SlideShare a Scribd company logo
CHAPTER -1
INTRODUCTION
For the power generation with 2x110 MW, 3x210 MW and 2x195 MW of K.S.T.P.S. authorities
are required to be operative to active full operation. The auxiliaries are basically operation either
on L.T. System i.e. 415 V 3-Ø power supply is made available to the system after providing the
station transformer of 3x50 MVA capacity with voltage 220 KV/ 7.2/7.2 KV & different service
transformers of capacity 1.0 MVA, 1.5 MVA, 2.0 MVA, which are located near the load centre
as the transformer having the voltage of 6.6 KV /415 V. The 6.6 KV power is distributed
through 6.6 KV interconnected Bus System for all the five units with a control through DC
The 415 V power supply is done through a L.T. SWGR (Switchgear) which are located
nearby the distribution transformer as well as the load centers. The all incomers, which are
breaker controlled , are having the control the L.T. SWGR are having the control system on 110/
220 V AC. The 6.6 KV power supply which are either MOCB(Minimum Oil Circuit Breaker) of
JYOTIMAKE or Air Circuit Breakers.
The 6.6 KV power supply to various draining equipment’s i.e. more is made through
breakers which are either MOCB of Jyoti make air circuit breaker which are either of voltage
makers as well as SF 6 of NGEF make. The LT supply is also controlled through air break
circuit breaker which are either L&T make or English Electric Company of India. The various
H.T. motors are switched on started through on direct ON line (DOL) in order to inverse the
availability of equipment at full efficiency without time gap.
Further, the 6.6 KV system which is normally in delta configuration and terms as an
unearthed system so also to keep the running motor complete in operating condition in case of
anyone .phase of motor winding is earthed due to any one reason. Earthling is detected by an
protection system with alarm facility to take remedial measures immediately and at the same
time to maintain the generation level in the same condition, prior to occurring the earth fault the
single phase earth fault is detected in due course till the motor is not earthed to other or another
phase. “PUBLIC ADDRESS SYSTEM” is available through in area of each unit which helps in
fast communication for prompt remedial measure.
1
K.S.T.P.S. IS DESISIGNED IN FOLLOWING STAGES
 STAGE I - 2x110 MW
 STAGE II - 2X210 MW
 STAGE III - 1X210 MW
 STAGE IV - 1X195 MW
 STAGE V - 1X195MW
LOCATION
The Kota Thermal Power Station is ideally on the left bank of Chambal River at Up Stream of
Kota Barrage. The large expanse of water reached by the barrage provides an efficient direct
circulation of cooling system for the power station. The 220 KV GSS is within ½ kms. from the
power station
COAL
Coal India limited owns and operates all the major coal fields in India through its coal producing
subsidiary companies viz. Northern Coal Fields Limited, South Eastern Coal Fields Limited,
Coal India limited is supply coal from its coal mines of coal producing subsidiaries SECL &
NCL to Kota Thermal Power Station through railway wagons. The average distances of SECL,
NCL are 800, 950 Kms. respectively.
WATER
The source of water for power station is reservoir formed by Kota Barrage on the Chambal
River. In case of large capacity plants huge quantities of coal and water is required. The cost of
transporting coal and water is particularly high. Therefore, as far as possible, the plant must be
located near the pit rather than at load centre for load above 200 MW and 375 MW. The
transportation of electrical energy is more economical as compared to the transportation of coal.
DESIGN FEATURES
The satisfactory design consists of the flowing steps.
• Estimation of cost.
• Selection of site.
• Capacity of Power Station.
• Selection of Boiler & Turbine.
2
• Selection of Condensing Unit.
• Selection of Electrical Generator.
• Selection of Cooling System.
• Design of Control and instrumentation system.
3
CHAPTER -2
GENERAL LAYOUT & BASIC IDEA
A control system of station basically works on Rankin Cycle. Steam is produced in Boiler is
exported in prime mover and is condensed in condenser to be fed into the boiler again. In
practice of good number of modifications are affected so as to have heat economy and to
increase the thermal efficiency of plant.
FIGURE 1:- PLANT OVERVIEW
The Kota Thermal Power Station is divided into four main circuits
 Fuel and Ash Circuit.
 Air and Gas Circuit.
 Feed water and Steam Circuit.
 Cooling Water Circuit.
4
Fuel & Ash Circuit
Fuel from the storage is fed to the boiler through fuel handling device. The fuel used in KSTPS
is coal, which on combustion in the boiler produced the ash. The quantity of ash produced is
approximately 35-40% of coal used. This ash is collected at the back of the boiler and removed
to ash storage tank through ash disposal equipment.
Air and Gas Circuit
Air from the atmosphere is supplied to the combustion chamber of Boiler through the action of
forced draft fan and induced draft fan. The flue gas gases are first pass around the boiler tubes
and super heated tubes in the furnace, next through dust collector (ESP) & then economizer.
Finally, they are exhausted to the atmosphere through fans.
Feed Water and Steam Circuit
The condensate leaving the condenser is first heated in low pressure (LP) heaters through
extracted steam from the lower pressure extraction of the turbine. Then its goes to dearator
where extra air and non-condensable gases are removed from the hot water to avoid pitting /
oxidation. From deaerator it goes to boiler feed pump which increases the pressure of the water.
From the BFP it passes through the high pressure heaters.
Cooling Water Circuit
A large quantity of cooling water is required to condense the steam in condenser and marinating
low pressure in it. The water is drawn from reservoir and after use it is drained into the river.
COAL HANDLING PLANT
5
FIGURE 2:- COAL HANDLING PLANT
INTRODUCTION
It can be called the heart of thermal power plant because it provided the fuel for combustion in
boiler. The coal is brought to the KSTPS through rails there are fourteen tracks in all for
transportation of coal through rails. The main coal sources for KSTPS are SECL (South Eastern
Coalfields Limited), NCL (Northern Coalfield Limited). Everyday 6 to 7 trains of coal are
unloaded at KSTPS. Each train consists of 58 wagons and each wagons consists of 50 tones of
coal. The approximate per day consumption at KSTPS is about 18000 metric tones. It costs
approximate 4.5 crores of rupees per day including transportation expenses. The coal is firstly
unloaded from wagon by wagon triplers then crushed by crushers and magnetic pulley and
pulverized to be transformed to the boiler. The whole transportation of coal is through conveyor
belt operated by 3-Ø Induction motor.
The coal handling plant can broadly be divided into three sections :-
1) Wagon Unloading System.
2) Crushing System.
3) Conveying System
CONVEYING SYSTEM
Stacker Reclaimer
The stacker re-claimer unit can stack the material on to the pipe or reclaim the stack filed
material and fed on to the main line conveyor. While stacking material is being fed from the
main line conveyor via tripler unit and vibrating feeder on the intermediate conveyor which feds
the boom conveyor of the stacker cum reclaimer. During reclaiming the material dis discharged
on to the boom conveyor by the bucket fitted to the bucket wheel body and boom conveyor feeds
the material on the main line conveyor running in the reverse direction.
FEEDERS
This structure is erected to serve the purpose of storage. Underground machines are installed
known as plow feeder machines.
These machines collect the coal from conveyor and drop it to the other from one
conveyor with the help of jaws and this coal is taken to huge erected structure from where the
coal falls to the ground. Jali chutes are used to prevent dust.
6
FIGURE 3:- ASH HANDLING PLANT
This plant can be divided into 3 sub plants as follows:-
1) Fuel and Ash Plant.
2) Air and Gas Plant.
3) Ash Disposal and & Dust Collection Plant.
Fuel and ash plant
Coal is used as combustion material in KTPS, In order to get an efficient utilization of coal
mills. The Pulverization also increases the overall efficiency and flexibility of boilers. However
for light up and with stand static load, oil burners are also used. Ash produced as the result of
combustion of coal is connected and removed by ash handling plant. Ash Handling Plant at
KTPS consists of specially designed bottom ash and fly ash in electro static precipitator
economizer and air pre-heaters hoppers.
7
Air & Gas Plant
Air from atmosphere is supplied to combustion chamber of boiler through the action of forced
draft fan. In KTPS there are two FD fans and three ID fans available for draft system per unit.
The air before being supplied to the boiler passes through pre-heater where the flue gases heat it.
The pre heating of primary air causes improved and intensified combustion of coal.
Ash Disposal & Dust Collection Plant
KSTPS has dry bottom furnace. Ash Handling Plant consists of especially designed bottom and
fly ash system for two path boiler. The system for both units is identical and following
description is applied to both the units the water compounded bottom ash hopper receives the
bottom ash from the furnace from where it is stores and discharged through the clinker grinder.
Two slurry pumps are provided which is common to both units & used to make slurry and
further transportation to ash dyke through pipe line.
ELECTRO-STATIC PRECIPITATOR
FIGURE 4:- ELECTRO-STATIC PRECIPITATOR
8
Scope & Principle of Operation
For general mankind, today an Eco friendly industry is must. As far as air pollution is concerned
now a days various flue gases filter are there in service. The choice depends on the size of
suspended particle matter. These filters are E.S.P. Fabric filter high efficiency cyclone
separations and sitelling room. Fop fly ash , where the particle size vary from 0.75 microns to
100 micron use gradually use E.S.P. to purify the flue gases due to its higher efficiency & low
running cost etc. In an ESP the dust lidder gas is passed through an intense electric field, which
causes ionization of the gases & they changed into ion while traveling towards opposite charged
electrode get deposited as particles and thus dust is electric deposited an electrode creating the
field. It is continuous process.
CONTROLLER
Now a day micro-processor based intelligent controllers are used to regulate the power fed to
the HVR. The controls the firing / ignition angle of the thyristor connected in parallel mode.
Input out waves of the controller and HVR are also shown above, which clearly indicates that
average power fed to ESP field can be controlled by variation of the firing angle of thyristor.
The output of controller with respect to time is also controlled by microprocessor,
so that ESP operation is smooth and efficient.
HIGH VOLTAGE RECTIFIER TRANSFORMER
HVR receives the regulated supply from controller. It steps up to high voltage rectifier. The
D.C. supply is fed to E.S.P. field through its negative bushing. The positive bushing so
connected to earth through small resistance which forms a current feedback circuit. A very high
resistance column is also connected with negative bushing. It forms the voltage feedback circuit.
These two feedback are used in the controller for indication and control purpose.
9
CHAPTER-3
BOILER
A boiler (or steam generator) is a closed vessel in which water, under pressure is converted into
steam. It is one of the major components of a thermal power plant. A boiler is always designed
to absorb maximum amount of heat released in process of combustion. This is transferred to the
boiler by all the three modes of heat transfer i.e. conduction, convection and radiation.
Boilers are classified as
Fire tube boiler
FIGURE 5:- FIRE TUBE BOILER
In this type the products of combustion pass through the tubes which are surrounded by water.
These are economical for low pressure only.
Water tube boiler
FIGURE 6:- WATER TUBE BOILER
10
In this type of boiler water flows inside the tubes and hot gases flow outside the tubes. These
tubes are interconnected to common water channels and to steam outlet.
• The water tube boilers have many advantages over the fire tube boilers
• High evaporation capacity due to availability of large heating surface.
• Better heat transfer to the mass of water.
• Better efficiency of plant owing to rapid and uniform circulation of water in tubes.
• Better overall control.
• Easy removal of scale from inside the tubes.
Furnace
Furnace is primary part of the boiler where the chemical energy available in the fuel is converted
into thermal energy by combustion. Furnace is designed for efficient and complete combustion.
Major factors that assist for efficient combustion are the temperature inside the furnace and
