SlideShare a Scribd company logo
Pile Load Test Method
PILE LOADING TEST METHOD
PROPOSED FOR :
PLTG MUARA TAWAR
PT.BERDIKARI PONDASI PERKASA
Foundation and Ground Improvement Specialist
Jl. Tubagus Angke 99, Jakarta Barat
Phone : 021-5662756-57 Fax: 021-5663058
Email : mahmud.bpp@gmail.com Web:Http:www.ptbppid.com
PT BERDIKARI PONDASI PERKASA Page 1
Pile Load Test Method
GEOTECH GEOTECH GEOTECH GEOTECH GEOTECH GEOTECH GEOTECH GEOTECH GEOTECH GEOTECH GEOTECH GEOTECH GEOTECH GEOTECH GEOTECH GEOTECH GEOTECH GEOTECH GEOTECH GEOTECH GEOTECH GEOTECH GE
I. INTRODUCTION
Proposed PLTG Muara Tawar Project located at North Jakarta is going to build in this
project. The load test are planned to be conducted at the site.
Type of Pile :
• Circular hollow pre-stressed concrete pile Dia. 600 mm
• Circular hollow pre-stressed concrete pile Dia. 500 mm
II. PILE TESTING METHOD
2.1. Static Vertical Compression Load Test
The single static vertical compression load test will conduct on site based on 200% of
working load with reading procedure presented in Appendix A.
The test will conduct by kentledge system, where the applied load on test pile will
produce by kentledge load (concrete blocks) connected with beam reaction frame. Load
will apply using hydraulic jack controlled by pressure gauge. In order to make sure the
load applied with minor eccentricity, on top of every hydraulic jack will provide by
spherical bearing plate. The static vertical loading test will be performed based on ASTM
D 1143 – 07. The purpose of pile test is to verifying the ultimate axial bearing capacity
and settlement under compression test.
Four dial gauges were installed to measure the total settlement at pile top under specified
test loads, as well as two additional dial gauges to measure the lateral movements for
compression test. Two dial gauges will be installed at each reaction pile with accuracy of
the dial gauges were +/- 0.01 millimeters.
2.2. Static Vertical Tensile Loading Test
The single static vertical tensile load test will conduct on site based on 200% of working
load with reading procedure presented in Appendix B. The test will conduct by reaction
system, where the applied load on test pile will produce by hydraulic pressure from jack
connected with beam reaction frame. Cyclic load will apply using hydraulic jack
controlled by pressure gauge. In order to make sure the load applied with minor
PT BERDIKARI PONDASI PERKASA Page 2
Pile Load Test Method
eccentricity, on top of every hydraulic jack will provide by spherical bearing. All of
equipment used in this pile testing program will provide by contractors and check before
pile test begin. The static tension test will conduct base on ASTM D 3689 – 07.
Four dial gauges were installed to measure the total movement at pile top under specified
test loads. The accuracy of the dial gauges were ± 0.01 millimeters.
2.3. Static Horizontal Load Test
The single static horizontal load test will conduct on site based on 200% of working load
with reading procedure presented in Appendix C. The test will conduct by pile-to-pile
system, where the applied load on test pile will produce by reaction between two pile
connected with a follower beam. Cyclic load will apply using hydraulic jack controlled by
pressure gauge. In order to make sure the load applied with minor eccentricity, on top of
every hydraulic jack will provide by spherical bearing. The static horizontal loading test
will conduct base on ASTM D3966-07. The purpose of pile test is to verifying the
displacement under lateral test.
Two dial gauges were installed to measure the total displacement at each pile top under
specified test loads. The accuracy of the dial gauges were ± 0.01 millimeters.
Jakarta, 02 June 2017
PT Berdikari Pondasi Perkasa
Ir. Mahmud
Project Manager
PT BERDIKARI PONDASI PERKASA Page 3
Pile Load Test Method
H
GEOTEH GE
TEST BEAM
TEST PILE
FRONT VIEW
CONCRETE BLOCK 194 PCS @2.45 TON
TOTAL WEIGHT = 475 TON
FOOTING
FRAME
CROSS BEAM 500X200X16X10 mm
LOAD CELL
FIGURE-1
SCHEMATIC OF STATIC COMPRESSION LOAD TEST KENTLEDGE SYSTEMENTLEDGE
BY KENTEEOTECH GEOTECH GEOTECH GEOTECH GEOTECH GEOTECHGEOTECH GEOTECH GEOTECH
TECH
PT BERDIKARI PONDASI PERKASA Page 4
Pile Load Test Method
FIGURE-2
SCHEMATIC OF STATIC VERTICAL TENSION LOAD TESTGEO
FIGURE-3
SCHEMATIC OF STATIC HORIZONTAL LOAD TEST
PT BERDIKARI PONDASI PERKASA Page 5
Pile Load Test Method
APPENDIX –A
READING PROCEDURE
AXIAL COMPRESSIVE LOADING TEST
300% Load
PT BERDIKARI PONDASI PERKASA Page 6
Pile Load Test Method
STEP CYCLE
%OF DESIGN
HOLDING TIME LOADING INTERVAL IN MINUTES
LOAD
1 0 0 0
2 1 25 "A" 0-10-20-30-40-50-60 (max 2 hours)
