SlideShare a Scribd company logo
Project Scheduling 2
Prepared by Sebghatullah Karimi
(Junior Lecturer of Kabul Polytechnic University)
1392
Kardan University
Civil Engineering Faculty
Explain how the work environment, the
construction contract, and the project scope
influence the scheduling process.
Explain the three types of project activities used
in scheduling.
Define milestone.
Describe the characteristics of a network diagram.
2
Work breakdown structure – The organization of the
project into specific parts that can be coordinated and
controlled.
Activity – A well-defined, measurable part of the
overall project. An activity must be suitable for
assignment to a particular project team member, and
it consumes both time and resources.
Trade – A construction specialty, such as plumber,
carpenter, welder.
Submittal – A sample of an item to be procured for a
project by a supplier or subcontractor. A submittal
must be approved by the owner or designer prior to
procurement.
3
• A network schedule is graphical drawing of a logical sequence of
events to complete a project. A network-based schedule is a
powerful tool for the planning, development, and construction of
sophisticated projects.
• The development of a network-based schedule follows a logical
process that should involve most of the key project team members.
Every network schedule must begin with a complete understanding
of the project objective, as defined by the owner. The project
participants then take this objective and break it down into tasks
that provide the level of detail necessary to organize, manage, and
control the project. Once these tasks are defined, the project team
establishes the order in which the tasks are to be performed, such
that the project will be completed in an efficient manner.
• To create the network, team members decide which activities must
precede, succeed, or run concurrently with other activities. The end
result of this process is a logic diagram that accurately depicts the
order that the work will follow.
4
The preparation of a network schedule requires a careful analysis of
three factors:
The work environment. The work environment includes such
consideration as the weather, site conditions, availability of building
materials, access for deliveries, availability of power, and the
amount of construction currently occurring in the region.
The contract. A construction contract will typically include the
project completion date, milestones, incentive clauses (which
provide bonuses for early completion), liquidated damages clauses
(which provide penalties for late completion), work rules governing
safety and hiring requirements, and identification of materials and
work that will be provided by the owner. All of these considerations
will affect project organization and scheduling.
The project scope. The scope of the project, as described in the
drawings and specifications, is a major consideration in scheduling.
Drawings and specifications are the source of all the materials and
quantities used in the project and may also describe required
construction methods.
5
1. The first step in the networking process is to define
the work breakdown structure for the project.
2. From the work breakdown structure, the team
defines the specific activities that will make up the
network diagram. An activity must be suitable for
assignment to a particular project team member,
and it should consume both time and resources.
6
Construction activities can generally be characterized as one of three
types:
Production activities are the activities that define the actual
physical construction of the project. Examples include Erect
Concrete Wall. A well-developed schedule allows the project team
to separate all activities of each trade in such a way that each
contractor has a clearly defined scope of work without overlap or
omission.
Procurement activities involve the purchase of materials,
equipment, and services for the project. Most procurement
activities follow a logical sequence, beginning with the preparation
of a submittal, the approval of the submittal by the owner or
designer, the ordering and fabrication of the item, and then the
delivery of the item to the job site..
Administrative activities include required inspections by local
officials or regulatory agencies, as well as permitting. Identifying
these activities requires the involvement of all project team
members, since normally no one person knows all the
administrative requirements for a complex project. 7
A key event in a project schedule can be identified by the use of a
milestone. Examples of milestones include the planned shutdown
of electricity or water supply in order to make connections to
existing utilities, the delivery of a certain phase of a project to the
owner, or a city agreement that a road be opened by a specific
date. Unlike an activity, a milestone cannot be assigned to a
company or person and does not consume time or resources. A
milestone is used simply to signify an important point in the life of
a project.
8
A network diagram is a pictorial representation of all
activities that make up a project and the order in
which these activities must occur to complete the
project in an efficient manner. In order to
develop the network diagram, the scheduler must
answer the following questions for each activity:
9
What activities must occur before this activity
can be done?
What activities must follow this activity?
What activities can be accomplished at the
same time that this activity is occurring?
10
A typical example of a network diagram is shown at the top of
Figure 9.4 in the Gould textbook. As you can see:
The diagram is read from left to right.
Activities are identified by rectangles (nodes) and connected
by arrows.
Each rectangle indicates a single activity.
The network is continuous. Each activity, except the first and
last, has both preceding and succeeding activities.
Activities without predecessors are assumed to begin at the
start of the project.
Activities without successors are assumed to be complete
when the project finishes.
No activity can start until all preceding activities have been
completed.
11
12
13

