SlideShare a Scribd company logo
DOC NO 
V 
DATE 
PAGE NO 
03 OF 05 
PROJECT 
TITLE 
JOB PROCEDURE FOR HYDRO TEST / WATER FILL 
UP TEST 
JOB PROCEDURE FOR HYDROTEST/WATER FILLUP TEST 
1. SCOPE 
This test procedure shall be carried out to detect the leak in shell weld joints and to 
observe the load stabilization of liquid in interval level height. 
2. PURPOSE 
The purpose of this procedure is providing the guideline and sequential steps for the 
hydro test / water fill up test for the tank. 
3. CHECK LIST 
 After completion of the erection, welding and NDT the following points shall be 
checked before testing. 
 All the mechanical activities completion in respect of the drawing and HPCL 
Specification and code requirements. 
 Radiography completion including repairs. 
 The entire NDT test like chalk-diesel test, LPT, RF .Pad pneumatic test, vacuum box 
test completion. 
 Finally mechanical clearance from the Engineer-In-Charge shall be taken before 
Hydrotest in approved format 
4. TEST MEDIA 
Test media shall be in iron free water, which is clean and free of silt i.e.; Portable 
water 
5. PROCEDURE 
 Proper arrangement shall be carried out for the water filling (pipe connection from 
the water resource point and providing valves and NRV wherever required. 
 markers shall be provided on the shell, 500 mm from the bottom to check tank 
settlement. Size shall be 50 X 50 X 6mm angle and 100 mm long. The nos. of 
setting marker shall be minimum 8 Nos or as per the approved Drg. 
 Code : API 650 (7.3.6) Eleven Edition 
Prepared by 
CONTRACTOR . 
Concurred by 
Name : 
Design: 
Hindustan Petroleum Crop. Ltd. 
Approved by 
Name : 
Design: 
Hindustan Petroleum Crop. Ltd
DOC NO 
VS 
DATE 
PAGE NO 
04 OF 05 
PROJECT 
TITLE 
JOB PROCEDURE FOR HYDRO TEST / WATER FILL 
UP TEST 
 Settling markers shall be provided at every 300 outside the tank at a height of 500 
mm from the top of annular plate. 
 Setting marker shall be welded and initial level reading shall be taken with respect 
to the permanent benchmark using dumpy level / Total station 
 Shell settlement measurements shall be made after tank erection, prior to 
hydrotesting and during water filling at 1000 mm intervals up to maximum filling 
height of tank. 
 The levels taken before water filling called as initial level of the tank and shall be 
record in an approved format. 
 The water filling height shall be restricted to the max. Liquid Level or up to the 
curb angle. 
 The water filling shall be carried out in four stages (25%, 50%, 75%  100% of the 
max liquid level of the tank) 
 Any leaks observed in the shell joint during the hydro test shall be noted and 
repaired with the water level min. of 300mm below the leak spot. 
 The repaired shall be carried out as per the procedure and tank test shall be 
recommenced. 
 After each stage of filling, a load stabilization period shall be observed as 
minimum 24 hours max between each stage of filling. 
 During the stabilization period the settlement reading shall be observed and 
recorded jointly with HPCL Engineer-In-Charge through dumpy level only. 
 Filling rate shall be not exceed 5 meters per day. 
 After completion of the water filling the water load shall be maintained for 24 
hours. After 24 hours the final settlement reading shall be recorded jointly with 
engineer-In-Charge. 
 Tank shall be emptied at a maximum water level variation rate of 5 meters per 
day. Care shall be taken that top manholes are open during empty operation of 
conical roof tanks. 
 If salt water is used then corrosion inhibitor should be sprayed (mixed) prior to 
filling / after hydro test the tank should be thoroughly cleaned with sweat water. 
Prepared by 
CONTRACTOR . 
Concurred by 
Name : 
Design: 
Hindustan Petroleum Crop. Ltd. 
Approved by 
Name : 
Design: 
Hindustan Petroleum Crop. Ltd
DOC NO 
DATE 
PAGE NO 
05 OF 05 
PROJECT 
TITLE 
JOB PROCEDURE FOR HYDRO TEST / WATER FILL 
UP TEST 
6. CLEANING 
After draining the water the tank shall be thoroughly cleaned, free from dirt and 
foreign materials and shall be dried by air. 
7. RECORDS 
Records shall be prepared and submitted to Engineer in-charge for approval. 
8. SAFETY 
All Safety precaution shall be taken during water fill up test. 
9. REFRENCE 
(A) API 650 
(B) OISD 129 
(C) PO Tech Specification 
Note : Permanent B M shall be min. 50Mtr away from Tank shell 
Prepared by 
CONTRACTOR . 
Concurred by 
Name : 
Design: 
Hindustan Petroleum Crop. Ltd. 
Approved by 
Name : 
Design: 
Hindustan Petroleum Crop. Ltd