3 1 50 1 hour 0-10-20-30-40-50-60
4 1 25 20 minutes 0-10-20
5 2 0 1 hour 0-10-20-30-40-50-60
6 2 50 20 minutes 0-10-20
7 2 75 "A" 0-10-20-30-40-50-60 (max 2 hours)
8 2 100 1 hour 0-10-20-30-40-50-60
9 2 75 20 minutes 0-10-20
10 2 50 20 minutes 0-10-20
11 2 0 1 hour 0-10-20-30-40-50-60
12 3 50 20 minutes 0-10-20
13 3 100 20 minutes 0-10-20
14 3 125 "A" 0-10-20-30-40-50-60 (max 2 hours)
15 3 150 1 hour 0-10-20-30-40-50-60
16 3 125 20 minutes 0-10-20
17 3 100 20 minutes 0-10-20
18 3 50 20 minutes 0-10-20
19 3 0 1 hour 0-10-20-30-40-50-60
20 4 50 20 minutes 0-10-20
21 4 100 20 minutes 0-10-20
22 4 150 20 minutes 0-10-20
23 4 175 "A" 0-10-20-30-40-50-60 (max 2 hours)
24 4 200 1 hour 0-10-20-30-40-50-60
25 4 150 20 minutes 0-10-20
26 4 100 20 minutes 0-10-20
27 4 50 20 minutes 0-10-20
28 4 0 1 hour 0-10-20-30-40-50-60
29 5 50 20 minutes 0-10-20
30 5 100 20 minutes 0-10-20
31 5 150 20 minutes 0-10-20
32 5 200 20 minutes 0-10-20
33 5 225 "A" 0-10-20-30-40-50-60 (max 2 hours)
34 5 250 1 hour 0-10-20-30-40-50-60
35 5 200 20 minutes 0-10-20
36 5 150 20 minutes 0-10-20
37 5 100 20 minutes 0-10-20
38 5 50 20 minutes 0-10-20
39 6 0 1 hour 0-10-20-30-40-50-60
40 6 50 20 minutes 0-10-20
41 6 100 20 minutes 0-10-20
42 6 125 20 minutes 0-10-20
43 6 150 20 minutes 0-10-20
44 6 175 20 minutes 0-10-20
45 6 200 20 minutes 0-10-20
46 6 250 20 minutes 0-10-20
47 6 275 "A" 0-10-20-30-40-50-60 (max 2 hours)
48 6 300 "B" 0-10-20-30-40-50-60 (for 4 hours)
and every 1 hour until 12 hours. (Max. 24 hour)
49 6 250 1 hour 0-10-20-30-40-50-60
50 6 200 1 hour 0-10-20-30-40-50-60
51 6 150 1 hour 0-10-20-30-40-50-60
52 6 100 1 hour 0-10-20-30-40-50-60
53 6 50 1 hour 0-10-20-30-40-50-60
54 6 0 12 hours 0-10-20-30-40-50-60 (for 4 hours)
and every 1 hour until 12 hours.
NOTE:
"A" Load is maintained for 1 hour or until settlement is not greater than 0.25 mm/hr with max 2 hours.
"B" Load is maintained for 12 hours or until settlement is not greater than 0.25 mm/hr with max 24 hours
PT BERDIKARI PONDASI PERKASA Page 7
Pile Load Test Method
APPENDIX –B
READING PROCEDURE
STATIC VERTICAL TENSION LOADING TEST
200% Load
PT BERDIKARI PONDASI PERKASA Page 8
Pile Load Test Method
STEP CYCLE %OF DESIGN HOLDING TIME LOADING INTERVAL IN MINUTES
LOAD
1 0 0 0 0
2 1 25 "A" 0-10-20-30-40-50-60 (max 2 hours)
3 1 50 1 hour 0-10-20-30-40-50-60
4 1 25 20 minutes 0-10-20
5 2 0 1 hour 0-10-20-30-40-50-60
6 2 50 20 minutes 0-10-20
7 2 75 "A" 0-10-20-30-40-50-60 (max 2 hours)
8 2 100 1 hour 0-10-20-30-40-50-60
9 2 75 20 minutes 0-10-20
10 2 50 20 minutes 0-10-20
11 2 0 1 hour 0-10-20-30-40-50-60
12 3 50 20 minutes 0-10-20
13 3 100 20 minutes 0-10-20
14 3 125 "A" 0-10-20-30-40-50-60 (max 2 hours)
15 3 150 1 hour 0-10-20-30-40-50-60
16 3 125 20 minutes 0-10-20
17 3 100 20 minutes 0-10-20
18 3 50 20 minutes 0-10-20
19 3 0 1 hour 0-10-20-30-40-50-60
20 4 50 20 minutes 0-10-20
21 4 100 20 minutes 0-10-20
22 4 150 20 minutes 0-10-20
23 4 175 "A" 0-10-20-30-40-50-60 (max 2 hours)
24 4 200 "B" 0-10-20-30-40-50-60 (for 4 hours)
and every 1 hour until 12 hours.
(Max. 24 hour)
25 4 150 1 hour 0-10-20-30-40-50-60
26 4 100 1 hour 0-10-20-30-40-50-60
27 4 50 1 hour 0-10-20-30-40-50-60
28 4 0 12 hours 0-10-20-30-40-50-60 (for 4 hours)
and every 1 hour until 12 hours.
NOTE:
"A" Load is maintained for 1 hour or until settlement is not greater than 0.25 mm/hr with max 2 hours.
"B" Load is maintained for 12 hours or until settlement is not greater than 0.25 mm/hr with max 24 hours
PT BERDIKARI PONDASI PERKASA Page 9
Pile Load Test Method
APPENDIX –C
READING PROCEDURE
STATIC HORIZONTAL LOADING TEST
PT BERDIKARI PONDASI PERKASA Page 10
Pile Load Test Method
READING PROCEDURE FOR HORIZONTAL TEST
STEP CYCLE %OF DESIGN HOLDING
LOADING INTERVAL IN
MINUTES
LOAD TIME
1 0 0 0 0
2 1 25 15 minutes 0-1-2-5-10-15
3 1 50 20 minutes 0-1-2-5-10-15-20
4 1 25 10 minutes 0-1-2-5-10
5 2 0 10 minutes 0-1-2-5-10
6 2 50 10 minutes 0-1-2-5-10
7 2 75 15 minutes 0-1-2-5-10-15
8 2 100 20 minutes 0-1-2-5-10-15-20
9 2 75 10 minutes 0-1-2-5-10
10 3 50 10 minutes 0-1-2-5-10
11 3 0 10 minutes 0-1-2-5-10
12 3 50 10 minutes 0-1-2-5-10
13 3 100 15 minutes 0-1-2-5-10-15
14 3 125 20 minutes 0-1-2-5-10-15-20
15 3 150 10 minutes 0-1-2-5-10
16 4 125 10 minutes 0-1-2-5-10
17 4 100 10 minutes 0-1-2-5-10
18 4 50 10 minutes 0-1-2-5-10
19 4 0 10 minutes 0-1-2-5-10
20 4 50 20 minutes 0-1-2-5-10-15-20
21 4 100 20 minutes 0-1-2-5-10-15-20
22 4 150 20 minutes 0-1-2-5-10-15-20
23 4 175 60 minutes 0-1-2-5-10-15-20-30-40-50-60
24 4 200 60 minutes 0-1-2-5-10-15-20-30-40-50-60
25 4 10 minutes 0-1-2-5-10
26 4 150 10 minutes 0-1-2-5-10
27 4 100 10 minutes 0-1-2-5-10