turbulance, which causes rapid mixing of fuel and air. In modern boilers, water-
cooled furnaces are used.
PULVERISED FUEL SYSTEM
The boiler fuel firing system is tangentially firing system in which the fuel is introduced from
wind nozzle located in the four corners inside the boiler.
The crushed coal from the coal crusher is transferred into the unit coalbunkers where the
coal is stored for feeding into pulverizing mill through rotary feeder. The rotary feeders feed the
coal to pulverize mill at a definite rate. Then coal burners are employed to fire the pulverized
coal along with primary air into furnace. These burners are placed in the corners of the furnace
and they send horizontal streams of air and fuel tangent to an imaginary circle in the center of the
furnace.
Fuel Oil System
The functional requirement of the fuel burning system is to supply a controllable and
uninterrupted flammable furnace input of fuel and air and to continuously ignite and burn the
11
fuel as rapidly as it is introduced into the furnace. This system provides efficient conversion of
chemical energy of fuel into heat energy. The fuel burning system should function such that fuel
and air input is ignited continuously and immediately upon its entry into furnace.
BOILER DRUM
The drum is a pressure vessel. Its function is to separate water and steam from mixture (of steam
& water) generated in the furnace walls. It provides water storage for preventing the saturation of
tubes. It also houses the equipment needed for purification of steam. The steam purification
primarily depends on the extent of moisture removal, since solids in steam are carried by the
moisture associated with it. The drum internals reduce the dissolved solids content of the steam
to below the acceptable limit. drum is made up of two halves of carbon steel plates having
thickness of 133 mm.
7:- STEAM DRUM INTERNALS
Boiler drum is located at a height of 53m from ground. The drum is provided with manholes and
manhole covers. Manhole is used for facilitating the maintenance person to go inside the drum
for maintenance.
12
Main parts of boiler drum are
• Feed pipe
• Riser tube
• Down comer
• Baffle plate
• Chemical dosing pipe
• Turbo separation
• Screen dryer
• Drum level gauge
Draft System
The combustion process in a furnace can take place only when it receives a steady flow of air
and has the combustion gases continuously removed. Theoretically balanced draft means
keeping furnace pressure equal to atmospheric pressure, but in practice the furnace is kept
slightly below atmospheric pressure. It ensures that there is no egress of air or hot gas and ash
into boiler house.
Draught Fans
A fan can be defined as volumetric machine which like pumps moves quantities of air or gas
from one place to another. In doing this it overcomes resistance to flow by supplying the fluid
with the energy necessary for contained motion. The following fans are used in boiler house.
Primary air fan (P.A. fan) or Exhauster fan
Pulverized coal is directly fed from coal mills to the burners at the four corners of the furnace
through coal pipes with the help of heated air coming from PA fan. Secondly, this fan also dries
the coal. Usually sized for 1500 RPM due to high pressure.
Forced draught fan (F.D. fan)
13
The combustion process in the furnace can take place only when it receives a steady flow of air.
This air is supplied by FD fan. Thus FD fan takes air from atmosphere at ambient temperature &
so provides additional draught. Its speed varies from 600-1500 RPM.
Specification of Force
Draft fan:
3φ,6.6KV,700KW
Rated.current-74A RPM-1500
Discharge- 408 T/Hr
FIGURE 8:-
FD FAN
Induced draught fan (I.D. fan)
The flue gases coming out of the boiler are passed to the ESP & then dust free gases are
discharged up by the chimney to the atmosphere through the ID fan.
FIGURE 9:-ID FAN
Specification of ID fan
Rated.current-192.1A
Discharge- 720 T/Hr
3φ,6.6KV,1750KW
14
Igniter air fan
It is used to provide necessary combustion air to igniter. Two fans are usually provided. One will
run and 2nd
will remain as stand by. A control damper is provided on the discharge which
modulates to maintain a constant differential pressure across igniter when any igniter is in
service. Typical speed is 1460 RPM.
Scanner Air Fan
Used to provide necessary cooling air to the flame scanners. Two air fans are usually provided.
One will run and other will remain as stand by. When F.D. fans trip the scanner air fan will draw
air from atmosphere through emergency damper. Typical speed 3000 RPM.
Economizer
FIGURE 10:- ECONOMIZER
15
FIGURE 11:- ECONOMIZER FIGURE 12:- AIR PRE HEATER
The flue gases coming out of the boiler carry lot of heat. An economiser extracts a part of this
heat from the flue gases and uses it for heating the feed water before it enters into the steam
drum. The use of economiser results in saving fuel consumption and higher boiler efficiency but
needs extra investment. In an economizer, a large number of small diameter thin walled tubes are
placed between two headers. Feed water enters the tubes through the other. The flue gases flow
outside the tubes.
Air preheaters
FIGURE 13:- AIR PRE HEATERS
Air preheaters are employed to recover the heat from the flue gases leaving the economiser and
are used to heat the incoming air for combustion. This raises the temperature of the furnace
gases, improves combustion rates and efficiency and lowers the stack (chimney) temperature,
thus improving the overall efficiency of the boiler. Cooling of flue gases by 20% raises the plant
efficiency by 1%.
16
Super heater
FIGURE 14:- SUPER HEATER
Superheated steam is that steam, which contains more heat than the saturated steam at the same
pressure i.e. it, has been heated above the temperature corresponding to its pressure. This
additional heat provides more energy to the turbine and thus the electrical power output is more.
Re-heater
Re-heaters are provided to raise the temperature of the steam from which part of energy has
already been extracted by HP turbine. This is done so that the steam remains dry as far as
possible through the last stage of the turbine. A re-heater can also be convection, radiation or
combination of both.
Circulation System
In natural circulation system, water delivered to steam generator from header, which are at a
temperature well below the saturation value corresponding to that pressure. After header, it is
delivered to economizer, which heated to above the saturation temperature.
From economizer the water enters the drum and thus joins the circulation system through
down covering water wall tubes. In water wall tubes a part of the water is converted to steam
17
due to boiler and the mixture flows back to the drum. In the drum, the steam is separated out
through the steam separators and passed to the super heater. After the super heater when the
steam temperature becomes high and pressure upto 150 Kg./cm3
steam is allowed to enter the
turbine to convert potential energy to kinetic energy.
CHAPTER - 4
STEAM TURBINE
INTRODUCTION
Turbine is a machine in which a shaft is rotated steadily by impact or reaction of current or
stream of working substance (steam, air, water, gases etc) upon blades of a wheel. It converts the
potential or kinetic energy of the working substance into mechanical power by virtue of dynamic
action of working substance. When the working substance is steam it is called the steam turbine.
FIGURE 15 :-STEAM TURBINE
PRINCIPAL OF OPERATION OF STEAM TURBINE
(1.) Working of the steam turbine depends wholly upon the dynamic action of Steam. The steam
is caused to fall in pressure in a passage of nozzle: doe to this fall in pressure a certain amount of
heat energy is converted into mechanical kinetic energy and the steam is set moving with a
greater velocity. The rapidly moving particles of steam, enter the moving part of the turbine and
18
here suffer a change in direction of motion which gives rose to change of momentum and
therefore to a force. This constitutes the driving force of the machine.
(2.) Blade may be less than that at the inlet side of the blades; the drop in pressure suffered by
the steam during its flow through the moving causes a further generation of kinetic energy
within the blades and adds to the propelling force which is applied to the turbine rotor. Such a
turbine is broadly termed as impulse reaction turbine
(3.) The blade or deflector, in which the steam particles changes its directions and hence its
momentum changes . The blades are attach to the rotating elements are attached to the stationary
part of the turbine which is usually termed the stator, casing or cylinder.
Although the fundamental principles on which all steam turbine operate the same, yet
the methods where by these principles carried into effect very end as a result, certain types of
turbine have come into existence.
A. Simple impulse steam turbine.
B.The pressure compounded impulse turbine.
C.Simple velocity compounded impulse turbine.
D.Pressure-velocity compounded turbine.
E.Pure reaction turbine.
F.Impulse reaction turbine.
TECHNICAL DATA OF TURBINES
The main technical data of 110 MW turbine is given below:-
Rated output 110 MW
Economic output 95 MW
Rated speed 3000 rpm
Direction of rotation viewing from the Front bearing pedestal. Clockwise
Rated steam pressure before stop valve. 130 ata
Maximum steam pressure before stop valve. 146 ata
Rated temperature of steam before the Stop valve 535o
C
Maximum temperature of steam before the Stop valve 545o
C
Rated pressure of steam MP Casting 31.6 ata
Rated pressure of steam before MP Casting 35 ata
.
19
MP Casing
Rated Temp. of steam before MP Casing 535o
C.
Maximum Temp. of steam before MP Casting 545o
C
Informative heat flow at the economic output 2135 K cal/Kwh
Informative heat rate at the rated output 2152.5 K Cal/Kwh.
HP Cylinder 2 row carts wheel
+ 8 moving wheels
MP Cylinder 12 moving wheels.
LP cylinder 4 moving wheels of
Double row design.
Quantity of oil for first filling. 1800 liters.
TECHNICAL DATA OF 210 MW TURBINE
Rated Output 210 MW.
Rated Speed. 3000 rpm.
Main steam pressure. 150 Kg./Cm2
Main steam temperature. 535o
C
Reheat steam temperature. 535o
C.
Weight of turbine. 475 T approx.
Overall length. 16.975 Mtrs. approx.
Single flow HP turbine with 25 reaction stages.
Double flow IP turbine with 20 reaction stages per flow.
Double flow LP turbine with 8 reaction stages per flow.
2 main stop & control valves. 2 steam check valve in CRH.
2 reheat stop & control valves,. 2 bypass stop & control valve.
turbines installed for unit 1 & 2 and 210 MW turbines installed for units 3, 4 & 5 & two 195
MW turbine installed for unit 6 & 7.
ELECTRICITY GENERATOR
20
Thermal power station burns the fuel and use the resultant heat to raise the steam which drives
the turbo-generator. The fuel may be “Fossil” (Coal, Oil and Natural Gas) whichever fuel is
used the object is same to convert the heat into mechanical energy to electrical energy by
rotating a magnet inside the set of winding. In a coal fired thermal power station other raw
materials are air and water. The coal is brought to station by train or other means travels from
the coal handling system.
i) By conveyer belts to coal bunkers from where it is fed to pulverizing mills.
ii) Mills grind it fine as face powder.
iii) Then this powdered coal mixed with preheated air is blow into boiler by a Fan known as
primary air fan (PA fan).
iv) When it burns more like a gas as solid in conventional domestic or industrial grate with
additional amount of air called secondary air supplied by “Forced Draft Fan”. As the coal has
been grinded so resultant ash is also as fine as powder. Some of its fine particles blinds
together to form a lump which falls into the ash pit at the bottom of furnace.
v) The water quenched ash from the bottom of furnace is carried out boiler to pit for
subsequent disposal.
vi) Most of ash still in fine particles form is carried out to electrostatic precipitators where it is
trapped by electrode charged with high voltage electricity. The dust is then conveyed to the
disposal area or to bunkers for sale.
vii)Now after passing through ESP few gases are discharged up to chimney
MAIN PARTS OF GENERATOR
(A) STATOR
1.STATOR FRAME
The stator frame of welded steel frame construction, which gives sufficient & necessary rigidity
to minimize the vibrations and to withstand the thermal gas pressure. form mounting of
generator bearings and radial shaft seals coolers.
21
FIGURE 16:- STATOR ASSEMBLY
2. STATOR CORE
It is built up of special sheet laminations and whose assembly is supported by a special guide
bass. The method of construction ensures that the core is firmly supported at a large number of
points on its periphery.
3. STATOR BARS
Stator bars are manufactured as half bars. Each stator half coil is composed of double glass cover
and bars of copper transposed in straight portion of “Robill Method” so that each strip occupies
