SlideShare a Scribd company logo
1 of 35
Download to read offline
A Sunrise Project for a Sunshine Future
PARADEEP REFINERY PROJECT
Faculty
Rajsekhar Patnala
DMPN-CG
Prepared by
Production-CG Team
CONTENTS
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
• Introduction
• Compressor Takeover From Maintenance
• Start-Up
• Normal Running And Monitoring
• Trip/Emergency Shutdown
• Hot/Cold Start Up
• Shutdown And Handover To Maintenance
INTRODUCTION
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
• Compressors are complex machines.
• Complexity lies in the forces(thermal, mechanical stresses etc) that are
acting on the machine components.
• Operating personnel should understand the systems and procedures
thoroughly.
• SOPs on various operational procedures should be available handy.
• Operating personnel should be very attentive and follow all the safety
norms while in the vicinity or working with compressor.
COMPRESSOR COMPONENTS
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
T
B
T
B J
B
J
B
COMPRESSOR COMPONENTS
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
• Compressor
• Turbine Drive
• Governor
• Anti-surge System
• Bearings (Temp, Vibration, axial displacement)
• LO System (cooler, Filter, accumulators, mist eliminator)
• Barring System
• Gland System
• Condensate System
• Rundown Tank
COMPRESSOR – TAKEOVER FROM MAINTENANCE
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
1. Ensure that all the jobs are completed as per the Job list.
2. Get the clearance from maintenance departments (mechanical / electrical
/ inst).
3. Ensure that blinding & deblinding is done for Normal Running condition.
4. Physically look around the compressor to check if there are any
incomplete jobs.
5. Ensure removal of debris, tools and tackle, scaffolding in the compressor
area.
6. Ensure area is cleaned properly and there is no oil spillage
7. Ensure proper lighting.
COMPRESSOR STARTUP
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
Depending on the Compressor vendor and type there will be minor
variations in the compressor operating procedures. The procedure
presented in the following slides gives general idea which will be common
for all the centrifugal steam driven compressors.
STEPS DURING STARTUP
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
1. Preparation.
2. Establish cooling water.
3. Establish separation seal buffer.
4. Startup oil system.
5. Establish seal system.
6. Take turning gear inline.
7. Start live steam piping warm-up HP side and LP side.
8. Steam turbine chest valve Initial warm-up.
9. Lineup the gland steam condenser.
10. Line-up vacuum condenser in line.
11. Preparation of compressor.
12. Starting steam turbine.
13. Compressor loading and stabilizing.
STEPS DURING STARTUP
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
PREPARATION
• Ensure all the utilities are commissioned namely Cooling Water, Plant air,
Nitrogen, HHP/HP/MP/LP Steam
• Get the clearance from maintenance departments( mechanical/electrical
/instrumentation (if maintenance job is carried out )
• Ensure that blinding & deblinding is done for Normal Running condition.
• Take Clearance for Steam from TPS.
• Ensure HHP steam main valves, bypass valves, control valve and trip valve
are closed
• Ensure backpressure LP Steam line main valves & bypass valves are closed.
• Open condensate drain valve in SHH line and dry the steam upto main B/V
Open condensate drain valve in SL line and dry the steam upto main B/V
STEPS DURING STARTUP
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
ESTABLISH COOLING WATER
Commission cooling water in following systems
• Ejector condenser of Gland System
• LO cooler.
• Turbine steam condenser
• LO pump bearing house
Precautions:
• Remove air pockets.
• Ensure TSV/PSVs are in line
• Ensure TG, PG are working
STEPS DURING STARTUP
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
ESTABLISH SEPARATION SEAL BUFFER
• Line up the Nitrogen supply Filter.
• Ensure DP across filter is in normal range,
• Service the filter if PDG shows high.
• Set pressure of separation seal buffer.
• Line up separation seal buffer valves
Precautions:
• Ensure TSV/PSVs are in line
• Ensure TG, PG are working
• Confirm the flow of nitrogen
STEPS DURING STARTUP
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
ESTABLISH LUBE OIL SYSTEM
• Ensure that sufficient oil level is there in the reservoir or else Top-up
• Heat oil if necessary
• Prepare accumulators ready.
• Prepare the LOP(T) and start the pump
• Circulate oil through various circuits
• Remove air pockets from TSV, impulse lines, filters, accumulators etc.
• Fill the rundown tank , commission it and check through sight glass
• Ensure flow through all the Oil return lines.
• Run the mist eliminator
• Run Centrifuge
Precautions:
• Ensure that leaks are not there,
• Stabilize the pressure, temperature level readings
• Check the auto start of the standby pump
STEPS DURING STARTUP
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
ESTABLISH SEAL GAS SYSTEM
• Keep the discharge PSV bypass open.
• Line up Flush gas supply to the seal.
• Set the flow of flush gas on both DE and NDE .
• Establish primary buffer
Precautions:
• Ensure there is not pressure buildup in the compressor casing that will
damage the seal
• Ensure that the filter DP is normal and there is no condensate in the
system.
STEPS DURING STARTUP
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
TAKING TURNING GEAR IN LINE
• Initial operation of turning gear should be done manually to ensure that
breakaway of the turbine train is possible without exceeding the torque
capability of the Turning Gear. This will be done by Maintenance.
• Start turning gear system (approx. one hour prior to start-up for cold start
up
• Disable lock out function of turning gear by selecting handle position on
turning gear before turning motor start.
• Confirm that the turning gear is in disengage position and start the motor.
• Check for shaft rotation and proper operation of turning gear. Adjust the
Seal gas system flows after turning gear is put in operation.
Precautions:
• Ensure shaft rotation physically and from field instruments
• Check the axial displacement and vibration probe readings
STEPS DURING STARTUP
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
START LIVE STEAM PIPING & STEAM TURBINE CHEST VALVE INITIAL WARM-UP
• Admit LP Steam(exhaust steam) for approximately 3 hours by opening bypass valve