More Related Content

What's hot

Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
MOHAMMAD ATIF ALI
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
Personal Secret
 
Presentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxPresentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptx
hesham ismail
 
Heat exchanger types and hydro testing
Heat exchanger types and hydro testingHeat exchanger types and hydro testing
Heat exchanger types and hydro testing
waqarahmed445
 
API 653 TANK INSPECTION.pdf
API 653 TANK INSPECTION.pdfAPI 653 TANK INSPECTION.pdf
Process piping fundamentals, codes and standards module 1
Process piping fundamentals, codes and standards    module 1Process piping fundamentals, codes and standards    module 1
Process piping fundamentals, codes and standards module 1
BHARAT BELLAD
 
Pressure testing
Pressure testingPressure testing
Pressure testing
Joshua Danquah
 
Methods of examination of joints(RT) - API 650 Tanks
Methods of examination of joints(RT) - API 650 TanksMethods of examination of joints(RT) - API 650 Tanks
Methods of examination of joints(RT) - API 650 Tanks
RajSamy
 
Saudi aramco standards
Saudi aramco standardsSaudi aramco standards
Saudi aramco standards
Jithu John
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and CommissioningWendy Soerachman
 
Piping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfPiping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdf
MDAbdullah621330
 
Piping presentation (master)
Piping presentation (master)Piping presentation (master)
Piping presentation (master)
Velmurugan Sivaraman
 
343312365 mt-ppt
343312365 mt-ppt343312365 mt-ppt
343312365 mt-ppt
MohamedAwad197
 
Online Pressure Vessel Training.pdf
Online Pressure Vessel Training.pdfOnline Pressure Vessel Training.pdf
Online Pressure Vessel Training.pdf
DharmeshBhati2
 
Piping design and flexibility analysis
Piping design and flexibility analysisPiping design and flexibility analysis
Piping design and flexibility analysis
Sarath Krishnakumar
 
Api 653 study guide
Api 653 study guideApi 653 study guide
Api 653 study guide
JayJay Makinano
 
API 653 - Material preparado.ppt
API 653 - Material preparado.pptAPI 653 - Material preparado.ppt
API 653 - Material preparado.ppt
ClaudiaPatriciaMagaa1
 
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Varun Patel
 
Process piping design & engineering per asme b 31.3
Process piping design & engineering per asme b 31.3Process piping design & engineering per asme b 31.3
Process piping design & engineering per asme b 31.3
Rajiv Kumar
 

What's hot (20)

HAZARDS-Pneumatic Test(1)
HAZARDS-Pneumatic Test(1)HAZARDS-Pneumatic Test(1)
HAZARDS-Pneumatic Test(1)
 
Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
 
Presentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxPresentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptx
 
Heat exchanger types and hydro testing
Heat exchanger types and hydro testingHeat exchanger types and hydro testing
Heat exchanger types and hydro testing
 
API 653 TANK INSPECTION.pdf
API 653 TANK INSPECTION.pdfAPI 653 TANK INSPECTION.pdf
API 653 TANK INSPECTION.pdf
 
Process piping fundamentals, codes and standards module 1
Process piping fundamentals, codes and standards    module 1Process piping fundamentals, codes and standards    module 1
Process piping fundamentals, codes and standards module 1
 
