This document is the dissertation submitted by George Mwamlowe M. for the Bachelor of Quantity Surveying (Honors) degree at the National University of Science and Technology. It includes a declaration signed by the candidate and supervisor confirming the originality of the work. The dedication section acknowledges those who supported the candidate including family members, fiancé, and university staff. The acknowledgements thank those who provided guidance during the research process such as academic and industry supervisors. The abstract provides a high-level overview of the dissertation which analyzes the effectiveness of construction productivity measurement on Zimbabwean projects using a mixed methods approach.
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...Omer Syed
This capstone report examines the impacts of building information modeling (BIM) on productivity in the construction industry. The report analyzes research conducted through interviews and literature reviews. It finds that BIM increases productivity by allowing for more efficient coordination and collaboration across disciplines. BIM also improves project turnover rates by catching issues earlier in the design process. While implementing BIM requires investment in software, hardware, and training, it provides long-term benefits such as reduced costs, time savings, and improved profitability for construction companies. The report concludes that BIM adoption will continue growing as its benefits become more widely recognized in the industry.
This document is a project report that examines the challenges faced by contractors using design and build contracts in Ghana. It begins with an introduction that provides background on construction contracts and outlines the problem statement, aim, and objectives of the research. The literature review covers topics like definitions of contracts, types of contracts including traditional and design-build, and challenges commonly faced by contractors. The methodology section describes the research approach, data collection through questionnaires, sampling of contractors, and data analysis. The findings from the data analysis are then presented and discussed. Finally, conclusions and recommendations are provided based on the research objectives of comparing design-build to traditional contracts, identifying challenges faced by contractors, and suggesting measures to improve the situation.
This document is an individual project report on prefabricated building systems. It includes an acknowledgement section thanking various people for their contributions. It also includes a table of contents outlining the various sections of the report such as the introduction, literature review on prefabricated systems, research methodology, and conclusions. The introduction provides background on the use of prefabricated systems in construction and their benefits over traditional methods.
AN INNOVATIVE TOOL SELECTION METHOD FOR CONSTRUCTION PROJECTS IN NEW ZEALANDToan Nguyen
This research’s aim is to build a practical model to help decision-makers in construction projects select an appropriate innovative construction tool that can significantly contribute to labour productivity rate improvement. Innovation is one of the biggest issues currently in the construction industry all over the
world. Many studies have confirmed that the benefits from implementing innovation activities in both firm and project levels are significant and remarkable. Among those benefits, labour productivity improvement is one of the crucial outcomes. Especially in New Zealand context, low labour productivity rate in the construction industry is very alarming. In order to achieve the aim, literature has been reviewed to identify key innovation types, components, and levels in New Zealand construction
projects accounting for labour productivity rate improvement. Based on several relevant alternative selection models, the research proposes a model that evaluates both innovative options’ Benefit and Cost factors. The evaluation processes use Analytic Hierarchy Process (AHP) method to derive the alternatives’ priorities. Findings from the proposed selection model survey, which was responded by eight project decision-makers, indicate following characteristics that an innovative tool should have: (i) worker safety in terms of less general loss-time injuries, (ii) less rework, and (iii) good observability (or “highvisibility”). The proposed AHP hierarchy structure is proved that it can be used in real jobs to assist project managers’ decisions on new tool investment. Further study is needed to carry out the integration of Delphi technique and AHP to gain more confidence in the AHP factors selection.
This document discusses schedule overruns of construction projects in Ghana. It begins with an introduction that provides background on construction delays and their significance. It then presents a literature review on topics such as definitions of schedule overruns, types of delays, responsibilities of parties in construction, and factors that contribute to delays. The methodology section describes the research strategy, design, population, and data collection/analysis approaches. The results and data analysis section presents findings from surveys administered to clients, consultants, and contractors on factors responsible for delays. It identifies the 15 most severe factors, grouped under national economic, managerial, and enterprise environmental factors. The conclusion provides a summary and recommendations.
Mit Masters Thesis on Mass Finishing SelectionDave Davidson
The document describes a study conducted by John Eustis for his master's thesis at MIT in which he investigated automated surface finishing technologies and implemented a small business team model in a production cell at Codman & Shurtleff, with the goals of reducing costs through new technologies and improving productivity and quality through work redesign. Eustis evaluated several surface finishing options, developed cost models, and made recommendations, while also analyzing the rongeur cell work and beginning the process of redesigning work around a small business team approach.
This document provides an introduction to a research project investigating the perception of Lean-BIM synergy in New Zealand. It discusses:
1) The purpose is to study how BIM can be used as an unconventional tool to implement Lean principles in the New Zealand construction industry in order to improve productivity.
2) Lean has been successful in manufacturing but its benefits have not been fully realized in construction due to differences between the sectors. BIM is a newer concept that could help address waste.
3) The research will involve a literature review on Lean, BIM, and their synergy, as well as qualitative interviews with industry professionals in Auckland to understand perceptions of Lean-BIM integration.
This document summarizes a project report submitted by Gwyneth Cameron in partial fulfillment of the requirements for a Bachelor of Engineering in Civil Engineering from the University of Pretoria. The report investigates the impacts of Bus Rapid Transit (BRT) on pedestrian movement in cities. Data was collected through observational studies at intersections along BRT corridors and conventional streets in Johannesburg and Pretoria, South Africa. Statistical analysis, including t-tests and chi-squared tests, was performed to determine if pedestrians' perceptions of safety differ between BRT corridors and conventional streets. The analysis found that pedestrians perceived similar safety levels even though crossing a BRT corridor carries higher risks due to bus speeds. The report concludes that pedestrian safety techniques are
Omer Syed - The Integration of BIM in Construction Organizations & its Impact...Omer Syed
This capstone report examines the impacts of building information modeling (BIM) on productivity in the construction industry. The report analyzes research conducted through interviews and literature reviews. It finds that BIM increases productivity by allowing for more efficient coordination and collaboration across disciplines. BIM also improves project turnover rates by catching issues earlier in the design process. While implementing BIM requires investment in software, hardware, and training, it provides long-term benefits such as reduced costs, time savings, and improved profitability for construction companies. The report concludes that BIM adoption will continue growing as its benefits become more widely recognized in the industry.
This document is a project report that examines the challenges faced by contractors using design and build contracts in Ghana. It begins with an introduction that provides background on construction contracts and outlines the problem statement, aim, and objectives of the research. The literature review covers topics like definitions of contracts, types of contracts including traditional and design-build, and challenges commonly faced by contractors. The methodology section describes the research approach, data collection through questionnaires, sampling of contractors, and data analysis. The findings from the data analysis are then presented and discussed. Finally, conclusions and recommendations are provided based on the research objectives of comparing design-build to traditional contracts, identifying challenges faced by contractors, and suggesting measures to improve the situation.
This document is an individual project report on prefabricated building systems. It includes an acknowledgement section thanking various people for their contributions. It also includes a table of contents outlining the various sections of the report such as the introduction, literature review on prefabricated systems, research methodology, and conclusions. The introduction provides background on the use of prefabricated systems in construction and their benefits over traditional methods.
AN INNOVATIVE TOOL SELECTION METHOD FOR CONSTRUCTION PROJECTS IN NEW ZEALANDToan Nguyen
This research’s aim is to build a practical model to help decision-makers in construction projects select an appropriate innovative construction tool that can significantly contribute to labour productivity rate improvement. Innovation is one of the biggest issues currently in the construction industry all over the
world. Many studies have confirmed that the benefits from implementing innovation activities in both firm and project levels are significant and remarkable. Among those benefits, labour productivity improvement is one of the crucial outcomes. Especially in New Zealand context, low labour productivity rate in the construction industry is very alarming. In order to achieve the aim, literature has been reviewed to identify key innovation types, components, and levels in New Zealand construction
projects accounting for labour productivity rate improvement. Based on several relevant alternative selection models, the research proposes a model that evaluates both innovative options’ Benefit and Cost factors. The evaluation processes use Analytic Hierarchy Process (AHP) method to derive the alternatives’ priorities. Findings from the proposed selection model survey, which was responded by eight project decision-makers, indicate following characteristics that an innovative tool should have: (i) worker safety in terms of less general loss-time injuries, (ii) less rework, and (iii) good observability (or “highvisibility”). The proposed AHP hierarchy structure is proved that it can be used in real jobs to assist project managers’ decisions on new tool investment. Further study is needed to carry out the integration of Delphi technique and AHP to gain more confidence in the AHP factors selection.
This document discusses schedule overruns of construction projects in Ghana. It begins with an introduction that provides background on construction delays and their significance. It then presents a literature review on topics such as definitions of schedule overruns, types of delays, responsibilities of parties in construction, and factors that contribute to delays. The methodology section describes the research strategy, design, population, and data collection/analysis approaches. The results and data analysis section presents findings from surveys administered to clients, consultants, and contractors on factors responsible for delays. It identifies the 15 most severe factors, grouped under national economic, managerial, and enterprise environmental factors. The conclusion provides a summary and recommendations.
Mit Masters Thesis on Mass Finishing SelectionDave Davidson
The document describes a study conducted by John Eustis for his master's thesis at MIT in which he investigated automated surface finishing technologies and implemented a small business team model in a production cell at Codman & Shurtleff, with the goals of reducing costs through new technologies and improving productivity and quality through work redesign. Eustis evaluated several surface finishing options, developed cost models, and made recommendations, while also analyzing the rongeur cell work and beginning the process of redesigning work around a small business team approach.
This document provides an introduction to a research project investigating the perception of Lean-BIM synergy in New Zealand. It discusses:
1) The purpose is to study how BIM can be used as an unconventional tool to implement Lean principles in the New Zealand construction industry in order to improve productivity.
2) Lean has been successful in manufacturing but its benefits have not been fully realized in construction due to differences between the sectors. BIM is a newer concept that could help address waste.
3) The research will involve a literature review on Lean, BIM, and their synergy, as well as qualitative interviews with industry professionals in Auckland to understand perceptions of Lean-BIM integration.
This document summarizes a project report submitted by Gwyneth Cameron in partial fulfillment of the requirements for a Bachelor of Engineering in Civil Engineering from the University of Pretoria. The report investigates the impacts of Bus Rapid Transit (BRT) on pedestrian movement in cities. Data was collected through observational studies at intersections along BRT corridors and conventional streets in Johannesburg and Pretoria, South Africa. Statistical analysis, including t-tests and chi-squared tests, was performed to determine if pedestrians' perceptions of safety differ between BRT corridors and conventional streets. The analysis found that pedestrians perceived similar safety levels even though crossing a BRT corridor carries higher risks due to bus speeds. The report concludes that pedestrian safety techniques are
An investigation into the critical factors involved in developing a Knowledge...Gowri Shankar
This document is the final report submitted by Gnanamoorthy Gowri Shankar for the course BN89 Master in Project Management at Queensland University of Technology. The report investigates the critical factors involved in developing a knowledge management system in project-based manufacturing industries, using the automobile components manufacturing industry as a case study. The report includes an introduction outlining the problem statement, objectives and approach. It also includes a literature review, research methodology, results and discussion, conclusion, and recommendations. The aim is to identify issues influencing knowledge management implementation and provide recommendations to improve knowledge management practices in the industry.
The document discusses the impact of developing enterprise architecture services on selecting IT projects at Philips Lighting. It first investigates the challenges faced by Philips Lighting in ensuring business demands are translated into IT projects and allocated budgets. Then, a new portfolio management methodology comprising enterprise architecture services is proposed, designed, developed and deployed to improve the process. Finally, the new model is validated to determine how well it overcomes problems in the previous method.
FACTORS AFFECTING ROAD CONSTRUCTION PROJECT PERFORMANCE: A CASE STUDY OF JIMM...abdiakib
This document is a research proposal submitted by Abdo Akib kelifa to Jimma University in Ethiopia to study factors affecting road construction project performance in Jimma zone. The proposal includes an introduction outlining the background and importance of studying project performance. It states the objectives are to investigate factors affecting project management performance in road construction. It will use both primary and secondary data collected through questionnaires from 310 respondents including owners, consultants, contractors and engineers. Statistical analysis will be done using SPSS software. The proposal provides details on the research methodology, time schedule, and budget.
The document is a stage 2 report for an individual project that aims to encourage STEM engagement within extra-curricular groups. It provides an overview of the conceptual design phase where concepts were generated, evaluated, and refined. It also describes initial modeling and testing. The detailed design phase is discussed where embodiment design questions were considered and prototypes were developed and tested. The report outlines the progress made against the project methodology and provides documentation to support the design process.
This document summarizes a research paper on design and build (D&B) as a procurement strategy. It begins with an abstract that states building procurement strategies are important for project success if the appropriate strategy is chosen. It then outlines the research objectives of investigating various procurement strategies, determining the relationship between time, cost and quality, and showcasing D&B's advantages. A literature review and case study of a public project were conducted. Survey results from construction professionals found D&B is preferred for projects under £50 million as it allows projects to meet time and cost goals while meeting client requirements. In conclusion, the research found D&B is a preferred strategy for both small and large private and public projects when certain factors are
derrick ampiire intern report with ozone group ltdDerrick Ampiire
This document is an industrial training report submitted by Ampire Derrick detailing their work with Ozone Group Ltd on the construction of a shopping mall in Mbarara, Uganda from May to August 2014. The report provides background on the project and company, describes the trainee's involvement in excavation, formwork, surveying, and steel fixing activities. It also outlines the site layout, management structure, health and safety practices, and materials used in the construction of the shopping mall.
This document provides a 9989-word dissertation submitted in partial fulfillment of a Master of Science in Major Programme Management. The dissertation explores creating a framework to govern infrastructure projects procured without necessary studies, which can cause cost overruns and delays. It analyzes data from four major projects in Brazil's 2014 World Cup program and a questionnaire of Brazilian government project managers. The goal is to determine if adopting an agile approach with early stakeholder involvement can reduce risks and uncertainties for projects procured without full construction designs. The framework is based on literature about project overruns and governance encouraging stakeholder involvement and benefits delivery in smaller batches like agile methods.
INGENUITY IN SOIL REINFORCEMENT METHODS AGAINST SCOUR FAILUREEdison Mugoya
GEOTECHNICAL ENGINEERING: INGENUITY IN SOIL
REINFORCEMENT METHODS AGAINST SCOUR FAILURE
is a study in geotechnical engineering regarding the scour failure at bridge abutments. its a methodology used to decrease it's effects and prolong the life cycle of bridge piers
This document provides an abstract and table of contents for a research project on the scope of 3D printing for domestic applications. The project was submitted in partial fulfillment of requirements for a Bachelor of Science degree in Aeronautical & Industrial Technology at Tennessee State University. The abstract indicates that the research aims to investigate the prospective role of 3D printers in the kitchen and better understand non-technical persons' views on 3D printing. Qualitative research methods will be used to gain insight into motivations and perceptions regarding residential 3D printing.
Industrial Land Intensification-What is it and how can it be measured-Gilmore...Ryan J. Gilmore
This document presents an academic research practicum exploring definitions and measures of industrial land intensification. It was submitted in partial fulfillment of a Master's degree in city planning. The research was motivated by the Metro Vancouver region's limited land supply and increasing pressure to convert industrial lands to other uses. The practicum developed a prototype analytical tool based on sustainability assessment models to define and measure intensification. Through stakeholder interviews, the tool was refined to better inform industrial intensification policies needed to make more efficient use of existing industrial lands in the region.
