SlideShare a Scribd company logo
Introduction –kstps
By Avdhesh kumar meena
B.Tech 4th Year Electrical Branch
NIET Alwar Rajasthan
INDEX
0. KSTPS PICTURES
1.INTRODUCTION
2. GENERAL LAYOUT AND BASIC IDEA
3.TURBO GENERATOR
4.COOLING SYSTEM
5.TRANSFORMERS
Looking at surface
1. INTRODUCTION
•Kota Super Thermal Power Station is the
first coal based Electricity Generating station
in rajasthan.
•At present the total installedcapacity of
KSTPS is 1240 MW.
• KSTPS has received Meritories
productivity awards during 1984, 1987,
1989, 1981 and every year since 1992
onwards.
K.S.T.P.S. IS DESISIGNED IN
FOLLOWING STAGES:-
STAGE I - 2x110 MW
STAGE II - 2X210 MW
STAGE III - 1X210 MW
STAGE IV - 1X195 MW
STAGE V - 1X195MW
Stage Unit number
Installed capacity
(MW)
Date of
commissioning
Status
Stage I 1 110 January 1983 Running
Stage I 2 110 July, 1983 Running
Stage II 3 210 September 1988 Running
Stage II 4 210 May, 1989 Running
Stage III 5 210 March 1994 Running
Stage IV 6 195 July, 2003 Running
Stage V 7 195 May 2009
Running
Installed capacity
•The planning commission cleared the
project report in Sept., 1976 for
installation of two units each of 110 MW
in first estimated cost of Rs. 143 Crores .
•And finally stage fifth Unit #7 costed
approximately Rs. 961 Crores.
COAL:
1.Northern Coal Fields Limited(NCL),
2.South Eastern Coal Fields
Limited(SECL)
• Coal India limited is supply coal from
its coal mines of coal producing
subsidiaries SECL & NCL to Kota
Thermal Power Station through
railway wagons.
• The average distances of SECL, NCL are
800, 950 Kms. respectively.
WATER:-
•The source of water for power station is
reservoir formed by Kota Barrage on the
Chambal River.
• In case of large capacity plants huge
quantities of coal and water is required.
2. General Layout & Basic Idea
•The Kota Thermal Power Station is divided into four
main circuits :
1.Fuel and Ash Circuit.
2 .Air and Gas Circuit.
3.Feed water and Steam Circuit.
4.Cooling Water Circuit.
• A control system of station basically works on Rankin
Cycle.
(a).COAL HANDLING PLANT
•It can be called the heart of thermal power plant because it
provided the fuel for combustion in boiler.
•Everyday 6 to 7 trains of coal are unloaded at KSTPS.
• Each train consists of 58 wagons and each wagons consists of
50 tones of coal.
• The approximate per day consumption at KSTPS is about
18000 metric tones.
• The whole transportation of coal is through
conveyor belt operated by 3-Ø Induction motor.
• It costs approximate 4.5 crores of rupees per day
including transportation expenses.
•The coal handling plant can broadly be divided into
thre sections.
1) Wagon Unloading system.
2) Crushing System.
3) Conveying System.
(b) ASH HANDLING PLANT
• This plant can be divided into 3 sub plants as follows:-
1)Fuel and Ash Plant.
2)Air and Gas Plant.
3)Ash Disposal and & Dust Collection Plant
USES ASH:
1.Manufacturing of building materials.
2.Making of concrete.
3.Manufacturing of pozzuolana cement.
4. Road construction
(C). ELECTRO-STATIC PRECIPITATOR
•As far as air pollution is concerned now a days various
flue gases filter are there in service.
•
•These filters are E.S.P. Fabric filter high efficiency
cyclone separations and sitelling room.
•where the particle size vary from 0.75 microns to 100
micron use gradually use E.S.P. to purify the flue gases
due to its higher efficiency & low running cost etc.
6.TURBO GENERATOR
THEORY :-
•TURBO GENERATOR manufactured by B.H.E.L.
• The generator stator is a tight construction, supporting &
enclosing the stator windings, core and hydrogen coolers.
• The generator is driven by directly coupled steam turbine
at a speed of 3000 r. p. m. the Generator is designed for
continuous operation at the rated output.
• The source of excitation of rotor windings is thyristor
controlled D.C. supply.
TECHNICAL DATA:-
Generator (110 MW):-
Type : t.g.p. 2,34,602
Continuous apparent power : 1,37,500 KVA.
Active power : 7,10,000 KW.
Power factor : 0.8 (lagging).
Rated voltage : 1000 + 5% rated.
Current : 7,220 A
Critical speed : 3000 r. p. m. at
frequency : 50 Hz.
Phase connection : double star.
No. of terminals : 6.
Main diameter of slip rings : 420 mm.
Voltage regulation : 39%.
Reactance : Infor
Main parts of generator:-
(a)STATOR:-
STATOR FRAME:-
The stator frame of welded steel frame construction.
STATOR CORE:-
•It is built up of special sheet laminations and whose assembly is supported by a special
guide bass.
STATOR BARS:-
•Stator bars are manufactured as half bars, For an equal length along the bar.
STATOR WINDINGS:-
•Stator windings are double star layers , lap wound, three phase, short pitch type.
• Phases are connected to form a double star winding.
TERMINAL BUSHINGS:-
• The conductor of Generator terminal bushing having hollow copper tubes with Copper
brazed at the ends to avoid leakage of hydrogen.
BEARINGS:-
Generator bearings have electrical seats of consists of steel bodies with removable steel
pads.
HYDROGEN COOLERS:-
•Three Hydrogen Coolers each comprising of two individual units are mounted inside the
stator frame.
VIBRATION OF ROTOR:
-
4.COOLING SYSTEM
a) GENERAL:-
•In KSTPS hydrogen cooling system is employed for generator cooling.
• Hydrogen is used for cooling medium primarily because of its superior cooling
properties & low density.
• Thermal conductivity of hydrogen 7.3 times of air.
• Its ability to transfer heat through forced convection is about 75% better than air.
b)HYDROGEN DRYERS:-
•Moisture in this gas is absorbed by silica gel in the dryer as the absorbed gas passes
through it.
•The silica gel is reactivated by heating.
10.TRANSFORMER
•Transformer is a static device which is used to change the voltage level keeping the power and frequency same.
•In the plant transformer is one of the most important equipment.
•It is located in between the main plant and the switchyard. The main transformers installed in the transformer yard are:
•GENERATOR TRANSFORMER (GT – A):-
It steps up the voltage from 16.5 KV to 220 KV. It connects the plant with the 220 KV switchyard.
•GENERATOR TRANSFORMER (GT – B):-
It steps up the voltage from 16.5 KV to 400 KV. It connects the plant with the 400 KV switchyard.
•STATION TRANSFORMER (ST):-
It is a step down transformer with 50 MVA capacities. It is used to step down 220 KV from the grid to 6.9 KV.
•AUXILIARY TRANSFORMER (UAT):-
It is a step down transformer with 20 MVA capacities. It steps down the voltage from 16.5 KV to 6.9 KV.
• STATION SERVICE TRANSFORMER (SST):-
It is a step down transformer with 2MVA capacity. It is used to step down from 6.6 KV to 0.4333 KV.
• UNIT SERVICE TRANSFORMER (UST):-
It is a step down transformer with 2 MVA capacity. It is used to step down from 6.6 kV to 0.4333 KV.
Thanks

