1. RESUME
Personal Details
Name: ANDREI SANNIKOV
E-mail: as27.ca@gmail.com
Date of birth: December 25, 1961
Place of
residence:
Richmond Hill, Ontario, Canada
Discipline: Planning Specialist (Project Controls)
Citizenship: CANADIAN & RUSSIAN (dual citizenship)
Computer skills Primavera (P3 and P6), PertMaster, Primavera Risk Analysis, Microsoft Office 2007 (Excel,
Access, Word, Power Point), Visio, Milestones Professional, Microsoft Project, SureTrak
Language skills English, French, German, Russian (all fluent); Italian & Spanish (good working knowledge)
Work
Experience
Project
overview:
North West Redwater Partnership. A bitumen refinery in Redwater Alberta, Canada, designed
from the ground up to incorporate gasification and a carbon capture and storage solution.
Apr 15 - current Fluor Canada (through TRS Staffing Solutions)
Lead planner
• Supervise planning and progress reporting activities for Fluor scope of the project.
• Schedule risk analysis.
• Interfacing with contractors and subcontractors.
• Integration of contractors schedules into overall master schedule.
• Work with contractors to assist them in development of construction and turnover
schedules and progress reporting systems.
• Produce schedule and progress reports for the Client.
• Audit progress figures reported by field contractors.
• Produce time-impact analyzes on as-needed basis to support Company’s position in
extension of time/delay claim defense.
Project
overview:
Kearl oil sands mining project with 4.6 billion barrels of bitumen resource and planned
production of approximately 110,000-barrel-per-day at the initial stage.
Owners: Imperial Oil Resources and ExxonMobil Canada Ltd.
May 14 – Mar 15 Fluor Canada (through TRS Staffing Solutions)
Lead planner (Ore Preparation Plant #2) on Kearl Oil Sands Expansion Project, Ft.
McMurray, Alberta, Canada
Responsibilities:
• Supervise planning and progress reporting activities.
• Support completions and turnover activities.
• Work with contractors to assist them in development of construction and turnover
schedules and progress reporting systems.
• Produce schedule and progress reports for the Client.
• Audit progress figures reported by field contractors.
• Produce time-impact analyzes on as-needed basis to support Company’s position in
extension of time/delay claim defense.
Feb 13 – May 14 Fluor Canada (through TRS Staffing Solutions)
Lead planner (Bitumen Area) on Kearl Oil Sands Expansion Project, Ft. McMurray, Alberta,
Canada
Page 1 of 7
Andrei Sannikov’s CV
Last updated on 16-Jul-15
2. July 12 – Jan 13 Fluor Canada (through TRS Staffing Solutions)
Lead planner (Infrastructure scope) on Kearl Oil Sands Initial Development Project, Ft.
McMurray, Alberta, Canada
Responsibilities:
• Supervise planning and progress reporting activities in the infrastructure area of the
project.
• Support completions and turnover activities.
• Work with contractors to assist them in development of construction and turnover
schedules and progress reporting systems.
• Produce schedule and progress reports for the Client.
• Audit progress figures reported by field contractors.
• Produce time-impact analyzes on as-needed basis to support Company’s position in
extension of time/delay claim defense.
July 10 – June 12 Fluor Canada (through TRS Staffing Solutions)
Area planner on Kearl Oil Sands Initial Development Project, Ft. McMurray, Alberta, Canada
Responsibilities:
• Create and maintain Level 3 schedules covering engineering, procurement and
construction phases of Hydrotransport and Tailings area.
• Ensure accurate and consistent progress and planning reporting.
• Analyze various engineering, progress and permitting data to determine potential impact of
various events on the critical path/Project Completion dates.
• Maintain an independent (realistic) schedule based on input from different sources as well
as own observations to analyze critical paths and forecast Project completion dates.
• Produce Critical Path/Float/Resource Analyses of contractors’ work, identify the most
critical resources and areas and make appropriate recommendations to contractors and
project area management.
• Identify schedule risks and Maintain Project risk model in a Monte-Carlo type package.
• Produce time-impact analyzes on as-needed basis to support Company’s position in
extension of time/delay claim defense.