Quality &Amp; Risk Management In Construction IndustryMichelle Madero
This document discusses quality and risk management in the construction industry. It provides an overview of key concepts like quality management, quality assurance, quality control, and total quality management. It also discusses risk management best practices and how to assess project risks. The goal is to help construction firms improve project quality and manage risks to build competitiveness and support business objectives.
This dissertation investigates the barriers to entry and benefits of 3D concrete printing (3DCP) in the architecture, engineering, and construction (AEC) industry. The document provides background on innovations in the AEC industry and compares it to more innovative industries. It also reviews research on 3DCP technologies and their potential benefits and barriers. The author conducted interviews with industry professionals to understand how a radical innovation like 3DCP could be introduced, the barriers it may face, what framework is needed for adoption, and where it may find application in the AEC industry. The dissertation aims to provide insight into how 3DCP could be adopted to help close the gap between design and construction.
This document provides an introduction to a study analyzing the effectiveness of resource management strategies used by contractors during the implementation phase of construction projects in Harare, Zimbabwe. It discusses the importance of effective resource management in construction projects given the finite resources and complex nature of projects. Key resources include money, materials, manpower, and machinery. Common resource management techniques mentioned are critical path method (CPM) and resource leveling, which aim to efficiently schedule and allocate limited resources. The study aims to evaluate the resource management strategies used by contractors and their effectiveness in the local context.
Rapid manufacturing is more than a novel method of production; rather, it represents a paradigm shift which will impact the very nature of production and consumption. The ability to quickly manufacture limited quantities of highly individualized or geometrically optimized products locally is a revolutionary prospect which challenges the fundamental principles of economies of scale, specialization, mass production, and outsourcing which have largely defined the manufacturing industry since the industrial revolution.
Many have speculated that rapid manufacturing will enable a manufacturing renaissance in high wage economies by reducing labor and assembly costs. Others declare rapid manufacturing to be the next industrial revolution. While such claims are common, there has been no attempt to quantify the potential impact of rapid manufacturing upon the global economy. This study will evaluate rapid manufacturing as a disruptive technology, identify which products will be most likely impacted by the uptake of additive fabrication, and quantify the potential impact widespread adoption of rapid manufacturing may have upon global trade.
Project Template Sample Kerala University MBAAnujith KR
This document is a project report submitted by a student to partial fulfillment of the requirements for a Master's degree. It examines the impact of e-procurement on purchasing indirect goods for a company. The report will include a literature review on e-procurement, data collection and analysis on the company's traditional procurement vs e-procurement, results and discussions. The objective is to understand why e-procurement has not succeeded as expected for indirect purchases and measure its cost-effectiveness for the company.
Application of terrestrial 3D laser scanning in building information modellin...Martin Ma
The document discusses the application of terrestrial 3D laser scanning and building information modeling (BIM) technology in the construction industry. It analyzes the working principles and methods of laser scanning, including static and kinematic scanning. It also discusses how laser scanning and BIM can minimize limitations through techniques like noise filtering, image matching, and automated recognition of 3D models. Beneficial outcomes of the technologies include sharing scanning data, predicting trends, and identifying unstable structures through colorization. The document concludes the technologies can dramatically reduce resources and costs compared to traditional methods.
Guiding Principles for Enterprise "Bring Your Own Device" (BYOD) InitiativesHelena Sefcovicova
This document provides a literature review on Bring Your Own Device (BYOD) initiatives within organizations. It begins by defining IT consumerization and tracing its evolution, driven by factors like the rise of cloud computing and mobile devices. Surveys find BYOD programs for smartphones and tablets have been most widely implemented. Key adoption drivers include improving employee productivity and enabling mobile workforces. Organizations typically measure BYOD's impact on expenses like software licensing fees and device reimbursements. The review also examines implications for IT departments, as they must adapt to supporting uncontrolled consumer technologies on corporate networks. Overall, the literature establishes the context around BYOD and identifies common benefits, challenges, practices and considerations for implementing BYOD programs.
A TECHNICAL REPORT ON STUDENTS’ INDUSTRIAL WORK EXPERIENCE SCHEME (SIWES) UND...Michael Agwulonu
This technical report encapsulates my four-month attachment experience with BOA Construction Company, a civil engineering consultancy firm. During this period, I delved into the practical application of civil engineering principles, transitioning from theoretical knowledge to hands-on structural design. I also acquired essential skills in manual design calculations, and participated in design, modelling and detailing of various residential and commercial projects. I also acquired knowledge in the steps, activities and processes involved in the actual execution of a project, and participated in many decision-making meetings in the course of construction, which helped me, enhance my mental ability and gave me insight to real-life problem-solving scenario. I was able to have practical knowledge in cost estimation and cost minimization in the course of construction. I obtained a practical knowledge of project supervision and management. The report outlines my extensive exposure to structural design, covering reinforced concrete and steel structures, my introduction to various software tools for structural analysis and my experience on site, as well as the challenges I encountered during the period of my training.
Innovation in the Age of Global Collaboration - CrowdsourcingSaadick Dhansay
The rapid development of new technologies has given rise to new forms of collaboration. Organisations are able to collaborate on a global scale with individuals around the world, in order to conduct R&D activities as a result of Web 2.0 tools and technologies. This study focuses on three areas relating to global collaboration (crowdsourcing); people, processes and technology.
The purpose of this study is to understand the motivational factors of people that partake in global collaboration (crowdsourcing), the change of process with regard to bringing to new products and services to the market and how technology has changed the way organisations collaborate to achieve this. The research was conducted in the form of case studies to analyse how products were brought to the market through the use of global collaboration.
This thesis submitted by Kristian Juel examines the development of an interactive framework for new product development. The document includes an abstract, table of contents, and 5 chapters that discuss literature on new product development, the case study research methodology used, case study observations of 7 companies, a proposed risk-based interactive new product development model, and conclusions. The thesis was submitted in partial fulfillment of a Bachelor of Engineering degree, with the goal of developing a model to help companies improve success in new product development.
Why Do I Need To Write My Essays Press Release PGina Brown
The document discusses how children in the 19th century often faced poverty and lived in urban slums. Progressive reformers focused on addressing the problems faced by these children. Their goals were to change perceptions of childhood and promote the proper treatment of children. Reformers advocated for better diets and hygiene for children to improve health outcomes and reduce infant mortality rates.
Top 100 Extended Essay Topics By Extended EssayGina Brown
This document provides instructions for seeking writing help from HelpWriting.net. It outlines a 5-step process: 1) Create an account, 2) Complete an order form with instructions and deadline, 3) Review writer bids and choose one, 4) Review the completed paper and authorize payment, 5) Request revisions until satisfied. It notes the site uses a bidding system and guarantees original, high-quality content or a full refund.
More Related Content
Similar to AN ANALYSIS INTO THE EFFECTIVENESS OF CONSTRUCTION PRODUCTIVITY MEASUREMENT ON ZIMBABWEAN PROJECTS
An investigation into the critical factors involved in developing a Knowledge...Gowri Shankar
This document is the final report submitted by Gnanamoorthy Gowri Shankar for the course BN89 Master in Project Management at Queensland University of Technology. The report investigates the critical factors involved in developing a knowledge management system in project-based manufacturing industries, using the automobile components manufacturing industry as a case study. The report includes an introduction outlining the problem statement, objectives and approach. It also includes a literature review, research methodology, results and discussion, conclusion, and recommendations. The aim is to identify issues influencing knowledge management implementation and provide recommendations to improve knowledge management practices in the industry.
The document discusses the impact of developing enterprise architecture services on selecting IT projects at Philips Lighting. It first investigates the challenges faced by Philips Lighting in ensuring business demands are translated into IT projects and allocated budgets. Then, a new portfolio management methodology comprising enterprise architecture services is proposed, designed, developed and deployed to improve the process. Finally, the new model is validated to determine how well it overcomes problems in the previous method.
FACTORS AFFECTING ROAD CONSTRUCTION PROJECT PERFORMANCE: A CASE STUDY OF JIMM...abdiakib
This document is a research proposal submitted by Abdo Akib kelifa to Jimma University in Ethiopia to study factors affecting road construction project performance in Jimma zone. The proposal includes an introduction outlining the background and importance of studying project performance. It states the objectives are to investigate factors affecting project management performance in road construction. It will use both primary and secondary data collected through questionnaires from 310 respondents including owners, consultants, contractors and engineers. Statistical analysis will be done using SPSS software. The proposal provides details on the research methodology, time schedule, and budget.
The document is a stage 2 report for an individual project that aims to encourage STEM engagement within extra-curricular groups. It provides an overview of the conceptual design phase where concepts were generated, evaluated, and refined. It also describes initial modeling and testing. The detailed design phase is discussed where embodiment design questions were considered and prototypes were developed and tested. The report outlines the progress made against the project methodology and provides documentation to support the design process.
This document summarizes a research paper on design and build (D&B) as a procurement strategy. It begins with an abstract that states building procurement strategies are important for project success if the appropriate strategy is chosen. It then outlines the research objectives of investigating various procurement strategies, determining the relationship between time, cost and quality, and showcasing D&B's advantages. A literature review and case study of a public project were conducted. Survey results from construction professionals found D&B is preferred for projects under £50 million as it allows projects to meet time and cost goals while meeting client requirements. In conclusion, the research found D&B is a preferred strategy for both small and large private and public projects when certain factors are
derrick ampiire intern report with ozone group ltdDerrick Ampiire
This document is an industrial training report submitted by Ampire Derrick detailing their work with Ozone Group Ltd on the construction of a shopping mall in Mbarara, Uganda from May to August 2014. The report provides background on the project and company, describes the trainee's involvement in excavation, formwork, surveying, and steel fixing activities. It also outlines the site layout, management structure, health and safety practices, and materials used in the construction of the shopping mall.
This document provides a 9989-word dissertation submitted in partial fulfillment of a Master of Science in Major Programme Management. The dissertation explores creating a framework to govern infrastructure projects procured without necessary studies, which can cause cost overruns and delays. It analyzes data from four major projects in Brazil's 2014 World Cup program and a questionnaire of Brazilian government project managers. The goal is to determine if adopting an agile approach with early stakeholder involvement can reduce risks and uncertainties for projects procured without full construction designs. The framework is based on literature about project overruns and governance encouraging stakeholder involvement and benefits delivery in smaller batches like agile methods.
INGENUITY IN SOIL REINFORCEMENT METHODS AGAINST SCOUR FAILUREEdison Mugoya
GEOTECHNICAL ENGINEERING: INGENUITY IN SOIL
REINFORCEMENT METHODS AGAINST SCOUR FAILURE
is a study in geotechnical engineering regarding the scour failure at bridge abutments. its a methodology used to decrease it's effects and prolong the life cycle of bridge piers
This document provides an abstract and table of contents for a research project on the scope of 3D printing for domestic applications. The project was submitted in partial fulfillment of requirements for a Bachelor of Science degree in Aeronautical & Industrial Technology at Tennessee State University. The abstract indicates that the research aims to investigate the prospective role of 3D printers in the kitchen and better understand non-technical persons' views on 3D printing. Qualitative research methods will be used to gain insight into motivations and perceptions regarding residential 3D printing.
Industrial Land Intensification-What is it and how can it be measured-Gilmore...Ryan J. Gilmore
This document presents an academic research practicum exploring definitions and measures of industrial land intensification. It was submitted in partial fulfillment of a Master's degree in city planning. The research was motivated by the Metro Vancouver region's limited land supply and increasing pressure to convert industrial lands to other uses. The practicum developed a prototype analytical tool based on sustainability assessment models to define and measure intensification. Through stakeholder interviews, the tool was refined to better inform industrial intensification policies needed to make more efficient use of existing industrial lands in the region.
Quality &Amp; Risk Management In Construction IndustryMichelle Madero
This document discusses quality and risk management in the construction industry. It provides an overview of key concepts like quality management, quality assurance, quality control, and total quality management. It also discusses risk management best practices and how to assess project risks. The goal is to help construction firms improve project quality and manage risks to build competitiveness and support business objectives.
This dissertation investigates the barriers to entry and benefits of 3D concrete printing (3DCP) in the architecture, engineering, and construction (AEC) industry. The document provides background on innovations in the AEC industry and compares it to more innovative industries. It also reviews research on 3DCP technologies and their potential benefits and barriers. The author conducted interviews with industry professionals to understand how a radical innovation like 3DCP could be introduced, the barriers it may face, what framework is needed for adoption, and where it may find application in the AEC industry. The dissertation aims to provide insight into how 3DCP could be adopted to help close the gap between design and construction.
This document provides an introduction to a study analyzing the effectiveness of resource management strategies used by contractors during the implementation phase of construction projects in Harare, Zimbabwe. It discusses the importance of effective resource management in construction projects given the finite resources and complex nature of projects. Key resources include money, materials, manpower, and machinery. Common resource management techniques mentioned are critical path method (CPM) and resource leveling, which aim to efficiently schedule and allocate limited resources. The study aims to evaluate the resource management strategies used by contractors and their effectiveness in the local context.
Rapid manufacturing is more than a novel method of production; rather, it represents a paradigm shift which will impact the very nature of production and consumption. The ability to quickly manufacture limited quantities of highly individualized or geometrically optimized products locally is a revolutionary prospect which challenges the fundamental principles of economies of scale, specialization, mass production, and outsourcing which have largely defined the manufacturing industry since the industrial revolution.
Many have speculated that rapid manufacturing will enable a manufacturing renaissance in high wage economies by reducing labor and assembly costs. Others declare rapid manufacturing to be the next industrial revolution. While such claims are common, there has been no attempt to quantify the potential impact of rapid manufacturing upon the global economy. This study will evaluate rapid manufacturing as a disruptive technology, identify which products will be most likely impacted by the uptake of additive fabrication, and quantify the potential impact widespread adoption of rapid manufacturing may have upon global trade.
Project Template Sample Kerala University MBAAnujith KR
This document is a project report submitted by a student to partial fulfillment of the requirements for a Master's degree. It examines the impact of e-procurement on purchasing indirect goods for a company. The report will include a literature review on e-procurement, data collection and analysis on the company's traditional procurement vs e-procurement, results and discussions. The objective is to understand why e-procurement has not succeeded as expected for indirect purchases and measure its cost-effectiveness for the company.
Application of terrestrial 3D laser scanning in building information modellin...Martin Ma
The document discusses the application of terrestrial 3D laser scanning and building information modeling (BIM) technology in the construction industry. It analyzes the working principles and methods of laser scanning, including static and kinematic scanning. It also discusses how laser scanning and BIM can minimize limitations through techniques like noise filtering, image matching, and automated recognition of 3D models. Beneficial outcomes of the technologies include sharing scanning data, predicting trends, and identifying unstable structures through colorization. The document concludes the technologies can dramatically reduce resources and costs compared to traditional methods.
