A TRICKY TASK SCHEDULING TECHNIQUE TO OPTIMIZE TIME
COST AND RELIABILITY IN MOBILE COMPUTING ENVIRONMENT
Faizul Navi Khan1
, Kapil Govil2
1
Department of Computer Application, Teerthanker Mahaveer University, Moradabad - 244 001, UP, INDIA
2
Department of Computer Application, Teerthanker Mahaveer University, Moradabad - 244 001, UP, INDIA
Abstract
Mobile Computing Environment (MCE) consisting portable computing devices interconnected by wireless medium, are
increasingly being used in many area of science, business and education etc nowadays. It is the computation made over physical
mobility. MCE facilitate the user to perform a task from a distant place from the device. This provides flexible communication
between user and continuous access to networked services. Mobile computing shares many features with distributed computing as
the application runs in MCE executes in distributed manner i.e. an application is combination of multiple tasks and these task
schedule on the available resources to be execute. The performance of an application is depending on task scheduling technique
in MCE. Task scheduling technique consist in finding an allocation of the tasks to the processors such that the total execution cost
and time are minimized or processing reliability is maximized. So the ultimate objective of finding task scheduling technique is to
improve the performance in terms to minimize cost and time and maximize reliability of MCE. In MCE an application can be seen
as one or multiple task modules and each of the task modules allocate on available processor for its execution. Therefore, in this
paper, the problem of scheduling the tasks in mobile computing environment is explore with objectives to minimize processing
cost, processing time or maximize the processing reliability through a new task scheduling technique to optimize performance in
MCE. The nature of the assignment will be static.
Keywords – Cost, Mobile Computing Environment, Performance, Reliability, Task scheduling
--------------------------------------------------------------------***-------------------------------------------------------------------
1. INTRODUCTION
Advances in communication and computing technologies
have introduced a new way of computing environment, called
„Mobile Computing Environment (MCE)‟, which allows
mobility of users thereby providing “anytime anywhere”
computing environment. The mobility of user (or device)
results in a highly dynamic environments with respect to the
availability of resources/infrastructures for any application
running on the mobile devices. Also, in a mobile computing
environment, location has a profound effect. A Mobile
Computing Environment (MCE) consists of a set of multiple
processors interconnected by wireless communication links
and equipped with software systems to produce an integrated
and consistent processing environment. The task partitioning
and scheduling strategies also play an important role for
achieving high performance in MCE and an efficient task
scheduling technique can utilize the resources in the MCE to
complete the task execution at the earliest or in optimize
manner. Task scheduling is a very common and challenging
problem in MCE and it deals with finding an optimal
scheduling of tasks to the processors so that the processing
cost and processing time are be minimized and the processing
reliability is maximized without violating any of the system
constraints.
Processing time is referred as the time taken by the task for
its execution, expenses occurs during the task execution is
describe as the processing cost and reliability can be
consider as the reliability of its processors as well as the
reliability of its communication links. Distribute data across
processors unevenly so that each processor performs the
volume of computation proportional to its speed is a common
approach to solve task scheduling problem in MCE. This
problem deals with finding an optimal task scheduling
technique to the processors so that the processing time and
cost can be minimized and processing reliability can be
maximized for task scheduling in MCE. In MCE, the
objective is to make processors busy executing tasks all the
time by ensuring that it does not get idle and this serves the
purpose. Task optimization is highly dependent on the tasks
allocation method onto the available processor. In order to
improve the performance of MCE, application workloads are
divided into small independents units called tasks and these
tasks need to be execute on available processor through a
task scheduling technique.
Task scheduling technique should be capable enough in
terms of optimize processing capabilities in MCE i.e.
minimize processing cost, minimize processing time and
maximize processing reliability. This research paper explore
task scheduling problem with n number of processors and m
number of tasks where m>n in MCE and these tasks are need
to schedule on the available processors in optimize manner
with satisfying the processing constraints i.e. time, cost and
reliability. In task scheduling problem once available
processors are scheduled with a single task while the
remaining tasks have to wait (if the numbers of task are
greater than numbers of processor) until the present
scheduled task will execute. To overcome such problem in a
MCE, a task scheduling technique would be needed where
more than one task to a single processor can be schedule in
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 03 Issue: 05 | May-2014, Available @ http://www.ijret.org 824
order to achieve minimum processing time, processing cost
and maximum processing reliability in MCE. Some of the
task allocation schemes have been reported in the literature,
such as Task modeling [1], Scheduling of tasks [2, 5, 7, 8,
11], Task allocation scheme [3, 15, 20], Resource allocation
[4, 13, 14, 16, 19], Load balancing [10], Static task
assignment [6], Resource scheduling [9], Job scheduling
algorithm [12], Resource management and scheduling [17],
Application scheduling in Mobile Cloud Computing [18].
This research paper propose a new task scheduling technique
to task allocation in MCE by using the proper utilization of
processors of the MCE so the problem of load balancing can
be avoid.
2. NOTATIONS
p Processor
t Task
n Number of Processors
m Number of Tasks
TCR Task Cost Reliability
MTCR Modified Task Cost Reliability
3. OBJECTIVE
The objective of this research paper is to solve task
scheduling problem in an efficient manner so that maximum
level of optimization is achieved in order to minimize
processing cost and time and maximize reliability by the
proper utilization of resource in Mobile Computing
Environment (MCE). The applied technique would also
ensure that processing of all the tasks and its sub tasks as task
modules are more than the numbers of processors in the
MCE. The type of assignment of tasks to the processor is
static. In this research paper performance is measured in term
of processing time, cost and reliability of the task that have to
be get processed on the processors of the environment and it
have to be optimally processed i.e., time, cost to be
minimized and reliability maximized.
4. TECHNIQUE
In order to obtain the overall optimal processing cost or
processing time or processing reliability of a Mobile
Computing Environment (MCE), this research paper consider
a problem of task scheduling where a set P = {p1, p2,
p3,………pn} of „n‟ processors with different processing
capabilities and a set T = {t1, t2, t3,………tm} of „m‟ tasks,
where m>n, every task has also contain some number of sub
tasks module. Processing time, cost and reliability are known
for each tasks module to the processor and arrange in TCTR.
Initially processing cost, processing time will be initializing
as zero (0) and processing reliability as one (1). Task
scheduling algorithm will find for the minimum value by row
(without repeating the column in the matrix) for processing
time, cost or maximum for processing reliability, in result
would get the tasks equal to number of processors available
in the MCE and those task will get assigned. The process will
repeat until number of tasks will remain lesser than the
processor available in the environment. Once that situation
will occur where the numbers of processors are greater than
the tasks waiting for the processing then will make slide
change in the technique. Instead of searching element row
wise, the search will be column wise that will make enable
the final allocation of remaining unscheduled task in MCE.
The function to calculate overall time [Etime], cost [Ecost]
and reliability [Ereilability] is given here:
Etime = ETij Xij
n
i=1
n
i=1
(i)
Ecost = ECij Xij
n
i=1
n
i=1
(ii)
Ereliablity = ERij
n
i=0
n
i=1
Xij (iii)
5. ALGORITHM
1. Start Algorithm
2. Read the number of task in m
3. Read the number of processor in n
4. Store task and Processing Cost, time and reliability into
Matrix PCTR (,) n x m of order
5. While (All task! = Assigned)
{
i. Check if the matrix containing numbers of tasks are
greater than or equal to numbers of processors (m>=n)
then go to step (ii) else step (iv)
ii. Search minimum value row wise in the matrix for
time, cost or maximum value for reliability.
iii. Check if the column is previously selected for
minimum/maximum value then GO TO step – (ii) to
find next minimum value for the row else Goto step
(vi) to assign eligible task.
iv. Search the minimum value for cost, time or maximum
value for reliability column wise in the matrix
v. Check if the row is previously selected for minimum
or maximum value then GO TO step – (iv) to find
next minimum or maximum value for the column else
Goto step (vi) to assign eligible task.
vi. Assign the eligible tasks to available processors
}
6. State the results
7. End of algorithm
6. IMPLEMENTATION
This research paper consider Mobile Computing
Environment (MCE) which consist a set P of 3 processors
{p1, p2, p3}, and a set T of 3 tasks {t1, t2, t3}. Each tasks
contained some number of modules and these modules
belongs to different tasks would be process on available
processors in MCE as mentioned in mentioned in Figure 1.
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 03 Issue: 05 | May-2014, Available @ http://www.ijret.org 825
Fig 1: Task modules originating from different mobile hosts
are waiting in queue.
Table 1: Tasks and their modules
t1 {m11, m12, m13, m14,m15, m16}
t2 {m21, m22, m23, m24, m25, m26, m27}
t3 {m31, m32, m33, m34, m35, m36, m37, m38}
Each task contained different individual task components
which are known as modules. The processing time (t),
processing cost (c) and processing reliability (r) of each task
modules to each processor are known and mentioned in
Processing Cost Time Reliability (PCTR) matrix as
mentioned in Table 2
Table 2: Processing Time Cost Reliability Matrix
Processors p1 p2 p3
Task Modules t-c-r t-c-r t-c-r
t1 m11 15-100-0.999111 18-135-0.999125 17-110-0.999450
m12 16-110-0.999429 20-125-0.999159 18-115-0.999429
m13 21-115-0.999423 16-105-0.999328 15-120-0.999418
m14 18-120-0.999218 22-130-0.999419 23-100-0.999458
m15 19-105-0.999451 30-150-0.999480 26-125-0.999450
m16 33-125-0.999329 25-145-0.999219 28-155-0.998219
t2 m21 16-110-0.999112 18-125-0.941124 17-115-0.999418
m22 17-100-0.999149 20-135-0.982152 18-110-0.999429
m23 22-125-0.999533 16-130-0.979317 15-120-0.999418
m24 19-110-0.973218 22-105-0.999419 23-100-0.999413
m25 29-105-0.929431 30-150-0.989411 26-125-0.999414
m26 33-125-0.979328 25-145-0.969019 28-150-0.998226
m27 31-115-0.924322 22-140-0.924219 25-155-0.998214
t3 m31 15-125-0.999669 19-110-0. 997854 18-150-0. 998967
m32 18-100-0.999433 21-135-0. 998780 19-110-0. 999232
m33 26-130-0.998798 14-125-0. 998955 16-115-0. 987432
m34 21-110-0.999754 21-135-0. 987432 22-100-0. 999876
m35 29-105-0. 998766 32-155-0. 999578 24-185-0. 999866
m36 37-115-0. 998654 22-145-0. 998643 29-140-0. 998456
m37 35-125-0. 999478 25-160-0. 998903 24-105-0. 999754