Project
overview:
Shtokman Gas Field Development is an Offshore gas drilling and production project (Floating
production unit) in the Barents Sea including Offshore trunk pipelines, Onshore receiving
facilities and LNG plant (7.5Mty).
Owners: Gasprom, Total, Statoil
Dec 08 – July 10 Shtokman Development AG (through Swift Oil and Gas UK)
Lead Planner of Shtokman Gas Field Development Project (Phase 1), Moscow, Russia
Responsibilities:
• Develop and maintain integrated schedules for Engineering, Construction, Commissioning
and Startup Phases of the Project.
• Identify conflicts between various schedule elements and advise management of their
potential impact.
• Produce critical path/float analysis for the project management.
• Produce overall schedule overviews for the project management.
• Identify schedule related risks and model their impact in the Project risk model.
• Develop and maintain Project progress base.
• Produce and implement all necessary planning and progress reporting procedures and
rules.
Since April 2010
Additional role of Risk Management Advisor for the Shtokman project
Responsibilities:
• Develop, update and implement the Project Risk Management Plan at the Project level
• Ensure that project members are trained to an appropriate level in the discipline of Project
Page 2 of 7
Andrei Sannikov’s CV
Last updated on 16-Jul-15
3. Risk Management
• Facilitate the inclusion of appropriate Project Risk Management requirements in all major
contracts (and ITTs), especially EPC lump sum contracts, to ensure risks and
opportunities are transparently, consistently and regularly reported between the Company
and Contractors.
• Organize and chair the Risk and Opportunity Coordination Meetings
• Facilitate identification and assessment of the Project level risks and opportunities through
group ‘brainstorming’ and individual interview sessions
• Create and maintain the Project Risk Register for Project level risks and opportunities
• Ensure the assignment of Risk Owners of the risk and opportunities within the Project Risk
Register and support them for the definition, implementation and follow-up of mitigation
actions
• Coordinate risk coordination and were necessary, transfer, of risks between the Onshore
and Offshore projects and the support functional departments as required
• Provide updates of the Project Risk Register to the Risk, Development & Planning
Manager.
• Provide schedule and cost QRA risk models to evaluate combined influences of
uncertainties (and the resultant risks and opportunities) on project time and cost
performance prospects
• Conduct sensitivity and scenario/decision-testing analyses as requested
• Provide a Risk Report to the Risk, Development & Planning Manager or SMT Risk
Management Committee prior to each meeting, as required.
Project
overview:
Engineering, procurement, construction and commissioning of Sakhalin-II Onshore pipeline
systems including 1568 km of pipelines (4.5” to 48”) in 781 km RoW; 180 actuated valves (4.5”
to 48”), 104 block valve stations; pipeline crossed 126 km of wetlands, 100 km of mountain
areas, 19 seismic faults, 40 km of landslide areas, 1086 watercourses, 158 environmentally
sensitive rivers.
Owners: Gasprom, Shell, Mitsubishi, Mitsui
Feb 07 – Nov 08 Sakhalin Energy Investment Company (through Orion Engineering Services Ltd.)
Lead Planner of Integrated Project Team for Sakhalin-II Onshore Pipeline construction (PDP),
Sakhalin Island, Russia
Responsibilities:
• Develop work completion schedules for each of the six pipeline construction spreads jointly
with the pipeline (sub)contractors.
• Setup progress base files and critical path/float/resource analyses tools for each spread
and the overall pipeline construction project.
• Assist field-based personnel in generation of weekly schedule updates, critical path/float
analyses for weekly construction meetings on site.
• Produce overall critical path in Primavera and trend analyses as well as progress reports
for the Project Management.
• Generate overall project network in Primavera based on sub-project schedules maintained
in the field.
• Supervise field-based planning engineers and visit each construction site on a regular
basis.
Mar 06 – Jan 07 Sakhalin Energy Investment Company (through Orion Engineering Services Ltd.)
Lead Construction Planner for Sakhalin-II Onshore Pipeline construction management team
(PDP), Sakhalin Island, Russia
Responsibilities:
• Supervise work of field and office based planning engineers to ensure accurate and
consistent progress and planning reporting.