every radial portion in the bar. For an equal length along the bar
4. STATOR WINDINGS
Stator windings are double star layers, lap wound, three phase, short pitch type. The top &
bottom are brazed and insulated at either end to form turns. Several such turns form a phase.
Phases are connected to form a double star winding.
22
5. TERMINAL BUSHINGS
Six output leads (3long, 3short) have been brought out of the coming on the exciter side.
External connections are to be made to the three shorter terminals, which are phase terminals.
The large terminals are of neutral & current transformer is inserted.
6. BEARINGS
Generator bearings have electrical seats of consists of steel bodies with removable steel pads.
The bearings are formed for forced lubrication of oil at a pressure of 2-3 ATM/ From the same
pump that supplies oils to the turbine, bearings & governing gears. There is a provision to
ensure & measure the rotor bearing temperature by inserting a resistance thermometer in the oil
pockets.
7. VENTILATION SYSTEM
The machine is designed with ventilation system having 2 atm rated hydrogen pressure. Two
axial fans mounted on either side of the rotor to ensure circulation of hydrogen. The stator is
designed for radial ventilation by stem. The end stator core packets & core clamping & plates are
intensively cooled.
(B) ROTOR
FIGURE 17:- ROTOR
Rotor shaft consists of single piece alloy steel forging of high mechanical and magnetic
properties performance test includes-
1. Tensile test on specimen piece.
2. Surface examination.
23
3. Sulfur prist tests.
4. Magnetic crack detection.
5. Visual examination of bore.
6. Ultrasonic examination.
ROTOR WINDINGS
Rotor winding is of direct coil type and consists of parallel strips of very high conductivity
Silver Bearing Copper, bent on edge to form coil. The coils are placed in impregnated glass,
laminated short shells; using glass strips inter turn insulation and will be brazed at the end to
form continuous winding.
BEARINGS
The bearings are self-aligned & consist of slip steel shells linked with special bearing metal
having very low coefficient of friction. The bore is machined on an elliptical shape so as to
increase the mechanical stability of the rotor
SLIP RINGS
The slip rings are made of forged steel. They are located at either side of Generator Shaft. The
slip ring towards the exciter side is given +ve polarity initially. They have helical grooves and
skewed holes in the body for cooling purpose by air.
BUSH GEAR ASSEMBLY
Generator bushes are made from the various compositions of natural graphite and binding
material. They have a low coefficient of friction and are self lubricating. The brushes are
provided with a double flexible copper or pigtails.
TECHNICAL DATA
Generator (110 MW)
Content Rating
Continuous apparent power 1,37,500 KVA
Active power 7,10,000 KW
Power factor 0.8 (lagging).
Rated voltage 1000 + 5% rated
Current 7,220 A
Critical speed 3000 r. p. m.
24
frequency 50 Hz
Phase connection double star
No. of terminals 6
Main diameter of slip rings 420 mm.
Voltage regulation 39%.
Reactance Informative.
CHAPTER - 5
EXCITATION SYSTEM
25
The electric power Generators requires direct current excited magnets for its field system. The
excitation system must be reliable, stable in operation and must response quickly to excitation
current requirements.
(A) Function of excitation system
The main function of excitation system is to supply required excitation current at rated load
condition of turbo Generator. It should be able to adjust the field current of the Generator, either
by normal controller automatic control so that for all operation & between no load and rated
load. The terminal voltage of the system machine is maintained at its value
(B)Type of Excitation System
There have been many developments in excitation system design. There has been continuing
reach among the design and the use alike from improving the excitation system performance.
The ultimate is to achieve stability, accuracy etc
WATER TREATMENT PLANT
The principle problem in high pressure boiler is to control corrosion and steam quality. Internal
corrosion costs power station crores of rupees in repair without strict control impurities in steam
also form deposit over turbine blades and nozzles. The impurities present in water are as follows
1) Un-dissolved and suspended solid materials.
2) Dissolved slats and minerals.
3) Dissolved gases.
CHAPTER-6
TRANSFORMER
26
Transformer is a static device which is used to change the voltage level keeping the power and
frequency same. In the plant transformer is one of the most important equipment. In the whole
plant, there are about 83 transformer installed at various places to operate the auxiliaries.
Main transformers, which are necessary:
1. To step up the generated voltage.
2. To supply power to the auxiliaries from the generator.
3. To start the plant by taking the supply from the grid.
Are installed in a transformer yard. It is located in between the main plant and the switchyard.
The main transformers installed in the transformer yard are:
1. GENERATOR TRANSFORMER (GT-A)
It steps up the voltage from 16.5 KV to 220 KV. It connects the plant with the 220 KV
switchyard.
2.GENERATOR TRANSFORMER (GT–B)
It steps up the voltage from 16.5 KV to 400 KV. It connects the plant with the 400 KV
switchyard.
3.STATION TRANSFORMER (ST)
It is a step down transformer with 50 MVA capacities. It is used to step down 220 KV from the
grid to 6.9 KV.
4.UNIT AUXILIARY TRANSFORMER (UAT)
It is a step down transformer with 20 MVA capacities. It steps down the voltage from 16.5 KV
to 6.9 KV.
5. STATION SERVICE TRANSFORMER (SST)
It is a step down transformer with 2MVA capacity. It is used to step down from 6.6 KV to
0.4333 KV.
6.UNIT SERVICE TRANSFORMER (UST)
27
It is a step down transformer with 2 MVA capacity. It is used to step down from 6.6 kV to
0.4333 KV.
WORKING OF TRANSFORMER
FIGURE 18:- WORKING OF TRANSFORMER
TABLE ABOUT GENERATOR TRANSFORMER
Type of cooling ONAN ONAF OFAF
Rating HV (in MVA)
Rating LV (in MVA)
160
160
240
240
315
315
Line Current HV 219.9 329.9 433.0
Line Current LV 5598.5 8397.8 11022
Temperature rise in oil (°C) 45 45 45
Temperature rise in wdg (°C) 50 50 50
TABLE-GENERATOR TRANSFORMER
No load voltage HV (KV) - 420KV
No Load voltage LV (KV) - 16.5 KV
Connection symbol - Ynd11
Oil - 65300 Liters
There are 5 generator transformers in the plant, one for each unit. The output from the generator
is fed to the generator transformer, which step up the voltage from 16.5 KV to 400 KV and
supplies power to grid.
28
STATION TRANSFORMER
When the unit is to be started, power supplied to the auxiliaries is taken from the station
transformer. The rating of the station transformer is 50 MVA. It takes power from the grid at 220
kV and steps it down to 6.6 kV. At the time of starting all the auxiliaries are supplied from the
station transformer. When the generator is synchronized and starts producing power, about 80%
of the load is shifted on to the unit auxiliary transformer. The load that requires uninterrupted
supply is left connected on the station transformer.
There are 5 S.T’s in the plant, one for each stage.
Type of cooling ONAN ONAF
MVA rating
H.V.
L.V.
40
26
50
31.05
Current (line)
H.V.
L.V.
105
3351
131
4189
Voltage (line)
H.V. L.V.
220 Kv 6.9 Kv
UNIT AUXILIARY TRANSFORMER
Each unit has two unit auxiliary transformers. When the unit starts generating electricity these
transformers are energized and then supplies power to the auxiliaries. Before starting of the unit,
UAT bus is connected to the station bus. Auxiliaries of one unit take about 20MW of power.
UAT is connected between the generator and the GT.
UNIT STATION TRANSFORMER
It is a step down transformer, which is connected to the station bus. It steps down the voltage
from 6.6 kV to 0.433 kV it is used to supply the low voltage auxiliaries.
UNIT SERVICE TRANSFORMER
It is also a 66-kV/ 415 V transformers which is used to supply the auxiliaries connected to the
unit secondary switchgear bus.
29
SWITCH YARD
220 KV SYSTEM
Two 220 KV bus bars have been provided in switch yard and are inter-connected through a bus
coupler. Each of the two 110 MW generator is connected to this system through a step up of 125
MVA 240/ 11 KV yard generator transformer. There are two step down transformer each
feeding 6.6 KV system ( Station Switchyard ) viz. BS-IS & SB-IB. Each station transformer has
two windings one secondary side and is rated for 50/25/25 mva, 270/7/7.2 kva four feeder take
off from 220 switch yard, two to SKATPURA GSS and other to HEERAPURA , Jaipur GSS.
Each of four feeder are provided with bypass isolators which is connected across line breaker
and breaker isolator. By closing bus coupler between 220 KV buses and putting line feeders
whose breaker required maintenance of any one bus through by pass isolators and all other line
feeders whose breaker is by passed is then transformed to bus coupler breaker. A brief
description of equipments of 220 KV system is as follows.
CIRCUIT BREAKERS
Each of generator transformer, station transformer, line feeder and bus coupler is provided with
minimum oil circuit breaker of BHEL make. It is rated for 245 KW, 2500 A and 13400 MVA
circuit breaker is used to break the circuit either in load condition or in no load condition.
ISOLATOR
All the isolators are provided in 220KV switchyard and are motor operated. Triple pole double
breaker type and power switch yard L&T make these and are rates for 245 KV and 1250 A. The
four isolators are provided with earth switch.
CURRENT TRANSFORMER
All the 220 KV current transformers are provided for measuring and protection. They are BHEL
make, single phase, oil filled nitrogen sealed outdoor type. All the E.T.S. are multi-cored with
each core having specification upon duty it is to perform. Feeder circuit have 5 cores.
1) Bus bar protection core I 1250/250/IA.
30
2) Distance protection core II 600-300/IA.
3) O/C and E/F protection core 600-300 /IA.
4) For metering and measuring 600-300/ IA.
POTENTIAL TRANSFORMER
Each of 220 KV buses is provided with three P.T.’S are core for each phase of BHEL make.
There are single phase, oil filled outdoor. N2 sealed, elicitor magnetic type P.T. has two
secondary windings on secondary side and selected for 220/53 KV, 10/53 KV.
LIGHTENING ARRESTOR
For protection against lightening each of line feeders, generator transformer, station transformer
has been provided with three L.A. (one for each phase). It has larger value of capacitance and
will change up to line voltage. If we have to do some work on line, first earth line through
earthing isolator for discharging the line capacitance and then work.
220 KV Current Transformer
Manufacturer. BHEL, Trichy.
Type Outdoor, Oil filled.
Rated Voltage. 220 KV
Nominal 220 KV
Max. 245 KV.
Rated Frequency. 50 Hz
No. of Phase. 1-Ø
Class of Insulation A.
Rated Primary Voltage 2220/ 53 V.
Secondary Voltage Wdg.1 110/53 V
Secondary Voltage Wdg.2 110/53 V
CHAPTER -7
PROTECTION
1. Field Protection.
2. Pole Slipping.
3. Plane Overload Protection.
4. Inter-turn Fault
5. Negative Phase Sequence Protection.
6. Reverse Power Protection.
31
7. Forward Power Protection.
8. Under Frequency & Over Frequency Protection.
9. Generator Voltage Protection.
10. Rotor Earth Fault Protection.
General Protection
It is most important electrical equipment of many generating station. Tripping of even a
generating unit may cause overloading of associated machines and even to system un-stability .
The basis function of protection applied to generator is to reduce voltage to minimum by rapid
discrimination clearance of faults. Unlike other apparatus the opening of C.B. to isolate faulty
generator is not sufficient to prevent future damage.
CONCLUSION
The first phase of practical training has proved to be quiet fruitful. It provided an opportunity for
encounter with such huge machines like wagon tippler .110 MW, 210 MW & 195 MW turbines
and generators.
The architecture of the power plant the way various units are linked and the way
working of whole plant is controlled make the student realize that engineering is not just learning
the structured description and working of various machines, but the greater part is of planning
proper management.
32
It also provides an opportunities to lean low technology used at proper place and time
can cave a lot of labour e.g. wagon Tripler (CHP).But there are few factors that require special
mention. Training is not carried out into its tree sprit. It is recommended that there should be
some project specially meant for students where presence of authorities should be ensured.
There should be strict monitoring of the performance of students and system of grading be
improved on the basis of work done.
However training has proved to be quite fruitful. It has allowed an opportunity to get an
exposure of the practical implementation to theoretical fundamentals.
33

