SlideShare a Scribd company logo
Classification
Variances are broadly classified into the following:
Material Cost Variance
Material Cost Variance
Material Cost Variance is the difference between the actual cost of direct materials
used and standard cost of direct materials specified for the output achieved.
This variance results from differences between quantities consumed and quantities of
materials allowed for production and from differences between prices paid and prices
predetermined.
Can be computed using the formula:
Material Cost Variance = (SQ x SP) – (AQ x AP)
Material Price Variance
A Materials Price Variance occurs when raw materials are purchased at a price
different from standard price.
It is that portion of the direct materials which is due to the difference between actual
price paid and standard price specified
Can be computed using the formula:
Material Price Variance = (Standard Price – Actual Price) x Actual Quantity
This variance is unfavourable when the actual price paid exceeds the predetermined
standard price.
It is advisable that materials price variance should be calculated at the time of
materials purchase rather than when materials are used. This is quite beneficial from
the viewpoint of performance measurement and corrective action.
Materials Usage Variance
The material quantity or usage variance results when actual quantities of raw
materials used in production differ from standard quantities that should have been
used to produce the output achieved.
It is that portion of the direct materials cost variance which is due to the difference
between the actual quantity used and standard quantity specified.
Can be computed using the formula:
Material Qty. variance = (SQ for actual output – AQ ) x Standard Price
This variance is favourable when the total actual quantity of direct materials used is
less than the total standard quantity allowed for the actual output.
Material Mix Variance
*The material mix variance is an sub variance of materials usage variance it arises
only where more than one type of materials is used for producing a product .
* Increase in the proportion of cheaper materials result in favourable mix variance &
vice versa
Can be computed using the formula:
Material Mix variance = (Revised Standard Qty. – AQ ) x Standard Price
Revised Standard Quantity =

x SQ
Materials Yield Variance
Materials Yield Variance
The material yield variance explains the remaining portion of the total materials
quantity variance. It occurs when output of the final product does not match with the
output that could have been obtained by using the actual inputs.
It is that portion of the materials usage variance which is due to the difference
between the actual yield obtained and the standard yield specified (in terms of actual
inputs).
Can be computed using the formula:
Material Yield variance
= (Standard yield or output for
actual input – Actual yield or output) x Standard Cost per unit
Standard Cost per unit

= Total cost of standard mix of material
Net standard output quantity
Labour Variances
Labour Variances constitution:
Labour Cost Variance
Labour Cost Variance denotes the difference between the actual Cost and standard
of direct labour
Can be computed using the formula:
Labour Cost Variance = (SH x SR) – (AH x AR)
When the actual
variance.cost

labour cost is more than standard cost, there will be adverse
Labour Rate Variance
A Labours Rate Variance is the difference between the standard labour rate
specified and the actual labour rate paid.
It is an uncontrollable variance as the labour rate are usually dertermined by
supply & supply & demand conditions in the labour market
Can be computed using the formula:
Labour Rate Variance = (Standard Wage Rate – Actual Rate) x Actual
Time
This variance is adverse when the actual wage rate paid exceeds the
predetermined standard wage rate.
Reasons for labour rate variance :
1)Change in the basic wage rate .
2)Use of diferent methods of wage payment .
3)Unscheduled overtime.
4)New workers not paid full wages
Labour Efficiency Variance
The Labour time or efficiency variance is the result of taking more or less time than
the standard time specified for the performance of a work.
It is that portion of the Labour cost variance which is due to the difference between
the actual labour hour expended and standard labour hours specified.
Can be computed using the formula:
Labour Efficiency variance = (SH for actual output – AH ) x Standard Rate
This variance is favourable when the total actual hours are less than the standard
hours allowed.
Reasons for LEV
1)`Using low qty materials
2)Improper working conditions .
Idle Time Variance
It is a sub-variance of Wage Efficiency or Time Variance.
The standard cost of actual hours of any employee may remain idle
due to abnormal circumstances like strikes, lock outs, power failure
etc.
Standard cost of such idle time is called Idle Time Variance.
It is always adverse or unfavourable.
Can be computed using the formula:
Idle Time variance = Idle Hours x Standard Rate per hour
Labour Mix Variance