• Analyze various engineering, progress and permitting data to determine potential impact of
various events on the critical path/Project Completion dates.
• Maintain an independent (realistic) schedule based on input from different sources as well
as own observations to analyze critical paths and forecast Project completion dates.
• Produce Critical Path/Float/Resource Analyses of contractors’ work, identify the most
critical resources and areas and make appropriate recommendations to contractors and
PDP management.
Page 3 of 7
Andrei Sannikov’s CV
Last updated on 16-Jul-15
4. • Identify schedule risks and Maintain Project risk model in a Monte-Carlo type package.
• Undertake Cost Phasing exercises to align with the current schedule.
• Work with PDP construction contractor (sub-contractors) in the field to assist them in
development and maintenance of resource-loaded networks.
• Visit all construction Spreads on regular basis to maintain interface with Company and
Contractors’ field personnel and analyse the situation in field from planning prospective.
• Produce time-impact analyzes on as-needed basis to support Company’s position in
extension of time/delay claim defense.
Oct 04 – Mar 06 Sakhalin Energy Investment Company (through Orion Engineering Services Ltd.)
Construction Planner for Sakhalin-II Onshore Pipeline construction management team (PDP),
Sakhalin Island, Russia
Responsibilities:
• Development and Management of the Onshore Pipelines Overall Plan from FEED to
commissioning ensuring it compliments the Project Level 1 and 2 plans.
• Undertake Cost Phasing exercises to align with the current schedule.
• Assist and support the various Onshore Pipeline Departments [Operations, Construction,
Approvals, HSE etc] on Planning and Scheduling Issues including the development of
stand-alone schedules.
• Provide reports to and support Pipeline Project Controls department and liaise with the
Central Planning Group where necessary. Ensure reporting is carried out in line with
Project objectives.
• Work with PDP construction contractor (sub-contractors) in the field to assist them in
development and maintenance of resource-loaded networks.
• Develop/maintain an independent construction schedule based on contractors’
performance and input from Company’s field representatives as well as own observations.
• Visit all construction Spreads on regular basis to maintain interface with Company and
Contractors’ field personnel and analyse the situation in field from planning prospective.
• Produce Critical Path/Float/Resource Analyses of contractors’ work, identify the most
critical resources and areas and make appropriate recommendations to contractors and
PDP management.
• Calculate daily/weekly production plans and required production rates for the most critical
areas in order to keep track of contractors’ performance.
• Analyze productivity, work organization and performance of individual contractors and
prepare independent completion forecasts for PDP Management.
• Train contractors’ personnel in the use of planning software packages and international
planning practices.
Support of Contracts Group
Review extension of time/delay and disruption claims.
Prepare Time Impact and Window Analysis (as well as resulting Float Analysis) to
support Company’s position in claim defense.
Jan 04 – Sep 04 Sakhalin Energy Investment Company (through Orion Engineering Services Ltd.)
Cost and Planning Engineer for Sakhalin-II Onshore Pipeline construction management team
(PDP), Sakhalin Island, Russia
Responsibilities:
• Development and Management of the Onshore Pipelines Overall Cost Report in line with
requirements of Project cost planning group.
• Be the custodian of all official “cost estimates” within onshore pipelines.
• Assist and support the various Onshore Pipeline Departments [Operations, Construction,
Approvals, HSE etc] on cost, planning and budgetary issues including the provision of
account codes and development of stand-alone schedules.
• Report to and support cost and planning initiatives through liaison with the Phase II Project
Planning Group and Finance. Ensure reporting is carried out in line with Project objectives.
• Agree the cost data to be reported monthly to Project Finance and Cost & planning.
Establish a Reporting Procedure/Routine for this interface. Be the focal point for cost
information flow on behalf of the Project Manager.
• Undertake Cost Phasing exercises to align with the current schedule.
Page 4 of 7
Andrei Sannikov’s CV
Last updated on 16-Jul-15
5. • Measure field progress and review invoices of contractors to provide independent judgment
for progress reporting and payment.
• Assist project management in formulating action plans to reverse undesirable trends.
• Coordinate and train other project controls personnel to provide guidance and on-the-job
training.