Guiding Principles for Enterprise "Bring Your Own Device" (BYOD) InitiativesHelena Sefcovicova
This document provides a literature review on Bring Your Own Device (BYOD) initiatives within organizations. It begins by defining IT consumerization and tracing its evolution, driven by factors like the rise of cloud computing and mobile devices. Surveys find BYOD programs for smartphones and tablets have been most widely implemented. Key adoption drivers include improving employee productivity and enabling mobile workforces. Organizations typically measure BYOD's impact on expenses like software licensing fees and device reimbursements. The review also examines implications for IT departments, as they must adapt to supporting uncontrolled consumer technologies on corporate networks. Overall, the literature establishes the context around BYOD and identifies common benefits, challenges, practices and considerations for implementing BYOD programs.
A TECHNICAL REPORT ON STUDENTS’ INDUSTRIAL WORK EXPERIENCE SCHEME (SIWES) UND...Michael Agwulonu
This technical report encapsulates my four-month attachment experience with BOA Construction Company, a civil engineering consultancy firm. During this period, I delved into the practical application of civil engineering principles, transitioning from theoretical knowledge to hands-on structural design. I also acquired essential skills in manual design calculations, and participated in design, modelling and detailing of various residential and commercial projects. I also acquired knowledge in the steps, activities and processes involved in the actual execution of a project, and participated in many decision-making meetings in the course of construction, which helped me, enhance my mental ability and gave me insight to real-life problem-solving scenario. I was able to have practical knowledge in cost estimation and cost minimization in the course of construction. I obtained a practical knowledge of project supervision and management. The report outlines my extensive exposure to structural design, covering reinforced concrete and steel structures, my introduction to various software tools for structural analysis and my experience on site, as well as the challenges I encountered during the period of my training.
Innovation in the Age of Global Collaboration - CrowdsourcingSaadick Dhansay
The rapid development of new technologies has given rise to new forms of collaboration. Organisations are able to collaborate on a global scale with individuals around the world, in order to conduct R&D activities as a result of Web 2.0 tools and technologies. This study focuses on three areas relating to global collaboration (crowdsourcing); people, processes and technology.
The purpose of this study is to understand the motivational factors of people that partake in global collaboration (crowdsourcing), the change of process with regard to bringing to new products and services to the market and how technology has changed the way organisations collaborate to achieve this. The research was conducted in the form of case studies to analyse how products were brought to the market through the use of global collaboration.
This thesis submitted by Kristian Juel examines the development of an interactive framework for new product development. The document includes an abstract, table of contents, and 5 chapters that discuss literature on new product development, the case study research methodology used, case study observations of 7 companies, a proposed risk-based interactive new product development model, and conclusions. The thesis was submitted in partial fulfillment of a Bachelor of Engineering degree, with the goal of developing a model to help companies improve success in new product development.
Similar to AN ANALYSIS INTO THE EFFECTIVENESS OF CONSTRUCTION PRODUCTIVITY MEASUREMENT ON ZIMBABWEAN PROJECTS (20)
Why Do I Need To Write My Essays Press Release PGina Brown
The document discusses how children in the 19th century often faced poverty and lived in urban slums. Progressive reformers focused on addressing the problems faced by these children. Their goals were to change perceptions of childhood and promote the proper treatment of children. Reformers advocated for better diets and hygiene for children to improve health outcomes and reduce infant mortality rates.
Top 100 Extended Essay Topics By Extended EssayGina Brown
This document provides instructions for seeking writing help from HelpWriting.net. It outlines a 5-step process: 1) Create an account, 2) Complete an order form with instructions and deadline, 3) Review writer bids and choose one, 4) Review the completed paper and authorize payment, 5) Request revisions until satisfied. It notes the site uses a bidding system and guarantees original, high-quality content or a full refund.
College Essay Career Goals - Educational And CareerGina Brown
1. The document discusses Kant's ethical theory of deontology, which focuses on duties and obligations rather than consequences of actions.
2. Kant's Categorical Imperative states that people should only act in a way that they can universalize and apply to everyone. This provides a test to determine if an action is morally right.
3. Lying to get out of a problematic situation is used as an example - if lying could become a universal rule without contradiction, then it would be morally permissible under Kant's theory. However, universalizing the rule of lying generally leads to contradictions.
The Value Of Education - Assignment PointGina Brown
The document discusses conducting a feasibility study to analyze alternative solutions to a problem and recommend the best option. A feasibility study examines market issues, technical and organizational requirements, and financial overview to determine if a new system can solve the problem more efficiently than the current one. The results of the feasibility study are then used to inform the decision on whether to implement the new system.
Thematic Photo Essay Examples Sitedoct.OrgGina Brown
The document discusses how language can influence the process of obtaining informed consent from patients or research participants. Issues of comprehension, fluency, and perceived power dynamics are important to consider. The person obtaining consent must be able to clearly explain the study in a way that promotes understanding. Informed consent requires voluntary participation and full comprehension of risks and goals.
Scholarship Essay Compare And Contrast Essay IntroduGina Brown
The document discusses the process for obtaining writing assistance from HelpWriting.net. It involves 5 steps: 1) Create an account with a password and email. 2) Complete an order form providing instructions, sources, and deadline. 3) Review bids from writers and select one based on qualifications. 4) Review the completed paper and authorize payment if satisfied. 5) Request revisions until fully satisfied, with a refund offered for plagiarized work. The service aims to provide original, high-quality content through a bidding system and revision process.
College Essay Examples Of Essay About LifeGina Brown
This summary provides an overview of the document in 3 sentences:
The document discusses steps to request a paper writing service through HelpWriting.net, including creating an account, providing instructions for the paper in an order form, and selecting a writer to complete the work. The bidding process and paper revisions are described. The service aims to provide original, high-quality content and offers refunds if papers are plagiarized.
Writing The Thesis Statement Write An A Research Paper - How To WriteGina Brown
The document discusses two female artists from different eras - Sofonisba Anguissola from the Renaissance period and Artemisia Gentileschi from the Baroque period. It notes some similarities in their lives and careers, such as both losing their mothers at a young age and traveling between various cities. It also discusses influences on their artistic styles, with Gentileschi being inspired by Caravaggio's tenebrism technique. There are suggested connections between the artists through other famous figures of their time as well.
Sample Persuasive Speech Powerpoint Defining A PeGina Brown
The document provides background information on the establishment of Liberia. It discusses how Liberia was founded in 1816 by the American Colonization Society to resettle freed American slaves in Africa. The first settlers established the settlement of Monrovia in 1824. Over time, conflicts arose between the settlers and the American society. In the mid-20th century, Liberia pursued economic development through foreign investment in iron ore mining, while indigenous groups were still denied full political rights.
Winter Writing Paper Free Worksheets. Online assignment writing service.Gina Brown
1. The document provides instructions for requesting and obtaining writing assistance from HelpWriting.net. It outlines a 5-step process: creating an account, submitting a request form, reviewing writer bids and selecting one, revising the paper if needed, and requesting revisions.
2. The site uses a bidding system where writers submit bids to complete writing requests, and clients can choose a writer based on qualifications, history, and feedback. The site promises original, high-quality work or a full refund.
3. The process allows clients to obtain writing assistance by having writers complete their assignments according to the provided instructions and deadline. Clients can also request revisions to ensure satisfaction.
Formal Essay What It Is And How To Write ItGina Brown
The document provides instructions for submitting an assignment request to the website HelpWriting.net. It outlines a 5-step process: 1) Create an account with a password and email. 2) Complete a 10-minute order form providing instructions, sources, and deadline. 3) Review bids from writers and choose one. 4) Review the completed paper and authorize payment. 5) Request revisions until satisfied with the work. The purpose is to help students get high-quality original assignments written for them through this online service.
Funny College Essay - College Homework Help AGina Brown
The document provides instructions for requesting and completing an assignment writing request through the HelpWriting.net website. It outlines a 5-step process: 1) Create an account with a password and email; 2) Complete a 10-minute order form with instructions, sources, and deadline; 3) Review bids from writers and choose one; 4) Review the completed paper and authorize payment; 5) Request revisions until satisfied. It emphasizes the site's commitment to original, high-quality work and full refunds for plagiarized content.
Hoja Para Escribir Texto - SEONegativo.ComGina Brown
This document summarizes the key steps to request writing assistance from the website HelpWriting.net:
1. Create an account with a password and valid email.
2. Complete a 10-minute order form providing instructions, sources, deadline, and attaching a sample work if wanting the writer to mimic your style.
3. Review bids from writers and choose one based on qualifications, history, and feedback, then pay a deposit to start the assignment.
4. Ensure the completed paper meets expectations, and if so, authorize full payment to the writer. Revisions are free.
Tips For Writing A Thesis Introduction - Writefiction58Gina Brown
The document provides tips for writing a thesis or requesting writing help from HelpWriting.net. It outlines a 5 step process: 1) Create an account, 2) Complete an order form providing instructions, sources and deadline, 3) Review bids from writers and choose one, 4) Review the completed paper and authorize payment, 5) Request revisions to ensure satisfaction and get a refund if plagiarized. The service aims to provide original, high-quality content meeting customers' needs.
Research Paper Outline 8Th Grade - How To Write A ReGina Brown
1. The document outlines 5 steps for requesting an assignment writing service from HelpWriting.net, including creating an account, submitting a request form, reviewing bids from writers, choosing a writer, and authorizing payment upon approval of the completed work.
2. Users can request revisions to ensure satisfaction with the completed assignment. HelpWriting.net promises original, high-quality content and refunds for plagiarized work.
3. The document provides instructions for using HelpWriting.net's assignment writing service.
92 Inspiration Forms Of Narrative Stories In GraphiGina Brown
The document provides instructions for requesting writing assistance from HelpWriting.net. It outlines a 5-step process: 1) Create an account with a password and email; 2) Complete a 10-minute order form with instructions, sources, and deadline; 3) Review bids from writers and select one; 4) Review the completed paper and authorize payment; 5) Request revisions until satisfied, with a refund option for plagiarism. The service aims to fully meet customer needs through this process.
001 Essay About Myself Thatsnotus. Online assignment writing service.Gina Brown
The document discusses how DNA evidence can be a powerful forensic tool for identifying criminals. DNA fingerprinting was first used in court in 1987, and even a small sample of hair, skin, or saliva contains enough DNA to identify a unique individual through analysis of short tandem repeats (STRs) in their DNA. Microbes like bacteria are also discussed, noting that while some can cause illness, others can be engineered to produce medicines through transgenic bacteria.
What Does A Research Paper Look Like For A Science FairGina Brown
This document discusses the importance and impact of English in Kenya. While English serves as an important lingua franca and was adopted post-colonization, its use has also divided society between elites who are proficient in English versus commoners who have low English comprehension. There are concerns that political elites use English selectively to maintain power over large segments of the population who do not fully understand the language.
Apsolventska Godina I Studentska Prava RCroatiaGina Brown
The document discusses the steps to get writing help from the website HelpWriting.net. It outlines registering for an account, completing an order form with instructions and deadline, reviewing writer bids and choosing one, placing a deposit to start the work, reviewing and approving the completed paper, and having the option to request revisions. The website promises original, high-quality content and refunds for plagiarized work.
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UPRAHUL
This Dissertation explores the particular circumstances of Mirzapur, a region located in the
core of India. Mirzapur, with its varied terrains and abundant biodiversity, offers an optimal
environment for investigating the changes in vegetation cover dynamics. Our study utilizes
advanced technologies such as GIS (Geographic Information Systems) and Remote sensing to
analyze the transformations that have taken place over the course of a decade.
The complex relationship between human activities and the environment has been the focus
of extensive research and worry. As the global community grapples with swift urbanization,
population expansion, and economic progress, the effects on natural ecosystems are becoming
more evident. A crucial element of this impact is the alteration of vegetation cover, which plays a
significant role in maintaining the ecological equilibrium of our planet.Land serves as the foundation for all human activities and provides the necessary materials for
these activities. As the most crucial natural resource, its utilization by humans results in different
'Land uses,' which are determined by both human activities and the physical characteristics of the
land.
The utilization of land is impacted by human needs and environmental factors. In countries
like India, rapid population growth and the emphasis on extensive resource exploitation can lead
to significant land degradation, adversely affecting the region's land cover.
Therefore, human intervention has significantly influenced land use patterns over many
centuries, evolving its structure over time and space. In the present era, these changes have
accelerated due to factors such as agriculture and urbanization. Information regarding land use and
cover is essential for various planning and management tasks related to the Earth's surface,
providing crucial environmental data for scientific, resource management, policy purposes, and
diverse human activities.
Accurate understanding of land use and cover is imperative for the development planning
of any area. Consequently, a wide range of professionals, including earth system scientists, land
and water managers, and urban planners, are interested in obtaining data on land use and cover
changes, conversion trends, and other related patterns. The spatial dimensions of land use and
cover support policymakers and scientists in making well-informed decisions, as alterations in
these patterns indicate shifts in economic and social conditions. Monitoring such changes with the
help of Advanced technologies like Remote Sensing and Geographic Information Systems is
crucial for coordinated efforts across different administrative levels. Advanced technologies like
Remote Sensing and Geographic Information Systems
9
Changes in vegetation cover refer to variations in the distribution, composition, and overall
structure of plant communities across different temporal and spatial scales. These changes can
occur natural.
A workshop hosted by the South African Journal of Science aimed at postgraduate students and early career researchers with little or no experience in writing and publishing journal articles.
বাংলাদেশের অর্থনৈতিক সমীক্ষা ২০২৪ [Bangladesh Economic Review 2024 Bangla.pdf] কম্পিউটার , ট্যাব ও স্মার্ট ফোন ভার্সন সহ সম্পূর্ণ বাংলা ই-বুক বা pdf বই " সুচিপত্র ...বুকমার্ক মেনু 🔖 ও হাইপার লিংক মেনু 📝👆 যুক্ত ..
আমাদের সবার জন্য খুব খুব গুরুত্বপূর্ণ একটি বই ..বিসিএস, ব্যাংক, ইউনিভার্সিটি ভর্তি ও যে কোন প্রতিযোগিতা মূলক পরীক্ষার জন্য এর খুব ইম্পরট্যান্ট একটি বিষয় ...তাছাড়া বাংলাদেশের সাম্প্রতিক যে কোন ডাটা বা তথ্য এই বইতে পাবেন ...
তাই একজন নাগরিক হিসাবে এই তথ্য গুলো আপনার জানা প্রয়োজন ...।
বিসিএস ও ব্যাংক এর লিখিত পরীক্ষা ...+এছাড়া মাধ্যমিক ও উচ্চমাধ্যমিকের স্টুডেন্টদের জন্য অনেক কাজে আসবে ...
Chapter wise All Notes of First year Basic Civil Engineering.pptxDenish Jangid
Chapter wise All Notes of First year Basic Civil Engineering
Syllabus
Chapter-1
Introduction to objective, scope and outcome the subject
Chapter 2
Introduction: Scope and Specialization of Civil Engineering, Role of civil Engineer in Society, Impact of infrastructural development on economy of country.
Chapter 3
Surveying: Object Principles & Types of Surveying; Site Plans, Plans & Maps; Scales & Unit of different Measurements.
Linear Measurements: Instruments used. Linear Measurement by Tape, Ranging out Survey Lines and overcoming Obstructions; Measurements on sloping ground; Tape corrections, conventional symbols. Angular Measurements: Instruments used; Introduction to Compass Surveying, Bearings and Longitude & Latitude of a Line, Introduction to total station.
Levelling: Instrument used Object of levelling, Methods of levelling in brief, and Contour maps.