of NRV with opening casing drain and other drains to remove condensate.
• Ensure that SSH steam is superheated by at least 30oC
• Open the b/v's in the drain including TTV drains and warm-up lines to allow the
removal of condensate arising during warm-up.
• Warm up inlet piping system simultaneously up to the recommended superheat
condition as shown in table. TTV warm up will be part of Inlet piping system.
• TTV drain line shall be kept open during warm up.
• Continue warming-up casing with exhaust steam until temperatures are climbing
very slowly. Increase casing metal temperature to (SL Temp - 30) oC approx. at deep
temperature sensors ( If necessary open TTV valves and admit steam into casing.
Precautions:
• Thoroughly remove the condensate forming.
• Follow the heating curve.
STEPS DURING STARTUP
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
LINEUP THE GLAND STEAM CONDENSER
• Ensure cooling water is Charged
• Check the CW pressures and temperatures on the gland steam condenser.
• Ensure that the goose neck sealed by filling with water Take inline the
condensate trap in the SM line.
• Charge steam slowly and establish vacuum.
• Ensure that no steam escapes at the rotor ends of the steam turbine,
• In case of steam escape have the malfunction corrected.
Precautions:
• If steam turbine is in hot condition during turbine trip break the vacuum till
the time steam is charged, ingress of air into gland will cause shaft
STEPS DURING STARTUP
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
PREPARATION OF COMPRESSOR
• Ensure Blinding/ Deblinding is done as per list.
• Purge the suction lines with Nitrogen purge provided, to remove air from
the circuit Pressurise the casing to 0.5kg/cm2 and vent to atmosphere
and Depressurise using LPDs in suction, discharge and spill back line.
• Repeat this till sample from casing reads oxygen <0.2%.
• Open anti-surge valves to full open condition and free from hand wheel.
• Open Inventory isolation valves.
• Lineup tracing steam of suction lines of the Compressor.
• Once Compressor is floating with suction close the PSV bypass that are
opened. Drain compressor casing free of any liquid.
Precautions:
• Discharge PSVs can now be closed
STEAM TURBINE - STARTUP
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
PERMISSIVES FOR STARTING STEAM TURBINE
• Normally unless certain conditions of the compressor are met as
mentioned typical of FCC WGC below, the compressor start is not allowed
by the ESD system
• WGC Start Permissive:
I305 STARTPERMISSIVE FOR WGC FROM 1ST AS VALVE OPEN FEEDBACK FSH0182 SP
I305 STARTPERMISSIVE FOR WGC FROM 2ND AS VALVE OPEN FEEDBACK FSH0135 SP
I305 LO COOLER O/L TEMP NOT LOW TT4402 SP
I305 LO SUPPLY HDR PRESSURE COMP PERMISSIVE NOTLOW PT4201 SP
I305 DP BETWEEN FLUSH N2 AND PRIMARY BUFFER PDT4203 SP
I305 ESV CLOSE FEED BACK ZSL4302 SP
I305 OVERHEAD TANK LEVEL HIGH LIA4200 SP
I305 CONTROL OIL HDR PRESSURE NOT LOW PT4303 SP
STEAM TURBINE - STARTUP
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
Start the Turbine (Typical of FCC WGC by Elliot Ebara)
• Check if Ready to start is achieved.
• Keep the governor valve full open.
• Slowly open the TTV valve manually to increase the RPM @ 10rpm/sec
• Bring the rpm to low idle speed of 600rpm.
• If any noise is observed reduce speed to previous step and wait till noise
gets reduced
• Monitor (SI-4300/2) and control speed at low Idle speed #1 using the T&T
valve (023-TOV-401).And confirm that the all mechanical conditions are
satisfactory.
• Confirm that the bearing temperatures (T1-4350/1/2/3/4/5/6/7) and
vibration levels (VIX-4350/2, VIY-4351/4) are stabilized before making
speed changes, And confirm that all the mechanical conditions are
satisfactory.
STEAM TURBINE - STARTUP
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
Start the Turbine (Typical of FCC WGC by Elliot Ebara)
• Confirm that the bearing temperatures (T1-4350/1/2/3/4/5/6/7) and
vibration levels (VIX-4350/2, VIY-4351/4) are stabilized before making
speed changes, And confirm that all the mechanical conditions are
satisfactory.
• Bring the RPM to low Idle speed#2 of 1500rpm @ 10 rpm/sec by throttling
023-TOV-401 manually with governor valves (SV-4302) wide open for
equalized casing warming and keep at that RPM for 80 min
• Confirm that the Deep casing metal temp (TI4302-TI4304) < 80 °C and
shallow casing metal temp (TI4303-TI4305) < 80 °C and Temp diff (TI4306-
TI4307) < 125 °C.
• Rise the deep casing metal temperatures to 150 °C at (TI-4302/4) at end of
low idle#2 1500 rpm.
STEAM TURBINE - STARTUP
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
Start the Turbine (Typical of FCC WGC by Elliot Ebara)
• Gradually open T&T valve fully. Then governor will control train speed a
Iittle bit above low Idle speed#2 of 1500. Confirm that governor is
controlling speed (once the speed exceeds reference speed (SI-4301/3) a
• Now press acceleration start (HS4321), the train will be brought to high Idle
speed of 2400 rpm by Auto Acceleration Logic. and then back to reference
speed).
• There is a critical speed band (1600-2100), in this band the acceleration will
be 20 rpm/sec
• Allow the deep casing temperatures to rise above 150 °C
• Increase the speed to minimum governing speed.
STEAM TURBINE - STARTUP
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
Loading the Turbine (Typical of FCC WGC by Elliot Ebara)
• Check the process readiness
• Put anti-surge controllers in auto.
• Slowly increase the load and allow the anti-surge to close.
• Put the speed controller in auto cascade.
• While loading watch for level increase in compressor KODs and turbine
condensate well.
NORMAL RUNNING AND MONITORING
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
• During normal running condition the operating parameter of both process
and machine are to be monitored.
• The monitoring interfaces are DCS panel, SRR, LCP.
Parameters to monitor
• Process P/T/F
• Anti-surge controller deviation
• Compressor discharge pressure controller.
• Compressor KOD levels and Auto Run of condensate pumps.
• LO system filter DP/ Temp, LO quality level
• Vibration/compressor temp/ axial displacement readings.
• Seal system health(DP, Nitrogen pressure, seal gas leak flow.)
• Cooling water flow
• Gland leak and Gland system
• Physical verification of compressor for integrity and coherence with
instrument readings
TRIP / EMERGENCY SHUTDOWN