28 4 50 30 minutes 0-1-2-5-10-15-20-30
PT BERDIKARI PONDASI PERKASA Page 11
Pile Load Test Method
RECORDING FORM
PT BERDIKARI PONDASI PERKASA Page 12
Page : Of
Project : No. Pile :
Location : Depth :
Pile Dia : mm Capacity :
Time Interval Ton Kg/cm² Dial 1 Dial 2 Dial 3 Dial 4 Dial x
PILE LOAD TEST RECORD
- COMPRESSION -
Date
Time Load
( ………………. )
Lateral
Dial y
Remark
Prepared /Checked By : Reviewed/Acknowledged By :
( ………………. )
Settlement (Test Pile)
Average
Reviewed/Witnessed :
( ………………. )
Page : Of
Project : No. Pile :
Location : Depth :
Pile Dia : mm Capacity :
Time Interval Ton Kg/cm² Dial 1 Dial 2 Dial 3 Dial 4 Dial x
( ………………. ) ( ………………. ) ( ………………. )
Prepared /Checked By : Reviewed/Witnessed : Reviewed/Acknowledged By :
PILE LOAD TEST RECORD
-TENSILE -
Date
Time Load Uplift (Test Pile)
Average
Lateral
Remark
Dial y
Page : Of
Project : No. Pile :
Location : Depth:
Pile Dia : mm Capacity :
Time Interval Ton Kg/cm² Dial 1 Dial 2
Reviewed/Witnessed : Reviewed/Acknowledged By :
( ………………. ) ( ………………. )( ………………. )
Prepared /Checked By :
PILE LOAD TEST RECORD
- HORIZONTAL -
Date
Time Load Displacement (Test Pile)
Average Remark
Pile Load Test Method
DIAL GAUGE SPECIFICATION
PT BERDIKARI PONDASI PERKASA Page 13
196
DIALINDICATORS
5
M2.5x0.45
16
ø78C
BA
D
ø6.5
9
E 21
Unit: mm
Unit: mm
ø8
5
M2.5x0.45
16
Ø78C
BA
D
Ø6.5
9
E 21
Ø8
0
-0.009
0
-0.009
Dial Indicators
SERIES 3
Mitutoyo's Series 3 dial indicators are recommended for larger
gaging distance or those applications where a larger dial face is
required for improved dial visibility and readability. They offer
excellent accuracy and repeatability over longer measuring
distances for operations such as turning and drilling.
Dimensions
3109F
3058F
ISO/JIS
Type
ISO/JIS
Type
Order No. A B C D E
3046F 56 75.5 15.5 21 16.5
3047F 56 75.5 15.5 21 16.5
3109F 56 79 25 15 17
Order No. A B C D E
3050F 49 93 25 29 16.5
3052F 73 104 25 40 17
3058F 82 142 43 60 17
3060F 112 203 73 91 17
3062F 132 243 94 110 17
Note 1: Dimensions of the inch (ANSI/
AGD Type) dial indicator partly
differ from those of the metric
(ISO/JIS Type) indicator.
Note 2: Inch (ANSI/AGD Type) dial
indicator is provided with a
stem of 3/8" dia. and #4-
48UNF thread mount for the
contact point.
Note 1: Dimensions of the inch (ANSI/
AGD Type) dial indicator partly
differ from those of the metric
(ISO/JIS Type) indicator.
Note 2: Inch (ANSI/AGD Type) dial
indicator is provided with a
stem of 3/8" dia. and #4-
48UNF thread mount for the
contact point.
High Precision Type Reverse Reading Balanced Dial Continuous Dial One Revolution
Shockproof
Peak Retaining Long Stem Dustproof Low Force
Adjustable Hand
JeweledCoaxial Revolution Counter
Water resistance Doubled Scale SpacingDamper at Lowest Rest Point
197
DIALINDICATORS
Inch ANSI/AGD
Graduation Range Order No. Order No. Range per Dial Accuracy Measuring Remarks
Lug-Back Flat-back revolution reading force
.001" .125" 3780 — .05" 0-50 ±.001" 1.5N or less
3781 — .05" 0-25-0 ±.001" 1.5N or less
.25" 3410 3410B .1" 0-100 ±.001" 1.5N or less
3411 3411B .1" 0-50-0 ±.001" 1.5N or less
.4" 3412 3412B .1" 0-100 ±.001" 1.5N or less
3413 3413B .1" 0-50-0 ±.001" 1.5N or less
1" 3416 3416B .1" 0-100 ±.002" 2.0N or less
3417 3417B .1" 0-50-0 ±.002" 2.0N or less
2" 3424-10 3424B-10 .1" 0-100 (100-0) ±.003" 2.5N or less
3" 3426-10 3426B-10 .1" 0-100 (100-0) ±.005" 3.0N or less
4" 3428-10 3428B-10 .1" 0-100 (100-0) ±.005" 4.0N or less
.0005" .075" 3570 — .03" 0-30 ±.0005" 1.5N or less
3571 — .03" 0-15-0 ±.0005" 1.5N or less
.0001" .025" 3802-10 — .01" 0-10 ±.0002" 1.5N or less
3803-10 — .01" 0-5-0 ±.0002" 1.5N or less
SPECIFICATIONS
Metric ISO/JIS
Graduation Range Order No. Order No. Range per Dial Accuracy Measuring Remarks
Lug-Back Flat-back revolution reading force
0.01mm 10mm 3046F 3046FB 1mm 0-100 (100-0) ±15µm 1.4N or less
3047F 3047FB 1mm 0-50-0 ±15µm 1.4N or less
20mm 3050F 3050FB 1mm 0-100 (100-0) ±20µm 2.0N or less
30mm 3052F 3052FB 1mm 0-100 (100-0) ±25µm 2.5N or less
50mm 3058F* 3058FB* 1mm 0-100 (100-0) ±35µm 3.0N or less
80mm 3060F* 3060FB* 1mm 0-100 (100-0) ±45µm 3.0N or less
100mm 3062F* 3062FB* 1mm 0-100 (100-0) ±50µm 3.2N or less
0.001mm 1mm 3109F 3109FB 0.2mm 0-100-0 ±6µm 1.5N or less
*Use the gage in a vertical position only.
3046F
3058F
3047F
3060F
3050F 3052F
3109F3062F
High Precision Type Reverse Reading Balanced Dial Continuous Dial One Revolution
Shockproof
Peak Retaining Long Stem Dustproof Low Force
Adjustable Hand
JeweledCoaxial Revolution Counter
Water resistance Doubled Scale SpacingDamper at Lowest Rest Point
Pile Load Test Method
HYDRAULIC JACK SPECIFICATION
PT BERDIKARI PONDASI PERKASA Page 14
4444