More Related Content

What's hot

NTPC BARH, BIHAR
NTPC BARH, BIHARNTPC BARH, BIHAR
NTPC BARH, BIHAR
Aditya Empire
 
Ntpc kahalgaon project by bhanu kishan
Ntpc kahalgaon project by bhanu kishanNtpc kahalgaon project by bhanu kishan
Ntpc kahalgaon project by bhanu kishan
BHANUKISHAN1
 
KBUNL - NTPC KANTI MUZAFFARPUR BIHAR
KBUNL - NTPC KANTI MUZAFFARPUR BIHARKBUNL - NTPC KANTI MUZAFFARPUR BIHAR
KBUNL - NTPC KANTI MUZAFFARPUR BIHAR
VIMAL VAIBHAV
 
Lovely Amit
Lovely AmitLovely Amit
Lovely Amit
Amit Kumar
 
thermal power station
thermal power stationthermal power station
thermal power station
Hari Ohm Singh
 
Shivesh ntpc ppt
Shivesh ntpc pptShivesh ntpc ppt
Shivesh ntpc ppt
Shivesh Sourabh
 
Indraprastha power
Indraprastha powerIndraprastha power
Indraprastha power
Anish Ansari
 
Pintu raj
Pintu rajPintu raj
Pintu raj
ritchaubey
 
Dev
DevDev
IPGCL/PPCL Training presentation
IPGCL/PPCL Training presentationIPGCL/PPCL Training presentation
IPGCL/PPCL Training presentation
Shubhra Dhyani
 
Ranjan NTPC KAHALGAON ppt
Ranjan  NTPC KAHALGAON pptRanjan  NTPC KAHALGAON ppt
Ranjan NTPC KAHALGAON ppt
Ranjan kumar
 