More Related Content

What's hot

Construction Management - New Trends
Construction Management - New TrendsConstruction Management - New Trends
Construction Management - New Trends
Ahmed El-Askalany, CSTE, CSQA, PMP, CQIA, ITIL
 
Spm ap-network model-
Spm ap-network model-Spm ap-network model-
Spm ap-network model-
Kanchana Devi
 
Project management cpm-pert
Project management   cpm-pertProject management   cpm-pert
Project management cpm-pert
Abu Bashar
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
SHAZEBALIKHAN1
 
Economics of project evaluation cpm module2
Economics of project evaluation cpm module2Economics of project evaluation cpm module2
Economics of project evaluation cpm module2
ahsanrabbani
 
rules of formulating network planning model .
rules of formulating network planning model .rules of formulating network planning model .
rules of formulating network planning model .
ritambharaaatre
 
Project management chapter 9
Project management chapter 9Project management chapter 9
Project management chapter 9
VancityInstitute
 
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Ahmed Fouad, MCIArb, PMP, SP, RMP
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniquesguestc8140fe
 
Ch09
Ch09Ch09
Construction project scheduling and quality control
Construction project scheduling and quality controlConstruction project scheduling and quality control
Construction project scheduling and quality control
monishkumark
 
MS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must knowMS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must know
SHAZEBALIKHAN1
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
Aditi Garg
 
Steps in project control process
Steps in project control processSteps in project control process
Steps in project control process
Uday Doyal
 
Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010B Sai Prasad
 
Scheduling of a project
Scheduling of a projectScheduling of a project
Scheduling of a project
Sailish Cephas
 
06 project time management
06  project time management06  project time management
06 project time management
Ala Ibrahim
 
Project time management
Project time managementProject time management
Project time management
Jack Pumpuni Frimpong-Manso
 

What's hot (19)

Construction Management - New Trends
Construction Management - New TrendsConstruction Management - New Trends
Construction Management - New Trends
 
Spm ap-network model-
Spm ap-network model-Spm ap-network model-
Spm ap-network model-
 
Project management cpm-pert
Project management   cpm-pertProject management   cpm-pert
Project management cpm-pert
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
Economics of project evaluation cpm module2
Economics of project evaluation cpm module2Economics of project evaluation cpm module2
Economics of project evaluation cpm module2
 
rules of formulating network planning model .
rules of formulating network planning model .rules of formulating network planning model .
rules of formulating network planning model .
 
Project management chapter 9
Project management chapter 9Project management chapter 9
Project management chapter 9
 
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
 
Ch09
Ch09Ch09
Ch09
 
Construction project scheduling and quality control
Construction project scheduling and quality controlConstruction project scheduling and quality control
Construction project scheduling and quality control
 
MS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must knowMS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must know
 
ACH 216 Lecture 02 (Project Format)
ACH 216 Lecture 02 (Project Format)ACH 216 Lecture 02 (Project Format)
ACH 216 Lecture 02 (Project Format)
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
 
Steps in project control process
Steps in project control processSteps in project control process
Steps in project control process
 
Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010Seven Basic Steps to Build Realistic Schedule in Project 2010
Seven Basic Steps to Build Realistic Schedule in Project 2010
 
Scheduling of a project
Scheduling of a projectScheduling of a project
Scheduling of a project
 
06 project time management
06  project time management06  project time management
06 project time management
 
Project time management
Project time managementProject time management
Project time management
 

Viewers also liked

11 lecture project scheduling 3
11 lecture project scheduling 311 lecture project scheduling 3
11 lecture project scheduling 3Ahmad Basim Hamza
 
12 lecture project scheduling 4
12 lecture project scheduling 412 lecture project scheduling 4
12 lecture project scheduling 4Ahmad Basim Hamza
 
Project Management (Soft)
Project Management (Soft)Project Management (Soft)
Project Management (Soft)
Ahmad Basim Hamza
 
Yd1305161 sprawozdanie finansowe_2010_z_us-eng done.
Yd1305161 sprawozdanie finansowe_2010_z_us-eng done.Yd1305161 sprawozdanie finansowe_2010_z_us-eng done.
Yd1305161 sprawozdanie finansowe_2010_z_us-eng done.
odfoundation
 
