The document provides an overview of the Kota Super Thermal Power Station (KSTPS) in India. It discusses the power generation capacity of KSTPS in multiple stages totaling 1,195 MW. The key components described include the coal handling plant, ash handling plant, electrostatic precipitator, boiler, and draft system. The coal handling plant conveys and stores coal delivered by train. The boiler converts the chemical energy of coal into steam using a pulverized fuel system. The electrostatic precipitator removes fly ash from flue gases before emission. Forced draft and induced draft fans provide air flow into and out of the boiler furnace.
This document provides an overview of the Kota Super Thermal Power Station located on the Chambal river in Kota, India. It has a total installed capacity of 1240MW across 7 units of varying sizes commissioned between 1983-2009. The power station uses a coal-fired thermal process, with key components including the coal handling plant, boiler, superheater, steam turbine, economizer, generator, water treatment plant, and ash handling plant. It benefits from abundant cooling water from the river and good transportation access for coal and industry in the local region.
1. The presentation summarizes the key features of the Kota Super Thermal Power Station (KSTPS) located in Sakatpura, Kota. KSTPS has a total installed capacity of 1240 MW and uses coal as its primary fuel source.
2. The power station operates via five stages, with the first two units producing 110 MW each and subsequent units producing 210 MW and 195 MW. It utilizes various equipment for coal handling, crushing, pulverizing, steam generation, and power production.
3. KSTPS feeds power into the electrical grid through its switchyard, which includes components like isolators, lightning arresters, busbars, and transformers to handle and distribute the generated electricity
This document provides an overview of the Kota Thermal Power Station (KSTPS) in India. It discusses the power generation units and auxiliaries used at KSTPS. The station uses coal from nearby mines as fuel and water from the Chambal River for cooling. It has a total installed capacity of 1240MW across 7 units of varying sizes installed in stages. The document describes the key components and processes of the coal handling plant and ash handling plant that supply fuel and remove waste from the power generation process.
The Kota Super Thermal Power Station is a coal-based steam plant located on the left bank of the Chambal River in Kota, Rajasthan. It has a total generation capacity of 1240MW from 7 units and requires 250 hectares of land. The first unit was commissioned in 1983. Coal is transported by rail from nearby mines and handles about 3074 tonnes per day. The plant has a coal handling system, boilers, turbines, generators, cooling system, water treatment plant, and ash handling facilities. It supplies power to various cities in Rajasthan.
This document provides a summary of a seminar on summer vocational training at NTPC thermal power plants. It discusses the key components of a thermal power plant including coal handling, pulverizing, boilers, turbines, generators, condensers, and ash handling. It also describes various equipment like ball mills used in pulverizing coal and control and instrumentation labs that monitor critical parameters. Finally, it lists some major thermal power plants in Rajasthan and references used in preparing the seminar.
The document describes the key components and processes involved in a typical coal-fired thermal power plant, including the boiler, turbine, condenser, coal handling equipment, and other auxiliary systems. It also provides diagrams to illustrate the general layout and flow of energy conversion from coal to steam to mechanical power to electricity. Additionally, it briefly mentions some major thermal power plants located in the state of Rajasthan, India.
The document discusses electric traction systems. It begins by defining electric traction as a locomotion system where the driving force is obtained from an electric motor. It then covers major classifications of traction systems including non-electric and electric examples. The document also outlines requirements of an ideal traction system and discusses merits and demerits of electric traction. It provides details on different electric traction supply systems and speed variation considerations.
A best ppt on kota super thermal power stationNaveen Kumar
Kota Super Thermal Power Station (KSTPS) is located in Kota, Rajasthan. It has a total generation capacity of 1240 MW across 7 stages of power production. Coal is used as fuel and is supplied by Coal India Limited. The presentation discusses the general layout and various key components of the power plant including the coal handling plant, boiler, ash handling plant, steam turbine, electricity generator, cooling system, transformer, and control panel. KSTPS uses a water tube boiler and produces electricity through a steam turbine connected to a generator.
This document provides an overview of the Kota Super Thermal Power Station located on the Chambal river in Kota, India. It has a total installed capacity of 1240MW across 7 units of varying sizes commissioned between 1983-2009. The power station uses a coal-fired thermal process, with key components including the coal handling plant, boiler, superheater, steam turbine, economizer, generator, water treatment plant, and ash handling plant. It benefits from abundant cooling water from the river and good transportation access for coal and industry in the local region.
1. The presentation summarizes the key features of the Kota Super Thermal Power Station (KSTPS) located in Sakatpura, Kota. KSTPS has a total installed capacity of 1240 MW and uses coal as its primary fuel source.
2. The power station operates via five stages, with the first two units producing 110 MW each and subsequent units producing 210 MW and 195 MW. It utilizes various equipment for coal handling, crushing, pulverizing, steam generation, and power production.
3. KSTPS feeds power into the electrical grid through its switchyard, which includes components like isolators, lightning arresters, busbars, and transformers to handle and distribute the generated electricity
This document provides an overview of the Kota Thermal Power Station (KSTPS) in India. It discusses the power generation units and auxiliaries used at KSTPS. The station uses coal from nearby mines as fuel and water from the Chambal River for cooling. It has a total installed capacity of 1240MW across 7 units of varying sizes installed in stages. The document describes the key components and processes of the coal handling plant and ash handling plant that supply fuel and remove waste from the power generation process.
The Kota Super Thermal Power Station is a coal-based steam plant located on the left bank of the Chambal River in Kota, Rajasthan. It has a total generation capacity of 1240MW from 7 units and requires 250 hectares of land. The first unit was commissioned in 1983. Coal is transported by rail from nearby mines and handles about 3074 tonnes per day. The plant has a coal handling system, boilers, turbines, generators, cooling system, water treatment plant, and ash handling facilities. It supplies power to various cities in Rajasthan.
This document provides a summary of a seminar on summer vocational training at NTPC thermal power plants. It discusses the key components of a thermal power plant including coal handling, pulverizing, boilers, turbines, generators, condensers, and ash handling. It also describes various equipment like ball mills used in pulverizing coal and control and instrumentation labs that monitor critical parameters. Finally, it lists some major thermal power plants in Rajasthan and references used in preparing the seminar.
The document describes the key components and processes involved in a typical coal-fired thermal power plant, including the boiler, turbine, condenser, coal handling equipment, and other auxiliary systems. It also provides diagrams to illustrate the general layout and flow of energy conversion from coal to steam to mechanical power to electricity. Additionally, it briefly mentions some major thermal power plants located in the state of Rajasthan, India.
The document discusses electric traction systems. It begins by defining electric traction as a locomotion system where the driving force is obtained from an electric motor. It then covers major classifications of traction systems including non-electric and electric examples. The document also outlines requirements of an ideal traction system and discusses merits and demerits of electric traction. It provides details on different electric traction supply systems and speed variation considerations.
A best ppt on kota super thermal power stationNaveen Kumar
Kota Super Thermal Power Station (KSTPS) is located in Kota, Rajasthan. It has a total generation capacity of 1240 MW across 7 stages of power production. Coal is used as fuel and is supplied by Coal India Limited. The presentation discusses the general layout and various key components of the power plant including the coal handling plant, boiler, ash handling plant, steam turbine, electricity generator, cooling system, transformer, and control panel. KSTPS uses a water tube boiler and produces electricity through a steam turbine connected to a generator.
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Shubham Thakur
A thermal power station is a power plant in which the prime mover is steam driven. Water is heated, turns into steam and spins a steam turbine which drives an electrical generator. After it passes through the turbine, the steam is condensed in a condenser and recycled to where it was heated; this is known as a Rankine cycle. The greatest variation in the design of thermal power stations is due to the different fossil fuel resources generally used to heat the water. Some prefer to use the term energy center because such facilities convert forms of heat energy into electrical energy.[1] Certain thermal power plants also are designed to produce heat energy for industrial purposes of district heating, or desalination of water, in addition to generating electrical power. Globally, fossil fueled thermal power plants produce a large part of man-made CO2 emissions to the atmosphere, and efforts to reduce these are varied and widespread.
For Video on Themal Power Plant (Animated Working Video) :- https://www.youtube.com/watch?v=ouWOhk1INjo
Subscribe To Our Youtube Channel For More Videos:-
https://www.youtube.com/TheEngineeringScienc
Click Here To Subscribe:-
http://www.youtube.com/user/TheEngineeringScienc?sub_confirmation=1
The document provides information about the author's 4 week training at NTPC from June to July 2016. They visited the Boiler Maintenance Department and Turbine Maintenance Department to learn how electricity is produced. NTPC is India's largest power company, generating over 45,000 MW of electricity using steam turbines powered by coal. The company was founded in 1975 and uses the Rankine cycle to convert heat from coal into mechanical power and then electrical power.
1) Power electronic converters are used in variable-speed wind turbines to control the speed of the generator and turbine based on wind speed, allowing for maximum energy capture.
2) Squirrel cage induction generators are commonly used due to their ruggedness and low cost, and are connected to the grid through diode or thyristor converters on the stator side.
3) Newer voltage source PWM converters are now used which provide sinusoidal voltages and currents, reducing torque pulsations and improving efficiency compared to older current source converters.
Thermal Power plant visit Report by Amit Hingeamit307
The document is an industrial visit report on Paras Thermal Power Plant in Akola, India. It provides an overview of the key components and processes of a coal-fired thermal power plant, including coal preparation, boilers, turbines, generators, condensers and cooling towers. Paras Thermal Power Plant is one of the oldest power plants owned by Maharashtra State Power Generation Company, with the first units installed in 1961. It has since been upgraded with newer 250MW units. The report serves to explain the functioning and technical aspects of thermal power generation to students who visited the plant.