LMV arises only when more than 1 grade of workers are
employed on a job , here grade refers to skilled & unskilled
Can be computed using the formula:
Labour Mix variance = (Revised Standard labour hours – AH )
x Standard Wage rate
Labours Yield Variance

The Labour yield variance occurs when there is a difference
between standard output and actual output.
Can be computed using the formula:
Labour Yield variance
= (Standard yield or output for
actual mix– Actual yield or output) x Standard labour Cost per
unit
Variable OH Variances
Variable Overhead Variance represents he difference between standard
variable overhead (specified for actual units produced) and the actual variable
overhead incurred.
Can be computed using the formula:
Variable OH Cost Variance = Standard Variable OH on actual production –
Actual
variable OH
OR
Variable OH Cost variance = (Actual time or standard hours for actual
production x
Standard variable OH Rate) – (Actual
Variable OH)
Sub-division
There may be two sub divisions of variable overhead variance.
(i) Variable Overhead Expenditure or Budget Variance
= Standard Variable Overheads for actual time – Actual variable overheads
Standard variable OH for actual time = standard variable OH rate per hour
x actual hours
(ii) Variable OH Efficiency Variance
= Standard Variable Overheads on actual production – standard variable
overheads for actual time
Standard or budgeted variable overhead for actual time
= Standard OH Rate per hour x Actual Hours
Standard variable OH on actual production
= standard variable OH per unit x Actual output
Fixed OH Variances
T
erms to be understood before calculating OH Variances:
1. Standard OH Rate per unit or per hour or B
udgeted OH Rate per unit
=

B
udgeted Overheads
B
udgeted Output Units or B
udgeted H
ours

or per hour

2. Recovered or Absorbed Overheads
= Standard OH R
ate per unit x Actual Output or Standard OH Rate per hour
x Standard hours for actual output
3. B
udgeted Overheads (for budgeted hours or budgeted output):
= Standard OH rate per unit x B
udgeted output units or Standard overhead
rate per hour x budgeted hours.
4. Standard Overheads (for actual time or budgeted output for actual time)
= Standard OH Rate per unit x Standard output for actual time or Standard OH
rate per hour x actual hours

Continued….
Important Terms
Important Terms
5. Actual Overheads = Actual OH Rate per unit x Actual
Output or Actual Rate per hours x Actual hours
6. Standard H
ours for actual output
=
B
udgeted hours
Output
B
udgeted Output
7. Standard output for Actual T
ime
=B
udgeted Output
hours
B
udgeted hours

x Actual

x Actual
Fixed OH Cost Variance
Fixed OH Cost Variance
Fixed Overhead Cost Variance is the difference between standard
overhead recovered or absorbed for actual output and the actual fixed
overhead.
Can be computed using the formula:
Fixed OH Cost Variance = (Recovered or absorbed Fixed OH) – (Actual
Fixed OH)
OR
(Actual output) x (Standard OH Rate) – (Actual OH Rate x Actual
Output)
Thank you

More Related Content

What's hot

Standrad costing
Standrad costingStandrad costing
Standrad costing
Faltu Focat
 
Standard costing
Standard costingStandard costing
Standard costing
abner domingo
 
Standard Costing
Standard Costing Standard Costing
Standard Costing
Nitin Parbhakar
 
Standard cost
Standard costStandard cost
Standard cost
Rohit Mohan
 
Budgetory Control System and Cost Control
Budgetory Control System and Cost ControlBudgetory Control System and Cost Control
Budgetory Control System and Cost Control
Kishore Raveendran
 
Standard Costing Operational Performance Measures And
Standard Costing Operational Performance Measures AndStandard Costing Operational Performance Measures And
Standard Costing Operational Performance Measures And
afiali
 
Management accounting overhead variance
Management accounting   overhead varianceManagement accounting   overhead variance
Management accounting overhead variance
Biswajit Bhattacharjee
 
Ca chap 13 standard costing&variance analysis(2)
Ca chap 13 standard costing&variance analysis(2)Ca chap 13 standard costing&variance analysis(2)
Ca chap 13 standard costing&variance analysis(2)
DSDEVDA
 
Standard Costing
Standard CostingStandard Costing
Standard Costing
Md. Moazzem Hossain
 
Variance Formulae
Variance FormulaeVariance Formulae
Variance Formulae
Abdul Basit
 
