SlideShare a Scribd company logo
1
Essam Harby
Program Planning &Projects Controls
Manager
Key Experience
26 Years of international experience having worked within consultancies, clients’ and contracting
organisations across various sectors, such as residential, hospitality, commercial, Education,
infrastructure. My career began from a Site Engineer to Projects Controls System Manager. Some of
the key skills and attributes are but not limited to the following:-
• Development of Projects Baseline Schedules, Analyze Resources Loading, Cash Flow, Project Budget,
Critical Milestone, Managing Budget Changes & Delay Analysis.
• Working Professionally on Primavera /P6 Version 16.2 - Cost Controls /TILOS for High Rise
& Infrastructure Projects - MS Project
• Project Management Support for Contracts Review, Cost Control, Change Management, Conduct
Extension of Time (E.O.T) Claims and Related Prolongation Costs Analysis Using the leading standards
(SCL Protocol - AACE 29R-03 Forensic Schedule Analysis)
• Complex Analysis of Impacts of Proposed Changes (V.O., Extension of Time, Etc.) on the Scope, Project
Schedules & Budgets.
• Review monthly progress Reports Including: Resources Productivity (Labour & Equipment), Schedule
Performance Index –SPI-, Cash Flow Analysis, and Cost Performance – CPI - and Earned Value Reports
• Comparing Progress VS Planning Identify Bottlenecks & Delays as Well as Potential Time Saving.
• Risk Evaluation (Qualitative Risk Analysis & Quantitative Risk Analysis).
• Liaising with the Internal & External Stakeholders to Address and Resolve the Potential Issues.
• Follow Contracts issues, Material Status, Shop Drawing Logs & Monitor H.S.E Statistical Data.
Profession
Planning &Projects Controls
Position
Program Planning &Projects Controls Manager
Nationality
Egyptian
Date of Birth
 20/10/1967
QUALIFICATIONS
 Civil Engineering Degree (Ain Shams University 1990).
 Advanced Primavera P6 - Promastar at K.S.A - MS Project Professional.
 Oracle Primavera Contract Manager (PCM)
 MC Prime Consulting -Delay Analysis
 Construction Claims - LEGAL Edition
 FIDIC Contract Administration
 Time-Location planning and Linear Scheduling (TILOS) for High Rise & Infra Structure.
2
 RIB (Cost Control) & JD EEnterprise 9.1.
Memberships
 PMI Membership 4355471
Areas of Expertise
 Program Management
 Primavera -P6 release 16.2
 Cost Control
 Extension of Time (E.O.T) Claims and Related Costs Analysis
Sector Experience
Hospitality
 Doho Heritage Quarter Renewal Projects (Heritage hotels)
o Overall project value SAR 440m
o Duration on Project – July 2012 – April 2014
 Marriott Diplomat Makarem Hotel
o Overall project value - SAR 220m
o Duration on Project – July 2007 – May2010
 Aida Beach Hotel (Northern Coast - Egypt)
o Overall project value L.E. 350m
o Duration on Project – Dec. 1990 – April 1993
Residential
 Doho Heritage Quarter Renewal Projects (multiple residential buildings)
o Overall project value SAR 440m
o Duration on Project – July 2012 – April 2014
 Al Qasr Palace Project
o Overall project value SAR 840m
o Duration on Project – July 2007 – April 2011
 Abha Airport Residential Accommodation (KSA)
o Overall project value SAR 1.8B
o Duration on Project – Dec 2014 – Present
 Aida Tourist / Residential Village (Northern Coast - Egypt)
o Overall project value L.E. 155m
o Duration on Project – May 1993 - Jan1996
Retail
 Al Qasr Palace Project
o Overall project value SAR 840m
o Duration on Project – July 2008 – April 2011
 Akaria Plaza (Retail& Residential).
o Duration on Project – July 2007 – April 2010
o Overall project value SAR 520 Million.
Infrastructure
 Abha Airport Project (KSA)
o Overall project value SAR 1.8B
o Duration on Project – Dec 2014 – Present