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
• Trip is executed by ESD system when any of the process/ machine parameters
crosses healthy values and bring the machine to safe shutdown
• Below is the Typical of FCC-INDMAX WGC
IZ302 LO TO BEARINGS HDR PRESSURE TO TRIP WGC 2/3 PZT4200A/B/C TRIP
IZ304 WGC SEAL NITROGEN PRESSURE LOW PZT4295A/B/C TRIP
IZ306 DP BETWEEN FLUSH N2 AND PRIMARY BUFFER TO TRIP WGC PDZT4202A/B/C TRIP
IZ311 RPM INDICATION TO TRIP CONFIRM SOURCE (SA4302) TRIP
IZ312 SPEED SIGNAL FROM GOVERNOR OVERSPEED TRIP (2/3) TRIP
IZ313 OVERSPEED PROTECHTION PROTECH203 SSHH4351 (2/3) TRIP
IZ314 EMERGENCY STOP PUSH BUTTON (HSZ4306) TRIP
IZ321 ZZS4250A/B/C 2/3 TRIP
IZ322 VZX4250/4251 1/2 TRIP
IZ323 VZX4252/4253 1/2 TRIP
IZ324 VZX4350/4351 1/2 TRIP
IZ325 VZX4352/4353 1/2 TRIP
IZ326 ZZS4350A/B/C 2/3 TRIP
IZ327 TZ4250/4251 1/2 TRIP
IZ328 TZ4252/4253 1/2 TRIP
IZ329 TZ4254/4255 1/2 TRIP
IZ330 TZ4256/4257 1/2 TRIP
IZ331 TZ4350/4351 1/2 TRIP
IZ332 TZ4352/4353 1/2 TRIP
IZ333 TZ4354/4355 1/2 TRIP
IZ334 TZ4356/4357 1/2 TRIP
IZ341 CONTROL OIL HEADER PRESSURE LOW PZT4304A/B/C (2/3) TRIP
IZ371 ASC FAILURE 1ST STG FIC4100A/B TRIP
IZ372 ASC FAILURE 2ND STG FIC4101A/B TRIP
IZ373 TRIP ON EXCESSIVE SURGE RECEIVING FROM ASC 1ST STG XA4100A/B TRIP
IZ374 TRIP ON EXCESSIVE SURGE RECEIVING FROM ASC 2ND STG XA4101A/B TRIP
TRIP / EMERGENCY SHUTDOWN
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
Usual Trip conditions
Process side
• High KOD level
• High discharge temperature
• Inventory valve accidental closure
Machine side
• High vibrations
• High axial displacement
• High temperature in bearings
• LO pressure low
• Low control oil pressure
• Excessive surge
• Seal failure detected by high seal gas flow
• Over speed trip
• Emergency stop
TRIP / EMERGENCY SHUTDOWN
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
AFTERMATH OF TRIP & HOT COLD START-UP
Effects of activation of trip
• TTV will close
• Control oil to governor will stop
• Inventory valve will close
• Machine train will coast down to barring condition
• Barring will be activated
HOT / COLD STARTUP
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
COLD START UP (WGC-FCC) HOT STARTUP
SHUTDOWN & HANDOVER TO MAINTENANCE
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
• Switch the Speed control and the Anti-surge valves to manual.
• Gradually reduce load by reducing the turbine speed to minimum
governing speed and open the anti-surge valve fully.
• Press the “Stop” Gov stop: This will eventually close the Governor Valve
and the T & T Valve.
• Monitor the vibration levels, particularly when approaching the unit critical
speeds. In the event that severe vibration is encountered when
approaching the critical speed, decelerate as quickly as possible.
• Shut down the gland condenser leak off system before rotor comes to a
stop.
SHUTDOWN & HANDOVER TO MAINTENANCE
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
• Close the exhaust block valve and release the casing internal pressure as
quickly as possible. Confirm zero speed for a while and confirm that there is
no possibility of reverse rotation.
• Then select ratcheting position (not lockout position) of the lever on the
turning gearbox. And start the turning gear.
• The recommended turning period is minimum 14 hrs after turbine shut
down. When turning period is over, stop the turning motor. And select
lockout position (not ratcheting position) of the lever on the turning
gearbox before rotor complete stop.
• Be sure that no steam can enter the turbine from any source when idle.
Open the turbine casing drains once unit is entirely blocked-in
• Ensure closing of the compressor suction and discharge valve
(XZV0026/0369/0370/0371)
SHUTDOWN & HANDOVER TO MAINTENANCE
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
• Open the compressor drains and drain off any liquid.
• Depressurise and purge with nitrogen and blind the suction and discharge
General Precaution
• Allow the auxiliary oil pump to operate until the bearings have reached
temp. of oil leaving the cooler.
• Shutdown the gas seal system after the compressor has been
depressurized. Shut down the separation seal buffer after oil system has
been shutdown
• If an unusual amount of liquid is drained from the compressor, it should be
analyzed to determine the source. Steps should be taken immediately to
prevent liquid from entering into the compressor.
• Handover to maintenance for blinding.
• After blinding purge the system and handover to maintenance only when
gas test is passed
LIST OF MAJOR CENTRIFUGAL COMPRESSORS
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
UNIT COMPRESSOR VENDOR SERVICE DRIVE
UNIT - 23 FCC
WGC (WETGAS
COMPRESSOR) ELLIOT EBARA HYDROCARBON
STEAM TURBINE
DRIVEN
UNIT - 23 FCC
MAB (MAIN AIR
BLOWER) MAN TURBO AIR
STEAM TURBINE
DRIVEN
UNIT - 70 PRU
VRC (VAPOR RECOVERY
COMPRESSOR) ELLIOT EBARA HYDROCARBON MOTOR DRIVEN
UNIT-40 NHT
40K001 (NHT RECYCLE
GAS COMPRESSOR HITACHI HYDROCARBON MOTOR DRIVEN
UNIT-42 CCR
42K001 (CCR RECYCLE
GAS COMPRESSOR) DRESSOR RAND HYDROCARBON
STEAM TURBINE
DRIVEN
UNIT-42 CCR
42K002 ( NET GAS
COMPRESSOR-1) HITACHI HYDROCARBON MOTOR DRIVEN
UNIT-42 CCR
42K003 ( NET GAS
COMPRESSOR-2) HITACHI HYDROCARBON MOTOR DRIVEN
UNIT-20/21/22
VGO-HDT
RECYCLE GAS
COMPRESSOR BHEL HYDROGEN
STEAM TURBINE
DRIVEN
UNIT- 13/14/15
DHDT
RECYCLE GAS
COMPRESSOR BHEL HYDROGEN
STEAM TURBINE
DRIVEN
UNIT-24
ALKYLATION
REFRIEGERATION GAS
COMPRESSOR HITACHI C3-C4 MOTOR DRIVEN
UNIT- 30 DCU WET GAS COMPRESSOR BHEL HYDROCARBON
STEAM TURBINE
DRIVEN
WHAT CAN GO WRONG?
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
During startup
• Not Properly drying the steam/ faulty Steam Traps
• Not Giving sufficient time for idling
• Not ensuring LO quality/quantity
• Improper lineup of process valves
• Bypassing Safety Interlocks
• Improper Inertisation
• Restriction in discharge circuit
• Improper Draining of KOD/Casing
SAFETY ASPECTS
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
• Strictly Avoid Assumptions
• Follow SOPs provided
• Communication between field and panel
• Keen observation for leaks with gas monitors
• Ear Muffs along with other safety gear
• Ensure that all the online gas detectors in the vicinity are functioning
• Checking of the Safety Interlock systems
• Test Run/Surge Test should be done before commissioning
QUERIES
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future
PARADEEP REFINERY PROJECT
A Sunrise Project for a Sunshine Future