Standard costs and variance analysis
Standard costs and variance analysisStandard costs and variance analysis
Standard costs and variance analysis
Sumit Malhotra
 
Mbaptscv ijuly2009 s
Mbaptscv ijuly2009 sMbaptscv ijuly2009 s
Mbaptscv ijuly2009 s
Kinshook Chaturvedi
 
Financial%20&%20 management%20accounting%20 %20chapter%2022%20(standard%20cos...
Financial%20&%20 management%20accounting%20 %20chapter%2022%20(standard%20cos...Financial%20&%20 management%20accounting%20 %20chapter%2022%20(standard%20cos...
Financial%20&%20 management%20accounting%20 %20chapter%2022%20(standard%20cos...
Kenesha Marshall
 
Standard costing
Standard costingStandard costing
Standard costing
Samitha Jayaweera
 
Standard Costing Day2
Standard Costing Day2Standard Costing Day2
Standard Costing Day2
Augustin Bangalore
 
standard costing & variances analysis
standard costing & variances analysisstandard costing & variances analysis
standard costing & variances analysis
Sanjaya Jayasundara
 
Variance Analysis
Variance AnalysisVariance Analysis
Variance Analysis
venkatesh y
 
Standard costing presentation
Standard costing presentationStandard costing presentation
Standard costing presentation
Jay Singh
 
Standard Costing
Standard CostingStandard Costing
Standard Costing
Tanmay C. Sant
 
Standard Costing & Variances
Standard Costing & VariancesStandard Costing & Variances
Standard Costing & Variances
Zareen Khan
 

What's hot (20)

Standrad costing
Standrad costingStandrad costing
Standrad costing
 
Standard costing
Standard costingStandard costing
Standard costing
 
Standard Costing
Standard Costing Standard Costing
Standard Costing
 
Standard cost
Standard costStandard cost
Standard cost
 
Budgetory Control System and Cost Control
Budgetory Control System and Cost ControlBudgetory Control System and Cost Control
Budgetory Control System and Cost Control
 
Standard Costing Operational Performance Measures And
Standard Costing Operational Performance Measures AndStandard Costing Operational Performance Measures And
Standard Costing Operational Performance Measures And
 
Management accounting overhead variance
Management accounting   overhead varianceManagement accounting   overhead variance
Management accounting overhead variance
 
Ca chap 13 standard costing&variance analysis(2)
Ca chap 13 standard costing&variance analysis(2)Ca chap 13 standard costing&variance analysis(2)
Ca chap 13 standard costing&variance analysis(2)
 
Standard Costing
Standard CostingStandard Costing
Standard Costing
 
Variance Formulae
Variance FormulaeVariance Formulae
Variance Formulae
 
Standard costs and variance analysis
Standard costs and variance analysisStandard costs and variance analysis
Standard costs and variance analysis
 
Mbaptscv ijuly2009 s
Mbaptscv ijuly2009 sMbaptscv ijuly2009 s
Mbaptscv ijuly2009 s
 
Financial%20&%20 management%20accounting%20 %20chapter%2022%20(standard%20cos...
Financial%20&%20 management%20accounting%20 %20chapter%2022%20(standard%20cos...Financial%20&%20 management%20accounting%20 %20chapter%2022%20(standard%20cos...
Financial%20&%20 management%20accounting%20 %20chapter%2022%20(standard%20cos...
 
Standard costing
Standard costingStandard costing
Standard costing
 
Standard Costing Day2
Standard Costing Day2Standard Costing Day2
Standard Costing Day2
 
standard costing & variances analysis
standard costing & variances analysisstandard costing & variances analysis
standard costing & variances analysis
 
Variance Analysis
Variance AnalysisVariance Analysis
Variance Analysis
 
Standard costing presentation
Standard costing presentationStandard costing presentation
Standard costing presentation
 
Standard Costing
Standard CostingStandard Costing
Standard Costing
 
Standard Costing & Variances
Standard Costing & VariancesStandard Costing & Variances
Standard Costing & Variances
 

Similar to Amresh management accounting

Bca i fma u 4.4 varience analysis
Bca i fma u 4.4 varience analysisBca i fma u 4.4 varience analysis
Bca i fma u 4.4 varience analysis
Rai University
 