	 	 47
	 	 134
	 	 84
CLRG-Series, High Tonnage Cylinders
	 Shown from left to right: CLRG-506, CLRG-5006, CLRG-4006
 The dismantling of the temporary support towers of Beijing’s “Bird’s Nest”.
During the stage lowering process the bird’s nest is alternatively supported
by CLRG-Series cylinders.
Double-Acting
Power Lifters
•	 Double-acting, for positive retraction
•	 Integral stop ring provides piston blow-out protection
•	 Safety valve in retract side of cylinder helps to prevent
damage in case of accidental over-pressurization
•	 Plunger wiper reduces contamination, extending
cylinder life
•	 CR-400 coupler and dust cap included on all models
•	 Baked enamel finish and plated pistons provide
superior corrosion resistance.
 Replacing adjustment rolls under a fly-over
with CLRG cylinders, for controlled lifting
and lowering.
Saddles
All CLRG cylinders are
equipped with bolt-on
removable grooved saddles.
For information on optional
tilt saddles, see selection chart.
	 Page:	
Safety Device
A pilot-operated check
valve (V-42) can be inserted
between cylinder and pump.
This valve provides a safety
lock on the cylinder under load at any
position and remote control for
unlocking.
	 Page:	
Standard Features
•	 Interchangeable, hardened
grooved saddles
•	Top and side mounted lifting eyes
•	CR-400 coupler and dustcap
•	All cylinders meet ASME B-30.1 and
ISO 10100 standards.
Optimum Performance
Enerpac’s range of
ZU4-Series electric pumps,
fitted with manual or
solenoid operated 4-way
valves, offer optimum combinations
with CLRG cylinders.
	 Page:
45www.enerpac.com 45www.enerpac.com
CLRG-502
CLRG-504
CLRG-506
CLRG-508
CLRG-5010
CLRG-5012
CLRG-1002
CLRG-1004
CLRG-1006
CLRG-1008
CLRG-10010
CLRG-10012
CLRG-1502
CLRG-1504
CLRG-1506
CLRG-1508
CLRG-15010
CLRG-15012
CLRG-2002
CLRG-2006
CLRG-20012
CLRG-2502
CLRG-2506
CLRG-25012
CLRG-3002
CLRG-3006
CLRG-30012
CLRG-4002
CLRG-4006
CLRG-40012
CLRG-5002
CLRG-5006
CLRG-50012
CLRG-6002
CLRG-6006
CLRG-60012
CLRG-8002
CLRG-8006
CLRG-80012
CLRG-10002
CLRG-10006
CLRG-100012
77,0
77,0
77,0
77,0
77,0
77,0
132,7
132,7
132,7
132,7
132,7
132,7
198,6
198,6
198,6
198,6
198,6
198,6
265,9
265,9
265,9
366,4
366,4
366,4
456,2
456,2
456,2
559,9
559,9
559,9
730,6
730,6
730,6
855,3
855,3
855,3
1176,3
1176,3
1176,3
1465,7
1465,7
1465,7
50
100
150
200
250
300
50
100
150
200
250
300
50
100
150
200
250
300
50
150
300
50
150
300
50
150
300
50
150
300
50
150
300
50
150
300
50
150
300
50
150
300
38,5
38,5
38,5
38,5
38,5
38,5
61,9
61,9
61,9
61,9
61,9
61,9
96,5
96,5
96,5
96,5
96,5
96,5
127,0
127,0
127,0
152,6
152,6
152,6
151,4
151,4
151,4
193,5
193,5
193,5
247,6
247,6
247,6
295,4
295,4
295,4
387,0
387,0
387,0
541,7
541,7
541,7
385
770
1155
1540
1924
2309
664
1327
1991
2655
3318
3982
993
1986
2978
3971
4964
5957
1330
3989
7977
1832
5497
10993
2281
6843
13685
2800
8399
16797
3653
10959
21918
4276
12829
25659
5881
17644
35288
7329
21986
43972
192
385
577
770
962
1155
309
619
928
1237
1546
1856
482
965
1447
1930
2412
2895
635
1905
3809
763
2289
4578
757
2270
4541
967
2902
5804
1238
3713
7427
1477
4431
8862
1935
5806
11611
2709
8126
16252
162
212
262
312
362
412
179
229
279
329
379
429
196
246
296
346
396
446
212
312
462
235
335
485
322
422
572
374
474
624
419
519
669
429
529
679
484
584
734
564
664
814
50
(539)
100
(929)
150
(1390)
200
(1861)
250
(2565)
300
(3193)
400
(3919)
500
(5114)
600
(5987)
800
(8234)
1000
(10260)
	 	 84
	 	 32
Double-Acting, High Tonnage Cylinders
Stroke
(mm)
Cylinder
Capacity
ton
(kN)
Cylinder
Effective Area
(cm2
)
Oil
Capacity
(cm3
)
