This document is a checklist for concrete works inspections at a construction site. It lists various items to check at different stages of construction including formwork, reinforcement, pouring, and finishing. The checklist includes points like dimensions, rigidity, rebar sizes and spacing, embedded items, and curing. Sign-offs are required from the main contractor and other subcontractors like electrical, HVAC, and plumbing at various stages before tasks can begin. Inspections will be conducted at multiple points like before pouring, after pouring, and after removal of formwork to ensure quality.
1. CHECKLIST
CONCRETE WORKS
Checklist No.
Name of Work: Pr. Start Date
Employer: Pr. End Date
Contract No.:
Contractor: S.S.PROJECTS, VIZAG
Item Dscrptn: Inspection Requested by: BOQ No.
1ST INSPECTION 2ND INSPECTION 3RD INSPECTIONMix Grade:
Req. on: Req. on: Req. on:
Location Section Level By.: By.: By.: Quantity
Date: Date: Date:
Time: Time: Time:
Points to Check Action Req. Action Req. Action Req. REMARKS
FORMWORK
1. Dimensions, level & Plumb
2. Tightness & Rigidity
3. Stop / Drop Formwork
4. Cleanliness
5. Shutter Release Agent
REBAR
1. Bar Size & Nos., spacing & Laps
2. Bar Spacing & Laps
3. Cleanliness
4. Covers, Hooks & Binding Rigidity
5. Starter & Bonding Bars
GENERAL
1. Anti Termite Treatment
2. Box Outs
3. Pipe Sleeves
4. Embedded Items
5. Quality of Bulk Materials / RMC
6. Plastisizers / Additives
7. Expansion Joint Provisions if any
8. Existing Concrete Hacking & Cleaning
9. Special treatments in existing surface
ENDORSEMENTS
Agency Name Sign with Date
Main Contractor
Electrical
ACMV
Fire Protection
Plumbing
Others[Specify]]
Approved for Concreting Task Start Date:
POSTCONCRETING
Pour Start Date & Time:
Concreting End Date & Time:
No. of Cubes Taken:
Average Slump:
Method of Pouring & Vibration Acceptable To Improve Arrangement for Curing / Ponding Acceptable To Improve
Stability of Formwork after Pour Acceptable To Improve Acceptable To Improve
Line, Level & finishing Acceptable To Improve Acceptable To Improve
DESHUTTER
Sch. date for formwork removal with supports Actual Date of Removal
Sch. date for form work removal entirely Actual Date of Removal
Line, Level & finishing of Concrete surface Acceptable To Rectify Acceptable To Rectify
Removal of Battens, Maskin tape etc. Acceptable To Rectify Acceptable To Rectify
Action Required:- Remarks: Rectifications done as specified:
Dry finish
Wet finish
Grouting Task End Date:
Epoxy Treatment
GLOBAL ENTROPOLIS
VIZAG PVT LTD
Checklist
Date
OP
OP
OP
Details of Additional Steel Provided if any: [Other than specified in Drg.]
Others [Specify]
2. DE
Note : Record typical dimensional check on reverse of this format
Civil (SSP) Elec (GEVPL) Mech (GEVPL) GEVPL( CIVIL )