Mca i fma u 4.4 varience analysis
Mca i fma u 4.4 varience analysisMca i fma u 4.4 varience analysis
Mca i fma u 4.4 varience analysis
Rai University
 
Standard costing and variances
Standard costing and variancesStandard costing and variances
Standard costing and variances
pankajmaini
 
Standard costing summary
Standard costing summaryStandard costing summary
Standard costing summary
CMAChanderDurejaClas
 
3901853 standard-costing
3901853 standard-costing3901853 standard-costing
3901853 standard-costing
SUMITMISHRA882344
 
Variance Analysis
Variance Analysis Variance Analysis
Variance Analysis
MACFAST
 
Managerial Accounting Project.pptx
Managerial Accounting Project.pptxManagerial Accounting Project.pptx
Managerial Accounting Project.pptx
TeeshaGehaniJagdesh
 
Standard Costs Variance Analysis and its impact on Managerial Accounting
Standard Costs Variance Analysis and its impact on Managerial AccountingStandard Costs Variance Analysis and its impact on Managerial Accounting
Standard Costs Variance Analysis and its impact on Managerial Accounting
Ghous2
 
Standard-Costing-Variance-Analysis.ppt
Standard-Costing-Variance-Analysis.pptStandard-Costing-Variance-Analysis.ppt
Standard-Costing-Variance-Analysis.ppt
JomarDoctora
 
181572.pdf
181572.pdf181572.pdf
181572.pdf
AryanPasrija2
 
Projecto variance
Projecto varianceProjecto variance
Projecto variance
Marcos Rodriguez
 
Standard costing setting standards and analysis of variance
Standard costing setting standards and analysis of varianceStandard costing setting standards and analysis of variance
Standard costing setting standards and analysis of variance
Quaid-i-Azam University Islamabad
 
Understanding SAP production order variance
Understanding SAP production order varianceUnderstanding SAP production order variance
Understanding SAP production order variance
Dhaval Gala
 
aaa aaa variance analysis.ppt
aaa aaa   variance  analysis.pptaaa aaa   variance  analysis.ppt
aaa aaa variance analysis.ppt
ssuser14de24
 
Variance Formulae
Variance FormulaeVariance Formulae
Variance Formulae
Abdul Basit
 
STANDARD COSTING & VARIANCE ANALYSIS (4).pptx
STANDARD COSTING & VARIANCE ANALYSIS (4).pptxSTANDARD COSTING & VARIANCE ANALYSIS (4).pptx
STANDARD COSTING & VARIANCE ANALYSIS (4).pptx
MaheshGV4
 
Advancedcostaccounting 140417192903-phpapp02
Advancedcostaccounting 140417192903-phpapp02Advancedcostaccounting 140417192903-phpapp02
Advancedcostaccounting 140417192903-phpapp02
Anqur Rauth
 
Standard costing
Standard costingStandard costing
Standard costing
zaidul2
 
Standard costing
Standard costingStandard costing
Standard costing
nishat2
 
Standard Costing
Standard CostingStandard Costing
Standard Costing
narman1402
 

Similar to Amresh management accounting (20)

Bca i fma u 4.4 varience analysis
Bca i fma u 4.4 varience analysisBca i fma u 4.4 varience analysis
Bca i fma u 4.4 varience analysis
 
Mca i fma u 4.4 varience analysis
Mca i fma u 4.4 varience analysisMca i fma u 4.4 varience analysis
Mca i fma u 4.4 varience analysis
 
Standard costing and variances
Standard costing and variancesStandard costing and variances
Standard costing and variances
 
Standard costing summary
Standard costing summaryStandard costing summary
Standard costing summary
 
3901853 standard-costing
3901853 standard-costing3901853 standard-costing
3901853 standard-costing
 
Variance Analysis
Variance Analysis Variance Analysis
Variance Analysis
 
Managerial Accounting Project.pptx
Managerial Accounting Project.pptxManagerial Accounting Project.pptx
Managerial Accounting Project.pptx
 
Standard Costs Variance Analysis and its impact on Managerial Accounting
Standard Costs Variance Analysis and its impact on Managerial AccountingStandard Costs Variance Analysis and its impact on Managerial Accounting
Standard Costs Variance Analysis and its impact on Managerial Accounting
 