More Related Content

What's hot

kota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptkota Super Thermal Power Station training ppt
kota Super Thermal Power Station training ppt
Er. Aman Agrawal
 
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Shubham Thakur
 
ntpc unchahar
ntpc unchaharntpc unchahar
ntpc unchahar
Aditya Narain
 
Power electronic converter in wind turbine
Power electronic converter in wind turbinePower electronic converter in wind turbine
Power electronic converter in wind turbine
SonuKumarBairwa
 
Thermal Power plant visit Report by Amit Hinge
Thermal Power plant visit Report by Amit HingeThermal Power plant visit Report by Amit Hinge
Thermal Power plant visit Report by Amit Hinge
amit307
 
Kstps ppt
Kstps pptKstps ppt
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
Prakash Jarotia
 
Power system stability
Power system stabilityPower system stability
Power system stability
Balaram Das
 
An Overview of Thermal Power Plant
An Overview of Thermal Power PlantAn Overview of Thermal Power Plant
An Overview of Thermal Power Plant
Venkata Satya Naveen KSS
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
Vinod Srivastava
 
PPT ON POWER SYSTEM STABILITY
PPT ON POWER SYSTEM STABILITYPPT ON POWER SYSTEM STABILITY
PPT ON POWER SYSTEM STABILITY
MAHESH CHAND JATAV
 
Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)
Srikanta Sinha
 
Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipat
pratikguptateddy
 
Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)
sometech
 
kota super thermal Power station training report
kota super thermal Power station training reportkota super thermal Power station training report
kota super thermal Power station training report
Er. Aman Agrawal
 
A Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power StationA Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power Station
LekhraJ Meena
 
Thermal power plant ppt
Thermal power plant pptThermal power plant ppt
Thermal power plant ppt
ayushi kesarvani
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
Ashvani Shukla
 
Demand side management: Demand response
Demand side management: Demand response Demand side management: Demand response
Demand side management: Demand response
Siksha 'O' Anusandhan (Deemed to be University )
 
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORTTHERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
Prasant Kumar
 

What's hot (20)

kota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptkota Super Thermal Power Station training ppt
kota Super Thermal Power Station training ppt
 
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
 
ntpc unchahar
ntpc unchaharntpc unchahar
ntpc unchahar
 
Power electronic converter in wind turbine
Power electronic converter in wind turbinePower electronic converter in wind turbine
Power electronic converter in wind turbine
 
Thermal Power plant visit Report by Amit Hinge
Thermal Power plant visit Report by Amit HingeThermal Power plant visit Report by Amit Hinge
Thermal Power plant visit Report by Amit Hinge
 
Kstps ppt
Kstps pptKstps ppt
Kstps ppt
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
 
Power system stability
Power system stabilityPower system stability
Power system stability
 
An Overview of Thermal Power Plant
An Overview of Thermal Power PlantAn Overview of Thermal Power Plant
An Overview of Thermal Power Plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
PPT ON POWER SYSTEM STABILITY
PPT ON POWER SYSTEM STABILITYPPT ON POWER SYSTEM STABILITY
PPT ON POWER SYSTEM STABILITY
 
Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)
 
Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipat
 
Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)
 
kota super thermal Power station training report
kota super thermal Power station training reportkota super thermal Power station training report
kota super thermal Power station training report
 
A Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power StationA Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power Station
 
Thermal power plant ppt
Thermal power plant pptThermal power plant ppt
Thermal power plant ppt
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Demand side management: Demand response
Demand side management: Demand response Demand side management: Demand response
Demand side management: Demand response
 
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORTTHERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
 

Viewers also liked

KTPS
KTPSKTPS
Ktps ppt
Ktps pptKtps ppt
Ktps ppt
Nazima Naaz
 
Ktps presentation
Ktps presentationKtps presentation
Ktps presentation
HITESH Kumawat
 
Best ppt on Presentation on Coal handling plant
Best ppt on Presentation on Coal handling plantBest ppt on Presentation on Coal handling plant
Best ppt on Presentation on Coal handling plant
Ronak Thakare
 
Power plant
Power plantPower plant
Power plant
PREJITH AYLARA
 
kstps summer training 36 slides
 kstps summer training 36 slides kstps summer training 36 slides
kstps summer training 36 slides
Danveer Singh
 
Thermal Power Plant - Manual
Thermal Power Plant - ManualThermal Power Plant - Manual
Thermal Power Plant - Manual
Sheel Shah
 
report on thermal power plant
report on thermal power plantreport on thermal power plant
report on thermal power plant
sagar20jain
 
Coal Handling Plant ( CHP )
Coal Handling Plant ( CHP )Coal Handling Plant ( CHP )
Coal Handling Plant ( CHP )
SHRIKANT KHATING
 
Power line carrier communication
Power  line  carrier  communicationPower  line  carrier  communication
Power line carrier communication
Rahul Mehta
 

Viewers also liked (10)

KTPS
KTPSKTPS
KTPS
 
Ktps ppt
Ktps pptKtps ppt
Ktps ppt
 
Ktps presentation
Ktps presentationKtps presentation
Ktps presentation
 
Best ppt on Presentation on Coal handling plant
Best ppt on Presentation on Coal handling plantBest ppt on Presentation on Coal handling plant
Best ppt on Presentation on Coal handling plant
 
Power plant
Power plantPower plant
Power plant
 
kstps summer training 36 slides
 kstps summer training 36 slides kstps summer training 36 slides
kstps summer training 36 slides
 
Thermal Power Plant - Manual
Thermal Power Plant - ManualThermal Power Plant - Manual
Thermal Power Plant - Manual
 
report on thermal power plant
report on thermal power plantreport on thermal power plant
report on thermal power plant
 
Coal Handling Plant ( CHP )
Coal Handling Plant ( CHP )Coal Handling Plant ( CHP )
Coal Handling Plant ( CHP )
 
Power line carrier communication
Power  line  carrier  communicationPower  line  carrier  communication
Power line carrier communication
 

Similar to C ktps training-report

Kota super thermal power plant training report
Kota super thermal power plant training reportKota super thermal power plant training report
Kota super thermal power plant training report
Avinash Kumawat
 
Kota Super Thermal Power Station Training report
Kota Super Thermal Power Station Training reportKota Super Thermal Power Station Training report
Kota Super Thermal Power Station Training report
Deepak Solanki
 
Introduction
IntroductionIntroduction
Introduction
mittal434
 
Kota super thermal power station
Kota super thermal power stationKota super thermal power station
Kota super thermal power station
Ashish Agarwal
 
MEJIA THERMAL POWER STATION VT REPORT
MEJIA THERMAL POWER STATION VT REPORTMEJIA THERMAL POWER STATION VT REPORT
MEJIA THERMAL POWER STATION VT REPORT
Abhinaw Rai
 