Chapter 4
Buildings: Selection of site for Buildings, Layout of Building Plan, Types of buildings, Plinth area, carpet area, floor space index, Introduction to building byelaws, concept of sun light & ventilation. Components of Buildings & their functions, Basic concept of R.C.C., Introduction to types of foundation
Chapter 5
Transportation: Introduction to Transportation Engineering; Traffic and Road Safety: Types and Characteristics of Various Modes of Transportation; Various Road Traffic Signs, Causes of Accidents and Road Safety Measures.
Chapter 6
Environmental Engineering: Environmental Pollution, Environmental Acts and Regulations, Functional Concepts of Ecology, Basics of Species, Biodiversity, Ecosystem, Hydrological Cycle; Chemical Cycles: Carbon, Nitrogen & Phosphorus; Energy Flow in Ecosystems.
Water Pollution: Water Quality standards, Introduction to Treatment & Disposal of Waste Water. Reuse and Saving of Water, Rain Water Harvesting. Solid Waste Management: Classification of Solid Waste, Collection, Transportation and Disposal of Solid. Recycling of Solid Waste: Energy Recovery, Sanitary Landfill, On-Site Sanitation. Air & Noise Pollution: Primary and Secondary air pollutants, Harmful effects of Air Pollution, Control of Air Pollution. . Noise Pollution Harmful Effects of noise pollution, control of noise pollution, Global warming & Climate Change, Ozone depletion, Greenhouse effect
Text Books:
1. Palancharmy, Basic Civil Engineering, McGraw Hill publishers.
2. Satheesh Gopi, Basic Civil Engineering, Pearson Publishers.
3. Ketki Rangwala Dalal, Essentials of Civil Engineering, Charotar Publishing House.
4. BCP, Surveying volume 1
How to Build a Module in Odoo 17 Using the Scaffold MethodCeline George
Odoo provides an option for creating a module by using a single line command. By using this command the user can make a whole structure of a module. It is very easy for a beginner to make a module. There is no need to make each file manually. This slide will show how to create a module using the scaffold method.
Leveraging Generative AI to Drive Nonprofit InnovationTechSoup
In this webinar, participants learned how to utilize Generative AI to streamline operations and elevate member engagement. Amazon Web Service experts provided a customer specific use cases and dived into low/no-code tools that are quick and easy to deploy through Amazon Web Service (AWS.)
This slide is special for master students (MIBS & MIFB) in UUM. Also useful for readers who are interested in the topic of contemporary Islamic banking.
Strategies for Effective Upskilling is a presentation by Chinwendu Peace in a Your Skill Boost Masterclass organisation by the Excellence Foundation for South Sudan on 08th and 09th June 2024 from 1 PM to 3 PM on each day.
Main Java[All of the Base Concepts}.docxadhitya5119
This is part 1 of my Java Learning Journey. This Contains Custom methods, classes, constructors, packages, multithreading , try- catch block, finally block and more.
How to Make a Field Mandatory in Odoo 17Celine George
In Odoo, making a field required can be done through both Python code and XML views. When you set the required attribute to True in Python code, it makes the field required across all views where it's used. Conversely, when you set the required attribute in XML views, it makes the field required only in the context of that particular view.
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
AN ANALYSIS INTO THE EFFECTIVENESS OF CONSTRUCTION PRODUCTIVITY MEASUREMENT ON ZIMBABWEAN PROJECTS
1. i |
DECLARATION
The candidate herewith adjudges that the work presented in this Dissertation on “AN ANALYSIS INTO
THE EFFECTIVENESS OF CONSTRUCTION PRODUCTIVITY MEASUREMENT ON
ZIMBABWEAN PROJECTS” for the Bachelor of Quantity Surveying (Honors) degree presented to the
Department of Quantity Surveying in the Faculty of the Built Environment at the National University of
Science and Technology, is that ofthe candidate alone andhas not previouslybeensubmitted,inwholeorpart,
in respect of any other academic award and has not been published in any form by any person except where
duereferenceis given.
Candidate ………………………. …………………….
(GeorgeMwamloweM.) Signature Date
Supervisorormarker ……………………… ……………………
(MrT. Moyo) Signature Date
2. ii |
DEDICATION
I would like to dedicate this dissertation to my Lord and Saviour Jesus Christ, without whom I
would not have made it through this program. A special dedication goes to my parents,
especially my father who has sacrificed his own desires that I may make it through my degree.
To my fiancé who has patiently walked with me through my degree program, offering support at
much needed times. To my extended family who have stood with me financially and
emotionally. Last but not least the academic staff at National University of Science and
Technology for supporting me as well during research for my dissertation.
3. iii |
ACKNOWLEDGEMENTS
The author would like to thank the following persons who provided guidance, information and
valuable time in the preparation of this dissertation:
Mr. T. Moyo my academic supervisor for the immense patience, depth and wisdom that
he offered without charge to help me finish this dissertation
Mr. I. Mambemba, my industrial supervisor, who infused the passion for project
productivity measurement.
Mr. L. Ncube, who helped me make the transition from Architecture to Quantity
Surveying.
Mr. B. Gaule, who stood with me as a research lecturer and went beyond the call of duty
to help me through the most trying academic year of my life.
My fellow classmates who walked with me in the journey to obtaining my degree, with a
special mention to; Munyaradzi Mapfumo, Arthur Chisango, Jonathan Hlabangana,
Aaron Mandizvidza, Devillious Shumba and Meluleki Dlodlo.
4. iv |
ABSTRACT
The issue of Construction projects time and cost overruns has been a major concern worldwide.
Construction productivity measurement has been one of the proposed solutions which most
developed countries have embraced. This productivity measurement has taken three distinct
measurement forms, that is, task level, project level, and at industry level. This research has
focussed mainly on project level productivity because it represents the productivity of the end
products of the industry. The research has been carried out using a mixed method approach as
has been seen from literature studies to be most effective when dealing with this field. The study
area has been Bulawayo and Harare, the main cities of Zimbabwe, random and judgemental
sampling were implemented to collect the data. The findings of this study indicate that labor
productivity measurement is the most widely practiced form of construction productivity
measurement, albeit the industry is still utilizing these methods in a very basic form. The major
hindrance to measurement has been seen to be a lack of management involvement and interest in
the subject. There is industry consensus on the cost and time reducing benefits of construction
productivity measurement however the cost obligations seem to be a deterrent to use of the
system.
5. v |
LIST OF FIGURES
Figure 2.3: Multi factor Productivity measurement methods................................................ 19
Figure 4.1: Response rate per class of contractor.................................................................. 31
Figure 4.2: Experience of respondents in industry................................................................ 32
Figure 4.3: Company experience in industry......................................................................... 32
Figure 4.4: Construction productivity measures utilized on projects.................................... 34
Figure 4.5: Use of construction productivity measurement per class of contractor.............. 35
Figure 4.6: Relative frequency of use of methods................................................................. 36
Figure 4.7: Impact of productivity measurement on KPIs..................................................... 39
6. vi |
LIST OF TABLES
Table 2.1: Relationship between performance, profitability and productivity…................ 10
Table 2.2: Single factor Productivity measurement methods.............................................. 13
Table 2.3: Single factor Productivity measurement methods.............................................. 18
Table 4.1: Severity index analysis of hindrances to productivity measurement.................. 36
Table 4.2: Other benefits of productivity measurement....................................................... 39
7. vii |
ABBREVIATIONS AND ACRONYMS
KPIs.........................................Key Performance Indicators
CIFOZ.....................................Construction Industry Federation of Zimbabwe
MFP..........................................Multifactor productivity
8. viii |
Table of Contents
DECLARATION...........................................................................................................................................i
DEDICATION..............................................................................................................................................ii
ACKNOWLEDGEMENTS.........................................................................................................................iii
ABSTRACT.................................................................................................................................................iv
LIST OF FIGURES ......................................................................................................................................v
LIST OF TABLES.......................................................................................................................................vi
ABBREVIATIONS AND ACRONYMS ...................................................................................................vii
CHAPTER 1: ................................................................................................................................................1
1.0 Introduction.........................................................................................................................................1
1.1 Background.........................................................................................................................................2
1.2 Problem statement...............................................................................................................................4
1.3 Aim .....................................................................................................................................................5
1.4 Research Questions.............................................................................................................................5
1.5 Objectives of the research...................................................................................................................5
1.6 Significance of study...........................................................................................................................5
1.7 Research Outline.................................................................................................................................6
CHAPTER 2: Literature Review ..................................................................................................................8
2.0 Introduction.........................................................................................................................................8
2.1 Construction Productivity Measurement and Performance ................................................................8
2.2 Construction Productivity Measurement Methods............................................................................11
2.2.1 Single Factor Methods ...............................................................................................................12
2.2.2 Multi Factor Methods.................................................................................................................17
2.3 Hindrances to Productivity measurement .........................................................................................18
2.4 Impact of Productivity measurement on Performance......................................................................21
2.5 Summary...........................................................................................................................................22
CHAPTER 3: Methodology........................................................................................................................23
3.0 Introduction.......................................................................................................................................23
3.1 Research Design................................................................................................................................23
3.1.1 Nature and Setting of Study.......................................................................................................23
3.1.2 Area of study..............................................................................................................................24
3.1.3 Target Population.......................................................................................................................24
3.1.4 Sampling frame..........................................................................................................................25
9. ix |
3.1.5 Sample size ................................................................................................................................25
3.2 Sampling Methods ............................................................................................................................25
3.2.1 Random Sampling......................................................................................................................25
3.2.2 Judgmental Sampling.................................................................................................................26
3.3 Research Instruments........................................................................................................................26
3.3.1 Desk research.............................................................................................................................26
3.3.2 Questionnaires............................................................................................................................27
3.3.3 Case studies................................................................................................................................27
3.4 Data Presentation and Analysis Plan ................................................................................................28
3.6 Summary...........................................................................................................................................29
CHAPTER 4: Data Presentation and Analysis ...........................................................................................30
4.0 Introduction.......................................................................................................................................30
4.1 General Data Report .........................................................................................................................30
4.2 Productivity measurement in the Zimbabwean industry...................................................................32
4.2.1 Degree of Utilization..................................................................................................................32
4.2.2 Methods Utilized........................................................................................................................35
4.2.3 Hindrances to Productivity Measurement..................................................................................36
4.3 Impact of Productivity Measurement on Performance .....................................................................38
4.4 Case studies.......................................................................................................................................40
4.4.1 Case Study A: Renovation of Flats............................................................................................40
4.4.2 Case Study B: New Residence for University Students.............................................................41
4.5 Summary.....................................................................................................................................43
CHAPTER 5: Recommendations and Conclusions....................................................................................45
5.0 Introduction.......................................................................................................................................45
5.1 Project level construction productivity measurement methods ........................................................45
5.2 Hindrances to productivity measurement..........................................................................................45
5.3 Impact of Construction productivity measurement on project performance.....................................46
5.4 Recommendations to Industry ..........................................................................................................47
5.5 Areas of future study.........................................................................................................................48
5.6 Summary...........................................................................................................................................48
REFERENCES: ..........................................................................................................................................49
APPENDICES ............................................................................................................................................53
QUESTIONNAIRE ................................................................................................................................55
10. 1 |
CHAPTER 1:
1.0 Introduction
The term productivity in the Construction Industry has over the past decades taken many
definitions. According to Bernolak (1997) productivity means “how much and how good we produce from
the resources used.Simplyput productivityis the ratio ofinput to output. Zakieh (2010) says that productivityis
theratio oftotal output tototal timeinput.Thereforeaccordingtothesedefinitions werealisethattheproducts in
construction are the projects themselves. These are the tangible products of all the task level efforts and the
constituents of the national productivity measures. The importance of productivity growth to an individual
enterprise, an industry or an economy is something on which most economists would agree (Lowe,
1987).Productivity measurement is therefore those systems put in place to monitor and quantify the amount of
productivitygeneratedwithinapredeterminedunit oftime.
Bowen, (1984), states that productivity performance is the best indicator of economic vitality. We know for a
start the three major inputs that we find in the construction industry, i.e. labour, plant and material so then a
priori (before the fact) we can say that these are what we expect to be encountered as one side of the
measurement that we expect to be seeing in the industry. These inputs are labour, plant and material. It is firmly
believed that going back to the basics of measuring productivity at the project level would be necessary in
facilitating improvements. This is because the construction industry is largely project-based (Chan and Kaka,
2007).Whilstthemeasuringofproductivityis usuallyclassifiedintothreebroadstratawhichare; Nationallevel,
project level and task level, for this research we will lookat that one level of productivitymeasurement which is
attheprojectlevel(Huanget.al,2009)
Oftentimes the concept of productivity is mistaken with profitability or performance (Chan and Kaka, 2007)
howeverperformanceinconstructionreferstoavarietyofvariables associatedwithsuccessusuallybytheclient
11. 2 |
and these may include cost, time and quality. These will then form the basis for valuation of a project’s
performance.Inthisstudyperformancewillmainlyrefertoprojectcostandproject completiontime.
1.1 Background
The centrality of productivity to world competitiveness and prosperity has been a matter of interest since the
beginning of industrialization (Pekuri et. al, 2011). Although there is widespread concern that
productivity is on the decline, there has however been a marked interest in productivity studies in
construction because of the recent prioritization of innovation projects and their expected
impacts on national construction productivity (Goodrum et al., 2011)
The general accepted idiom in this vein is that we cannot improve what we cannot measure efficiently and
accurately. It is expedient for us to have accurate systems of productivitymeasurement for the evaluation of the
state of productivity and hence vitality of the said projects for the improvement of productivity and of project
viability. However, the systems used to measure productivity have been a major dispute area. This
has been largely due to the multiple and case specific definitions for the term productivity itself.
Following Zakieh (2010) definition as previously referred to, Chye (1996) also agrees that the
measurement of productivity on projects should be done holistically instead of the traditional
way of only looking at it from the labour point of view.It follows that, in order to increase
productivity, the system must either produce more or better goods from the same resources, or
the same goods from fewer resources.
Ameh and Osegbo (2011) observed that the problem in Construction however has been the
persistent cost and time overruns (implying greater resource usage to achieve either equal or less
product value). Yang et.al (2010) categorically list lost productivity or loss of productivity, as
12. 3 |
one essential delay cause, and that it is a resultant of a contractor accomplishing works at less
than planned rate ofproduction.It means therefore that project performance is directly related to
project productivity and these two are dependant variables. Addressing project productivity
therefore should improve on the much decried project performance.
Al-Momani (2000) conducted a survey on 130 public projects in Jordan and found delays
occurred in 106 (82%). Frimpong et al. (2003) observed that 33(70%) out of 47 projects in
Ghana were delayed. Ogunlana et al.’s (1996) study in Thailand and Kaming et al.’s (1997)
study in Indonesia found that the blame for most project delays were laid on the contractor.
Abd.Majid and McCaffer (1998) found that 50% of the delays to construction projects can be
categorized as non-excusable delays, for which the contractors were responsible. It is this
suboptimum output (delivery of projects), that we want to investigate. Time overrun affects the
project owners, contractors and other project participants. Project owners may be affected
through lost benefits that could have accrued from the completed facility, while contractors may
have to spend more on labour and plant, pay penalties as per the contract or even lose other
profitable contracts because resources for the next job are tied up on delayed projects.
