The document provides local details for several policy units along the Severn Estuary between Gloucester and Haw Bridge. For policy unit MAI 1, the preferred policy is managed realignment for the first epoch to allow habitat creation by establishing a new set back defense line, then hold the line for the next two epochs to maintain the new defenses. For policy unit MAI 2, the preferred policy is hold the line for all three epochs to maintain existing and new defenses along this reach. For policy unit MAI 3, the preferred policy for the first epoch is no active intervention since there is limited flood risk, but mitigation may be considered for some properties.
Smp2 part b policy statements tidenham only_finalSevern Estuary
This document summarizes the preferred policies for two policy units - TID 1 and TID 2 - along the Severn Estuary coastline in Gloucestershire. For TID 1, the preferred policy is No Active Intervention for all three epochs (0-20 years, 20-50 years, and 50-100 years) as the mudstone cliffs are expected to undergo only limited erosion. For TID 2, the preferred policies are Hold the Line for the first two epochs, and Managed Realignment for the third epoch, as new defences may need to be constructed further inland to manage increasing flood risks in the long term.
Smp2 part b policy statements wentlooge only_finalSevern Estuary
This document provides local details for two policy units, WEN1 and WEN2, located along the Severn Estuary in the context of the wider SMP policy. For both units, the preferred policy is to hold the line over the short (0-20 years), medium (20-50 years) and long (50-100 years) term. This involves maintaining and replacing existing flood defences to protect agricultural land, infrastructure, and communities from flooding and erosion due to sea level rise, while seeking opportunities to mitigate environmental impacts through managed realignment.
Smp2 part b policy statements sharpness-sev cross only_finalSevern Estuary
The document summarizes the preferred policies for six policy units along the Severn Estuary shoreline from Sharpness to Severn Crossings. The preferred policy for all units over all time periods (0-20, 20-50, 50-100 years) is Hold the Line (HTL) to manage flood risk and protect critical infrastructure like nuclear power stations. HTL involves maintaining and replacing existing flood defenses but does not guarantee funding to address future risks from sea level rise. Coastal squeeze is expected to increase due to HTL, reducing intertidal habitats over time.
Smp2 part b policy statements portishead only_finalSevern Estuary
This document provides local details for shoreline management in four policy units along the east bank of the River Severn from Portishead to Clevedon. The preferred policy for all four policy units from the present day to 2100 is No Active Intervention (NAI) as the high ground and hard geology naturally limit flood and erosion risk. NAI will allow natural processes to continue with limited impact on coastal assets and intertidal habitats. The rate of erosion will be monitored and actions may be considered if erosion increases and puts assets at risk.
Smp2 part b policy statements newport-usk only_finalSevern Estuary
This document summarizes the local coastal management plan for an area along the Severn Estuary in South Wales, including the city of Newport. It outlines 5 policy units - NEW 1 to NEW 5 - and describes the preferred coastal management policies for each over the next 100 years to balance flood risk management with nature conservation and development needs. The key drivers are international nature sites, critical infrastructure like railways and ports, and residential areas. For units NEW 1 and NEW 2, which border Newport, the preferred long-term policy is to "Hold the Line" and maintain existing flood defenses to protect properties and infrastructure. For unit NEW 3 along the River Usk, the plan shifts to "No Active Intervention" and then "Managed
Smp2 part b policy statements glos-sharpness only_finalSevern Estuary
This document provides local details for several policy units along the Gloucester to Sharpness area of the Severn Estuary in England. It summarizes the preferred policies for coastal management over three time periods (epochs) from present day to 100 years in the future. The preferred policies are generally to hold the existing flood defense line until defenses need replenishing, then allow managed realignment to create intertidal habitat while maintaining a new secondary defense line. This will involve breaching existing defenses to allow approximately 350 hectares of agricultural land to flood but will reduce risk to assets behind the new defenses.
Smp2 part b policy statements lydney-glos only_finalSevern Estuary
This document summarizes the preferred policies for coastal management in Policy Units GLO 1, GLO 2, and GLO 3 along the west bank of the Severn Estuary from Lydney Harbour to Newnham Church. For GLO 1 and GLO 3, the preferred policy is No Active Intervention due to limited flood and erosion risk from the hard geology. For GLO 2, the preferred policy has Managed Realignment in the short-term to create new intertidal habitat, followed by Hold the Line policies in the medium and long-term to maintain the new flood defenses.
Smp2 part b policy statements caldicot only_finalSevern Estuary
This document summarizes the preferred policies for three policy units in the Caldicot Levels area of the Severn Estuary:
- CALD 1 (Uskmouth Power Station point to Sudbrook point) will have a Hold the Line policy to protect coastal defences and maintain flood protection for infrastructure and development.
- CALD 2 (Sudbrook point to Black Rock) will have a No Active Intervention policy as high ground and geology limit flood and erosion risks.
- CALD 3 (Black Rock to River Wye) is not described.
Smp2 part b policy statements tidenham only_finalSevern Estuary
This document summarizes the preferred policies for two policy units - TID 1 and TID 2 - along the Severn Estuary coastline in Gloucestershire. For TID 1, the preferred policy is No Active Intervention for all three epochs (0-20 years, 20-50 years, and 50-100 years) as the mudstone cliffs are expected to undergo only limited erosion. For TID 2, the preferred policies are Hold the Line for the first two epochs, and Managed Realignment for the third epoch, as new defences may need to be constructed further inland to manage increasing flood risks in the long term.
Smp2 part b policy statements wentlooge only_finalSevern Estuary
This document provides local details for two policy units, WEN1 and WEN2, located along the Severn Estuary in the context of the wider SMP policy. For both units, the preferred policy is to hold the line over the short (0-20 years), medium (20-50 years) and long (50-100 years) term. This involves maintaining and replacing existing flood defences to protect agricultural land, infrastructure, and communities from flooding and erosion due to sea level rise, while seeking opportunities to mitigate environmental impacts through managed realignment.
Smp2 part b policy statements sharpness-sev cross only_finalSevern Estuary
The document summarizes the preferred policies for six policy units along the Severn Estuary shoreline from Sharpness to Severn Crossings. The preferred policy for all units over all time periods (0-20, 20-50, 50-100 years) is Hold the Line (HTL) to manage flood risk and protect critical infrastructure like nuclear power stations. HTL involves maintaining and replacing existing flood defenses but does not guarantee funding to address future risks from sea level rise. Coastal squeeze is expected to increase due to HTL, reducing intertidal habitats over time.
Smp2 part b policy statements portishead only_finalSevern Estuary
This document provides local details for shoreline management in four policy units along the east bank of the River Severn from Portishead to Clevedon. The preferred policy for all four policy units from the present day to 2100 is No Active Intervention (NAI) as the high ground and hard geology naturally limit flood and erosion risk. NAI will allow natural processes to continue with limited impact on coastal assets and intertidal habitats. The rate of erosion will be monitored and actions may be considered if erosion increases and puts assets at risk.
Smp2 part b policy statements newport-usk only_finalSevern Estuary
This document summarizes the local coastal management plan for an area along the Severn Estuary in South Wales, including the city of Newport. It outlines 5 policy units - NEW 1 to NEW 5 - and describes the preferred coastal management policies for each over the next 100 years to balance flood risk management with nature conservation and development needs. The key drivers are international nature sites, critical infrastructure like railways and ports, and residential areas. For units NEW 1 and NEW 2, which border Newport, the preferred long-term policy is to "Hold the Line" and maintain existing flood defenses to protect properties and infrastructure. For unit NEW 3 along the River Usk, the plan shifts to "No Active Intervention" and then "Managed
Smp2 part b policy statements glos-sharpness only_finalSevern Estuary
This document provides local details for several policy units along the Gloucester to Sharpness area of the Severn Estuary in England. It summarizes the preferred policies for coastal management over three time periods (epochs) from present day to 100 years in the future. The preferred policies are generally to hold the existing flood defense line until defenses need replenishing, then allow managed realignment to create intertidal habitat while maintaining a new secondary defense line. This will involve breaching existing defenses to allow approximately 350 hectares of agricultural land to flood but will reduce risk to assets behind the new defenses.
Smp2 part b policy statements lydney-glos only_finalSevern Estuary
This document summarizes the preferred policies for coastal management in Policy Units GLO 1, GLO 2, and GLO 3 along the west bank of the Severn Estuary from Lydney Harbour to Newnham Church. For GLO 1 and GLO 3, the preferred policy is No Active Intervention due to limited flood and erosion risk from the hard geology. For GLO 2, the preferred policy has Managed Realignment in the short-term to create new intertidal habitat, followed by Hold the Line policies in the medium and long-term to maintain the new flood defenses.
Smp2 part b policy statements caldicot only_finalSevern Estuary
This document summarizes the preferred policies for three policy units in the Caldicot Levels area of the Severn Estuary:
- CALD 1 (Uskmouth Power Station point to Sudbrook point) will have a Hold the Line policy to protect coastal defences and maintain flood protection for infrastructure and development.
- CALD 2 (Sudbrook point to Black Rock) will have a No Active Intervention policy as high ground and geology limit flood and erosion risks.
- CALD 3 (Black Rock to River Wye) is not described.
Smp2 part b policy statements cardiff only_finalSevern Estuary
The document outlines policies for three policy units along the Cardiff coastline in Wales:
1) CAR 1 focuses on Cardiff Bay Barrage and prefers a long-term policy of holding the line to maintain defences and manage flood risk.
2) CAR 2 covers an area west of Cardiff Bay and also prefers holding the line to maintain earth embankments and manage flood risk to urban areas.
3) CAR 3 covers both banks of the River Rhymney and prefers holding the line to maintain defences and manage flood risk, including to a landfill site.
The policies aim to balance flood protection for communities with potential environmental impacts like coastal squeeze over the long term.
