SlideShare a Scribd company logo
CHECKLIST
CONCRETE WORKS
Checklist No.
Name of Work: Pr. Start Date
Employer: Pr. End Date
Contract No.:
Contractor: S.S.PROJECTS, VIZAG
Item Dscrptn: Inspection Requested by: BOQ No.
1ST INSPECTION 2ND INSPECTION 3RD INSPECTIONMix Grade:
Req. on: Req. on: Req. on:
Location Section Level By.: By.: By.: Quantity
Date: Date: Date:
Time: Time: Time:
Points to Check Action Req. Action Req. Action Req. REMARKS
FORMWORK
1. Dimensions, level & Plumb
2. Tightness & Rigidity
3. Stop / Drop Formwork
4. Cleanliness
5. Shutter Release Agent
REBAR
1. Bar Size & Nos., spacing & Laps
2. Bar Spacing & Laps
3. Cleanliness
4. Covers, Hooks & Binding Rigidity
5. Starter & Bonding Bars
GENERAL
1. Anti Termite Treatment
2. Box Outs
3. Pipe Sleeves
4. Embedded Items
5. Quality of Bulk Materials / RMC
6. Plastisizers / Additives
7. Expansion Joint Provisions if any
8. Existing Concrete Hacking & Cleaning
9. Special treatments in existing surface
ENDORSEMENTS
Agency Name Sign with Date
Main Contractor
Electrical
ACMV
Fire Protection
Plumbing
Others[Specify]]
Approved for Concreting Task Start Date:
POSTCONCRETING
Pour Start Date & Time:
Concreting End Date & Time:
No. of Cubes Taken:
Average Slump:
Method of Pouring & Vibration Acceptable To Improve Arrangement for Curing / Ponding Acceptable To Improve
Stability of Formwork after Pour Acceptable To Improve Acceptable To Improve
Line, Level & finishing Acceptable To Improve Acceptable To Improve
DESHUTTER
Sch. date for formwork removal with supports Actual Date of Removal
Sch. date for form work removal entirely Actual Date of Removal
Line, Level & finishing of Concrete surface Acceptable To Rectify Acceptable To Rectify
Removal of Battens, Maskin tape etc. Acceptable To Rectify Acceptable To Rectify
Action Required:- Remarks: Rectifications done as specified:
Dry finish
Wet finish
Grouting Task End Date:
Epoxy Treatment
GLOBAL ENTROPOLIS
VIZAG PVT LTD
Checklist
Date
OP
OP
OP
Details of Additional Steel Provided if any: [Other than specified in Drg.]
Others [Specify]
DE
Note : Record typical dimensional check on reverse of this format
Civil (SSP) Elec (GEVPL) Mech (GEVPL) GEVPL( CIVIL )

More Related Content

What's hot

Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structureMinh Bui Si
 
Itp & ceklist kolom erlangga 22160008
Itp & ceklist kolom erlangga 22160008Itp & ceklist kolom erlangga 22160008
Itp & ceklist kolom erlangga 22160008ErlanggaMahansmara
 
File_Soal_17_160_29_1660796769.pptx
File_Soal_17_160_29_1660796769.pptxFile_Soal_17_160_29_1660796769.pptx
File_Soal_17_160_29_1660796769.pptxTeguhRiswanto2
 
QA/QC Civil Engineer
QA/QC Civil EngineerQA/QC Civil Engineer
QA/QC Civil EngineerRavi chandran
 
PPT SKK PELAKSANA JALAN - rev.pptx_1677900456.pdf
PPT SKK PELAKSANA JALAN - rev.pptx_1677900456.pdfPPT SKK PELAKSANA JALAN - rev.pptx_1677900456.pdf
PPT SKK PELAKSANA JALAN - rev.pptx_1677900456.pdfTaufikkurrahman Upik Teler
 
Site organization in Construction
Site organization in ConstructionSite organization in Construction
Site organization in ConstructionSamsonFemiAdesope
 
Method statement for civil works
Method statement for civil worksMethod statement for civil works
Method statement for civil worksMuhammad Shahid
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002Minh Bui Si
 
