International Competitive BiddingGeneral Asian Development Bank Procurement Guidelines
Introduction Para 2.1 The objective of international competitive bidding (ICB), as described in these Guidelines, is to provide all eligible prospective bidders15 with timely and adequate notification of a borrower’s requirements and an equal opportunity to bid for the required goods and works.
General Type and Size of Contracts
Type and Size of Contracts Para 2.2  The bidding documents shall clearly state the type of contract to be entered into and contain the proposed contract provisions appropriate therefore.  The most common types of contracts provide for payments on the basis of a lump sum or unit prices, or combinations thereof.
Type and Size of Contracts Para 2.3  The size and scope of individual contracts will depend on the magnitude, nature, and location of the project.  For projects requiring a variety of goods and works, separate contracts generally are awarded for the supply and/or installation of different items of equipment and plant16 and for the works.
Type and Size of Contracts Para 2.4  For a project requiring similar but separate items of equipment or works, bids may be invited under alternative contract options that would attract the interest of both small and large firms, which could be allowed, at their option, to bid for individual contracts (slices) or for a group of similar contracts (package).  All bids and combinations of bids shall be received by the same deadline and opened and evaluated simultaneously so as to determine the bid or combination of bids offering the lowest evaluated cost to the borrower.17
Type and Size of Contracts Para 2.5  In certain cases ADB may accept or require a turnkey contract under which the design and engineering, the supply and installation of equipment, and the construction of a complete facility or works are provided under one contract.  Alternatively, the borrower may remain responsible for the design and engineering, and invite bids for a single responsibility contract for the supply and installation of all goods and works required for the project component. Design and build, and management contracting18 contracts are also acceptable where appropriate.19
General Two-Stage Bidding
Two-Stage Bidding  Para 2.6 (a) In the case of turnkey contracts or contracts for large complex facilities or works of a special nature or complex information and communication technology, it may be undesirable or impractical to prepare complete technical specifications in advance. In such a case, a two-stage bidding procedure may be used, under which unpriced technical proposals are invited first.  These are prepared on the basis of a conceptual design or performance specification, and are subject to technical as well as commercial clarifications and adjustments.  The first stage technical proposal clarification is to be followed by issuance of amended bidding documents20 and the submission of final technical proposals and priced bids in the second stage.
Two-Stage Bidding  Para 2.6 (b) Two-envelope procedures, wherein bids with separate envelopes for technical and financial proposals are submitted simultaneously, may be used for the procurement of goods, works or turnkey contracts. The borrower has the option to use the two-envelope procedure with single-stage or two-stage bidding.  In the single-stage, two-envelope procedure, the technical proposal is opened first and reviewed to determine responsiveness to the bidding documents.  Only the financial proposals of bidders with responsive technical proposals are opened for evaluation and comparison. The financial proposals of bidders whose technical proposals are not responsive shall be returned unopened.
Two-Stage Bidding  Para 2.6 (b) In the two-stage, two-envelope procedure, bidders are allowed to amend their technical proposals in order to ensure conformance to the same technical standards. Only the financial proposals, including supplementary price proposals, of bidders whose original or revised technical proposals are found conforming to the agreed technical standards, are opened for evaluation and comparison.  The use of these procedures must be agreed upon by ADB and the borrower.
General Notification and Advertising
Notification and Advertising  Para 2.7  Timely notification of bidding opportunities is essential in competitive bidding. For projects that include ICB the borrower is required to prepare and submit to ADB a draft general procurement notice. ADB will arrange for its publication.21  The notice shall contain information concerning  the borrower (or prospective borrower),  amount and purpose of the loan,  scope of procurement under ICB, and  the name, telephone number, email address (or fax number) and address of the borrower’s agency responsible for procurement and the address of the website where specific procurement notices will be posted.
Notification and Advertising  Para 2.7  If known, the scheduled date for availability of prequalification or bidding documents should be indicated. Except in the case of advance contracting22 the related prequalification or bidding documents, as the case may be, shall not be released to the public earlier than the date of publication of the general procurement notice.
Notification and Advertising  Para 2.8  Invitations to prequalify or to bid, as the case may be, shall be advertised as specific procurement notices in ADB’s website as well as in  a newspaper of national circulation in the borrower’s country (at least in one English language newspaper, if available), or  on an internationally known and freely accessible website in English.  A copy of the invitation for bids shall be submitted to ADB for approval and for publication in ADB’s website in accordance with the provisions of the financing agreement.
General Prequalification of Bidders
Prequalification of Bidders  Para 2.9  Prequalification may be necessary for large or complex works, or in any other circumstances in which the high costs of preparing detailed bids could discourage competition, such as custom-designed equipment,  industrial plant,  specialized services,  some complex information and technology contracts and  contracts to be let under turnkey, design and build, or management contracting.  This also ensures that invitations to bid are extended only to those who have adequate capabilities and resources
Prequalification of Bidders  Para 2.9  Prequalification shall be based entirely upon the capability and resources of prospective bidders to perform the particular contract satisfactorily, taking into account their  experience and past performance on similar contracts,  capabilities with respect to construction or manufacturing facilities, and  financial position.23
Prequalification of Bidders  Para 2.10  The invitation to prequalify for bidding on specific contracts or groups of similar contracts shall be advertised and notified as described in paragraphs 2.7 and 2.8 above.  The scope of the contract and a clear statement of the requirements for qualification shall be sent to those who responded to the invitation. Generally, a minimum period of six weeks shall be allowed for the submission of prequalification applications.  There shall be no limits on the number of bidders to be prequalified, and all found capable of performing the work satisfactorily in accordance with the approved prequalification criteria shall be prequalified and invited to submit bids.
Prequalification of Bidders  Para 2.10  As soon as prequalification is completed, the bidding documents shall be made available to the prequalified prospective bidders.  For prequalification for groups of contracts to be awarded over a period of time, a limit for the number or total value of awards to any one bidder may be made on the basis of the bidder’s resources.  The list of prequalified firms in such instances shall be updated periodically.  Verification of the information provided in the submission for prequalification shall be confirmed at the time of award of contract, and award may be denied to a bidder that is judged to no longer have the capability or resources to successfully perform the contract.