 Al Ehsaa Infrastructure Project
3
o Overall project value - Confidential
o Duration on Project – May 2014 - Present
Healthcare
 Shemessy Hospital Complex (Riyadh)
o Overall project value SAR 580m
o Duration on Project – July 2007 – Sep. 2010
 King Faisal University Hospital - Almubarak Consultant)(Dammam)
o Overall project value SAR 650m
o Duration on Project – Jan 2005 – June 2007
Professional History
Year Position Company Country
May 2014 – up to now Planning & Projects
Controls Manager
Al Jaber Transport & General
Contracting Co. KSA
Jul 2007 - Apr 2014 Planning Manager Saudi Lebanese Modern Cons.
Co.
KSA
Jan. 2005 - Jun 2007 Senior Planning
Engineer
King Faisal University
(Almubarak Consultant)
KSA
May 1998 - Apr 2014 Planning Engineer Civil Aviation Authority Egypt
Feb 1996 - Apr1998 Planning Engineer ElJaber Consultant Egypt
May 1993 - Jan1996 Site Engineer Golden Eagle Co. Egypt
Dec 1990 - Apr1993 Site Engineer ElJezera Investment Company Egypt
Project summary
May 2014 up to date Al Jabber Transport & General Contracting Co., Planning & Projects
Controls Manager, KSA
Projects: Abha Airport Development Project : PTB Steel Structure of total
Area 86,000 Square meter ,11 Ancillary Concrete Buildings for Family
Accommodation, Bachelor Accommodation, Stores , Maintenance Buildings ,
Administration Building , 2 Parking Areas ,Taxiway , electrical Transformer
Stations , A.C. Chillers Building ,Infrastructure (Cost S.R. 1.8 Billion).
Key Responsibilities:
 Controlling & Development The Projects in Coordination With the Stakeholders
& Reporting Data Of The Program Controls : -
 Ensure The Availability Of Necessary Project Control System Resources
(Personnel, Procedures and Software Tools Specially Contract Manager (PCM)
4
& Primavera Systems (P6) to Plan and Execute Work.
 Review Financial and Cost Reporting Forms, Development and Specific
Formats For Design and Construction Monitoring Purposes.
 Impacts of Project Schedules and Budgets, Including Financial and Cash Flow
Analysis.
 Development Of The Master and Baseline Schedule, Project Budget in
Coordination With Assigned Project Manager and in Particular The
Development Of Critical Milestone.
 Review Global Planning Drafts For Projects.
 Review Progress Reports Of Each Project Submitted By The Site Planners.
 Provide Support in Reconciliation Of Impacts Of Proposed Changes Of Scope,
Schedule and Cost.
 Provide Project Management Recommendation On Factors Affecting The Timely
Completion Of Projects.
 Review Special Analysis for Resource Loading and Performance Progress.
Jul 2007 – Apr 2014 Saudi Lebanese Modern Construction Co. (SALMOC), Planning &
Projects Control Manager
Projects:
 Al Qasr Palace Project - Consists of Commercial Mall (Retail) & Residential
Buildings Packages, (Project Cost S.R. 840 Million) .
 Doho Heritage Quarter Renewal Projects (Residential, hospitality, retail &
leisure) Stage 01, Stage 02. ((Project Cost S.R. 440 Million))
 Shemessy Hospital Complex, Riyadh, - (Project Cost S.R. 580 Million).
 Marriot Hotel Redevelopment (Riyadh) - Overall project value - SAR 220m
 Criminal Court project (Project cost S.R. 420 Million) Consists of Main
Building For Courts, Underground Car Park , Mixed Use Building ,External
Work and North Plaza.
 National Guard Project (Project Cost S.R. 480 Million) Consists of 310
Concrete & Steel Buildings.
Key Responsibilities:
Controlling & Developing the Project Sites in Coordination with Assigned
Project Managers & reporting Data of the Project Control System (PCS).
1- Establishing PCS:
 Ensure The Availability Of Necessary Project Control System Resources
(Personnel, Procedures and Software Tools Specially Contract Manager
(Primavera Expedition) & Primavera Enterprise (P6).
