SlideShare a Scribd company logo
DURATION:01-07-2015 to 28-07-2015
AT
Kanti Bijlee Utpadan Nigam Limited
(A Subsidiary of NTPC)
Kanti, Muzaffarpur, Bihar
By- VIMAL VAIBHAV
vmleee@gmail.com
RIT Roorkee
Formerly
• Vaishali Power Generating Company Limited.(VPGCL)
• Owned by “Bihar State Electricity Board”
Currently
• Kanti Bijlee Utpadan Nigam Limited. (KBUN)
• A joint venture of NTPC (64.57%) and BSEB (35.43%)
Features
• It is totally coal fired thermal power station.
Capacity
• There are two units in stage-I each of 110MW under operation.
• Stage-II having capacity of 2x195MW is at stage of completion.
Coal to
Steam
Steam to
Mechanical
Power
Power
Generation
The coal is unloaded either manually or with the help of
wagon tippler into the hopper to the conveyer belt.
Coal is passed through metal detectors in order to remove
metals present in coal.
Stones from coal is removed manually in its journey
through conveyer belt.
Then the coal is passed through vibrating screen where
coal of 5mm is separated from large coals.
Then coal is crushed in crusher and passed through metal
detectors to remove iron particles.
Coal is then supplied from coal bunker to pulverizing mill.
Coal dust comes out of this mill.(KBUNL have ball mills)
At KBUNL water tube boiler is employed for steam generation.
Fuel is burnt in furnace . The pulverized coal is dried by P.A fans and
secondary air is provided by F.D fan for pulverized coal combustion in
the furnace.
Water from boiler is passed through the down comers to the bottom
ring header. From bottom ring header water goes to water walls for
heat absorption and conversion in to steam.
Bottom of furnace is open to allow ash/clinkers to fall freely in to the
bottom ash hopper. And flue gas is used in economizer and reheaters.
Then it is discharged with the help of I.D fan in to atmosphere.
High pressure
turbine
• It is of single
flow design with
eight stages of
blading.
• Each stage has
moving and
stationary
blades.
• Superheated
steam(at 1100⁰c)
from boiler drum
enters in to it.
Intermediate
pressure turbine
• Double flow design
with seven stages
of blading .
• Each stage has
moving and
stationary blades.
• Reheated steam(at
535⁰ c) from H.P
turbine outlet
enters in to it.
Low pressure turbine
• It is also of double flow
design with 6 stages in
front and rear flow
paths.
• Each stage has moving
and stationary blades.
• Stem out of I.P. turbine
directly enters in to it.
Rating Continuous
Active Output 110 MW
Rated Voltage 11000 +/- 5%V
Rated Current 7220 A
Power Factor 0.8 Lagging
Frequency 50 Hz
Excitation System Static type
Field Current at
Rated Output
1335 A
Type of Cooling
System
Hydrogen Cooled
Hydrogen Pressure 2 Ata
No. of H₂ Cooled
Elements
06
Cooling Medium for
H₂
Soft water
 Mechanical power produced at the shaft of
the turbine is used to rotate rotor.
 Rotating Magnetic flux produced by rotor
cuts stator conductor flux and from
electromagnetic induction, electricity is
produced .
 Rotor runs at 3000 rpm, produces 3-phase
voltage at 11kv , and of 50 HZ frequency.
 Oil shielded hydrogen is used for the cooling
purpose of generator.
KBUNL has a capacity to generate 220 MW of
electricity but only one unit is working and
another is under R&M process. 90 MW is
generated out of 110 MW.
The transmission is done through 3-
phase , double circuit system.
With the help of station transformer 11kv
is step up to 220 kv and fed to substation.
Relay circuit
• A protective device that operate during faulty condition and
gives command to circuit breaker to trip. Mainly the
electromagnetic induction relays are used.
Fault Locator
By comparing voltage and current the relay measures the line
impedance up to the point of fault and locate the position of
fault from the previous knowledge of line impedance.
Switchgear
• Switches used in substation for making or breaking the
electrical contacts in convenient way. There are two type of
switches air switch and oil switch.
It is the brain of any substation. All necessary steps about
Transmission , protection, Charging etc. are carried out in the
control room.
Measuring instruments of the control room:-
Voltmeter and Ammeter
• As the names imply they are used for measuring voltage
and current respectively.
Power meter
• Used to measure the power in standard unit of MW or KW.
Circuit screen
• A computer arrangement in which current information
about transmission line is seen.
Battery room
Consists of several batteries and chargers for
emergency purpose.
It consists of following equipments :-
Transformer
• The autotransformer used in power station. It has three
windings primary, secondary and tertiary. The 220kv voltage
is fed as input to primary by step down 132kv fed to KBUNL as
input.
Circuit Breaker (SF6 at KBUNL)
• Used for closing or opening an electrical circuit under normal or
abnormal conditions. These circuit breakers are equipped with
trip coil connected to relay, design to open breaker
automatically
Tower
• We have suspension type tower called as ‘A’ type tower. The
peak point angle is 0⁰ to 2⁰. In this type conductor is
suspended with an insulator. Guard ring Is used to balance
the capacitive current in transmission lines.
Current transformer
• Used to measure the current level such that it can be control
easily.
Bus isolators
• Used to isolate bus bars.
Lightning arrestor
• Used to protect the transmission line and connected
equipment during lightening .
Wave Trap
Wave trap which changes the frequency 50Hz to 500Hz can be
used for communicate between power plants.
Why cylindrical pipes are used in switchyard instead
of wire conductor ?
Why cylindrical pipes are used in switchyard instead
of wire conductor ?
Because of following purpose :-
•Safety.
•Reduce Ferranti Effect.
•Reduce the effect of vibration during opening and closing of
circuit breakers and isolators.
Why motor is used to rotate the shaft of turbine, when
the turbine is not in operation?
Why motor is used to rotate the shaft of turbine, when
the turbine is not in operation?
This is because in case of any fault if
production of plants stops then bearing
motor rotates rotor shaft of turbine
continuously at 65 rpm. This is because if
shaft doesn’t rotate then due to load it may
bend.
THANK
YOU
By- VIMAL VAIBHAV
vmleee@gmail.com
RIT Roorkee