m38 30-155-0. 999268 21-140-0. 998458 25-165-0. 996371
To proceed further with task scheduling problem in PCTR
matrix, considering that t1 is based on processing time (t) (it
may be processing cost or reliability), task t2 is based on
processing cost (c) (it may be processing time and reliability)
and task t3 is based on processing reliability (r) (it
may be processing time and processing cost). Hence a new
matrix named MPCTR can be derived by using PCTR, In
MPCTR task t1 will represent processing time (t), t2 task
processing cost (c) and t3 task processing reliability (r). New
matrix MPCTR represent as Table 3:
Table 3: Modified Processor Cost Time Reliability Matrix
Processors p1 p2 p3
Task Modules t-c-r t-c-r t-c-r
t1 m11 15-…-… 18-…-… 17-…-…
m12 16-…-… 20-…-… 18-…-…
m13 21-…-… 16-…-… 15-…-…
m14 18-…-… 22-…-… 23-…-…
m15 19-…-… 30-…-… 26-…-…
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 03 Issue: 05 | May-2014, Available @ http://www.ijret.org 826
m16 33-…-… 25-…-… 28-…-…
t2 m21 ...-110-… ...-125-… ...-115-…
m22 ...-100-… ...-135-… ...-110-…
m23 ...-125-… ...-130-… ...-120-…
m24 ...-110-… ...-105-… ...-100-…
m25 ...-105-… ...-150-… ...-125-…
m26 ...-125-… ...-145-… ...-150-…
m27 ...-115-… ...-140-… ...-155--…
t3 m31 …-…-0. 999669 …-…-0. 997854 …-…-0. 998967
m32 …-…-0. 999433 …-…-0. 998780 …-…-0. 999232
m33 …-…-0.998798 …-…-0. 998955 …-…-0. 987432
m34 …-…-0. 999754 …-…-0. 987432 …-…-0. 999876
m35 …-…-0. 998766 …-…-0. 999578 …-…-0. 999866
m36 …-…-0. 998654 …-…-0. 998643 …-…-0. 998456
m37 …-…-0. 999478 …-…-0. 998903 …-…-0. 999754
m38 …-…-0. 999268 …-…-0. 998458 …-…-0. 996371
MPCTR can be break into three different tables for each
constraint i.e. Table 4 for processing time, Table 5 for
processing cost and Table 6 for processing reliability in order
to demonstrate all the three constraints of processing i.e. time
cost and reliability in Mobile Computing Environment
(MCE).
Table 4: Processing Time
m11 m12 m13 m14 m15
p1 15 16 21 18 19
p2 18 20 16 22 30
p3 17 18 15 23 26
Table 5: Processing Cost
m21 m22 m23 m24 m25 m26 m27
p1 110 100 125 110 105 125 115
p2 125 135 130 105 150 145 140
p3 115 110 120 100 125 150 155
Table 6: Processing Reliability
m31 m32 m33 m34 m35 m36 m37 m38
p1 0. 999669 0. 999433 0.998798 0. 999754 0. 998766 0. 998654 0. 999478 0. 999268
p2 0. 997854 0. 998780 0. 998955 0. 987432 0. 999578 0. 998643 0. 998903 0. 998458
p3 0. 998967 0. 999232 0. 987432 0. 999876 0. 999866 0. 998456 0. 999754 0. 996371
To demonstrate new scheduling technique, this research
paper is initially considering Table 4 for task scheduling in
MCE. Table 4 represent number of five modules which are
originally belongs to task t1 need to get schedule on number
of 3 processors. In Table 4 numbers of task modules are 5
and the numbers of processors are 3 (m>n), scheduling
technique will determine minimum value for each row and
will get the resulting output as mentioned in Table 7:
Table 7: Matrix representing minimum value
m11 m12 m13 m14 m15
p1 15
p2 16
p3 18
Hence there are only three processors in the environment,
employed technique would schedule only three task module
in MCE as mentioned in Table 8.
Table 8: Scheduling Table
Processor Task Processing Cost
p1 m11 15
p2 m12 16
p3 m13 18
After the first task scheduling step execution, still two task in
the queue and gets unscheduled, here numbers of processors
are greater than number of task (two) (m<n), now the element
will be searched by column wise and that approach will
ensure that none of the task module will get remain
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 03 Issue: 05 | May-2014, Available @ http://www.ijret.org 827
unexecuted. And the final task scheduling is mentioned in
Table 9.
Table 9: Overall processing time
Processor Task Processing
time
Etime
p1 m11 * m14 33 93
p2 m12 16
p3 m13 * m15 44
Graphical representation of overall processing time is
mentioned in Fig 2:
Fig 2: Overall processing time taken by the processor in
MCE
By applying the same task scheduling technique, this
research paper would also calculate processing cost and
processing reliability for the given example in this research
paper as mentioned in Table 10 and Table 11 respectively.
Table 10: Overall processing cost
Processor Task Processing
Cost
Ecost
p1 m22 * m25 *
m27
320 820
p2 m23 * m24 235
p3 m21* m26 265
Graphical representation of overall processing cost is
mentioned in Fig 3:
Fig 3: Overall processing cost occurred during the execution
in MCE
Table 11: Overall processing reliability
Processor Task Processing
Cost
Ereliability
p1 m31* m34 *
m36
0.998077 0.993508
p2 m33 * m37 *
m38
0.996320
p3 m32* m35 0.999098
Figure 4 showing graphical representation of overall
processing reliability of given example:
Fig 4: Overall processing reliability of the task in MCE
7. CONCLUSIONS
This research paper provide the solution to the problem of
task scheduling through a smart task scheduling technique, in
which the number of the tasks is more than the number of
processors in Mobile Computing Environment (MCE). Opted
scheduling technique will ensure to satisfy various
constraints i.e. time, cost and reliability in MCE. The task
scheduling technique is presented in pseudo code and applied
on the several sets of input data to test the performance and
effectiveness of the pseudo code. Optimization of task is the
common objective for any task scheduling problem that the
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 03 Issue: 05 | May-2014, Available @ http://www.ijret.org 828
task needs to be processed with optimal time, cost and
reliability. This paper consider three tasks i.e. t1, t2 and t3 with
different tasks module and process t1 with minimum time, t2
process with minimum cost and t3 process with maximum
reliability in MCE. The optimal output of the given example
that is consider in research paper to test the task scheduling
technique is mentioned in the implementation section of the
paper is mentioned in Table 12:
Table 12: Consolidated results for Time, Cost and Reliability in MCE
Task p1 p2 p3 Optimal
ETime
Optimal
ECost
Optimal
Ereliablity
t1 m11 * m14 m12 m13 * m15 93 --- ---
t2 m22 * m25 * m27 m23 * m24 m21 * m26 --- 820 ---
t3 m34 * m31 * m36 m33 * m37 * m38 m32* m35 --- --- 0.993508
Fig 5: Final Task Scheduling in Mobile Computing
Environment (MCE)
The technique stated in pseudo code applied on several sets
of input data and that verified the objective of get maximum
processing reliability for given tasks for their execution. The
analysis of an algorithm mainly focuses on time complexity.
The time complexity of above mentioned algorithm is
O(m+n). By taking several input examples, the above
algorithm returns results as mentioned in Table 13.
Table 13 Time Complexity
Number of
Processors
(n)
Number
of tasks
(m)
Complexity of
algorithm [5]
O(mn2
)
Complexity
of present
algorithm
O(m+n)
3 5 45 8
3 6 54 9
3 7 63 10
3 8 72 11
3 9 81 12
4 5 80 9
4 6 96 10
4 7 112 11
4 8 128 12
4 9 144 13
5 6 125 11
5 7 150 12
5 8 175 13
5 9 200 14
5 10 225 15
Time complexity comparisons (as mentioned in Table 13) are
shown in Figure 6, 7 and 8.
Fig 6: Time complexity for No of Processors 3
Fig 7: Time complexity for No of Processors 4
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 03 Issue: 05 | May-2014, Available @ http://www.ijret.org 829
Fig 8: Time complexity for No of Processors 5
REFERENCES
[1] Ana Isabel Molina, Miguel Ángel Redondo, Manuel
Ortega, 2007, Applying Task Modeling and Pattern-
based techniques in Reengineering Processes for
Mobile Learning User Interfaces: A case study,
JOURNAL OF COMPUTERS, VOL. 2, Issue 4, 23-
30
[2] Benazir Fateh, G. Manimaran, 2013, Joint Scheduling
of Tasks and Messages for Energy Minimization in
Interference-aware Real-time Sensor Networks, IEEE
Transactions on Mobile Computing, 25 June 2013.
IEEE computer Society Digital Library. IEEE
Computer Society,
<http://doi.ieeecomputersociety.org/10.1109/TMC.20
13.81>, ISSN: 1536-1233
[3] Faizul Navi Khan, Kapil Govil, 2013, Distributed
Task Allocation Scheme for Performance
Improvement in Mobile Computing Network,
International Journal of Trends in Computer Science,
vol: 2 issue: 3, pp: 809-817
[4] Hongbin Liang, Dijiang Huang, Lin X. Cai, Xuemin
(Sherman) Shen, Daiyuan Peng, 2011, Resource
Allocation for Security Services in Mobile Cloud
Computing, IEEE INFOCOM 2011 Workshop on
M2MCN-2011, ISBN: 978-1-4244-9920-5, 191-195
[5] Ilavarasan E, Manoharan R, 2010, High Performance
and Energy Efficient Task Scheduling Algorithm for
Heterogeneous Mobile Computing System,
International Journal of Computer Science &
Information Technology, Vol. 2, Issue 2, 10-27
[6] Kapil Govil and Dr. Avanish Kumar. 2011. A
modified and efficient algorithm for Static task
assignment in Distributed Processing Environment.
International Journal of Computer Applications, Vol.
23, Number 8, Article 1, 1–5, ISBN: 978-93-80752-
82-3, ISSN: 0975 – 8887
[7] L. Yu, G. Zhou, Y. Pu, 2011, An Improved Task
Scheduling Algorithm in Grid Computing
Environment, Int'l J. of Communications, Network
and System Sciences, Vol. 4 No. 4, 227-231. doi:
10.4236/ijcns.2011.44027.
[8] Marjan Kuchaki Rafsanjani, Amid Khatibi Bardsiri,
2012, A New Heuristic Approach for Scheduling
Independent Tasks on Heterogeneous Computing
Systems, International Journal of Machine Learning
and Computing, Vol: 2, No 4, 371-376
[9] S. Nagendram, J. Vijaya Lakshmi, D. Venkata
Narasimha Rao, 2011, Efficient resource scheduling
in data centers using MRIS, Indian Journal of
Computer Science and Engineering, vol. 2, no. 5, pp.
764–769.
[10] S. Suryadevera, J. Chourasia, S. Rathore, A.
Jhummarwala, 2012, Load balancing in computational
grids using ant colony optimization algorithm,”
International Journal of Computer & Communication
Technology, vol. 3, Issue 3, 20-23
[11] S. Thenmozhi , A. Tamilarasi, K. Thangavel, 2012,
Fuzzy Based Task Scheduling for Hierarchical
Resource Allocation in Mobile Grid Environment,
International Journal of Soft Computing, Vol: 7, Issue:
3, 97-103
[12] Sandeep Kaur, Sukhpreet Kaur, 2013, Survey of
Resource and Grouping Based Job Scheduling
Algorithm in Grid Computing, International Journal of
Computer Science and Mobile Computing, Vol: 2,
Issue. 5, 214-218
[13] Sayed Chhattan Shah, Myong-Soon Park, 2010,
Resource Allocation Scheme to Minimize
Communication Cost in Mobile Ad Hoc
Computational Grids, International Conference on
Intelligent Networking and Collaborative Systems,
ISBN: 978-0-7695-4278-2, 169-176
[14] Sayed Chhattan Shah, Qurat-Ul-Ain Nizamanib,
Sajjad Hussain Chauhdaryc, Myong-Soon Park, 2012,
An effective and robust two-phase resource allocation
scheme for interdependent tasks in mobile ad hoc
computational Grids, Journal of Parallel and
Distributed Computing, Vol: 72, Issue 12, 1664–1679
[15] T. Xie and X. Qin, 2008, An Energy-Delay Tunable
Task Allocation Strategy for Collaborative
Applications in Networked Embedded Systems, IEEE
Trans. Computers, Vol: 57, Issue 3, 329-343.
[16] Thenmozhi S., A. Tamilarasi and P.T. Vanathi, 2012,
A Fault Tolerant Resource Allocation Architecture for
Mobile Grid, Journal of Computer Science, Vol: 8,
Issue 6, 978-982
[17] Vignesh V, Sendhil Kumar KS, Jaisankar N, 2013,
Resource Management and Scheduling in Cloud
Environment, International Journal of Scientific and
Research Publications, Volume 3, Issue 6, 1-6
[18] Xianglin Wei,Jianhua Fan, Ziyi Lu,Ke Ding, 2013,
Application Scheduling in Mobile Cloud Computing
with Load Balancing, Journal of Applied
Mathematics, Vol: 2013, 1-13
[19] Yashpal Rohilla, Preeti Gulia, 2012, Resource
Allocation in cellular Network : A cross layer
approach, International Journal of Engineering
Research and Applications, Vol. 2, Issue 4, 912-915
[20] Yichao Jin, Jiong Jin, Alexander Gluhak, Klaus
Moessner and Marimuthu Palaniswami, 2012, An
Intelligent Task Allocation Scheme for Multihop
Wireless Networks, IEEE Transactions on Parallel and
Distributed Systems, Vol: 23, Issue 3, 444-451