Smp2 part b policy statements chepstow-wye only_finalSevern Estuary
This document provides local details for the Chepstow and River Wye area in Wales. It discusses four policy units - WYE1, WYE2, WYE3, and WYE4 - along the River Wye from Thornwell to Beachley Point. The key policy drivers in this area are international nature conservation sites, critical infrastructure like roads and railways, and residential developments in Chepstow. For each policy unit, the document outlines the preferred policies of no active intervention over the short (0-20 years), medium (20-50 years), and long (50-100 years) terms to allow natural processes to continue while limiting flood risk and erosion.
Smp2 part b policy statements kingston seymour only_finalSevern Estuary
This document summarizes coastal management plans for several policy units along the east bank of the River Severn in England. For unit KIN 1, the preferred policy is managed realignment over all three epochs (0-20 years, 20-50 years, and 50-100 years) to allow for habitat creation and reduced flood risk. For unit KIN 2, the preferred policy is no active intervention for all epochs due to naturally stable geology. For unit KIN 3, the preferred policy is hold the line for all epochs to maintain protective sand dunes and manage flood risk to properties.
This document summarizes regulations and liability issues related to flood and erosion control structures in Connecticut. It discusses two common types of structures - seawalls and breakwaters - and how their permitting requirements differ. Seawalls require municipal approval through coastal site planning and may require state and federal permits depending on their location. Breakwaters often require both state and federal permits. The document also discusses potential liability issues if structures cause flooding or erosion on neighboring properties. Property owners may sue under theories of trespass, nuisance or failure to provide lateral support in such cases.
Community engagement on adaptation to sea level changeNeil Dufty
A change in mean sea levels will require new ways to estimate flood risk, and ways
to mitigate this risk. This paper looks at the process of developing Adaptation Plans,
which are suburb specific studies on the risks and options for potential sea level rise,
and the key component of successful adaptation planning, community engagement.
Many coastal decision makers are actively assessing options to manage coastal
flood risk that incorporates rising sea levels. These adaptation options are broadly
grouped into three categories - protect, accommodate or retreat and each option has
its costs and benefits. The mix of options chosen largely depends on the attitudes
and perspectives of the community at risk - without their support, decisions within a
democratic political system are unlikely to be successful.
This paper reports the findings of a large survey and series of workshops of ‘at risk’
residents within Lake Macquarie Local Government Area. The survey helped gauge
their preferences for management options and decision-making considerations.
Following on from this survey is the current work on community engagement as part
of developing Adaptation Plans. This engagement is using an innovative
collaborative approach to engaging the community on sea level rise and adaptation
that focuses on building the capacity of Council and the community to work together
to find a solution that sticks.
The usefulness of this research is to increase understanding on the key concerns of
community to coastal adaptation, and more effective collaborative engagement on a
topic that is often controversial. As a result, this work aims to develop management
strategies that are more appealing to those at risk and the wider community.
Climate Change Adaptation Policy for HawaiiJesse Souki
State of Hawaii Office of Planning's presentation to Society for Marketing Professional Services (SMPS) Hawaii Chapter. Climate Change Adaptation Panel Speakers were Elizabeth “Liz” Fischer, RLA, ASLA, APA, IALEM, Emergency Coordinator, U.S. Department of Transportation Federal Highway Administration Hawaii; John Marra, U.S. Regional Climate Services Director, Pacific Region, U.S. National Oceanic and Atmospheric Administration, National Climate Data Center; and Jesse K. Souki, Director, Hawaii State Office of Planning.
A new initiative is developing a strategy to better protect communities in the Lower Mainland region of British Columbia from floods. The strategy will identify opportunities to strengthen flood management policies, practices, and flood protection infrastructure across the region. An integrated, collaborative approach is needed given the significant flood risks and economic consequences the region faces. The strategy will be developed in two phases, with the first building understanding of flood risks and vulnerabilities and assessing current approaches, and the second developing and implementing the strategy.
This document discusses the process that groundwater conservation districts must follow when jointly establishing desired future conditions for aquifers within a management area. It outlines that districts in a management area must meet annually to review management plans, accomplishments, and proposals for desired future conditions. The districts must consider factors like aquifer characteristics, water needs, and property rights when proposing desired future conditions, which must be approved by a two-thirds vote. The districts then adopt the agreed upon desired future conditions through resolutions and explanatory reports.
Smp2 part b policy statements holms only_finalSevern Estuary
This document discusses coastal management plans for two islands, Flat Holm and Steep Holm. For both islands, the preferred policy for the next 100 years is no active intervention (NAI). High ground and hard geology on the islands means coastal flooding and erosion impacts will be limited in the short, medium, and long term. A NAI policy will allow natural processes to dominate while limiting risks to properties, land use, nature conservation sites, landscape, historic environment, and recreational areas on the islands.
Appendix i part a sea annexes_final_dec2010Severn Estuary
The document reviews policies, plans, and programmes and their relevance to the Shoreline Management Plan Review. It identifies several pieces of EU and UK legislation related to environmental protection, water quality, waste management, and flood risk that the SMP2 will need to comply with. It also discusses national and regional planning documents in Wales, including strategies that address sustainable development, spatial planning, and the environment. The review concludes that the SMP2 process should seek opportunities to work with other organizations to deliver measures with environmental benefits and ensure planning incorporates the objectives and policies of the SMP2, including considering flood risk at a catchment scale.
Eslam Mohamed Helmy is an Egyptian auditor seeking a challenging position. He has over 4 years of experience auditing various banks and companies. His education includes a Bachelor's degree in Accounting from Helwan University in 2011. He is proficient in Arabic and English and has advanced skills in Microsoft Office applications. His experience includes communication, accounting policies/procedures, auditing, and the ability to work under pressure as part of a team. In his spare time, he volunteers with the Resala Association in charitable activities.
El documento describe la historia y características de la banda británica The Beatles. Se formó en Liverpool en la década de 1950 y estuvo activa hasta 1970, liderando la invasión británica en Estados Unidos y convirtiéndose en la banda más popular e influyente de los años 60 con su mezcla de rock, pop y otros estilos. Sus integrantes fueron John Lennon, Paul McCartney, George Harrison y Ringo Starr.
Las redes inalámbricas permiten conectar dispositivos sin cables, transmitiendo datos a través de ondas electromagnéticas. Existen tres tipos principales clasificados por su alcance: redes personales inalámbricas, redes locales inalámbricas y redes amplias de área inalámbricas. Las redes inalámbricas se han vuelto populares debido a su conveniencia, bajo costo y fácil implementación.
Este documento resume varios deportes populares divididos en categorías como deportes de cancha, acuáticos y sobre rueda. Entre los deportes de cancha destaca el fútbol, básquet y vóley que se juegan entre dos equipos y tienen reglas específicas. Los deportes acuáticos incluyen natación, waterpolo y remo, que requieren habilidades acuáticas. Los deportes sobre rueda son rally, ciclismo y motociclismo, donde los competidores demuestran su habilidad manejando
This document provides guidance on personal branding for innovators and changemakers. It outlines a discovery process to help the reader get clear on who they want to help, what problem they solve, and what makes them unique. The reader is prompted to reflect on their strengths, values, experiences, and ideal clients. They are also given exercises to further define their brand, including creating an elevator pitch and identifying value-driven words to represent their mission. The overall goal is for the reader to fully understand and be able to articulate what makes them distinct in order to effectively communicate their personal brand.
The document analyzes how the media product, a psychological thriller, uses conventions from other thriller films. It compares scenes and elements from films like Saw V, Skyfall, Harry Potter, and The Maze Runner. Similarities include shots of characters facing challenging tasks above them against time limits. Differences include the realistic versus dystopian settings and calm versus frantic character reactions. The conclusion reflects on how using conventions like faster pacing, less dialogue, and darker lighting could have made the psychological thriller more engaging for audiences.
Smp2 part b policy statements bristol only_finalSevern Estuary
This document summarizes the preferred policies for coastal management in several policy units along the Severn Estuary in Bristol for three time periods: short term (0-20 years), medium term (20-50 years), and long term (50-100 years). The preferred policy for most units is Hold the Line (HTL), which means maintaining or replacing existing coastal defences to prevent coastal erosion and flooding. HTL is chosen to protect important infrastructure, economic assets, and residential areas from flooding while also considering environmental impacts like coastal squeeze and habitat loss over time with sea level rise. Maintaining defences is deemed economically viable but funding to do so is not guaranteed.
The document summarizes the Severn Estuary Shoreline Management Plan Review (SMP2). Key points include:
- The SMP2 proposes draft policies for managing the Severn Estuary shoreline over the next 100 years.
- It divides the shoreline into theme areas and policy units, with a preferred policy option chosen for each unit in three time periods.
- The main policy options are hold the line, no active intervention, and managed realignment.
- Climate change is a major consideration, as sea levels are projected to rise significantly over the century.
- The SMP2 aims to guide decisions on shoreline development in a sustainable way that considers risks to communities and
The document provides guidance on requirements and recommendations for developing a Safety Element for a general plan update. It discusses how the Safety Element must address hazards from fires, floods, earthquakes and other geologic hazards. It recommends integrating the Local Hazard Mitigation Plan into the Safety Element and considering climate change impacts. Specific requirements outlined include identifying hazards, emergency response priorities, and mitigation strategies through land use and development policies. The document provides definitions of key terms and an overview of legislation related to flood hazard mitigation planning.
This document summarizes the Stage 1 assessment undertaken as part of the Habitats Regulations Assessment for the Severn Estuary Shoreline Management Plan Review. 30 European sites were initially considered based on their location and potential connectivity to the study area. Following an analysis of their interest features and conservation objectives, 20 sites were scoped out from further assessment because they were deemed unlikely to be affected by changes resulting from implementation of the SMP2. The remaining 10 sites were carried forward to Stage 2 assessment.