Bangladesh Power Stations & Power Plants Overview
Bangladesh Power Stations & Power Plants OverviewBangladesh Power Stations & Power Plants Overview
Bangladesh Power Stations & Power Plants Overview
Ridwanul Hoque
 
NTPC Singrauli
NTPC SingrauliNTPC Singrauli
NTPC Singrauli
Vinay Vishwakarma
 
Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)
Ajeet Chaurasia
 
Basics of Diesel Generator System
Basics of Diesel Generator SystemBasics of Diesel Generator System
Basics of Diesel Generator System
prabakaran G
 

What's hot (18)

NTPC BARH, BIHAR
NTPC BARH, BIHARNTPC BARH, BIHAR
NTPC BARH, BIHAR
 
Ntpc kahalgaon project by bhanu kishan
Ntpc kahalgaon project by bhanu kishanNtpc kahalgaon project by bhanu kishan
Ntpc kahalgaon project by bhanu kishan
 
KBUNL - NTPC KANTI MUZAFFARPUR BIHAR
KBUNL - NTPC KANTI MUZAFFARPUR BIHARKBUNL - NTPC KANTI MUZAFFARPUR BIHAR
KBUNL - NTPC KANTI MUZAFFARPUR BIHAR
 
Lovely Amit
Lovely AmitLovely Amit
Lovely Amit
 
thermal power station
thermal power stationthermal power station
thermal power station
 
Shivesh ntpc ppt
Shivesh ntpc pptShivesh ntpc ppt
Shivesh ntpc ppt
 
Indraprastha power
Indraprastha powerIndraprastha power
Indraprastha power
 
Pintu raj
Pintu rajPintu raj
Pintu raj
 
Dev
DevDev
Dev
 
IPGCL/PPCL Training presentation
IPGCL/PPCL Training presentationIPGCL/PPCL Training presentation
IPGCL/PPCL Training presentation
 
K.s.t.p.s. ppt
K.s.t.p.s.  pptK.s.t.p.s.  ppt
K.s.t.p.s. ppt
 
Ranjan NTPC KAHALGAON ppt
Ranjan  NTPC KAHALGAON pptRanjan  NTPC KAHALGAON ppt
Ranjan NTPC KAHALGAON ppt
 
Bangladesh Power Stations & Power Plants Overview
Bangladesh Power Stations & Power Plants OverviewBangladesh Power Stations & Power Plants Overview
Bangladesh Power Stations & Power Plants Overview
 
ntpc ppt
ntpc pptntpc ppt
ntpc ppt
 
project -2
project -2project -2
project -2
 
NTPC Singrauli
NTPC SingrauliNTPC Singrauli
NTPC Singrauli
 
Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)
 
Basics of Diesel Generator System
Basics of Diesel Generator SystemBasics of Diesel Generator System
Basics of Diesel Generator System
 

Similar to Avdhehs kumar presention kstps kota

Kstps ppt niet alwar
Kstps  ppt  niet alwarKstps  ppt  niet alwar
Kstps ppt niet alwar
Avdhesh kumar NIET
 
Kstps ppt niet alwar
Kstps  ppt  niet alwarKstps  ppt  niet alwar
Kstps ppt niet alwar
Avdhesh kumar NIET
 
Kstps ppt niet alwar
Kstps  ppt  niet alwarKstps  ppt  niet alwar
Kstps ppt niet alwar
Avdhesh kumar NIET
 
Kstps ppt
Kstps  pptKstps  ppt
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
Om Prakash
 
Vocational training at mejia thermal power plant
Vocational training at mejia thermal power plantVocational training at mejia thermal power plant
Vocational training at mejia thermal power plant
Nipak Banerjee
 
ntpc khalgaon
ntpc khalgaonntpc khalgaon
ntpc khalgaon
Vimal Tripathi
 
kota super thermal poer plant
kota super thermal poer plantkota super thermal poer plant
kota super thermal poer plant
Niranjan kumar sah
 
Kota super thermal power plant training report
Kota super thermal power plant training reportKota super thermal power plant training report
Kota super thermal power plant training report
Avinash Kumawat
 
Power plants in bangladesh
Power plants in bangladeshPower plants in bangladesh
Power plants in bangladesh
Imran Hossain
 
kstps training report
kstps training reportkstps training report
kstps training report
Omprakash Choudhary
 
A Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power StationA Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power Station
LekhraJ Meena
 