Pressure testing
Pressure testingPressure testing
Pressure testing
 
Methods of examination of joints(RT) - API 650 Tanks
Methods of examination of joints(RT) - API 650 TanksMethods of examination of joints(RT) - API 650 Tanks
Methods of examination of joints(RT) - API 650 Tanks
 
Saudi aramco standards
Saudi aramco standardsSaudi aramco standards
Saudi aramco standards
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and Commissioning
 
Piping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfPiping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdf
 
Piping presentation (master)
Piping presentation (master)Piping presentation (master)
Piping presentation (master)
 
343312365 mt-ppt
343312365 mt-ppt343312365 mt-ppt
343312365 mt-ppt
 
Online Pressure Vessel Training.pdf
Online Pressure Vessel Training.pdfOnline Pressure Vessel Training.pdf
Online Pressure Vessel Training.pdf
 
Piping design and flexibility analysis
Piping design and flexibility analysisPiping design and flexibility analysis
Piping design and flexibility analysis
 
Api 653 study guide
Api 653 study guideApi 653 study guide
Api 653 study guide
 
API 653 - Material preparado.ppt
API 653 - Material preparado.pptAPI 653 - Material preparado.ppt
API 653 - Material preparado.ppt
 
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
 
Process piping design & engineering per asme b 31.3
Process piping design & engineering per asme b 31.3Process piping design & engineering per asme b 31.3
Process piping design & engineering per asme b 31.3
 

Viewers also liked

20 Essential Hydrotest Safety Checklist
20 Essential Hydrotest Safety Checklist20 Essential Hydrotest Safety Checklist
20 Essential Hydrotest Safety Checklist
Lukman Nulhakiem
 
Pipe Hydrotest , Inspection, Visual and Dimensional Inspection & Marking
Pipe Hydrotest , Inspection, Visual and Dimensional Inspection & MarkingPipe Hydrotest , Inspection, Visual and Dimensional Inspection & Marking
Pipe Hydrotest , Inspection, Visual and Dimensional Inspection & Marking
Varun Patel
 
Hydro test pump
Hydro test pumpHydro test pump
Hydro test pump
Shrikunj Patel
 
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure  What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
Varun Patel
 
Valves presentation
Valves presentationValves presentation
Valves presentation
mohdalaamri
 
Use of nitrogen purge in flare and vent systems
Use of nitrogen purge in flare and vent systemsUse of nitrogen purge in flare and vent systems
Use of nitrogen purge in flare and vent systemsLanphuong Pham
 
Valves for hydro power applications
Valves for hydro power applicationsValves for hydro power applications
Valves for hydro power applications
John McNeill
 
Stainless steel tanks
Stainless steel tanksStainless steel tanks
Stainless steel tanks
Carson McClane
 
Manual Gate Valve Kick-off Meeting (brand : VELAN)
Manual Gate Valve Kick-off Meeting  (brand : VELAN)Manual Gate Valve Kick-off Meeting  (brand : VELAN)
Manual Gate Valve Kick-off Meeting (brand : VELAN)
Aestikani Mahani
 
Asme sec viii div 2
Asme sec viii div 2Asme sec viii div 2
Asme sec viii div 2
Jithu John
 
Welded steel tanks for storage oil
Welded steel tanks for storage oilWelded steel tanks for storage oil
Welded steel tanks for storage oilYahya Haggag
 

Viewers also liked (14)

20 Essential Hydrotest Safety Checklist
20 Essential Hydrotest Safety Checklist20 Essential Hydrotest Safety Checklist
20 Essential Hydrotest Safety Checklist
 
Pipe Hydrotest , Inspection, Visual and Dimensional Inspection & Marking
Pipe Hydrotest , Inspection, Visual and Dimensional Inspection & MarkingPipe Hydrotest , Inspection, Visual and Dimensional Inspection & Marking
Pipe Hydrotest , Inspection, Visual and Dimensional Inspection & Marking
 
Hydro test pump
Hydro test pumpHydro test pump
Hydro test pump
 
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure  What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
 