More Related Content

Similar to Compressor operation.pdf

171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.pptssuser9e9be71
 
Simple vapour compression system
Simple vapour compression systemSimple vapour compression system
Simple vapour compression systemKaushal Patel
 
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdfEC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdfsuryanshsingh836763
 
On Power Plant Operation cource In Urdu by Khalid ayaz Soomro.pdf
On Power Plant Operation  cource In Urdu by Khalid ayaz Soomro.pdfOn Power Plant Operation  cource In Urdu by Khalid ayaz Soomro.pdf
On Power Plant Operation cource In Urdu by Khalid ayaz Soomro.pdfKhalidAyaz3
 
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineThermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineManohar Tatwawadi
 
psv calculation ppt jhjghgh jghjgh jhjgj
psv calculation ppt jhjghgh jghjgh jhjgjpsv calculation ppt jhjghgh jghjgh jhjgj
psv calculation ppt jhjghgh jghjgh jhjgjHashemAli23
 
psv and pvrvdesign calculation.ppt
psv and pvrvdesign calculation.pptpsv and pvrvdesign calculation.ppt
psv and pvrvdesign calculation.pptssuser73bb74
 
psv-calculation_psv-calculation_psv-calc
psv-calculation_psv-calculation_psv-calcpsv-calculation_psv-calculation_psv-calc
psv-calculation_psv-calculation_psv-calcAmit Chopra
 
SAFE HANDING OVER OF EQUIPMENTS.pptx
SAFE HANDING OVER OF EQUIPMENTS.pptxSAFE HANDING OVER OF EQUIPMENTS.pptx
SAFE HANDING OVER OF EQUIPMENTS.pptxJOMON M.C
 
Thermal Power Plant Simulator Operations Training
Thermal Power Plant Simulator Operations TrainingThermal Power Plant Simulator Operations Training
Thermal Power Plant Simulator Operations TrainingManohar Tatwawadi
 
Training on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdfTraining on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdfMadan Karki
 

Similar to Compressor operation.pdf (20)