More Related Content

What's hot

Power plant ppt on kalisindh by vikas
Power plant ppt on kalisindh by vikasPower plant ppt on kalisindh by vikas
Power plant ppt on kalisindh by vikas
Vikas Gupta
 
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESHppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
AKHILESH KUMAR
 
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
Amit Gupta
 
training report NTPC Muzaffarpur Bihar
training report  NTPC Muzaffarpur Bihar training report  NTPC Muzaffarpur Bihar
training report NTPC Muzaffarpur Bihar
Dilip kumar
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
Prakash Jarotia
 
Kota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathurKota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathur
Abhishek Mathur
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
Shikhar Sodhani
 
A Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power StationA Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power Station
LekhraJ Meena
 
coal based thermal power plant
coal based thermal power plantcoal based thermal power plant
thermal power plant NTPC singrauli
thermal power plant NTPC singrauli thermal power plant NTPC singrauli
thermal power plant NTPC singrauli
Ram Narayan Shah
 
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHALVOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
Milind Punj
 
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
Utkarsh Chaubey
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
Abha Tripathi
 
Ranjan NTPC KAHALGAON ppt
Ranjan  NTPC KAHALGAON pptRanjan  NTPC KAHALGAON ppt
Ranjan NTPC KAHALGAON ppt
Ranjan kumar
 
GSECL Electrical branch Training Report
GSECL Electrical branch Training ReportGSECL Electrical branch Training Report
GSECL Electrical branch Training Report
Utsav Yagnik
 
Industrial training report of NTPC
Industrial training report of NTPC Industrial training report of NTPC
Industrial training report of NTPC
Shivam Singh
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
DilipKumar1072
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
Ishant Gautam.
 