Standard-Costing-Variance-Analysis.ppt
Standard-Costing-Variance-Analysis.pptStandard-Costing-Variance-Analysis.ppt
Standard-Costing-Variance-Analysis.ppt
 
181572.pdf
181572.pdf181572.pdf
181572.pdf
 
Projecto variance
Projecto varianceProjecto variance
Projecto variance
 
Standard costing setting standards and analysis of variance
Standard costing setting standards and analysis of varianceStandard costing setting standards and analysis of variance
Standard costing setting standards and analysis of variance
 
Understanding SAP production order variance
Understanding SAP production order varianceUnderstanding SAP production order variance
Understanding SAP production order variance
 
aaa aaa variance analysis.ppt
aaa aaa   variance  analysis.pptaaa aaa   variance  analysis.ppt
aaa aaa variance analysis.ppt
 
Variance Formulae
Variance FormulaeVariance Formulae
Variance Formulae
 
STANDARD COSTING & VARIANCE ANALYSIS (4).pptx
STANDARD COSTING & VARIANCE ANALYSIS (4).pptxSTANDARD COSTING & VARIANCE ANALYSIS (4).pptx
STANDARD COSTING & VARIANCE ANALYSIS (4).pptx
 
Advancedcostaccounting 140417192903-phpapp02
Advancedcostaccounting 140417192903-phpapp02Advancedcostaccounting 140417192903-phpapp02
Advancedcostaccounting 140417192903-phpapp02
 