More Related Content

What's hot

SCHEDULING DIFFERENT CUSTOMER ACTIVITIES WITH SENSING DEVICE
SCHEDULING DIFFERENT CUSTOMER ACTIVITIES WITH SENSING DEVICESCHEDULING DIFFERENT CUSTOMER ACTIVITIES WITH SENSING DEVICE
SCHEDULING DIFFERENT CUSTOMER ACTIVITIES WITH SENSING DEVICEijait
 
Fault-Tolerance Aware Multi Objective Scheduling Algorithm for Task Schedulin...
Fault-Tolerance Aware Multi Objective Scheduling Algorithm for Task Schedulin...Fault-Tolerance Aware Multi Objective Scheduling Algorithm for Task Schedulin...
Fault-Tolerance Aware Multi Objective Scheduling Algorithm for Task Schedulin...csandit
 
Modified heuristic time deviation Technique for job sequencing and Computatio...
Modified heuristic time deviation Technique for job sequencing and Computatio...Modified heuristic time deviation Technique for job sequencing and Computatio...
Modified heuristic time deviation Technique for job sequencing and Computatio...ijcsit
 
DYNAMIC TASK PARTITIONING MODEL IN PARALLEL COMPUTING
DYNAMIC TASK PARTITIONING MODEL IN PARALLEL COMPUTINGDYNAMIC TASK PARTITIONING MODEL IN PARALLEL COMPUTING
DYNAMIC TASK PARTITIONING MODEL IN PARALLEL COMPUTINGcscpconf
 
Optimized Assignment of Independent Task for Improving Resources Performance ...
Optimized Assignment of Independent Task for Improving Resources Performance ...Optimized Assignment of Independent Task for Improving Resources Performance ...
Optimized Assignment of Independent Task for Improving Resources Performance ...ijgca
 
Scheduling of Heterogeneous Tasks in Cloud Computing using Multi Queue (MQ) A...
Scheduling of Heterogeneous Tasks in Cloud Computing using Multi Queue (MQ) A...Scheduling of Heterogeneous Tasks in Cloud Computing using Multi Queue (MQ) A...
Scheduling of Heterogeneous Tasks in Cloud Computing using Multi Queue (MQ) A...IRJET Journal
 
Vol 3 No 1 - July 2013
Vol 3 No 1 - July 2013Vol 3 No 1 - July 2013
Vol 3 No 1 - July 2013ijcsbi
 
Resource Management for Computer Operating Systems
Resource Management for Computer Operating SystemsResource Management for Computer Operating Systems
Resource Management for Computer Operating Systemsinside-BigData.com
 
Comparative Analysis of Various Grid Based Scheduling Algorithms
Comparative Analysis of Various Grid Based Scheduling AlgorithmsComparative Analysis of Various Grid Based Scheduling Algorithms
Comparative Analysis of Various Grid Based Scheduling Algorithmsiosrjce
 
Bragged Regression Tree Algorithm for Dynamic Distribution and Scheduling of ...
Bragged Regression Tree Algorithm for Dynamic Distribution and Scheduling of ...Bragged Regression Tree Algorithm for Dynamic Distribution and Scheduling of ...
Bragged Regression Tree Algorithm for Dynamic Distribution and Scheduling of ...Editor IJCATR
 
Task scheduling methodologies for high speed computing systems
Task scheduling methodologies for high speed computing systemsTask scheduling methodologies for high speed computing systems
Task scheduling methodologies for high speed computing systemsijesajournal
 
(5 10) chitra natarajan
(5 10) chitra natarajan(5 10) chitra natarajan
(5 10) chitra natarajanIISRTJournals
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)inventionjournals
 
IRJET- Enhance Dynamic Heterogeneous Shortest Job first (DHSJF): A Task Schedu...
IRJET- Enhance Dynamic Heterogeneous Shortest Job first (DHSJF): A Task Schedu...IRJET- Enhance Dynamic Heterogeneous Shortest Job first (DHSJF): A Task Schedu...
IRJET- Enhance Dynamic Heterogeneous Shortest Job first (DHSJF): A Task Schedu...IRJET Journal
 
An improved approach to minimize context switching in round robin scheduling ...
An improved approach to minimize context switching in round robin scheduling ...An improved approach to minimize context switching in round robin scheduling ...
An improved approach to minimize context switching in round robin scheduling ...eSAT Publishing House
 
A GUI-driven prototype for synthesizing self-adaptation decision
A GUI-driven prototype for synthesizing self-adaptation decisionA GUI-driven prototype for synthesizing self-adaptation decision
A GUI-driven prototype for synthesizing self-adaptation decisionjournalBEEI
 
A hybrid approach for scheduling applications in cloud computing environment
A hybrid approach for scheduling applications in cloud computing environment A hybrid approach for scheduling applications in cloud computing environment
A hybrid approach for scheduling applications in cloud computing environment IJECEIAES
 

What's hot (18)

SCHEDULING DIFFERENT CUSTOMER ACTIVITIES WITH SENSING DEVICE
SCHEDULING DIFFERENT CUSTOMER ACTIVITIES WITH SENSING DEVICESCHEDULING DIFFERENT CUSTOMER ACTIVITIES WITH SENSING DEVICE
SCHEDULING DIFFERENT CUSTOMER ACTIVITIES WITH SENSING DEVICE
 
Fault-Tolerance Aware Multi Objective Scheduling Algorithm for Task Schedulin...
Fault-Tolerance Aware Multi Objective Scheduling Algorithm for Task Schedulin...Fault-Tolerance Aware Multi Objective Scheduling Algorithm for Task Schedulin...
Fault-Tolerance Aware Multi Objective Scheduling Algorithm for Task Schedulin...
 
Modified heuristic time deviation Technique for job sequencing and Computatio...
Modified heuristic time deviation Technique for job sequencing and Computatio...Modified heuristic time deviation Technique for job sequencing and Computatio...
Modified heuristic time deviation Technique for job sequencing and Computatio...
 