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Raghab Gorain
 
Presentation on thermal power plant
Presentation on thermal power plantPresentation on thermal power plant
Presentation on thermal power plant
Rashmi Nimje
 

What's hot (20)

Power plant ppt on kalisindh by vikas
Power plant ppt on kalisindh by vikasPower plant ppt on kalisindh by vikas
Power plant ppt on kalisindh by vikas
 
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESHppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
 
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
 
training report NTPC Muzaffarpur Bihar
training report  NTPC Muzaffarpur Bihar training report  NTPC Muzaffarpur Bihar
training report NTPC Muzaffarpur Bihar
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
 
Kota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathurKota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathur
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
A Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power StationA Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power Station
 
coal based thermal power plant
coal based thermal power plantcoal based thermal power plant
coal based thermal power plant
 
thermal power plant NTPC singrauli
thermal power plant NTPC singrauli thermal power plant NTPC singrauli
thermal power plant NTPC singrauli
 
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHALVOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
VOCATIONAL TRAINING REPORT @ NTPC VINDHYACHAL
 
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Ranjan NTPC KAHALGAON ppt
Ranjan  NTPC KAHALGAON pptRanjan  NTPC KAHALGAON ppt
Ranjan NTPC KAHALGAON ppt
 
GSECL Electrical branch Training Report
GSECL Electrical branch Training ReportGSECL Electrical branch Training Report
GSECL Electrical branch Training Report
 
Industrial training report of NTPC
Industrial training report of NTPC Industrial training report of NTPC
Industrial training report of NTPC
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
 
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
 
Presentation on thermal power plant
Presentation on thermal power plantPresentation on thermal power plant
Presentation on thermal power plant
 

Similar to KBUNL - NTPC KANTI MUZAFFARPUR BIHAR

NTPC,muzaffarpur
NTPC,muzaffarpurNTPC,muzaffarpur
NTPC,muzaffarpur
Hari Ohm Singh
 
thermal power station
thermal power stationthermal power station
thermal power station
Hari Ohm Singh
 
Vocational trainning presentation at ESSAR Power Salaya (Electrical Engineering)
Vocational trainning presentation at ESSAR Power Salaya (Electrical Engineering)Vocational trainning presentation at ESSAR Power Salaya (Electrical Engineering)
Vocational trainning presentation at ESSAR Power Salaya (Electrical Engineering)
Lakhan Vadher
 
IPGCL/PPCL Training presentation
IPGCL/PPCL Training presentationIPGCL/PPCL Training presentation
IPGCL/PPCL Training presentation
Shubhra Dhyani
 
Internship PPT final.pptx on ukai thermal power station
Internship PPT final.pptx on ukai thermal power stationInternship PPT final.pptx on ukai thermal power station
Internship PPT final.pptx on ukai thermal power station
malikavita731
 
Internship PPT ukai thermal power station .pptx
Internship PPT ukai thermal power station .pptxInternship PPT ukai thermal power station .pptx
Internship PPT ukai thermal power station .pptx
malikavita731
 
Internship PPT final ukai thermal power station
Internship PPT final ukai thermal power stationInternship PPT final ukai thermal power station
Internship PPT final ukai thermal power station
malikavita731
 
A PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYA PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITY
Rohitashav Goyal
 
ntpc
ntpcntpc
Durgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentationDurgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentation
Saumyadip Moitra
 
363088778-Presentation-on-220kv-Sub-Station.pptx
363088778-Presentation-on-220kv-Sub-Station.pptx363088778-Presentation-on-220kv-Sub-Station.pptx
363088778-Presentation-on-220kv-Sub-Station.pptx
mk0558572
 
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
Devesh54
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation ppt
Ashutosh Srivastava
 
WBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportWBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training Report
Arijit Basu
 
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
Om Prakash
 
ntpc ppt
ntpc pptntpc ppt
ntpc ppt
Jatan Soni
 
Vocational training at mejia thermal power plant
Vocational training at mejia thermal power plantVocational training at mejia thermal power plant
Vocational training at mejia thermal power plant
Nipak Banerjee
 
tps 180150109049 180150109078.pptx
tps 180150109049 180150109078.pptxtps 180150109049 180150109078.pptx
tps 180150109049 180150109078.pptx
AnandNakum
 
industrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxindustrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptx
ShubhoDas5
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptx
Ankur Mahajan
 

Similar to KBUNL - NTPC KANTI MUZAFFARPUR BIHAR (20)