 Development, Review, Upgrade and Implementation of the Projects Control
System (PCS), Integration With The Administrative & Operational Procedures.
 Discuss Suggestions, Improve Existing Methods, Systems and Procedures.
 Review The Development, Upgrade Of Projects Information and The
Graphical Presentation Materials.
2- Managing PCS :
 Development Of The Master and Baseline Schedule, Cash Flow Schedules
and Project Budget in Coordination With Assigned Project Manager and in
Particular The Development Of Critical Milestone.
 Review Global Planning Drafts For Projects and Analyze Logical Breakdown.
 Review Financial and Cost Reporting Data ,Forms, Development and Specific
Formats For Design and Construction Monitoring Purposes Including Planned
Versus Actual Projections and Indicated Outcome Reports
 Review The Monthly Narrative, Cost, Schedule and Financial Reports,
Submitted By The Site Planners.
 Manage Document control department using PMCS software &Review
Regular Progress Reports of each Project Submitted by the Site Planners.
5
Project summary (Continued)
Continuation: Saudi Lebanese Modern Construction Co. (SALMOC),
Planning & Projects Control Manager
Projects:
 Complex Analysis to Monitor The Impacts On The Project Schedules and
Budgets, Including Financial and Cash Flow Analysis.
 Provide Support in Reconciliation Of Impacts Of Proposed Changes Of
Scope, Schedule and Cost.
 Comparing Progress Data Done By Site Planners Against Planning, Identify
Planning Bottlenecks and Delays as Well as Potential Time-Saving
Measures.
 Monitor Detailed Schedules, Analyze Man Power and Advice On Timing Of
Requisitions, Ensure Interfaces With Internal and External Parties to
Address and Resolve Potential Issues.
Review Special Analysis For Resource Loading and Performance Progress.
 Develops and Maintains Status Reports Including: Labor Productivity,
Schedule Status, Financial Analysis, Cost Performance Reports and Earned
Value Curves Reports.
 Provide Management Recommendation on Factors Affecting The Timely
Completion of Projects.
 Liaising With Client and Projects Managers.
Jan 2005 – Jun 2007
King Faisal University (Almubarak Consultant), Senior
Planning/Project Controls Engineer, KSA
Projects:
KFU Complex Project of Overall Value SAR 650m Including :
 KFU Teaching Hospital Project (Project cost S.R.304 Million).
 Medicine College (Project cost S.R.35 Million).
 Dentistry College (Project cost S.R. 30 Million).
 Administration Building & Mosque (Project cost S.R.70 Million).
 Construction Of Infrastructures For The University ( Roads, Curbstone,
Pipe Lines & Construction Of Utility Building (Hinged Frame With 25 M
Span, Mechanical Rooms, Control Rooms, R.O. Plant Underground
Tanks.
May 1998 – Nov 2004 Civil Aviation Authority, Planning Engineer, Egypt
Projects:
 Holding Aviation Company Complex including the Administrative
Buildings (Project Cost L.E.650 Million).
 Infrastructure For all Airports all Over Egypt.
 Development of Roads, Bridges & Runways For all Airports all Over
Egypt.
Feb 1996 – Apr 1998 Eljaber Consultant Co., Planning Engineer, Egypt
Projects:
 Monitor Detailed Time Schedule for Cairo Rail Project.
 Computer College (Project Cost L.E.150 Million).
 Three Residential Housing (Project Cost L.E.120 Million).
6
May 1993 – Jan 1996 Golden Eagle Co., Site Engineer, Egypt
Projects:
 Egyptian Gulf Bank (Project Cost L.E. 125 Million).
 Touristic Resort @ Hurghada (Cost L.E. 110 Million).
Project summary (Continued)
Dec 1990 – Apr 1993 El Jezera Investment Co., Site Engineer, Egypt
Projects:
 Aida Hotel in Northern Coast ( Cost L.E. 350 Million)
 25 Residential Housing (Project Cost L.E. 155 million)
 Ware Houses in Cairo Airport (Cost L.E. 40 Million)