DYNAMIC TASK PARTITIONING MODEL IN PARALLEL COMPUTING
DYNAMIC TASK PARTITIONING MODEL IN PARALLEL COMPUTINGDYNAMIC TASK PARTITIONING MODEL IN PARALLEL COMPUTING
DYNAMIC TASK PARTITIONING MODEL IN PARALLEL COMPUTING
 
Optimized Assignment of Independent Task for Improving Resources Performance ...
Optimized Assignment of Independent Task for Improving Resources Performance ...Optimized Assignment of Independent Task for Improving Resources Performance ...
Optimized Assignment of Independent Task for Improving Resources Performance ...
 
Scheduling of Heterogeneous Tasks in Cloud Computing using Multi Queue (MQ) A...
Scheduling of Heterogeneous Tasks in Cloud Computing using Multi Queue (MQ) A...Scheduling of Heterogeneous Tasks in Cloud Computing using Multi Queue (MQ) A...
Scheduling of Heterogeneous Tasks in Cloud Computing using Multi Queue (MQ) A...
 
Vol 3 No 1 - July 2013
Vol 3 No 1 - July 2013Vol 3 No 1 - July 2013
Vol 3 No 1 - July 2013
 
Resource Management for Computer Operating Systems
Resource Management for Computer Operating SystemsResource Management for Computer Operating Systems
Resource Management for Computer Operating Systems
 
Comparative Analysis of Various Grid Based Scheduling Algorithms
Comparative Analysis of Various Grid Based Scheduling AlgorithmsComparative Analysis of Various Grid Based Scheduling Algorithms
Comparative Analysis of Various Grid Based Scheduling Algorithms
 
Bragged Regression Tree Algorithm for Dynamic Distribution and Scheduling of ...
Bragged Regression Tree Algorithm for Dynamic Distribution and Scheduling of ...Bragged Regression Tree Algorithm for Dynamic Distribution and Scheduling of ...
Bragged Regression Tree Algorithm for Dynamic Distribution and Scheduling of ...
 
Task scheduling methodologies for high speed computing systems
Task scheduling methodologies for high speed computing systemsTask scheduling methodologies for high speed computing systems
Task scheduling methodologies for high speed computing systems
 
(5 10) chitra natarajan
(5 10) chitra natarajan(5 10) chitra natarajan
(5 10) chitra natarajan
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)
 
IRJET- Enhance Dynamic Heterogeneous Shortest Job first (DHSJF): A Task Schedu...
IRJET- Enhance Dynamic Heterogeneous Shortest Job first (DHSJF): A Task Schedu...IRJET- Enhance Dynamic Heterogeneous Shortest Job first (DHSJF): A Task Schedu...
IRJET- Enhance Dynamic Heterogeneous Shortest Job first (DHSJF): A Task Schedu...
 
An improved approach to minimize context switching in round robin scheduling ...
An improved approach to minimize context switching in round robin scheduling ...An improved approach to minimize context switching in round robin scheduling ...
An improved approach to minimize context switching in round robin scheduling ...
 
genetic paper
genetic papergenetic paper
genetic paper
 
A GUI-driven prototype for synthesizing self-adaptation decision
A GUI-driven prototype for synthesizing self-adaptation decisionA GUI-driven prototype for synthesizing self-adaptation decision
A GUI-driven prototype for synthesizing self-adaptation decision
 
A hybrid approach for scheduling applications in cloud computing environment
A hybrid approach for scheduling applications in cloud computing environment A hybrid approach for scheduling applications in cloud computing environment
A hybrid approach for scheduling applications in cloud computing environment
 

Viewers also liked

Hydraulic peroformnace of faucet aerator as water
Hydraulic peroformnace of faucet aerator as waterHydraulic peroformnace of faucet aerator as water
Hydraulic peroformnace of faucet aerator as watereSAT Publishing House
 
Comparative study on tax compliance software
Comparative study on tax compliance softwareComparative study on tax compliance software
Comparative study on tax compliance softwareeSAT Publishing House
 
An adaptive broadcast mechanism to improve alert
An adaptive broadcast mechanism to improve alertAn adaptive broadcast mechanism to improve alert
An adaptive broadcast mechanism to improve alerteSAT Publishing House
 
Evaluation of mechanical properties of retrogression and reaged al 7075 alloy...
Evaluation of mechanical properties of retrogression and reaged al 7075 alloy...Evaluation of mechanical properties of retrogression and reaged al 7075 alloy...
Evaluation of mechanical properties of retrogression and reaged al 7075 alloy...eSAT Publishing House
 
Experimental study of behaviour of poultry feather fiber a reinforcing mate...
Experimental study of behaviour of poultry feather fiber   a reinforcing mate...Experimental study of behaviour of poultry feather fiber   a reinforcing mate...
Experimental study of behaviour of poultry feather fiber a reinforcing mate...eSAT Publishing House
 
Effect of dyeing parameters on dyeing of cotton fabrics with fluoro chloro py...
Effect of dyeing parameters on dyeing of cotton fabrics with fluoro chloro py...Effect of dyeing parameters on dyeing of cotton fabrics with fluoro chloro py...
Effect of dyeing parameters on dyeing of cotton fabrics with fluoro chloro py...eSAT Publishing House
 
An overview of wireless based subsea tunnel monitoring system
An overview of wireless based subsea tunnel monitoring systemAn overview of wireless based subsea tunnel monitoring system
An overview of wireless based subsea tunnel monitoring systemeSAT Publishing House
 
A survey on incremental relaying protocols in cooperative communication
A survey on incremental relaying protocols in cooperative communicationA survey on incremental relaying protocols in cooperative communication
A survey on incremental relaying protocols in cooperative communicationeSAT Publishing House
 
Study of the effects of carbon and glass fibre reinforcement and other filler...
Study of the effects of carbon and glass fibre reinforcement and other filler...Study of the effects of carbon and glass fibre reinforcement and other filler...
Study of the effects of carbon and glass fibre reinforcement and other filler...eSAT Publishing House
 
Potential utilisation of untreatedtreated textile effluent in concrete
Potential utilisation of untreatedtreated textile effluent in concretePotential utilisation of untreatedtreated textile effluent in concrete
Potential utilisation of untreatedtreated textile effluent in concreteeSAT Publishing House
 
Analytical study of abutment and pile behaviour of iab with soil interaction
Analytical study of abutment and pile behaviour of iab with soil interactionAnalytical study of abutment and pile behaviour of iab with soil interaction
Analytical study of abutment and pile behaviour of iab with soil interactioneSAT Publishing House
 
Real time voting system using face recognition for different expressions and ...
Real time voting system using face recognition for different expressions and ...Real time voting system using face recognition for different expressions and ...
Real time voting system using face recognition for different expressions and ...eSAT Publishing House
 
Hexagonal carpet antenna for wlan wi max & bluetooth applications
Hexagonal carpet antenna for wlan wi max & bluetooth applicationsHexagonal carpet antenna for wlan wi max & bluetooth applications
Hexagonal carpet antenna for wlan wi max & bluetooth applicationseSAT Publishing House
 
Pattern –based with surface based morphometry survey
Pattern –based with surface based morphometry surveyPattern –based with surface based morphometry survey
Pattern –based with surface based morphometry surveyeSAT Publishing House
 
Size effect in brick masonry wallets
Size effect in brick masonry walletsSize effect in brick masonry wallets
Size effect in brick masonry walletseSAT Publishing House
 
Implementation of lru algorithm for location update in wireless m2 m communic...
Implementation of lru algorithm for location update in wireless m2 m communic...Implementation of lru algorithm for location update in wireless m2 m communic...
Implementation of lru algorithm for location update in wireless m2 m communic...eSAT Publishing House
 
Development of strain prediction models for concrete roads
Development of strain prediction models for concrete roadsDevelopment of strain prediction models for concrete roads
Development of strain prediction models for concrete roadseSAT Publishing House
 
A distinct approach for xmotif application gui test automation
A distinct approach for xmotif application gui test automationA distinct approach for xmotif application gui test automation
A distinct approach for xmotif application gui test automationeSAT Publishing House
 
Review work on analysis of f1 car frame using ansys
Review work on analysis of f1 car frame using ansysReview work on analysis of f1 car frame using ansys
Review work on analysis of f1 car frame using ansyseSAT Publishing House
 
Enhancement of upfc performance with matrix
Enhancement of upfc performance with matrixEnhancement of upfc performance with matrix
Enhancement of upfc performance with matrixeSAT Publishing House
 

Viewers also liked (20)

Hydraulic peroformnace of faucet aerator as water
Hydraulic peroformnace of faucet aerator as waterHydraulic peroformnace of faucet aerator as water
Hydraulic peroformnace of faucet aerator as water
 
Comparative study on tax compliance software
Comparative study on tax compliance softwareComparative study on tax compliance software
Comparative study on tax compliance software
 
An adaptive broadcast mechanism to improve alert
An adaptive broadcast mechanism to improve alertAn adaptive broadcast mechanism to improve alert
An adaptive broadcast mechanism to improve alert
 
Evaluation of mechanical properties of retrogression and reaged al 7075 alloy...
Evaluation of mechanical properties of retrogression and reaged al 7075 alloy...Evaluation of mechanical properties of retrogression and reaged al 7075 alloy...
Evaluation of mechanical properties of retrogression and reaged al 7075 alloy...
 
Experimental study of behaviour of poultry feather fiber a reinforcing mate...
Experimental study of behaviour of poultry feather fiber   a reinforcing mate...Experimental study of behaviour of poultry feather fiber   a reinforcing mate...
Experimental study of behaviour of poultry feather fiber a reinforcing mate...
 
Effect of dyeing parameters on dyeing of cotton fabrics with fluoro chloro py...
Effect of dyeing parameters on dyeing of cotton fabrics with fluoro chloro py...Effect of dyeing parameters on dyeing of cotton fabrics with fluoro chloro py...
Effect of dyeing parameters on dyeing of cotton fabrics with fluoro chloro py...
 