Smp2 part b policy statements intro sections_finalSevern Estuary
This document summarizes changes in shoreline management policies between the SMP1 and the proposed SMP2 around the Severn Estuary. Key points:
- Policy changes are proposed upstream of the River Usk, around Congresbury Yeo, the Avon, Alvington, Sharpness, the upper Severn, and the Noose and Elmore areas.
- Changes reflect a better understanding of long-term tidal flood risks in these areas and opportunities to create new intertidal habitat.
- The potential outcomes of these policy changes over 50-100 years include allowing tidal flood risks to certain areas to be managed more naturally in the long run.
Smp2 part b policy statements cardiff only_finalSevern Estuary
The document outlines policies for three policy units along the Cardiff coastline in Wales:
1) CAR 1 focuses on Cardiff Bay Barrage and prefers a long-term policy of holding the line to maintain defences and manage flood risk.
2) CAR 2 covers an area west of Cardiff Bay and also prefers holding the line to maintain earth embankments and manage flood risk to urban areas.
3) CAR 3 covers both banks of the River Rhymney and prefers holding the line to maintain defences and manage flood risk, including to a landfill site.
The policies aim to balance flood protection for communities with potential environmental impacts like coastal squeeze over the long term.
Smp2 part b policy statements chepstow-wye only_finalSevern Estuary
This document provides local details for the Chepstow and River Wye area in Wales. It discusses four policy units - WYE1, WYE2, WYE3, and WYE4 - along the River Wye from Thornwell to Beachley Point. The key policy drivers in this area are international nature conservation sites, critical infrastructure like roads and railways, and residential developments in Chepstow. For each policy unit, the document outlines the preferred policies of no active intervention over the short (0-20 years), medium (20-50 years), and long (50-100 years) terms to allow natural processes to continue while limiting flood risk and erosion.
Smp2 part b policy statements kingston seymour only_finalSevern Estuary
This document summarizes coastal management plans for several policy units along the east bank of the River Severn in England. For unit KIN 1, the preferred policy is managed realignment over all three epochs (0-20 years, 20-50 years, and 50-100 years) to allow for habitat creation and reduced flood risk. For unit KIN 2, the preferred policy is no active intervention for all epochs due to naturally stable geology. For unit KIN 3, the preferred policy is hold the line for all epochs to maintain protective sand dunes and manage flood risk to properties.
This document summarizes regulations and liability issues related to flood and erosion control structures in Connecticut. It discusses two common types of structures - seawalls and breakwaters - and how their permitting requirements differ. Seawalls require municipal approval through coastal site planning and may require state and federal permits depending on their location. Breakwaters often require both state and federal permits. The document also discusses potential liability issues if structures cause flooding or erosion on neighboring properties. Property owners may sue under theories of trespass, nuisance or failure to provide lateral support in such cases.
Community engagement on adaptation to sea level changeNeil Dufty
A change in mean sea levels will require new ways to estimate flood risk, and ways
to mitigate this risk. This paper looks at the process of developing Adaptation Plans,
which are suburb specific studies on the risks and options for potential sea level rise,
and the key component of successful adaptation planning, community engagement.
Many coastal decision makers are actively assessing options to manage coastal
flood risk that incorporates rising sea levels. These adaptation options are broadly
grouped into three categories - protect, accommodate or retreat and each option has
its costs and benefits. The mix of options chosen largely depends on the attitudes
and perspectives of the community at risk - without their support, decisions within a
democratic political system are unlikely to be successful.
This paper reports the findings of a large survey and series of workshops of ‘at risk’
residents within Lake Macquarie Local Government Area. The survey helped gauge
their preferences for management options and decision-making considerations.
Following on from this survey is the current work on community engagement as part
of developing Adaptation Plans. This engagement is using an innovative
collaborative approach to engaging the community on sea level rise and adaptation
that focuses on building the capacity of Council and the community to work together
to find a solution that sticks.
The usefulness of this research is to increase understanding on the key concerns of
community to coastal adaptation, and more effective collaborative engagement on a
topic that is often controversial. As a result, this work aims to develop management
strategies that are more appealing to those at risk and the wider community.
Climate Change Adaptation Policy for HawaiiJesse Souki
State of Hawaii Office of Planning's presentation to Society for Marketing Professional Services (SMPS) Hawaii Chapter. Climate Change Adaptation Panel Speakers were Elizabeth “Liz” Fischer, RLA, ASLA, APA, IALEM, Emergency Coordinator, U.S. Department of Transportation Federal Highway Administration Hawaii; John Marra, U.S. Regional Climate Services Director, Pacific Region, U.S. National Oceanic and Atmospheric Administration, National Climate Data Center; and Jesse K. Souki, Director, Hawaii State Office of Planning.
A new initiative is developing a strategy to better protect communities in the Lower Mainland region of British Columbia from floods. The strategy will identify opportunities to strengthen flood management policies, practices, and flood protection infrastructure across the region. An integrated, collaborative approach is needed given the significant flood risks and economic consequences the region faces. The strategy will be developed in two phases, with the first building understanding of flood risks and vulnerabilities and assessing current approaches, and the second developing and implementing the strategy.
This document discusses the process that groundwater conservation districts must follow when jointly establishing desired future conditions for aquifers within a management area. It outlines that districts in a management area must meet annually to review management plans, accomplishments, and proposals for desired future conditions. The districts must consider factors like aquifer characteristics, water needs, and property rights when proposing desired future conditions, which must be approved by a two-thirds vote. The districts then adopt the agreed upon desired future conditions through resolutions and explanatory reports.
Smp2 part b policy statements holms only_finalSevern Estuary
This document discusses coastal management plans for two islands, Flat Holm and Steep Holm. For both islands, the preferred policy for the next 100 years is no active intervention (NAI). High ground and hard geology on the islands means coastal flooding and erosion impacts will be limited in the short, medium, and long term. A NAI policy will allow natural processes to dominate while limiting risks to properties, land use, nature conservation sites, landscape, historic environment, and recreational areas on the islands.
Appendix i part a sea annexes_final_dec2010Severn Estuary
The document reviews policies, plans, and programmes and their relevance to the Shoreline Management Plan Review. It identifies several pieces of EU and UK legislation related to environmental protection, water quality, waste management, and flood risk that the SMP2 will need to comply with. It also discusses national and regional planning documents in Wales, including strategies that address sustainable development, spatial planning, and the environment. The review concludes that the SMP2 process should seek opportunities to work with other organizations to deliver measures with environmental benefits and ensure planning incorporates the objectives and policies of the SMP2, including considering flood risk at a catchment scale.
Eslam Mohamed Helmy is an Egyptian auditor seeking a challenging position. He has over 4 years of experience auditing various banks and companies. His education includes a Bachelor's degree in Accounting from Helwan University in 2011. He is proficient in Arabic and English and has advanced skills in Microsoft Office applications. His experience includes communication, accounting policies/procedures, auditing, and the ability to work under pressure as part of a team. In his spare time, he volunteers with the Resala Association in charitable activities.
El documento describe la historia y características de la banda británica The Beatles. Se formó en Liverpool en la década de 1950 y estuvo activa hasta 1970, liderando la invasión británica en Estados Unidos y convirtiéndose en la banda más popular e influyente de los años 60 con su mezcla de rock, pop y otros estilos. Sus integrantes fueron John Lennon, Paul McCartney, George Harrison y Ringo Starr.
Las redes inalámbricas permiten conectar dispositivos sin cables, transmitiendo datos a través de ondas electromagnéticas. Existen tres tipos principales clasificados por su alcance: redes personales inalámbricas, redes locales inalámbricas y redes amplias de área inalámbricas. Las redes inalámbricas se han vuelto populares debido a su conveniencia, bajo costo y fácil implementación.
Este documento resume varios deportes populares divididos en categorías como deportes de cancha, acuáticos y sobre rueda. Entre los deportes de cancha destaca el fútbol, básquet y vóley que se juegan entre dos equipos y tienen reglas específicas. Los deportes acuáticos incluyen natación, waterpolo y remo, que requieren habilidades acuáticas. Los deportes sobre rueda son rally, ciclismo y motociclismo, donde los competidores demuestran su habilidad manejando
This document provides guidance on personal branding for innovators and changemakers. It outlines a discovery process to help the reader get clear on who they want to help, what problem they solve, and what makes them unique. The reader is prompted to reflect on their strengths, values, experiences, and ideal clients. They are also given exercises to further define their brand, including creating an elevator pitch and identifying value-driven words to represent their mission. The overall goal is for the reader to fully understand and be able to articulate what makes them distinct in order to effectively communicate their personal brand.
The document analyzes how the media product, a psychological thriller, uses conventions from other thriller films. It compares scenes and elements from films like Saw V, Skyfall, Harry Potter, and The Maze Runner. Similarities include shots of characters facing challenging tasks above them against time limits. Differences include the realistic versus dystopian settings and calm versus frantic character reactions. The conclusion reflects on how using conventions like faster pacing, less dialogue, and darker lighting could have made the psychological thriller more engaging for audiences.
Smp2 part b policy statements bristol only_finalSevern Estuary
This document summarizes the preferred policies for coastal management in several policy units along the Severn Estuary in Bristol for three time periods: short term (0-20 years), medium term (20-50 years), and long term (50-100 years). The preferred policy for most units is Hold the Line (HTL), which means maintaining or replacing existing coastal defences to prevent coastal erosion and flooding. HTL is chosen to protect important infrastructure, economic assets, and residential areas from flooding while also considering environmental impacts like coastal squeeze and habitat loss over time with sea level rise. Maintaining defences is deemed economically viable but funding to do so is not guaranteed.