QUANTITY SURVEYING & ESTIMATION- Nicmar
QUANTITY SURVEYING & ESTIMATION- NicmarQUANTITY SURVEYING & ESTIMATION- Nicmar
QUANTITY SURVEYING & ESTIMATION- NicmarMuneesh Methwani
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTmustafa hussain
 
Manajer Lapangan Pelaksanaan Pekerjaan.pptx
Manajer Lapangan Pelaksanaan Pekerjaan.pptxManajer Lapangan Pelaksanaan Pekerjaan.pptx
Manajer Lapangan Pelaksanaan Pekerjaan.pptxmuchamadhumaedi
 

What's hot (20)

A.G.sajid cv
A.G.sajid  cvA.G.sajid  cv
A.G.sajid cv
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
 
JSA For Work at Height.docx
JSA For Work at Height.docxJSA For Work at Height.docx
JSA For Work at Height.docx
 
Itp & ceklist kolom erlangga 22160008
Itp & ceklist kolom erlangga 22160008Itp & ceklist kolom erlangga 22160008
Itp & ceklist kolom erlangga 22160008
 
File_Soal_17_160_29_1660796769.pptx
File_Soal_17_160_29_1660796769.pptxFile_Soal_17_160_29_1660796769.pptx
File_Soal_17_160_29_1660796769.pptx
 
BS course bldg diagnostic
BS course bldg diagnosticBS course bldg diagnostic
BS course bldg diagnostic
 
QA/QC Civil Engineer
QA/QC Civil EngineerQA/QC Civil Engineer
QA/QC Civil Engineer
 
PPT SKK PELAKSANA JALAN - rev.pptx_1677900456.pdf
PPT SKK PELAKSANA JALAN - rev.pptx_1677900456.pdfPPT SKK PELAKSANA JALAN - rev.pptx_1677900456.pdf
PPT SKK PELAKSANA JALAN - rev.pptx_1677900456.pdf
 
Column & beam
Column & beamColumn & beam
Column & beam
 
Itp
ItpItp
Itp
 
Site organization in Construction
Site organization in ConstructionSite organization in Construction
Site organization in Construction
 
Saudi Aramco Inspection Checklist (SAIC)
Saudi Aramco Inspection Checklist (SAIC)Saudi Aramco Inspection Checklist (SAIC)
Saudi Aramco Inspection Checklist (SAIC)
 
Method statement for civil works
Method statement for civil worksMethod statement for civil works
Method statement for civil works
 
dayat PIPA.pptx
dayat PIPA.pptxdayat PIPA.pptx
dayat PIPA.pptx
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002
 
QUANTITY SURVEYING & ESTIMATION- Nicmar
QUANTITY SURVEYING & ESTIMATION- NicmarQUANTITY SURVEYING & ESTIMATION- Nicmar
QUANTITY SURVEYING & ESTIMATION- Nicmar
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENT
 
Design Checklist Civil & Structural
Design Checklist Civil & StructuralDesign Checklist Civil & Structural
Design Checklist Civil & Structural
 
ACH 216 Lecture 12 (Closeut & Turnover)
ACH 216 Lecture 12 (Closeut & Turnover)ACH 216 Lecture 12 (Closeut & Turnover)
ACH 216 Lecture 12 (Closeut & Turnover)
 
Manajer Lapangan Pelaksanaan Pekerjaan.pptx
Manajer Lapangan Pelaksanaan Pekerjaan.pptxManajer Lapangan Pelaksanaan Pekerjaan.pptx
Manajer Lapangan Pelaksanaan Pekerjaan.pptx
 

Similar to 50338447 checklist-concrete-works

Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...
Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...
Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...Sangilimuthu Samiayyah
 
Lowerin Laying & Jointing of Pipelie.pptx
Lowerin Laying & Jointing of Pipelie.pptxLowerin Laying & Jointing of Pipelie.pptx
Lowerin Laying & Jointing of Pipelie.pptxBharat Somani
 