Model
Number
Push Pull Push Pull
Collapsed
Height
(mm)
CLRG
Series
Capacity:
50 - 1000 ton
Stroke:
50 - 300 mm
Maximum Operating Pressure:
700 bar
RR-series
For higher cycle applications
Enerpac RR-Series cylinders
are a good alternative.
Page:
 QUICK SELECTION CHART
For complete technical information see next page.
Higher Capacities
1500 and 2000 ton models are
available on request.
Additional Stroke Lengths
Models above 150 ton are also available
with standard stroke lengths of 100, 200
and 250 mm. Please contact Enerpac for
ordering information.
Pump Selection
A double-acting cylinder
must be powered by a pump
with a 4-way valve.
	 Page:	
Optional features
To add optional features
to your cylinders, add the
following suffixes to the end
of the model number.
	 Collar thread *	 E002
	 Plunger thread	 E003
	 Collar * and plunger thread	 E005
* On 400 ton and higher
Example:
•	For CLRG-5006 cylinder with collar
thread, order: CLRG-5006E002
Technical specifications for these
features are available from Enerpac.
4646
CLRG-502
CLRG-504
CLRG-506
CLRG-508
CLRG-5010
CLRG-5012
CLRG-1002
CLRG-1004
CLRG-1006
CLRG-1008
CLRG-10010
CLRG-10012
CLRG-1502
CLRG-1504
CLRG-1506
CLRG-1508
CLRG-15010
CLRG-15012
CLRG-2002
CLRG-2006
CLRG-20012
CLRG-2502
CLRG-2506
CLRG-25012
CLRG-3002
CLRG-3006
CLRG-30012
CLRG-4002
CLRG-4006
CLRG-40012
CLRG-5002
CLRG-5006
CLRG-50012
CLRG-6002
CLRG-6006
CLRG-60012
CLRG-8002
CLRG-8006
CLRG-80012
CLRG-10002
CLRG-10006
CLRG-100012
50
100
150
200
250
300
400
500
600
800
1000
50
100
150
200
250
300
50
100
150
200
250
300
50
100
150
200
250
300
50
150
300
50
150
300
50
150
300
50
150
300
50
150
300
50
150
300
50
150
300
50
150
300
77,0
77,0
77,0
77,0
77,0
77,0
132,7
132,7
132,7
132,7
132,7
132,7
198,6
198,6
198,6
198,6
198,6
198,6
265,9
265,9
265,9
366,4
366,4
366,4
456,2
456,2
456,2
559,9
559,9
559,9
730,6
730,6
730,6
855,3
855,3
855,3
1176,3
1176,3
1176,3
1465,7
1465,7
1465,7
539
539
539
539
539
539
929
929
929
929
929
929
1390
1390
1390
1390
1390
1390
1861
1861
1861
2565
2565
2565
3193
3193
3193
3919
3919
3919
5114
5114
5114
5987
5987
5987
8234
8234
8234
10260
10260
10260
269
269
269
269
269
269
433
433
433
433
433
433
675
675
675
675
675
675
889
889
889
1068
1068
1068
1060
1060
1060
1354
1354
1354
1733
1733
1733
2068
2068
2068
2709
2709
2709
3792
3792
3792
38,5
38,5
38,5
38,5
38,5
38,5
61,9
61,9
61,9
61,9
61,9
61,9
96,5
96,5
96,5
96,5
96,5
96,5
127,0
127,0
127,0
152,6
152,6
152,6
151,4
151,4
151,4
193,5
193,5
193,5
247,6
247,6
247,6
295,4
295,4
295,4
387,0
387,0
387,0
541,7
541,7
541,7
385
770
1155
1540
1924
2309
664
1327
1991
2655
3318
3982
993
1986
2978
3971
4964
5957
1330
3989
7977
1832
5497
10993
2281
6843
13685
2800
8399
16797
3653
10959
21918
4276
12829
25659
5881
17644
35288
7329
21986
43972
192
385
577
770
962
1155
309
619
928
1237
1546
1856
482
965
1447
1930
2412
2895
635
1905
3809
763
2289
4578
757
2270
4541
967
2902
5804
1238
3713
7427
1477
4431
8862
1935
5806
11611
2709
8126
16252
CLRG-50
CLRG-100
CLRG-150
CLRG-200
CLRG-250
CLRG-300
CLRG-400
CLRG-500
CLRG-600
CLRG-800
CLRG-1000
65
95
130
165
190
180
205
250
275
330
375
2x M12
2x M12
2x M12
3x M12
3x M12
3x M16
3x M16
3x M24
3x M24
3x M24
3x M24
22
22
22
22
22
30
30
36
36
36
36
CLRG-502 - CLRG-15012
CLRG-2002 - CLRG-100012
CLRG-Series, High Tonnage Cylinders
Stroke
(mm)
Cylinder
Capacity
(ton)
Cylinder
Effective
Area
(cm2
)
Maximum
Cylinder
Capacity
(kN)
Model
Number
Oil
Capacity
(cm3
)
 For full features see previous page.
Push Pull Push Pull Push Pull
Model /
Capacity
ton
Base Mounting Hole 1)