More Related Content

What's hot

What's hot (19)

Resume f sanchez Project Manager Oct 2016.pdf
Resume f sanchez Project Manager Oct 2016.pdfResume f sanchez Project Manager Oct 2016.pdf
Resume f sanchez Project Manager Oct 2016.pdf
 
Shahzad Sikandaruk
Shahzad SikandarukShahzad Sikandaruk
Shahzad Sikandaruk
 
Peter White CV - Latest
Peter White CV - LatestPeter White CV - Latest
Peter White CV - Latest
 
Snr. Planning Engineer -WP- Kemya Sabic
Snr. Planning Engineer -WP- Kemya SabicSnr. Planning Engineer -WP- Kemya Sabic
Snr. Planning Engineer -WP- Kemya Sabic
 
engineer_Mohamed_Gamal Projects' control_CV-016
engineer_Mohamed_Gamal Projects' control_CV-016engineer_Mohamed_Gamal Projects' control_CV-016
engineer_Mohamed_Gamal Projects' control_CV-016
 
CV
CVCV
CV
 
A2) CV - July 2016 incl. EXXON & NES-BHP
A2) CV - July 2016 incl. EXXON & NES-BHP A2) CV - July 2016 incl. EXXON & NES-BHP
A2) CV - July 2016 incl. EXXON & NES-BHP
 
EPC Contract - M. Khalid Quantity Surveyor 2015
EPC Contract - M. Khalid Quantity Surveyor 2015EPC Contract - M. Khalid Quantity Surveyor 2015
EPC Contract - M. Khalid Quantity Surveyor 2015
 
Cv s.sankarasubramanian - senior planning engineer
Cv   s.sankarasubramanian - senior planning engineerCv   s.sankarasubramanian - senior planning engineer
Cv s.sankarasubramanian - senior planning engineer
 
ZAKI Michael_CV 042014
ZAKI Michael_CV 042014ZAKI Michael_CV 042014
ZAKI Michael_CV 042014
 
Peter White CV
Peter White CV Peter White CV
Peter White CV
 
Resume - Nermeen Atef sam
Resume - Nermeen Atef samResume - Nermeen Atef sam
Resume - Nermeen Atef sam
 
AMIR' s CV
AMIR' s CVAMIR' s CV
AMIR' s CV
 
Rao Yagitila CV
Rao Yagitila CVRao Yagitila CV
Rao Yagitila CV
 
inayat ur rahman cv 1
inayat ur rahman cv 1inayat ur rahman cv 1
inayat ur rahman cv 1
 
CV mohamed
CV mohamedCV mohamed
CV mohamed
 
Amr. 2015....
Amr. 2015....Amr. 2015....
Amr. 2015....
 
Mesbah_Elazrig_Sr Drilling Eng
Mesbah_Elazrig_Sr Drilling EngMesbah_Elazrig_Sr Drilling Eng
Mesbah_Elazrig_Sr Drilling Eng
 
Curriculum Vitea Neil Herbst
Curriculum Vitea Neil HerbstCurriculum Vitea Neil Herbst
Curriculum Vitea Neil Herbst
 

Similar to 2017 Updated CV - Essam Harby

Similar to 2017 Updated CV - Essam Harby (20)

CV- Faraz Yasin, Planning Engineer 28-Nov-2016
CV- Faraz Yasin,  Planning Engineer 28-Nov-2016CV- Faraz Yasin,  Planning Engineer 28-Nov-2016
CV- Faraz Yasin, Planning Engineer 28-Nov-2016
 
C.V - Hosam A. Eid Mohammed kandeel
C.V - Hosam A. Eid Mohammed kandeelC.V - Hosam A. Eid Mohammed kandeel
C.V - Hosam A. Eid Mohammed kandeel
 
Peter Khalil CV
Peter Khalil CVPeter Khalil CV
Peter Khalil CV
 
Jordan Wallins Resume Sep 16
Jordan Wallins Resume Sep 16Jordan Wallins Resume Sep 16
Jordan Wallins Resume Sep 16
 
CV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerCV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning Engineer
 
BMH - Detail Resume - August 2016
BMH - Detail Resume - August  2016BMH - Detail Resume - August  2016
BMH - Detail Resume - August 2016
 
Mervyn_Stephens CV
Mervyn_Stephens CVMervyn_Stephens CV
Mervyn_Stephens CV
 
CV 15-08-16 M.K.Narayana _ Seaport Technology & Engineering -
CV 15-08-16 M.K.Narayana _ Seaport Technology & Engineering -CV 15-08-16 M.K.Narayana _ Seaport Technology & Engineering -
CV 15-08-16 M.K.Narayana _ Seaport Technology & Engineering -
 
RESUME
RESUMERESUME
RESUME
 
Project controls function
Project controls functionProject controls function
Project controls function
 