The document summarizes the Severn Estuary Shoreline Management Plan Review (SMP2). Key points include:
- The SMP2 proposes draft policies for managing the Severn Estuary shoreline over the next 100 years.
- It divides the shoreline into theme areas and policy units, with a preferred policy option chosen for each unit in three time periods.
- The main policy options are hold the line, no active intervention, and managed realignment.
- Climate change is a major consideration, as sea levels are projected to rise significantly over the century.
- The SMP2 aims to guide decisions on shoreline development in a sustainable way that considers risks to communities and
The document provides guidance on requirements and recommendations for developing a Safety Element for a general plan update. It discusses how the Safety Element must address hazards from fires, floods, earthquakes and other geologic hazards. It recommends integrating the Local Hazard Mitigation Plan into the Safety Element and considering climate change impacts. Specific requirements outlined include identifying hazards, emergency response priorities, and mitigation strategies through land use and development policies. The document provides definitions of key terms and an overview of legislation related to flood hazard mitigation planning.
This document summarizes the Stage 1 assessment undertaken as part of the Habitats Regulations Assessment for the Severn Estuary Shoreline Management Plan Review. 30 European sites were initially considered based on their location and potential connectivity to the study area. Following an analysis of their interest features and conservation objectives, 20 sites were scoped out from further assessment because they were deemed unlikely to be affected by changes resulting from implementation of the SMP2. The remaining 10 sites were carried forward to Stage 2 assessment.
Smp2 part b policy statements intro sections_finalSevern Estuary
This document summarizes changes in shoreline management policies between the SMP1 and the proposed SMP2 around the Severn Estuary. Key points:
- Policy changes are proposed upstream of the River Usk, around Congresbury Yeo, the Avon, Alvington, Sharpness, the upper Severn, and the Noose and Elmore areas.
- Changes reflect a better understanding of long-term tidal flood risks in these areas and opportunities to create new intertidal habitat.
- The potential outcomes of these policy changes over 50-100 years include allowing tidal flood risks to certain areas to be managed more naturally in the long run.
The document summarizes Cambodia's efforts to improve disaster risk management, particularly for flood risk. It finds that while various agencies have implemented activities, efforts have lacked coordination. It recommends strengthening the National Committee for Disaster Management to better coordinate multi-agency disaster risk reduction efforts, and to develop strategic frameworks and community-based programs to reduce flood vulnerability.
This document provides a theme review for the Severn Estuary Shoreline Management Plan Review (SMP2). It identifies and evaluates key natural, historic, and land use features along the shoreline. The review includes summaries of relevant policies and legislation, assessments of landscape and nature conservation designations, the historic environment, and current and future land uses. It then provides more detailed summaries of these themes for 16 specific areas along the shoreline to inform the development of objectives and policy options for the SMP2.
Appendix f policy development and appraisal final_dec2010Severn Estuary
This document summarizes the initial approach taken to develop policy options for the Severn Estuary Shoreline Management Plan Review (SMP2). The coastline was divided into Policy Units based on land use, flood and erosion risk. Potential policy options were identified for each unit considering features and objectives. Multiple options were selected for later appraisal over three epochs (0-20, 20-50, 50-100 years) to assess impacts on coastal processes and features. The aim was to identify appropriate combinations of policies to appraise for the whole coast as interactions between locations are important to developing a sustainable long-term plan.
The document discusses flood management systems in Ireland. It covers topics such as flood policy, flood risk assessment, flood risk management plans, and sustainable urban drainage systems (SUDS). SUDS aim to minimize storm water runoff and treat water close to its source using methods like filter strips, swales, filter drains, permeable surfaces, infiltration devices, and detention ponds. National flood policy in Ireland requires flood risk to be considered in the planning process and aims to avoid development in flood-prone areas where possible.
Climate Tipping Points and the Insurance SectorOpen Knowledge
Climate change won’t be a smooth transition to a warmer world, warns the Tipping Points Report by Allianz and WWF. Twelve regions around the world will be most affected by abrupt changes.
AEMA-restoration white paper-Final-r 031715Megan Maxwell
1) Current federal policies for restoring sagebrush habitats impacted by wildfire, such as the BLM's ES&R program, are inadequate and impose unrealistic timelines that do not support restoration of low-elevation Wyoming sagebrush, which is an important habitat for the greater sage-grouse.
2) The ES&R program's preference for passive recovery, 3-year funding limits, and metrics for measuring success are inappropriate for restoring low-elevation Wyoming sagebrush and instead favor higher elevation areas.
3) Revisions are needed to the ES&R program and other policies to develop special provisions for low-elevation Wyoming sagebrush restoration, and to provide adequate funding and monitoring timelines to implement recent orders aimed
Coastal Regulation Zones (CRZ) regulate development near coastlines to protect fragile coastal ecosystems. The CRZ Rules were first implemented in 1991 and restrict activities like large developments, factories, waste storage, mining within 500 meters of the coast. The new CRZ Rules in 2021 classify rural coastal areas into two types based on population density, and establish no-development zones of 50 meters or 200 meters from the high tide line accordingly. Environmental Impact Assessments (EIAs) identify environmental, social and economic impacts of projects before approval. The EIA process involves screening, scoping, collecting baseline data, impact prediction, mitigation measures, public hearings, and monitoring project implementation.
The document provides an environmental assessment report for the Severn Estuary Shoreline Management Plan Review (SMP2). It summarizes the baseline environmental conditions in the study area, including populations and human health, biodiversity, fisheries, geology, land use, water, air and climate, cultural heritage, landscape and contaminated land. It then describes the strategic environmental assessment process undertaken to evaluate the potential environmental impacts of different shoreline management policies. This included developing objectives, consulting stakeholders, reviewing other relevant plans and strategies, and assessing alternative policy options. The preferred policies were selected and their impacts evaluated, including cumulative effects and mitigation measures. An implementation and monitoring plan was also developed to track effects relating to access and recreation, biodiversity
Covering Natural Disaster Losses for Water Utilities - An insurance mutual fo...CAWASA
The Caribbean region is highly prone to climate hazards and has a history of being adversely impacted by weather related events, resulting in significant losses and damages.
Most of the Caribbean islands lie within the North Atlantic “hurricane belt,” with the major climatic events affecting the region being tropical depressions and cyclones, which generate strong winds, and rainstorms that cause flooding, landslides, and storm surges.
Mangrove Restoration Monitoring Plan FinalIan Kissoon
The monitoring plan outlines data collection strategies to evaluate the success of mangrove restoration efforts in Guyana. The plan aims to 1) verify that 11km of coastline has been replanted/protected by September 2012 and 2) determine factors influencing the success or failure of replanting sites. Data on seedling survival, plant growth, anthropogenic activities, soil type, topography, wave energy, salinity, and pH will be collected regularly at replanted and natural sites. Community rangers will monitor sites and record data to be analyzed and reported on annually to assess progress towards project goals and inform future restoration efforts.
Louisiana In-Lieu-Fee Wetland Mitigation Program Proposal George Howard
The document evaluates Louisiana's mitigation program and recommends improvements to better align it with the state's coastal master plan. It finds the current program over-relies on individual mitigation projects that are not sustainable and do not support integrated coastal protection. It recommends giving higher priority to mitigation banks and in-lieu fee programs if located strategically, and creating a state-operated in-lieu fee program to increase flexibility and support critical projects. Federal rules need adjusting to address Louisiana's unique coastal challenges.
Towards a Comprehensive Climate Adaptation Framework for India’s Port Infrast...IEREK Press
The ever-growing impacts of climate change such as extreme heat, more frequent heavy precipitation events, intensifying tropical revolving storms, and sea level rise continue to pose major threats to India’s critical maritime infrastructure. As the country moves towards its ambition of becoming a leading Blue Economy of the world, a wide range of initiatives have been taken by the central and state governments to expand the maritime sector with a specific focus on the transport sector. However, there is little emphasis being paid on protecting the existing and planned seaport infrastructure against the deleterious impacts of climate change. None of the major ports in India have a dedicated climate action strategy and climate adaptation finds no mention in the policy documents pertaining to the maritime transport sector. In this context, this paper aims to highlight the need for a comprehensive, holistic and dynamic climate change adaptation strategy for India’s port infrastructure including support infrastructure and supply chains. The adaptation strategy, at the individual ports’ level and the national level, must be preceded by rigorous risk assessment studies toidentify and prioritise the major challenges arising from climate change at the local level. The paper draws upon international best practices in climate risk assessments and adaptation measures to provide a way forward for Indian ports.
Analysis of life cycle costs - Roseau Dam - final projectPaulaBauwens
The presentation considers the life-cycle costing issues that arise during the rehabilitation of the Dam and provides recommendations on how they could be properly considered through various phases of the project’s life cycle.
Similar to Smp2 part b policy statements glos-haw bridge only_final (20)
Appendix k metadata and bibliographic database final_dec2010Severn Estuary
This document provides a bibliographic database of references used in developing the Severn Estuary Shoreline Management Plan Review (SMP2). It is divided into two parts: Part A lists key documents and reports produced for the SMP2, including the main SMP2 document and its appendices on development, stakeholder engagement, baseline understanding, theme review, policy development, and environmental assessments. Part B lists mapped data and digital information used in the SMP2, including policy maps, flood/erosion maps, and theme maps. The references provide transparency on the information and evidence base supporting the SMP2.
This document provides a Water Framework Directive (WFD) assessment of the Severn Estuary Shoreline Management Plan 2 (SMP2). It identifies the transitional, coastal, river, lake and groundwater bodies in the SMP2 area and assesses how the SMP2's preferred policies may impact the environmental objectives of the WFD. The assessment found that several management areas' policies have the potential to not fully meet some of the WFD objectives. It provides recommendations to better align some SMP boundaries with WFD waterbody boundaries. Overall, the assessment determines whether the SMP2's policies will help or hinder achieving the WFD's goals in different water bodies in the plan's coastal region.