(Keshav) report file on kali sindh thermal power project, jhalawar
(Keshav) report file on kali sindh thermal power project, jhalawar(Keshav) report file on kali sindh thermal power project, jhalawar
(Keshav) report file on kali sindh thermal power project, jhalawar
Keshav Meena
 
vocational training at DVC andal
 vocational training at DVC andal vocational training at DVC andal
vocational training at DVC andal
ANIL kumar
 
Project Report on “WORKING MODEL OF POWER GRID/SMART GRID
Project Report on “WORKING MODEL OF POWER GRID/SMART GRIDProject Report on “WORKING MODEL OF POWER GRID/SMART GRID
Project Report on “WORKING MODEL OF POWER GRID/SMART GRID
Prasant Kumar
 
Pm ppt
Pm pptPm ppt
Cseb (chhattisgarh state electricity board) korba east vocational training pr...
Cseb (chhattisgarh state electricity board) korba east vocational training pr...Cseb (chhattisgarh state electricity board) korba east vocational training pr...
Cseb (chhattisgarh state electricity board) korba east vocational training pr...
haxxo24
 
Lakvijaya_Presentation1.pptx
Lakvijaya_Presentation1.pptxLakvijaya_Presentation1.pptx
Lakvijaya_Presentation1.pptx
BhathiyaRanawaka
 
Presentation on Kota super Thermal Power Station
Presentation on Kota super Thermal Power StationPresentation on Kota super Thermal Power Station
Presentation on Kota super Thermal Power Station
pukhraj palariya
 
Ppt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distributionPpt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distribution
SuvamSahu2
 
Attachment.doc
Attachment.docAttachment.doc
Attachment.doc
CHANDAN JAISWAL
 
Kota super thermal power plant seminar
Kota super thermal power plant seminarKota super thermal power plant seminar
Kota super thermal power plant seminar
Century Rayon
 
Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT
Abhijeet Thakur
 
project
projectproject
Kota super thermal power plant
Kota super thermal power plantKota super thermal power plant
Kota super thermal power plant
R G Sanjay Prakash
 
Internship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plantInternship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plant
Abhishek Kumar
 
Thermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E JaipurThermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E Jaipur
Chandra veer singh
 

Similar to C ktps training-report (20)

Kota super thermal power plant training report
Kota super thermal power plant training reportKota super thermal power plant training report
Kota super thermal power plant training report
 
Kota Super Thermal Power Station Training report
Kota Super Thermal Power Station Training reportKota Super Thermal Power Station Training report
Kota Super Thermal Power Station Training report
 
Introduction
IntroductionIntroduction
Introduction
 
Kota super thermal power station
Kota super thermal power stationKota super thermal power station
Kota super thermal power station
 
MEJIA THERMAL POWER STATION VT REPORT
MEJIA THERMAL POWER STATION VT REPORTMEJIA THERMAL POWER STATION VT REPORT
MEJIA THERMAL POWER STATION VT REPORT
 
(Keshav) report file on kali sindh thermal power project, jhalawar
(Keshav) report file on kali sindh thermal power project, jhalawar(Keshav) report file on kali sindh thermal power project, jhalawar
(Keshav) report file on kali sindh thermal power project, jhalawar
 
vocational training at DVC andal
 vocational training at DVC andal vocational training at DVC andal
vocational training at DVC andal
 
Project Report on “WORKING MODEL OF POWER GRID/SMART GRID
Project Report on “WORKING MODEL OF POWER GRID/SMART GRIDProject Report on “WORKING MODEL OF POWER GRID/SMART GRID
Project Report on “WORKING MODEL OF POWER GRID/SMART GRID
 
Pm ppt
Pm pptPm ppt
Pm ppt
 
Cseb (chhattisgarh state electricity board) korba east vocational training pr...
Cseb (chhattisgarh state electricity board) korba east vocational training pr...Cseb (chhattisgarh state electricity board) korba east vocational training pr...
Cseb (chhattisgarh state electricity board) korba east vocational training pr...
 
Lakvijaya_Presentation1.pptx
Lakvijaya_Presentation1.pptxLakvijaya_Presentation1.pptx
Lakvijaya_Presentation1.pptx
 
Presentation on Kota super Thermal Power Station
Presentation on Kota super Thermal Power StationPresentation on Kota super Thermal Power Station
Presentation on Kota super Thermal Power Station
 
Ppt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distributionPpt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distribution
 
Attachment.doc
Attachment.docAttachment.doc
Attachment.doc
 
Kota super thermal power plant seminar
Kota super thermal power plant seminarKota super thermal power plant seminar
Kota super thermal power plant seminar
 
Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT
 
project
projectproject
project
 
Kota super thermal power plant
Kota super thermal power plantKota super thermal power plant
Kota super thermal power plant
 
Internship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plantInternship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plant
 
Thermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E JaipurThermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E Jaipur
 

Recently uploaded

Kirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper PresentationKirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
Cover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SUCover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SU
msthrill
 
Registered-Establishment-List-in-Uttarakhand-pdf.pdf
Registered-Establishment-List-in-Uttarakhand-pdf.pdfRegistered-Establishment-List-in-Uttarakhand-pdf.pdf
Registered-Establishment-List-in-Uttarakhand-pdf.pdf
dazzjoker
 
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
dpbossdpboss69
 
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
taqyea
 
AI Transformation Playbook: Thinking AI-First for Your Business
AI Transformation Playbook: Thinking AI-First for Your BusinessAI Transformation Playbook: Thinking AI-First for Your Business
AI Transformation Playbook: Thinking AI-First for Your Business
Arijit Dutta
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
list of states and organizations .pdf
list of  states  and  organizations .pdflist of  states  and  organizations .pdf
list of states and organizations .pdf
Rbc Rbcua
 
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
ISONIKELtd
 
CULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for dukeCULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for duke
ZevinAttisha
 
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
valvereliz227
 
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
irhcs
 
Discover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling ServiceDiscover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling Service
obriengroupinc04
 
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian MatkaDpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian Matka
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
IPLTech Electric
 
GKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt PresentationGKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt Presentation
GraceKohler1
 
DearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUniDearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUni
katiejasper96
 
Kalyan chart 6366249026 India satta Matta Matka 143 jodi fix
Kalyan chart 6366249026 India satta Matta Matka 143 jodi fixKalyan chart 6366249026 India satta Matta Matka 143 jodi fix
Kalyan chart 6366249026 India satta Matta Matka 143 jodi fix
satta Matta matka 143 Kalyan chart jodi 6366249026
 
High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15
advik4387
 

Recently uploaded (20)

Kirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper PresentationKirill Klip GEM Royalty TNR Gold Copper Presentation
Kirill Klip GEM Royalty TNR Gold Copper Presentation
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
Cover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SUCover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SU
 
Registered-Establishment-List-in-Uttarakhand-pdf.pdf
Registered-Establishment-List-in-Uttarakhand-pdf.pdfRegistered-Establishment-List-in-Uttarakhand-pdf.pdf
Registered-Establishment-List-in-Uttarakhand-pdf.pdf
 
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
 
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
 
AI Transformation Playbook: Thinking AI-First for Your Business
AI Transformation Playbook: Thinking AI-First for Your BusinessAI Transformation Playbook: Thinking AI-First for Your Business
AI Transformation Playbook: Thinking AI-First for Your Business
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
list of states and organizations .pdf
list of  states  and  organizations .pdflist of  states  and  organizations .pdf
list of states and organizations .pdf
 
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
 
CULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for dukeCULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for duke
 
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
 
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
1Q24_HYUNDAI CAPITAL SERVICES INC. AND SUBSIDIARIES
 
Discover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling ServiceDiscover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling Service
 
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian MatkaDpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian Matka
 
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
 
GKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt PresentationGKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt Presentation
 
DearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUniDearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUni
 
Kalyan chart 6366249026 India satta Matta Matka 143 jodi fix
Kalyan chart 6366249026 India satta Matta Matka 143 jodi fixKalyan chart 6366249026 India satta Matta Matka 143 jodi fix
Kalyan chart 6366249026 India satta Matta Matka 143 jodi fix
 
