tax authorities. TAX DISCLOSURE All discussions and any related materials relating to the tax treatment or tax structure of any transactions described in this document (including any attachments) may be disclosed without limitation. This authorisation of tax disclosure supersedes anything to the contrary contained in this document or otherwise communicated. CONFIDENTIAL This document is confidential and is for the benefit and internal use of the recipient for the purpose of considering the securities/transaction described herein, and no part of it may be reproduced, distributed or transmitted without the prior written permission of Barclays. ABOUT BARCLAYS Barclays offers premier investment banking products and services to its clients through Barclays Bank PLC. Barclays Bank PLC is authorised by the Prudential Regulation Authority and regulated by the Financial Conduct Authority and the Prudential Regulation Authority and is a member of the London Stock Exchange. Barclays Bank PLC is registered in England No. 1026167 with its registered office at 1 Churchill Place, London E14 5HP. Barclays Securities Japan Limited is a joint-stock company incorporated in Japan with registered office of 6-10-1, Roppongi, Minato-ku, Tokyo 106-6131, Japan. It is a subsidiary of Barclays Bank PLC and a financial instruments firm regulated by the Financial Services Agency of Japan. Registered Number: Kanto Zaimukyokucho (kinsho) No. 143.
  • 42. 42 | <BCCJ Risk Seminar 2018> | <4 October 2018> COPYRIGHT © Copyright Barclays 2018 (all rights reserved). MATTERS TO BE INDICATED IN ADVERTISEMENT, ETC. Barclays Securities Japan Limited is a financial instruments business operator (kinyushohin torihikigyosha) regulated by the Financial Services Agency of Japan. Registered Number: Kanto Zaimukyokucho (kinsho) No. 143. It is a member of the Japan Securities Dealers Association, the Financial Futures Association of Japan and Type II Financial Instruments Firms Association. This event given by Barclays may have the purpose to solicit the execution of financial instrument transactions with Barclays. When you enter into transactions involving financial instruments sold by Barclays, you may be required to pay charges, fees or expenses for each financial instrument. You may also be required, by prior agreement with Barclays, to deposit margin and/or other cash guarantee (“Cash Guarantee”), depending on the type of transaction, such as derivative and margin transactions, that you enter into with Barclays. For certain transactions, the notional amount of the transaction may exceed the amount of Cash Guarantee (i.e., the ratio of the notional amount of transaction compared to the amount of Cash Guarantee cannot be calculated in advance, since the specific terms of the transaction may not have yet been determined). PLEASE BE AWARE OF THE RISK THAT YOU MAY INCUR LOSSES IN CONNECTION WITH YOUR INVESTMENT CAUSED BY VARIOUS FACTORS INCLUDING, WITHOUT LIMITATION, FLUCTUATIONS IN THE INTEREST RATES, CURRENCY VALUES, OR PRICES OR OTHER INDICES IN THE FINANCIAL INSTRUMENT MARKET AND THAT YOUR POSSIBLE LOSSES MAY EXCEED THE AMOUNT OF CASH GUARANTEE YOU HAVE DEPOSITED BECAUSE OF SUCH FACTORS. Disclaimer 4/5 © Copyright Barclays 2018 (all rights reserved)
  • 43. 43 | <BCCJ Risk Seminar 2018> | <4 October 2018> Disclaimer 5/5 © Copyright Barclays 2018 (all rights reserved) In relation to over-the-counter derivative transactions, the indicative price for purchasing financial instruments from Barclays will differ from that for selling financial instruments. In addition, there is a risk that you may lose your principal or that you may incur losses exceeding the amount of your original investment in connection with the sale or other transactions involving financial instruments which you enter into with Barclays because of a change in the business or creditworthiness of the person engaging in such sale or such other transactions involving financial instruments or any other person. There is also a risk that there may be a limitation period in which to exercise any right that is derived from such sale or such other transactions involving financial instruments or in which contracts relating to the sale or entry into other transactions involving such financial instruments may be cancelled. Please read carefully the documents which have been delivered to you prior to the execution of any agreement, prospectus and other marketing materials and be aware that the fees and commissions which are payable and the risks involved may differ depending on the type of financial instrument, as mentioned above.
  • 44. 44 | <BCCJ Risk Seminar 2018> | <4 October 2018> Thank you very much © Copyright Barclays 2018 (all rights reserved)