This document summarizes an economic appraisal of the preferred plan for the Severn Estuary Shoreline Management Plan Review (SMP2). It finds that:
1) Allowing natural coastal evolution with no active intervention would result in significant economic damages from flooding and loss of assets over time.
2) Implementing the preferred plan of maintaining or improving coastal defences would cost an estimated $15 million but would prevent substantial economic damages estimated at $30 million.
3) A high-level benefit-cost assessment finds the preferred plan is economically viable, with benefits expected to outweigh the costs. However, more detailed analysis will be required to justify specific future schemes.
Appendix g preferred management approach testing final_dec2010Severn Estuary
This document tests different management approaches for shoreline policy units along the Severn Estuary to help identify preferred policies. It analyzes how policy units interact through coastal processes and flooding, and assesses approaches against objectives. Management Approach A represents the initial starting point, Approach B prioritizes natural processes, Approach C protects assets, and Approach D continues current policies. Completing the approach tables helps determine the most appropriate long-term policy, which is identified in the SMP2 Final Report. The analysis aims to improve understanding of coastal change to inform planning and development decisions.
Appendix e issues and features final_dec2010Severn Estuary
This document provides an appendix to the Severn Estuary Shoreline Management Plan Review. It outlines the methodology used to identify issues, features, and objectives along the Severn Estuary coastline. Key features were identified through a theme review process and stakeholder input. The importance of each feature is evaluated based on the scale of its benefits, importance to users, sufficiency of the feature, and whether the benefits can be substituted. Features at risk of flooding under a no active intervention scenario within the next 100 years are also identified using GIS data. The appendix is divided into two parts: part A covers the identification and assessment of issues and features, while part B establishes objectives for shoreline management.
Appendix b stakeholder engagement and consultation final_dec2010Severn Estuary
This document outlines the stakeholder engagement and consultation process for the Shoreline Management Plan Review (SMP2) of the Severn Estuary in the UK. It describes the various stakeholder groups involved, including a Client Steering Group, Elected Members Forum, and Key Stakeholders Group. It details the stages of stakeholder engagement during the SMP2 development and policy setting process, including identifying issues, developing policies, and public consultation. It also provides summaries of key stakeholder consultation events held from January to June 2009 to inform the SMP2 process.
Appendix c baseline understanding final_dec2010Severn Estuary
This document contains three parts that provide baseline information for the Severn Estuary Shoreline Management Plan Review (SMP2):
Part A assesses coastal processes and evolution in the estuary based on geology, geomorphology, hydrodynamics, and sediment transport.
Part B details existing coastal defences along the shoreline based on surveys and updates from local authorities. It considers residual life of defences over 20, 50, and 100 years.
Part C develops baseline scenarios of shoreline change under conditions of No Active Intervention (NAI) and With Present Management (WPM), taking into account climate change and potential defence failure over different time periods. It aims to improve understanding of coastal risks to inform SMP
Appendix a development of the smp2 final_dec2010Severn Estuary
This document provides background information on the development of the second generation Shoreline Management Plan (SMP2) for the Severn Estuary. It discusses the purpose and process of SMPs, including considering longer timescales and factors like climate change. It also describes the relationship between the SMP2 and the parallel Flood Risk Management Strategy (SEFRMS) study. The SEFRMS will develop the policies in the SMP2 into more detailed coastal defence options. Finally, it briefly outlines the progress that has been made nationally on shoreline management planning since the first generation of SMPs.
What is a Shoreline Management Plan?
Developed in partnership by local authorities, regulators and other stakeholders, a Shoreline Management Plan (SMP) is a high level non-statutory policy document designed to assist coastal flood and erosion risk management planning. It provides a large-scale assessment of the risks (to people, property, the natural and historic environment) associated with coastal erosion and flooding at the coast over the long-term. It also proposes policies to help manage these risks sustainably over the next hundred years.
The SMP enables planners and regulators to plan for and manage the way that the coast will change. This could be by maintaining or improving defences, by enabling the natural processes to play a greater role, creating new natural habitat or by helping areas that are at risk of flooding at some point in the future to cope with and limit the impact of flooding events.
The SMP2 for the Severn Estuary updates an earlier SMP1 (2000) for the estuary. It aims to provide more certainty for landowners, residents and businesses; to know how the coast will be managed by regulators during the next 100 years, so that they can plan ahead and make decisions about investments, homes, development and the management of their resources.
There is a tremendous amount of news being disseminated every day online about dangerous forever chemicals called PFAS. In this interview with a global PFAS testing expert, Geraint Williams of ALS, he and York Analytical President Michael Beckerich discuss the hot-button issues for the environmental engineering and consulting industry -- the wider range of PFAS contamination sites, new PFAS that are unregulated, and the compliance challenges ahead.
Widespread PFAS contamination requires stringent sampling and laboratory analyses by certified laboratories only -- whether it is for PFAS in soil, groundwater, wastewater or drinking water.
Contact us at York Analytical Laboratories for expert environmental testing with fast turnaround times and client service. We have 4 state-certified laboratories in Connecticut, New York and New Jersey, and 4 client service centers.
P: 800-306-YORK
E: clientservices@YorkLab.com
W: YorkLab.com
(Q)SAR Assessment Framework: Guidance for Assessing (Q)SAR Models and Predict...hannahthabet
The webinar provided an overview of the new OECD (Q)SAR Assessment Framework for evaluating the scientific validity of (Q)SAR models, predictions, and results from multiple predictions. The QAF provides assessment elements for existing principles for evaluating models, as well as new principles for evaluating predictions and results. In addition to the principles, assessment elements, and guidance for evaluating each element, the QAF includes a checklist for reporting assessments.
This new Framework provides regulators with a consistent and transparent approach for reviewing the use of (Q)SAR predictions in a regulatory context and increases the confidence to accept alternative methods for evaluating chemical hazards. The OECD worked closely together with the Istituto Superiore di Sanità (Italy) and the European Chemicals Agency (ECHA), supported by a variety of international experts to develop a checklist of criteria and guidance for evaluating each criterion. The aim of the QAF is to help establish confidence in the use of (Q)SARs in evaluating chemical safety, and was designed to be applicable irrespective of the modelling technique used to build the model, the predicted endpoint, and the intended regulatory purpose.
The webinar provided an overview of the project and presented the main aspects of the framework for assessing models and results based on individual or multiple predictions.
A Comprehensive Guide on Cable Location Services Detections Method, Tools, an...Aussie Hydro-Vac Services
Explore Aussie Hydrovac's comprehensive cable location services, employing advanced tools like ground-penetrating radar and robotic CCTV crawlers for precise detection. Also offering aerial surveying solutions. Contact for reliable service in Australia.
The modification of an existing product or the formulation of a new product to fill a newly identified market niche or customer need are both examples of product development. This study generally developed and conducted the formulation of aramang baked products enriched with malunggay conducted by the researchers. Specifically, it answered the acceptability level in terms of taste, texture, flavor, odor, and color also the overall acceptability of enriched aramang baked products. The study used the frequency distribution for evaluators to determine the acceptability of enriched aramang baked products enriched with malunggay. As per sensory evaluation conducted by the researchers, it was proven that aramang baked products enriched with malunggay was acceptable in terms of Odor, Taste, Flavor, Color, and Texture. Based on the results of sensory evaluation of enriched aramang baked products proven that three (3) treatments were all highly acceptable in terms of variable Odor, Taste, Flavor, Color and Textures conducted by the researchers.
Exploring low emissions development opportunities in food systemsCIFOR-ICRAF
Presented by Christopher Martius (CIFOR-ICRAF) at "Side event 60th sessions of the UNFCCC Subsidiary Bodies - Sustainable Bites: Innovating Low Emission Food Systems One Country at a Time" on 13 June 2024
Download the Latest OSHA 10 Answers PDF : oyetrade.comNarendra Jayas
Latest OSHA 10 Test Question and Answers PDF for Construction and General Industry Exam.
Download the full set of 390 MCQ type question and answers - https://www.oyetrade.com/OSHA-10-Answers-2021.php
To Help OSHA 10 trainees to pass their pre-test and post-test we have prepared set of 390 question and answers called OSHA 10 Answers in downloadable PDF format. The OSHA 10 Answers question bank is prepared by our in-house highly experienced safety professionals and trainers. The OSHA 10 Answers document consists of 390 MCQ type question and answers updated for year 2024 exams.
Smp2 part b policy statements glos-haw bridge only_final
1. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
1
GLOUCESTER TO HAW BRIDGE
This Theme area contains the Policy Units MAI 1, MAI 2, MAI 3, MAI 4, MAI 5, and MAI 6.
It starts at the drain from Long Brook and ends at Haw Bridge (upstream extent of Severn
Estuary SMP2).
The Key Policy Drivers in this area are:
• International nature conservation sites – Severn Estuary SAC, SPA and Ramsar sites;
• Critical infrastructure – railway line, A48, A40, electricity network and substations,
Netheridge sewage treatment works;
• Residential – Gloucester.
2. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
2
3. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
3
Policy Unit: MAI 1 – the drain at Long Brook to the railway/A40 bridge
(west bank of the Severn)
4. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
4
Preferred Policies to Implement the Plan:
Epoch
Preferred
Policy
Comments
0 to 20
years
(2025)
MR
The Short Term policy for this unit is Managed Realignment.
Existing defences are likely to come to the end of their serviceable life in the
next epoch. A new realigned defence will enable new intertidal habitat to be
created and manage the risk of impacts from flooding and erosion to assets
behind new defences in this and linked Policy Units (MAI 2, MAI 3, MAI 4,
MAI 5 and MAI 6). MR will manage the risk of impacts from flooding and
erosion to assets behind the new defences.