Dimensions (mm)
Bolt
Circle
U
Thread
Size
V
Min. Thread
Depth
Z
1)
	 Base mounting holes are random positioned in
regard to coupler position.
Mounting Hole Orientation
Top mounting hole orientation is maintained to
port location. Base mounting hole orientation
is not maintained to port location.
47www.enerpac.com 47www.enerpac.com
CLRG-502
CLRG-504
CLRG-506
CLRG-508
CLRG-5010
CLRG-5012
CLRG-1002
CLRG-1004
CLRG-1006
CLRG-1008
CLRG-10010
CLRG-10012
CLRG-1502
CLRG-1504
CLRG-1506
CLRG-1508
CLRG-15010
CLRG-15012
CLRG-2002
CLRG-2006
CLRG-20012
CLRG-2502
CLRG-2506
CLRG-25012
CLRG-3002
CLRG-3006
CLRG-30012
CLRG-4002
CLRG-4006
CLRG-40012
CLRG-5002
CLRG-5006
CLRG-50012
CLRG-6002
CLRG-6006
CLRG-60012
CLRG-8002
CLRG-8006
CLRG-80012
CLRG-10002
CLRG-10006
CLRG-100012
CATG-50
CATG-50
CATG-50
CATG-50
CATG-50
CATG-50
CATG-100
CATG-100
CATG-100
CATG-100
CATG-100
CATG-100
CATG-150
CATG-150
CATG-150
CATG-150
CATG-150
CATG-150
CATG-200
CATG-200
CATG-200
CATG-250
CATG-250
CATG-250
CATG-300
CATG-300
CATG-300
CATG-400
CATG-400
CATG-400
CATG-500
CATG-500
CATG-500
CATG-600
CATG-600
CATG-600
CATG-800
CATG-800
CATG-800
CATG-1000
CATG-1000
CATG-1000
24
24
24
24
24
24
29
29
29
29
29
29
31
31
31
31
31
31
35
35
35
46
46
46
62
62
62
51
51
51
63
63
63
76
76
76
75
75
75
93
93
93
50
50
50
50
50
50
73
73
73
73
73
73
91
91
91
91
91
91
118
118
118
144
144
144
160
160
160
193
193
193
228
228
228
241
241
241
287
287
287
311
311
311
17
20
23
27
31
34
29
34
40
46
52
58
39
52
65
78
92
105
55
91
146
89
136
207
184
232
303
270
330
421
401
480
599
474
565
701
741
868
1058
1062
1213
1439
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
24
24
24
24
24
24
19
19
19
27
27
27
27
27
27
27
27
27
27
27
27
27
27
27
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
50
50
50
50
50
50
75
75
75
75
75
75
94
94
94
94
94
94
113
113
113
145
145
145
177
177
177
196
196
196
228
228
228
247
247
247
297
297
297
323
323
323
33
33
33
33
33
33
48
48
48
48
48
48
56
56
56
56
56
56
66
66
66
78
78
78
75
75
75
105
105
105
135
135
135
135
135
135
135
135
135
170
170
170
52
52
52
52
52
52
54
54
54
54
54
54
61
61
61
61
61
61
67
67
67
73
73
73
101
101
101
114
114
114
114
114
114
114
114
114
149
149
149
174
174
174
70
70
70
70
70
70
95
95
95
95
95
95
114
114
114
114
114
114
133
133
133
165
165
165
197
197
197
216
216
216
248
248
248
267
267
267
317
317
317
343
343
343
99
99
99
99
99
99
130
130
130
130
130
130
159
159
159
159
159
159
184
184
184
216
216
216
241
241
241
267
267
267
305
305
305
330
330
330
387
387
387
432
432
432
130
130
130
130
130
130
165
165
165
165
165
165
205
205
205
205
205
205
235
235
235
275
275
275
310
310
310
350
350
350
400
400
400
430
430
430
505
505
505
560
560
560
212
312
412
512
612
712
229
329
429
529
629
729
246
346
446
546
646
746
262
462
762
285
485
785
372
572
872
424
624
924
469
669
969
479
679
979
534
734
1034
614
814
1114
162
212
262
312
362
412
179
229
279
329
379
429
196
246
296
346
396
446
212
312
462
235
335
485
322
422
572
374
474
624
419
519
669
429
529
679
484
584
734
564
664
814
Double-Acting, High Tonnage Cylinders
Model
Number
(kg)
Extend.
Height
B
(mm)
Cyl.
Bore
Dia.
E
(mm)
Plunger
Dia.
F
(mm)
Base to
Advance
Port
H
(mm)
Collaps.
Height
A
(mm)
Outside
Dia.
D
(mm)
Optional Tilt Saddle *Saddle
Protr.
from Plgr.
K
(mm)
Standard
Saddle
Dia.
J
(mm)
Saddle
Height
K1
(mm)
Saddle
Model
Number
Top to
Retract
Port
I
(mm)
Saddle
Dia.
J1
(mm)
Depth of
Plunger
Hole
L
(mm)
* Optional Tilt Saddle
CLRG
Series
Capacity:
50 - 1000 ton
Stroke:
50 - 300 mm
Maximum Operating Pressure:
700 bar