Naps
Naps Naps
NARENDRA MEENA REPORT AND PPT
NARENDRA MEENA  REPORT AND PPT NARENDRA MEENA  REPORT AND PPT
NARENDRA MEENA REPORT AND PPT
NarendraMeena41
 
C ktps training-report
C ktps training-reportC ktps training-report
C ktps training-reportAnil Saharan
 
Thermal Power Simulator Training
Thermal Power Simulator TrainingThermal Power Simulator Training
Thermal Power Simulator TrainingVedant Sumaria
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
Prakash Jarotia
 
Internship PPT final.pptx on ukai thermal power station
Internship PPT final.pptx on ukai thermal power stationInternship PPT final.pptx on ukai thermal power station
Internship PPT final.pptx on ukai thermal power station
malikavita731
 
Internship PPT ukai thermal power station .pptx
Internship PPT ukai thermal power station .pptxInternship PPT ukai thermal power station .pptx
Internship PPT ukai thermal power station .pptx
malikavita731
 
Internship PPT final ukai thermal power station
Internship PPT final ukai thermal power stationInternship PPT final ukai thermal power station
Internship PPT final ukai thermal power station
malikavita731
 

Similar to Avdhehs kumar presention kstps kota (20)

Kstps ppt niet alwar
Kstps  ppt  niet alwarKstps  ppt  niet alwar
Kstps ppt niet alwar
 
Kstps ppt niet alwar
Kstps  ppt  niet alwarKstps  ppt  niet alwar
Kstps ppt niet alwar
 
Kstps ppt niet alwar
Kstps  ppt  niet alwarKstps  ppt  niet alwar
Kstps ppt niet alwar
 
Kstps ppt
Kstps  pptKstps  ppt
Kstps ppt
 
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
 
Vocational training at mejia thermal power plant
Vocational training at mejia thermal power plantVocational training at mejia thermal power plant
Vocational training at mejia thermal power plant
 
ntpc khalgaon
ntpc khalgaonntpc khalgaon
ntpc khalgaon
 
kota super thermal poer plant
kota super thermal poer plantkota super thermal poer plant
kota super thermal poer plant
 
Kota super thermal power plant training report
Kota super thermal power plant training reportKota super thermal power plant training report
Kota super thermal power plant training report
 
Power plants in bangladesh
Power plants in bangladeshPower plants in bangladesh
Power plants in bangladesh
 
kstps training report
kstps training reportkstps training report
kstps training report
 
A Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power StationA Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power Station
 
Naps
Naps Naps
Naps
 
NARENDRA MEENA REPORT AND PPT
NARENDRA MEENA  REPORT AND PPT NARENDRA MEENA  REPORT AND PPT
NARENDRA MEENA REPORT AND PPT
 
C ktps training-report
C ktps training-reportC ktps training-report
C ktps training-report
 
Thermal Power Simulator Training
Thermal Power Simulator TrainingThermal Power Simulator Training
Thermal Power Simulator Training
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
 
Internship PPT final.pptx on ukai thermal power station
Internship PPT final.pptx on ukai thermal power stationInternship PPT final.pptx on ukai thermal power station
Internship PPT final.pptx on ukai thermal power station
 
Internship PPT ukai thermal power station .pptx
Internship PPT ukai thermal power station .pptxInternship PPT ukai thermal power station .pptx
Internship PPT ukai thermal power station .pptx
 
Internship PPT final ukai thermal power station
Internship PPT final ukai thermal power stationInternship PPT final ukai thermal power station
Internship PPT final ukai thermal power station
 

More from Avdhesh kumar NIET

Smart Home Appliance Control Niet Alwar
Smart Home  Appliance Control Niet AlwarSmart Home  Appliance Control Niet Alwar
Smart Home Appliance Control Niet Alwar
Avdhesh kumar NIET
 
Smart home appliance Control Niet Alwar
Smart home appliance Control Niet AlwarSmart home appliance Control Niet Alwar
Smart home appliance Control Niet Alwar
Avdhesh kumar NIET
 
Presentation instrument transformerr
Presentation instrument transformerrPresentation instrument transformerr
Presentation instrument transformerr
Avdhesh kumar NIET
 
Presentation Instrument Transformer NIET
Presentation Instrument Transformer  NIET Presentation Instrument Transformer  NIET
Presentation Instrument Transformer NIET
Avdhesh kumar NIET
 
Transmission network
Transmission  networkTransmission  network
Transmission network
Avdhesh kumar NIET
 
Transmission network
Transmission  networkTransmission  network
Transmission network
Avdhesh kumar NIET
 

More from Avdhesh kumar NIET (6)