An overview of wireless based subsea tunnel monitoring system
An overview of wireless based subsea tunnel monitoring systemAn overview of wireless based subsea tunnel monitoring system
An overview of wireless based subsea tunnel monitoring system
 
A survey on incremental relaying protocols in cooperative communication
A survey on incremental relaying protocols in cooperative communicationA survey on incremental relaying protocols in cooperative communication
A survey on incremental relaying protocols in cooperative communication
 
Study of the effects of carbon and glass fibre reinforcement and other filler...
Study of the effects of carbon and glass fibre reinforcement and other filler...Study of the effects of carbon and glass fibre reinforcement and other filler...
Study of the effects of carbon and glass fibre reinforcement and other filler...
 
Potential utilisation of untreatedtreated textile effluent in concrete
Potential utilisation of untreatedtreated textile effluent in concretePotential utilisation of untreatedtreated textile effluent in concrete
Potential utilisation of untreatedtreated textile effluent in concrete
 
Analytical study of abutment and pile behaviour of iab with soil interaction
Analytical study of abutment and pile behaviour of iab with soil interactionAnalytical study of abutment and pile behaviour of iab with soil interaction
Analytical study of abutment and pile behaviour of iab with soil interaction
 
Real time voting system using face recognition for different expressions and ...
Real time voting system using face recognition for different expressions and ...Real time voting system using face recognition for different expressions and ...
Real time voting system using face recognition for different expressions and ...
 
Hexagonal carpet antenna for wlan wi max & bluetooth applications
Hexagonal carpet antenna for wlan wi max & bluetooth applicationsHexagonal carpet antenna for wlan wi max & bluetooth applications
Hexagonal carpet antenna for wlan wi max & bluetooth applications
 
Pattern –based with surface based morphometry survey
Pattern –based with surface based morphometry surveyPattern –based with surface based morphometry survey
Pattern –based with surface based morphometry survey
 
Size effect in brick masonry wallets
Size effect in brick masonry walletsSize effect in brick masonry wallets
Size effect in brick masonry wallets
 
Implementation of lru algorithm for location update in wireless m2 m communic...
Implementation of lru algorithm for location update in wireless m2 m communic...Implementation of lru algorithm for location update in wireless m2 m communic...
Implementation of lru algorithm for location update in wireless m2 m communic...
 
Development of strain prediction models for concrete roads
Development of strain prediction models for concrete roadsDevelopment of strain prediction models for concrete roads
Development of strain prediction models for concrete roads
 
A distinct approach for xmotif application gui test automation
A distinct approach for xmotif application gui test automationA distinct approach for xmotif application gui test automation
A distinct approach for xmotif application gui test automation
 
Review work on analysis of f1 car frame using ansys
Review work on analysis of f1 car frame using ansysReview work on analysis of f1 car frame using ansys
Review work on analysis of f1 car frame using ansys
 
Enhancement of upfc performance with matrix
Enhancement of upfc performance with matrixEnhancement of upfc performance with matrix
Enhancement of upfc performance with matrix
 

Similar to A tricky task scheduling technique to optimize time cost and reliability in mobile computing environment

A Survey on Task Scheduling and Load Balanced Algorithms in Cloud Computing
A Survey on Task Scheduling and Load Balanced Algorithms in Cloud ComputingA Survey on Task Scheduling and Load Balanced Algorithms in Cloud Computing
A Survey on Task Scheduling and Load Balanced Algorithms in Cloud ComputingIRJET Journal
 
A Survey on Heuristic Based Techniques in Cloud Computing
A Survey on Heuristic Based Techniques in Cloud ComputingA Survey on Heuristic Based Techniques in Cloud Computing
A Survey on Heuristic Based Techniques in Cloud ComputingIRJET Journal
 
An Algorithm for Optimized Cost in a Distributed Computing System
An Algorithm for Optimized Cost in a Distributed Computing SystemAn Algorithm for Optimized Cost in a Distributed Computing System
An Algorithm for Optimized Cost in a Distributed Computing SystemIRJET Journal
 
An adaptive algorithm for task scheduling for computational grid
An adaptive algorithm for task scheduling for computational gridAn adaptive algorithm for task scheduling for computational grid
An adaptive algorithm for task scheduling for computational grideSAT Journals
 
Quality of Service based Task Scheduling Algorithms in Cloud Computing
Quality of Service based Task Scheduling Algorithms in  Cloud Computing  Quality of Service based Task Scheduling Algorithms in  Cloud Computing
Quality of Service based Task Scheduling Algorithms in Cloud Computing IJECEIAES
 
A Novel Dynamic Priority Based Job Scheduling Approach for Cloud Environment
A Novel Dynamic Priority Based Job Scheduling Approach for Cloud EnvironmentA Novel Dynamic Priority Based Job Scheduling Approach for Cloud Environment
A Novel Dynamic Priority Based Job Scheduling Approach for Cloud EnvironmentIRJET Journal
 
Optimized Assignment of Independent Task for Improving Resources Performance ...
Optimized Assignment of Independent Task for Improving Resources Performance ...Optimized Assignment of Independent Task for Improving Resources Performance ...
Optimized Assignment of Independent Task for Improving Resources Performance ...Ricardo014
 
Optimized Assignment of Independent Task for Improving Resources Performance ...
Optimized Assignment of Independent Task for Improving Resources Performance ...Optimized Assignment of Independent Task for Improving Resources Performance ...
Optimized Assignment of Independent Task for Improving Resources Performance ...ijgca
 
A Virtual Machine Resource Management Method with Millisecond Precision
A Virtual Machine Resource Management Method with Millisecond PrecisionA Virtual Machine Resource Management Method with Millisecond Precision
A Virtual Machine Resource Management Method with Millisecond PrecisionIRJET Journal
 
PERFORMANCE FACTORS OF CLOUD COMPUTING DATA CENTERS USING [(M/G/1) : (∞/GDM O...
PERFORMANCE FACTORS OF CLOUD COMPUTING DATA CENTERS USING [(M/G/1) : (∞/GDM O...PERFORMANCE FACTORS OF CLOUD COMPUTING DATA CENTERS USING [(M/G/1) : (∞/GDM O...
PERFORMANCE FACTORS OF CLOUD COMPUTING DATA CENTERS USING [(M/G/1) : (∞/GDM O...ijgca
 
An optimized cost-based data allocation model for heterogeneous distributed ...
An optimized cost-based data allocation model for  heterogeneous distributed ...An optimized cost-based data allocation model for  heterogeneous distributed ...
An optimized cost-based data allocation model for heterogeneous distributed ...IJECEIAES
 
Dynamic task scheduling on multicore automotive ec us
Dynamic task scheduling on multicore automotive ec usDynamic task scheduling on multicore automotive ec us
Dynamic task scheduling on multicore automotive ec usVLSICS Design
 
DYNAMIC TASK SCHEDULING ON MULTICORE AUTOMOTIVE ECUS
DYNAMIC TASK SCHEDULING ON MULTICORE AUTOMOTIVE ECUSDYNAMIC TASK SCHEDULING ON MULTICORE AUTOMOTIVE ECUS
DYNAMIC TASK SCHEDULING ON MULTICORE AUTOMOTIVE ECUSVLSICS Design
 
DYNAMIC TASK SCHEDULING ON MULTICORE AUTOMOTIVE ECUS
DYNAMIC TASK SCHEDULING ON MULTICORE AUTOMOTIVE ECUSDYNAMIC TASK SCHEDULING ON MULTICORE AUTOMOTIVE ECUS
DYNAMIC TASK SCHEDULING ON MULTICORE AUTOMOTIVE ECUSVLSICS Design
 
Max Min Fair Scheduling Algorithm using In Grid Scheduling with Load Balancing
Max Min Fair Scheduling Algorithm using In Grid Scheduling with Load Balancing Max Min Fair Scheduling Algorithm using In Grid Scheduling with Load Balancing
Max Min Fair Scheduling Algorithm using In Grid Scheduling with Load Balancing IJORCS
 
Distributed Feature Selection for Efficient Economic Big Data Analysis
Distributed Feature Selection for Efficient Economic Big Data AnalysisDistributed Feature Selection for Efficient Economic Big Data Analysis
Distributed Feature Selection for Efficient Economic Big Data AnalysisIRJET Journal
 
High Dimensionality Structures Selection for Efficient Economic Big data usin...
High Dimensionality Structures Selection for Efficient Economic Big data usin...High Dimensionality Structures Selection for Efficient Economic Big data usin...
High Dimensionality Structures Selection for Efficient Economic Big data usin...IRJET Journal
 
Cloud service analysis using round-robin algorithm for qualityof-service awar...
Cloud service analysis using round-robin algorithm for qualityof-service awar...Cloud service analysis using round-robin algorithm for qualityof-service awar...
Cloud service analysis using round-robin algorithm for qualityof-service awar...IJECEIAES
 

Similar to A tricky task scheduling technique to optimize time cost and reliability in mobile computing environment (20)

A Survey on Task Scheduling and Load Balanced Algorithms in Cloud Computing
A Survey on Task Scheduling and Load Balanced Algorithms in Cloud ComputingA Survey on Task Scheduling and Load Balanced Algorithms in Cloud Computing
A Survey on Task Scheduling and Load Balanced Algorithms in Cloud Computing
 
A Survey on Heuristic Based Techniques in Cloud Computing
A Survey on Heuristic Based Techniques in Cloud ComputingA Survey on Heuristic Based Techniques in Cloud Computing
A Survey on Heuristic Based Techniques in Cloud Computing
 
An Algorithm for Optimized Cost in a Distributed Computing System
An Algorithm for Optimized Cost in a Distributed Computing SystemAn Algorithm for Optimized Cost in a Distributed Computing System
An Algorithm for Optimized Cost in a Distributed Computing System
 
An adaptive algorithm for task scheduling for computational grid
An adaptive algorithm for task scheduling for computational gridAn adaptive algorithm for task scheduling for computational grid
An adaptive algorithm for task scheduling for computational grid
 
Quality of Service based Task Scheduling Algorithms in Cloud Computing
Quality of Service based Task Scheduling Algorithms in  Cloud Computing  Quality of Service based Task Scheduling Algorithms in  Cloud Computing
Quality of Service based Task Scheduling Algorithms in Cloud Computing
 
A Novel Dynamic Priority Based Job Scheduling Approach for Cloud Environment
A Novel Dynamic Priority Based Job Scheduling Approach for Cloud EnvironmentA Novel Dynamic Priority Based Job Scheduling Approach for Cloud Environment
A Novel Dynamic Priority Based Job Scheduling Approach for Cloud Environment
 
Optimized Assignment of Independent Task for Improving Resources Performance ...
Optimized Assignment of Independent Task for Improving Resources Performance ...Optimized Assignment of Independent Task for Improving Resources Performance ...
Optimized Assignment of Independent Task for Improving Resources Performance ...
 