BALAJI RESUME. UPDATED
BALAJI RESUME. UPDATEDBALAJI RESUME. UPDATED
BALAJI RESUME. UPDATEDP. Balaji
 
Aim condition assessment (2)
Aim condition assessment (2)Aim condition assessment (2)
Aim condition assessment (2)Akshay Gottlieb
 
Tendering Document for the Procurement of Works
Tendering Document for the Procurement of WorksTendering Document for the Procurement of Works
Tendering Document for the Procurement of WorksMohammad Alimuzzaman Bappy
 
Die casting die design process
Die casting die design processDie casting die design process
Die casting die design processShuvamKumar9
 
Kumar.R Multi Inspector cv -5 - Copy
Kumar.R   Multi Inspector cv   -5 - CopyKumar.R   Multi Inspector cv   -5 - Copy
Kumar.R Multi Inspector cv -5 - CopyKumar ramalingam
 
Structural & Piping QC Inspector CV - PDF
Structural & Piping QC Inspector CV - PDFStructural & Piping QC Inspector CV - PDF
Structural & Piping QC Inspector CV - PDFChandra Battu
 
Mohammad Taher_QA-QC Piping-Welding
Mohammad Taher_QA-QC Piping-WeldingMohammad Taher_QA-QC Piping-Welding
Mohammad Taher_QA-QC Piping-WeldingMohammad Taher
 
Rajasekaran CV-updated
Rajasekaran CV-updatedRajasekaran CV-updated
Rajasekaran CV-updatedRaja Sekhar
 

Similar to 50338447 checklist-concrete-works (20)

Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...
Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...
Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...
 
111.pdf
111.pdf111.pdf
111.pdf
 
LINGAM
LINGAMLINGAM
LINGAM
 
Lowerin Laying & Jointing of Pipelie.pptx
Lowerin Laying & Jointing of Pipelie.pptxLowerin Laying & Jointing of Pipelie.pptx
Lowerin Laying & Jointing of Pipelie.pptx
 
sapl-presentation
sapl-presentationsapl-presentation
sapl-presentation
 
BALAJI RESUME. UPDATED
BALAJI RESUME. UPDATEDBALAJI RESUME. UPDATED
BALAJI RESUME. UPDATED
 
Linsin CV
Linsin CVLinsin CV
Linsin CV
 
Aim condition assessment (2)
Aim condition assessment (2)Aim condition assessment (2)
Aim condition assessment (2)
 
Tendering Document for the Procurement of Works
Tendering Document for the Procurement of WorksTendering Document for the Procurement of Works
Tendering Document for the Procurement of Works
 
Die casting die design process
Die casting die design processDie casting die design process
Die casting die design process
 
Kumar.R Multi Inspector cv -5 - Copy
Kumar.R   Multi Inspector cv   -5 - CopyKumar.R   Multi Inspector cv   -5 - Copy
Kumar.R Multi Inspector cv -5 - Copy
 
Pipe fabricator cv venkata ratna kumar yarrapragada
Pipe fabricator cv venkata ratna kumar yarrapragadaPipe fabricator cv venkata ratna kumar yarrapragada
Pipe fabricator cv venkata ratna kumar yarrapragada
 
haitham abdelaal CV
haitham abdelaal CVhaitham abdelaal CV
haitham abdelaal CV
 
Nookaraju - CV
Nookaraju - CVNookaraju - CV
Nookaraju - CV
 
Structural & Piping QC Inspector CV - PDF
Structural & Piping QC Inspector CV - PDFStructural & Piping QC Inspector CV - PDF
Structural & Piping QC Inspector CV - PDF
 
Mohammad Taher_QA-QC Piping-Welding
Mohammad Taher_QA-QC Piping-WeldingMohammad Taher_QA-QC Piping-Welding
Mohammad Taher_QA-QC Piping-Welding
 
Kumar KV
Kumar KVKumar KV
Kumar KV
 
Trial mixing concrete .pdf
Trial mixing concrete .pdfTrial mixing concrete .pdf
Trial mixing concrete .pdf
 