Smart Home Appliance Control Niet Alwar
Smart Home  Appliance Control Niet AlwarSmart Home  Appliance Control Niet Alwar
Smart Home Appliance Control Niet Alwar
 
Smart home appliance Control Niet Alwar
Smart home appliance Control Niet AlwarSmart home appliance Control Niet Alwar
Smart home appliance Control Niet Alwar
 
Presentation instrument transformerr
Presentation instrument transformerrPresentation instrument transformerr
Presentation instrument transformerr
 
Presentation Instrument Transformer NIET
Presentation Instrument Transformer  NIET Presentation Instrument Transformer  NIET
Presentation Instrument Transformer NIET
 
Transmission network
Transmission  networkTransmission  network
Transmission network
 
Transmission network
Transmission  networkTransmission  network
Transmission network
 

Recently uploaded

WEEK 11 PART 1- SOULMAKING (ARTMAKING) (1).pdf
WEEK 11 PART 1- SOULMAKING (ARTMAKING) (1).pdfWEEK 11 PART 1- SOULMAKING (ARTMAKING) (1).pdf
WEEK 11 PART 1- SOULMAKING (ARTMAKING) (1).pdf
AntonetteLaurio1
 
Rishikesh @ℂall @Girls ꧁❤Book❤꧂@ℂall @Girls Service Vip Top Model Safe
Rishikesh  @ℂall @Girls ꧁❤Book❤꧂@ℂall @Girls Service Vip Top Model SafeRishikesh  @ℂall @Girls ꧁❤Book❤꧂@ℂall @Girls Service Vip Top Model Safe
Rishikesh @ℂall @Girls ꧁❤Book❤꧂@ℂall @Girls Service Vip Top Model Safe
hilij84961
 
Investors Data Sample containing data.csv.pdf
Investors Data Sample containing data.csv.pdfInvestors Data Sample containing data.csv.pdf
Investors Data Sample containing data.csv.pdf
danielses2
 
This is a certificate template for Daily Vacation Bible School Awards Can edi...
This is a certificate template for Daily Vacation Bible School Awards Can edi...This is a certificate template for Daily Vacation Bible School Awards Can edi...
This is a certificate template for Daily Vacation Bible School Awards Can edi...
RodilynColampit
 
The Last Polymath: Muntadher Saleh‎‎‎‎‎‎‎‎‎‎‎‎
The Last Polymath: Muntadher Saleh‎‎‎‎‎‎‎‎‎‎‎‎The Last Polymath: Muntadher Saleh‎‎‎‎‎‎‎‎‎‎‎‎
The Last Polymath: Muntadher Saleh‎‎‎‎‎‎‎‎‎‎‎‎
iraqartsandculture
 
Fashionista Chic Couture Mazes and Coloring AdventureA
Fashionista Chic Couture Mazes and Coloring AdventureAFashionista Chic Couture Mazes and Coloring AdventureA
Fashionista Chic Couture Mazes and Coloring AdventureA
julierjefferies8888
 
Codes n Conventionss copy (2).pptx new new
Codes n Conventionss copy (2).pptx new newCodes n Conventionss copy (2).pptx new new
Codes n Conventionss copy (2).pptx new new
ZackSpencer3
 
Caffeinated Pitch Bible- developed by Claire Wilson
Caffeinated Pitch Bible- developed by Claire WilsonCaffeinated Pitch Bible- developed by Claire Wilson
Caffeinated Pitch Bible- developed by Claire Wilson
ClaireWilson398082
 
一比一原版(qut毕业证)昆士兰科技大学毕业证如何办理
一比一原版(qut毕业证)昆士兰科技大学毕业证如何办理一比一原版(qut毕业证)昆士兰科技大学毕业证如何办理
一比一原版(qut毕业证)昆士兰科技大学毕业证如何办理
taqyed
 
HOW TO USE PINTEREST_by: Clarissa Credito
HOW TO USE PINTEREST_by: Clarissa CreditoHOW TO USE PINTEREST_by: Clarissa Credito
HOW TO USE PINTEREST_by: Clarissa Credito
ClarissaAlanoCredito
 
A Brief Introduction About Hadj Ounis
A Brief  Introduction  About  Hadj OunisA Brief  Introduction  About  Hadj Ounis
A Brief Introduction About Hadj Ounis
Hadj Ounis
 
Complete Lab 123456789123456789123456789
Complete Lab 123456789123456789123456789Complete Lab 123456789123456789123456789
Complete Lab 123456789123456789123456789
vickyvikas51556
 