This document provides an overview of the Kota Super Thermal Power Station located in Kota, Rajasthan, India. It discusses the key reasons for locating the power station in Kota, including the availability of cooling water from the Chambal River and proximity to coal fields. The presentation describes the design and layout of the power station and its various units. It also provides details on the coal handling plant, turbines, generators, transformers, and other major components. The document aims to educate about the functioning and components of the thermal power station.
The Kota Super Thermal Power Station is a 1240MW coal power plant located in Kota, Rajasthan. It uses a steam turbine generator system fueled by coal. Coal is transported via a conveyor system to the boiler, where it is burned to produce steam that drives the turbine generator. The steam is then condensed in condensers using cooling water from the Chambal River. Fly ash from combustion is captured and can be used for products like cement or road construction. The power station began operating in 1983 and has since expanded in stages to its current capacity.
The document discusses power system stability, including classifications of stability (steady state, transient, and dynamic) and factors that affect transient stability. It also covers topics like the swing equation, equal area criterion, critical clearing angle, and multi-machine stability studies. Some key points:
1) Power system stability refers to a system's ability to return to normal operating conditions after disturbances like faults or load changes.
2) Transient stability depends on factors like fault duration and location, generator inertia, and pre-fault loading conditions.
3) The equal area criterion states that a system will remain stable if the accelerating and decelerating area segments on the power-angle curve are equal.
4)
KTPS-V Station in Andhra Pradesh was commissioned in 1996 as the first major thermal power station in the state. It uses a steam turbine generator system where coal is burned to produce steam that spins the turbine to generate electricity. The station has four main circuits: steam and water, air and gas, coal and ash, and cooling water. Steam is produced in a boiler and drives high, intermediate, and low pressure turbines connected to an electrical generator before condensing in a condenser.
This document describes the key components and working of a thermal power plant. It explains that thermal power plants generate electricity by burning fuel to create high pressure steam, which spins a steam turbine connected to a generator. The main components are the boiler, which produces steam from water; a superheater that increases the steam's temperature; and a steam turbine, which is spun by the steam and connected to a generator to produce electricity. After passing through the turbine, the steam enters a condenser where it is cooled and condensed back into water to repeat the process.
This document discusses power system stability and microgrids. It defines power system stability and classifies it into several types including rotor angle stability, voltage stability, and frequency stability. It also discusses microgrids, their interconnection to main grids for availability and economic benefits, and methods for connecting microgrids using switchgear or static switches. In conclusion, it states that power system stability is important for normal operation and can be improved through devices like capacitors and FACTS controllers, and that microgrids satisfy local loads while reducing transmission losses through local renewable generation.
A thermal power station uses coal to generate steam, which spins turbines that create electrical power. Coal is pulverized and burned to heat water and create steam. The steam spins turbines connected to generators, producing electricity. The steam is then condensed back into water and recycled through the system. Thermal power stations use various pumps, fans, condensers and other equipment to efficiently convert the energy in coal into electrical power for transmission and distribution.
This training report summarizes Pratik Gupta's vocational training at the SIPAT Super Thermal Power Project. It provides details on the production of electricity at a thermal power plant. Coal is ground and blown into boilers where it burns, heating water in tubes to produce high pressure steam. The steam powers turbines connected to generators, producing electricity. The steam is then condensed back into water in condensers to be reused in the cycle. The report outlines the key components and processes involved in electricity generation at a coal-fired thermal power station.
The Thermal Power Station burns fuel & uses the resultant to make the steam, which derives the turbo generator. The Fuel i.e. coal is burnt in pulverized from. The pressure energy of the steam produce is converted into mechanical energy with the help of turbine. The mechanical energy is fed to the generator where the magnet rotate inside a set of stator winding & thus electricity is produced in India 65% of total power is generated by thermal power stations. To understand the working of the Thermal Power Station plant, we can divide the whole process into following parts.
kota super thermal Power station training reportEr. Aman Agrawal
it is a practical training report on kota super thermal power station
For any other enquiry u can contact me on +919540278218....
and can join my Page www.facebook.com/engineeringindia
A Presentation on Kota Super Thermal Power StationLekhraJ Meena
The document provides information about the Kota Super Thermal Power Plant in India including its establishment, generation capacity, units and their installation details. It describes the main components of the plant including the coal handling plant, boiler, superheater, steam turbine, generator, water treatment plant, ash handling plant and control room. The coal handling plant section explains the wagon unloading, crushing and conveying systems. The document also provides diagrams to illustrate the layout and processes of the power plant.
The document expresses gratitude to various people who helped with a vocational training project at a thermal power plant. It thanks the officials who oversaw the project, the power plant staff who provided assistance, and the author's parents for their support in completing the project successfully.
introduction to thermal powerplant,type of thermal powerplant,captive powerplant,rankin cycle,co-generation powerplant,subcritical powerplant,supercritical powerplant,theory of operation,working principle,parts of powerplant,boiler,turbine,etc
The document discusses demand side management (DSM) in the context of distribution generation and smart grids. It defines DSM as modifying consumer energy demand through methods like financial incentives or education. The goal is usually to encourage reducing energy use during peak hours or shifting it to off-peak times. This helps reduce the need for network and power plant investments to meet peak demand. The document then outlines various DSM programs and strategies like demand response, time-of-use pricing, and direct load control.
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORTPrasant Kumar
The document provides an overview of the components and operation of a thermal power plant. It discusses the key elements including coal handling, pulverizers, boilers, superheaters, turbines, generators, condensers and cooling towers. The coal is pulverized and burned to produce steam, which spins turbines connected to generators to produce electricity. The steam is then condensed and recycled to the boilers to complete the Rankine cycle. The document outlines the functions of the major equipment in a coal-fired thermal power station.
The document provides information about Kolaghat Thermal Power Station located in West Bengal, India. It has six units totaling 1,260 MW capacity. The power plant uses a steam turbine process to convert the heat from burning coal into electrical energy. It describes the main equipment used including the coal handling plant, boiler, turbine, condenser, and electrical equipment like transformers and generators. The document provides technical specifications for many of the major components.
This document discusses the Kotthagudem Thermal Power Station located in Andhra Pradesh, India. The power station has a total power generation capacity of 720 MW produced across 8 generating units. Coal is supplied from nearby Singareni Coal Mines and used to fuel the boilers, which heat water into steam to power the turbines and alternators that generate electricity. Water is supplied to the plant from the Kinnera sani Dam. The generated power is stepped up in voltage by transformers and transmitted via transmission lines and towers to consumers.
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Shubham Thakur
A thermal power station is a power plant in which the prime mover is steam driven. Water is heated, turns into steam and spins a steam turbine which drives an electrical generator. After it passes through the turbine, the steam is condensed in a condenser and recycled to where it was heated; this is known as a Rankine cycle. The greatest variation in the design of thermal power stations is due to the different fossil fuel resources generally used to heat the water. Some prefer to use the term energy center because such facilities convert forms of heat energy into electrical energy.[1] Certain thermal power plants also are designed to produce heat energy for industrial purposes of district heating, or desalination of water, in addition to generating electrical power. Globally, fossil fueled thermal power plants produce a large part of man-made CO2 emissions to the atmosphere, and efforts to reduce these are varied and widespread.
For Video on Themal Power Plant (Animated Working Video) :- https://www.youtube.com/watch?v=ouWOhk1INjo
Subscribe To Our Youtube Channel For More Videos:-
https://www.youtube.com/TheEngineeringScienc
Click Here To Subscribe:-
http://www.youtube.com/user/TheEngineeringScienc?sub_confirmation=1
The document provides information about the author's 4 week training at NTPC from June to July 2016. They visited the Boiler Maintenance Department and Turbine Maintenance Department to learn how electricity is produced. NTPC is India's largest power company, generating over 45,000 MW of electricity using steam turbines powered by coal. The company was founded in 1975 and uses the Rankine cycle to convert heat from coal into mechanical power and then electrical power.
1) Power electronic converters are used in variable-speed wind turbines to control the speed of the generator and turbine based on wind speed, allowing for maximum energy capture.
2) Squirrel cage induction generators are commonly used due to their ruggedness and low cost, and are connected to the grid through diode or thyristor converters on the stator side.
3) Newer voltage source PWM converters are now used which provide sinusoidal voltages and currents, reducing torque pulsations and improving efficiency compared to older current source converters.
Thermal Power plant visit Report by Amit Hingeamit307
The document is an industrial visit report on Paras Thermal Power Plant in Akola, India. It provides an overview of the key components and processes of a coal-fired thermal power plant, including coal preparation, boilers, turbines, generators, condensers and cooling towers. Paras Thermal Power Plant is one of the oldest power plants owned by Maharashtra State Power Generation Company, with the first units installed in 1961. It has since been upgraded with newer 250MW units. The report serves to explain the functioning and technical aspects of thermal power generation to students who visited the plant.
This document provides an overview of the Kota Super Thermal Power Station located in Kota, Rajasthan, India. It discusses the key reasons for locating the power station in Kota, including the availability of cooling water from the Chambal River and proximity to coal fields. The presentation describes the design and layout of the power station and its various units. It also provides details on the coal handling plant, turbines, generators, transformers, and other major components. The document aims to educate about the functioning and components of the thermal power station.
The Kota Super Thermal Power Station is a 1240MW coal power plant located in Kota, Rajasthan. It uses a steam turbine generator system fueled by coal. Coal is transported via a conveyor system to the boiler, where it is burned to produce steam that drives the turbine generator. The steam is then condensed in condensers using cooling water from the Chambal River. Fly ash from combustion is captured and can be used for products like cement or road construction. The power station began operating in 1983 and has since expanded in stages to its current capacity.