Melton (2008) argues that any resource needs to be robustly managed in order to ensure that the
required level of performance is achieved (Cited by Chigara and Mangore 2012) We can also
deduce then that mismanagement of resources is a rampant source of the lack of productivity in
the construction industry and for it to be curbed there is need to assess the levels of productivity
measurement for the different resources going into the projects.
13. 4 |
1.2 Problem statement
In the Auditor General’s report to parliament on the management of construction projects in
Zimbabwe (2009), it was stated that the delays in project completion were an attributing factor to
perpetual cost overruns on construction projects in Zimbabwe. Among the reasons cited for the
poor project delivery rate, project monitoring was cited as a major factor. This then implies that
inadequate monitoring is somehow linked to decreased productivity which then leads to delayed
project delivery or failure. Generally in the construction industry productivity loss is seen as one
of the greatest and most severe problems (Gundecha, 2012). Kasimu(2012) states that cost
overruns have become a chronic problem in developing countries like Zimbabwe. Chigara and
Mangore, (2012) also highlight the scarcity of production resources in the construction industry
which in itself warrants a better management of and value reconciliation for their usage on
projects.
It would follow then that in the absence of proper monitoring of resource utilisation during
project delivery, resources are subject to sub-optimum use. The major underlying assertion is
that input productiveness is the major determinant of product cost and delivery time. Although
most contractors benchmark productivity on labour, Pekuri et al., (2011) say that the main
challenge with using labour productivity only is that it will not reveal the effects of productivity
in plant, material and energy input, which are a significant part of project level input variables. In
line with continuous process improvement in the industry it would be of great disadvantage to
not be able to assess the products of construction enterprise which are the projects themselves
and be able to determine whether we are meeting acceptable levels of productivity. As Drucker
(1980) states there is nothing as dangerous to an economy as a decrease in productivities because
it creates inflationary pressure, social conflict and mutual suspicion.
14. 5 |
1.3 Aim
To analyse Construction Productivity Measurement and performance at project level in the Zimbabwean
Construction Industrytoimprovesuccessful project delivery.
1.4 Research Questions
• What are the current methods being employed to measure construction productivityat project level in
theZimbabweanConstruction Industry?
• What is hinderingthemeasuringofproductivityatproject level inZimbabwe’s constructionindustry?
• Howhas constructionproductivitymeasurement impactedperformanceofprojects in Zimbabwe?
1.5 Objectives of the research
• To investigate the different methods of Construction Productivity Measurement at project level being
used in Zimbabwe
• To determine the major hindrances to measuring construction productivity at project level in the
Zimbabweanindustry
• To assess howproductivitymeasurement has impacted onperformance at project level
1.6 Significance of study
Studies done in the U.S. show that construction productivity in the U.S. has been on a steady decline over the
past four decades, running at about half the rate of U.S. non-farm industry (Sawyer, 2005). Studies done by
Warner, (2004) in the “Construction Industry Productivity Survey” show that 53% of construction companies
15. 6 |
surveyed reported that their productivityhas been flat ordecreasing over the past five years. Moreover, 81% of
those surveyed said that they could save over 5% of their annual field labour costs through better management
ofproductivity.This sets precedenceforus toanalyseour veryown Zimbabweanscenario.
A study that was conducted in 1994, which looked at 8,000 projects, showed that only 16% of the projects
could satisfy the following three famous performance criteria: completing projects on time, within the
budgeted cost and maintaining a high standard of quality (Frame, 1997).Productivity study is an economics
fundamental as it addresses the question of why we are engaging in all forms of trade, that is, for obtaining
gain. It deals with the question of how much is resulting from what we input into economic endeavour.
Motwani et al, (1995) state that a company should strive to improve productivity to the point of diminishing
returns. Simply put productivity improvement is an exercise that should be monitored and improved to its
zenith. This studywill find its place in the offices of Contractors who are interested in makingthe most of their
input in projects.
It is also crucial to note that the current industry practices brought to light through this study will bring
awareness of the best methods or the methods producing greatest utility to their proponents and in what way.
Jonsson, (2010) brings to light the shortcomings that come from trying to contain productivity analysis to an
end system tool like profit hence the need to engage in the process analysis if there is to be improvement in the
industry’s productivity. This becomes very crucial then in an industry that is viewed as being one of the most
growth stuntedindustries.
1.7 Research Outline
• Chapter 1- Introductory Chapter: An introduction to the topic, the background of study,
aim and research objectives, and the significance of the research
16. 7 |
• Chapter 2- Literature review: An appraisal of current literature on the subject matter of
the research, with critical analysis on methods suggested vis-a-vis industry validity and
applicability
• Chapter 3- Research Methodology: Data collection methods employed, sample space and
size and research type
• Chapter 4- Data analysis and Presentation: Detailed analysis of collected data, comments
on industry response and presentation in suitable formats
• Chapter 5- Research Findings, Conclusions and Recommendations: Reconciling
objectives to findings and stating the resultant conclusions, also stating the researcher’s
recommendations on the subject matter.
• Appendices
17. 8 |
CHAPTER 2: Literature Review
2.0 Introduction
This chapter aims to carry out a review on the existent literature on construction productivity
measurement at project level. It will detail the methods, hindrances and the impact of
productivity measurement on performance of projects.
2.1 Construction Productivity Measurement and Performance
Construction productivity measurement is an analysis into the ratio of total output versus the
total input of the construction process (Mawdesley and Qambar, 2000). Thomas and Mathews in
Park, (2006) stated that no standardized productivity definition has been established in the
construction industry. From the 1960s, developed countries have grappled with the problem of
productivity in the construction industry with a view to understanding the basic problem of how
to measure it (Sezer and Brochner, 2013). However the definition of productivity itself has had
its fair share in the confusion prevalent in the computation of productivity data. For example
many companies measure profitability and report it as productivity. The difference between these
two is that whereas profitability is the monetary process, productivity is a physical process
(Pekuri et al, 2012). However, productivity is eventually measured in monetary units of output
per level of input (Stainer, 1997). Profitability has been known to change for reasons unrelated to
productivity hence the base measures of productivity remain crucial.
Productivity has also been mistaken with performance. Performance is a composite of all
measures of an organisation’s competitiveness. Tangen (2005) attempted to distinguish
productivity from profitability and performance in a simplified diagram relating the three.
18. 9 |
Figure 2.1 Relationship between performance, profitability and productivity Source: Tangen (2005)
The measurement problem is exacerbated by the fact that the construction industry is composed
of four sectors that differ significantly in; the outputs produced, firm size, and use of technology.
The four sectors, which taken together define the construction industry, are residential,
commercial/institutional, industrial, and infrastructure (Huang et al., 2009) This means that for
each of these unique sectors, which in most cases construction companies are engaged in
simultaneously, the contractor has to develop systems of measuring the different forms of output
and the varied conditions under which all these projects are carried out.
The major drive however with productivity has been the global push towards continuous process
improvement (CPI).According to Koskela (1992), the concept of process improvement needs to
be embraced by the construction industry as a necessity. He went further on to place productivity
measurement efforts as being at the core of improving project processes. In the Business Round
19. 10 |
Table (BRT) in Park (2006) it was stated that in the morden business environment, construction
companies needed comprehensive measurement efforts in order to remain competitive and
business. The modern approach to productivity has thus been more holistic with more and more
industry players realising the need to be deliberate and thorough in their measurement efforts.
Huang et al. (2009) proposed what became the major delimitation criteria for this study when
they identified that the construction industry has three distinct levels as far as productivity is
concerned; task level, project level and industry level. Task refers to a specific activity like
pouring concrete or structural steel erection, projects refers to the collection of activities which
result in the renovation or the construction of a facility. Industry refers to the total portfolio of
projects within an economy.
Jonsson, (1996) highlighted that the construction company was an entity that had various
projects where the actual productivity was taking place. This then places the projects in a key
position with regards to productivity measurement as the ultimate products of construction. With
this in mind this study will focus on project level productivity because according to Park (2006),
Construction productivity rates differ between projects because of the varying environments,
characteristics, and project management efforts for each project. Therefore, when analysing
construction productivity, one should consider the drivers that cause construction productivity
differences between projects.
Chan and Kaka (2007) took the case for project based measurement of productivity further by
highlighting that although strategic levels of management were crucial in improving construction
productivity, there was a need to relate it to the projects themselves. They quote Groak (1994:
288) who reinforces this by saying that industry had gone amiss by failing to recognise the
20. 11 |
project site as the “defining locus of production organisation”. This meant that the industry
needed to reorient its production improving efforts to the projects, and to do this measurement
becomes critical.
2.2 Construction Productivity Measurement Methods
There is Information needed to calculate a meaningful project level productivity metric. For
instance, information yielding the task weight (share that it represents to the overall project) is
required, as is an understanding of the task flows. Because some tasks are completed in parallel,
while others in series, the composition of the task flows affects overall project productivity.
Therefore, each component of the project productivity metric contains: (1) the task weight; (2)
the raw task productivity baseline value in the denominator; (3) the raw task productivity value
for that project in the numerator; and (4) a measure of the task mix (in parallel versus in series
task flows). The project productivity index value is a function of the individual components
(Huang et al, 2009)
Huang et al (2009) also proposed that an alternative project level productivity index can be
produced as follows. We can create an index which is the quotient of two ratios, in each ratio the
numerator is the value of construction put in place and the denominator is the number of field
work hours. As noted earlier, a reference data set can be used to fix a baseline value for the ratio
of value put in place to field work hours. The baseline value for the ratio is then used as the
denominator in the index calculation. How an individual project compares to the baseline is
determined by inserting its ratio of value put in place to field work hours in the numerator of the
index.
21. 12 |
2.2.1 Single Factor Methods
There are a number of factors that are identified as being critical to the production process and
these are classed into two broad groups, that is; labour related factors and capital related factors
(Motwani et al, 1995). According to Dean and Harper (1998), capital is defined as “structures,
land, natural resources, machinery and other durable equipment”. The measurement of
productivity using only one of these factors is termed single factor productivity measurement
(Schreyer, 2001).
Table 2.1 Single factor productivity measurement Methods (Adapted from Schreyer, 2001)
Types of Output
Measures
Types of Input Measures
Labour Capital
Gross Output Labour productivity
(based on gross output)
Capital Productivity (Based on
gross output)
Value Added Labour productivity
(Based on value added)
Capital Productivity (Based on
value added)
Single Factor productivity measures
2.2.1.1 Labour Productivity: The norm in productivity studies in construction has been to use
labour productivity as a measure of overall productivity (Ameh and Osegbo, 2011; Goodrumet
al, 1999). The reasons cited for this standard have been the labour intensive nature of the
industry. Freeman (2008) in the Organisation for economic co-operation and development
(OECD) also highlighted the macro-economic importance of labour productivity measurement
22. 13 |
saying that it was a critical indicator of competitiveness in an industry. The major advantage of
labour based productivity measurement is its ease of measurement and readability.
The researcher discovered that there has been great research and development in the field of
labour productivity measurement as compared to capital productivity measurement mainly
reflected by the number of methods in use to compute labour productivity against those used to
assess capital productivity. According to Noor (1998), labour productivity measurement
techniques fall within a spectrum between two broad categories of observational methods,
namely continuous observation (e.g. direct observation and work study) and intermittent
observation (e.g. audio-visual methods, delay surveys and activity sampling) (Cited in Chan and
Kaka, 2007)
2.2.1.1.1. Manpower Surveys- These are a system which utilizes foremen or work supervisors
in order to monitor the time input of laborers, the number per task and the delays if any, against
the quantity of production. Tucker (1988) proposed that through such surveys it was seen that
skilled craftsmen spent just as much time on productive tasks as non-productive tasks due to
management inefficiencies and antiquated methods.
Basically only the major trades are surveyed which means that a number of supporting tasks,
which may contribute heavily to the project outcome, might not be measured or accounted for.
However because of the levels of interdependence of job packages on a project, the progress on
one job package will usually be a good estimate of other levels of productivity. Berg (1999)
commented that when used as performance measurement tools, manpower surveys take little
time to implement. The primary disadvantage however is that they can become routine, and if
action isn’t taken to correct problems, jobsite personnel might lose interest in the effort
23. 14 |
2.2.1.1.2 Time cards- Cards are made for different tradesmen with common tasks listed, common delays
can also be listed on the cards and noted when theyoccur. Time cards can be made for labour as well as plant.
Time Cards were originally proposed by Stokes (1984) to be an effective way of tracking labor productivity.
He posited that instead of using time cards to record hours worked only, that they should be coded with task
codes which wouldthenindicatethetimespent oneachtask.
Berg (1999) also deals with the technique noting the weaknesses that are encountered whilst trying to
implement this method on project sites. He noted at the top of cons, that the time card method takes a
conscientious effort and is time consuming. Further, because it is continuous, the paperwork related to it is also
perpetual and must be maintained. He also highlighted the fact that it was prone to “lying” as Foremen might
interpret it as a way of checking on their leadership and present skewed information. However he still
maintained that this method was the most accurate way of actually tracking the workers productive and non-
productivetime.
2.2.1.1.3 Activity analysis- This is a continuous productivity improvement process which efficiently
measures the time expenditure of workers onsite and identifies productivity inhibitors that management must
reduce or eliminate to provide workers with more time for direct-work activities (Gouett, 2010). Unlike Work
sampling, activity analysis is a full time project assessment tool. It can be used on plant as well which makes it
broaderin its applications.
2.2.1.1.4 Time Analysis- Noor (1998) identifies that there are some industry players who do not have a
formal productivitymethod ofmeasurement but theyrefertotheirWork Breakdown Structure(WBS) ontheir
programs so as to analyse their progress. It has been seen that such companies will periodically compute
24. 15 |
estimates of how far they have progressed on the project against the planned projections, and this they use to
make decisions on whether to accelerate or increase manpower for the purposes of improving their
productivity. It is also these analyses that are used to determine the effectiveness of their work strategies in
terms of producing the desired output rates. The limitations noted by Noor are that the method neglects the
complex combinations of tasks and how they contribute to the overall outcome. Tangen (2005) also notes that
project programs have to be “extremely detailed” from the onset in order to be of any use in assessing
productivityoftheproject.
2.2.1.1.5 Work Sampling- Random observations of certain tasks are made by trained observers and non-
productivityascertained.Useofvideo cameras and skilledmanpower is madeuseoftorecordcertain activities
on site. From these observations, conclusions are drawn as to the sources of non-productive time. The method
can beregardedbylabourers as toointrusiveandtheworkermoraleis reduced.
There is also the issue of inadequate capture of the project environment and hence the misrepresentation of
actual project productivity due to largesse extrapolation. Radosavljevic and Horner (2002) in studying the
United States construction productivity in masonry, and formwork found that productivity in most cases was
not normally distributed as previously espoused in the industry and hence the need to adopt other statistical
tools in order to extrapolate and produce expected values for areas that needed to be worked on. According to
Berg (1999), this method is very intrusive but it is ideal if an end to productivity losses on particular work
sections is tobeinvestigated andadequatelydealt with.