Fed by curiosity and beauty - Remembering Myrsine Zorba
Fed by curiosity and beauty - Remembering Myrsine ZorbaFed by curiosity and beauty - Remembering Myrsine Zorba
Fed by curiosity and beauty - Remembering Myrsine Zorba
mariavlachoupt
 
Memory Rental Store - The Ending(Storyboard)
Memory Rental Store - The Ending(Storyboard)Memory Rental Store - The Ending(Storyboard)
Memory Rental Store - The Ending(Storyboard)
SuryaKalyan3
 
Memory Rental Store - The Chase (Storyboard)
Memory Rental Store - The Chase (Storyboard)Memory Rental Store - The Chase (Storyboard)
Memory Rental Store - The Chase (Storyboard)
SuryaKalyan3
 
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单如何办理
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单如何办理一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单如何办理
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单如何办理
zeyhe
 
Cream and Brown Illustrative Food Journal Presentation.pptx
Cream and Brown Illustrative Food Journal Presentation.pptxCream and Brown Illustrative Food Journal Presentation.pptx
Cream and Brown Illustrative Food Journal Presentation.pptx
cndywjya001
 
一比一原版(UniSA毕业证)南澳大学毕业证成绩单如何办理
一比一原版(UniSA毕业证)南澳大学毕业证成绩单如何办理一比一原版(UniSA毕业证)南澳大学毕业证成绩单如何办理
一比一原版(UniSA毕业证)南澳大学毕业证成绩单如何办理
zeyhe
 

Recently uploaded (18)

WEEK 11 PART 1- SOULMAKING (ARTMAKING) (1).pdf
WEEK 11 PART 1- SOULMAKING (ARTMAKING) (1).pdfWEEK 11 PART 1- SOULMAKING (ARTMAKING) (1).pdf
WEEK 11 PART 1- SOULMAKING (ARTMAKING) (1).pdf
 
Rishikesh @ℂall @Girls ꧁❤Book❤꧂@ℂall @Girls Service Vip Top Model Safe
Rishikesh  @ℂall @Girls ꧁❤Book❤꧂@ℂall @Girls Service Vip Top Model SafeRishikesh  @ℂall @Girls ꧁❤Book❤꧂@ℂall @Girls Service Vip Top Model Safe
Rishikesh @ℂall @Girls ꧁❤Book❤꧂@ℂall @Girls Service Vip Top Model Safe
 
Investors Data Sample containing data.csv.pdf
Investors Data Sample containing data.csv.pdfInvestors Data Sample containing data.csv.pdf
Investors Data Sample containing data.csv.pdf
 
This is a certificate template for Daily Vacation Bible School Awards Can edi...
This is a certificate template for Daily Vacation Bible School Awards Can edi...This is a certificate template for Daily Vacation Bible School Awards Can edi...
This is a certificate template for Daily Vacation Bible School Awards Can edi...
 
The Last Polymath: Muntadher Saleh‎‎‎‎‎‎‎‎‎‎‎‎
The Last Polymath: Muntadher Saleh‎‎‎‎‎‎‎‎‎‎‎‎The Last Polymath: Muntadher Saleh‎‎‎‎‎‎‎‎‎‎‎‎
The Last Polymath: Muntadher Saleh‎‎‎‎‎‎‎‎‎‎‎‎
 
Fashionista Chic Couture Mazes and Coloring AdventureA
Fashionista Chic Couture Mazes and Coloring AdventureAFashionista Chic Couture Mazes and Coloring AdventureA
Fashionista Chic Couture Mazes and Coloring AdventureA
 
Codes n Conventionss copy (2).pptx new new
Codes n Conventionss copy (2).pptx new newCodes n Conventionss copy (2).pptx new new
Codes n Conventionss copy (2).pptx new new
 
Caffeinated Pitch Bible- developed by Claire Wilson
Caffeinated Pitch Bible- developed by Claire WilsonCaffeinated Pitch Bible- developed by Claire Wilson
Caffeinated Pitch Bible- developed by Claire Wilson
 
一比一原版(qut毕业证)昆士兰科技大学毕业证如何办理
一比一原版(qut毕业证)昆士兰科技大学毕业证如何办理一比一原版(qut毕业证)昆士兰科技大学毕业证如何办理
一比一原版(qut毕业证)昆士兰科技大学毕业证如何办理
 
HOW TO USE PINTEREST_by: Clarissa Credito
HOW TO USE PINTEREST_by: Clarissa CreditoHOW TO USE PINTEREST_by: Clarissa Credito
HOW TO USE PINTEREST_by: Clarissa Credito
 