High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15
 

C ktps training-report

  • 1. CHAPTER -1 INTRODUCTION For the power generation with 2x110 MW, 3x210 MW and 2x195 MW of K.S.T.P.S. authorities are required to be operative to active full operation. The auxiliaries are basically operation either on L.T. System i.e. 415 V 3-Ø power supply is made available to the system after providing the station transformer of 3x50 MVA capacity with voltage 220 KV/ 7.2/7.2 KV & different service transformers of capacity 1.0 MVA, 1.5 MVA, 2.0 MVA, which are located near the load centre as the transformer having the voltage of 6.6 KV /415 V. The 6.6 KV power is distributed through 6.6 KV interconnected Bus System for all the five units with a control through DC The 415 V power supply is done through a L.T. SWGR (Switchgear) which are located nearby the distribution transformer as well as the load centers. The all incomers, which are breaker controlled , are having the control the L.T. SWGR are having the control system on 110/ 220 V AC. The 6.6 KV power supply which are either MOCB(Minimum Oil Circuit Breaker) of JYOTIMAKE or Air Circuit Breakers. The 6.6 KV power supply to various draining equipment’s i.e. more is made through breakers which are either MOCB of Jyoti make air circuit breaker which are either of voltage makers as well as SF 6 of NGEF make. The LT supply is also controlled through air break circuit breaker which are either L&T make or English Electric Company of India. The various H.T. motors are switched on started through on direct ON line (DOL) in order to inverse the availability of equipment at full efficiency without time gap. Further, the 6.6 KV system which is normally in delta configuration and terms as an unearthed system so also to keep the running motor complete in operating condition in case of anyone .phase of motor winding is earthed due to any one reason. Earthling is detected by an protection system with alarm facility to take remedial measures immediately and at the same time to maintain the generation level in the same condition, prior to occurring the earth fault the single phase earth fault is detected in due course till the motor is not earthed to other or another phase. “PUBLIC ADDRESS SYSTEM” is available through in area of each unit which helps in fast communication for prompt remedial measure. 1
  • 2. K.S.T.P.S. IS DESISIGNED IN FOLLOWING STAGES  STAGE I - 2x110 MW  STAGE II - 2X210 MW  STAGE III - 1X210 MW  STAGE IV - 1X195 MW  STAGE V - 1X195MW LOCATION The Kota Thermal Power Station is ideally on the left bank of Chambal River at Up Stream of Kota Barrage. The large expanse of water reached by the barrage provides an efficient direct circulation of cooling system for the power station. The 220 KV GSS is within ½ kms. from the power station COAL Coal India limited owns and operates all the major coal fields in India through its coal producing subsidiary companies viz. Northern Coal Fields Limited, South Eastern Coal Fields Limited, Coal India limited is supply coal from its coal mines of coal producing subsidiaries SECL & NCL to Kota Thermal Power Station through railway wagons. The average distances of SECL, NCL are 800, 950 Kms. respectively. WATER The source of water for power station is reservoir formed by Kota Barrage on the Chambal River. In case of large capacity plants huge quantities of coal and water is required. The cost of transporting coal and water is particularly high. Therefore, as far as possible, the plant must be located near the pit rather than at load centre for load above 200 MW and 375 MW. The transportation of electrical energy is more economical as compared to the transportation of coal. DESIGN FEATURES The satisfactory design consists of the flowing steps. • Estimation of cost. • Selection of site. • Capacity of Power Station. • Selection of Boiler & Turbine. 2
  • 3. • Selection of Condensing Unit. • Selection of Electrical Generator. • Selection of Cooling System. • Design of Control and instrumentation system. 3
  • 4. CHAPTER -2 GENERAL LAYOUT & BASIC IDEA A control system of station basically works on Rankin Cycle. Steam is produced in Boiler is exported in prime mover and is condensed in condenser to be fed into the boiler again. In practice of good number of modifications are affected so as to have heat economy and to increase the thermal efficiency of plant. FIGURE 1:- PLANT OVERVIEW The Kota Thermal Power Station is divided into four main circuits  Fuel and Ash Circuit.  Air and Gas Circuit.  Feed water and Steam Circuit.  Cooling Water Circuit. 4
  • 5. Fuel & Ash Circuit Fuel from the storage is fed to the boiler through fuel handling device. The fuel used in KSTPS is coal, which on combustion in the boiler produced the ash. The quantity of ash produced is approximately 35-40% of coal used. This ash is collected at the back of the boiler and removed to ash storage tank through ash disposal equipment. Air and Gas Circuit Air from the atmosphere is supplied to the combustion chamber of Boiler through the action of forced draft fan and induced draft fan. The flue gas gases are first pass around the boiler tubes and super heated tubes in the furnace, next through dust collector (ESP) & then economizer. Finally, they are exhausted to the atmosphere through fans. Feed Water and Steam Circuit The condensate leaving the condenser is first heated in low pressure (LP) heaters through extracted steam from the lower pressure extraction of the turbine. Then its goes to dearator where extra air and non-condensable gases are removed from the hot water to avoid pitting / oxidation. From deaerator it goes to boiler feed pump which increases the pressure of the water. From the BFP it passes through the high pressure heaters. Cooling Water Circuit A large quantity of cooling water is required to condense the steam in condenser and marinating low pressure in it. The water is drawn from reservoir and after use it is drained into the river. COAL HANDLING PLANT 5
  • 6. FIGURE 2:- COAL HANDLING PLANT INTRODUCTION It can be called the heart of thermal power plant because it provided the fuel for combustion in boiler. The coal is brought to the KSTPS through rails there are fourteen tracks in all for transportation of coal through rails. The main coal sources for KSTPS are SECL (South Eastern Coalfields Limited), NCL (Northern Coalfield Limited). Everyday 6 to 7 trains of coal are unloaded at KSTPS. Each train consists of 58 wagons and each wagons consists of 50 tones of coal. The approximate per day consumption at KSTPS is about 18000 metric tones. It costs approximate 4.5 crores of rupees per day including transportation expenses. The coal is firstly unloaded from wagon by wagon triplers then crushed by crushers and magnetic pulley and pulverized to be transformed to the boiler. The whole transportation of coal is through conveyor belt operated by 3-Ø Induction motor. The coal handling plant can broadly be divided into three sections :- 1) Wagon Unloading System. 2) Crushing System. 3) Conveying System CONVEYING SYSTEM Stacker Reclaimer The stacker re-claimer unit can stack the material on to the pipe or reclaim the stack filed material and fed on to the main line conveyor. While stacking material is being fed from the main line conveyor via tripler unit and vibrating feeder on the intermediate conveyor which feds the boom conveyor of the stacker cum reclaimer. During reclaiming the material dis discharged on to the boom conveyor by the bucket fitted to the bucket wheel body and boom conveyor feeds the material on the main line conveyor running in the reverse direction. FEEDERS This structure is erected to serve the purpose of storage. Underground machines are installed known as plow feeder machines. These machines collect the coal from conveyor and drop it to the other from one conveyor with the help of jaws and this coal is taken to huge erected structure from where the coal falls to the ground. Jali chutes are used to prevent dust. 6
  • 7. FIGURE 3:- ASH HANDLING PLANT This plant can be divided into 3 sub plants as follows:- 1) Fuel and Ash Plant. 2) Air and Gas Plant. 3) Ash Disposal and & Dust Collection Plant. Fuel and ash plant Coal is used as combustion material in KTPS, In order to get an efficient utilization of coal mills. The Pulverization also increases the overall efficiency and flexibility of boilers. However for light up and with stand static load, oil burners are also used. Ash produced as the result of combustion of coal is connected and removed by ash handling plant. Ash Handling Plant at KTPS consists of specially designed bottom ash and fly ash in electro static precipitator economizer and air pre-heaters hoppers. 7
  • 8. Air & Gas Plant Air from atmosphere is supplied to combustion chamber of boiler through the action of forced draft fan. In KTPS there are two FD fans and three ID fans available for draft system per unit. The air before being supplied to the boiler passes through pre-heater where the flue gases heat it. The pre heating of primary air causes improved and intensified combustion of coal. Ash Disposal & Dust Collection Plant KSTPS has dry bottom furnace. Ash Handling Plant consists of especially designed bottom and fly ash system for two path boiler. The system for both units is identical and following description is applied to both the units the water compounded bottom ash hopper receives the bottom ash from the furnace from where it is stores and discharged through the clinker grinder. Two slurry pumps are provided which is common to both units & used to make slurry and further transportation to ash dyke through pipe line. ELECTRO-STATIC PRECIPITATOR FIGURE 4:- ELECTRO-STATIC PRECIPITATOR 8
  • 9. Scope & Principle of Operation For general mankind, today an Eco friendly industry is must. As far as air pollution is concerned now a days various flue gases filter are there in service. The choice depends on the size of suspended particle matter. These filters are E.S.P. Fabric filter high efficiency cyclone separations and sitelling room. Fop fly ash , where the particle size vary from 0.75 microns to 100 micron use gradually use E.S.P. to purify the flue gases due to its higher efficiency & low running cost etc. In an ESP the dust lidder gas is passed through an intense electric field, which causes ionization of the gases & they changed into ion while traveling towards opposite charged electrode get deposited as particles and thus dust is electric deposited an electrode creating the field. It is continuous process. CONTROLLER Now a day micro-processor based intelligent controllers are used to regulate the power fed to the HVR. The controls the firing / ignition angle of the thyristor connected in parallel mode. Input out waves of the controller and HVR are also shown above, which clearly indicates that average power fed to ESP field can be controlled by variation of the firing angle of thyristor. The output of controller with respect to time is also controlled by microprocessor, so that ESP operation is smooth and efficient. HIGH VOLTAGE RECTIFIER TRANSFORMER HVR receives the regulated supply from controller. It steps up to high voltage rectifier. The D.C. supply is fed to E.S.P. field through its negative bushing. The positive bushing so connected to earth through small resistance which forms a current feedback circuit. A very high resistance column is also connected with negative bushing. It forms the voltage feedback circuit. These two feedback are used in the controller for indication and control purpose. 9
  • 10. CHAPTER-3 BOILER A boiler (or steam generator) is a closed vessel in which water, under pressure is converted into steam. It is one of the major components of a thermal power plant. A boiler is always designed to absorb maximum amount of heat released in process of combustion. This is transferred to the boiler by all the three modes of heat transfer i.e. conduction, convection and radiation. Boilers are classified as Fire tube boiler FIGURE 5:- FIRE TUBE BOILER In this type the products of combustion pass through the tubes which are surrounded by water. These are economical for low pressure only. Water tube boiler FIGURE 6:- WATER TUBE BOILER 10