The document discusses power system stability, including classifications of stability (steady state, transient, and dynamic) and factors that affect transient stability. It also covers topics like the swing equation, equal area criterion, critical clearing angle, and multi-machine stability studies. Some key points:
1) Power system stability refers to a system's ability to return to normal operating conditions after disturbances like faults or load changes.
2) Transient stability depends on factors like fault duration and location, generator inertia, and pre-fault loading conditions.
3) The equal area criterion states that a system will remain stable if the accelerating and decelerating area segments on the power-angle curve are equal.
4)
KTPS-V Station in Andhra Pradesh was commissioned in 1996 as the first major thermal power station in the state. It uses a steam turbine generator system where coal is burned to produce steam that spins the turbine to generate electricity. The station has four main circuits: steam and water, air and gas, coal and ash, and cooling water. Steam is produced in a boiler and drives high, intermediate, and low pressure turbines connected to an electrical generator before condensing in a condenser.
This document describes the key components and working of a thermal power plant. It explains that thermal power plants generate electricity by burning fuel to create high pressure steam, which spins a steam turbine connected to a generator. The main components are the boiler, which produces steam from water; a superheater that increases the steam's temperature; and a steam turbine, which is spun by the steam and connected to a generator to produce electricity. After passing through the turbine, the steam enters a condenser where it is cooled and condensed back into water to repeat the process.
This document discusses power system stability and microgrids. It defines power system stability and classifies it into several types including rotor angle stability, voltage stability, and frequency stability. It also discusses microgrids, their interconnection to main grids for availability and economic benefits, and methods for connecting microgrids using switchgear or static switches. In conclusion, it states that power system stability is important for normal operation and can be improved through devices like capacitors and FACTS controllers, and that microgrids satisfy local loads while reducing transmission losses through local renewable generation.
A thermal power station uses coal to generate steam, which spins turbines that create electrical power. Coal is pulverized and burned to heat water and create steam. The steam spins turbines connected to generators, producing electricity. The steam is then condensed back into water and recycled through the system. Thermal power stations use various pumps, fans, condensers and other equipment to efficiently convert the energy in coal into electrical power for transmission and distribution.
This training report summarizes Pratik Gupta's vocational training at the SIPAT Super Thermal Power Project. It provides details on the production of electricity at a thermal power plant. Coal is ground and blown into boilers where it burns, heating water in tubes to produce high pressure steam. The steam powers turbines connected to generators, producing electricity. The steam is then condensed back into water in condensers to be reused in the cycle. The report outlines the key components and processes involved in electricity generation at a coal-fired thermal power station.
The Thermal Power Station burns fuel & uses the resultant to make the steam, which derives the turbo generator. The Fuel i.e. coal is burnt in pulverized from. The pressure energy of the steam produce is converted into mechanical energy with the help of turbine. The mechanical energy is fed to the generator where the magnet rotate inside a set of stator winding & thus electricity is produced in India 65% of total power is generated by thermal power stations. To understand the working of the Thermal Power Station plant, we can divide the whole process into following parts.
kota super thermal Power station training reportEr. Aman Agrawal
it is a practical training report on kota super thermal power station
For any other enquiry u can contact me on +919540278218....
and can join my Page www.facebook.com/engineeringindia
A Presentation on Kota Super Thermal Power StationLekhraJ Meena
The document provides information about the Kota Super Thermal Power Plant in India including its establishment, generation capacity, units and their installation details. It describes the main components of the plant including the coal handling plant, boiler, superheater, steam turbine, generator, water treatment plant, ash handling plant and control room. The coal handling plant section explains the wagon unloading, crushing and conveying systems. The document also provides diagrams to illustrate the layout and processes of the power plant.
The document expresses gratitude to various people who helped with a vocational training project at a thermal power plant. It thanks the officials who oversaw the project, the power plant staff who provided assistance, and the author's parents for their support in completing the project successfully.
introduction to thermal powerplant,type of thermal powerplant,captive powerplant,rankin cycle,co-generation powerplant,subcritical powerplant,supercritical powerplant,theory of operation,working principle,parts of powerplant,boiler,turbine,etc
The document discusses demand side management (DSM) in the context of distribution generation and smart grids. It defines DSM as modifying consumer energy demand through methods like financial incentives or education. The goal is usually to encourage reducing energy use during peak hours or shifting it to off-peak times. This helps reduce the need for network and power plant investments to meet peak demand. The document then outlines various DSM programs and strategies like demand response, time-of-use pricing, and direct load control.
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORTPrasant Kumar
The document provides an overview of the components and operation of a thermal power plant. It discusses the key elements including coal handling, pulverizers, boilers, superheaters, turbines, generators, condensers and cooling towers. The coal is pulverized and burned to produce steam, which spins turbines connected to generators to produce electricity. The steam is then condensed and recycled to the boilers to complete the Rankine cycle. The document outlines the functions of the major equipment in a coal-fired thermal power station.
The document provides information about Kolaghat Thermal Power Station located in West Bengal, India. It has six units totaling 1,260 MW capacity. The power plant uses a steam turbine process to convert the heat from burning coal into electrical energy. It describes the main equipment used including the coal handling plant, boiler, turbine, condenser, and electrical equipment like transformers and generators. The document provides technical specifications for many of the major components.
This document discusses the Kotthagudem Thermal Power Station located in Andhra Pradesh, India. The power station has a total power generation capacity of 720 MW produced across 8 generating units. Coal is supplied from nearby Singareni Coal Mines and used to fuel the boilers, which heat water into steam to power the turbines and alternators that generate electricity. Water is supplied to the plant from the Kinnera sani Dam. The generated power is stepped up in voltage by transformers and transmitted via transmission lines and towers to consumers.
The document summarizes the key components and specifications of the KTPS power plant in India. It describes the plant in four stages with a total generation of 1045 MW. It then outlines the main parts of the plant including the fuel and ash plant, air and gas plant, feed water and steam plant, and cooling water plant. It provides technical specifications for the turbo generator, steam turbine, boiler, coal handling plant, ash handling plant, water treatment plant, and transformers.
Best ppt on Presentation on Coal handling plantRonak Thakare
This document provides an overview of a coal handling plant (CHP). It discusses what a CHP is, its main components and processes. The key points covered include:
- A CHP receives, processes, stores and feeds coal to boiler bunkers. Its main goal is to supply processed coal to coal mills.
- Main components include wagon tipplers, crushers, conveyor belts, feeders, bunkers. Coal is crushed to different sizes and conveyed to bunkers or storage.
- Coal is transported mainly by railways in wagons and unloaded by rotary or side tipplers. Other transport modes include ropeways and road.
- The document outlines the operating sequence,
A power plant converts one form of energy into electrical energy. The most common type of power plant is a thermal power plant, which burns fossil fuels like coal to heat water and produce steam that spins turbines connected to generators. At the center of power plants is a generator that converts mechanical energy from the turbine into electrical energy. The main types of power plants in India are thermal, hydroelectric, and nuclear power plants. Thermal power plants, which produce over half of India's electricity, work by burning coal to heat water and produce high-pressure steam that drives the turbines.
1) The document summarizes Divesh Kacolia's practical training at the Kota Super Thermal Power Station from July 21st to August 4th 2008.
2) Key aspects of the power station covered include its four stages with a total capacity of 1045MW, the coal handling process, pulverization, boiler, turbine, generator and other components.
3) Detailed information is provided about the energy generated, electricity generation process, coal handling plant, pulverizing plant, boiler, turbine, DC system, economizer, generator, transformer, chimney, cooling tower and water treatment systems.
This document provides an overview of the key components and processes in a thermal power plant. It describes how coal is pulverized and burned to generate high-temperature steam in a boiler. The steam then drives turbines which power electrical generators, after which the steam is condensed back into water and recycled through the system in a closed-loop Rankine cycle. The document outlines the basic working principle and lists the main parts of a thermal power plant, including coal conveyors, pulverizers, boilers, turbines and condensers.
This document is a seminar report submitted by Mukesh Kumar for partial fulfillment of a Bachelor of Technology degree in Mechanical Engineering. It discusses thermal power plants, including an overview of their operation and efficiency, descriptions of typical components like boilers and steam cycles, and examples of power plants located in India with a focus on those in Rajasthan. The document received certification from internal and external examiners for Mukesh Kumar's seminar work on the topic of thermal power plants.
This document provides an overview of a coal handling plant (CHP). It discusses the key components and processes within a CHP, including:
- Transportation of coal primarily via railways to the plant.
- Analysis of incoming coal to check quality matches agreements.
- The general layout and flow of coal through the plant via wagon tipplers, conveyor belts, crushers, and bunkers.
- The crushing process uses a three stage system to reduce coal size.
- Operational cycles to bunker, stack, or reclaim coal depending on bunker levels and maintenance needs.
- Key equipment used includes wagon tipplers, conveyor belts, double roll crushers, rotary break
This document is a training report submitted by Rahul Kumar on Power Line Carrier Communication (PLCC) during an internship at a 132kV grid substation in Jaipur, India. The report provides an introduction to PLCC, describes the key indoor and outdoor equipment used in a PLCC system such as line traps, coupling capacitors, wave traps and carrier terminals. It also discusses different modes of coupling carrier signals to power lines, and the functions of essential components like the coupling capacitor, wave trap, line matching unit and battery charger. The report aims to provide a practical understanding of PLCC technologies and their industrial applications for power network communication and monitoring.
Kota super thermal power plant training reportAvinash Kumawat
Kota Thermal Power Station (KTPS) has a total installed capacity of 1240 MW across 5 stages. Coal is the primary fuel and is supplied by rail from mines located 800-950 km away. The coal handling plant receives coal by train, unloads it using wagon triplers, and uses crushers and conveyor belts to transport the crushed coal to the boilers. The plant has 4 main circuits - fuel and ash, air and gas, feedwater and steam, and cooling water. Coal is the key fuel source and its efficient handling and processing is crucial to the operation of the thermal power station.