A Brief Introduction About Hadj Ounis
A Brief  Introduction  About  Hadj OunisA Brief  Introduction  About  Hadj Ounis
A Brief Introduction About Hadj Ounis
 
Complete Lab 123456789123456789123456789
Complete Lab 123456789123456789123456789Complete Lab 123456789123456789123456789
Complete Lab 123456789123456789123456789
 
Fed by curiosity and beauty - Remembering Myrsine Zorba
Fed by curiosity and beauty - Remembering Myrsine ZorbaFed by curiosity and beauty - Remembering Myrsine Zorba
Fed by curiosity and beauty - Remembering Myrsine Zorba
 
Memory Rental Store - The Ending(Storyboard)
Memory Rental Store - The Ending(Storyboard)Memory Rental Store - The Ending(Storyboard)
Memory Rental Store - The Ending(Storyboard)
 
Memory Rental Store - The Chase (Storyboard)
Memory Rental Store - The Chase (Storyboard)Memory Rental Store - The Chase (Storyboard)
Memory Rental Store - The Chase (Storyboard)
 
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单如何办理
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单如何办理一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单如何办理
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单如何办理
 
Cream and Brown Illustrative Food Journal Presentation.pptx
Cream and Brown Illustrative Food Journal Presentation.pptxCream and Brown Illustrative Food Journal Presentation.pptx
Cream and Brown Illustrative Food Journal Presentation.pptx
 
一比一原版(UniSA毕业证)南澳大学毕业证成绩单如何办理
一比一原版(UniSA毕业证)南澳大学毕业证成绩单如何办理一比一原版(UniSA毕业证)南澳大学毕业证成绩单如何办理
一比一原版(UniSA毕业证)南澳大学毕业证成绩单如何办理
 