Optimized Assignment of Independent Task for Improving Resources Performance ...
Optimized Assignment of Independent Task for Improving Resources Performance ...Optimized Assignment of Independent Task for Improving Resources Performance ...
Optimized Assignment of Independent Task for Improving Resources Performance ...
 
M017419499
M017419499M017419499
M017419499
 
Ijmet 10 01_022
Ijmet 10 01_022Ijmet 10 01_022
Ijmet 10 01_022
 
A Virtual Machine Resource Management Method with Millisecond Precision
A Virtual Machine Resource Management Method with Millisecond PrecisionA Virtual Machine Resource Management Method with Millisecond Precision
A Virtual Machine Resource Management Method with Millisecond Precision
 
PERFORMANCE FACTORS OF CLOUD COMPUTING DATA CENTERS USING [(M/G/1) : (∞/GDM O...
PERFORMANCE FACTORS OF CLOUD COMPUTING DATA CENTERS USING [(M/G/1) : (∞/GDM O...PERFORMANCE FACTORS OF CLOUD COMPUTING DATA CENTERS USING [(M/G/1) : (∞/GDM O...
PERFORMANCE FACTORS OF CLOUD COMPUTING DATA CENTERS USING [(M/G/1) : (∞/GDM O...
 
An optimized cost-based data allocation model for heterogeneous distributed ...
An optimized cost-based data allocation model for  heterogeneous distributed ...An optimized cost-based data allocation model for  heterogeneous distributed ...
An optimized cost-based data allocation model for heterogeneous distributed ...
 
Dynamic task scheduling on multicore automotive ec us
Dynamic task scheduling on multicore automotive ec usDynamic task scheduling on multicore automotive ec us
Dynamic task scheduling on multicore automotive ec us
 
DYNAMIC TASK SCHEDULING ON MULTICORE AUTOMOTIVE ECUS
DYNAMIC TASK SCHEDULING ON MULTICORE AUTOMOTIVE ECUSDYNAMIC TASK SCHEDULING ON MULTICORE AUTOMOTIVE ECUS
DYNAMIC TASK SCHEDULING ON MULTICORE AUTOMOTIVE ECUS
 
DYNAMIC TASK SCHEDULING ON MULTICORE AUTOMOTIVE ECUS
DYNAMIC TASK SCHEDULING ON MULTICORE AUTOMOTIVE ECUSDYNAMIC TASK SCHEDULING ON MULTICORE AUTOMOTIVE ECUS
DYNAMIC TASK SCHEDULING ON MULTICORE AUTOMOTIVE ECUS
 
Max Min Fair Scheduling Algorithm using In Grid Scheduling with Load Balancing
Max Min Fair Scheduling Algorithm using In Grid Scheduling with Load Balancing Max Min Fair Scheduling Algorithm using In Grid Scheduling with Load Balancing
Max Min Fair Scheduling Algorithm using In Grid Scheduling with Load Balancing
 
Distributed Feature Selection for Efficient Economic Big Data Analysis
Distributed Feature Selection for Efficient Economic Big Data AnalysisDistributed Feature Selection for Efficient Economic Big Data Analysis
Distributed Feature Selection for Efficient Economic Big Data Analysis
 
High Dimensionality Structures Selection for Efficient Economic Big data usin...
High Dimensionality Structures Selection for Efficient Economic Big data usin...High Dimensionality Structures Selection for Efficient Economic Big data usin...
High Dimensionality Structures Selection for Efficient Economic Big data usin...
 
Cloud service analysis using round-robin algorithm for qualityof-service awar...
Cloud service analysis using round-robin algorithm for qualityof-service awar...Cloud service analysis using round-robin algorithm for qualityof-service awar...
Cloud service analysis using round-robin algorithm for qualityof-service awar...
 

More from eSAT Publishing House

Likely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnamLikely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnameSAT Publishing House
 
Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...eSAT Publishing House
 
Hudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnamHudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnameSAT Publishing House
 
Groundwater investigation using geophysical methods a case study of pydibhim...
Groundwater investigation using geophysical methods  a case study of pydibhim...Groundwater investigation using geophysical methods  a case study of pydibhim...
Groundwater investigation using geophysical methods a case study of pydibhim...eSAT Publishing House
 
Flood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, indiaFlood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, indiaeSAT Publishing House
 
Enhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity buildingEnhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity buildingeSAT Publishing House
 
Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...eSAT Publishing House
 
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...eSAT Publishing House
 
Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...eSAT Publishing House
 
Shear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a reviewShear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a revieweSAT Publishing House
 
Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...eSAT Publishing House
 
Risk analysis and environmental hazard management
Risk analysis and environmental hazard managementRisk analysis and environmental hazard management
Risk analysis and environmental hazard managementeSAT Publishing House
 
Review study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear wallsReview study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear wallseSAT Publishing House
 
Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...eSAT Publishing House
 
Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...eSAT Publishing House
 
Coastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of indiaCoastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of indiaeSAT Publishing House
 
Can fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structuresCan fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structureseSAT Publishing House
 
Assessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildingsAssessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildingseSAT Publishing House
 
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...eSAT Publishing House
 
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...eSAT Publishing House
 

More from eSAT Publishing House (20)

Likely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnamLikely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnam
 
Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...
 
Hudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnamHudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnam
 
Groundwater investigation using geophysical methods a case study of pydibhim...
Groundwater investigation using geophysical methods  a case study of pydibhim...Groundwater investigation using geophysical methods  a case study of pydibhim...
Groundwater investigation using geophysical methods a case study of pydibhim...
 
Flood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, indiaFlood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, india
 
Enhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity buildingEnhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity building
 
Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...
 
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
 
Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...
 
Shear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a reviewShear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a review
 
Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...
 
Risk analysis and environmental hazard management
Risk analysis and environmental hazard managementRisk analysis and environmental hazard management
Risk analysis and environmental hazard management
 
Review study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear wallsReview study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear walls
 
Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...
 
Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...
 
Coastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of indiaCoastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of india
 
Can fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structuresCan fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structures
 
Assessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildingsAssessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildings
 
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
 
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
 

Recently uploaded

Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 

Recently uploaded (20)

Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 

A tricky task scheduling technique to optimize time cost and reliability in mobile computing environment