More Related Content

Similar to 1. metode loading test muara tawar (bpp)

final Presentation1680
final Presentation1680final Presentation1680
final Presentation1680Reda Matoug
 
Mikazuki Slide.pptx
Mikazuki Slide.pptxMikazuki Slide.pptx
Mikazuki Slide.pptx
Viet Anh Nguyen
 
CE Confr Presentation 08 Oct 2022.pptx
CE Confr Presentation 08 Oct 2022.pptxCE Confr Presentation 08 Oct 2022.pptx
CE Confr Presentation 08 Oct 2022.pptx
SaketChandra4
 
Ass 1 12-46 report engineering dynamics problem
Ass 1  12-46 report engineering dynamics problemAss 1  12-46 report engineering dynamics problem
Ass 1 12-46 report engineering dynamics problem
Hammad ur Rehman
 
Performance investigation of conventional heat pipe with hydrocarbon as worki...
Performance investigation of conventional heat pipe with hydrocarbon as worki...Performance investigation of conventional heat pipe with hydrocarbon as worki...
Performance investigation of conventional heat pipe with hydrocarbon as worki...
eSAT Journals
 
Pump out tests in alluvial sands – a case study
Pump out tests in alluvial sands – a case studyPump out tests in alluvial sands – a case study
Pump out tests in alluvial sands – a case study
Infocengrs63
 
Tarea 2 hidraulica iii-cabrera arias roberto alejandro
Tarea 2 hidraulica iii-cabrera arias roberto alejandroTarea 2 hidraulica iii-cabrera arias roberto alejandro
Tarea 2 hidraulica iii-cabrera arias roberto alejandro
Alejandro Cabrera
 
160316_Proposal for SAMAN FARAZ GHESHM Ultra Low Coal Seam Longwall Mining Un...
160316_Proposal for SAMAN FARAZ GHESHM Ultra Low Coal Seam Longwall Mining Un...160316_Proposal for SAMAN FARAZ GHESHM Ultra Low Coal Seam Longwall Mining Un...
160316_Proposal for SAMAN FARAZ GHESHM Ultra Low Coal Seam Longwall Mining Un...Serena Fu
 
MBFC Test Report Dec2008.doc
MBFC Test Report Dec2008.docMBFC Test Report Dec2008.doc
MBFC Test Report Dec2008.doc
RekaNext Capital
 
HIGH WALL MINING at SCCL - A Case Study
HIGH WALL MINING at SCCL - A Case StudyHIGH WALL MINING at SCCL - A Case Study
HIGH WALL MINING at SCCL - A Case Study
knowledge stuff
 
Jaw Crusher
Jaw CrusherJaw Crusher
Jaw Crusher
guestb600a625
 
IRJET- Geotechnical Investigation of Different Soil Samples using Regression ...
IRJET- Geotechnical Investigation of Different Soil Samples using Regression ...IRJET- Geotechnical Investigation of Different Soil Samples using Regression ...
IRJET- Geotechnical Investigation of Different Soil Samples using Regression ...
IRJET Journal
 