Avdhehs kumar presention kstps kota

  • 1. Introduction –kstps By Avdhesh kumar meena B.Tech 4th Year Electrical Branch NIET Alwar Rajasthan
  • 2. INDEX 0. KSTPS PICTURES 1.INTRODUCTION 2. GENERAL LAYOUT AND BASIC IDEA 3.TURBO GENERATOR 4.COOLING SYSTEM 5.TRANSFORMERS
  • 3.
  • 5. 1. INTRODUCTION •Kota Super Thermal Power Station is the first coal based Electricity Generating station in rajasthan. •At present the total installedcapacity of KSTPS is 1240 MW. • KSTPS has received Meritories productivity awards during 1984, 1987, 1989, 1981 and every year since 1992 onwards.
  • 6. K.S.T.P.S. IS DESISIGNED IN FOLLOWING STAGES:- STAGE I - 2x110 MW STAGE II - 2X210 MW STAGE III - 1X210 MW STAGE IV - 1X195 MW STAGE V - 1X195MW
  • 7. Stage Unit number Installed capacity (MW) Date of commissioning Status Stage I 1 110 January 1983 Running Stage I 2 110 July, 1983 Running Stage II 3 210 September 1988 Running Stage II 4 210 May, 1989 Running Stage III 5 210 March 1994 Running Stage IV 6 195 July, 2003 Running Stage V 7 195 May 2009 Running Installed capacity
  • 8. •The planning commission cleared the project report in Sept., 1976 for installation of two units each of 110 MW in first estimated cost of Rs. 143 Crores . •And finally stage fifth Unit #7 costed approximately Rs. 961 Crores.
  • 9. COAL: 1.Northern Coal Fields Limited(NCL), 2.South Eastern Coal Fields Limited(SECL) • Coal India limited is supply coal from its coal mines of coal producing subsidiaries SECL & NCL to Kota Thermal Power Station through railway wagons. • The average distances of SECL, NCL are 800, 950 Kms. respectively.
  • 10. WATER:- •The source of water for power station is reservoir formed by Kota Barrage on the Chambal River. • In case of large capacity plants huge quantities of coal and water is required.
  • 11. 2. General Layout & Basic Idea •The Kota Thermal Power Station is divided into four main circuits : 1.Fuel and Ash Circuit. 2 .Air and Gas Circuit. 3.Feed water and Steam Circuit. 4.Cooling Water Circuit. • A control system of station basically works on Rankin Cycle.
  • 12.
  • 13. (a).COAL HANDLING PLANT •It can be called the heart of thermal power plant because it provided the fuel for combustion in boiler. •Everyday 6 to 7 trains of coal are unloaded at KSTPS. • Each train consists of 58 wagons and each wagons consists of 50 tones of coal. • The approximate per day consumption at KSTPS is about 18000 metric tones.
  • 14. • The whole transportation of coal is through conveyor belt operated by 3-Ø Induction motor. • It costs approximate 4.5 crores of rupees per day including transportation expenses. •The coal handling plant can broadly be divided into thre sections. 1) Wagon Unloading system. 2) Crushing System. 3) Conveying System.
  • 15. (b) ASH HANDLING PLANT • This plant can be divided into 3 sub plants as follows:- 1)Fuel and Ash Plant. 2)Air and Gas Plant. 3)Ash Disposal and & Dust Collection Plant USES ASH: 1.Manufacturing of building materials. 2.Making of concrete. 3.Manufacturing of pozzuolana cement. 4. Road construction
  • 16. (C). ELECTRO-STATIC PRECIPITATOR •As far as air pollution is concerned now a days various flue gases filter are there in service. • •These filters are E.S.P. Fabric filter high efficiency cyclone separations and sitelling room. •where the particle size vary from 0.75 microns to 100 micron use gradually use E.S.P. to purify the flue gases due to its higher efficiency & low running cost etc.
  • 17. 6.TURBO GENERATOR THEORY :- •TURBO GENERATOR manufactured by B.H.E.L. • The generator stator is a tight construction, supporting & enclosing the stator windings, core and hydrogen coolers. • The generator is driven by directly coupled steam turbine at a speed of 3000 r. p. m. the Generator is designed for continuous operation at the rated output. • The source of excitation of rotor windings is thyristor controlled D.C. supply.
  • 18. TECHNICAL DATA:- Generator (110 MW):- Type : t.g.p. 2,34,602 Continuous apparent power : 1,37,500 KVA. Active power : 7,10,000 KW. Power factor : 0.8 (lagging). Rated voltage : 1000 + 5% rated. Current : 7,220 A Critical speed : 3000 r. p. m. at frequency : 50 Hz. Phase connection : double star. No. of terminals : 6. Main diameter of slip rings : 420 mm. Voltage regulation : 39%. Reactance : Infor
  • 19. Main parts of generator:- (a)STATOR:- STATOR FRAME:- The stator frame of welded steel frame construction. STATOR CORE:- •It is built up of special sheet laminations and whose assembly is supported by a special guide bass. STATOR BARS:- •Stator bars are manufactured as half bars, For an equal length along the bar. STATOR WINDINGS:- •Stator windings are double star layers , lap wound, three phase, short pitch type. • Phases are connected to form a double star winding. TERMINAL BUSHINGS:- • The conductor of Generator terminal bushing having hollow copper tubes with Copper brazed at the ends to avoid leakage of hydrogen. BEARINGS:- Generator bearings have electrical seats of consists of steel bodies with removable steel pads. HYDROGEN COOLERS:- •Three Hydrogen Coolers each comprising of two individual units are mounted inside the stator frame.
  • 21. 4.COOLING SYSTEM a) GENERAL:- •In KSTPS hydrogen cooling system is employed for generator cooling. • Hydrogen is used for cooling medium primarily because of its superior cooling properties & low density. • Thermal conductivity of hydrogen 7.3 times of air. • Its ability to transfer heat through forced convection is about 75% better than air. b)HYDROGEN DRYERS:- •Moisture in this gas is absorbed by silica gel in the dryer as the absorbed gas passes through it. •The silica gel is reactivated by heating.
  • 22. 10.TRANSFORMER •Transformer is a static device which is used to change the voltage level keeping the power and frequency same. •In the plant transformer is one of the most important equipment. •It is located in between the main plant and the switchyard. The main transformers installed in the transformer yard are: •GENERATOR TRANSFORMER (GT – A):- It steps up the voltage from 16.5 KV to 220 KV. It connects the plant with the 220 KV switchyard. •GENERATOR TRANSFORMER (GT – B):- It steps up the voltage from 16.5 KV to 400 KV. It connects the plant with the 400 KV switchyard. •STATION TRANSFORMER (ST):- It is a step down transformer with 50 MVA capacities. It is used to step down 220 KV from the grid to 6.9 KV. •AUXILIARY TRANSFORMER (UAT):- It is a step down transformer with 20 MVA capacities. It steps down the voltage from 16.5 KV to 6.9 KV. • STATION SERVICE TRANSFORMER (SST):- It is a step down transformer with 2MVA capacity. It is used to step down from 6.6 KV to 0.4333 KV. • UNIT SERVICE TRANSFORMER (UST):- It is a step down transformer with 2 MVA capacity. It is used to step down from 6.6 kV to 0.4333 KV.

Editor's Notes

  1. Picture by satelite