NTPC,muzaffarpur
NTPC,muzaffarpurNTPC,muzaffarpur
NTPC,muzaffarpur
 
thermal power station
thermal power stationthermal power station
thermal power station
 
Vocational trainning presentation at ESSAR Power Salaya (Electrical Engineering)
Vocational trainning presentation at ESSAR Power Salaya (Electrical Engineering)Vocational trainning presentation at ESSAR Power Salaya (Electrical Engineering)
Vocational trainning presentation at ESSAR Power Salaya (Electrical Engineering)
 
IPGCL/PPCL Training presentation
IPGCL/PPCL Training presentationIPGCL/PPCL Training presentation
IPGCL/PPCL Training presentation
 
Internship PPT final.pptx on ukai thermal power station
Internship PPT final.pptx on ukai thermal power stationInternship PPT final.pptx on ukai thermal power station
Internship PPT final.pptx on ukai thermal power station
 
Internship PPT ukai thermal power station .pptx
Internship PPT ukai thermal power station .pptxInternship PPT ukai thermal power station .pptx
Internship PPT ukai thermal power station .pptx
 
Internship PPT final ukai thermal power station
Internship PPT final ukai thermal power stationInternship PPT final ukai thermal power station
Internship PPT final ukai thermal power station
 
A PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYA PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITY
 
ntpc
ntpcntpc
ntpc
 
Durgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentationDurgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentation
 
363088778-Presentation-on-220kv-Sub-Station.pptx
363088778-Presentation-on-220kv-Sub-Station.pptx363088778-Presentation-on-220kv-Sub-Station.pptx
363088778-Presentation-on-220kv-Sub-Station.pptx
 
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation ppt
 
WBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportWBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training Report
 
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
 
ntpc ppt
ntpc pptntpc ppt
ntpc ppt
 
Vocational training at mejia thermal power plant
Vocational training at mejia thermal power plantVocational training at mejia thermal power plant
Vocational training at mejia thermal power plant
 
tps 180150109049 180150109078.pptx
tps 180150109049 180150109078.pptxtps 180150109049 180150109078.pptx
tps 180150109049 180150109078.pptx
 
industrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxindustrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptx
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptx
 

Recently uploaded

KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
NazakatAliKhoso2
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
enizeyimana36
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
Recycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part IIRecycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part II
Aditya Rajan Patra
 

Recently uploaded (20)

KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
Recycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part IIRecycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part II
 