The direct observation methods have been found to be very comprehensive in nature albeit their
implementationis just as equallytaxingon contractor’s funds (Noor, 1988). Theyare alsotimeconsumingand
can be very tedious for the labourers engaged in the task of measuring. However the methods are very
reflective of the actual work being done when carried out diligently. It should be noted that productivity
25. 16 |
measurement will itself be viewed as a non-productive activity in the industry because it does not add to the
physical progress ofthestructuredirectly.
2.2.1.2 Capital Productivity: This is a monetary value based measure of productivity. In most
cases Materials cannot be directly traced per unit input and hence monetary input value is
compared to monetary output value (Schreyer, 2001). Plant productivity is more easily computed
because of technological advances which have brought on board timing devices which can keep
track of the period of use of a particular piece of equipment (Motwani et al, 1995).
It carries the same advantage as labour productivity which is an ease of readability because basic
prices are used to compute the productivity data. The disadvantage however, is that, like labour
productivity measurement, it is a partial measure based on a jointly influenced factor, that is, it
assumes mutual exclusivity on dependant factors. Where materials are countable, or where the
activity being carried out by a particular type of plant is easily quantifiable, it was seen that the
Unit count method can be employed.
2.2.1.2.1 Unit count- Mostly used for countable work portions or tasks for example, brick counts, paving,
installed units, number of items lifted by a crane or loads transported by a tipper. It is however not useful if the
work is monolithic or if it’s a multiple number of heterogeneous elements. The final productivity value is
obtained usingthe followingformula;
Quantityindex ofvalueadded
Quantityindex ofinput
26. 17 |
2.2.2 Multi Factor Methods
These are methods that take into consideration the inter-dependence of factors of production to
assess construction productivity (www.dbrownmanagement.com, 2010). The two most documented
are the capital-labour method and the Capital-Labour and intermediate inputs (energy, materials
and services) also called the KLEMS method (Schreyer, 2001).
Table 2.3 Multi factor productivity measurement Methods (Adapted from Schreyer, 2001)
Types of Output
Measures
Types of Input Measures
Capital & Labour Capital, Labour Intermediate
inputs (energy, materials,
services)
Gross Output Capital-Labour MFP (based
on gross output)
KLEMS multi factor productivity
Value Added Capital-Labour productivity
(Based on value added)
-
Multifactor productivity(MFP) measures
2.2.2.1 Capital-Labour Method: This is a method which uses a combination of capital and
labour to compute the productivity of a project. According to Schreyer (2001) the value added by
each input is computed and weighted as a function of the bill rates and compared with the total
quantity weighted averages of all inputs, that is, productivity of project is obtained using the
formula below:
27. 18 |
Quantity index of value added
Quantity index of combined labour and capital input
The labour productivity and capital productivity values to be used in computing the indices are
obtained using any of the above detailed methods.
2.2.2.2 KLEMS Method: This is a very detailed and comprehensive productivity measure
which is mainly used to aggregate industry wide or sectorial performance. It is therefore not
popularly used to assess project level productivity (Shreyer, 2001 and Huang et al, 2009). The
following formula defines how the KLEMS productivity metric is obtained:
Quantity index of gross output
Quantity index of combined inputs
Its main advantage is that it acknowledges the contribution made by intermediate inputs and
therefore represents the best measure of technical improvements in an industry. A drawback
however is cited as being the requirements for large amounts of data to be compiled which
means that more resources have to be spent in the production of the KLEMS productivity metric
(www.oecd.com).
2.3 Hindrances to Productivity measurement
It is difficult to define a standard productivity measure because companies use their internal
systems which are not standardized (Park, 2006). In studying the literature it seems the problem
of productivity measurement has gone so far as being called “impossible” (James, 1980). Chan
28. 19 |
and Kaka (2007) described the reluctance of the industry to measure productivity as a type of
inertia. It is their thinking that there was first an inherent industry reluctance to engage
themselves in productivity measurement practices, before there was a real technical difficulty to
engage in the practice. This is attributed to the fact that the construction industry has been on the
outskirts of real productivity improvement and measurement for such a large part of the
industry’s existence.
Sezer and Brochner (2013) highlighted that one of the primary hindrances to measuring
productivity is the difference in definition of productivity itself in the industry. The industry is
split into so many trades and with each project and each contractor who engages in a particular
trade, there are an array of techniques and tools and combinations of labourers that are available
to accomplish the job. This means that for every unique project type we would be developing a
new measure for productivity. Unfortunately this is not practical and neither is it useful as a base
measure of growth studies in productivity.
2.3.1 Complexity of methods: The methods used in productivity studies have been a major
source of industry reluctance to indulge itself in it. From the huge disparity in project types to the
intricate differences between projects of similar nature, the changes and tweaking required to
retain validity of measures and comparisons seems to be a major industry turn-off (Chan and
kaka, 2007) It was also noted by Goodrum et al (2002), that the relationship between aggregate
and activity level productivity was complex to compound. This was realized to be a major reason
why industry professionals were reluctant to engage in the exercise.
29. 20 |
2.3.2 Lack of Management Interest in Productivity Assessments: Arditi and Mochtar (2000)
in reviewing factors that were driving productivity measurement in construction companies
noted that Management involvement was a major driver. It meant that without management
interest in productivity of projects, there was no fuel for employing the system on sites.
2.3.3 Rate of Task allocation changeover: In an article by the National Research Council of
Canada (NRCC, 1993), cited as one of the major hindrances to productivity measurement was
the rate of task changeover on a construction site. It has been seen that especially with more
general labourers, the rate at which their assigned tasks and areas of work changes, makes it hard
if not impossible to gather the productivity data.
2.3.4 Cost to company: Burton F, (1991) states that the major goal of any construction company
is to maximize their profitability by reducing the cost of production. He further goes on to note
that productivity measurement has costs associated with it in terms of the labour employed to do
it, the recording material, the logging devices and the increased non-productive time spent on the
measurement. When the perceived benefit of carrying out the measurement is not seen to
outweigh the costs, most companies will not carry out the measurement.
2.3.5 Commensurability Problem: Broman (2004) identified the difficulty in productivity
measurement as being that each variable in the process is not measurable against the same
standard. This means for each variable a different standard of measurement has to be employed,
therefore considering the large number of variables that can be on a project this becomes an
arduous task to carry out.
30. 21 |
2.4 Impact of Productivity measurement on Performance
For a contractor, field productivity represents the single biggest risk and differentiating factor
when it comes to project execution (www.dbrownmanagement.com, 2010). This implies that
assessing the productivity on a project can greatly increase contractors’ awareness of this risk
and help them mitigate it. Winch and Carr (2001) gave a shocking industry study when they
realized that of the companies that they studied, the very fact that they were doing a productivity
study led the workforce to increase their productivity rates. In other words, the competitiveness
and drive to please increased when they perceived that their work was being held to some kind of
standard.
Stokes (1984) was the first to note that worker morale was boosted by noting their daily
accomplishments when he was making his case for task recording time cards. Chang (1991) also
highlighted that worker morale was one key resultant from productivity improvement. He found
that contactors who measured their productivity were better placed to improve it and hence they
experienced a greater morale on their projects. Conversely he discovered that poor worker
morale led to poorer productivity.
Santosh and Apte (2014) in studying productivity measurement also noted that the labor force
was motivated by getting feedback on their performance. They found a greater performance was
achieved because the workers were aiming at set targets. They went on to list more benefits that
they found were accrued to contractors from performing productivity measurement, namely;
Decreased total cost of production
Decreased total duration of production
31. 22 |
Improved Quality of work
Higher profitability
A tool for management to use in continuous improvement
2.5 Summary
This chapter has given us an in-depth literature review highlighting what construction
productivity measurement is all about, what are the current methods in use to carry it out, what
are the hindrances that have been cited and what have been seen to be the performance related
benefits of construction productivity measurement.
32. 23 |
CHAPTER 3: Methodology
3.0 Introduction
This chapter describes clearly and concisely how the study was carried out. It outlines the
methods used to conduct this research. These concerns are the research design, research
instruments, data collection procedures, data presentation, and analysis plans.
3.1 Research Design
3.1.1 Nature and Setting of Study
There are three main research designs to choose from when looking at methodology to use in
research. Firstly there is the Qualitative (Interpretive approach), the Quantitative research
(Positivist research paradigm) and the mixed method (A combination of the first two), (Panas,
and Pantouvakis, 2010). The two aforementioned researchers also state that the complexity of
construction productivity measurement has led to the adoption of multiple method approaches in
researching it.
The Qualitative method of research has helped us to get general principles that govern or hinder
construction productivity. It has been useful in arriving at specific factors that affect on-site
performance (Park, 2006). The quantitative approach has been useful in that it gave us an
empirical, measureable picture of construction productivity. It is based in Mathematics, Statistics
and Probability and has assisted us with drawing accurate simulations of prevailing Industry
trends (Martinez and Ioannou, 1999).
The third and last type which is the Mixed Method approach is also called Triangulation. As
there are various types of triangulation, it is important to distinguish the selected approach from
33. 24 |
the other available options. Webb et al. (1996) proposed that once a proposition is reinforced by
two or more processes of measurement its likelihood for error is greatly reduced. Denzin (1970)
extended the idea of triangulation beyond its conventional association with research methods and
designs.
The researcher used Methodological triangulation, which refers to the use of more than one
method for gathering data. In essence there was use of both questionnaires and case studies to
collect data in an approach further distinguished by Denzin, (1970) as between method
triangulation, meaning the use of two methods to triangulate data in lieu of one method but
having within it variations. It is this type of triangulation that caters for the use of qualitative and
quantitative methods of data collection as was employed by this researcher.
3.1.2 Area of study
This research was carried out in Bulawayo and Harare. According to Charizeni, (2009) these are
the two industrial hubs of the nation from which I expected to obtain the most construction
projects. These were also the places which were most likely to have industry trendsetters.
3.1.3 Target Population
According to Nanayakkara, (1999), stratified populations offer a more fair representation when
dealing with the construction industry. In this research, our strata are defined by the Construction
Industry Federation of Zimbabwe (CIFOZ) registration system. Our population was those
companies that are duly registered members of the above institution as building construction
34. 25 |
companies rated according to capacity and capitalisation and in total they are 95. The strata were
6 in number and named alphabetically from A-F, with the most capitalised falling into Group A
and the least into group F.
3.1.4 Sampling frame
A sampling frame is a list of elements that compose a defined target population. In carrying out
a pilot book and literature study it was evident that, the major stakeholders in the industry when
it comes to construction productivity are; Quantity Surveyors, Engineers, Project Managers/
Contract Managers, and Site Agents working for contractors. These then became my focussed
sample frame.
3.1.5 Sample size
According to Hanke & Reitsch, (1992) it is not necessary to sample the entire population or even
a major portion of it to achieve results, the researcher can use a relatively small part of the
population to represent the whole. The sample though small in size if carried out accurately, will
be adequate enough to enable one to make accurate and valid generalisation. According to
Oppenhein, (1992) Sample accuracy is more important than sample size. Therefore the
researcher used a sample of 40 Contractors which represent 44% of the population.
3.2 Sampling Methods
3.2.1 Random Sampling
35. 26 |
In this method, each item in the population has the same probability of being selected as part of
the sample as any other item. To achieve this, the researcher numbered each member of the
population and then used a random number generator to select the required sample. This
approach was used to select the respondents for questionnaires.
3.2.2 Judgmental Sampling
In judgmental sampling, the person doing the sample uses his/her knowledge or experience to
select the items to be sampled. Patton (1990), states that it can be more useful to identify
respondents who are more likely to have the required information. The researcher used the
method to select the case study sites.
3.3 Research Instruments
Research instruments are tools used for collecting information data needed to find solutions to
the problem under investigation.
3.3.1 Desk research
Basically this entails a data gathering approach of using information from past publications and
statistics. This is the research that was carried out from, past publications, books, other
researches and online publications so that we compile the already available data and information
on other similar studies. These studies were then used to do comparative studies and to draw
inferences on similarities and differences arising from actual findings.
36. 27 |
3.3.2 Questionnaires
Questionnaires are research tools which consist of questions which seek to get an opinion of the
respondent who cannot be directly interviewed due to limited time and or availability. They were
used for those who are busy and cannot be interviewed. The thrust was to obtain from
respondents the kind of information that would help us assess the level of Construction
Productivity measurement on projects in Zimbabwe. They were also aimed at getting
information which relates to performance issues in project delivery and thus allowing us to
assess the performance trends on Zimbabwean projects. A questionnaire was designed and
distributed to each of the above recipients. The questionnaire comprised of more close ended
questions so that the data obtained is uniform and comparable and fewer open ended questions
which needed further clarifications. Close ended questions were either dichotomous offering two
alternatives which are mutually exclusive for example, YES/NO, or multiple choice offering
three or more alternatives. They were less time consuming and thus more prone to getting
responses from recipients and they are easy to administer if need be. Due to the sensitivity of the
information to be obtained, the questionnaire was designed in such a way that the respondents’
identity and the identity of the company they work for are kept anonymous.
3.3.3 Case studies
According to Yin (2003) a case study design should be considered when: (a) the focus of the
study is to answer “how” and “why” questions; (b) you cannot manipulate the behaviour of those
involved in the study; (c) you want to cover contextual conditions because you believe they are
relevant to the phenomenon under study; or (d) the boundaries are not clear between the
37. 28 |
phenomenon and context. Specific questions should be asked in order to determine what the case
is that is to be investigated (Baxter et al, 2008). According to Stake (1995), the case has to then
be bound in order to remain within the scope. Yin (2003) categorizes case studies as either:
exploratory, explanatory or descriptive. The researcher conducted a multiple case study of two
cases in order to examine trends that are consistent or some conflicting phenomena with regards
to productivity of projects in Zimbabwe.
The Case studies will looked at the following areas:
1. Company Profile i.e. Name, Duration of Operation, CIFOZ Category, Staff complement
2. Project Profile i.e. Value, Type, Worker complement,
3. Methods used on productivity measurement i.e. Detail methods, note frequency, note post
measurement response.
4. Performance Appraisal i.e. Look at the issues affecting performance on the site, note the
methods used to assess project performance
3.4 Data Presentation and Analysis Plan
The data was presented in Tables i.e. presenting information in row by column format. Figures-
presenting data in pictorial form through use of graphs, pie charts and time series plots Data
Analysis is the process of systematically applying statistical and/or logical techniques to describe and
illustrate, condense and recap, and evaluate data. Descriptive statistical data analysis was used to analyse
data. Data obtained was analysed using the aid of tables, bar graphs and pie charts. There was also the use
of the Relative Importance and Severity Indices. The data was collected as both quantitative and
qualitative therefore there was need to first discriminate the two sets of data. Some of the qualitative data
was used to make statistical inferences that were assessed by compiling in the form of the tables and pie
38. 29 |
charts and bar charts to reveal the trends in the various projects. The quantitative data was also compiled
in the same format and presented in such a way that it can be visible to the consumers of the information.
For example the pie charts will assist with best illustrating information to do with industry segmentation
with regards to certain factors or trends.
3.6 Summary
This chapter has focused on the core task of how the researcher carried out the study. The data
choosing, presentation and analysis have been set out so as to provide a guideline on the way the
research was carried out to achieve the objectives set out in the beginning. The following chapter
will then continue to analyse the collected data in the way specified above.