More Related Content

What's hot

Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
Muneesh Methwani
 

What's hot (20)

Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Tendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessTendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award Process
 
Quantity Surveyor presentation
Quantity Surveyor presentationQuantity Surveyor presentation
Quantity Surveyor presentation
 
Unit-2_Tender
Unit-2_TenderUnit-2_Tender
Unit-2_Tender
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Tender and tender document
Tender and tender documentTender and tender document
Tender and tender document
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
 
Tendering
TenderingTendering
Tendering
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Clause 16 suspension
Clause 16 suspensionClause 16 suspension
Clause 16 suspension
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Types of contract
Types of contractTypes of contract
Types of contract
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post q
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Tender
TenderTender
Tender
 
Real Estate (Development & Regulation) Act, 2016
Real Estate (Development & Regulation) Act, 2016Real Estate (Development & Regulation) Act, 2016
Real Estate (Development & Regulation) Act, 2016
 
QUANTITY SURVEYOR magazine
QUANTITY SURVEYOR magazineQUANTITY SURVEYOR magazine
QUANTITY SURVEYOR magazine
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
 

Viewers also liked

PRMG-080 Projects Bids and Contracts Certificate
PRMG-080 Projects Bids and Contracts CertificatePRMG-080 Projects Bids and Contracts Certificate
PRMG-080 Projects Bids and Contracts Certificate
Islam Nour
 
Sales management ppt
Sales management pptSales management ppt
Sales management ppt
9436418562
 
Introduction to sales management
Introduction to sales managementIntroduction to sales management
Introduction to sales management
Gautam Anand
 

Viewers also liked (11)

AUC Certificate - Projects, Bids and Contracts
AUC Certificate - Projects, Bids and ContractsAUC Certificate - Projects, Bids and Contracts
AUC Certificate - Projects, Bids and Contracts
 
PRMG-080 Projects Bids and Contracts Certificate
PRMG-080 Projects Bids and Contracts CertificatePRMG-080 Projects Bids and Contracts Certificate
PRMG-080 Projects Bids and Contracts Certificate
 
Apm opm branch presentation april 2016
Apm opm branch presentation april 2016 Apm opm branch presentation april 2016
Apm opm branch presentation april 2016
 
Project manager's survival guide to bids, tenders and proposals workshop by D...
Project manager's survival guide to bids, tenders and proposals workshop by D...Project manager's survival guide to bids, tenders and proposals workshop by D...
Project manager's survival guide to bids, tenders and proposals workshop by D...
 