Boiler Mountings
Boiler MountingsBoiler Mountings
Boiler Mountings
 
Boiler light up & loading
Boiler light up & loadingBoiler light up & loading
Boiler light up & loading
 
171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt
 
Refrigeration
RefrigerationRefrigeration
Refrigeration
 
Simple vapour compression system
Simple vapour compression systemSimple vapour compression system
Simple vapour compression system
 
job des
job desjob des
job des
 
Barry Cutting - Booster fans Angus Place Colliery
Barry Cutting  - Booster fans Angus Place CollieryBarry Cutting  - Booster fans Angus Place Colliery
Barry Cutting - Booster fans Angus Place Colliery
 
Piping system
Piping systemPiping system
Piping system
 
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdfEC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
 
11. membrane unit
11. membrane unit11. membrane unit
11. membrane unit
 
On Power Plant Operation cource In Urdu by Khalid ayaz Soomro.pdf
On Power Plant Operation  cource In Urdu by Khalid ayaz Soomro.pdfOn Power Plant Operation  cource In Urdu by Khalid ayaz Soomro.pdf
On Power Plant Operation cource In Urdu by Khalid ayaz Soomro.pdf
 
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineThermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
 
psv calculation ppt jhjghgh jghjgh jhjgj
psv calculation ppt jhjghgh jghjgh jhjgjpsv calculation ppt jhjghgh jghjgh jhjgj
psv calculation ppt jhjghgh jghjgh jhjgj
 
psv and pvrvdesign calculation.ppt
psv and pvrvdesign calculation.pptpsv and pvrvdesign calculation.ppt
psv and pvrvdesign calculation.ppt
 
psv-calculation_psv-calculation_psv-calc
psv-calculation_psv-calculation_psv-calcpsv-calculation_psv-calculation_psv-calc
psv-calculation_psv-calculation_psv-calc
 
SAFE HANDING OVER OF EQUIPMENTS.pptx
SAFE HANDING OVER OF EQUIPMENTS.pptxSAFE HANDING OVER OF EQUIPMENTS.pptx
SAFE HANDING OVER OF EQUIPMENTS.pptx
 
Thermal Power Plant Simulator Operations Training
Thermal Power Plant Simulator Operations TrainingThermal Power Plant Simulator Operations Training
Thermal Power Plant Simulator Operations Training
 
Condensate system
Condensate systemCondensate system
Condensate system
 
PUMPS.ppt
PUMPS.pptPUMPS.ppt
PUMPS.ppt
 
Training on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdfTraining on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdf
 

Recently uploaded

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 

Recently uploaded (20)