  • 1. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 03 Issue: 05 | May-2014, Available @ http://www.ijret.org 823 A TRICKY TASK SCHEDULING TECHNIQUE TO OPTIMIZE TIME COST AND RELIABILITY IN MOBILE COMPUTING ENVIRONMENT Faizul Navi Khan1 , Kapil Govil2 1 Department of Computer Application, Teerthanker Mahaveer University, Moradabad - 244 001, UP, INDIA 2 Department of Computer Application, Teerthanker Mahaveer University, Moradabad - 244 001, UP, INDIA Abstract Mobile Computing Environment (MCE) consisting portable computing devices interconnected by wireless medium, are increasingly being used in many area of science, business and education etc nowadays. It is the computation made over physical mobility. MCE facilitate the user to perform a task from a distant place from the device. This provides flexible communication between user and continuous access to networked services. Mobile computing shares many features with distributed computing as the application runs in MCE executes in distributed manner i.e. an application is combination of multiple tasks and these task schedule on the available resources to be execute. The performance of an application is depending on task scheduling technique in MCE. Task scheduling technique consist in finding an allocation of the tasks to the processors such that the total execution cost and time are minimized or processing reliability is maximized. So the ultimate objective of finding task scheduling technique is to improve the performance in terms to minimize cost and time and maximize reliability of MCE. In MCE an application can be seen as one or multiple task modules and each of the task modules allocate on available processor for its execution. Therefore, in this paper, the problem of scheduling the tasks in mobile computing environment is explore with objectives to minimize processing cost, processing time or maximize the processing reliability through a new task scheduling technique to optimize performance in MCE. The nature of the assignment will be static. Keywords – Cost, Mobile Computing Environment, Performance, Reliability, Task scheduling --------------------------------------------------------------------***------------------------------------------------------------------- 1. INTRODUCTION Advances in communication and computing technologies have introduced a new way of computing environment, called „Mobile Computing Environment (MCE)‟, which allows mobility of users thereby providing “anytime anywhere” computing environment. The mobility of user (or device) results in a highly dynamic environments with respect to the availability of resources/infrastructures for any application running on the mobile devices. Also, in a mobile computing environment, location has a profound effect. A Mobile Computing Environment (MCE) consists of a set of multiple processors interconnected by wireless communication links and equipped with software systems to produce an integrated and consistent processing environment. The task partitioning and scheduling strategies also play an important role for achieving high performance in MCE and an efficient task scheduling technique can utilize the resources in the MCE to complete the task execution at the earliest or in optimize manner. Task scheduling is a very common and challenging problem in MCE and it deals with finding an optimal scheduling of tasks to the processors so that the processing cost and processing time are be minimized and the processing reliability is maximized without violating any of the system constraints. Processing time is referred as the time taken by the task for its execution, expenses occurs during the task execution is describe as the processing cost and reliability can be consider as the reliability of its processors as well as the reliability of its communication links. Distribute data across processors unevenly so that each processor performs the volume of computation proportional to its speed is a common approach to solve task scheduling problem in MCE. This problem deals with finding an optimal task scheduling technique to the processors so that the processing time and cost can be minimized and processing reliability can be maximized for task scheduling in MCE. In MCE, the objective is to make processors busy executing tasks all the time by ensuring that it does not get idle and this serves the purpose. Task optimization is highly dependent on the tasks allocation method onto the available processor. In order to improve the performance of MCE, application workloads are divided into small independents units called tasks and these tasks need to be execute on available processor through a task scheduling technique. Task scheduling technique should be capable enough in terms of optimize processing capabilities in MCE i.e. minimize processing cost, minimize processing time and maximize processing reliability. This research paper explore task scheduling problem with n number of processors and m number of tasks where m>n in MCE and these tasks are need to schedule on the available processors in optimize manner with satisfying the processing constraints i.e. time, cost and reliability. In task scheduling problem once available processors are scheduled with a single task while the remaining tasks have to wait (if the numbers of task are greater than numbers of processor) until the present scheduled task will execute. To overcome such problem in a MCE, a task scheduling technique would be needed where more than one task to a single processor can be schedule in
  • 2. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 03 Issue: 05 | May-2014, Available @ http://www.ijret.org 824 order to achieve minimum processing time, processing cost and maximum processing reliability in MCE. Some of the task allocation schemes have been reported in the literature, such as Task modeling [1], Scheduling of tasks [2, 5, 7, 8, 11], Task allocation scheme [3, 15, 20], Resource allocation [4, 13, 14, 16, 19], Load balancing [10], Static task assignment [6], Resource scheduling [9], Job scheduling algorithm [12], Resource management and scheduling [17], Application scheduling in Mobile Cloud Computing [18]. This research paper propose a new task scheduling technique to task allocation in MCE by using the proper utilization of processors of the MCE so the problem of load balancing can be avoid. 2. NOTATIONS p Processor t Task n Number of Processors m Number of Tasks TCR Task Cost Reliability MTCR Modified Task Cost Reliability 3. OBJECTIVE The objective of this research paper is to solve task scheduling problem in an efficient manner so that maximum level of optimization is achieved in order to minimize processing cost and time and maximize reliability by the proper utilization of resource in Mobile Computing Environment (MCE). The applied technique would also ensure that processing of all the tasks and its sub tasks as task modules are more than the numbers of processors in the MCE. The type of assignment of tasks to the processor is static. In this research paper performance is measured in term of processing time, cost and reliability of the task that have to be get processed on the processors of the environment and it have to be optimally processed i.e., time, cost to be minimized and reliability maximized. 4. TECHNIQUE In order to obtain the overall optimal processing cost or processing time or processing reliability of a Mobile Computing Environment (MCE), this research paper consider a problem of task scheduling where a set P = {p1, p2, p3,………pn} of „n‟ processors with different processing capabilities and a set T = {t1, t2, t3,………tm} of „m‟ tasks, where m>n, every task has also contain some number of sub tasks module. Processing time, cost and reliability are known for each tasks module to the processor and arrange in TCTR. Initially processing cost, processing time will be initializing as zero (0) and processing reliability as one (1). Task scheduling algorithm will find for the minimum value by row (without repeating the column in the matrix) for processing time, cost or maximum for processing reliability, in result would get the tasks equal to number of processors available in the MCE and those task will get assigned. The process will repeat until number of tasks will remain lesser than the processor available in the environment. Once that situation will occur where the numbers of processors are greater than the tasks waiting for the processing then will make slide change in the technique. Instead of searching element row wise, the search will be column wise that will make enable the final allocation of remaining unscheduled task in MCE. The function to calculate overall time [Etime], cost [Ecost] and reliability [Ereilability] is given here: Etime = ETij Xij n i=1 n i=1 (i) Ecost = ECij Xij n i=1 n i=1 (ii) Ereliablity = ERij n i=0 n i=1 Xij (iii) 5. ALGORITHM 1. Start Algorithm 2. Read the number of task in m 3. Read the number of processor in n 4. Store task and Processing Cost, time and reliability into Matrix PCTR (,) n x m of order 5. While (All task! = Assigned) { i. Check if the matrix containing numbers of tasks are greater than or equal to numbers of processors (m>=n) then go to step (ii) else step (iv) ii. Search minimum value row wise in the matrix for time, cost or maximum value for reliability. iii. Check if the column is previously selected for minimum/maximum value then GO TO step – (ii) to find next minimum value for the row else Goto step (vi) to assign eligible task. iv. Search the minimum value for cost, time or maximum value for reliability column wise in the matrix v. Check if the row is previously selected for minimum or maximum value then GO TO step – (iv) to find next minimum or maximum value for the column else Goto step (vi) to assign eligible task. vi. Assign the eligible tasks to available processors } 6. State the results 7. End of algorithm 6. IMPLEMENTATION This research paper consider Mobile Computing Environment (MCE) which consist a set P of 3 processors {p1, p2, p3}, and a set T of 3 tasks {t1, t2, t3}. Each tasks contained some number of modules and these modules belongs to different tasks would be process on available processors in MCE as mentioned in mentioned in Figure 1.
  • 3. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 03 Issue: 05 | May-2014, Available @ http://www.ijret.org 825 Fig 1: Task modules originating from different mobile hosts are waiting in queue. Table 1: Tasks and their modules t1 {m11, m12, m13, m14,m15, m16} t2 {m21, m22, m23, m24, m25, m26, m27} t3 {m31, m32, m33, m34, m35, m36, m37, m38} Each task contained different individual task components which are known as modules. The processing time (t), processing cost (c) and processing reliability (r) of each task modules to each processor are known and mentioned in Processing Cost Time Reliability (PCTR) matrix as mentioned in Table 2 Table 2: Processing Time Cost Reliability Matrix Processors p1 p2 p3 Task Modules t-c-r t-c-r t-c-r t1 m11 15-100-0.999111 18-135-0.999125 17-110-0.999450 m12 16-110-0.999429 20-125-0.999159 18-115-0.999429 m13 21-115-0.999423 16-105-0.999328 15-120-0.999418 m14 18-120-0.999218 22-130-0.999419 23-100-0.999458 m15 19-105-0.999451 30-150-0.999480 26-125-0.999450 m16 33-125-0.999329 25-145-0.999219 28-155-0.998219 t2 m21 16-110-0.999112 18-125-0.941124 17-115-0.999418 m22 17-100-0.999149 20-135-0.982152 18-110-0.999429 m23 22-125-0.999533 16-130-0.979317 15-120-0.999418 m24 19-110-0.973218 22-105-0.999419 23-100-0.999413 m25 29-105-0.929431 30-150-0.989411 26-125-0.999414 m26 33-125-0.979328 25-145-0.969019 28-150-0.998226 m27 31-115-0.924322 22-140-0.924219 25-155-0.998214 t3 m31 15-125-0.999669 19-110-0. 997854 18-150-0. 998967 m32 18-100-0.999433 21-135-0. 998780 19-110-0. 999232 m33 26-130-0.998798 14-125-0. 998955 16-115-0. 987432 m34 21-110-0.999754 21-135-0. 987432 22-100-0. 999876 m35 29-105-0. 998766 32-155-0. 999578 24-185-0. 999866 m36 37-115-0. 998654 22-145-0. 998643 29-140-0. 998456 m37 35-125-0. 999478 25-160-0. 998903 24-105-0. 999754 m38 30-155-0. 999268 21-140-0. 998458 25-165-0. 996371 To proceed further with task scheduling problem in PCTR matrix, considering that t1 is based on processing time (t) (it may be processing cost or reliability), task t2 is based on processing cost (c) (it may be processing time and reliability) and task t3 is based on processing reliability (r) (it may be processing time and processing cost). Hence a new matrix named MPCTR can be derived by using PCTR, In MPCTR task t1 will represent processing time (t), t2 task processing cost (c) and t3 task processing reliability (r). New matrix MPCTR represent as Table 3: Table 3: Modified Processor Cost Time Reliability Matrix Processors p1 p2 p3 Task Modules t-c-r t-c-r t-c-r t1 m11 15-…-… 18-…-… 17-…-… m12 16-…-… 20-…-… 18-…-… m13 21-…-… 16-…-… 15-…-… m14 18-…-… 22-…-… 23-…-… m15 19-…-… 30-…-… 26-…-…