Valves presentation
Valves presentationValves presentation
Valves presentation
 
Use of nitrogen purge in flare and vent systems
Use of nitrogen purge in flare and vent systemsUse of nitrogen purge in flare and vent systems
Use of nitrogen purge in flare and vent systems
 
Valves for hydro power applications
Valves for hydro power applicationsValves for hydro power applications
Valves for hydro power applications
 
Stainless steel tanks
Stainless steel tanksStainless steel tanks
Stainless steel tanks
 
Manual Gate Valve Kick-off Meeting (brand : VELAN)
Manual Gate Valve Kick-off Meeting  (brand : VELAN)Manual Gate Valve Kick-off Meeting  (brand : VELAN)
Manual Gate Valve Kick-off Meeting (brand : VELAN)
 
Welding of pipelines
Welding of pipelinesWelding of pipelines
Welding of pipelines
 
Introduction_to_NDT
Introduction_to_NDTIntroduction_to_NDT
Introduction_to_NDT
 
Asme sec viii div 2
Asme sec viii div 2Asme sec viii div 2
Asme sec viii div 2
 
Ppt
PptPpt
Ppt
 
Welded steel tanks for storage oil
Welded steel tanks for storage oilWelded steel tanks for storage oil
Welded steel tanks for storage oil
 

Similar to 7) hydro test 3

171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt
ssuser9e9be71
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouring
Bharatha Rathnayke
 
Flushing cleaning procedure
Flushing  cleaning procedureFlushing  cleaning procedure
Flushing cleaning procedure
Natee Tsui
 
Hazard operability study - in Industires and plant
Hazard operability study - in Industires and plantHazard operability study - in Industires and plant
Hazard operability study - in Industires and plant
JayaKarthic1
 
HAZOP.ppt
HAZOP.pptHAZOP.ppt
HAZOP.ppt
JayaKarthic1
 
Oil & Gas Production theory cocnepts.ppt
Oil & Gas Production theory cocnepts.pptOil & Gas Production theory cocnepts.ppt
Oil & Gas Production theory cocnepts.ppt
jainjainik6096
 
Presentation chapter 5
Presentation chapter 5Presentation chapter 5
Presentation chapter 5
Paulo P
 
Presentation chapter 5
Presentation chapter 5Presentation chapter 5
Presentation chapter 5Paulo P
 
DEPLETED OIL FIELDS - Regeneration with Water_Shutoff - EUCO Group
DEPLETED OIL FIELDS - Regeneration with Water_Shutoff - EUCO GroupDEPLETED OIL FIELDS - Regeneration with Water_Shutoff - EUCO Group
DEPLETED OIL FIELDS - Regeneration with Water_Shutoff - EUCO GroupBoris Svasta
 
Depleted oil fields regeneration with water shutoff - euco group
Depleted oil fields   regeneration with water shutoff - euco groupDepleted oil fields   regeneration with water shutoff - euco group
Depleted oil fields regeneration with water shutoff - euco groupBoris Svasta
 
TANK presentation-2.pptx
TANK presentation-2.pptxTANK presentation-2.pptx
TANK presentation-2.pptx
Murugan I
 
26-grover-john-final
26-grover-john-final26-grover-john-final
26-grover-john-finalJohn Grover
 
Operation & maintenance 2011
Operation & maintenance 2011Operation & maintenance 2011
Operation & maintenance 2011
Abdul Hakeem S.K.
 
Api 650 & 653 questions closed book with answers
Api 650 & 653 questions closed book with answersApi 650 & 653 questions closed book with answers
Api 650 & 653 questions closed book with answers
Jasminder singh
 
TDLR Well Driller/Pump Installer Program, W.L. Stribling, Project Manager, Te...
TDLR Well Driller/Pump Installer Program, W.L. Stribling, Project Manager, Te...TDLR Well Driller/Pump Installer Program, W.L. Stribling, Project Manager, Te...
TDLR Well Driller/Pump Installer Program, W.L. Stribling, Project Manager, Te...Texas Alliance of Groundwater Districts
 