Kota Super Thermal Power Station Training reportDeepak Solanki
The document provides information about the Kota Super Thermal Power Station (KSTPS) in Kota, India. It discusses the power generation capacity of KSTPS in stages from 2x110 MW initially to a final stage of 1x195 MW. It describes the basic layout and circuits of the power station including the fuel and ash circuit, air and gas circuit, feedwater and steam circuit, and cooling water circuit. It also provides details about the coal handling plant, ash handling plant, and location, land, water, and coal requirements of KSTPS.
The document provides an overview of the Kota Thermal Power Station (KSTPS) in India. Key points:
1. KSTPS has a total generation capacity of 1240 MW across 5 stages, with coal being its primary fuel source transported via rail.
2. The plant layout consists of 4 main circuits - fuel and ash, air and gas, feedwater and steam, and cooling water.
3. The coal handling process involves unloading coal from trains via wagon tipplers, crushing the coal, and conveying it via belts to the boilers for combustion.
Kota Super Thermal Power Station (KSTPS) in Kota, India has four stages with a total generation capacity of 1,045 MW. Stage I has two 110 MW units, Stage II has two 210 MW units, Stage III has one 210 MW unit, and Stage IV has one 195 MW unit. A fifth 195 MW unit in Stage V is under construction. KSTPS uses coal from nearby mines to produce steam that drives turbines to generate electricity. Cooling water is drawn from the Chambal River reservoir. The plant has four main circuits: fuel and ash, air and gas, feedwater and steam, and cooling water.
The document provides technical details about Mejia Thermal Power Station (MTPS) in Bankura, West Bengal, India. MTPS has a total installed capacity of 2340MW generated across 8 units, with 4 units of 210MW each, 2 units of 250MW each, and 2 units of 500MW each. The document describes the various components that make up the thermal power generation process at MTPS, including the coal handling plant, water treatment plant, boilers, turbines, generators, transformers, and cooling towers.
(Keshav) report file on kali sindh thermal power project, jhalawarKeshav Meena
This document provides an introduction and overview of the Kali Sindh Thermal Power Project (KSTPP) located in Jhalawar City, India. It discusses the key factors that make the site suitable for a power plant, including access to water from the Kali Sindh river, proximity to a railway station and transmission lines, and available land for ash disposal. The KSTPP currently has 2 units generating 1200 MW of power, with plans for 2 additional 660 MW units. The document then goes on to describe the general layout and basic systems of the plant, including the fuel, air/gas, feedwater/steam, and cooling water circuits. It provides details on the coal handling plant, including unloading
This document provides an overview of the vocational training seminar on the Durgapur Steel Thermal Power Station in Andal, India. It discusses the key components and processes of a thermal power plant, including the Rankine cycle used to convert heat from coal into electrical power. The main parts of the plant are the coal handling plant, boiler, condenser, turbine, and desalination plant. The coal handling plant receives and prepares coal for use in the boilers, which convert water into high-pressure steam. The steam then drives the turbine, which turns a generator to produce electricity.
Project Report on “WORKING MODEL OF POWER GRID/SMART GRIDPrasant Kumar
Over a century of years ago, the power system has been developed into one of the predominantly complicated network viewed in human history. Due to the mounting of consumption demand, the modern electrical power grids are now increasing into a huge structure with various interconnected regional grids, owned and operated by Power Corporation at every height and hierarchy.
Due to dense attention, management and operation among various power companies periodically complex the cross-region transmission work and more time results in poor coordination and inefficient power delivery. So the conventional power grid in today’s world is facing some upcoming challenges.
As the demand and category of consumption increases, various types of modern technologies are introduced in power system, like the electric component charging system, distributed renewable energy generation, smart meters etc, that all work towards the complication of modern power delivery.
The day to day increasing dependence on electricity and growing need for power quality have been regularly asking for better power delivery, faster power restoration and more flexible pricing among others.
An electrical grid is an interconnected network for delivering electricity from suppliers to consumers. It consists of three main components power generation transmission and distribution.
(1) The document discusses the Chhabra Thermal Power Plant located in Baran, Rajasthan, India. It has a total installed capacity of 1000 MW across 4 units, with 2 additional supercritical units of 660 MW each under construction.
(2) The plant uses a coal handling system to transport coal via railway to the plant where it is pulverized and fired into the boiler to produce steam. This steam powers the steam turbine which drives the generator to produce electricity.
(3) The plant also has various auxiliary systems including water treatment, ash handling, flue gas cleaning, and switchyard systems to transmit the generated power.
Cseb (chhattisgarh state electricity board) korba east vocational training pr...haxxo24
This document provides an overview of vocational training received at a power plant in Korba, Chhattisgarh, India. It discusses the key components and processes involved in power generation, including coal handling, fuel and air circuits, turbines, condensers, heaters, and other equipment. The training covered the parts, functioning, and interlocking of equipment like turbines, pumps, condensers, and boilers. Trainees learned about the resources like water, coal, and air required for power generation and the classification and transportation of coal used as fuel at the plant.
Half of the electricity produced by CEB is produced by this Lakvijaya power plant
900MW power is generated from this plant.
Coal is exported from these countries such as indonesia, south africa, and Russiya.
Coal is transported from the jetty to the coal yard and from there to the main plant by a belt system.
Water spray methods are used to maintain moisture in coal
The coal bundles coming from the coal yard are pulverized well by some machines, mixed with air and released into the boiler.
There, the thermal energy generated by the combustion is absorbed by the tubes in the boiler and turns into steam
The electricity produced by the generators connected to the turbines is transmitted to the power stations through an h2 plant.
The gas coming out of coal combustion is first removed by ESP and then the harmful sulfur dioxide in the gas is removed by a device called FGD
Presentation on Kota super Thermal Power Stationpukhraj palariya
The document provides information about the Kota Super Thermal Power Station (KSTPS) in Kota, Rajasthan. It discusses the key stages and features of the power station, including that it began operations in 1983, has a total generation capacity of 1240 MW from 7 units, and sources coal from local mines to power its boilers. The power station uses a steam turbine generator process to convert the thermal energy of steam into electrical energy.
Ppt on power generation(thermal), transmission & distributionSuvamSahu2
The document provides information about electrical power generation at a thermal power plant (KTPS). It discusses the working principle, layout, main equipment, waste generated and their control, advantages and disadvantages. The main equipment discussed includes the coal handling plant, pulverizing plant, boiler, turbine, condenser, cooling towers/ponds, feed water heater, economizer, and air preheater. It also provides additional data about KTPS such as its generating capacity and types of circuit breakers used.
1. The document provides an acknowledgement and thanks to various individuals and departments at NTPC Tanda for allowing the training and providing support and knowledge.
2. It then outlines the content which will be covered, including a brief description of the Tanda thermal project, production of electricity, description of the thermal plant, basic cycle of a power plant, control and instrumentation unit, and important equipment of the plant.
3. It begins describing the Tanda thermal project, providing its geographical location, features such as its installed capacity and suppliers, and performance metrics like its designed boiler efficiency.
The document summarizes the layout and components of the Kota Super Thermal Power Station, a power plant located in Kota, India. It consists of 7 units with a total generation capacity of 1240 MW. The main parts of the plant include the coal handling plant, boiler, superheater, steam turbine, generator, generating transformer, and cooling system. The coal handling plant processes and conveys coal to the furnace. Steam is generated in the boiler and superheated before powering the steam turbine, which drives the generator to produce electricity.
The document provides information about the Sanjay Gandhi Thermal Power Station located in Birsinghpur, India. It has a total installed capacity of 1340 MW distributed across 5 units ranging from 210-500 MW each. The power plant uses coal as its primary fuel sourced from local mines via rail. Water for the plant is sourced from the nearby Johila River and Dam. The plant has conventional systems for coal handling, steam generation in the boiler, power generation in the turbine, and effluent management. It provides key specifications and details of the various units and systems to run the thermal power generation process.
The Calcutta Electric Supply Corporation (CESC) supplies electricity to over 2.4 million consumers in areas around Kolkata, India. It has four power plants with a total generation capacity of 1025 MW. The Budge Budge Generating Station is CESC's largest plant, commissioned in 1997 with a capacity of 750 MW from three 250 MW units. It uses modern technology like vertical down shot boilers and a tandem compounded turbine. A vocational training was organized at the Budge Budge plant to give engineering students practical experience in plant operations and components.
The document summarizes the training seminar on the Kota Super Thermal Power Station. It describes the power station's establishment in 1973 with initial capacity of 220 MW expanding to 1240 MW currently. It details the main components of the plant including the coal handling plant, boiler, superheater, steam turbine, generator, cooling system, and ash handling plant. The layout and functioning of each component is briefly explained.
Internship Report on thermal power station in vizag steel plantAbhishek Kumar
This document provides information about a study of power generation and distribution at a thermal power plant in Visakhapatnam Steel Plant. It discusses the key components of the thermal power plant including five water tube boilers that produce steam at 101 atmospheres of pressure and 540 degrees Celsius. The steam powers five steam turbines coupled to generators with a total installed capacity of 286.5 MW. The document outlines the processes of coal combustion in the boilers, steam generation, power generation using steam turbines, and distribution of power within the steel plant. It also discusses operational aspects like load management and limits of the turbo generators.
The document is a seminar presentation on thermal power plants. It discusses the classification, layout, components and working of thermal power plants. The main components discussed are the coal handling plant, pulverizing plant, boiler, turbine, condenser, cooling tower, feedwater heater and economizer. Thermal power plants in Rajasthan like Kota, Suratgarh, Giral, Chhabra and Kalisindh are also summarized along with their installed capacities and commissioning details. Advantages, limitations and site selection parameters for thermal plants are also highlighted.