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 

Compressor operation.pdf

  • 1. A Sunrise Project for a Sunshine Future PARADEEP REFINERY PROJECT Faculty Rajsekhar Patnala DMPN-CG Prepared by Production-CG Team
  • 2. CONTENTS PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future • Introduction • Compressor Takeover From Maintenance • Start-Up • Normal Running And Monitoring • Trip/Emergency Shutdown • Hot/Cold Start Up • Shutdown And Handover To Maintenance
  • 3. INTRODUCTION PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future • Compressors are complex machines. • Complexity lies in the forces(thermal, mechanical stresses etc) that are acting on the machine components. • Operating personnel should understand the systems and procedures thoroughly. • SOPs on various operational procedures should be available handy. • Operating personnel should be very attentive and follow all the safety norms while in the vicinity or working with compressor.
  • 4. COMPRESSOR COMPONENTS PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future T B T B J B J B
  • 5. COMPRESSOR COMPONENTS PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future • Compressor • Turbine Drive • Governor • Anti-surge System • Bearings (Temp, Vibration, axial displacement) • LO System (cooler, Filter, accumulators, mist eliminator) • Barring System • Gland System • Condensate System • Rundown Tank
  • 6. COMPRESSOR – TAKEOVER FROM MAINTENANCE PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future 1. Ensure that all the jobs are completed as per the Job list. 2. Get the clearance from maintenance departments (mechanical / electrical / inst). 3. Ensure that blinding & deblinding is done for Normal Running condition. 4. Physically look around the compressor to check if there are any incomplete jobs. 5. Ensure removal of debris, tools and tackle, scaffolding in the compressor area. 6. Ensure area is cleaned properly and there is no oil spillage 7. Ensure proper lighting.
  • 7. COMPRESSOR STARTUP PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future Depending on the Compressor vendor and type there will be minor variations in the compressor operating procedures. The procedure presented in the following slides gives general idea which will be common for all the centrifugal steam driven compressors.
  • 8. STEPS DURING STARTUP PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future 1. Preparation. 2. Establish cooling water. 3. Establish separation seal buffer. 4. Startup oil system. 5. Establish seal system. 6. Take turning gear inline. 7. Start live steam piping warm-up HP side and LP side. 8. Steam turbine chest valve Initial warm-up. 9. Lineup the gland steam condenser. 10. Line-up vacuum condenser in line. 11. Preparation of compressor. 12. Starting steam turbine. 13. Compressor loading and stabilizing.
  • 9. STEPS DURING STARTUP PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future PREPARATION • Ensure all the utilities are commissioned namely Cooling Water, Plant air, Nitrogen, HHP/HP/MP/LP Steam • Get the clearance from maintenance departments( mechanical/electrical /instrumentation (if maintenance job is carried out ) • Ensure that blinding & deblinding is done for Normal Running condition. • Take Clearance for Steam from TPS. • Ensure HHP steam main valves, bypass valves, control valve and trip valve are closed • Ensure backpressure LP Steam line main valves & bypass valves are closed. • Open condensate drain valve in SHH line and dry the steam upto main B/V Open condensate drain valve in SL line and dry the steam upto main B/V
  • 10. STEPS DURING STARTUP PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future ESTABLISH COOLING WATER Commission cooling water in following systems • Ejector condenser of Gland System • LO cooler. • Turbine steam condenser • LO pump bearing house Precautions: • Remove air pockets. • Ensure TSV/PSVs are in line • Ensure TG, PG are working
  • 11. STEPS DURING STARTUP PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future ESTABLISH SEPARATION SEAL BUFFER • Line up the Nitrogen supply Filter. • Ensure DP across filter is in normal range, • Service the filter if PDG shows high. • Set pressure of separation seal buffer. • Line up separation seal buffer valves Precautions: • Ensure TSV/PSVs are in line • Ensure TG, PG are working • Confirm the flow of nitrogen
  • 12. STEPS DURING STARTUP PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future ESTABLISH LUBE OIL SYSTEM • Ensure that sufficient oil level is there in the reservoir or else Top-up • Heat oil if necessary • Prepare accumulators ready. • Prepare the LOP(T) and start the pump • Circulate oil through various circuits • Remove air pockets from TSV, impulse lines, filters, accumulators etc. • Fill the rundown tank , commission it and check through sight glass • Ensure flow through all the Oil return lines. • Run the mist eliminator • Run Centrifuge Precautions: • Ensure that leaks are not there, • Stabilize the pressure, temperature level readings • Check the auto start of the standby pump
  • 13. STEPS DURING STARTUP PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future ESTABLISH SEAL GAS SYSTEM • Keep the discharge PSV bypass open. • Line up Flush gas supply to the seal. • Set the flow of flush gas on both DE and NDE . • Establish primary buffer Precautions: • Ensure there is not pressure buildup in the compressor casing that will damage the seal • Ensure that the filter DP is normal and there is no condensate in the system.
  • 14. STEPS DURING STARTUP PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future TAKING TURNING GEAR IN LINE • Initial operation of turning gear should be done manually to ensure that breakaway of the turbine train is possible without exceeding the torque capability of the Turning Gear. This will be done by Maintenance. • Start turning gear system (approx. one hour prior to start-up for cold start up • Disable lock out function of turning gear by selecting handle position on turning gear before turning motor start. • Confirm that the turning gear is in disengage position and start the motor. • Check for shaft rotation and proper operation of turning gear. Adjust the Seal gas system flows after turning gear is put in operation. Precautions: • Ensure shaft rotation physically and from field instruments • Check the axial displacement and vibration probe readings