Introduction to sales management
Introduction to sales management Introduction to sales management
Introduction to sales management
 
Concepts of sales management
Concepts of sales managementConcepts of sales management
Concepts of sales management
 
An Introduction to Sales Management
An Introduction to Sales ManagementAn Introduction to Sales Management
An Introduction to Sales Management
 
Sales management ppt
Sales management pptSales management ppt
Sales management ppt
 
Sales management
Sales managementSales management
Sales management
 
Introduction To Sales Management
 Introduction To Sales Management Introduction To Sales Management
Introduction To Sales Management
 
Introduction to sales management
Introduction to sales managementIntroduction to sales management
Introduction to sales management
 

Similar to Adb procurement guidelines icb-a

Wb procurement icb a
Wb procurement icb aWb procurement icb a
Wb procurement icb a
Joy Irman
 
Adb procurement guidelines icb-b1
Adb procurement guidelines   icb-b1Adb procurement guidelines   icb-b1
Adb procurement guidelines icb-b1
Joy Irman
 
Wb procurement icb b1
Wb procurement icb b1Wb procurement icb b1
Wb procurement icb b1
Joy Irman
 
Adb procurement guidelines icb-b2
Adb procurement guidelines   icb-b2Adb procurement guidelines   icb-b2
Adb procurement guidelines icb-b2
Joy Irman
 
Itt provision of wi fi network design and implementation services
Itt   provision of wi fi network design and implementation servicesItt   provision of wi fi network design and implementation services
Itt provision of wi fi network design and implementation services
abenyeung1
 
Wb procurement icb c2
Wb procurement icb c2Wb procurement icb c2
Wb procurement icb c2
Joy Irman
 
Adb procurement guidelines icb-c1
Adb procurement guidelines   icb-c1Adb procurement guidelines   icb-c1
Adb procurement guidelines icb-c1
Joy Irman
 

Similar to Adb procurement guidelines icb-a (20)

Wb procurement icb a
Wb procurement icb aWb procurement icb a
Wb procurement icb a
 
Adb procurement guidelines icb-b1
Adb procurement guidelines   icb-b1Adb procurement guidelines   icb-b1
Adb procurement guidelines icb-b1
 
Wb procurement icb b1
Wb procurement icb b1Wb procurement icb b1
Wb procurement icb b1
 
Mode of Tendering.pptx
 Mode of Tendering.pptx Mode of Tendering.pptx
Mode of Tendering.pptx
 
Pai 3-03
Pai 3-03Pai 3-03
Pai 3-03
 
4. international procurement guideline
4. international procurement guideline4. international procurement guideline
4. international procurement guideline
 
1658466483_Supply_of_Stationery_Items_English.pdf
1658466483_Supply_of_Stationery_Items_English.pdf1658466483_Supply_of_Stationery_Items_English.pdf
1658466483_Supply_of_Stationery_Items_English.pdf
 
Ppra rules 2004
Ppra rules   2004Ppra rules   2004
Ppra rules 2004
 
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
 
Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)
Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)
Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)
 
Adb procurement guidelines icb-b2
Adb procurement guidelines   icb-b2Adb procurement guidelines   icb-b2
Adb procurement guidelines icb-b2
 
Final standard tender doc
Final standard tender docFinal standard tender doc
Final standard tender doc
 
Document samples
Document samplesDocument samples
Document samples
 
Bid document for Solar in Himachal Pradesh
Bid document for Solar in Himachal PradeshBid document for Solar in Himachal Pradesh
Bid document for Solar in Himachal Pradesh
 
Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”
 
Itt provision of wi fi network design and implementation services
Itt   provision of wi fi network design and implementation servicesItt   provision of wi fi network design and implementation services
Itt provision of wi fi network design and implementation services
 
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
 
Wb procurement icb c2
Wb procurement icb c2Wb procurement icb c2
Wb procurement icb c2
 
Tenders , Invitation of tender
Tenders , Invitation of tender Tenders , Invitation of tender
Tenders , Invitation of tender
 
Adb procurement guidelines icb-c1
Adb procurement guidelines   icb-c1Adb procurement guidelines   icb-c1
Adb procurement guidelines icb-c1
 

More from Joy Irman

Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010
Joy Irman
 
Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010
Joy Irman
 
Lampiran iv b jasa konsultansi - perorangan
Lampiran iv b   jasa konsultansi - peroranganLampiran iv b   jasa konsultansi - perorangan
Lampiran iv b jasa konsultansi - perorangan
Joy Irman
 
Lampiran iv a jasa konsultansi - badan usaha
Lampiran iv a   jasa konsultansi - badan usahaLampiran iv a   jasa konsultansi - badan usaha
Lampiran iv a jasa konsultansi - badan usaha
Joy Irman
 
5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola
Joy Irman
 
3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaan3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaan
Joy Irman
 

More from Joy Irman (20)

Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010
 
Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010
 
Lampiran iv b jasa konsultansi - perorangan
Lampiran iv b   jasa konsultansi - peroranganLampiran iv b   jasa konsultansi - perorangan
Lampiran iv b jasa konsultansi - perorangan
 
Lampiran iv a jasa konsultansi - badan usaha
Lampiran iv a   jasa konsultansi - badan usahaLampiran iv a   jasa konsultansi - badan usaha
Lampiran iv a jasa konsultansi - badan usaha
 
Consulting Services Operation Manual, Asian Development Bank
Consulting Services Operation Manual, Asian Development BankConsulting Services Operation Manual, Asian Development Bank
Consulting Services Operation Manual, Asian Development Bank
 
Guidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank FinancingGuidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank Financing
 
Guidelines for the Employment of Consultants under Japanese ODA Loans
Guidelines for the Employment of Consultants under Japanese ODA LoansGuidelines for the Employment of Consultants under Japanese ODA Loans
Guidelines for the Employment of Consultants under Japanese ODA Loans
 
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
 
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
 
12 konsep ramah lingkungan
12 konsep ramah lingkungan12 konsep ramah lingkungan
12 konsep ramah lingkungan
 
13 pengadaan secara elektronik
13 pengadaan secara elektronik13 pengadaan secara elektronik
13 pengadaan secara elektronik
 
6 1 persiapan dan perencanaan pengadaan
6 1 persiapan dan perencanaan pengadaan6 1 persiapan dan perencanaan pengadaan
6 1 persiapan dan perencanaan pengadaan
 
3 1 organisasi pengadaan
3 1 organisasi pengadaan3 1 organisasi pengadaan
3 1 organisasi pengadaan
 
4 rencana umum pengadaan barang
4 rencana umum pengadaan barang4 rencana umum pengadaan barang
4 rencana umum pengadaan barang
 
5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola
 
5 1 ketentuan umum swakelola
5 1 ketentuan umum swakelola5 1 ketentuan umum swakelola
5 1 ketentuan umum swakelola
 
3 7 penyedia barang jasa
3 7 penyedia barang jasa3 7 penyedia barang jasa
3 7 penyedia barang jasa
 
3 6 pejabat penerima hasil pekerjaan
3 6 pejabat penerima hasil pekerjaan3 6 pejabat penerima hasil pekerjaan
3 6 pejabat penerima hasil pekerjaan
 
3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaan3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaan
 
3 4 pejabat pembuat komitmen
3 4 pejabat pembuat komitmen3 4 pejabat pembuat komitmen
3 4 pejabat pembuat komitmen
 

Recently uploaded

chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
AUDIJEAngelo
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
LR1709MUSIC
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
seri bangash
 

Recently uploaded (20)