Ehab Radwan
Ehab RadwanEhab Radwan
Ehab Radwan
 
Cv - Anil
Cv - AnilCv - Anil
Cv - Anil
 
C.V Mr. Rabih Makhoul
C.V Mr. Rabih MakhoulC.V Mr. Rabih Makhoul
C.V Mr. Rabih Makhoul
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&t
 
Tarek Hassanain Eladawi - Final
Tarek Hassanain Eladawi - FinalTarek Hassanain Eladawi - Final
Tarek Hassanain Eladawi - Final
 
CV_KAD_PMP+BDM
CV_KAD_PMP+BDMCV_KAD_PMP+BDM
CV_KAD_PMP+BDM
 
Jamal Oklah CV
Jamal Oklah CVJamal Oklah CV
Jamal Oklah CV
 
TDCCV 2016
TDCCV 2016TDCCV 2016
TDCCV 2016
 
CV _Rajasekhar- Project Management
CV _Rajasekhar- Project ManagementCV _Rajasekhar- Project Management
CV _Rajasekhar- Project Management
 
Roshanak Jalili CV
Roshanak Jalili CVRoshanak Jalili CV
Roshanak Jalili CV
 

2017 Updated CV - Essam Harby

  • 1. 1 Essam Harby Program Planning &Projects Controls Manager Key Experience 26 Years of international experience having worked within consultancies, clients’ and contracting organisations across various sectors, such as residential, hospitality, commercial, Education, infrastructure. My career began from a Site Engineer to Projects Controls System Manager. Some of the key skills and attributes are but not limited to the following:- • Development of Projects Baseline Schedules, Analyze Resources Loading, Cash Flow, Project Budget, Critical Milestone, Managing Budget Changes & Delay Analysis. • Working Professionally on Primavera /P6 Version 16.2 - Cost Controls /TILOS for High Rise & Infrastructure Projects - MS Project • Project Management Support for Contracts Review, Cost Control, Change Management, Conduct Extension of Time (E.O.T) Claims and Related Prolongation Costs Analysis Using the leading standards (SCL Protocol - AACE 29R-03 Forensic Schedule Analysis) • Complex Analysis of Impacts of Proposed Changes (V.O., Extension of Time, Etc.) on the Scope, Project Schedules & Budgets. • Review monthly progress Reports Including: Resources Productivity (Labour & Equipment), Schedule Performance Index –SPI-, Cash Flow Analysis, and Cost Performance – CPI - and Earned Value Reports • Comparing Progress VS Planning Identify Bottlenecks & Delays as Well as Potential Time Saving. • Risk Evaluation (Qualitative Risk Analysis & Quantitative Risk Analysis). • Liaising with the Internal & External Stakeholders to Address and Resolve the Potential Issues. • Follow Contracts issues, Material Status, Shop Drawing Logs & Monitor H.S.E Statistical Data. Profession Planning &Projects Controls Position Program Planning &Projects Controls Manager Nationality Egyptian Date of Birth  20/10/1967 QUALIFICATIONS  Civil Engineering Degree (Ain Shams University 1990).  Advanced Primavera P6 - Promastar at K.S.A - MS Project Professional.  Oracle Primavera Contract Manager (PCM)  MC Prime Consulting -Delay Analysis  Construction Claims - LEGAL Edition  FIDIC Contract Administration  Time-Location planning and Linear Scheduling (TILOS) for High Rise & Infra Structure.
  • 2. 2  RIB (Cost Control) & JD EEnterprise 9.1. Memberships  PMI Membership 4355471 Areas of Expertise  Program Management  Primavera -P6 release 16.2  Cost Control  Extension of Time (E.O.T) Claims and Related Costs Analysis Sector Experience Hospitality  Doho Heritage Quarter Renewal Projects (Heritage hotels) o Overall project value SAR 440m o Duration on Project – July 2012 – April 2014  Marriott Diplomat Makarem Hotel o Overall project value - SAR 220m o Duration on Project – July 2007 – May2010  Aida Beach Hotel (Northern Coast - Egypt) o Overall project value L.E. 350m o Duration on Project – Dec. 1990 – April 1993 Residential  Doho Heritage Quarter Renewal Projects (multiple residential buildings) o Overall project value SAR 440m o Duration on Project – July 2012 – April 2014  Al Qasr Palace Project o Overall project value SAR 840m o Duration on Project – July 2007 – April 2011  Abha Airport Residential Accommodation (KSA) o Overall project value SAR 1.8B o Duration on Project – Dec 2014 – Present  Aida Tourist / Residential Village (Northern Coast - Egypt) o Overall project value L.E. 155m o Duration on Project – May 1993 - Jan1996 Retail  Al Qasr Palace Project o Overall project value SAR 840m o Duration on Project – July 2008 – April 2011  Akaria Plaza (Retail& Residential). o Duration on Project – July 2007 – April 2010 o Overall project value SAR 520 Million. Infrastructure  Abha Airport Project (KSA) o Overall project value SAR 1.8B o Duration on Project – Dec 2014 – Present  Al Ehsaa Infrastructure Project