MR in this Policy Unit may allow short lengths of existing defence to be
maintained and a NAI policy along other undefended lengths to allow the
shoreline to evolve naturally. The precise location and type of defence
should be determined by the SEFRMS. This should also determine if the
existing defences can be allowed to erode naturally or should be breached.
Any defences allowed to erode should be monitored to ensure they do not
pose a risk to H&S. New, set back defences and other defences in the policy
unit should be maintained.
Land, nature conservation and historic environment features in front of the
new line of defences or in areas of NAI will be at increased risk of flooding
and erosion. Adaptation actions should be considered and implemented.
The habitat created in this policy unit will help compensate for areas lost
elsewhere in the estuary and help maintain/improve the condition of the
European protected sites.
MR does not guarantee funding to build or maintain new realigned defences.
20 to 50
years
(2055)
HTL
The medium term policy for this unit is Hold The Line.
New realigned defences should be maintained. HTL will manage the risk of
impacts from flooding and erosion to assets behind the new defences.
HTL does not guarantee funding to build or maintain current or future
defences or to counter sea level rise.
50 to 100
years
(2105)
HTL
The long term policy for this unit is Hold The Line.
New realigned defences should be maintained. HTL will manage the risk of
impacts from flooding and erosion to assets behind the new defences.
HTL does not guarantee funding to build or maintain current or future
defences or to counter sea level rise..
5. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
5
Economics
Policy
Unit
Existing
SMP1
Policy
Time Period
(epoch)
SMP2 Assessment
0-
20
20-
50
50-
100
Preferred Plan Present Value
Damages
Preferred Plan Present Value
Defence Costs
MAI 1 HTL MR HTL HTL
£18m
(MAI1-6 total)
£5m
(MAI1-6 total)
The preferred policy is economically viable for the linked Policy Units of MAI 1, MAI 2, MAI 3, MAI 4, MAI 5
and MAI 6. The costs and damages of the preferred policy in the table above relate to actions taken in all
linked policy units.
6. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
6
Predicted Implication of the Preferred Plan for the MAI 1 Policy Unit
Time
Period
Management
Activities
Property, Land Use and
Human Health
Nature Conservation –
including Earth Heritage,
Geology and Biodiversity
Landscape Character
and Visual Amenity
Historic Environment
Amenity and
Recreational Use
0 – 20
years
The existing defence
line will not be
maintained and a new
set back defence
should be established
to allow habitat creation
and to reduce the
impact from fluvial
flooding by increasing
floodwater conveyance
A total of 349 Ha of
agricultural land will be
undefended and subject to
frequent flood risk. Erosion
in this section of the estuary
is limited. Realigned
defences will manage the
risk to properties and land
behind new defences.
Assets in front of realigned
defences will be at risk from
inundation. Impacts on
property and land, and
mitigation actions will need
to be considered in
determining realignment of
defences
A MR policy will allow the
creation of approximately
349 Ha of additional
intertidal habitat. However
there may be loss of
terrestrial habitats as
intertidal habitats roll back.
Works should take account
of possible environmental
impacts and the need for an
EIA.
The creation of intertidal
habitat will replace
existing agricultural land,
altering the landscape.
Realigned defences will
manage the risk to
historic environment
assets behind new
defences. Assets in
front of realigned
defences will be at risk
from inundation.
Impacts on property
and land and mitigation
actions will need to be
considered in
determining realignment
of defences.
Realigned defences will
manage the risk to the
amenity value or
recreational use of the
land behind new
defences. Assets in front
of realigned defences will
be at risk from inundation.
Impacts to amenity and
recreational use will need
to be considered in
determining realignment
of defences
20 – 50
years
The new defence line
should be maintained.
Defences will manage the
risk of flooding to existing
properties and land in this
epoch.
Defences will manage the
risk of flooding to the natural
environment. Works should
take account of possible
environmental impacts and
the need for an EIA.
The creation of intertidal
habitat will replace
existing agricultural land,
altering the landscape.
Defences will manage
the risk of flooding to
the historic environment
Defences will manage the
risk of flooding to the
amenity value of the land
or recreational use.
50 – 100
years
The new defence line
should be maintained.
Defences will manage the
risk of flooding to existing
properties and land in this
epoch.
Defences will manage the
risk of flooding to the natural
environment. Works should
take account of possible
environmental impacts and
the need for an EIA.
In the long term sea level
rise will result in more
frequent flooding of the
seaward side of the
defence line and creation
of intertidal habitat.
Defences will manage
the risk of flooding to
the historic environment
Defences will manage the
risk of flooding to the
amenity value of the land
or recreational use.
7. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
7
Policy Unit: MAI 2 – Railway/A40 bridge to Haw Bridge (west bank of
the Severn, including the River Leadon) to Wainlode Hill (east bank)
8. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
8
Preferred Policies to Implement the Plan:
Epoch
Preferred
Policy
Comments
0 to 20
years
(2025)
HTL
The Short Term policy for this unit is a Hold the Line policy.
The existing defences will come to the end of their serviceable life in this
epoch, although maintenance and repairs may extend the life of the existing
defences. HTL recommends that defences are replaced. The position, size
and materials of new defences should be considered in detail by the
SEFRMS – in some areas high ground limits the risk from coastal flooding.
NAI is not appropriate due to areas of low lying ground in this and linked
Policy Units (MAI 1, MAI 3, MAI 4, MAI 5 and MAI 6). HTL manages the risk
of impacts from flooding and erosion.
HTL does not guarantee funding to build or maintain current or future
defences or to counter sea level rise.
20 to 50
years
(2055)
HTL
The medium term policy for this unit is a Hold the Line policy.
If defences have not been replaced in the previous epoch, HTL recommends
that they are replaced during this epoch. The position, size and materials of
new defences should be considered in detail by the SEFRMS – in some
areas high ground limits the risk from coastal flooding.
If defences have been replaced in the previous epoch, they should be
monitored and maintained during this epoch. Actions taken in this Policy
Unit should take account of effects in linked Policy Units (MAI 1, MAI 3, MAI
4, MAI 5 and MAI 6). HTL manages the risk of impacts from flooding and
erosion.
HTL does not guarantee funding to build or maintain current or future
defences or to counter sea level rise.
50 to 100
years
(2105)
HTL
The long term policy for this unit is a Hold the Line policy.
New defences should be maintained. Actions taken in this Policy Unit should
take account of effects in linked Policy Units (MAI 1, MAI 3, MAI 4, MAI 5 and
MAI 6). HTL manages the risk of impacts from flooding and erosion.
HTL does not guarantee funding to build or maintain current or future
defences or to counter sea level rise.
It should be noted that this unit does not end at Haw Bridge but extends to Wainlode Hill on the left bank of
the River Severn. This is due to the large area of flood plain extending east and connected to this section
of the shoreline.
Economics
Policy
Unit
Existing
SMP1
Policy
Time Period
(epoch)
SMP2 Assessment
0-
20
20-
50
50-
100
Preferred Plan Present Value
Damages
Preferred Plan Present Value
Defence Costs
MAI 2 N/A HTL HTL HTL
£18m
(MAI1-6 total)
£5m
(MAI1-6 total)
The preferred policy is economically viable for the linked Policy Units of MAI 1, MAI 2, MAI 3, MAI 4, MAI 5
and MAI 6. The costs and damages of the preferred policy in the table above relate to actions taken in all
linked policy units.
9. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
9
Predicted Implication of the Preferred Plan for the MAI 2 Policy Unit
Time
Period
Management Activities
Property, Land Use and
Human Health
Nature Conservation –
including Earth
Heritage, Geology and
Biodiversity
Landscape Character
and Visual Amenity
Historic Environment
Amenity and
Recreational Use
0 – 20
years
The current earth
embankment defences
are expected to come to
the end of their
serviceable life during this
epoch and should be
replaced, although
maintenance may extend
their life into the next
epoch.
Defences will manage the
risk of flooding to existing
property, land use or
human health.
An HTL policy will not
impact the nature
conservation sites during
this time period. Works
should take account of
possible environmental
impacts and the need for
an EIA.
Defences are likely to
come to the end of their
serviceable life and
require reconstruction in
this epoch. Increased
height of defences or
change in defence
construction materials will
affect local landscape -
increasing presence in
the landscape and
disrupting views.
Defences will manage the
risk of impacts from
flooding to the historic
environment
Defences will manage the
risk of flooding to the
amenity value of the land
or recreational use.
20 – 50
years
An on-going maintenance
programme should be
established to ensure the
defences remain
operational.
Defences will manage the
risk of flooding to existing
property, land use or
human health.
An HTL policy will not
impact the nature
conservation sites during
this time period. Works
should take account of
possible environmental
impacts and the need for
an EIA.
Increased height of
defences or change in
defence construction
materials will affect local
landscape - increasing
presence in the
landscape and disrupting
views.
Defences will manage the
risk of impacts from
flooding to the historic
environment
Defences will manage the
risk of flooding to the
amenity value of the land
or recreational use.
50 – 100
years
An on-going maintenance
programme should be
established including the
monitoring of shoreline
erosion as sea level rise
increases.
Defences will manage the
risk of flooding to existing
property, land use or
human health.
A HTL policy will manage
the impact of saline
intrusion on Ashleworth
Ham (SSSI). Works
should take account of
possible environmental
impacts and the need for
an EIA.
Increased height of
defences or change in
defence construction
materials will affect local
landscape - increasing
presence in the
landscape and disrupting
views.
Defences will manage the
risk of impacts from
flooding to the historic
environment
Defences will manage the
risk of flooding to the
amenity value of the land
or recreational use.
10. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
10
Policy Unit: MAI 3 - Wainlode Hill (east bank)to Upper Parting (east
bank of the Severn)
11. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
11
Policies to Implement the Plan:
Epoch
Preferred
Policy
Comments
0 to 20
years
(2025)
NAI
The Short Term policy for this unit is No Active Intervention.