HR and Employment law update: May 2024.
HR and Employment law update:  May 2024.HR and Employment law update:  May 2024.
HR and Employment law update: May 2024.
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
Maximizing Efficiency Migrating AccountEdge Data to QuickBooks.pdf
Maximizing Efficiency Migrating AccountEdge Data to QuickBooks.pdfMaximizing Efficiency Migrating AccountEdge Data to QuickBooks.pdf
Maximizing Efficiency Migrating AccountEdge Data to QuickBooks.pdf
 
chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
 
Lookback Analysis
Lookback AnalysisLookback Analysis
Lookback Analysis
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
 
G-Mica Wood Chip Particle board Table Design
G-Mica Wood Chip Particle board Table DesignG-Mica Wood Chip Particle board Table Design
G-Mica Wood Chip Particle board Table Design
 
New Product Development.kjiy7ggbfdsddggo9lo
New Product Development.kjiy7ggbfdsddggo9loNew Product Development.kjiy7ggbfdsddggo9lo
New Product Development.kjiy7ggbfdsddggo9lo
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
12 Conversion Rate Optimization Strategies for Ecommerce Websites.pdf
12 Conversion Rate Optimization Strategies for Ecommerce Websites.pdf12 Conversion Rate Optimization Strategies for Ecommerce Websites.pdf
12 Conversion Rate Optimization Strategies for Ecommerce Websites.pdf
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 
Strategy Analysis and Selecting ( Space Matrix)
Strategy Analysis and Selecting ( Space Matrix)Strategy Analysis and Selecting ( Space Matrix)
Strategy Analysis and Selecting ( Space Matrix)
 
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
 
Team-Spandex-Northern University-CS1035.
Team-Spandex-Northern University-CS1035.Team-Spandex-Northern University-CS1035.
Team-Spandex-Northern University-CS1035.
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
 
