The document provides an overview of the 110kV Mangad substation. It summarizes that the substation was commissioned in 1976 and has two 12.5MVA power transformers. It has 11 outgoing feeders and receives its main supply through the 110kV TAMG feeder. The document also provides details about the transformer specifications, capacitor bank, battery bank, feeders and safety guidelines for operating personnel.