There is limited impact from coastal erosion or flood risk in this Policy Unit
over all three SMP2 epochs. For properties at some risk of flooding,
mitigation should be considered – this may include individual property
defences or other actions. Actions taken in this Policy Unit should take
account of effects in linked Policy Units (MAI 1, MAI 2, MAI 4, MAI 5 and MAI
6) and the CFMP policy (reduce flood risk management actions, accepting
that flood risk will increase over time – see Section 3.4 SMP2-CFMP
interactions). Defences should be monitored to ensure they do not pose a
risk to H&S under NAI.
20 to 50
years
(2055)
NAI
The Medium Term policy for this unit is No Active Intervention.
Most of the existing defences will come to the end of their serviceable life in
this epoch. Defences should be monitored to ensure they do not pose a risk
to H&S under NAI, impact on the linked Policy Units (MAI 1, MAI 2, MAI 4,
MAI 5 and MAI 6) or affect CFMP policy actions (reduce flood risk
management actions, accepting that flood risk will increase over time – see
Section 3.4 SMP2-CFMP interactions).
The extent of the floodplain is limited by high ground. Some agricultural land
may be at risk of flooding. For properties at some risk of flooding, mitigation
should be considered – this may include individual property defences or
other actions.
50 to 100
years
(2105)
NAI
The Long Term policy for this unit is No Active Intervention.
Any remaining defences will come to the end of their serviceable life during
in this epoch and flooding will be more frequent. The extent of the floodplain
is limited by high ground. Defences should be monitored to ensure they do
not pose a risk to H&S under NAI, impact on the linked Policy Units (MAI 1,
MAI 2, MAI 4, MAI 5 and MAI 6) or affect CFMP policy actions (reduce flood
risk management actions, accepting that flood risk will increase over time –
see Section 3.4 SMP2-CFMP interactions).
The extent of the floodplain is limited by high ground. Some agricultural land
may be at risk of flooding. For properties at some risk of flooding, mitigation
should be considered – this may include individual property defences or
other actions.
12. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
12
Economics
Policy
Unit
Existing
SMP1
Policy
Time Period
(epoch)
SMP2 Assessment
0-
20
20-
50
50-
100
Preferred Plan Present Value
Damages
Preferred Plan Present Value
Defence Costs
MAI 3 N/A NAI NAI NAI
£18m
(MAI1-6 total)
£5m
(MAI1-6 total)
The preferred policy has no economic impact in this Policy Unit. The preferred policy is economically
viable for the linked Policy Units of MAI 1, MAI 2, MAI 3, MAI 4, MAI 5 and MAI 6. The costs of the
preferred policy in the table above relate to actions taken in all linked policy units, not in MAI 3.
13. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
13
Predicted Implication of the Preferred Plan for the MAI 3 Policy Unit
Time
Period
Management Activities
Property, Land Use and
Human Health
Nature Conservation –
including Earth
Heritage, Geology and
Biodiversity
Landscape Character
and Visual Amenity
Historic Environment
Amenity and
Recreational Use
0 – 20
years
The existing defence line
will not be maintained and
will deteriorate with time.
The existing flood
defences will continue to
afford protection to
existing properties and
land in this epoch.
There will be limited
impact in this epoch as
the existing defence line
is expected to remain in
place reducing the risk of
flooding and erosion.
Limited erosion and flood
risk will not impact on
existing landscape and
visual amenity.
Limited erosion and flood
risk will not impact on the
historic environment
Limited erosion and flood
risk will not impact on the
amenity value of the land
or recreational use.
20 – 50
years
The shoreline will
undergo limited erosion.
High ground constrains
flooding in this period. As
a result erosion and flood
risk management
activities will be limited.
Flooding will remain
constrained to a strip
along the river.
Agricultural land will
experience more frequent
flooding and become
unusable.
A NAI policy will allow
natural processes to
dominate. Wainlode Cliff
SSSI will continue to be
exposed. Freshwater and
terrestrial environments
are not expected to be
affected outside the area
of saline intrusion
constrained by high
ground.
Flooding and erosion will
only impact on landscape
and visual amenity within
the area affected by
saline flooding – limited
due to high ground.
Flooding and erosion will
only impact on historic
environment assets within
the area affected by
saline flooding – limited
due to high ground.
Flooding and erosion will
only impact on the
amenity value of the land
within the area affected
by saline flooding –
limited due to high
ground.
50 – 100
years
The shoreline will
undergo limited erosion.
High ground constrains
flooding in this period. As
a result erosion and flood
risk management
activities will be limited.
Flooding will remain
constrained to a strip
along the river.
Agricultural land will
experience more frequent
flooding and become
unusable.
A NAI policy will allow
natural processes to
dominate. Wainlode Cliff
SSSI will continue to be
exposed. Freshwater and
terrestrial environments
are not expected to be
affected outside the area
of saline intrusion
constrained by high
ground.
Flooding and erosion will
only impact on landscape
and visual amenity within
the area affected by
saline flooding – limited
due to high ground.
Flooding and erosion will
only impact on historic
environment assets within
the area affected by
saline flooding – limited
due to high ground.
Flooding and erosion will
only impact on the
amenity value of the land
within the area affected
by saline flooding –
limited due to high
ground.
14. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
14
Policy Unit: MAI 4 – Upper Parting to Lower Parting (east bank of the
River Severn)
15. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
15
Preferred Policies to Implement the Plan:
Epoch
Preferred
Policy
Comments
0 to 20
years
(2025)
HTL
The short term policy for this unit is Hold the Line.
Defences are expected to remain in place during this epoch. A HTL policy
would continue the current defence policy and manage the risk of impacts
from flooding to residential properties, commercial and industrial assets as
well as a significant number of historical assets. HTL will require minimal
management activities in some areas, where the impacts of tidal flood risk
are limited.
HTL does not guarantee funding to build or maintain current or future
defences or to counter sea level rise.
20 to 50
years
(2055)
HTL
The medium term policy for this unit is Hold the Line.
The existing defences will come to the end of their serviceable life in this
epoch, although maintenance and repairs may extend the life of the existing
defences. HTL recommends that defences are replaced and the need for
defences in currently undefended areas should be investigated. The
position, size and materials of new defences should be considered in detail
by the SEFRMS – in some areas high ground limits the risk from coastal
flooding. Actions should take account of effects in linked Policy Units (MAI 1,
MAI 2, MAI 3, MAI 5 and MAI 6). HTL manages the risk of impacts from
flooding and erosion.
HTL does not guarantee funding to build or maintain current or future
defences or to counter sea level rise.
50 to 100
years
(2105)
HTL
The long term policy for this unit is Hold the Line.
New defences should be maintained. Actions taken in this Policy Unit should
take account of effects in linked Policy Units (MAI 1, MAI 2, MAI 3, MAI 5 and
MAI 6). HTL manages the risk of impacts from flooding and erosion.
HTL does not guarantee funding to build or maintain current or future
defences or to counter sea level rise.
Economics
Policy
Unit
Existing
SMP1
Policy
Time Period
(epoch)
SMP2 Assessment
0-
20
20-
50
50-
100
Preferred Plan Present Value
Damages
Preferred Plan Present Value
Defence Costs
MAI 4 HTL HTL HTL HTL
£18m
(MAI1-6 total)
£5m
(MAI1-6 total)
The preferred policy is economically viable for the linked Policy Units of MAI 1, MAI 2, MAI 3, MAI 4, MAI 5
and MAI 6. The costs and damages of the preferred policy in the table above relate to actions taken in all
linked policy units.
16. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein
Severn Estuary SMP2 Review – Final Report
16
Predicted Implication of the Preferred Plan for the MAI 4 Policy Unit
Time
Period
Management Activities
Property, Land Use and
Human Health
Nature Conservation –
including Earth
Heritage, Geology and
Biodiversity
Landscape Character
and Visual Amenity
Historic Environment
Amenity and
Recreational Use
0 – 20
years
The shoreline will remain
stable and constrained
flooding in this period will
result in minimal
management activities.
Defences will manage the
risk of flooding to existing
property, land use or
human health.
Limited coastal squeeze,
primarily north of
Gloucester, is likely,
resulting in loss of
intertidal habitats. Works
should take account of
possible environmental
impacts and the need for
an EIA.
Limited erosion and flood
risk under a HTL policy
will not impact on existing
landscape and visual
amenity
Defences will manage the
risk of impacts from
flooding to the historic
environment
Defences will manage the
risk of flooding on
amenity or recreational
value of the land.
20 – 50
years
The current defences will
have deteriorated in this
time frame and should be
replaced.
Defences will manage the
risk of flooding to existing
property, land use or
human health.
Coastal squeeze may
occur which will result in
loss of intertidal habitats.
Works should take
account of possible
environmental impacts
and the need for an EIA.
Defences are likely to
come to the end of their
serviceable life and
require reconstruction in
this epoch. Increased
height of defences or
change in defence
construction materials will
affect local landscape -
increasing presence in
the landscape and
disrupting views.
Defences will manage the
risk of impacts from
flooding to the historic
environment
Defences will manage the
risk of flooding on
amenity or recreational
value of the land.
50 – 100
years
An on-going maintenance
programme should be
established including the
monitoring of tidal flood
risk as sea level rise
increases.
Defences will manage the
risk of flooding to existing
property, land use or
human health.
Coastal squeeze may
occur which will result in
loss of intertidal habitats.
Works should take
account of possible
environmental impacts
and the need for an EIA.
Increased height of
defences or change in
defence construction
materials will affect local
landscape - increasing
presence in the
landscape and disrupting
views.