  • 4. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 03 Issue: 05 | May-2014, Available @ http://www.ijret.org 826 m16 33-…-… 25-…-… 28-…-… t2 m21 ...-110-… ...-125-… ...-115-… m22 ...-100-… ...-135-… ...-110-… m23 ...-125-… ...-130-… ...-120-… m24 ...-110-… ...-105-… ...-100-… m25 ...-105-… ...-150-… ...-125-… m26 ...-125-… ...-145-… ...-150-… m27 ...-115-… ...-140-… ...-155--… t3 m31 …-…-0. 999669 …-…-0. 997854 …-…-0. 998967 m32 …-…-0. 999433 …-…-0. 998780 …-…-0. 999232 m33 …-…-0.998798 …-…-0. 998955 …-…-0. 987432 m34 …-…-0. 999754 …-…-0. 987432 …-…-0. 999876 m35 …-…-0. 998766 …-…-0. 999578 …-…-0. 999866 m36 …-…-0. 998654 …-…-0. 998643 …-…-0. 998456 m37 …-…-0. 999478 …-…-0. 998903 …-…-0. 999754 m38 …-…-0. 999268 …-…-0. 998458 …-…-0. 996371 MPCTR can be break into three different tables for each constraint i.e. Table 4 for processing time, Table 5 for processing cost and Table 6 for processing reliability in order to demonstrate all the three constraints of processing i.e. time cost and reliability in Mobile Computing Environment (MCE). Table 4: Processing Time m11 m12 m13 m14 m15 p1 15 16 21 18 19 p2 18 20 16 22 30 p3 17 18 15 23 26 Table 5: Processing Cost m21 m22 m23 m24 m25 m26 m27 p1 110 100 125 110 105 125 115 p2 125 135 130 105 150 145 140 p3 115 110 120 100 125 150 155 Table 6: Processing Reliability m31 m32 m33 m34 m35 m36 m37 m38 p1 0. 999669 0. 999433 0.998798 0. 999754 0. 998766 0. 998654 0. 999478 0. 999268 p2 0. 997854 0. 998780 0. 998955 0. 987432 0. 999578 0. 998643 0. 998903 0. 998458 p3 0. 998967 0. 999232 0. 987432 0. 999876 0. 999866 0. 998456 0. 999754 0. 996371 To demonstrate new scheduling technique, this research paper is initially considering Table 4 for task scheduling in MCE. Table 4 represent number of five modules which are originally belongs to task t1 need to get schedule on number of 3 processors. In Table 4 numbers of task modules are 5 and the numbers of processors are 3 (m>n), scheduling technique will determine minimum value for each row and will get the resulting output as mentioned in Table 7: Table 7: Matrix representing minimum value m11 m12 m13 m14 m15 p1 15 p2 16 p3 18 Hence there are only three processors in the environment, employed technique would schedule only three task module in MCE as mentioned in Table 8. Table 8: Scheduling Table Processor Task Processing Cost p1 m11 15 p2 m12 16 p3 m13 18 After the first task scheduling step execution, still two task in the queue and gets unscheduled, here numbers of processors are greater than number of task (two) (m<n), now the element will be searched by column wise and that approach will ensure that none of the task module will get remain
  • 5. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 03 Issue: 05 | May-2014, Available @ http://www.ijret.org 827 unexecuted. And the final task scheduling is mentioned in Table 9. Table 9: Overall processing time Processor Task Processing time Etime p1 m11 * m14 33 93 p2 m12 16 p3 m13 * m15 44 Graphical representation of overall processing time is mentioned in Fig 2: Fig 2: Overall processing time taken by the processor in MCE By applying the same task scheduling technique, this research paper would also calculate processing cost and processing reliability for the given example in this research paper as mentioned in Table 10 and Table 11 respectively. Table 10: Overall processing cost Processor Task Processing Cost Ecost p1 m22 * m25 * m27 320 820 p2 m23 * m24 235 p3 m21* m26 265 Graphical representation of overall processing cost is mentioned in Fig 3: Fig 3: Overall processing cost occurred during the execution in MCE Table 11: Overall processing reliability Processor Task Processing Cost Ereliability p1 m31* m34 * m36 0.998077 0.993508 p2 m33 * m37 * m38 0.996320 p3 m32* m35 0.999098 Figure 4 showing graphical representation of overall processing reliability of given example: Fig 4: Overall processing reliability of the task in MCE 7. CONCLUSIONS This research paper provide the solution to the problem of task scheduling through a smart task scheduling technique, in which the number of the tasks is more than the number of processors in Mobile Computing Environment (MCE). Opted scheduling technique will ensure to satisfy various constraints i.e. time, cost and reliability in MCE. The task scheduling technique is presented in pseudo code and applied on the several sets of input data to test the performance and effectiveness of the pseudo code. Optimization of task is the common objective for any task scheduling problem that the
  • 6. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 03 Issue: 05 | May-2014, Available @ http://www.ijret.org 828 task needs to be processed with optimal time, cost and reliability. This paper consider three tasks i.e. t1, t2 and t3 with different tasks module and process t1 with minimum time, t2 process with minimum cost and t3 process with maximum reliability in MCE. The optimal output of the given example that is consider in research paper to test the task scheduling technique is mentioned in the implementation section of the paper is mentioned in Table 12: Table 12: Consolidated results for Time, Cost and Reliability in MCE Task p1 p2 p3 Optimal ETime Optimal ECost Optimal Ereliablity t1 m11 * m14 m12 m13 * m15 93 --- --- t2 m22 * m25 * m27 m23 * m24 m21 * m26 --- 820 --- t3 m34 * m31 * m36 m33 * m37 * m38 m32* m35 --- --- 0.993508 Fig 5: Final Task Scheduling in Mobile Computing Environment (MCE) The technique stated in pseudo code applied on several sets of input data and that verified the objective of get maximum processing reliability for given tasks for their execution. The analysis of an algorithm mainly focuses on time complexity. The time complexity of above mentioned algorithm is O(m+n). By taking several input examples, the above algorithm returns results as mentioned in Table 13. Table 13 Time Complexity Number of Processors (n) Number of tasks (m) Complexity of algorithm [5] O(mn2 ) Complexity of present algorithm O(m+n) 3 5 45 8 3 6 54 9 3 7 63 10 3 8 72 11 3 9 81 12 4 5 80 9 4 6 96 10 4 7 112 11 4 8 128 12 4 9 144 13 5 6 125 11 5 7 150 12 5 8 175 13 5 9 200 14 5 10 225 15 Time complexity comparisons (as mentioned in Table 13) are shown in Figure 6, 7 and 8. Fig 6: Time complexity for No of Processors 3 Fig 7: Time complexity for No of Processors 4
  • 7. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 03 Issue: 05 | May-2014, Available @ http://www.ijret.org 829 Fig 8: Time complexity for No of Processors 5 REFERENCES [1] Ana Isabel Molina, Miguel Ángel Redondo, Manuel Ortega, 2007, Applying Task Modeling and Pattern- based techniques in Reengineering Processes for Mobile Learning User Interfaces: A case study, JOURNAL OF COMPUTERS, VOL. 2, Issue 4, 23- 30 [2] Benazir Fateh, G. Manimaran, 2013, Joint Scheduling of Tasks and Messages for Energy Minimization in Interference-aware Real-time Sensor Networks, IEEE Transactions on Mobile Computing, 25 June 2013. IEEE computer Society Digital Library. IEEE Computer Society, <http://doi.ieeecomputersociety.org/10.1109/TMC.20 13.81>, ISSN: 1536-1233 [3] Faizul Navi Khan, Kapil Govil, 2013, Distributed Task Allocation Scheme for Performance Improvement in Mobile Computing Network, International Journal of Trends in Computer Science, vol: 2 issue: 3, pp: 809-817 [4] Hongbin Liang, Dijiang Huang, Lin X. Cai, Xuemin (Sherman) Shen, Daiyuan Peng, 2011, Resource Allocation for Security Services in Mobile Cloud Computing, IEEE INFOCOM 2011 Workshop on M2MCN-2011, ISBN: 978-1-4244-9920-5, 191-195 [5] Ilavarasan E, Manoharan R, 2010, High Performance and Energy Efficient Task Scheduling Algorithm for Heterogeneous Mobile Computing System, International Journal of Computer Science & Information Technology, Vol. 2, Issue 2, 10-27 [6] Kapil Govil and Dr. Avanish Kumar. 2011. A modified and efficient algorithm for Static task assignment in Distributed Processing Environment. International Journal of Computer Applications, Vol. 23, Number 8, Article 1, 1–5, ISBN: 978-93-80752- 82-3, ISSN: 0975 – 8887 [7] L. Yu, G. Zhou, Y. Pu, 2011, An Improved Task Scheduling Algorithm in Grid Computing Environment, Int'l J. of Communications, Network and System Sciences, Vol. 4 No. 4, 227-231. doi: 10.4236/ijcns.2011.44027. [8] Marjan Kuchaki Rafsanjani, Amid Khatibi Bardsiri, 2012, A New Heuristic Approach for Scheduling Independent Tasks on Heterogeneous Computing Systems, International Journal of Machine Learning and Computing, Vol: 2, No 4, 371-376 [9] S. Nagendram, J. Vijaya Lakshmi, D. Venkata Narasimha Rao, 2011, Efficient resource scheduling in data centers using MRIS, Indian Journal of Computer Science and Engineering, vol. 2, no. 5, pp. 764–769. [10] S. Suryadevera, J. Chourasia, S. Rathore, A. Jhummarwala, 2012, Load balancing in computational grids using ant colony optimization algorithm,” International Journal of Computer & Communication Technology, vol. 3, Issue 3, 20-23 [11] S. Thenmozhi , A. Tamilarasi, K. Thangavel, 2012, Fuzzy Based Task Scheduling for Hierarchical Resource Allocation in Mobile Grid Environment, International Journal of Soft Computing, Vol: 7, Issue: 3, 97-103 [12] Sandeep Kaur, Sukhpreet Kaur, 2013, Survey of Resource and Grouping Based Job Scheduling Algorithm in Grid Computing, International Journal of Computer Science and Mobile Computing, Vol: 2, Issue. 5, 214-218 [13] Sayed Chhattan Shah, Myong-Soon Park, 2010, Resource Allocation Scheme to Minimize Communication Cost in Mobile Ad Hoc Computational Grids, International Conference on Intelligent Networking and Collaborative Systems, ISBN: 978-0-7695-4278-2, 169-176 [14] Sayed Chhattan Shah, Qurat-Ul-Ain Nizamanib, Sajjad Hussain Chauhdaryc, Myong-Soon Park, 2012, An effective and robust two-phase resource allocation scheme for interdependent tasks in mobile ad hoc computational Grids, Journal of Parallel and Distributed Computing, Vol: 72, Issue 12, 1664–1679 [15] T. Xie and X. Qin, 2008, An Energy-Delay Tunable Task Allocation Strategy for Collaborative Applications in Networked Embedded Systems, IEEE Trans. Computers, Vol: 57, Issue 3, 329-343. [16] Thenmozhi S., A. Tamilarasi and P.T. Vanathi, 2012, A Fault Tolerant Resource Allocation Architecture for Mobile Grid, Journal of Computer Science, Vol: 8, Issue 6, 978-982 [17] Vignesh V, Sendhil Kumar KS, Jaisankar N, 2013, Resource Management and Scheduling in Cloud Environment, International Journal of Scientific and Research Publications, Volume 3, Issue 6, 1-6 [18] Xianglin Wei,Jianhua Fan, Ziyi Lu,Ke Ding, 2013, Application Scheduling in Mobile Cloud Computing with Load Balancing, Journal of Applied Mathematics, Vol: 2013, 1-13 [19] Yashpal Rohilla, Preeti Gulia, 2012, Resource Allocation in cellular Network : A cross layer approach, International Journal of Engineering Research and Applications, Vol. 2, Issue 4, 912-915 [20] Yichao Jin, Jiong Jin, Alexander Gluhak, Klaus Moessner and Marimuthu Palaniswami, 2012, An Intelligent Task Allocation Scheme for Multihop Wireless Networks, IEEE Transactions on Parallel and Distributed Systems, Vol: 23, Issue 3, 444-451