Pagrindines unix komandos
Pagrindines unix komandosPagrindines unix komandos
Pagrindines unix komandos
Donatas Bukelis
 
Paskaita nr3 funkcijos
Paskaita nr3 funkcijosPaskaita nr3 funkcijos
Paskaita nr3 funkcijos
Donatas Bukelis
 
TechTalk#2: Принципы управления временем
TechTalk#2: Принципы управления временемTechTalk#2: Принципы управления временем
TechTalk#2: Принципы управления временем
DA-14
 
Odf report-massacre-in-odessa-pl
Odf report-massacre-in-odessa-plOdf report-massacre-in-odessa-pl
Odf report-massacre-in-odessa-plodfoundation
 
SmartSuite Webinar: Turning Data into Actionable Information
SmartSuite Webinar: Turning Data into Actionable InformationSmartSuite Webinar: Turning Data into Actionable Information
SmartSuite Webinar: Turning Data into Actionable Information
Relational Solutions a Mindtree Company
 
Top 10 tips for growing your social media following
Top 10 tips for growing your social media followingTop 10 tips for growing your social media following
Top 10 tips for growing your social media following
Debbie O'Connor
 
03.07.2014 odf oleg_sentsov_case_ua
03.07.2014 odf oleg_sentsov_case_ua03.07.2014 odf oleg_sentsov_case_ua
03.07.2014 odf oleg_sentsov_case_ua
odfoundation
 
Paskaita nr5 modeliai
Paskaita nr5 modeliaiPaskaita nr5 modeliai
Paskaita nr5 modeliai
Donatas Bukelis
 
Sprawozdanie merytoryczne 2014
Sprawozdanie merytoryczne 2014Sprawozdanie merytoryczne 2014
Sprawozdanie merytoryczne 2014
odfoundation
 
Группа компаний "Скобеев и Партнеры"
Группа компаний "Скобеев и Партнеры"Группа компаний "Скобеев и Партнеры"
Группа компаний "Скобеев и Партнеры"
Скобеев и Партнеры
 
Elektroninio pasto klientu_konfiguravimas
Elektroninio pasto klientu_konfiguravimasElektroninio pasto klientu_konfiguravimas
Elektroninio pasto klientu_konfiguravimas
Donatas Bukelis
 
Burabod
BurabodBurabod
25 08-2014-odf-report-case-of-nadezhda-savchenko-ru 1
25 08-2014-odf-report-case-of-nadezhda-savchenko-ru 125 08-2014-odf-report-case-of-nadezhda-savchenko-ru 1
25 08-2014-odf-report-case-of-nadezhda-savchenko-ru 1
odfoundation
 
Ubuntu failu share_unix_net_komandos
Ubuntu failu share_unix_net_komandosUbuntu failu share_unix_net_komandos
Ubuntu failu share_unix_net_komandos
Donatas Bukelis
 
Paskaita nr9 eksplotavimas_tti
Paskaita nr9 eksplotavimas_ttiPaskaita nr9 eksplotavimas_tti
Paskaita nr9 eksplotavimas_tti
Donatas Bukelis
 

Viewers also liked (20)

11 lecture project scheduling 3
11 lecture project scheduling 311 lecture project scheduling 3
11 lecture project scheduling 3
 
12 lecture project scheduling 4
12 lecture project scheduling 412 lecture project scheduling 4
12 lecture project scheduling 4
 
Project Management (Soft)
Project Management (Soft)Project Management (Soft)
Project Management (Soft)
 
Yd1305161 sprawozdanie finansowe_2010_z_us-eng done.
Yd1305161 sprawozdanie finansowe_2010_z_us-eng done.Yd1305161 sprawozdanie finansowe_2010_z_us-eng done.
Yd1305161 sprawozdanie finansowe_2010_z_us-eng done.
 