Well_Completions.pdf
Well_Completions.pdfWell_Completions.pdf
Well_Completions.pdf
AihamAltayeh1
 
Analyzing Multi-zone completion using multilayer by IPR (PROSPER)
Analyzing Multi-zone completion using multilayer by IPR (PROSPER)  Analyzing Multi-zone completion using multilayer by IPR (PROSPER)
Analyzing Multi-zone completion using multilayer by IPR (PROSPER)
Arez Luqman
 
Internship Report
Internship ReportInternship Report
Internship ReportMalik Ehsan
 

Similar to 7) hydro test 3 (20)

171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouring
 
Flushing cleaning procedure
Flushing  cleaning procedureFlushing  cleaning procedure
Flushing cleaning procedure
 
Hazard operability study - in Industires and plant
Hazard operability study - in Industires and plantHazard operability study - in Industires and plant
Hazard operability study - in Industires and plant
 
HAZOP.ppt
HAZOP.pptHAZOP.ppt
HAZOP.ppt
 
Oil & Gas Production theory cocnepts.ppt
Oil & Gas Production theory cocnepts.pptOil & Gas Production theory cocnepts.ppt
Oil & Gas Production theory cocnepts.ppt
 
Presentation chapter 5
Presentation chapter 5Presentation chapter 5
Presentation chapter 5
 
Presentation chapter 5
Presentation chapter 5Presentation chapter 5
Presentation chapter 5
 
Husam CV updated (1)
Husam CV updated (1)Husam CV updated (1)
Husam CV updated (1)
 
DEPLETED OIL FIELDS - Regeneration with Water_Shutoff - EUCO Group
DEPLETED OIL FIELDS - Regeneration with Water_Shutoff - EUCO GroupDEPLETED OIL FIELDS - Regeneration with Water_Shutoff - EUCO Group
DEPLETED OIL FIELDS - Regeneration with Water_Shutoff - EUCO Group
 
Depleted oil fields regeneration with water shutoff - euco group
Depleted oil fields   regeneration with water shutoff - euco groupDepleted oil fields   regeneration with water shutoff - euco group
Depleted oil fields regeneration with water shutoff - euco group
 
TANK presentation-2.pptx
TANK presentation-2.pptxTANK presentation-2.pptx
TANK presentation-2.pptx
 
26-grover-john-final
26-grover-john-final26-grover-john-final
26-grover-john-final
 
Operation & maintenance 2011
Operation & maintenance 2011Operation & maintenance 2011
Operation & maintenance 2011
 
NDL FUEL STATION OPERATION
NDL FUEL STATION OPERATIONNDL FUEL STATION OPERATION
NDL FUEL STATION OPERATION
 
Api 650 & 653 questions closed book with answers
Api 650 & 653 questions closed book with answersApi 650 & 653 questions closed book with answers
Api 650 & 653 questions closed book with answers
 
TDLR Well Driller/Pump Installer Program, W.L. Stribling, Project Manager, Te...
TDLR Well Driller/Pump Installer Program, W.L. Stribling, Project Manager, Te...TDLR Well Driller/Pump Installer Program, W.L. Stribling, Project Manager, Te...
TDLR Well Driller/Pump Installer Program, W.L. Stribling, Project Manager, Te...
 
Well_Completions.pdf
Well_Completions.pdfWell_Completions.pdf
Well_Completions.pdf
 
Analyzing Multi-zone completion using multilayer by IPR (PROSPER)
Analyzing Multi-zone completion using multilayer by IPR (PROSPER)  Analyzing Multi-zone completion using multilayer by IPR (PROSPER)
Analyzing Multi-zone completion using multilayer by IPR (PROSPER)
 
Internship Report
Internship ReportInternship Report
Internship Report
 

Recently uploaded

ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 

Recently uploaded (20)

ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 

7) hydro test 3

  • 1. DOC NO V DATE PAGE NO 03 OF 05 PROJECT TITLE JOB PROCEDURE FOR HYDRO TEST / WATER FILL UP TEST JOB PROCEDURE FOR HYDROTEST/WATER FILLUP TEST 1. SCOPE This test procedure shall be carried out to detect the leak in shell weld joints and to observe the load stabilization of liquid in interval level height. 2. PURPOSE The purpose of this procedure is providing the guideline and sequential steps for the hydro test / water fill up test for the tank. 3. CHECK LIST After completion of the erection, welding and NDT the following points shall be checked before testing. All the mechanical activities completion in respect of the drawing and HPCL Specification and code requirements. Radiography completion including repairs. The entire NDT test like chalk-diesel test, LPT, RF .Pad pneumatic test, vacuum box test completion. Finally mechanical clearance from the Engineer-In-Charge shall be taken before Hydrotest in approved format 4. TEST MEDIA Test media shall be in iron free water, which is clean and free of silt i.e.; Portable water 5. PROCEDURE Proper arrangement shall be carried out for the water filling (pipe connection from the water resource point and providing valves and NRV wherever required. markers shall be provided on the shell, 500 mm from the bottom to check tank settlement. Size shall be 50 X 50 X 6mm angle and 100 mm long. The nos. of setting marker shall be minimum 8 Nos or as per the approved Drg. Code : API 650 (7.3.6) Eleven Edition Prepared by CONTRACTOR . Concurred by Name : Design: Hindustan Petroleum Crop. Ltd. Approved by Name : Design: Hindustan Petroleum Crop. Ltd
  • 2. DOC NO VS DATE PAGE NO 04 OF 05 PROJECT TITLE JOB PROCEDURE FOR HYDRO TEST / WATER FILL UP TEST Settling markers shall be provided at every 300 outside the tank at a height of 500 mm from the top of annular plate. Setting marker shall be welded and initial level reading shall be taken with respect to the permanent benchmark using dumpy level / Total station Shell settlement measurements shall be made after tank erection, prior to hydrotesting and during water filling at 1000 mm intervals up to maximum filling height of tank. The levels taken before water filling called as initial level of the tank and shall be record in an approved format. The water filling height shall be restricted to the max. Liquid Level or up to the curb angle. The water filling shall be carried out in four stages (25%, 50%, 75% 100% of the max liquid level of the tank) Any leaks observed in the shell joint during the hydro test shall be noted and repaired with the water level min. of 300mm below the leak spot. The repaired shall be carried out as per the procedure and tank test shall be recommenced. After each stage of filling, a load stabilization period shall be observed as minimum 24 hours max between each stage of filling. During the stabilization period the settlement reading shall be observed and recorded jointly with HPCL Engineer-In-Charge through dumpy level only. Filling rate shall be not exceed 5 meters per day. After completion of the water filling the water load shall be maintained for 24 hours. After 24 hours the final settlement reading shall be recorded jointly with engineer-In-Charge. Tank shall be emptied at a maximum water level variation rate of 5 meters per day. Care shall be taken that top manholes are open during empty operation of conical roof tanks. If salt water is used then corrosion inhibitor should be sprayed (mixed) prior to filling / after hydro test the tank should be thoroughly cleaned with sweat water. Prepared by CONTRACTOR . Concurred by Name : Design: Hindustan Petroleum Crop. Ltd. Approved by Name : Design: Hindustan Petroleum Crop. Ltd
  • 3. DOC NO DATE PAGE NO 05 OF 05 PROJECT TITLE JOB PROCEDURE FOR HYDRO TEST / WATER FILL UP TEST 6. CLEANING After draining the water the tank shall be thoroughly cleaned, free from dirt and foreign materials and shall be dried by air. 7. RECORDS Records shall be prepared and submitted to Engineer in-charge for approval. 8. SAFETY All Safety precaution shall be taken during water fill up test. 9. REFRENCE (A) API 650 (B) OISD 129 (C) PO Tech Specification Note : Permanent B M shall be min. 50Mtr away from Tank shell Prepared by CONTRACTOR . Concurred by Name : Design: Hindustan Petroleum Crop. Ltd. Approved by Name : Design: Hindustan Petroleum Crop. Ltd