SATTA MATKA DPBOSS KALYAN MATKA RESULTS KALYAN CHART KALYAN MATKA MATKA RESULT KALYAN MATKA TIPS SATTA MATKA MATKA COM MATKA PANA JODI TODAY BATTA SATKA MATKA PATTI JODI NUMBER MATKA RESULTS MATKA CHART MATKA JODI SATTA COM INDIA SATTA MATKA MATKA TIPS MATKA WAPKA ALL MATKA RESULT LIVE ONLINE MATKA RESULT KALYAN MATKA RESULT DPBOSS MATKA 143 MAIN MATKA KALYAN MATKA RESULTS KALYAN CHART
Cover Story - China's Investment Leader - Dr. Alyce SUmsthrill
In World Expo 2010 Shanghai – the most visited Expo in the World History
https://www.britannica.com/event/Expo-Shanghai-2010
China’s official organizer of the Expo, CCPIT (China Council for the Promotion of International Trade https://en.ccpit.org/) has chosen Dr. Alyce Su as the Cover Person with Cover Story, in the Expo’s official magazine distributed throughout the Expo, showcasing China’s New Generation of Leaders to the World.
AI Transformation Playbook: Thinking AI-First for Your BusinessArijit Dutta
I dive into how businesses can stay competitive by integrating AI into their core processes. From identifying the right approach to building collaborative teams and recognizing common pitfalls, this guide has got you covered. AI transformation is a journey, and this playbook is here to help you navigate it successfully.
SATTA MATKA DPBOSS KALYAN MATKA RESULTS KALYAN CHART KALYAN MATKA MATKA RESULT KALYAN MATKA TIPS SATTA MATKA MATKA COM MATKA PANA JODI TODAY BATTA SATKA MATKA PATTI JODI NUMBER MATKA RESULTS MATKA CHART MATKA JODI SATTA COM INDIA SATTA MATKA MATKA TIPS MATKA WAPKA ALL MATKA RESULT LIVE ONLINE MATKA RESULT KALYAN MATKA RESULT DPBOSS MATKA 143 MAIN MATKA KALYAN MATKA RESULTS KALYAN CHART
Discover the Beauty and Functionality of The Expert Remodeling Serviceobriengroupinc04
Unlock your kitchen's true potential with expert remodeling services from O'Brien Group Inc. Transform your space into a functional, modern, and luxurious haven with their experienced professionals. From layout reconfiguration to high-end upgrades, they deliver stunning results tailored to your style and needs. Visit obriengroupinc.com to elevate your kitchen's beauty and functionality today.
63662490260Kalyan chart, satta matta matka 143, satta matka jodi fix , matka boss OTC 420, Indian Satta, India matka, matka ank, spbossmatka, online satta matka game play, live satta matka results, fix fix fix satta namber, free satta matka games, Kalyan matka jodi chart, Kalyan weekly final anl matka 420
High-Quality IPTV Monthly Subscription for $15advik4387
Experience high-quality entertainment with our IPTV monthly subscription for just $15. Access a vast array of live TV channels, movies, and on-demand shows with crystal-clear streaming. Our reliable service ensures smooth, uninterrupted viewing at an unbeatable price. Perfect for those seeking premium content without breaking the bank. Start streaming today!
https://rb.gy/f409dk
1. CHAPTER -1
INTRODUCTION
For the power generation with 2x110 MW, 3x210 MW and 2x195 MW of K.S.T.P.S. authorities
are required to be operative to active full operation. The auxiliaries are basically operation either
on L.T. System i.e. 415 V 3-Ø power supply is made available to the system after providing the
station transformer of 3x50 MVA capacity with voltage 220 KV/ 7.2/7.2 KV & different service
transformers of capacity 1.0 MVA, 1.5 MVA, 2.0 MVA, which are located near the load centre
as the transformer having the voltage of 6.6 KV /415 V. The 6.6 KV power is distributed
through 6.6 KV interconnected Bus System for all the five units with a control through DC
The 415 V power supply is done through a L.T. SWGR (Switchgear) which are located
nearby the distribution transformer as well as the load centers. The all incomers, which are
breaker controlled , are having the control the L.T. SWGR are having the control system on 110/
220 V AC. The 6.6 KV power supply which are either MOCB(Minimum Oil Circuit Breaker) of
JYOTIMAKE or Air Circuit Breakers.
The 6.6 KV power supply to various draining equipment’s i.e. more is made through
breakers which are either MOCB of Jyoti make air circuit breaker which are either of voltage
makers as well as SF 6 of NGEF make. The LT supply is also controlled through air break
circuit breaker which are either L&T make or English Electric Company of India. The various
H.T. motors are switched on started through on direct ON line (DOL) in order to inverse the
availability of equipment at full efficiency without time gap.
Further, the 6.6 KV system which is normally in delta configuration and terms as an
unearthed system so also to keep the running motor complete in operating condition in case of
anyone .phase of motor winding is earthed due to any one reason. Earthling is detected by an
protection system with alarm facility to take remedial measures immediately and at the same
time to maintain the generation level in the same condition, prior to occurring the earth fault the
single phase earth fault is detected in due course till the motor is not earthed to other or another
phase. “PUBLIC ADDRESS SYSTEM” is available through in area of each unit which helps in
fast communication for prompt remedial measure.
1
2. K.S.T.P.S. IS DESISIGNED IN FOLLOWING STAGES
STAGE I - 2x110 MW
STAGE II - 2X210 MW
STAGE III - 1X210 MW
STAGE IV - 1X195 MW
STAGE V - 1X195MW
LOCATION
The Kota Thermal Power Station is ideally on the left bank of Chambal River at Up Stream of
Kota Barrage. The large expanse of water reached by the barrage provides an efficient direct
circulation of cooling system for the power station. The 220 KV GSS is within ½ kms. from the
power station
COAL
Coal India limited owns and operates all the major coal fields in India through its coal producing
subsidiary companies viz. Northern Coal Fields Limited, South Eastern Coal Fields Limited,
Coal India limited is supply coal from its coal mines of coal producing subsidiaries SECL &
NCL to Kota Thermal Power Station through railway wagons. The average distances of SECL,
NCL are 800, 950 Kms. respectively.
WATER
The source of water for power station is reservoir formed by Kota Barrage on the Chambal
River. In case of large capacity plants huge quantities of coal and water is required. The cost of
transporting coal and water is particularly high. Therefore, as far as possible, the plant must be
located near the pit rather than at load centre for load above 200 MW and 375 MW. The
transportation of electrical energy is more economical as compared to the transportation of coal.
DESIGN FEATURES
The satisfactory design consists of the flowing steps.
• Estimation of cost.
• Selection of site.
• Capacity of Power Station.
• Selection of Boiler & Turbine.
2
3. • Selection of Condensing Unit.
• Selection of Electrical Generator.
• Selection of Cooling System.
• Design of Control and instrumentation system.
3
4. CHAPTER -2
GENERAL LAYOUT & BASIC IDEA
A control system of station basically works on Rankin Cycle. Steam is produced in Boiler is
exported in prime mover and is condensed in condenser to be fed into the boiler again. In
practice of good number of modifications are affected so as to have heat economy and to
increase the thermal efficiency of plant.
FIGURE 1:- PLANT OVERVIEW
The Kota Thermal Power Station is divided into four main circuits
Fuel and Ash Circuit.
Air and Gas Circuit.
Feed water and Steam Circuit.
Cooling Water Circuit.
4
5. Fuel & Ash Circuit
Fuel from the storage is fed to the boiler through fuel handling device. The fuel used in KSTPS
is coal, which on combustion in the boiler produced the ash. The quantity of ash produced is
approximately 35-40% of coal used. This ash is collected at the back of the boiler and removed
to ash storage tank through ash disposal equipment.
Air and Gas Circuit
Air from the atmosphere is supplied to the combustion chamber of Boiler through the action of
forced draft fan and induced draft fan. The flue gas gases are first pass around the boiler tubes
and super heated tubes in the furnace, next through dust collector (ESP) & then economizer.
Finally, they are exhausted to the atmosphere through fans.
Feed Water and Steam Circuit
The condensate leaving the condenser is first heated in low pressure (LP) heaters through
extracted steam from the lower pressure extraction of the turbine. Then its goes to dearator
where extra air and non-condensable gases are removed from the hot water to avoid pitting /
oxidation. From deaerator it goes to boiler feed pump which increases the pressure of the water.
From the BFP it passes through the high pressure heaters.
Cooling Water Circuit
A large quantity of cooling water is required to condense the steam in condenser and marinating
low pressure in it. The water is drawn from reservoir and after use it is drained into the river.
COAL HANDLING PLANT
5
6. FIGURE 2:- COAL HANDLING PLANT
INTRODUCTION
It can be called the heart of thermal power plant because it provided the fuel for combustion in
boiler. The coal is brought to the KSTPS through rails there are fourteen tracks in all for
transportation of coal through rails. The main coal sources for KSTPS are SECL (South Eastern
Coalfields Limited), NCL (Northern Coalfield Limited). Everyday 6 to 7 trains of coal are
unloaded at KSTPS. Each train consists of 58 wagons and each wagons consists of 50 tones of
coal. The approximate per day consumption at KSTPS is about 18000 metric tones. It costs
approximate 4.5 crores of rupees per day including transportation expenses. The coal is firstly
unloaded from wagon by wagon triplers then crushed by crushers and magnetic pulley and
pulverized to be transformed to the boiler. The whole transportation of coal is through conveyor
belt operated by 3-Ø Induction motor.
The coal handling plant can broadly be divided into three sections :-
1) Wagon Unloading System.
2) Crushing System.