• Maintain progress charts and reports to inform the project management of project
performance including change control.
• Analyze information produced by project controls systems to determine trends based upon
baseline versus actual progress and cost data within area of responsibility.
Project
overview:
Sakhalin Infrastructure Upgrade Project comprised Construction of bridges, roads, ports,
airports, supervision camps as well field surveys and UXO to support the needs of upcoming
Sakhalin-II project.
Owners: Shell, Mitsubishi, Mitsui
Jun 02 – Dec 03 Arctic Pacific Contractors (Joint Venture Partnership between Kellogg Brown & Root
and Fluor Daniel)
Lead Planning Engineer for design and construction phases of the Sakhalin Infrastructure
Upgrade Project (IUP) in Yuzhno-Sakhalinsk, Russia.
Responsibilities:
• Interface with IUP Project Management, Engineering department and Construction
department to obtain timely and accurate information for the development and
maintenance of
− IUP Baseline Schedule
− Weekly schedule updates
− Progress measurement base
− Progress curves
− Monthly progress updates
− Weekly 60-day schedule reports
− Weekly Slippage Reports
• Manage and supervise the day to day work of the IUP Planning Group.
• Oversee the development and maintenance of the project progress measurement and
reporting system.
• Identify project interfaces and ensure they are included in the IUP project schedules.
• Identify the critical path for the IUP project and review the critical path activities weekly.
• Maintain the updated project schedules.
• Develop and maintain the schedule risk model for the IUP project.
• Review risk mitigation actions and re-assess level of risk.
• Provide input to the Monthly Project Progress Report.
• Review scope changes and change requests for schedule impact.
• Provide project management with forecasts and analyses, as required, to ensure the
achievement of key project targets and milestones.
• Provide input during bid evaluations to aid in contract award recommendations.
• Train contractors’ personnel in the use of planning software packages and international
planning practices.
Special assignment on part-time basis:
Regional Approvals Planner to support Sakhalin Energy Corporate Approval Dept. in Yuzhno-
Sakhalinsk.
Responsibilities:
• Create and maintain a logic-driven network covering 21 Land Management Files required
for the Final Land Allocation for construction phase of Sakhalin II oil and gas gathering
project.
• Interface with Final Land Allocation and Land Marking Contractors as well as with Land
Committees and other Governmental Agencies in order to reflect the most current and
accurate forecast in the schedule.
• Identify the critical path and review the critical path activities weekly.
Page 5 of 7
Andrei Sannikov’s CV
Last updated on 16-Jul-15
6. • Conduct schedule review meetings with Land Management File Holders.
• Produce and publish plan and actual S-curves and summary level schedule reports for
Phase II Project Management.
Project
overview:
The Caspian Pipeline Consortium (CPC) was a major international crude oil transportation
project with the participation of Russia, Kazakhstan and leading international oil and gas
companies, created for the construction and operation of a pipeline system from Tengiz field in
Kazakhstan to the Novorossiysk-2 Marine Terminal on Russia's Black Sea coast. The project
included 1,510 km (940 mi) long oil pipeline (40” and 42”), five pump stations and a marine
terminal with two single point moorings and a tank farm with four storage tanks of 100,000 cubic
meters (3,500,000 cu ft) each.
Owners: Chevron, Shell, ExxonMobil, Eni, British Gas, Rosneft, Lukoil
Nov 01 – May 02 Fluor Daniel Eurasia
Planner for the Commissioning and Start-up Team on the Caspian Pipeline Project.
Responsibilities:
• Create and maintain Commissioning and Start-up schedules for three CPC pump stations
i.e. Kropotkin, Komsomolsk (in Russia) & Atyrau (in Kazakhstan).
• Interface with project construction teams to ensure coordination between construction and
commissioning activities.
• Visit construction sites and check physical construction/commissioning progress and notify
Project management of problems/potential delays.
• Prepare weekly and monthly commissioning progress reports, documentation status
reports, publish periodic updates of startup and commissioning schedules.
Jun 01 – Nov 01 Fluor Daniel Eurasia
Project Scheduler for the Fluor Daniel Marine Terminal Team on the Caspian Pipeline
Project.