  • 3. 3 o Overall project value - Confidential o Duration on Project – May 2014 - Present Healthcare  Shemessy Hospital Complex (Riyadh) o Overall project value SAR 580m o Duration on Project – July 2007 – Sep. 2010  King Faisal University Hospital - Almubarak Consultant)(Dammam) o Overall project value SAR 650m o Duration on Project – Jan 2005 – June 2007 Professional History Year Position Company Country May 2014 – up to now Planning & Projects Controls Manager Al Jaber Transport & General Contracting Co. KSA Jul 2007 - Apr 2014 Planning Manager Saudi Lebanese Modern Cons. Co. KSA Jan. 2005 - Jun 2007 Senior Planning Engineer King Faisal University (Almubarak Consultant) KSA May 1998 - Apr 2014 Planning Engineer Civil Aviation Authority Egypt Feb 1996 - Apr1998 Planning Engineer ElJaber Consultant Egypt May 1993 - Jan1996 Site Engineer Golden Eagle Co. Egypt Dec 1990 - Apr1993 Site Engineer ElJezera Investment Company Egypt Project summary May 2014 up to date Al Jabber Transport & General Contracting Co., Planning & Projects Controls Manager, KSA Projects: Abha Airport Development Project : PTB Steel Structure of total Area 86,000 Square meter ,11 Ancillary Concrete Buildings for Family Accommodation, Bachelor Accommodation, Stores , Maintenance Buildings , Administration Building , 2 Parking Areas ,Taxiway , electrical Transformer Stations , A.C. Chillers Building ,Infrastructure (Cost S.R. 1.8 Billion). Key Responsibilities:  Controlling & Development The Projects in Coordination With the Stakeholders & Reporting Data Of The Program Controls : -  Ensure The Availability Of Necessary Project Control System Resources (Personnel, Procedures and Software Tools Specially Contract Manager (PCM)
  • 4. 4 & Primavera Systems (P6) to Plan and Execute Work.  Review Financial and Cost Reporting Forms, Development and Specific Formats For Design and Construction Monitoring Purposes.  Impacts of Project Schedules and Budgets, Including Financial and Cash Flow Analysis.  Development Of The Master and Baseline Schedule, Project Budget in Coordination With Assigned Project Manager and in Particular The Development Of Critical Milestone.  Review Global Planning Drafts For Projects.  Review Progress Reports Of Each Project Submitted By The Site Planners.  Provide Support in Reconciliation Of Impacts Of Proposed Changes Of Scope, Schedule and Cost.  Provide Project Management Recommendation On Factors Affecting The Timely Completion Of Projects.  Review Special Analysis for Resource Loading and Performance Progress. Jul 2007 – Apr 2014 Saudi Lebanese Modern Construction Co. (SALMOC), Planning & Projects Control Manager Projects:  Al Qasr Palace Project - Consists of Commercial Mall (Retail) & Residential Buildings Packages, (Project Cost S.R. 840 Million) .  Doho Heritage Quarter Renewal Projects (Residential, hospitality, retail & leisure) Stage 01, Stage 02. ((Project Cost S.R. 440 Million))  Shemessy Hospital Complex, Riyadh, - (Project Cost S.R. 580 Million).  Marriot Hotel Redevelopment (Riyadh) - Overall project value - SAR 220m  Criminal Court project (Project cost S.R. 420 Million) Consists of Main Building For Courts, Underground Car Park , Mixed Use Building ,External Work and North Plaza.  National Guard Project (Project Cost S.R. 480 Million) Consists of 310 Concrete & Steel Buildings. Key Responsibilities: Controlling & Developing the Project Sites in Coordination with Assigned Project Managers & reporting Data of the Project Control System (PCS). 