3) Conveying System
CONVEYING SYSTEM
Stacker Reclaimer
The stacker re-claimer unit can stack the material on to the pipe or reclaim the stack filed
material and fed on to the main line conveyor. While stacking material is being fed from the
main line conveyor via tripler unit and vibrating feeder on the intermediate conveyor which feds
the boom conveyor of the stacker cum reclaimer. During reclaiming the material dis discharged
on to the boom conveyor by the bucket fitted to the bucket wheel body and boom conveyor feeds
the material on the main line conveyor running in the reverse direction.
FEEDERS
This structure is erected to serve the purpose of storage. Underground machines are installed
known as plow feeder machines.
These machines collect the coal from conveyor and drop it to the other from one
conveyor with the help of jaws and this coal is taken to huge erected structure from where the
coal falls to the ground. Jali chutes are used to prevent dust.
6
7. FIGURE 3:- ASH HANDLING PLANT
This plant can be divided into 3 sub plants as follows:-
1) Fuel and Ash Plant.
2) Air and Gas Plant.
3) Ash Disposal and & Dust Collection Plant.
Fuel and ash plant
Coal is used as combustion material in KTPS, In order to get an efficient utilization of coal
mills. The Pulverization also increases the overall efficiency and flexibility of boilers. However
for light up and with stand static load, oil burners are also used. Ash produced as the result of
combustion of coal is connected and removed by ash handling plant. Ash Handling Plant at
KTPS consists of specially designed bottom ash and fly ash in electro static precipitator
economizer and air pre-heaters hoppers.
7
8. Air & Gas Plant
Air from atmosphere is supplied to combustion chamber of boiler through the action of forced
draft fan. In KTPS there are two FD fans and three ID fans available for draft system per unit.
The air before being supplied to the boiler passes through pre-heater where the flue gases heat it.
The pre heating of primary air causes improved and intensified combustion of coal.
Ash Disposal & Dust Collection Plant
KSTPS has dry bottom furnace. Ash Handling Plant consists of especially designed bottom and
fly ash system for two path boiler. The system for both units is identical and following
description is applied to both the units the water compounded bottom ash hopper receives the
bottom ash from the furnace from where it is stores and discharged through the clinker grinder.
Two slurry pumps are provided which is common to both units & used to make slurry and
further transportation to ash dyke through pipe line.
ELECTRO-STATIC PRECIPITATOR
FIGURE 4:- ELECTRO-STATIC PRECIPITATOR
8
9. Scope & Principle of Operation
For general mankind, today an Eco friendly industry is must. As far as air pollution is concerned
now a days various flue gases filter are there in service. The choice depends on the size of
suspended particle matter. These filters are E.S.P. Fabric filter high efficiency cyclone
separations and sitelling room. Fop fly ash , where the particle size vary from 0.75 microns to
100 micron use gradually use E.S.P. to purify the flue gases due to its higher efficiency & low
running cost etc. In an ESP the dust lidder gas is passed through an intense electric field, which
causes ionization of the gases & they changed into ion while traveling towards opposite charged
electrode get deposited as particles and thus dust is electric deposited an electrode creating the
field. It is continuous process.
CONTROLLER
Now a day micro-processor based intelligent controllers are used to regulate the power fed to
the HVR. The controls the firing / ignition angle of the thyristor connected in parallel mode.
Input out waves of the controller and HVR are also shown above, which clearly indicates that
average power fed to ESP field can be controlled by variation of the firing angle of thyristor.
The output of controller with respect to time is also controlled by microprocessor,
so that ESP operation is smooth and efficient.
HIGH VOLTAGE RECTIFIER TRANSFORMER
HVR receives the regulated supply from controller. It steps up to high voltage rectifier. The
D.C. supply is fed to E.S.P. field through its negative bushing. The positive bushing so
connected to earth through small resistance which forms a current feedback circuit. A very high
resistance column is also connected with negative bushing. It forms the voltage feedback circuit.
These two feedback are used in the controller for indication and control purpose.
9
10. CHAPTER-3
BOILER
A boiler (or steam generator) is a closed vessel in which water, under pressure is converted into
steam. It is one of the major components of a thermal power plant. A boiler is always designed
to absorb maximum amount of heat released in process of combustion. This is transferred to the
boiler by all the three modes of heat transfer i.e. conduction, convection and radiation.
Boilers are classified as
Fire tube boiler
FIGURE 5:- FIRE TUBE BOILER
In this type the products of combustion pass through the tubes which are surrounded by water.
These are economical for low pressure only.
Water tube boiler
FIGURE 6:- WATER TUBE BOILER
10
11. In this type of boiler water flows inside the tubes and hot gases flow outside the tubes. These
tubes are interconnected to common water channels and to steam outlet.
• The water tube boilers have many advantages over the fire tube boilers
• High evaporation capacity due to availability of large heating surface.
• Better heat transfer to the mass of water.
• Better efficiency of plant owing to rapid and uniform circulation of water in tubes.
• Better overall control.
• Easy removal of scale from inside the tubes.
Furnace
Furnace is primary part of the boiler where the chemical energy available in the fuel is converted
into thermal energy by combustion. Furnace is designed for efficient and complete combustion.
Major factors that assist for efficient combustion are the temperature inside the furnace and
turbulance, which causes rapid mixing of fuel and air. In modern boilers, water-
cooled furnaces are used.
PULVERISED FUEL SYSTEM
The boiler fuel firing system is tangentially firing system in which the fuel is introduced from
wind nozzle located in the four corners inside the boiler.
The crushed coal from the coal crusher is transferred into the unit coalbunkers where the
coal is stored for feeding into pulverizing mill through rotary feeder. The rotary feeders feed the
coal to pulverize mill at a definite rate. Then coal burners are employed to fire the pulverized
coal along with primary air into furnace. These burners are placed in the corners of the furnace
and they send horizontal streams of air and fuel tangent to an imaginary circle in the center of the
furnace.
Fuel Oil System
The functional requirement of the fuel burning system is to supply a controllable and
uninterrupted flammable furnace input of fuel and air and to continuously ignite and burn the
11
12. fuel as rapidly as it is introduced into the furnace. This system provides efficient conversion of
chemical energy of fuel into heat energy. The fuel burning system should function such that fuel
and air input is ignited continuously and immediately upon its entry into furnace.
BOILER DRUM
The drum is a pressure vessel. Its function is to separate water and steam from mixture (of steam
& water) generated in the furnace walls. It provides water storage for preventing the saturation of
tubes. It also houses the equipment needed for purification of steam. The steam purification
primarily depends on the extent of moisture removal, since solids in steam are carried by the
moisture associated with it. The drum internals reduce the dissolved solids content of the steam
to below the acceptable limit. drum is made up of two halves of carbon steel plates having
thickness of 133 mm.
7:- STEAM DRUM INTERNALS
Boiler drum is located at a height of 53m from ground. The drum is provided with manholes and
manhole covers. Manhole is used for facilitating the maintenance person to go inside the drum
for maintenance.
12
13. Main parts of boiler drum are
• Feed pipe
• Riser tube
• Down comer
• Baffle plate
• Chemical dosing pipe
• Turbo separation
• Screen dryer
• Drum level gauge
Draft System
The combustion process in a furnace can take place only when it receives a steady flow of air
and has the combustion gases continuously removed. Theoretically balanced draft means
keeping furnace pressure equal to atmospheric pressure, but in practice the furnace is kept
slightly below atmospheric pressure. It ensures that there is no egress of air or hot gas and ash
into boiler house.
Draught Fans
A fan can be defined as volumetric machine which like pumps moves quantities of air or gas
from one place to another. In doing this it overcomes resistance to flow by supplying the fluid
with the energy necessary for contained motion. The following fans are used in boiler house.
Primary air fan (P.A. fan) or Exhauster fan
Pulverized coal is directly fed from coal mills to the burners at the four corners of the furnace
through coal pipes with the help of heated air coming from PA fan. Secondly, this fan also dries
the coal. Usually sized for 1500 RPM due to high pressure.
Forced draught fan (F.D. fan)
13
14. The combustion process in the furnace can take place only when it receives a steady flow of air.
This air is supplied by FD fan. Thus FD fan takes air from atmosphere at ambient temperature &
so provides additional draught. Its speed varies from 600-1500 RPM.
Specification of Force
Draft fan:
3φ,6.6KV,700KW
Rated.current-74A RPM-1500
Discharge- 408 T/Hr
FIGURE 8:-
FD FAN
Induced draught fan (I.D. fan)
The flue gases coming out of the boiler are passed to the ESP & then dust free gases are
discharged up by the chimney to the atmosphere through the ID fan.
FIGURE 9:-ID FAN
Specification of ID fan
Rated.current-192.1A
Discharge- 720 T/Hr
3φ,6.6KV,1750KW
14
15. Igniter air fan
It is used to provide necessary combustion air to igniter. Two fans are usually provided. One will
run and 2nd
will remain as stand by. A control damper is provided on the discharge which
modulates to maintain a constant differential pressure across igniter when any igniter is in
service. Typical speed is 1460 RPM.
Scanner Air Fan
Used to provide necessary cooling air to the flame scanners. Two air fans are usually provided.
One will run and other will remain as stand by. When F.D. fans trip the scanner air fan will draw
air from atmosphere through emergency damper. Typical speed 3000 RPM.
Economizer
FIGURE 10:- ECONOMIZER
15
16. FIGURE 11:- ECONOMIZER FIGURE 12:- AIR PRE HEATER
The flue gases coming out of the boiler carry lot of heat. An economiser extracts a part of this
heat from the flue gases and uses it for heating the feed water before it enters into the steam
drum. The use of economiser results in saving fuel consumption and higher boiler efficiency but
needs extra investment. In an economizer, a large number of small diameter thin walled tubes are
placed between two headers. Feed water enters the tubes through the other. The flue gases flow
outside the tubes.