Rajasekaran CV-updated
Rajasekaran CV-updatedRajasekaran CV-updated
Rajasekaran CV-updated
 
javed cv
javed cvjaved cv
javed cv
 

More from imaduddin91

07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagementimaduddin91
 
Remotesensingandgisapplications
RemotesensingandgisapplicationsRemotesensingandgisapplications
Remotesensingandgisapplicationsimaduddin91
 
R05410107 advancedfoundationengineering
R05410107 advancedfoundationengineeringR05410107 advancedfoundationengineering
R05410107 advancedfoundationengineeringimaduddin91
 
07 a80101 advanced structural design
07 a80101 advanced structural design07 a80101 advanced structural design
07 a80101 advanced structural designimaduddin91
 
07 a70401 remotesensingandgisapplications
07 a70401 remotesensingandgisapplications07 a70401 remotesensingandgisapplications
07 a70401 remotesensingandgisapplicationsimaduddin91
 
07 a70102 finite element methods in civil engineering
07 a70102 finite element methods in civil engineering07 a70102 finite element methods in civil engineering
07 a70102 finite element methods in civil engineeringimaduddin91
 
R05410103 remotesensingandgisapplications
R05410103 remotesensingandgisapplicationsR05410103 remotesensingandgisapplications
R05410103 remotesensingandgisapplicationsimaduddin91
 
R05410102 finiteelementmethodsincivilengineering
R05410102 finiteelementmethodsincivilengineeringR05410102 finiteelementmethodsincivilengineering
R05410102 finiteelementmethodsincivilengineeringimaduddin91
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcostingimaduddin91
 
07 a82101 advanced structural design
07 a82101  advanced structural design07 a82101  advanced structural design
07 a82101 advanced structural designimaduddin91
 
07 a80106 pavementanalysisanddesign
07 a80106 pavementanalysisanddesign07 a80106 pavementanalysisanddesign
07 a80106 pavementanalysisanddesignimaduddin91
 
07 a80104 watershedmanagement
07 a80104 watershedmanagement07 a80104 watershedmanagement
07 a80104 watershedmanagementimaduddin91
 
07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagementimaduddin91
 
07 a70110 remotesensingandgisapplications
07 a70110 remotesensingandgisapplications07 a70110 remotesensingandgisapplications
07 a70110 remotesensingandgisapplicationsimaduddin91
 
07 a70107 waterresourcessystemplanningandmanagement
07 a70107 waterresourcessystemplanningandmanagement07 a70107 waterresourcessystemplanningandmanagement
07 a70107 waterresourcessystemplanningandmanagementimaduddin91
 
07 a70102 finite element methods in civil engineering
07 a70102  finite element methods in civil engineering07 a70102  finite element methods in civil engineering
07 a70102 finite element methods in civil engineeringimaduddin91
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcostingimaduddin91
 
Statistical metods
Statistical metodsStatistical metods
Statistical metodsimaduddin91
 
Sas language reference concepts
Sas language reference  conceptsSas language reference  concepts
Sas language reference conceptsimaduddin91
 

More from imaduddin91 (20)

07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement
 
Remotesensingandgisapplications
RemotesensingandgisapplicationsRemotesensingandgisapplications
Remotesensingandgisapplications
 
R05410107 advancedfoundationengineering
R05410107 advancedfoundationengineeringR05410107 advancedfoundationengineering
R05410107 advancedfoundationengineering
 
07 a80101 advanced structural design
07 a80101 advanced structural design07 a80101 advanced structural design
07 a80101 advanced structural design
 
07 a70401 remotesensingandgisapplications
07 a70401 remotesensingandgisapplications07 a70401 remotesensingandgisapplications
07 a70401 remotesensingandgisapplications
 
07 a70102 finite element methods in civil engineering
07 a70102 finite element methods in civil engineering07 a70102 finite element methods in civil engineering
07 a70102 finite element methods in civil engineering
 
R05410103 remotesensingandgisapplications
R05410103 remotesensingandgisapplicationsR05410103 remotesensingandgisapplications
R05410103 remotesensingandgisapplications
 
R05410102 finiteelementmethodsincivilengineering
R05410102 finiteelementmethodsincivilengineeringR05410102 finiteelementmethodsincivilengineering
R05410102 finiteelementmethodsincivilengineering
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcosting
 