  • 15. STEPS DURING STARTUP PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future START LIVE STEAM PIPING & STEAM TURBINE CHEST VALVE INITIAL WARM-UP • Admit LP Steam(exhaust steam) for approximately 3 hours by opening bypass valve of NRV with opening casing drain and other drains to remove condensate. • Ensure that SSH steam is superheated by at least 30oC • Open the b/v's in the drain including TTV drains and warm-up lines to allow the removal of condensate arising during warm-up. • Warm up inlet piping system simultaneously up to the recommended superheat condition as shown in table. TTV warm up will be part of Inlet piping system. • TTV drain line shall be kept open during warm up. • Continue warming-up casing with exhaust steam until temperatures are climbing very slowly. Increase casing metal temperature to (SL Temp - 30) oC approx. at deep temperature sensors ( If necessary open TTV valves and admit steam into casing. Precautions: • Thoroughly remove the condensate forming. • Follow the heating curve.
  • 16. STEPS DURING STARTUP PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future LINEUP THE GLAND STEAM CONDENSER • Ensure cooling water is Charged • Check the CW pressures and temperatures on the gland steam condenser. • Ensure that the goose neck sealed by filling with water Take inline the condensate trap in the SM line. • Charge steam slowly and establish vacuum. • Ensure that no steam escapes at the rotor ends of the steam turbine, • In case of steam escape have the malfunction corrected. Precautions: • If steam turbine is in hot condition during turbine trip break the vacuum till the time steam is charged, ingress of air into gland will cause shaft
  • 17. STEPS DURING STARTUP PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future PREPARATION OF COMPRESSOR • Ensure Blinding/ Deblinding is done as per list. • Purge the suction lines with Nitrogen purge provided, to remove air from the circuit Pressurise the casing to 0.5kg/cm2 and vent to atmosphere and Depressurise using LPDs in suction, discharge and spill back line. • Repeat this till sample from casing reads oxygen <0.2%. • Open anti-surge valves to full open condition and free from hand wheel. • Open Inventory isolation valves. • Lineup tracing steam of suction lines of the Compressor. • Once Compressor is floating with suction close the PSV bypass that are opened. Drain compressor casing free of any liquid. Precautions: • Discharge PSVs can now be closed
  • 18. STEAM TURBINE - STARTUP PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future PERMISSIVES FOR STARTING STEAM TURBINE • Normally unless certain conditions of the compressor are met as mentioned typical of FCC WGC below, the compressor start is not allowed by the ESD system • WGC Start Permissive: I305 STARTPERMISSIVE FOR WGC FROM 1ST AS VALVE OPEN FEEDBACK FSH0182 SP I305 STARTPERMISSIVE FOR WGC FROM 2ND AS VALVE OPEN FEEDBACK FSH0135 SP I305 LO COOLER O/L TEMP NOT LOW TT4402 SP I305 LO SUPPLY HDR PRESSURE COMP PERMISSIVE NOTLOW PT4201 SP I305 DP BETWEEN FLUSH N2 AND PRIMARY BUFFER PDT4203 SP I305 ESV CLOSE FEED BACK ZSL4302 SP I305 OVERHEAD TANK LEVEL HIGH LIA4200 SP I305 CONTROL OIL HDR PRESSURE NOT LOW PT4303 SP
  • 19. STEAM TURBINE - STARTUP PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future Start the Turbine (Typical of FCC WGC by Elliot Ebara) • Check if Ready to start is achieved. • Keep the governor valve full open. • Slowly open the TTV valve manually to increase the RPM @ 10rpm/sec • Bring the rpm to low idle speed of 600rpm. • If any noise is observed reduce speed to previous step and wait till noise gets reduced • Monitor (SI-4300/2) and control speed at low Idle speed #1 using the T&T valve (023-TOV-401).And confirm that the all mechanical conditions are satisfactory. • Confirm that the bearing temperatures (T1-4350/1/2/3/4/5/6/7) and vibration levels (VIX-4350/2, VIY-4351/4) are stabilized before making speed changes, And confirm that all the mechanical conditions are satisfactory.
  • 20. STEAM TURBINE - STARTUP PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future Start the Turbine (Typical of FCC WGC by Elliot Ebara) • Confirm that the bearing temperatures (T1-4350/1/2/3/4/5/6/7) and vibration levels (VIX-4350/2, VIY-4351/4) are stabilized before making speed changes, And confirm that all the mechanical conditions are satisfactory. • Bring the RPM to low Idle speed#2 of 1500rpm @ 10 rpm/sec by throttling 023-TOV-401 manually with governor valves (SV-4302) wide open for equalized casing warming and keep at that RPM for 80 min • Confirm that the Deep casing metal temp (TI4302-TI4304) < 80 °C and shallow casing metal temp (TI4303-TI4305) < 80 °C and Temp diff (TI4306- TI4307) < 125 °C. • Rise the deep casing metal temperatures to 150 °C at (TI-4302/4) at end of low idle#2 1500 rpm.
  • 21. STEAM TURBINE - STARTUP PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future Start the Turbine (Typical of FCC WGC by Elliot Ebara) • Gradually open T&T valve fully. Then governor will control train speed a Iittle bit above low Idle speed#2 of 1500. Confirm that governor is controlling speed (once the speed exceeds reference speed (SI-4301/3) a • Now press acceleration start (HS4321), the train will be brought to high Idle speed of 2400 rpm by Auto Acceleration Logic. and then back to reference speed). • There is a critical speed band (1600-2100), in this band the acceleration will be 20 rpm/sec • Allow the deep casing temperatures to rise above 150 °C • Increase the speed to minimum governing speed.
  • 22. STEAM TURBINE - STARTUP PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future Loading the Turbine (Typical of FCC WGC by Elliot Ebara) • Check the process readiness • Put anti-surge controllers in auto. • Slowly increase the load and allow the anti-surge to close. • Put the speed controller in auto cascade. • While loading watch for level increase in compressor KODs and turbine condensate well.
  • 23. NORMAL RUNNING AND MONITORING PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future • During normal running condition the operating parameter of both process and machine are to be monitored. • The monitoring interfaces are DCS panel, SRR, LCP. Parameters to monitor • Process P/T/F • Anti-surge controller deviation • Compressor discharge pressure controller. • Compressor KOD levels and Auto Run of condensate pumps. • LO system filter DP/ Temp, LO quality level • Vibration/compressor temp/ axial displacement readings. • Seal system health(DP, Nitrogen pressure, seal gas leak flow.) • Cooling water flow • Gland leak and Gland system • Physical verification of compressor for integrity and coherence with instrument readings