Air preheaters
FIGURE 13:- AIR PRE HEATERS
Air preheaters are employed to recover the heat from the flue gases leaving the economiser and
are used to heat the incoming air for combustion. This raises the temperature of the furnace
gases, improves combustion rates and efficiency and lowers the stack (chimney) temperature,
thus improving the overall efficiency of the boiler. Cooling of flue gases by 20% raises the plant
efficiency by 1%.
16
17. Super heater
FIGURE 14:- SUPER HEATER
Superheated steam is that steam, which contains more heat than the saturated steam at the same
pressure i.e. it, has been heated above the temperature corresponding to its pressure. This
additional heat provides more energy to the turbine and thus the electrical power output is more.
Re-heater
Re-heaters are provided to raise the temperature of the steam from which part of energy has
already been extracted by HP turbine. This is done so that the steam remains dry as far as
possible through the last stage of the turbine. A re-heater can also be convection, radiation or
combination of both.
Circulation System
In natural circulation system, water delivered to steam generator from header, which are at a
temperature well below the saturation value corresponding to that pressure. After header, it is
delivered to economizer, which heated to above the saturation temperature.
From economizer the water enters the drum and thus joins the circulation system through
down covering water wall tubes. In water wall tubes a part of the water is converted to steam
17
18. due to boiler and the mixture flows back to the drum. In the drum, the steam is separated out
through the steam separators and passed to the super heater. After the super heater when the
steam temperature becomes high and pressure upto 150 Kg./cm3
steam is allowed to enter the
turbine to convert potential energy to kinetic energy.
CHAPTER - 4
STEAM TURBINE
INTRODUCTION
Turbine is a machine in which a shaft is rotated steadily by impact or reaction of current or
stream of working substance (steam, air, water, gases etc) upon blades of a wheel. It converts the
potential or kinetic energy of the working substance into mechanical power by virtue of dynamic
action of working substance. When the working substance is steam it is called the steam turbine.
FIGURE 15 :-STEAM TURBINE
PRINCIPAL OF OPERATION OF STEAM TURBINE
(1.) Working of the steam turbine depends wholly upon the dynamic action of Steam. The steam
is caused to fall in pressure in a passage of nozzle: doe to this fall in pressure a certain amount of
heat energy is converted into mechanical kinetic energy and the steam is set moving with a
greater velocity. The rapidly moving particles of steam, enter the moving part of the turbine and
18
19. here suffer a change in direction of motion which gives rose to change of momentum and
therefore to a force. This constitutes the driving force of the machine.
(2.) Blade may be less than that at the inlet side of the blades; the drop in pressure suffered by
the steam during its flow through the moving causes a further generation of kinetic energy
within the blades and adds to the propelling force which is applied to the turbine rotor. Such a
turbine is broadly termed as impulse reaction turbine
(3.) The blade or deflector, in which the steam particles changes its directions and hence its
momentum changes . The blades are attach to the rotating elements are attached to the stationary
part of the turbine which is usually termed the stator, casing or cylinder.
Although the fundamental principles on which all steam turbine operate the same, yet
the methods where by these principles carried into effect very end as a result, certain types of
turbine have come into existence.
A. Simple impulse steam turbine.
B.The pressure compounded impulse turbine.
C.Simple velocity compounded impulse turbine.
D.Pressure-velocity compounded turbine.
E.Pure reaction turbine.
F.Impulse reaction turbine.
TECHNICAL DATA OF TURBINES
The main technical data of 110 MW turbine is given below:-
Rated output 110 MW
Economic output 95 MW
Rated speed 3000 rpm
Direction of rotation viewing from the Front bearing pedestal. Clockwise
Rated steam pressure before stop valve. 130 ata
Maximum steam pressure before stop valve. 146 ata
Rated temperature of steam before the Stop valve 535o
C
Maximum temperature of steam before the Stop valve 545o
C
Rated pressure of steam MP Casting 31.6 ata
Rated pressure of steam before MP Casting 35 ata
.
19
20. MP Casing
Rated Temp. of steam before MP Casing 535o
C.
Maximum Temp. of steam before MP Casting 545o
C
Informative heat flow at the economic output 2135 K cal/Kwh
Informative heat rate at the rated output 2152.5 K Cal/Kwh.
HP Cylinder 2 row carts wheel
+ 8 moving wheels
MP Cylinder 12 moving wheels.
LP cylinder 4 moving wheels of
Double row design.
Quantity of oil for first filling. 1800 liters.
TECHNICAL DATA OF 210 MW TURBINE
Rated Output 210 MW.
Rated Speed. 3000 rpm.
Main steam pressure. 150 Kg./Cm2
Main steam temperature. 535o
C
Reheat steam temperature. 535o
C.
Weight of turbine. 475 T approx.
Overall length. 16.975 Mtrs. approx.
Single flow HP turbine with 25 reaction stages.
Double flow IP turbine with 20 reaction stages per flow.
Double flow LP turbine with 8 reaction stages per flow.
2 main stop & control valves. 2 steam check valve in CRH.
2 reheat stop & control valves,. 2 bypass stop & control valve.
turbines installed for unit 1 & 2 and 210 MW turbines installed for units 3, 4 & 5 & two 195
MW turbine installed for unit 6 & 7.
ELECTRICITY GENERATOR
20
21. Thermal power station burns the fuel and use the resultant heat to raise the steam which drives
the turbo-generator. The fuel may be “Fossil” (Coal, Oil and Natural Gas) whichever fuel is
used the object is same to convert the heat into mechanical energy to electrical energy by
rotating a magnet inside the set of winding. In a coal fired thermal power station other raw
materials are air and water. The coal is brought to station by train or other means travels from
the coal handling system.
i) By conveyer belts to coal bunkers from where it is fed to pulverizing mills.
ii) Mills grind it fine as face powder.
iii) Then this powdered coal mixed with preheated air is blow into boiler by a Fan known as
primary air fan (PA fan).
iv) When it burns more like a gas as solid in conventional domestic or industrial grate with
additional amount of air called secondary air supplied by “Forced Draft Fan”. As the coal has
been grinded so resultant ash is also as fine as powder. Some of its fine particles blinds
together to form a lump which falls into the ash pit at the bottom of furnace.
v) The water quenched ash from the bottom of furnace is carried out boiler to pit for
subsequent disposal.
vi) Most of ash still in fine particles form is carried out to electrostatic precipitators where it is
trapped by electrode charged with high voltage electricity. The dust is then conveyed to the
disposal area or to bunkers for sale.
vii)Now after passing through ESP few gases are discharged up to chimney
MAIN PARTS OF GENERATOR
(A) STATOR
1.STATOR FRAME
The stator frame of welded steel frame construction, which gives sufficient & necessary rigidity
to minimize the vibrations and to withstand the thermal gas pressure. form mounting of
generator bearings and radial shaft seals coolers.
21
22. FIGURE 16:- STATOR ASSEMBLY
2. STATOR CORE
It is built up of special sheet laminations and whose assembly is supported by a special guide
bass. The method of construction ensures that the core is firmly supported at a large number of
points on its periphery.
3. STATOR BARS
Stator bars are manufactured as half bars. Each stator half coil is composed of double glass cover
and bars of copper transposed in straight portion of “Robill Method” so that each strip occupies
every radial portion in the bar. For an equal length along the bar
4. STATOR WINDINGS
Stator windings are double star layers, lap wound, three phase, short pitch type. The top &
bottom are brazed and insulated at either end to form turns. Several such turns form a phase.
Phases are connected to form a double star winding.
22
23. 5. TERMINAL BUSHINGS
Six output leads (3long, 3short) have been brought out of the coming on the exciter side.
External connections are to be made to the three shorter terminals, which are phase terminals.
The large terminals are of neutral & current transformer is inserted.
6. BEARINGS
Generator bearings have electrical seats of consists of steel bodies with removable steel pads.
The bearings are formed for forced lubrication of oil at a pressure of 2-3 ATM/ From the same
pump that supplies oils to the turbine, bearings & governing gears. There is a provision to
ensure & measure the rotor bearing temperature by inserting a resistance thermometer in the oil
pockets.
7. VENTILATION SYSTEM
The machine is designed with ventilation system having 2 atm rated hydrogen pressure. Two
axial fans mounted on either side of the rotor to ensure circulation of hydrogen. The stator is
designed for radial ventilation by stem. The end stator core packets & core clamping & plates are
intensively cooled.
(B) ROTOR
FIGURE 17:- ROTOR
Rotor shaft consists of single piece alloy steel forging of high mechanical and magnetic
properties performance test includes-
1. Tensile test on specimen piece.
2. Surface examination.
23
24. 3. Sulfur prist tests.
4. Magnetic crack detection.
5. Visual examination of bore.
6. Ultrasonic examination.
ROTOR WINDINGS
Rotor winding is of direct coil type and consists of parallel strips of very high conductivity
Silver Bearing Copper, bent on edge to form coil. The coils are placed in impregnated glass,
laminated short shells; using glass strips inter turn insulation and will be brazed at the end to
form continuous winding.
BEARINGS
The bearings are self-aligned & consist of slip steel shells linked with special bearing metal
having very low coefficient of friction. The bore is machined on an elliptical shape so as to
increase the mechanical stability of the rotor
SLIP RINGS
The slip rings are made of forged steel. They are located at either side of Generator Shaft. The
slip ring towards the exciter side is given +ve polarity initially. They have helical grooves and
skewed holes in the body for cooling purpose by air.
BUSH GEAR ASSEMBLY
Generator bushes are made from the various compositions of natural graphite and binding
material. They have a low coefficient of friction and are self lubricating. The brushes are
provided with a double flexible copper or pigtails.
TECHNICAL DATA
Generator (110 MW)
Content Rating
Continuous apparent power 1,37,500 KVA
Active power 7,10,000 KW
Power factor 0.8 (lagging).