07 a82101 advanced structural design
07 a82101  advanced structural design07 a82101  advanced structural design
07 a82101 advanced structural design
 
07 a80106 pavementanalysisanddesign
07 a80106 pavementanalysisanddesign07 a80106 pavementanalysisanddesign
07 a80106 pavementanalysisanddesign
 
07 a80104 watershedmanagement
07 a80104 watershedmanagement07 a80104 watershedmanagement
07 a80104 watershedmanagement
 
07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement
 
07 a70110 remotesensingandgisapplications
07 a70110 remotesensingandgisapplications07 a70110 remotesensingandgisapplications
07 a70110 remotesensingandgisapplications
 
07 a70107 waterresourcessystemplanningandmanagement
07 a70107 waterresourcessystemplanningandmanagement07 a70107 waterresourcessystemplanningandmanagement
07 a70107 waterresourcessystemplanningandmanagement
 
07 a70102 finite element methods in civil engineering
07 a70102  finite element methods in civil engineering07 a70102  finite element methods in civil engineering
07 a70102 finite element methods in civil engineering
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcosting
 
Statistical metods
Statistical metodsStatistical metods
Statistical metods
 
Sas cheat
Sas cheatSas cheat
Sas cheat
 
Sas language reference concepts
Sas language reference  conceptsSas language reference  concepts
Sas language reference concepts
 

50338447 checklist-concrete-works

  • 1. CHECKLIST CONCRETE WORKS Checklist No. Name of Work: Pr. Start Date Employer: Pr. End Date Contract No.: Contractor: S.S.PROJECTS, VIZAG Item Dscrptn: Inspection Requested by: BOQ No. 1ST INSPECTION 2ND INSPECTION 3RD INSPECTIONMix Grade: Req. on: Req. on: Req. on: Location Section Level By.: By.: By.: Quantity Date: Date: Date: Time: Time: Time: Points to Check Action Req. Action Req. Action Req. REMARKS FORMWORK 1. Dimensions, level & Plumb 2. Tightness & Rigidity 3. Stop / Drop Formwork 4. Cleanliness 5. Shutter Release Agent REBAR 1. Bar Size & Nos., spacing & Laps 2. Bar Spacing & Laps 3. Cleanliness 4. Covers, Hooks & Binding Rigidity 5. Starter & Bonding Bars GENERAL 1. Anti Termite Treatment 2. Box Outs 3. Pipe Sleeves 4. Embedded Items 5. Quality of Bulk Materials / RMC 6. Plastisizers / Additives 7. Expansion Joint Provisions if any 8. Existing Concrete Hacking & Cleaning 9. Special treatments in existing surface ENDORSEMENTS Agency Name Sign with Date Main Contractor Electrical ACMV Fire Protection Plumbing Others[Specify]] Approved for Concreting Task Start Date: POSTCONCRETING Pour Start Date & Time: Concreting End Date & Time: No. of Cubes Taken: Average Slump: Method of Pouring & Vibration Acceptable To Improve Arrangement for Curing / Ponding Acceptable To Improve Stability of Formwork after Pour Acceptable To Improve Acceptable To Improve Line, Level & finishing Acceptable To Improve Acceptable To Improve DESHUTTER Sch. date for formwork removal with supports Actual Date of Removal Sch. date for form work removal entirely Actual Date of Removal Line, Level & finishing of Concrete surface Acceptable To Rectify Acceptable To Rectify Removal of Battens, Maskin tape etc. Acceptable To Rectify Acceptable To Rectify Action Required:- Remarks: Rectifications done as specified: Dry finish Wet finish Grouting Task End Date: Epoxy Treatment GLOBAL ENTROPOLIS VIZAG PVT LTD Checklist Date OP OP OP Details of Additional Steel Provided if any: [Other than specified in Drg.] Others [Specify]
  • 2. DE Note : Record typical dimensional check on reverse of this format Civil (SSP) Elec (GEVPL) Mech (GEVPL) GEVPL( CIVIL )