1- Establishing PCS:  Ensure The Availability Of Necessary Project Control System Resources (Personnel, Procedures and Software Tools Specially Contract Manager (Primavera Expedition) & Primavera Enterprise (P6).  Development, Review, Upgrade and Implementation of the Projects Control System (PCS), Integration With The Administrative & Operational Procedures.  Discuss Suggestions, Improve Existing Methods, Systems and Procedures.  Review The Development, Upgrade Of Projects Information and The Graphical Presentation Materials. 2- Managing PCS :  Development Of The Master and Baseline Schedule, Cash Flow Schedules and Project Budget in Coordination With Assigned Project Manager and in Particular The Development Of Critical Milestone.  Review Global Planning Drafts For Projects and Analyze Logical Breakdown.  Review Financial and Cost Reporting Data ,Forms, Development and Specific Formats For Design and Construction Monitoring Purposes Including Planned Versus Actual Projections and Indicated Outcome Reports  Review The Monthly Narrative, Cost, Schedule and Financial Reports, Submitted By The Site Planners.  Manage Document control department using PMCS software &Review Regular Progress Reports of each Project Submitted by the Site Planners.
  • 5. 5 Project summary (Continued) Continuation: Saudi Lebanese Modern Construction Co. (SALMOC), Planning & Projects Control Manager Projects:  Complex Analysis to Monitor The Impacts On The Project Schedules and Budgets, Including Financial and Cash Flow Analysis.  Provide Support in Reconciliation Of Impacts Of Proposed Changes Of Scope, Schedule and Cost.  Comparing Progress Data Done By Site Planners Against Planning, Identify Planning Bottlenecks and Delays as Well as Potential Time-Saving Measures.  Monitor Detailed Schedules, Analyze Man Power and Advice On Timing Of Requisitions, Ensure Interfaces With Internal and External Parties to Address and Resolve Potential Issues. Review Special Analysis For Resource Loading and Performance Progress.  Develops and Maintains Status Reports Including: Labor Productivity, Schedule Status, Financial Analysis, Cost Performance Reports and Earned Value Curves Reports.  Provide Management Recommendation on Factors Affecting The Timely Completion of Projects.  Liaising With Client and Projects Managers. Jan 2005 – Jun 2007 King Faisal University (Almubarak Consultant), Senior Planning/Project Controls Engineer, KSA Projects: KFU Complex Project of Overall Value SAR 650m Including :  KFU Teaching Hospital Project (Project cost S.R.304 Million).  Medicine College (Project cost S.R.35 Million).  Dentistry College (Project cost S.R. 30 Million).  Administration Building & Mosque (Project cost S.R.70 Million).  Construction Of Infrastructures For The University ( Roads, Curbstone, Pipe Lines & Construction Of Utility Building (Hinged Frame With 25 M Span, Mechanical Rooms, Control Rooms, R.O. Plant Underground Tanks. May 1998 – Nov 2004 Civil Aviation Authority, Planning Engineer, Egypt Projects:  Holding Aviation Company Complex including the Administrative Buildings (Project Cost L.E.650 Million).  Infrastructure For all Airports all Over Egypt.  Development of Roads, Bridges & Runways For all Airports all Over Egypt. Feb 1996 – Apr 1998 Eljaber Consultant Co., Planning Engineer, Egypt Projects:  Monitor Detailed Time Schedule for Cairo Rail Project.  Computer College (Project Cost L.E.150 Million).  Three Residential Housing (Project Cost L.E.120 Million).
  • 6. 6 May 1993 – Jan 1996 Golden Eagle Co., Site Engineer, Egypt Projects:  Egyptian Gulf Bank (Project Cost L.E. 125 Million).  Touristic Resort @ Hurghada (Cost L.E. 110 Million). Project summary (Continued) Dec 1990 – Apr 1993 El Jezera Investment Co., Site Engineer, Egypt Projects:  Aida Hotel in Northern Coast ( Cost L.E. 350 Million)  25 Residential Housing (Project Cost L.E. 155 million)  Ware Houses in Cairo Airport (Cost L.E. 40 Million)