Defences will manage the
risk of impacts from
flooding to the historic
environment
Defences will manage the
risk of flooding on
amenity or recreational
value of the land.
17. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
17
Policy Unit: MAI 5 – Alney Island
18. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
18
Preferred Policies to Implement the Plan:
Epoch
Preferred
Policy
Comments
0 to 20
years
(2025)
HTL
The short term policy for this unit is Hold the Line.
Defences are expected to remain in place during this epoch. A HTL policy
would continue the current defence policy and manage the risk of impacts
from flooding to residential properties, commercial and industrial assets as
well as a significant number of historical assets. HTL will require minimal
management activities in some areas, where the impacts of tidal flood risk
are limited.
HTL does not guarantee funding to build or maintain current or future
defences or to counter sea level rise.
20 to 50
years
(2055)
HTL
The medium term policy for this unit is Hold the Line.
The existing defences will come to the end of their serviceable life in this
epoch, although maintenance and repairs may extend the life of the existing
defences. HTL recommends that defences are replaced and the need for
defences in currently undefended areas should be investigated. The
position, size and materials of new defences should be considered in detail
by the SEFRMS – in some areas high ground limits the risk from coastal
flooding.
Actions should take account of effects in linked Policy Units (MAI 1, MAI 2,
MAI 3, MAI 4 and MAI 6). HTL will manage the risk of impacts from flooding
and erosion.
HTL does not guarantee funding to build or maintain current or future
defences or to counter sea level rise.
50 to 100
years
(2105)
HTL
The long term policy for this unit is Hold the Line.
New defences should be maintained. Actions taken in this Policy Unit should
take account of effects in linked Policy Units (MAI 1, MAI 2, MAI 3, MAI 4 and
MAI 6). HTL will manage the risk of impacts from flooding and erosion.
HTL does not guarantee funding to build or maintain current or future
defences or to counter sea level rise.
Economics
Policy
Unit
Existing
SMP1
Policy
Time Period
(epoch)
SMP2 Assessment
0-
20
20-
50
50-
100
Preferred Plan Present Value
Damages
Preferred Plan Present Value
Defence Costs
MAI 5 HTL HTL HTL HTL
£18m
(MAI1-6 total)
£5m
(MAI1-6 total)
The preferred policy is economically viable for the linked Policy Units of MAI 1, MAI 2, MAI 3, MAI 4, MAI 5
and MAI 6. The costs and damages of the preferred policy in the table above relate to actions taken in all
linked policy units.
19. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
19
Predicted Implication of the Preferred Plan for the MAI 5 Policy Unit
Time
Period
Management Activities
Property, Land Use and
Human Health
Nature Conservation –
including Earth
Heritage, Geology and
Biodiversity
Landscape Character
and Visual Amenity
Historic Environment
Amenity and
Recreational Use
0 – 20
years
The shoreline will remain
stable and constrained
flooding in this period will
result in minimal
management activities.
Defences will manage the
risk of flooding to existing
property, land use or
human health.
A HTL policy will prevent
saline intrusion of the
Alney Island LNR. Limited
coastal squeeze may
occur along the northern
shoreline, resulting in loss
of intertidal habitats.
Works should take
account of possible
environmental impacts
and the need for an EIA.
Defences will manage the
risk of flooding to existing
landscape and visual
amenity
Defences will manage the
risk of impacts from
flooding to the historic
environment
Defences will manage the
risk of flooding on
amenity or recreational
value of the land.
20 – 50
years
The current defences will
have deteriorated in this
time frame and should be
replaced.
Defences will manage the
risk of flooding to existing
property, land use or
human health.
A HTL policy will prevent
saline intrusion of the
Alney Island LNR.
Coastal squeeze may
occur which will result in
loss of intertidal habitats.
Works should take
account of possible
environmental impacts
and the need for an EIA.
Defences are likely to
come to the end of their
serviceable life and
require reconstruction in
this epoch. Increased
height of defences or
change in defence
construction materials will
affect local landscape -
increasing presence in
the landscape and
disrupting views.
Defences will manage the
risk of impacts from
flooding to the historic
environment
Defences will manage the
risk of flooding on
amenity or recreational
value of the land.
50 – 100
years
An on-going maintenance
programme should be
established including the
monitoring of tidal flood
risk as sea level rise
increases.
Defences will manage the
risk of flooding to existing
property, land use or
human health.
A HTL policy will prevent
saline intrusion of the
Alney Island LNR.
Coastal squeeze may
occur which will result in
loss of intertidal habitats.
Works should take
account of possible
environmental impacts
and the need for an EIA.
Increased height of
defences or change in
defence construction
materials will affect local
landscape - increasing
presence in the
landscape and disrupting
views.
Defences will manage the
risk of impacts from
flooding to the historic
environment
Defences will manage the
risk of flooding on
amenity or recreational
value of the land.
20. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
20
Policy Unit: MAI 6 – Lower Parting to Severn Farm (east bank of the
River Severn)
21. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
21
Preferred Policies to Implement the Plan:
Epoch
Preferred
Policy
Comments
0 to 20
years
(2025)
HTL
The Short Term policy for this unit is a Hold the Line policy.
The existing defences will come to the end of their serviceable life in this
epoch. HTL recommends that defences are replaced. In other areas,
minimal management activities will be needed as high ground limits the
impacts of tidal flood risk.
Actions should take account of effects in linked Policy Units (MAI 1, MAI 2,
MAI 3, MAI 4 and MAI 5). HTL continues the current policy and manages the
risk of impacts from flooding to the landfill site, residential properties and
agricultural land.
HTL does not guarantee funding to build or maintain current or future
defences or to counter sea level rise.
20 to 50
years
(2055)
HTL
The Medium Term policy for this unit is a Hold the Line policy.
Rebuilt defences should be maintained. The need for defences in currently
undefended areas should be investigated. The position, size and materials of
new defences should be considered in detail by the SEFRMS – in some
areas high ground limits the risk from coastal flooding.
Actions should take account of effects in linked Policy Units (MAI 1, MAI 2,
MAI 3, MAI 4 and MAI 5). HTL manages the risk of impacts from flooding to
the landfill site, residential properties and agricultural land.
HTL does not guarantee funding to build or maintain current or future
defences or to counter sea level rise.
50 to 100
years
(2105)
HTL
The Long Term policy for this unit is a Hold the Line policy.
Rebuilt defences should be maintained. Actions should take account of
effects in linked Policy Units (MAI 1, MAI 2, MAI 3, MAI 4 and MAI 5). HTL
manages the risk of impacts from flooding to the landfill site, residential
properties and agricultural land.
HTL does not guarantee funding to build or maintain current or future
defences or to counter sea level rise.
Economics
Policy
Unit
Existing
SMP1
Policy
Time Period
(epoch)
SMP2 Assessment
0-
20
20-
50
50-
100
Preferred Plan Present Value
Damages
Preferred Plan Present Value
Defence Costs
MAI 6 HTL HTL HTL HTL
£18m
(MAI1-6 total)
£5m
(MAI1-6 total)
The preferred policy is economically viable for the linked Policy Units of MAI 1, MAI 2, MAI 3, MAI 4, MAI 5
and MAI 6. The costs and damages of the preferred policy in the table above relate to actions taken in all
linked policy units.
22. The above provides the local details in respect of the SMP-wide policy presented in the preceding sections of this Plan
document. These details must be read in the context of the wider-scales issues and policy implications, as reported therein.
Severn Estuary SMP2 Review – Final Report
22
Predicted Implication of the Preferred Plan for the MAI 6 Policy Unit
Time
Period
Management Activities
Property, Land Use
and Human Health
Nature Conservation –
including Earth Heritage,
Geology and Biodiversity
Landscape Character
and Visual Amenity
Historic Environment
Amenity and
Recreational Use
0 – 20
years
The current defences are
expected to come to the
end of their serviceable
life during this epoch. In
some areas only minimal
management activities
will be required due to
high ground limiting
flooding.
Defences will manage
the risk of impacts from
flooding to existing
property, land use or
human health.
A HTL policy will prevent
saline intrusion of
freshwater habitats. Works
should take account of
possible environmental
impacts and the need for
an EIA.
Defences are likely to
come to the end of their
serviceable life and
require reconstruction in
this epoch. Increased
height of defences or
change in defence
construction materials
will affect local landscape
- increasing presence in
the landscape and
disrupting views.
Defences will manage the
risk of impacts from
flooding to the historic
environment
Defences will manage the
risk of flooding to amenity
or recreational value of
the land.
20 – 50
years
An on-going maintenance
programme should be
established including the
monitoring of tidal flood
risk as sea level rise
increases.
Defences will manage
the risk of impacts from
flooding to existing
property, land use or
human health.
A HTL policy will prevent
saline intrusion of
freshwater habitats Coastal
squeeze may occur which
will result in loss of
intertidal habitats. Works
should take account of
possible environmental
impacts and the need for
an EIA.
Increased height of
defences or change in
defence construction
materials will affect local
landscape - increasing
presence in the
landscape and disrupting
views.
Defences will manage the
risk of impacts from
flooding to the historic
environment
Defences will manage the
risk of flooding to amenity
or recreational value of
the land.
50 – 100
years
An on-going maintenance
programme should be
established including the
monitoring of tidal flood
risk as sea level rise
increases.
Defences will manage
the risk of impacts from
flooding to existing
property, land use or
human health.
A HTL policy will prevent
saline intrusion of
freshwater habitats Coastal
squeeze may occur which
will result in loss of
intertidal habitats. Works
should take account of
possible environmental
impacts and the need for
an EIA.
Increased height of
defences or change in
defence construction
materials will affect local
landscape - increasing
presence in the
landscape and disrupting
views.
Defences will manage the
risk of impacts from
flooding to the historic
environment
Defences will manage the
risk of flooding to amenity
or recreational value of
the land.