  • 11. In this type of boiler water flows inside the tubes and hot gases flow outside the tubes. These tubes are interconnected to common water channels and to steam outlet. • The water tube boilers have many advantages over the fire tube boilers • High evaporation capacity due to availability of large heating surface. • Better heat transfer to the mass of water. • Better efficiency of plant owing to rapid and uniform circulation of water in tubes. • Better overall control. • Easy removal of scale from inside the tubes. Furnace Furnace is primary part of the boiler where the chemical energy available in the fuel is converted into thermal energy by combustion. Furnace is designed for efficient and complete combustion. Major factors that assist for efficient combustion are the temperature inside the furnace and turbulance, which causes rapid mixing of fuel and air. In modern boilers, water- cooled furnaces are used. PULVERISED FUEL SYSTEM The boiler fuel firing system is tangentially firing system in which the fuel is introduced from wind nozzle located in the four corners inside the boiler. The crushed coal from the coal crusher is transferred into the unit coalbunkers where the coal is stored for feeding into pulverizing mill through rotary feeder. The rotary feeders feed the coal to pulverize mill at a definite rate. Then coal burners are employed to fire the pulverized coal along with primary air into furnace. These burners are placed in the corners of the furnace and they send horizontal streams of air and fuel tangent to an imaginary circle in the center of the furnace. Fuel Oil System The functional requirement of the fuel burning system is to supply a controllable and uninterrupted flammable furnace input of fuel and air and to continuously ignite and burn the 11
  • 12. fuel as rapidly as it is introduced into the furnace. This system provides efficient conversion of chemical energy of fuel into heat energy. The fuel burning system should function such that fuel and air input is ignited continuously and immediately upon its entry into furnace. BOILER DRUM The drum is a pressure vessel. Its function is to separate water and steam from mixture (of steam & water) generated in the furnace walls. It provides water storage for preventing the saturation of tubes. It also houses the equipment needed for purification of steam. The steam purification primarily depends on the extent of moisture removal, since solids in steam are carried by the moisture associated with it. The drum internals reduce the dissolved solids content of the steam to below the acceptable limit. drum is made up of two halves of carbon steel plates having thickness of 133 mm. 7:- STEAM DRUM INTERNALS Boiler drum is located at a height of 53m from ground. The drum is provided with manholes and manhole covers. Manhole is used for facilitating the maintenance person to go inside the drum for maintenance. 12
  • 13. Main parts of boiler drum are • Feed pipe • Riser tube • Down comer • Baffle plate • Chemical dosing pipe • Turbo separation • Screen dryer • Drum level gauge Draft System The combustion process in a furnace can take place only when it receives a steady flow of air and has the combustion gases continuously removed. Theoretically balanced draft means keeping furnace pressure equal to atmospheric pressure, but in practice the furnace is kept slightly below atmospheric pressure. It ensures that there is no egress of air or hot gas and ash into boiler house. Draught Fans A fan can be defined as volumetric machine which like pumps moves quantities of air or gas from one place to another. In doing this it overcomes resistance to flow by supplying the fluid with the energy necessary for contained motion. The following fans are used in boiler house. Primary air fan (P.A. fan) or Exhauster fan Pulverized coal is directly fed from coal mills to the burners at the four corners of the furnace through coal pipes with the help of heated air coming from PA fan. Secondly, this fan also dries the coal. Usually sized for 1500 RPM due to high pressure. Forced draught fan (F.D. fan) 13
  • 14. The combustion process in the furnace can take place only when it receives a steady flow of air. This air is supplied by FD fan. Thus FD fan takes air from atmosphere at ambient temperature & so provides additional draught. Its speed varies from 600-1500 RPM. Specification of Force Draft fan: 3φ,6.6KV,700KW Rated.current-74A RPM-1500 Discharge- 408 T/Hr FIGURE 8:- FD FAN Induced draught fan (I.D. fan) The flue gases coming out of the boiler are passed to the ESP & then dust free gases are discharged up by the chimney to the atmosphere through the ID fan. FIGURE 9:-ID FAN Specification of ID fan Rated.current-192.1A Discharge- 720 T/Hr 3φ,6.6KV,1750KW 14
  • 15. Igniter air fan It is used to provide necessary combustion air to igniter. Two fans are usually provided. One will run and 2nd will remain as stand by. A control damper is provided on the discharge which modulates to maintain a constant differential pressure across igniter when any igniter is in service. Typical speed is 1460 RPM. Scanner Air Fan Used to provide necessary cooling air to the flame scanners. Two air fans are usually provided. One will run and other will remain as stand by. When F.D. fans trip the scanner air fan will draw air from atmosphere through emergency damper. Typical speed 3000 RPM. Economizer FIGURE 10:- ECONOMIZER 15
  • 16. FIGURE 11:- ECONOMIZER FIGURE 12:- AIR PRE HEATER The flue gases coming out of the boiler carry lot of heat. An economiser extracts a part of this heat from the flue gases and uses it for heating the feed water before it enters into the steam drum. The use of economiser results in saving fuel consumption and higher boiler efficiency but needs extra investment. In an economizer, a large number of small diameter thin walled tubes are placed between two headers. Feed water enters the tubes through the other. The flue gases flow outside the tubes. Air preheaters FIGURE 13:- AIR PRE HEATERS Air preheaters are employed to recover the heat from the flue gases leaving the economiser and are used to heat the incoming air for combustion. This raises the temperature of the furnace gases, improves combustion rates and efficiency and lowers the stack (chimney) temperature, thus improving the overall efficiency of the boiler. Cooling of flue gases by 20% raises the plant efficiency by 1%. 16
  • 17. Super heater FIGURE 14:- SUPER HEATER Superheated steam is that steam, which contains more heat than the saturated steam at the same pressure i.e. it, has been heated above the temperature corresponding to its pressure. This additional heat provides more energy to the turbine and thus the electrical power output is more. Re-heater Re-heaters are provided to raise the temperature of the steam from which part of energy has already been extracted by HP turbine. This is done so that the steam remains dry as far as possible through the last stage of the turbine. A re-heater can also be convection, radiation or combination of both. Circulation System In natural circulation system, water delivered to steam generator from header, which are at a temperature well below the saturation value corresponding to that pressure. After header, it is delivered to economizer, which heated to above the saturation temperature. From economizer the water enters the drum and thus joins the circulation system through down covering water wall tubes. In water wall tubes a part of the water is converted to steam 17
  • 18. due to boiler and the mixture flows back to the drum. In the drum, the steam is separated out through the steam separators and passed to the super heater. After the super heater when the steam temperature becomes high and pressure upto 150 Kg./cm3 steam is allowed to enter the turbine to convert potential energy to kinetic energy. CHAPTER - 4 STEAM TURBINE INTRODUCTION Turbine is a machine in which a shaft is rotated steadily by impact or reaction of current or stream of working substance (steam, air, water, gases etc) upon blades of a wheel. It converts the potential or kinetic energy of the working substance into mechanical power by virtue of dynamic action of working substance. When the working substance is steam it is called the steam turbine. FIGURE 15 :-STEAM TURBINE PRINCIPAL OF OPERATION OF STEAM TURBINE (1.) Working of the steam turbine depends wholly upon the dynamic action of Steam. The steam is caused to fall in pressure in a passage of nozzle: doe to this fall in pressure a certain amount of heat energy is converted into mechanical kinetic energy and the steam is set moving with a greater velocity. The rapidly moving particles of steam, enter the moving part of the turbine and 18
  • 19. here suffer a change in direction of motion which gives rose to change of momentum and therefore to a force. This constitutes the driving force of the machine. (2.) Blade may be less than that at the inlet side of the blades; the drop in pressure suffered by the steam during its flow through the moving causes a further generation of kinetic energy within the blades and adds to the propelling force which is applied to the turbine rotor. Such a turbine is broadly termed as impulse reaction turbine (3.) The blade or deflector, in which the steam particles changes its directions and hence its momentum changes . The blades are attach to the rotating elements are attached to the stationary part of the turbine which is usually termed the stator, casing or cylinder. Although the fundamental principles on which all steam turbine operate the same, yet the methods where by these principles carried into effect very end as a result, certain types of turbine have come into existence. A. Simple impulse steam turbine. B.The pressure compounded impulse turbine. C.Simple velocity compounded impulse turbine. D.Pressure-velocity compounded turbine. E.Pure reaction turbine. F.Impulse reaction turbine. TECHNICAL DATA OF TURBINES The main technical data of 110 MW turbine is given below:- Rated output 110 MW Economic output 95 MW Rated speed 3000 rpm Direction of rotation viewing from the Front bearing pedestal. Clockwise Rated steam pressure before stop valve. 130 ata Maximum steam pressure before stop valve. 146 ata Rated temperature of steam before the Stop valve 535o C Maximum temperature of steam before the Stop valve 545o C Rated pressure of steam MP Casting 31.6 ata Rated pressure of steam before MP Casting 35 ata . 19
  • 20. MP Casing Rated Temp. of steam before MP Casing 535o C. Maximum Temp. of steam before MP Casting 545o C Informative heat flow at the economic output 2135 K cal/Kwh Informative heat rate at the rated output 2152.5 K Cal/Kwh. HP Cylinder 2 row carts wheel + 8 moving wheels MP Cylinder 12 moving wheels. LP cylinder 4 moving wheels of Double row design. Quantity of oil for first filling. 1800 liters. TECHNICAL DATA OF 210 MW TURBINE Rated Output 210 MW. Rated Speed. 3000 rpm. Main steam pressure. 150 Kg./Cm2 Main steam temperature. 535o C Reheat steam temperature. 535o C. Weight of turbine. 475 T approx. Overall length. 16.975 Mtrs. approx. Single flow HP turbine with 25 reaction stages. Double flow IP turbine with 20 reaction stages per flow. Double flow LP turbine with 8 reaction stages per flow. 2 main stop & control valves. 2 steam check valve in CRH. 2 reheat stop & control valves,. 2 bypass stop & control valve. turbines installed for unit 1 & 2 and 210 MW turbines installed for units 3, 4 & 5 & two 195 MW turbine installed for unit 6 & 7. ELECTRICITY GENERATOR 20
  • 21. Thermal power station burns the fuel and use the resultant heat to raise the steam which drives the turbo-generator. The fuel may be “Fossil” (Coal, Oil and Natural Gas) whichever fuel is used the object is same to convert the heat into mechanical energy to electrical energy by rotating a magnet inside the set of winding. In a coal fired thermal power station other raw materials are air and water. The coal is brought to station by train or other means travels from the coal handling system. i) By conveyer belts to coal bunkers from where it is fed to pulverizing mills. ii) Mills grind it fine as face powder. iii) Then this powdered coal mixed with preheated air is blow into boiler by a Fan known as primary air fan (PA fan). iv) When it burns more like a gas as solid in conventional domestic or industrial grate with additional amount of air called secondary air supplied by “Forced Draft Fan”. As the coal has been grinded so resultant ash is also as fine as powder. Some of its fine particles blinds together to form a lump which falls into the ash pit at the bottom of furnace. v) The water quenched ash from the bottom of furnace is carried out boiler to pit for subsequent disposal. vi) Most of ash still in fine particles form is carried out to electrostatic precipitators where it is trapped by electrode charged with high voltage electricity. The dust is then conveyed to the disposal area or to bunkers for sale. vii)Now after passing through ESP few gases are discharged up to chimney MAIN PARTS OF GENERATOR (A) STATOR 1.STATOR FRAME The stator frame of welded steel frame construction, which gives sufficient & necessary rigidity to minimize the vibrations and to withstand the thermal gas pressure. form mounting of generator bearings and radial shaft seals coolers. 21
  • 22. FIGURE 16:- STATOR ASSEMBLY 2. STATOR CORE It is built up of special sheet laminations and whose assembly is supported by a special guide bass. The method of construction ensures that the core is firmly supported at a large number of points on its periphery. 3. STATOR BARS Stator bars are manufactured as half bars. Each stator half coil is composed of double glass cover and bars of copper transposed in straight portion of “Robill Method” so that each strip occupies every radial portion in the bar. For an equal length along the bar 4. STATOR WINDINGS Stator windings are double star layers, lap wound, three phase, short pitch type. The top & bottom are brazed and insulated at either end to form turns. Several such turns form a phase. Phases are connected to form a double star winding. 22