  • 24. TRIP / EMERGENCY SHUTDOWN PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future • Trip is executed by ESD system when any of the process/ machine parameters crosses healthy values and bring the machine to safe shutdown • Below is the Typical of FCC-INDMAX WGC IZ302 LO TO BEARINGS HDR PRESSURE TO TRIP WGC 2/3 PZT4200A/B/C TRIP IZ304 WGC SEAL NITROGEN PRESSURE LOW PZT4295A/B/C TRIP IZ306 DP BETWEEN FLUSH N2 AND PRIMARY BUFFER TO TRIP WGC PDZT4202A/B/C TRIP IZ311 RPM INDICATION TO TRIP CONFIRM SOURCE (SA4302) TRIP IZ312 SPEED SIGNAL FROM GOVERNOR OVERSPEED TRIP (2/3) TRIP IZ313 OVERSPEED PROTECHTION PROTECH203 SSHH4351 (2/3) TRIP IZ314 EMERGENCY STOP PUSH BUTTON (HSZ4306) TRIP IZ321 ZZS4250A/B/C 2/3 TRIP IZ322 VZX4250/4251 1/2 TRIP IZ323 VZX4252/4253 1/2 TRIP IZ324 VZX4350/4351 1/2 TRIP IZ325 VZX4352/4353 1/2 TRIP IZ326 ZZS4350A/B/C 2/3 TRIP IZ327 TZ4250/4251 1/2 TRIP IZ328 TZ4252/4253 1/2 TRIP IZ329 TZ4254/4255 1/2 TRIP IZ330 TZ4256/4257 1/2 TRIP IZ331 TZ4350/4351 1/2 TRIP IZ332 TZ4352/4353 1/2 TRIP IZ333 TZ4354/4355 1/2 TRIP IZ334 TZ4356/4357 1/2 TRIP IZ341 CONTROL OIL HEADER PRESSURE LOW PZT4304A/B/C (2/3) TRIP IZ371 ASC FAILURE 1ST STG FIC4100A/B TRIP IZ372 ASC FAILURE 2ND STG FIC4101A/B TRIP IZ373 TRIP ON EXCESSIVE SURGE RECEIVING FROM ASC 1ST STG XA4100A/B TRIP IZ374 TRIP ON EXCESSIVE SURGE RECEIVING FROM ASC 2ND STG XA4101A/B TRIP
  • 25. TRIP / EMERGENCY SHUTDOWN PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future Usual Trip conditions Process side • High KOD level • High discharge temperature • Inventory valve accidental closure Machine side • High vibrations • High axial displacement • High temperature in bearings • LO pressure low • Low control oil pressure • Excessive surge • Seal failure detected by high seal gas flow • Over speed trip • Emergency stop
  • 26. TRIP / EMERGENCY SHUTDOWN PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future AFTERMATH OF TRIP & HOT COLD START-UP Effects of activation of trip • TTV will close • Control oil to governor will stop • Inventory valve will close • Machine train will coast down to barring condition • Barring will be activated
  • 27. HOT / COLD STARTUP PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future COLD START UP (WGC-FCC) HOT STARTUP
  • 28. SHUTDOWN & HANDOVER TO MAINTENANCE PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future • Switch the Speed control and the Anti-surge valves to manual. • Gradually reduce load by reducing the turbine speed to minimum governing speed and open the anti-surge valve fully. • Press the “Stop” Gov stop: This will eventually close the Governor Valve and the T & T Valve. • Monitor the vibration levels, particularly when approaching the unit critical speeds. In the event that severe vibration is encountered when approaching the critical speed, decelerate as quickly as possible. • Shut down the gland condenser leak off system before rotor comes to a stop.
  • 29. SHUTDOWN & HANDOVER TO MAINTENANCE PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future • Close the exhaust block valve and release the casing internal pressure as quickly as possible. Confirm zero speed for a while and confirm that there is no possibility of reverse rotation. • Then select ratcheting position (not lockout position) of the lever on the turning gearbox. And start the turning gear. • The recommended turning period is minimum 14 hrs after turbine shut down. When turning period is over, stop the turning motor. And select lockout position (not ratcheting position) of the lever on the turning gearbox before rotor complete stop. • Be sure that no steam can enter the turbine from any source when idle. Open the turbine casing drains once unit is entirely blocked-in • Ensure closing of the compressor suction and discharge valve (XZV0026/0369/0370/0371)
  • 30. SHUTDOWN & HANDOVER TO MAINTENANCE PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future • Open the compressor drains and drain off any liquid. • Depressurise and purge with nitrogen and blind the suction and discharge General Precaution • Allow the auxiliary oil pump to operate until the bearings have reached temp. of oil leaving the cooler. • Shutdown the gas seal system after the compressor has been depressurized. Shut down the separation seal buffer after oil system has been shutdown • If an unusual amount of liquid is drained from the compressor, it should be analyzed to determine the source. Steps should be taken immediately to prevent liquid from entering into the compressor. • Handover to maintenance for blinding. • After blinding purge the system and handover to maintenance only when gas test is passed
  • 31. LIST OF MAJOR CENTRIFUGAL COMPRESSORS PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future UNIT COMPRESSOR VENDOR SERVICE DRIVE UNIT - 23 FCC WGC (WETGAS COMPRESSOR) ELLIOT EBARA HYDROCARBON STEAM TURBINE DRIVEN UNIT - 23 FCC MAB (MAIN AIR BLOWER) MAN TURBO AIR STEAM TURBINE DRIVEN UNIT - 70 PRU VRC (VAPOR RECOVERY COMPRESSOR) ELLIOT EBARA HYDROCARBON MOTOR DRIVEN UNIT-40 NHT 40K001 (NHT RECYCLE GAS COMPRESSOR HITACHI HYDROCARBON MOTOR DRIVEN UNIT-42 CCR 42K001 (CCR RECYCLE GAS COMPRESSOR) DRESSOR RAND HYDROCARBON STEAM TURBINE DRIVEN UNIT-42 CCR 42K002 ( NET GAS COMPRESSOR-1) HITACHI HYDROCARBON MOTOR DRIVEN UNIT-42 CCR 42K003 ( NET GAS COMPRESSOR-2) HITACHI HYDROCARBON MOTOR DRIVEN UNIT-20/21/22 VGO-HDT RECYCLE GAS COMPRESSOR BHEL HYDROGEN STEAM TURBINE DRIVEN UNIT- 13/14/15 DHDT RECYCLE GAS COMPRESSOR BHEL HYDROGEN STEAM TURBINE DRIVEN UNIT-24 ALKYLATION REFRIEGERATION GAS COMPRESSOR HITACHI C3-C4 MOTOR DRIVEN UNIT- 30 DCU WET GAS COMPRESSOR BHEL HYDROCARBON STEAM TURBINE DRIVEN
  • 32. WHAT CAN GO WRONG? PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future During startup • Not Properly drying the steam/ faulty Steam Traps • Not Giving sufficient time for idling • Not ensuring LO quality/quantity • Improper lineup of process valves • Bypassing Safety Interlocks • Improper Inertisation • Restriction in discharge circuit • Improper Draining of KOD/Casing
  • 33. SAFETY ASPECTS PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future • Strictly Avoid Assumptions • Follow SOPs provided • Communication between field and panel • Keen observation for leaks with gas monitors • Ear Muffs along with other safety gear • Ensure that all the online gas detectors in the vicinity are functioning • Checking of the Safety Interlock systems • Test Run/Surge Test should be done before commissioning
  • 34. QUERIES PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future
  • 35. PARADEEP REFINERY PROJECT A Sunrise Project for a Sunshine Future