KBUNL - NTPC KANTI MUZAFFARPUR BIHAR

  • 1. DURATION:01-07-2015 to 28-07-2015 AT Kanti Bijlee Utpadan Nigam Limited (A Subsidiary of NTPC) Kanti, Muzaffarpur, Bihar By- VIMAL VAIBHAV vmleee@gmail.com RIT Roorkee
  • 2. Formerly • Vaishali Power Generating Company Limited.(VPGCL) • Owned by “Bihar State Electricity Board” Currently • Kanti Bijlee Utpadan Nigam Limited. (KBUN) • A joint venture of NTPC (64.57%) and BSEB (35.43%) Features • It is totally coal fired thermal power station. Capacity • There are two units in stage-I each of 110MW under operation. • Stage-II having capacity of 2x195MW is at stage of completion.
  • 4. The coal is unloaded either manually or with the help of wagon tippler into the hopper to the conveyer belt. Coal is passed through metal detectors in order to remove metals present in coal. Stones from coal is removed manually in its journey through conveyer belt. Then the coal is passed through vibrating screen where coal of 5mm is separated from large coals. Then coal is crushed in crusher and passed through metal detectors to remove iron particles. Coal is then supplied from coal bunker to pulverizing mill. Coal dust comes out of this mill.(KBUNL have ball mills)
  • 5.
  • 6. At KBUNL water tube boiler is employed for steam generation. Fuel is burnt in furnace . The pulverized coal is dried by P.A fans and secondary air is provided by F.D fan for pulverized coal combustion in the furnace. Water from boiler is passed through the down comers to the bottom ring header. From bottom ring header water goes to water walls for heat absorption and conversion in to steam. Bottom of furnace is open to allow ash/clinkers to fall freely in to the bottom ash hopper. And flue gas is used in economizer and reheaters. Then it is discharged with the help of I.D fan in to atmosphere.
  • 7.
  • 8.
  • 9. High pressure turbine • It is of single flow design with eight stages of blading. • Each stage has moving and stationary blades. • Superheated steam(at 1100⁰c) from boiler drum enters in to it. Intermediate pressure turbine • Double flow design with seven stages of blading . • Each stage has moving and stationary blades. • Reheated steam(at 535⁰ c) from H.P turbine outlet enters in to it. Low pressure turbine • It is also of double flow design with 6 stages in front and rear flow paths. • Each stage has moving and stationary blades. • Stem out of I.P. turbine directly enters in to it.
  • 10. Rating Continuous Active Output 110 MW Rated Voltage 11000 +/- 5%V Rated Current 7220 A Power Factor 0.8 Lagging Frequency 50 Hz Excitation System Static type Field Current at Rated Output 1335 A Type of Cooling System Hydrogen Cooled Hydrogen Pressure 2 Ata No. of H₂ Cooled Elements 06 Cooling Medium for H₂ Soft water
  • 11.  Mechanical power produced at the shaft of the turbine is used to rotate rotor.  Rotating Magnetic flux produced by rotor cuts stator conductor flux and from electromagnetic induction, electricity is produced .  Rotor runs at 3000 rpm, produces 3-phase voltage at 11kv , and of 50 HZ frequency.  Oil shielded hydrogen is used for the cooling purpose of generator.
  • 12. KBUNL has a capacity to generate 220 MW of electricity but only one unit is working and another is under R&M process. 90 MW is generated out of 110 MW. The transmission is done through 3- phase , double circuit system. With the help of station transformer 11kv is step up to 220 kv and fed to substation.
  • 13. Relay circuit • A protective device that operate during faulty condition and gives command to circuit breaker to trip. Mainly the electromagnetic induction relays are used. Fault Locator By comparing voltage and current the relay measures the line impedance up to the point of fault and locate the position of fault from the previous knowledge of line impedance. Switchgear • Switches used in substation for making or breaking the electrical contacts in convenient way. There are two type of switches air switch and oil switch. It is the brain of any substation. All necessary steps about Transmission , protection, Charging etc. are carried out in the control room. Measuring instruments of the control room:-
  • 14. Voltmeter and Ammeter • As the names imply they are used for measuring voltage and current respectively. Power meter • Used to measure the power in standard unit of MW or KW. Circuit screen • A computer arrangement in which current information about transmission line is seen. Battery room Consists of several batteries and chargers for emergency purpose.
  • 15. It consists of following equipments :- Transformer • The autotransformer used in power station. It has three windings primary, secondary and tertiary. The 220kv voltage is fed as input to primary by step down 132kv fed to KBUNL as input. Circuit Breaker (SF6 at KBUNL) • Used for closing or opening an electrical circuit under normal or abnormal conditions. These circuit breakers are equipped with trip coil connected to relay, design to open breaker automatically Tower • We have suspension type tower called as ‘A’ type tower. The peak point angle is 0⁰ to 2⁰. In this type conductor is suspended with an insulator. Guard ring Is used to balance the capacitive current in transmission lines.
  • 16. Current transformer • Used to measure the current level such that it can be control easily. Bus isolators • Used to isolate bus bars. Lightning arrestor • Used to protect the transmission line and connected equipment during lightening . Wave Trap Wave trap which changes the frequency 50Hz to 500Hz can be used for communicate between power plants.
  • 17. Why cylindrical pipes are used in switchyard instead of wire conductor ?
  • 18. Why cylindrical pipes are used in switchyard instead of wire conductor ? Because of following purpose :- •Safety. •Reduce Ferranti Effect. •Reduce the effect of vibration during opening and closing of circuit breakers and isolators.
  • 19. Why motor is used to rotate the shaft of turbine, when the turbine is not in operation?
  • 20. Why motor is used to rotate the shaft of turbine, when the turbine is not in operation? This is because in case of any fault if production of plants stops then bearing motor rotates rotor shaft of turbine continuously at 65 rpm. This is because if shaft doesn’t rotate then due to load it may bend.