Deep well submersible pump(Weihu)
Deep well submersible pump(Weihu)Deep well submersible pump(Weihu)
Deep well submersible pump(Weihu)Alex Ren
 
Sachpazis Cantilever Retaining Wall, In accordance to IBC 2012 and ASCE 7-10 ...
Sachpazis Cantilever Retaining Wall, In accordance to IBC 2012 and ASCE 7-10 ...Sachpazis Cantilever Retaining Wall, In accordance to IBC 2012 and ASCE 7-10 ...
Sachpazis Cantilever Retaining Wall, In accordance to IBC 2012 and ASCE 7-10 ...
Dr.Costas Sachpazis
 
coal handling plant
coal handling plantcoal handling plant
coal handling plant
vikash.mech05
 
SPC Project_Discharging Time 2016
SPC Project_Discharging Time 2016SPC Project_Discharging Time 2016
SPC Project_Discharging Time 2016Mahender Singh
 

Similar to 1. metode loading test muara tawar (bpp) (20)

final Presentation1680
final Presentation1680final Presentation1680
final Presentation1680
 
Mikazuki Slide.pptx
Mikazuki Slide.pptxMikazuki Slide.pptx
Mikazuki Slide.pptx
 
report
reportreport
report
 
CE Confr Presentation 08 Oct 2022.pptx
CE Confr Presentation 08 Oct 2022.pptxCE Confr Presentation 08 Oct 2022.pptx
CE Confr Presentation 08 Oct 2022.pptx
 
Ass 1 12-46 report engineering dynamics problem
Ass 1  12-46 report engineering dynamics problemAss 1  12-46 report engineering dynamics problem
Ass 1 12-46 report engineering dynamics problem
 
Performance investigation of conventional heat pipe with hydrocarbon as worki...
Performance investigation of conventional heat pipe with hydrocarbon as worki...Performance investigation of conventional heat pipe with hydrocarbon as worki...
Performance investigation of conventional heat pipe with hydrocarbon as worki...
 
Pump out tests in alluvial sands – a case study
Pump out tests in alluvial sands – a case studyPump out tests in alluvial sands – a case study
Pump out tests in alluvial sands – a case study
 
Tarea 2 hidraulica iii-cabrera arias roberto alejandro
Tarea 2 hidraulica iii-cabrera arias roberto alejandroTarea 2 hidraulica iii-cabrera arias roberto alejandro
Tarea 2 hidraulica iii-cabrera arias roberto alejandro
 
HOP Yick BD Ltd SMED
HOP Yick BD Ltd SMEDHOP Yick BD Ltd SMED
HOP Yick BD Ltd SMED
 
160316_Proposal for SAMAN FARAZ GHESHM Ultra Low Coal Seam Longwall Mining Un...
160316_Proposal for SAMAN FARAZ GHESHM Ultra Low Coal Seam Longwall Mining Un...160316_Proposal for SAMAN FARAZ GHESHM Ultra Low Coal Seam Longwall Mining Un...
160316_Proposal for SAMAN FARAZ GHESHM Ultra Low Coal Seam Longwall Mining Un...
 
MBFC Test Report Dec2008.doc
MBFC Test Report Dec2008.docMBFC Test Report Dec2008.doc
MBFC Test Report Dec2008.doc
 
HIGH WALL MINING at SCCL - A Case Study
HIGH WALL MINING at SCCL - A Case StudyHIGH WALL MINING at SCCL - A Case Study
HIGH WALL MINING at SCCL - A Case Study
 
Jaw Crusher
Jaw CrusherJaw Crusher
Jaw Crusher
 
PRESENTATION
PRESENTATIONPRESENTATION
PRESENTATION
 
IRJET- Geotechnical Investigation of Different Soil Samples using Regression ...
IRJET- Geotechnical Investigation of Different Soil Samples using Regression ...IRJET- Geotechnical Investigation of Different Soil Samples using Regression ...
IRJET- Geotechnical Investigation of Different Soil Samples using Regression ...
 
Deep well submersible pump(Weihu)
Deep well submersible pump(Weihu)Deep well submersible pump(Weihu)
Deep well submersible pump(Weihu)
 
WORKING PORTFOLIO - 01
WORKING PORTFOLIO - 01WORKING PORTFOLIO - 01
WORKING PORTFOLIO - 01
 
Sachpazis Cantilever Retaining Wall, In accordance to IBC 2012 and ASCE 7-10 ...
Sachpazis Cantilever Retaining Wall, In accordance to IBC 2012 and ASCE 7-10 ...Sachpazis Cantilever Retaining Wall, In accordance to IBC 2012 and ASCE 7-10 ...
Sachpazis Cantilever Retaining Wall, In accordance to IBC 2012 and ASCE 7-10 ...
 
coal handling plant
coal handling plantcoal handling plant
coal handling plant
 
SPC Project_Discharging Time 2016
SPC Project_Discharging Time 2016SPC Project_Discharging Time 2016
SPC Project_Discharging Time 2016
 

Recently uploaded

Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
zwunae
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
ambekarshweta25
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
dxobcob
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
Kamal Acharya
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 

Recently uploaded (20)

Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 

1. metode loading test muara tawar (bpp)