Standard costing
Standard costingStandard costing
Standard costing
 
Standard costing
Standard costingStandard costing
Standard costing
 
Standard Costing
Standard CostingStandard Costing
Standard Costing
 

Amresh management accounting

  • 1.
  • 2. Classification Variances are broadly classified into the following:
  • 3. Material Cost Variance Material Cost Variance Material Cost Variance is the difference between the actual cost of direct materials used and standard cost of direct materials specified for the output achieved. This variance results from differences between quantities consumed and quantities of materials allowed for production and from differences between prices paid and prices predetermined. Can be computed using the formula: Material Cost Variance = (SQ x SP) – (AQ x AP)
  • 4. Material Price Variance A Materials Price Variance occurs when raw materials are purchased at a price different from standard price. It is that portion of the direct materials which is due to the difference between actual price paid and standard price specified Can be computed using the formula: Material Price Variance = (Standard Price – Actual Price) x Actual Quantity This variance is unfavourable when the actual price paid exceeds the predetermined standard price. It is advisable that materials price variance should be calculated at the time of materials purchase rather than when materials are used. This is quite beneficial from the viewpoint of performance measurement and corrective action.
  • 5. Materials Usage Variance The material quantity or usage variance results when actual quantities of raw materials used in production differ from standard quantities that should have been used to produce the output achieved. It is that portion of the direct materials cost variance which is due to the difference between the actual quantity used and standard quantity specified. Can be computed using the formula: Material Qty. variance = (SQ for actual output – AQ ) x Standard Price This variance is favourable when the total actual quantity of direct materials used is less than the total standard quantity allowed for the actual output.
  • 6. Material Mix Variance *The material mix variance is an sub variance of materials usage variance it arises only where more than one type of materials is used for producing a product . * Increase in the proportion of cheaper materials result in favourable mix variance & vice versa Can be computed using the formula: Material Mix variance = (Revised Standard Qty. – AQ ) x Standard Price Revised Standard Quantity = x SQ
  • 7. Materials Yield Variance Materials Yield Variance The material yield variance explains the remaining portion of the total materials quantity variance. It occurs when output of the final product does not match with the output that could have been obtained by using the actual inputs. It is that portion of the materials usage variance which is due to the difference between the actual yield obtained and the standard yield specified (in terms of actual inputs). Can be computed using the formula: Material Yield variance = (Standard yield or output for actual input – Actual yield or output) x Standard Cost per unit Standard Cost per unit = Total cost of standard mix of material Net standard output quantity
  • 9. Labour Cost Variance Labour Cost Variance denotes the difference between the actual Cost and standard of direct labour Can be computed using the formula: Labour Cost Variance = (SH x SR) – (AH x AR) When the actual variance.cost labour cost is more than standard cost, there will be adverse
  • 10. Labour Rate Variance A Labours Rate Variance is the difference between the standard labour rate specified and the actual labour rate paid. It is an uncontrollable variance as the labour rate are usually dertermined by supply & supply & demand conditions in the labour market Can be computed using the formula: Labour Rate Variance = (Standard Wage Rate – Actual Rate) x Actual Time This variance is adverse when the actual wage rate paid exceeds the predetermined standard wage rate. Reasons for labour rate variance : 1)Change in the basic wage rate . 2)Use of diferent methods of wage payment . 3)Unscheduled overtime. 4)New workers not paid full wages
  • 11. Labour Efficiency Variance The Labour time or efficiency variance is the result of taking more or less time than the standard time specified for the performance of a work. It is that portion of the Labour cost variance which is due to the difference between the actual labour hour expended and standard labour hours specified. Can be computed using the formula: Labour Efficiency variance = (SH for actual output – AH ) x Standard Rate This variance is favourable when the total actual hours are less than the standard hours allowed. Reasons for LEV 1)`Using low qty materials 2)Improper working conditions .
  • 12. Idle Time Variance It is a sub-variance of Wage Efficiency or Time Variance. The standard cost of actual hours of any employee may remain idle due to abnormal circumstances like strikes, lock outs, power failure etc. Standard cost of such idle time is called Idle Time Variance. It is always adverse or unfavourable. Can be computed using the formula: Idle Time variance = Idle Hours x Standard Rate per hour
  • 13. Labour Mix Variance LMV arises only when more than 1 grade of workers are employed on a job , here grade refers to skilled & unskilled Can be computed using the formula: Labour Mix variance = (Revised Standard labour hours – AH ) x Standard Wage rate
  • 14. Labours Yield Variance The Labour yield variance occurs when there is a difference between standard output and actual output. Can be computed using the formula: Labour Yield variance = (Standard yield or output for actual mix– Actual yield or output) x Standard labour Cost per unit
  • 15. Variable OH Variances Variable Overhead Variance represents he difference between standard variable overhead (specified for actual units produced) and the actual variable overhead incurred. Can be computed using the formula: Variable OH Cost Variance = Standard Variable OH on actual production – Actual variable OH OR Variable OH Cost variance = (Actual time or standard hours for actual production x Standard variable OH Rate) – (Actual Variable OH)
  • 16. Sub-division There may be two sub divisions of variable overhead variance. (i) Variable Overhead Expenditure or Budget Variance = Standard Variable Overheads for actual time – Actual variable overheads Standard variable OH for actual time = standard variable OH rate per hour x actual hours (ii) Variable OH Efficiency Variance = Standard Variable Overheads on actual production – standard variable overheads for actual time Standard or budgeted variable overhead for actual time = Standard OH Rate per hour x Actual Hours Standard variable OH on actual production = standard variable OH per unit x Actual output
  • 17. Fixed OH Variances T erms to be understood before calculating OH Variances: 1. Standard OH Rate per unit or per hour or B udgeted OH Rate per unit = B udgeted Overheads B udgeted Output Units or B udgeted H ours or per hour 2. Recovered or Absorbed Overheads = Standard OH R ate per unit x Actual Output or Standard OH Rate per hour x Standard hours for actual output 3. B udgeted Overheads (for budgeted hours or budgeted output): = Standard OH rate per unit x B udgeted output units or Standard overhead rate per hour x budgeted hours. 4. Standard Overheads (for actual time or budgeted output for actual time) = Standard OH Rate per unit x Standard output for actual time or Standard OH rate per hour x actual hours Continued….
  • 18. Important Terms Important Terms 5. Actual Overheads = Actual OH Rate per unit x Actual Output or Actual Rate per hours x Actual hours 6. Standard H ours for actual output = B udgeted hours Output B udgeted Output 7. Standard output for Actual T ime =B udgeted Output hours B udgeted hours x Actual x Actual
  • 19. Fixed OH Cost Variance Fixed OH Cost Variance Fixed Overhead Cost Variance is the difference between standard overhead recovered or absorbed for actual output and the actual fixed overhead. Can be computed using the formula: Fixed OH Cost Variance = (Recovered or absorbed Fixed OH) – (Actual Fixed OH) OR (Actual output) x (Standard OH Rate) – (Actual OH Rate x Actual Output)