  • 23. 5. TERMINAL BUSHINGS Six output leads (3long, 3short) have been brought out of the coming on the exciter side. External connections are to be made to the three shorter terminals, which are phase terminals. The large terminals are of neutral & current transformer is inserted. 6. BEARINGS Generator bearings have electrical seats of consists of steel bodies with removable steel pads. The bearings are formed for forced lubrication of oil at a pressure of 2-3 ATM/ From the same pump that supplies oils to the turbine, bearings & governing gears. There is a provision to ensure & measure the rotor bearing temperature by inserting a resistance thermometer in the oil pockets. 7. VENTILATION SYSTEM The machine is designed with ventilation system having 2 atm rated hydrogen pressure. Two axial fans mounted on either side of the rotor to ensure circulation of hydrogen. The stator is designed for radial ventilation by stem. The end stator core packets & core clamping & plates are intensively cooled. (B) ROTOR FIGURE 17:- ROTOR Rotor shaft consists of single piece alloy steel forging of high mechanical and magnetic properties performance test includes- 1. Tensile test on specimen piece. 2. Surface examination. 23
  • 24. 3. Sulfur prist tests. 4. Magnetic crack detection. 5. Visual examination of bore. 6. Ultrasonic examination. ROTOR WINDINGS Rotor winding is of direct coil type and consists of parallel strips of very high conductivity Silver Bearing Copper, bent on edge to form coil. The coils are placed in impregnated glass, laminated short shells; using glass strips inter turn insulation and will be brazed at the end to form continuous winding. BEARINGS The bearings are self-aligned & consist of slip steel shells linked with special bearing metal having very low coefficient of friction. The bore is machined on an elliptical shape so as to increase the mechanical stability of the rotor SLIP RINGS The slip rings are made of forged steel. They are located at either side of Generator Shaft. The slip ring towards the exciter side is given +ve polarity initially. They have helical grooves and skewed holes in the body for cooling purpose by air. BUSH GEAR ASSEMBLY Generator bushes are made from the various compositions of natural graphite and binding material. They have a low coefficient of friction and are self lubricating. The brushes are provided with a double flexible copper or pigtails. TECHNICAL DATA Generator (110 MW) Content Rating Continuous apparent power 1,37,500 KVA Active power 7,10,000 KW Power factor 0.8 (lagging). Rated voltage 1000 + 5% rated Current 7,220 A Critical speed 3000 r. p. m. 24
  • 25. frequency 50 Hz Phase connection double star No. of terminals 6 Main diameter of slip rings 420 mm. Voltage regulation 39%. Reactance Informative. CHAPTER - 5 EXCITATION SYSTEM 25
  • 26. The electric power Generators requires direct current excited magnets for its field system. The excitation system must be reliable, stable in operation and must response quickly to excitation current requirements. (A) Function of excitation system The main function of excitation system is to supply required excitation current at rated load condition of turbo Generator. It should be able to adjust the field current of the Generator, either by normal controller automatic control so that for all operation & between no load and rated load. The terminal voltage of the system machine is maintained at its value (B)Type of Excitation System There have been many developments in excitation system design. There has been continuing reach among the design and the use alike from improving the excitation system performance. The ultimate is to achieve stability, accuracy etc WATER TREATMENT PLANT The principle problem in high pressure boiler is to control corrosion and steam quality. Internal corrosion costs power station crores of rupees in repair without strict control impurities in steam also form deposit over turbine blades and nozzles. The impurities present in water are as follows 1) Un-dissolved and suspended solid materials. 2) Dissolved slats and minerals. 3) Dissolved gases. CHAPTER-6 TRANSFORMER 26
  • 27. Transformer is a static device which is used to change the voltage level keeping the power and frequency same. In the plant transformer is one of the most important equipment. In the whole plant, there are about 83 transformer installed at various places to operate the auxiliaries. Main transformers, which are necessary: 1. To step up the generated voltage. 2. To supply power to the auxiliaries from the generator. 3. To start the plant by taking the supply from the grid. Are installed in a transformer yard. It is located in between the main plant and the switchyard. The main transformers installed in the transformer yard are: 1. GENERATOR TRANSFORMER (GT-A) It steps up the voltage from 16.5 KV to 220 KV. It connects the plant with the 220 KV switchyard. 2.GENERATOR TRANSFORMER (GT–B) It steps up the voltage from 16.5 KV to 400 KV. It connects the plant with the 400 KV switchyard. 3.STATION TRANSFORMER (ST) It is a step down transformer with 50 MVA capacities. It is used to step down 220 KV from the grid to 6.9 KV. 4.UNIT AUXILIARY TRANSFORMER (UAT) It is a step down transformer with 20 MVA capacities. It steps down the voltage from 16.5 KV to 6.9 KV. 5. STATION SERVICE TRANSFORMER (SST) It is a step down transformer with 2MVA capacity. It is used to step down from 6.6 KV to 0.4333 KV. 6.UNIT SERVICE TRANSFORMER (UST) 27
  • 28. It is a step down transformer with 2 MVA capacity. It is used to step down from 6.6 kV to 0.4333 KV. WORKING OF TRANSFORMER FIGURE 18:- WORKING OF TRANSFORMER TABLE ABOUT GENERATOR TRANSFORMER Type of cooling ONAN ONAF OFAF Rating HV (in MVA) Rating LV (in MVA) 160 160 240 240 315 315 Line Current HV 219.9 329.9 433.0 Line Current LV 5598.5 8397.8 11022 Temperature rise in oil (°C) 45 45 45 Temperature rise in wdg (°C) 50 50 50 TABLE-GENERATOR TRANSFORMER No load voltage HV (KV) - 420KV No Load voltage LV (KV) - 16.5 KV Connection symbol - Ynd11 Oil - 65300 Liters There are 5 generator transformers in the plant, one for each unit. The output from the generator is fed to the generator transformer, which step up the voltage from 16.5 KV to 400 KV and supplies power to grid. 28
  • 29. STATION TRANSFORMER When the unit is to be started, power supplied to the auxiliaries is taken from the station transformer. The rating of the station transformer is 50 MVA. It takes power from the grid at 220 kV and steps it down to 6.6 kV. At the time of starting all the auxiliaries are supplied from the station transformer. When the generator is synchronized and starts producing power, about 80% of the load is shifted on to the unit auxiliary transformer. The load that requires uninterrupted supply is left connected on the station transformer. There are 5 S.T’s in the plant, one for each stage. Type of cooling ONAN ONAF MVA rating H.V. L.V. 40 26 50 31.05 Current (line) H.V. L.V. 105 3351 131 4189 Voltage (line) H.V. L.V. 220 Kv 6.9 Kv UNIT AUXILIARY TRANSFORMER Each unit has two unit auxiliary transformers. When the unit starts generating electricity these transformers are energized and then supplies power to the auxiliaries. Before starting of the unit, UAT bus is connected to the station bus. Auxiliaries of one unit take about 20MW of power. UAT is connected between the generator and the GT. UNIT STATION TRANSFORMER It is a step down transformer, which is connected to the station bus. It steps down the voltage from 6.6 kV to 0.433 kV it is used to supply the low voltage auxiliaries. UNIT SERVICE TRANSFORMER It is also a 66-kV/ 415 V transformers which is used to supply the auxiliaries connected to the unit secondary switchgear bus. 29
  • 30. SWITCH YARD 220 KV SYSTEM Two 220 KV bus bars have been provided in switch yard and are inter-connected through a bus coupler. Each of the two 110 MW generator is connected to this system through a step up of 125 MVA 240/ 11 KV yard generator transformer. There are two step down transformer each feeding 6.6 KV system ( Station Switchyard ) viz. BS-IS & SB-IB. Each station transformer has two windings one secondary side and is rated for 50/25/25 mva, 270/7/7.2 kva four feeder take off from 220 switch yard, two to SKATPURA GSS and other to HEERAPURA , Jaipur GSS. Each of four feeder are provided with bypass isolators which is connected across line breaker and breaker isolator. By closing bus coupler between 220 KV buses and putting line feeders whose breaker required maintenance of any one bus through by pass isolators and all other line feeders whose breaker is by passed is then transformed to bus coupler breaker. A brief description of equipments of 220 KV system is as follows. CIRCUIT BREAKERS Each of generator transformer, station transformer, line feeder and bus coupler is provided with minimum oil circuit breaker of BHEL make. It is rated for 245 KW, 2500 A and 13400 MVA circuit breaker is used to break the circuit either in load condition or in no load condition. ISOLATOR All the isolators are provided in 220KV switchyard and are motor operated. Triple pole double breaker type and power switch yard L&T make these and are rates for 245 KV and 1250 A. The four isolators are provided with earth switch. CURRENT TRANSFORMER All the 220 KV current transformers are provided for measuring and protection. They are BHEL make, single phase, oil filled nitrogen sealed outdoor type. All the E.T.S. are multi-cored with each core having specification upon duty it is to perform. Feeder circuit have 5 cores. 1) Bus bar protection core I 1250/250/IA. 30
  • 31. 2) Distance protection core II 600-300/IA. 3) O/C and E/F protection core 600-300 /IA. 4) For metering and measuring 600-300/ IA. POTENTIAL TRANSFORMER Each of 220 KV buses is provided with three P.T.’S are core for each phase of BHEL make. There are single phase, oil filled outdoor. N2 sealed, elicitor magnetic type P.T. has two secondary windings on secondary side and selected for 220/53 KV, 10/53 KV. LIGHTENING ARRESTOR For protection against lightening each of line feeders, generator transformer, station transformer has been provided with three L.A. (one for each phase). It has larger value of capacitance and will change up to line voltage. If we have to do some work on line, first earth line through earthing isolator for discharging the line capacitance and then work. 220 KV Current Transformer Manufacturer. BHEL, Trichy. Type Outdoor, Oil filled. Rated Voltage. 220 KV Nominal 220 KV Max. 245 KV. Rated Frequency. 50 Hz No. of Phase. 1-Ø Class of Insulation A. Rated Primary Voltage 2220/ 53 V. Secondary Voltage Wdg.1 110/53 V Secondary Voltage Wdg.2 110/53 V CHAPTER -7 PROTECTION 1. Field Protection. 2. Pole Slipping. 3. Plane Overload Protection. 4. Inter-turn Fault 5. Negative Phase Sequence Protection. 6. Reverse Power Protection. 31
  • 32. 7. Forward Power Protection. 8. Under Frequency & Over Frequency Protection. 9. Generator Voltage Protection. 10. Rotor Earth Fault Protection. General Protection It is most important electrical equipment of many generating station. Tripping of even a generating unit may cause overloading of associated machines and even to system un-stability . The basis function of protection applied to generator is to reduce voltage to minimum by rapid discrimination clearance of faults. Unlike other apparatus the opening of C.B. to isolate faulty generator is not sufficient to prevent future damage. CONCLUSION The first phase of practical training has proved to be quiet fruitful. It provided an opportunity for encounter with such huge machines like wagon tippler .110 MW, 210 MW & 195 MW turbines and generators. The architecture of the power plant the way various units are linked and the way working of whole plant is controlled make the student realize that engineering is not just learning the structured description and working of various machines, but the greater part is of planning proper management. 32
  • 33. It also provides an opportunities to lean low technology used at proper place and time can cave a lot of labour e.g. wagon Tripler (CHP).But there are few factors that require special mention. Training is not carried out into its tree sprit. It is recommended that there should be some project specially meant for students where presence of authorities should be ensured. There should be strict monitoring of the performance of students and system of grading be improved on the basis of work done. However training has proved to be quite fruitful. It has allowed an opportunity to get an exposure of the practical implementation to theoretical fundamentals. 33