Pagrindines unix komandos
Pagrindines unix komandosPagrindines unix komandos
Pagrindines unix komandos
 
Paskaita nr3 funkcijos
Paskaita nr3 funkcijosPaskaita nr3 funkcijos
Paskaita nr3 funkcijos
 
TechTalk#2: Принципы управления временем
TechTalk#2: Принципы управления временемTechTalk#2: Принципы управления временем
TechTalk#2: Принципы управления временем
 
Odf report-massacre-in-odessa-pl
Odf report-massacre-in-odessa-plOdf report-massacre-in-odessa-pl
Odf report-massacre-in-odessa-pl
 
SmartSuite Webinar: Turning Data into Actionable Information
SmartSuite Webinar: Turning Data into Actionable InformationSmartSuite Webinar: Turning Data into Actionable Information
SmartSuite Webinar: Turning Data into Actionable Information
 
Top 10 tips for growing your social media following
Top 10 tips for growing your social media followingTop 10 tips for growing your social media following
Top 10 tips for growing your social media following
 
03.07.2014 odf oleg_sentsov_case_ua
03.07.2014 odf oleg_sentsov_case_ua03.07.2014 odf oleg_sentsov_case_ua
03.07.2014 odf oleg_sentsov_case_ua
 
Paskaita nr5 modeliai
Paskaita nr5 modeliaiPaskaita nr5 modeliai
Paskaita nr5 modeliai
 
Sprawozdanie merytoryczne 2014
Sprawozdanie merytoryczne 2014Sprawozdanie merytoryczne 2014
Sprawozdanie merytoryczne 2014
 
Группа компаний "Скобеев и Партнеры"
Группа компаний "Скобеев и Партнеры"Группа компаний "Скобеев и Партнеры"
Группа компаний "Скобеев и Партнеры"
 
Elektroninio pasto klientu_konfiguravimas
Elektroninio pasto klientu_konfiguravimasElektroninio pasto klientu_konfiguravimas
Elektroninio pasto klientu_konfiguravimas
 
Log book.ashx
Log book.ashxLog book.ashx
Log book.ashx
 
Burabod
BurabodBurabod
Burabod
 
25 08-2014-odf-report-case-of-nadezhda-savchenko-ru 1
25 08-2014-odf-report-case-of-nadezhda-savchenko-ru 125 08-2014-odf-report-case-of-nadezhda-savchenko-ru 1
25 08-2014-odf-report-case-of-nadezhda-savchenko-ru 1
 
Ubuntu failu share_unix_net_komandos
Ubuntu failu share_unix_net_komandosUbuntu failu share_unix_net_komandos
Ubuntu failu share_unix_net_komandos
 
Paskaita nr9 eksplotavimas_tti
Paskaita nr9 eksplotavimas_ttiPaskaita nr9 eksplotavimas_tti
Paskaita nr9 eksplotavimas_tti
 

Similar to 10 lecture project scheduling 2

09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1
Ahmad Basim Hamza
 
MBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docxMBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docx
alfredacavx97
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
Golam Bitonsir
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
Anupama holla
 
Chapter 5-Project Management.pptx
Chapter 5-Project Management.pptxChapter 5-Project Management.pptx
Chapter 5-Project Management.pptx
BahredinAbdella1
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
AMIT PAYAL
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
Golam Bitonsir
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
Golam Bitonsir
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
BetshaTizazu2
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
NaimishKishor
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
pisal3
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
SHAZEBALIKHAN1
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
dyaksa hanindito
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
S.Vijaya Bhaskar
 
Project time management
Project time managementProject time management
Project time management
Jivan Nepali
 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4
POOJA UDAYAN
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
rielaantonio
 
Chapter 4.pptx
Chapter 4.pptxChapter 4.pptx
Chapter 4.pptx
ssuser8cd298
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
TinotendaChivese
 

Similar to 10 lecture project scheduling 2 (20)

09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1
 
MBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docxMBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docx
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Network Analysis- CPM ppt..pptx
Network Analysis- CPM  ppt..pptxNetwork Analysis- CPM  ppt..pptx
Network Analysis- CPM ppt..pptx
 
Chapter 5-Project Management.pptx
Chapter 5-Project Management.pptxChapter 5-Project Management.pptx
Chapter 5-Project Management.pptx
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Project time management
Project time managementProject time management
Project time management
 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
Chapter 4.pptx
Chapter 4.pptxChapter 4.pptx
Chapter 4.pptx
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 

Recently uploaded

NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
top1002
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
veerababupersonal22
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 

Recently uploaded (20)

NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 

10 lecture project scheduling 2

  • 1. Project Scheduling 2 Prepared by Sebghatullah Karimi (Junior Lecturer of Kabul Polytechnic University) 1392 Kardan University Civil Engineering Faculty
  • 2. Explain how the work environment, the construction contract, and the project scope influence the scheduling process. Explain the three types of project activities used in scheduling. Define milestone. Describe the characteristics of a network diagram. 2
  • 3. Work breakdown structure – The organization of the project into specific parts that can be coordinated and controlled. Activity – A well-defined, measurable part of the overall project. An activity must be suitable for assignment to a particular project team member, and it consumes both time and resources. Trade – A construction specialty, such as plumber, carpenter, welder. Submittal – A sample of an item to be procured for a project by a supplier or subcontractor. A submittal must be approved by the owner or designer prior to procurement. 3
  • 4. • A network schedule is graphical drawing of a logical sequence of events to complete a project. A network-based schedule is a powerful tool for the planning, development, and construction of sophisticated projects. • The development of a network-based schedule follows a logical process that should involve most of the key project team members. Every network schedule must begin with a complete understanding of the project objective, as defined by the owner. The project participants then take this objective and break it down into tasks that provide the level of detail necessary to organize, manage, and control the project. Once these tasks are defined, the project team establishes the order in which the tasks are to be performed, such that the project will be completed in an efficient manner. • To create the network, team members decide which activities must precede, succeed, or run concurrently with other activities. The end result of this process is a logic diagram that accurately depicts the order that the work will follow. 4
  • 5. The preparation of a network schedule requires a careful analysis of three factors: The work environment. The work environment includes such consideration as the weather, site conditions, availability of building materials, access for deliveries, availability of power, and the amount of construction currently occurring in the region. The contract. A construction contract will typically include the project completion date, milestones, incentive clauses (which provide bonuses for early completion), liquidated damages clauses (which provide penalties for late completion), work rules governing safety and hiring requirements, and identification of materials and work that will be provided by the owner. All of these considerations will affect project organization and scheduling. The project scope. The scope of the project, as described in the drawings and specifications, is a major consideration in scheduling. Drawings and specifications are the source of all the materials and quantities used in the project and may also describe required construction methods. 5
  • 6. 1. The first step in the networking process is to define the work breakdown structure for the project. 2. From the work breakdown structure, the team defines the specific activities that will make up the network diagram. An activity must be suitable for assignment to a particular project team member, and it should consume both time and resources. 6
  • 7. Construction activities can generally be characterized as one of three types: Production activities are the activities that define the actual physical construction of the project. Examples include Erect Concrete Wall. A well-developed schedule allows the project team to separate all activities of each trade in such a way that each contractor has a clearly defined scope of work without overlap or omission. Procurement activities involve the purchase of materials, equipment, and services for the project. Most procurement activities follow a logical sequence, beginning with the preparation of a submittal, the approval of the submittal by the owner or designer, the ordering and fabrication of the item, and then the delivery of the item to the job site.. Administrative activities include required inspections by local officials or regulatory agencies, as well as permitting. Identifying these activities requires the involvement of all project team members, since normally no one person knows all the administrative requirements for a complex project. 7
  • 8. A key event in a project schedule can be identified by the use of a milestone. Examples of milestones include the planned shutdown of electricity or water supply in order to make connections to existing utilities, the delivery of a certain phase of a project to the owner, or a city agreement that a road be opened by a specific date. Unlike an activity, a milestone cannot be assigned to a company or person and does not consume time or resources. A milestone is used simply to signify an important point in the life of a project. 8
  • 9. A network diagram is a pictorial representation of all activities that make up a project and the order in which these activities must occur to complete the project in an efficient manner. In order to develop the network diagram, the scheduler must answer the following questions for each activity: 9
  • 10. What activities must occur before this activity can be done? What activities must follow this activity? What activities can be accomplished at the same time that this activity is occurring? 10
  • 11. A typical example of a network diagram is shown at the top of Figure 9.4 in the Gould textbook. As you can see: The diagram is read from left to right. Activities are identified by rectangles (nodes) and connected by arrows. Each rectangle indicates a single activity. The network is continuous. Each activity, except the first and last, has both preceding and succeeding activities. Activities without predecessors are assumed to begin at the start of the project. Activities without successors are assumed to be complete when the project finishes. No activity can start until all preceding activities have been completed. 11
  • 12. 12
  • 13. 13