Responsibilities:
• Update and maintain Overall CPC Project First Oil Schedule based on input from all CPC
Project Teams.
• Update and maintain the CPC Project Master List of activities to be performed during
future oil delivery shutdowns.
• Track and analyze construction progress and contractors' performance to forecast
completion dates for various milestones and assist Project management in understanding
general Project trends.
• Prepare various deliverables for progress/forecast reporting including P3 logic networks,
progress curves, spreadsheets etc.
• Check physical construction/commissioning progress on site and notify Project
management of problems/potential delays.
Oct 1999 - Jun
01
Fluor Daniel Eurasia
Project Scheduler/Cost Engineer in the Project Controls Dept. of Fluor Daniel Eurasia in
Krasnodar, Russia, on the Caspian Pipeline Project - Construction Phase.
Responsibilities:
• Prepare scheduling, estimating, and cost engineering data to provide accurate information
to be used for project planning and analysis of project status.
• Forecast progress, performance and cost and schedule trends to provide the client and
project management with quality information for decision making.
• Process progress reports, maintain progress logs and review invoices
• Maintain progress charts and reports to inform client and project management of project
performance including change control.
• Perform risk analysis using Crystal Ball software package for cost forecast and
contingency funds calculation.
• Inform project management of schedule, estimate, or cost variances and potential problem
areas to provide adequate warning for appropriate action.
• Investigate causes of variances between estimated, committed, and actual amounts.
• Maintain detailed man-hours and invoice logs.
Page 6 of 7
Andrei Sannikov’s CV
Last updated on 16-Jul-15
7. • Gather and check accurate cost and schedule progress data to update the progress of the
project on a periodic basis.
• Perform material take-off based on construction drawings and estimate the cost of relative
construction activities.
• Issue monthly Cost Reports and Cash Call forecasts.
• Update and maintain Overall CPC Project First Oil Schedule based on input from all
Project Teams.
Oct 1998 - Sep
1999
Fluor Daniel Eurasia
Project Scheduler/Cost Engineer in the Project Controls Dept. of Fluor Daniel Eurasia in
Moscow on the Caspian Pipeline Project – Feasibility Study and Detailed Engineering Phase.
Sept 1997- Sep
1998
Fluor Daniel Eurasia
Interpreter and translator with Fluor Daniel Eurasia in Moscow on the Caspian Pipeline Project.
1996-1997 Free-lance Interpreting/Translation (English, French, German, Russian) in Moscow in the
following fields: Oil production, geology, computers’ hard- & software, mechanical & electrical
engineering, pipe production, banking & financial operations, automotive production, law, civil
engineering, economics.
1994-1996 International Payment Dept. of the Bank for Social Development, Kirov, Russia.
Responsibilities: processing of wire transfers, letters of credit and other international banking
operations.
1993-1994 Interpreter (German-Russian) with Rieter Spinning Systems (Germany) on a project of cotton
spinning mills construction in Azerbaijan.
1991-1992 Free-lance Interpreting/Translation (English, French and German) for various companies in
Azerbaijan covering cotton processing, oil production, textile, automotive production etc.
1988-1991 Deputy head of Foreign Liaison Department at Ganja Automotive Plant in Ganja, Azerbaijan
1984-1986 Interpreter (English-Russian) at Vyksa Steel Plant (Casing Pipes Production Project under
contract with Nippon Steel Corporation), Vyksa, Russia
Education
1979-1984 Dobrolyubov State University of Nizhny Novgorod, Russia
Bachelor Degree
1982-1983 French Language course in Grenoble University, France
1994 Commerzbank AG, Stuttgart, Germany
Training in International Banking Operations
2003 Advanced Training Courses (602-604) in Primavera (P3) Planning software provided by
PMSOFT (Authorized representative of Primavera Systems Inc. in Russia)
2008-2011 Moscow Business School, Master of Business Administration.
2009 Advanced Training Courses (P102 and P106-P) in Primavera (P6) Planning software provided
by PMSOFT (Authorized representative of Primavera Systems Inc. in Russia)
References Available upon request.
Page 7 of 7
Andrei Sannikov’s CV
Last updated on 16-Jul-15