39. 30 |
CHAPTER 4: Data Presentation and Analysis
4.0 Introduction
This Chapter focuses on presenting and analyzing data obtained from fieldwork. The industry
respondents’ profiles, the degree to which productivity measurement is utilized in Zimbabwe, the
methods so employed, the hindrances to productivity measurement and the perceived benefits
with regards to performance are assessed.
4.1 General Data Report
Of the 95 contractors who are based in Bulawayo and Harare, Questionnaires were sent to 40
contractors by post and by hand delivery. 25 responses were received which represent 63% of the
total sample. Of those the spread in terms of class of contractor according to the CIFOZ system
was as follows;
Fig 4.1 Response rate per class of contractor
This shows firstly, that there is a higher interest in productivity issues as the size of contractor
increases.
56%
8%
16%
12%
0%
8%
0%
10%
20%
30%
40%
50%
60%
A B C D E F
Response
rate
Class of Contractor
Response rate per Class of Contractor
40. 31 |
The respondents’ were composed of 76% Quantity Surveyors, 20% Engineers and 4% other
professions showing us that the Quantity Surveyor is the main reference point when it comes to
monitoring productivity issues on construction projects. The experience of the respondents in the
industry was seen as follows;
Fig 4.2: Experience of respondents in the construction industry
The skew on the graph indicates that the industry in Zimbabwe is largely young. The reason for
this may be due largely to an intense brain drain syndrome that has resulted from the economic
crisis which has crippled the industry (www.standardnews.co.zw).
Fig 4.3: Company experience in Zimbabwean Industry
24%
44%
20%
8% 4%
Experience of Respondents in the
Construction Industry
0 to 2years
3 to 5years
6 to 10years
11 to 15years
15years and above
8%
28%
64%
Company Experience in Zimbabwean
Industry
0 to 4 years
5 to 15 years
16 years and above
41. 32 |
The company experience in the industry has been seen to be more inclined towards the more
established contractors, that is, those that have more than 15 years of experience in the industry
contributing more than 60% of the whole respondents. This may be attributed to the fact that
smaller contractors have found it hard to keep operating in the face of the economic challenges.
The Capital markets have not been functioning and hence it has negatively impacted the
operations of the smaller industry players who rely heavily on borrowed capital (Saungweme,
2011; cited in Chigara, 2012).
4.2 Productivity measurement in the Zimbabwean industry
4.2.1 Degree of Utilization
Of the sampled building contractors in Bulawayo and Harare, it was realized firstly that 64% of
the respondents were employing productivity measurement in one form or another. Of those,
36% of the respondents were not using productivity measurement as part of their construction
project management. This was very similar to literature trends where 31% of respondents said
they had no formal measures of productivity (Motwani et al, 1995) This indicates that although
economic hardships are prevailing in Zimbabwe, this has not caused a significant divergence of
the industry from other industries studied world-wide.
The distribution of which factors are being measured at project level was as follows;
42. 33 |
Fig 4.4: Productivity measures utilized on projects
The above table shows that by far labour productivity is viewed as the dominant productivity
measure on Zimbabwean projects. This is consistent with studies in literature (Dean and Harper,
1998; O’Grady, 2008; Stiedl, 1998). There is an industry consensus that labour monitoring
equates to project productivity monitoring. However 20% of respondents are using both labour
and plant (Capital) as a benchmark for assessing productivity. This can be seen as an addition on
labour productivity measurement as well as validation of the existence of capital-labour
productivity measurement in Zimbabwe. (Schreyer, 2001) Only one respondent utilizes a
measure of labor, plant and material to assess project productivity. The use of construction
productivity measurement by contractor class was found to be as follows;
8
1
0
5
0
1
0
2
4
6
8
10
Labor Only(L) Plant Only(P) Material
Only(M)
L&P L&M L, M &P
Number
of
users
Construction Productivity measures Utilized on Projects
[ Single Factor measures ] [ Multi-Factor productivity ]
43. 34 |
Fig 4.5: Use of construction productivity measurement per class of contractor
This graph shows us that the majority of industry players who carry out productivity
measurement are the Group A Contractors. This is probably due to their resource base and due to
the greater proportion of risk posed by not measuring productivity for the size of projects that
they embark on (www.dbrownmanagement.com). The graph also shows the respondents per class
who engage in productivity measurement compared to the total who responded. 79% of Group A
respondents carry out productivity measurement compared to 50% for both Group B and C. The
sharp rise to 100% in group D might be attributable to sampling bias as results are very
inconsistent with the observed trends.
Firstly the larger contractors have more resources available to them therefore they can better
absorb the costs of productivity measurement activities. We can also cite the increased risk borne
by the larger contractor due to handling bigger projects as an incentive for them to carry out
0
2
4
6
8
10
12
14
16
Group A Group B Group C Group D Group E Group F
Number
of
respondents
Class of contractor
Total Number of
respondents
Respondents
measuring
productivity
Use of Construction productivity measurement per class of
contractor
44. 35 |
productivity analysis, whereas it can also be stated that the smaller contractors have very small
projects that do not entail much complexity and hence no formal measure of productivity is done
as supervisors verbally deal with issues arising on site. It was also seen that 7 out of the 9
respondents who were not using productivity measurement did not have any knowledge about
the management system.
4.2.2 Methods Utilized
The following is a relative frequency table depicting Productivity measurement methods and the
degree to which they are being utilized on Zimbabwean projects.
Fig 4.6: Relative frequency of use of methods
The combined relative frequencies of Manpower Surveys, Time Cards and Work Sampling is
comparatively larger than that of Unit Count and Time Analysis. This is consistent with findings
in literature that indicate that usage of labour productivity parameters is most widely practiced
(Park, 2006). Work Sampling is almost non-existent in the industry. This is probably due to the
relatively cost intensive nature of the method (Berg, 1999). It should also be highlighted that the
0.26
0.25
0.02
0.25
0.23
0.00
0.05
0.10
0.15
0.20
0.25
0.30
Manpower
Surveys
Time Cards Work Sampling Unit Count Time Analysis
Relative
frequency
Method Utilized
Relative Frequency of use of methods
45. 36 |
form in which these methods are being used is largely basic in comparison to some of the forms
which have been arrived at in other more developed countries where index based metrics have
been adopted which can be used industry wide to do analyses (Schreyer, 2001). We must infer
that the Zimbabwean construction industry is lagging behind world productivity measurement
efforts.
It was also found that over 60% of Contractors said that their laborers did not respond positively
to the measurement of productivity. It was found to be a source of offense for many. This could
also be cited as a hindrance to measurement by some contractors. It also tells us that most
probably the way they are implementing these methods is flawed at the psychological thrust
being portrayed by management.
4.2.3 Hindrances to Productivity Measurement
The respondents were asked to mention any hindrances that they encountered as they endeavored
to measure productivity. They were also given a list of common hindrances gleaned from
literature to assess and indicate the level to which they were hindering their own efforts. The
results according to a severity index (SI) analysis came out as follows;
Table 4.1 Severity index analysis of hindrances to productivity measurement
Hindrance Score SI Rank
Lackofmanagementinterestinproductivity
reports
67 0.136 1
Lackofpersonnel 62 0.126 4
Inadequateprojectbudget 64 0.130 3
Complexityoftasks 64 0.130 3
Rateoftaskallocationchangeover 66 0.134 2
46. 37 |
Lackofmaterialtrackingschedules 50 0.102 6
Lackofplanttimingdevices 57 0.116 5
Plantmulti-tasking 62 0.126 4
Using the Severity Index it is clear from Industry’s perspective that the lack of management
interest in productivity measurement ranks as the most severe hindrance. From literature
however, it was the rate of task allocation changeover, and the complexity of tasks that were the
highest ranking and most frequently appearing hindrances (Goodrum et al, 2002; Broman, 2004;
Motwani et al). It is most likely that the recent change in most company structures due to
national policy like the indigenization policy, has led to the coming in of a relatively
inexperienced management group in construction. It is also likely that management is ignorant of
the benefits that this management system can add to their project performance as highlighted by
Zakhieh (2010).
It should be noted that the relative differences in the indices for the top four factors is minimal,
hence we can conclude that project budget constraints, rates of task allocation changeover and
complexity of tasks are also significant hindrances to productivity measurement. This is a
worldwide cry amongst construction industry professionals which as a developing nation, the
Zimbabwean industry players might have to find innovative ways of dealing with (Broman,
2004).
The least ranking hindrances were found to be lack of plant timing devices and lack of material
tracking schedules. According to Schreyker (2001), these hindrances relate to the measurement
47. 38 |
of capital productivity. We can therefore conclude that the industry is better equipped to measure
capital productivity than it is to measure labour productivity.
4.3 Impact of Productivity Measurement on Performance
Of all the respondents, 100% agreed that productivity measurement does help to increase project
performance. Of those companies that do carry out productivity measurement, 90% of them
carry it out at least once a week of which 50% of them carry it out daily. This shows how vested
they are in the system, and also it highlights why other players might not want to carry it out
because it is very involving in terms of time and cost implications for the project.
Using the Severity Index it was found that of the Triple constraints, which are Key Performance
Indicators (KPI), the most impacted indicator due to carrying out productivity measurement was
Project Completion Time. This was followed by the project cost reduction which is an apparent
down-flow from reduced project times. It was however noted that most respondents concur that
project quality was not impacted much by the exercise of productivity measurement. This can be
reasoned through easily because the major thrust of productivity measurement has been towards
cost and time reduction and not really as a Quality control system albeit it does impact quality of
work for the better (Zakhieh, 2010).
48. 39 |
Fig 4.7: Impact of construction productivity measurement on KPIs
A further assessment of other benefits that have been cited in literature as being attributable to
productivity measurement produced the following table computed using the RII;
Table 4.2: Other benefits of construction productivity measurement
Area Score RII Score
Workermorale 42 0.077 9
Projectprofitability 61 0.112 3
Costcontrolofmaterials 57 0.105 6
Projecttimedelivery 59 0.108 4
Qualityofwork 49 0.090 8
Workerpunctuality 71 0.130 1
Plantoptimization 59 0.108 4
Competitivebidcompilations 54 0.099 7
Projectlabourcosts 66 0.121 2
Safeworkprocedures 27 0.050 10
0.41
0.34
0.25
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45
Time
Cost
Quality
Severity Index
KPI
Severity Index Bar Graph of impact on KPIs
49. 40 |
From the above table it is apparent that contractors who utilize productivity measurement have
received the greatest benefit from the increased punctuality by workers on site. This is probably
due to the fact that workers are more conscious of the impact of delay on their end output. Apart
from the already stated cost reduction benefits, contractors also cited profitability of projects as
another major benefit of productivity measurement. This follows on from the cost reduction on
major inputs and reduction of non-productive labor time.
4.4 Case studies
4.4.1 Case Study A: Renovation of Flats.
The Project is a $6 million renovation of flats into commercial offices being carried out by a
reputable class “A” contractor with over 25 years of experience in the construction industry.
There are 3 staff members and at its peak the project had 66 workers on site.
Major Works include:
Excavations, concreting, demolitions of concrete and masonry structures, brickwork, painting,
plastering, electrical and plumbing.
Measurement procedures:
Labor Productivity data is captured daily using manpower surveys. A foreman allocates tasks
and is responsible for capturing daily productivity and reporting it to the site agent in a weekly
meeting. An assessment is made as to whether the laborers are being productive or not, and what
the reasons are. It was noted that the contractor had strict productivity targets and was making
50. 41 |
use of stringent punitive measures including dismissal for unjustifiable failure to meet
productivity targets.
The Site agent noted that there were many complex activities taking place because the works
were being done on a very old building (commissioned 1924). This was a hindrance to
measuring the productivity of workers who were constantly trans-locating to other tasks and
other areas to attend to emergency tasks. He also noted that material shortages were also a
hindrance to labor productivity.
The contractor was also carrying out plant productivity measurement. There was intensive use of
a compressor for the demolitions and the unavailability of the clock was seen by the researcher
as a point of dispute with the clients, and worse still as a productivity indicator. Without a fully
functioning clock on a piece of plant, it becomes the contractors word unless if there is a clerk of
works who is constantly monitoring the plant. The major hindrance cited by the contractor on
plant productivity measurement was the fact that due to the site restrictions and the novelty of
some of the tasks carried out by the plant, it was not reasonable to use conventional plant outputs
as a benchmark. In such instances, productivity was halted altogether.
This contractor cited amongst the performance related benefits of employing productivity
measurement:
Cost savings on labour
Enhanced target meeting due to increased worker productivity
Ease of contract management
4.4.2 Case Study B: New Residence for University Students
51. 42 |
The project is a $12Million proposed student’s hostels, Kitchen and Dining area with Sub-
warden houses. The Contractor is a Class A contractor with over 50 years’ experience in building
and civil works. There are 12 staff members and 360 laborers on the site.
Major Works include;
Excavations, concreting, brickworks, plastering, painting, plumbing and electricals.
Measurement procedures:
A very deliberate attempt at measuring productivity is in force on the site with the task of
recording outputs of labour and plant being carried out by a trained “Checker” and recorded
daily. For labour productivity the system in place is such that; twice a day the “checker” goes out
into the site with a printed plan of the works which has works recorded on it for example
“concrete to strip footings: Male Hostel”. He will then mark out on the plan to the level at which
works have been carried out. This is done in consultation with the supervisor for the said works
so as to note any areas pertinent to either the above normal or below expected productivity by the
workers. The same “Checker” produces a labor allocation sheet every day to note how long a
worker has been engaged in a particular task.
At the end of the week, the “Checker” submits the weeks work plans and labor allocation sheets
to the Quantity Surveyor on site. The Quantity Surveyor (QS) then calculates the quantity of
work carried on every allocated task during the week using conventional measurement standards
and units. The labor hours are collated in such a way that the basic rates of the laborers at tender
and the current rates of the individuals are multiplied by the total hours worked by each laborer.
This results in a quantification of the labor increased costs. The quantity of work done is also
multiplied by the tender rates for the items and a total tender allowable cost is found for labor.
52. 43 |
Then the tender rates for the individuals who were actually employed to do the task are collated
and compared to the tender allowables. This shows whether there was a loss or gain on labor
productivity for a particular task. Then all the Gains and losses for the project are summed up to
give a net project labor gain or loss on labour. These results are reported to the head office of the
contractor weekly.
Plant hours are recorded daily as well against assigned tasks. These will be taken to the QS who
in turn calculates the productivity. (see appendix for typical plant return sheet) Material issues to
both main contractor and subcontractors is recorded and reconciled by the Store man. The QS is
then tasked with evaluating the material used against the projected in what they called a
profitability report. It was seen that not all materials were monitored. The major materials
monitored were, Cement, Stone, Bricks, Sand and Rebar.
The contractor cited that their use of productivity measurement was driven by the derived
benefits from the use of the tool. Among the benefits they noted:
That workers were more punctual due to the monitoring
Ease of tracking sources of project losses
Maximization of plant capacity and consequently profitability
Ease of bid preparation for tendering on other similar projects
Cost savings on labour
4.5 Summary
This Chapter has looked at the data that has been collected from industry with an attempt to
summarize the data, present it in a way that will make it appreciable and to analyze it. In this
regard, various tables have been made use of in order to summarize the data in a way that can be
53. 44 |
absorbed with relative ease. It was also expedient to use indices that would bring out the most
severe and the most relevant parts of the data collected. The next chapter will deal with
conclusions and recommendations that the student has made.