Rated voltage 1000 + 5% rated
Current 7,220 A
Critical speed 3000 r. p. m.
24
25. frequency 50 Hz
Phase connection double star
No. of terminals 6
Main diameter of slip rings 420 mm.
Voltage regulation 39%.
Reactance Informative.
CHAPTER - 5
EXCITATION SYSTEM
25
26. The electric power Generators requires direct current excited magnets for its field system. The
excitation system must be reliable, stable in operation and must response quickly to excitation
current requirements.
(A) Function of excitation system
The main function of excitation system is to supply required excitation current at rated load
condition of turbo Generator. It should be able to adjust the field current of the Generator, either
by normal controller automatic control so that for all operation & between no load and rated
load. The terminal voltage of the system machine is maintained at its value
(B)Type of Excitation System
There have been many developments in excitation system design. There has been continuing
reach among the design and the use alike from improving the excitation system performance.
The ultimate is to achieve stability, accuracy etc
WATER TREATMENT PLANT
The principle problem in high pressure boiler is to control corrosion and steam quality. Internal
corrosion costs power station crores of rupees in repair without strict control impurities in steam
also form deposit over turbine blades and nozzles. The impurities present in water are as follows
1) Un-dissolved and suspended solid materials.
2) Dissolved slats and minerals.
3) Dissolved gases.
CHAPTER-6
TRANSFORMER
26
27. Transformer is a static device which is used to change the voltage level keeping the power and
frequency same. In the plant transformer is one of the most important equipment. In the whole
plant, there are about 83 transformer installed at various places to operate the auxiliaries.
Main transformers, which are necessary:
1. To step up the generated voltage.
2. To supply power to the auxiliaries from the generator.
3. To start the plant by taking the supply from the grid.
Are installed in a transformer yard. It is located in between the main plant and the switchyard.
The main transformers installed in the transformer yard are:
1. GENERATOR TRANSFORMER (GT-A)
It steps up the voltage from 16.5 KV to 220 KV. It connects the plant with the 220 KV
switchyard.
2.GENERATOR TRANSFORMER (GT–B)
It steps up the voltage from 16.5 KV to 400 KV. It connects the plant with the 400 KV
switchyard.
3.STATION TRANSFORMER (ST)
It is a step down transformer with 50 MVA capacities. It is used to step down 220 KV from the
grid to 6.9 KV.
4.UNIT AUXILIARY TRANSFORMER (UAT)
It is a step down transformer with 20 MVA capacities. It steps down the voltage from 16.5 KV
to 6.9 KV.
5. STATION SERVICE TRANSFORMER (SST)
It is a step down transformer with 2MVA capacity. It is used to step down from 6.6 KV to
0.4333 KV.
6.UNIT SERVICE TRANSFORMER (UST)
27
28. It is a step down transformer with 2 MVA capacity. It is used to step down from 6.6 kV to
0.4333 KV.
WORKING OF TRANSFORMER
FIGURE 18:- WORKING OF TRANSFORMER
TABLE ABOUT GENERATOR TRANSFORMER
Type of cooling ONAN ONAF OFAF
Rating HV (in MVA)
Rating LV (in MVA)
160
160
240
240
315
315
Line Current HV 219.9 329.9 433.0
Line Current LV 5598.5 8397.8 11022
Temperature rise in oil (°C) 45 45 45
Temperature rise in wdg (°C) 50 50 50
TABLE-GENERATOR TRANSFORMER
No load voltage HV (KV) - 420KV
No Load voltage LV (KV) - 16.5 KV
Connection symbol - Ynd11
Oil - 65300 Liters
There are 5 generator transformers in the plant, one for each unit. The output from the generator
is fed to the generator transformer, which step up the voltage from 16.5 KV to 400 KV and
supplies power to grid.
28
29. STATION TRANSFORMER
When the unit is to be started, power supplied to the auxiliaries is taken from the station
transformer. The rating of the station transformer is 50 MVA. It takes power from the grid at 220
kV and steps it down to 6.6 kV. At the time of starting all the auxiliaries are supplied from the
station transformer. When the generator is synchronized and starts producing power, about 80%
of the load is shifted on to the unit auxiliary transformer. The load that requires uninterrupted
supply is left connected on the station transformer.
There are 5 S.T’s in the plant, one for each stage.
Type of cooling ONAN ONAF
MVA rating
H.V.
L.V.
40
26
50
31.05
Current (line)
H.V.
L.V.
105
3351
131
4189
Voltage (line)
H.V. L.V.
220 Kv 6.9 Kv
UNIT AUXILIARY TRANSFORMER
Each unit has two unit auxiliary transformers. When the unit starts generating electricity these
transformers are energized and then supplies power to the auxiliaries. Before starting of the unit,
UAT bus is connected to the station bus. Auxiliaries of one unit take about 20MW of power.
UAT is connected between the generator and the GT.
UNIT STATION TRANSFORMER
It is a step down transformer, which is connected to the station bus. It steps down the voltage
from 6.6 kV to 0.433 kV it is used to supply the low voltage auxiliaries.
UNIT SERVICE TRANSFORMER
It is also a 66-kV/ 415 V transformers which is used to supply the auxiliaries connected to the
unit secondary switchgear bus.
29
30. SWITCH YARD
220 KV SYSTEM
Two 220 KV bus bars have been provided in switch yard and are inter-connected through a bus
coupler. Each of the two 110 MW generator is connected to this system through a step up of 125
MVA 240/ 11 KV yard generator transformer. There are two step down transformer each
feeding 6.6 KV system ( Station Switchyard ) viz. BS-IS & SB-IB. Each station transformer has
two windings one secondary side and is rated for 50/25/25 mva, 270/7/7.2 kva four feeder take
off from 220 switch yard, two to SKATPURA GSS and other to HEERAPURA , Jaipur GSS.
Each of four feeder are provided with bypass isolators which is connected across line breaker
and breaker isolator. By closing bus coupler between 220 KV buses and putting line feeders
whose breaker required maintenance of any one bus through by pass isolators and all other line
feeders whose breaker is by passed is then transformed to bus coupler breaker. A brief
description of equipments of 220 KV system is as follows.
CIRCUIT BREAKERS
Each of generator transformer, station transformer, line feeder and bus coupler is provided with
minimum oil circuit breaker of BHEL make. It is rated for 245 KW, 2500 A and 13400 MVA
circuit breaker is used to break the circuit either in load condition or in no load condition.
ISOLATOR
All the isolators are provided in 220KV switchyard and are motor operated. Triple pole double
breaker type and power switch yard L&T make these and are rates for 245 KV and 1250 A. The
four isolators are provided with earth switch.
CURRENT TRANSFORMER
All the 220 KV current transformers are provided for measuring and protection. They are BHEL
make, single phase, oil filled nitrogen sealed outdoor type. All the E.T.S. are multi-cored with
each core having specification upon duty it is to perform. Feeder circuit have 5 cores.
1) Bus bar protection core I 1250/250/IA.
30
31. 2) Distance protection core II 600-300/IA.
3) O/C and E/F protection core 600-300 /IA.
4) For metering and measuring 600-300/ IA.
POTENTIAL TRANSFORMER
Each of 220 KV buses is provided with three P.T.’S are core for each phase of BHEL make.
There are single phase, oil filled outdoor. N2 sealed, elicitor magnetic type P.T. has two
secondary windings on secondary side and selected for 220/53 KV, 10/53 KV.
LIGHTENING ARRESTOR
For protection against lightening each of line feeders, generator transformer, station transformer
has been provided with three L.A. (one for each phase). It has larger value of capacitance and
will change up to line voltage. If we have to do some work on line, first earth line through
earthing isolator for discharging the line capacitance and then work.
220 KV Current Transformer
Manufacturer. BHEL, Trichy.
Type Outdoor, Oil filled.
Rated Voltage. 220 KV
Nominal 220 KV
Max. 245 KV.
Rated Frequency. 50 Hz
No. of Phase. 1-Ø
Class of Insulation A.
Rated Primary Voltage 2220/ 53 V.
Secondary Voltage Wdg.1 110/53 V
Secondary Voltage Wdg.2 110/53 V
CHAPTER -7
PROTECTION
1. Field Protection.
2. Pole Slipping.
3. Plane Overload Protection.
4. Inter-turn Fault
5. Negative Phase Sequence Protection.
6. Reverse Power Protection.
31
32. 7. Forward Power Protection.
8. Under Frequency & Over Frequency Protection.
9. Generator Voltage Protection.
10. Rotor Earth Fault Protection.
General Protection
It is most important electrical equipment of many generating station. Tripping of even a
generating unit may cause overloading of associated machines and even to system un-stability .
The basis function of protection applied to generator is to reduce voltage to minimum by rapid
discrimination clearance of faults. Unlike other apparatus the opening of C.B. to isolate faulty
generator is not sufficient to prevent future damage.
CONCLUSION
The first phase of practical training has proved to be quiet fruitful. It provided an opportunity for
encounter with such huge machines like wagon tippler .110 MW, 210 MW & 195 MW turbines
and generators.
The architecture of the power plant the way various units are linked and the way
working of whole plant is controlled make the student realize that engineering is not just learning
the structured description and working of various machines, but the greater part is of planning
proper management.
32
33. It also provides an opportunities to lean low technology used at proper place and time
can cave a lot of labour e.g. wagon Tripler (CHP).But there are few factors that require special
mention. Training is not carried out into its tree sprit. It is recommended that there should be
some project specially meant for students where presence of authorities should be ensured.
There should be strict monitoring of the performance of students and system of grading be
improved on the basis of work done.
However training has proved to be quite fruitful. It has allowed an opportunity to get an
exposure of the practical implementation to theoretical fundamentals.
33