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
 

Adb procurement guidelines icb-a

  • 1. International Competitive BiddingGeneral Asian Development Bank Procurement Guidelines
  • 2. Introduction Para 2.1 The objective of international competitive bidding (ICB), as described in these Guidelines, is to provide all eligible prospective bidders15 with timely and adequate notification of a borrower’s requirements and an equal opportunity to bid for the required goods and works.
  • 3. General Type and Size of Contracts
  • 4. Type and Size of Contracts Para 2.2 The bidding documents shall clearly state the type of contract to be entered into and contain the proposed contract provisions appropriate therefore. The most common types of contracts provide for payments on the basis of a lump sum or unit prices, or combinations thereof.
  • 5. Type and Size of Contracts Para 2.3 The size and scope of individual contracts will depend on the magnitude, nature, and location of the project. For projects requiring a variety of goods and works, separate contracts generally are awarded for the supply and/or installation of different items of equipment and plant16 and for the works.
  • 6. Type and Size of Contracts Para 2.4 For a project requiring similar but separate items of equipment or works, bids may be invited under alternative contract options that would attract the interest of both small and large firms, which could be allowed, at their option, to bid for individual contracts (slices) or for a group of similar contracts (package). All bids and combinations of bids shall be received by the same deadline and opened and evaluated simultaneously so as to determine the bid or combination of bids offering the lowest evaluated cost to the borrower.17
  • 7. Type and Size of Contracts Para 2.5 In certain cases ADB may accept or require a turnkey contract under which the design and engineering, the supply and installation of equipment, and the construction of a complete facility or works are provided under one contract. Alternatively, the borrower may remain responsible for the design and engineering, and invite bids for a single responsibility contract for the supply and installation of all goods and works required for the project component. Design and build, and management contracting18 contracts are also acceptable where appropriate.19
  • 9. Two-Stage Bidding Para 2.6 (a) In the case of turnkey contracts or contracts for large complex facilities or works of a special nature or complex information and communication technology, it may be undesirable or impractical to prepare complete technical specifications in advance. In such a case, a two-stage bidding procedure may be used, under which unpriced technical proposals are invited first. These are prepared on the basis of a conceptual design or performance specification, and are subject to technical as well as commercial clarifications and adjustments. The first stage technical proposal clarification is to be followed by issuance of amended bidding documents20 and the submission of final technical proposals and priced bids in the second stage.
  • 10. Two-Stage Bidding Para 2.6 (b) Two-envelope procedures, wherein bids with separate envelopes for technical and financial proposals are submitted simultaneously, may be used for the procurement of goods, works or turnkey contracts. The borrower has the option to use the two-envelope procedure with single-stage or two-stage bidding. In the single-stage, two-envelope procedure, the technical proposal is opened first and reviewed to determine responsiveness to the bidding documents. Only the financial proposals of bidders with responsive technical proposals are opened for evaluation and comparison. The financial proposals of bidders whose technical proposals are not responsive shall be returned unopened.
  • 11. Two-Stage Bidding Para 2.6 (b) In the two-stage, two-envelope procedure, bidders are allowed to amend their technical proposals in order to ensure conformance to the same technical standards. Only the financial proposals, including supplementary price proposals, of bidders whose original or revised technical proposals are found conforming to the agreed technical standards, are opened for evaluation and comparison. The use of these procedures must be agreed upon by ADB and the borrower.
  • 13. Notification and Advertising Para 2.7 Timely notification of bidding opportunities is essential in competitive bidding. For projects that include ICB the borrower is required to prepare and submit to ADB a draft general procurement notice. ADB will arrange for its publication.21 The notice shall contain information concerning the borrower (or prospective borrower), amount and purpose of the loan, scope of procurement under ICB, and the name, telephone number, email address (or fax number) and address of the borrower’s agency responsible for procurement and the address of the website where specific procurement notices will be posted.
  • 14. Notification and Advertising Para 2.7 If known, the scheduled date for availability of prequalification or bidding documents should be indicated. Except in the case of advance contracting22 the related prequalification or bidding documents, as the case may be, shall not be released to the public earlier than the date of publication of the general procurement notice.
  • 15. Notification and Advertising Para 2.8 Invitations to prequalify or to bid, as the case may be, shall be advertised as specific procurement notices in ADB’s website as well as in a newspaper of national circulation in the borrower’s country (at least in one English language newspaper, if available), or on an internationally known and freely accessible website in English. A copy of the invitation for bids shall be submitted to ADB for approval and for publication in ADB’s website in accordance with the provisions of the financing agreement.
  • 17. Prequalification of Bidders Para 2.9 Prequalification may be necessary for large or complex works, or in any other circumstances in which the high costs of preparing detailed bids could discourage competition, such as custom-designed equipment, industrial plant, specialized services, some complex information and technology contracts and contracts to be let under turnkey, design and build, or management contracting. This also ensures that invitations to bid are extended only to those who have adequate capabilities and resources
  • 18. Prequalification of Bidders Para 2.9 Prequalification shall be based entirely upon the capability and resources of prospective bidders to perform the particular contract satisfactorily, taking into account their experience and past performance on similar contracts, capabilities with respect to construction or manufacturing facilities, and financial position.23
  • 19. Prequalification of Bidders Para 2.10 The invitation to prequalify for bidding on specific contracts or groups of similar contracts shall be advertised and notified as described in paragraphs 2.7 and 2.8 above. The scope of the contract and a clear statement of the requirements for qualification shall be sent to those who responded to the invitation. Generally, a minimum period of six weeks shall be allowed for the submission of prequalification applications. There shall be no limits on the number of bidders to be prequalified, and all found capable of performing the work satisfactorily in accordance with the approved prequalification criteria shall be prequalified and invited to submit bids.
  • 20. Prequalification of Bidders Para 2.10 As soon as prequalification is completed, the bidding documents shall be made available to the prequalified prospective bidders. For prequalification for groups of contracts to be awarded over a period of time, a limit for the number or total value of awards to any one bidder may be made on the basis of the bidder’s resources. The list of prequalified firms in such instances shall be updated periodically. Verification of the information provided in the submission for prequalification shall be confirmed at the time of award of contract, and award may be denied to a bidder that is judged to no longer have the capability or resources to successfully perform the contract.