54. 45 |
CHAPTER 5: Recommendations and Conclusions
5.0 Introduction
This Chapter will look at the conclusions that the researcher has reached, the recommendations
that researcher wishes to make to industry players and the recommendations for areas of further
study based on findings from this study.
5.1 Project level construction productivity measurement methods
There is a significant use of labour productivity measurement as the main construction
productivity measurement method on Zimbabwean projects, that is, 53% of the
respondents.
There is also a significant acceptance of capital measurement as a productivity
measurement tool, however there are more contractors using multifactor productivity
than those using single factor capital productivity measurement.
The methods being used in productivity measurement are in a rudimentary form. There
was no contractor using any metrics to compute their productivity values hence only raw
and unadjusted measures and data is available.
5.2 Hindrances to productivity measurement
The most significant hindrance to the productivity measurement agenda on projects is the
lack of management interest in productivity issues.
55. 46 |
Project budgets that do not cater for productivity measurement are also a major hindrance
to measurement of productivity. It is likely that the productivity measurement efforts are
also being affected by the economic downturns.
The complexity of the measurement methods also ranks high on factors hindering
productivity measurement. It has been noted that those who are using the methods lament
the complexity of the methods even in their most basic state.
The rate of task allocation changeover is another major ranking factor of concern.
Unfortunately this factor is an industry characteristic that cannot be eradicated but needs
more innovative ways or rather more complex tracking systems that can effectively keep
track of labourers.
5.3 Impact of Construction productivity measurement on project performance
Project completion time is the most impacted performance indicator amongst the KPIs.
Therefore construction productivity measurement is likely to lead to more timeous
completion times of projects.
According to industry players, it lowers project cost as well. We can expect final project
values that are within tolerable deviations from estimated completion cost values.
The quality of project although affected by measuring construction productivity is the
least affected of the KPIs. This means that quality control has to be implemented jointly
with construction productivity measurement in order to deliver projects within required
time, cost and at the optimum quality.
56. 47 |
In general, employees are more punctual when they know that their productivity is being
measured. This indicates that they will respond to productivity measurement by
increasing productivity.
More profitable projects can be expected when there is a culture of productivity
measurement.
Construction productivity measurement and construction site safety have very low
correlation according to industry players.
5.4 Recommendations to Industry
Firstly the researcher recommends that there be an equipping of students studying
construction management related courses, for example, Quantity Surveying and
Engineering, with productivity measurement expertise so that they get into the industry
with an appreciation for the management tool.
More earnest involvement by management in tracking and monitoring productivity at a
project level. This should see a productivity measurement culture emerging in
Zimbabwe’s construction industry.
In the same way that safety has been seen to be of the essence in managing a project
successfully, the researcher would encourage industry to view productivity measurement
as a cost saving and not as a cost incurring process. This should see it being placed in
project budgets.
57. 48 |
5.5 Areas of future study
The researcher recommends a further study to be carried out on productivity measurement at
project level on a nationwide scale. This should allow us to have a more comprehensive report on
the industry in Zimbabwe.
The researcher also recommends a study into how industry construction productivity indices and
metrics are computed so that this can provide industry with much needed know-how about
productivity metrics.
The researcher also recommends a study into industry level construction productivity
measurement methods as the next level of interest that we should investigate. This should allow
us to investigate and recommend updated methods for the local industry.
5.6 Summary
This chapter has focussed on the researcher’s conclusions based on the findings made in this
study. It has also explored the recommendations made by the researcher to industry with regards
to productivity measurement and also some recommendations of future study stemming from this
research
58. 49 |
REFERENCES:
1. Abd.Majid, M.Z.A., & McCaffer, R. (1998). Factors of non-excusable delays that
influence contractors’ performance. Journal of Management in Engineering, 14(3), 42-48.
2. Ahmet Anil Sezer& Jan Bröchner , Construction Management and Economics (2013):
The construction productivity debate and the measurement of service qualities,
Construction Management and Economics
3. Aki Pekuri1, Harri Haapasalo, Maila Herrala, (2011) International Journal of
Performance Measurement, Vol. 1, 39-58.
4. Allen, S.G. (1985). “Why construction industry productivity is declining,” Review of
Economics and Statistics 117(4), 661-65
5. Al-Momani, A. H. (2000). Construction delay: A quantitative analysis. International
Journal of Project Management, 17, 51-59.
6. Ameh, O.J., & Osegbo, E.E. (2011). Study of relationship between time overrun and
productivity on construction sites. International Journal of Construction Supply Chain
Management 1 (1). 56-67.
7. Arditi, D. and Mochtar, K. (2000). Trends in Productivity Improvement in the US
Construction Industry, Journal of Construction Management and economics, Vol. 18.
8. Berndt, Ernst R. and Melvyn A. Fuss (1986). “Productivity Measurement with Adjustments for
Variations in Capacity Utilisation and Other Forms of Temporary Equilibria”, Journal of
Econometrics 33.
9. Bernolak, I. (1997). Effective measurement and successful elements of company
productivity: the basis of competitiveness and world prosperity. International Journal of
Production Economics, 52:203-213.
10. Chan, P and Kaka, A (2003) Construction labour productivity improvements. In: Aouad,
G and Ruddock, L (Ed.) Proceedings of the third international postgraduate research
conference, 3 – 4 April, Escola Superior de Actividades Imobiliárias (ESAI), Lisbon, 583
– 598.
11. Chang, L., (1991), “A methodology for measuringconstruction productivity”,Cost
Engineering, Vol. 3 No. 10, pp. 19-25
12. Cohen, J., & Cohen, P. (1983). Applied multiple regression/correlation analysis for the
behavior sciences (2nd ed.). Hillsdale, NJ: Lawrence Erlbaum
59. 50 |
13. Dean, Edwin R., Michael J. Harper, and Mark S. Sherwood. (1996). “Productivity
Measurementwith Changing-Weight Indices of Outputs and Inputs” In Industry
Productivity: International Comparison and Measurement Issues. Paris: OECD.
14. Drucker, P. F. (1980). Managing In turbulent times. New York. Harper Collins Publishers
15. Ewe Chye LIM (1996), The Analysis Of Productivity, Loughborough University
Singapore. Creative Commons
16. Frimpong, Y., Oluwoye, J., & Crawford, L. (2003). Causes of delays and cost overruns in
construction of groundwater projects in developing countries: Ghana as a Case Study.
International Journal of Project Management, 21, 321-326.
17. Goodrum et al. (2002). The divergence in aggregate and activity estimates of US
construction productivity. Construction Management and Economics, 20(5), 415-423.
18. Gouett, M.C., (2010). Activity Analysis for Continuous Productivity Improvement in
Construction by. Population (English Edition), p.1-150.
19. Griliches, Zvi (1987), “Productivity: Measurement Problems”, in J. Eatwell, M. Milgate and P.
Newman (eds.), The New Palgrave: A Dictionary of Economics.
20. Groák, S (1994) Is construction an industry? Notes towards a greater analytic emphasis
on external linkages. Construction management and economics, 12, 287 – 293.
21. Hill, R C and Bowen, P (1997) Sustainable construction: Principles and a framework for
attainment. Construction Management and Economics, 15, 223-239
22. http://www.pmi-agc.com/technical-presentations-2010/dr-rashad-zakieh-pmp-productivity-
measurement-improvement-and-its-role-in-mitigating-the-risk-of-disputes-in-construction-
projects. Accessed 19.11.2013
23. Huang et al. (2009). Metrics and Tools for Measuring Construction Productivity:
Technical and Empirical Considerations. NIST Spec. Publ. 1101. Gaithersburg, MD:
National Institute of Standards and Technology.
24. Jonsson, J (1996) Construction site productivity measurements: selection, application and
evaluation of methods and measures, Ph.D. thesis, Luleå University of Technology,
Sweden.
25. Kaming, P.F., Olomolaiye, P.O., Holt, G.D., & Harris, F.C. (1997). Factors influencing
construction time and cost overruns on high-rise projects in Indonesia. Construction
Management and Economics, 15, 83-94.
60. 51 |
26. Kasimu M. (2012), Significant Factors that Cause Cost Overruns in Building
Construction Projects in Nigeria. Institute of Interdisciplinary Journal of Contemporary
Research in Business: 3(11);775 – 780.
27. Koskela, L. (1992) “Application of the new production philosophy to construction,”
Technical Report #72, Center for Integrated Facility Engineering, Stanford University.
28. Koskela, L., (2000). An exploration towards a production theory and its application to
construction.
29. Koskela, Lauri. (1992). Process Improvement and Automation in Construction: Opposing
or Complementing Approaches? The 9th International Symposium on Automation and
Robotics in Construction, 3 - 5 June 1992, Tokyo. Proceedings. Pp. 105-112.
30. Latham, M (1994) Constructing the Team. London: HMSO.
31. Lowe, J. G. (1987), The Measurement of Productivity in the Construction Industry,
Construction Management and Economics, E & FN Spon, v. 5, pp. 101 – 113
32. Noor, I. A.(1992). “Study of the Variability in labour Productivity in Building trades.”
Construction Management research Unit, department of Civil Engineering, university of
Dundee, Dundee
33. OECD (2000), A New Economy? The Changing Role of Innovation and Information Technology
in Growth, OECD, Paris.
34. OECD (Organization for Economic Co-operation and Development). (2001). Measuring
Productivity—Measurement of Aggregate and Industry-Level Productivity Growth.
Paris: OECD.
35. Oglesby, C.H., Parker, H.W. & Howell, G.A., (1989). Productivity improvement in
construction, McGraw-Hill. Available at:
http://ascelibrary.org/coo/resource/1/jcemd4/v111/i1/p1_s1.
36. Ogunlana, S.O, Promkuntong, K., & Vithool, J. (1996). Construction delays in a fast
growing economy: Comparing Thailand with other economies. International Journal
Project Management, 14(1), 37-45.
37. Olomolaiye, P O (1990) An evaluation of the relationship between bricklayers’
motivation and productivity. Construction management and economics, 8, 301 – 313.
38. Park, H.-S., Thomas, S.R. & Tucker, R.L., (2005). Benchmarking of Construction
Productivity. Journal of Construction Engineering and Management, 131(7), p.772-778.
61. 52 |
39. Paul W. Chan, Ammar Kaka, (2007) "Productivity improvements: understand the
workforce perceptions of productivity first", Personnel Review, Vol. 36 Iss: 4, pp.564 –
584
40. Project Management Institute (PMI), (2000). A Guide to Project Management Body of
Knowledge (PMBOK Guide). Newtown Square: Project Management Institute, Inc.
41. Tangen, S. (2004) “Performance measurement: from philosophy to practice,”
International Journal of Productivity and Performance Management 53(8), , 726-37
42. Teicholz, P., Goodrum, P., and Haas, C. (2001). ”U.S. Construction Labor Productivity
Trends, 1970–1998.” Journal of Construction Engineering and Management, 127(5),
427–429.
43. Thomas, H R (2000) Schedule acceleration, work flow and labour productivity. Journal
of construction engineering and management, ASCE, 126(4), 261 – 267.
44. Tucker, R.L., (1986). Management of Construction Productivity. Journal of Management
in Engineering, 2(3), p.148-156
45. Tucker, R.L., D.F. Rogge, W.R. Hayes, and F.P. Hendrickson. (1982). "Implementing
Foreman Delay Surveys." ASCE J. Const: Div. 108(4):577-591.
46. Warner P, (2004). The multispace adaptable building concept and its extension into mass
customisation. IN: Scheublin .. et al (eds). Proceedings of the Joint CIB, IASS
International Conference on Adaptability in Design and Construction, Eindhoven
University of Technology, 3rd-5th July 2006, pp 12.7-12.13
47. Winch, G and Carr, B (2001) Benchmarking on-site productivity in France and the UK: a
CALIBRE approach. Construction management and economics, 19, 577 – 590.
48. Winch, G.M., (2006). Towards a theory of construction as production by
projects.Building Research & Information, 34(2), p.154-163.
64. 55 |
QUESTIONNAIRE
Dear Sir/Madam
I am studying for a Quantity Surveying degree at the National University of Science and Technology. As
part of my course, I am writing a dissertation titled “An analysis into Construction Productivity
measurement and performance in Zimbabwe”
My dissertation may be made available to other students and the general public in the university library. I
will ensure your anonymity by excluding identifiable personal data from the dissertation. However, please
be aware that one of your colleagues or any other person who knows that you have taken part in the study
may be able to recognise your input from what is said. Your participation in this study is on a voluntary
basis and you are free to withdraw from the study if you inform me by the 4th
of April 2014.
If you have any questions about my study, I will be glad to answer them. You can reach me on my mobile
phone on 0773218645 or by email mwamlowegeorge@gmail.com You can also contact my supervisor
Mr. T. Moyo for further information by e-mail
Please sign and date the statement below if you are willing to participate. Many thanks for your interest in
my research,
Yours sincerely,
George Mwamlowe
Consent agreement
I have read the above statement and understand its contents. I have been given the opportunity to ask
questions and discuss any concerns. I agree to participate in the study as it has been explained. I
understand that extracts of the interview may be used, in anonymous form, in the student’s dissertation.
However I understand also that my identity will not be disclosed by the researcher or the University.
Name .Date .
PLEASE RETURN SIGNED COPY TO THE STUDENT, AND RETAIN A COPY FOR YOUR OWN
RECORDS
65. 56 |
SECTIONA: RESPONDENTPROFILE
1. Companyname:……………………………………………...
2. Classofcontractor:…………………………………………...
3. Typeofjob/Position:…………………………………………
4. Profession:…………………………………………………..
5. Respondent’sexperienceinconstructionindustry:
Less than 2 years
3 - 5 years
6 - 10 years
11 - 15 years
16 years and above
6. CompanyexperienceinconstructionIndustry:
Less than 5 years
5 - 10 years
15 years and above
SECTIONB:PRODUCTIVITYMEASUREMENT
MethodsUtilized
a) Doesyourcompanycarryoutproductivitymeasurementforitsprojects?
Yes
No
66. 57 |
b) If NOto(a),pleasebrieflyoutlinewhy…………………………………………………….
………………………………………………………………………………………………………
………………………………………………………...…………………….
c) If YESto(a)whichofthefollowingismonitoredontheprojectintermsofproductivity?
Labour
Plant
Material
d) Brieflydescribethemethod(s)thatareemployedtodotheaboveonyour
project?………………………………………………………………………………………………
………………………………………………………………………………………………………
………………………………………………………………………
e) Ofthebelowmentionedpleasetickthemethod(s)thathavebeenusedonyourprojectstomeasure
constructionproductivity
METHOD TICK
ManpowerSurveys(Foremancapturestheproductionpertaskdoneandnotesthe
numberofpeopleworkingonit,andanydelays)
Timecards(Cardsaremadefordifferenttradesmenwithcommontaskslisted,common
delayscanalsobelistedonthecardsandnotedwhentheyoccur)
WorkSampling(Randomobservationsofcertaintasksaremadebytrainedobservers
andnon-productivityascertained)
Unitcount(Mostlyusedforcountableworkportionsortaskse.gbrickcounts,column
counts,installedunits)
TimeAnalysis(Scheduledagainstactualcompletiontimeiscollatedandanalysedfor
specificworkportions)