SlideShare a Scribd company logo
1 of 17
A 
PRESENTATION 
ON 
COAL HANDLING PLANT
6-CD 
5ABCD 
4-CD 
3-CD 
SR-3 C-14 
1-EF 
TT-5 
CRH 
TT-6 
TT-8 
Unit#6 
Unit#5 
Unit#4 
Unit#3 
Unit#2 
Unit#1 
6-AB 7-AB 
TT-4 
TT-3 
4-AB 
TT-2 
TT-7 
TT-9 
3-AB 
TT-1 
TT-0 
1-AB 
2-AB 
8-AB 
10-AB 
11-AB 
SR-1 C-12 
Track Hopper- 1 & 2 
8-CD 
1-CD 
2-CD 
7-CD 
9-CD 
SR-2 
C-13 
WT-1&2 
COAL HANDLING SYSTEM 
WASTE WATER 
TREATMENT
Track Hopper-2 
1-EF 
TT-5 
CRH 
TT-6 
TT-8 
Unit#6 
Unit#5 
Unit#4 
Unit#3 
Unit#2 
Unit#1 
6-AB 7-AB 
TT-4 
5-AB 
TT-3 
4-AB 
TT-2 
TT-7 
TT-9 
3-AB 
TT-1 
TT-0 
1-AB 
2-AB 
8-AB 
10-AB 
11-AB 
SR-1 C-12 
WT- 
2 
WT- 
1 
Track Hopper-1 
OPERATION OF COAL HANDLING PLANT 
WASTE WATER 
TREATMENT 
Note: 
Two streams are running for 
feeding of bunker of Unit # 3 & 4, 
by this only we are able to feed in 
bunker of unit#2 by 
commissioning of Plough 
discharger.
STACKER RECLAIMER OPERATION 
STACKING RECLAIMING
TT-5 
CRH 
TT-6 
TT-8 
Unit#6 
Unit#5 
Unit#4 
Unit#3 
Unit#2 
Unit#1 
TT-4 
TT-3 
4ABCD 
TT-2 
TT-7 
TT-9 
TT-1 
TT-0 
11-AB 
SR-3 C-14 
Track Hopper- 1 & 2 
1-CD 
2ABCD 
9-CD 
SR-2 
C-13 
WT-1&2 
BALANCE CHP STRUCTURAL 
WASTE WATER 
TREATMENT 
3ABCD 
5ABCD 
6ABCD 
7ABCD 
8CD 
Erection Completed 
1 gallery Erection Balance 
MPH +41m Erection Balance 
Note:
TT-5 
CRH 
TT-6 
TT-8 
Unit#6 
Unit#5 
Unit#4 
Unit#3 
Unit#2 
Unit#1 
TT-4 
TT-3 
TT-2 
TT-7 
TT-9 
TT-1 
TT-0 
11-AB 
SR-3 C-14 
Track Hopper- 1 & 2 
8-CD 
1-CD 
6-CD 
5ABCD 
4-CD 
3-CD 
2-CD 
7-CD 
9-CD 
SR-2 
C-13 
WT-1&2 
BALANCE CHP MECHANICAL 
WASTE WATER 
TREATMENT
CONVEYOR 1ABCD STATUS / BALANCE WORK 
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 
Conveyor 1A 
Conveyor 1B 
Conveyor 1C 
Conveyor 1D 
Completed 
Balance 
Sno. Conveyor 
Belt 
Width 
(mm) 
Conveyor 
Length 
(mtr) 
Total 
Weight 
(MT) 
Progress 
(MT) 
progress 
(%) 
Status/ Balance work 
Expected 
Days 
Remarks 
1 1A 1400 303.5 205.52 205.52 100 Completed 
2 1B 1400 303.5 205.52 205.52 100 Completed 
3 1C 1400 303.5 205.52 170.00 83 
1. Conveyor Erection Balance. 
2. Belt Laying & Jointing Balance. 
3. Moving Head & paddle Feeder 
Commissioning Balance. 
4. Chute (2 nos) & Skirt Board 
Erection & alignment Balance. 
70 
1. Work was under NEO 
scope. 
2. SEPCO has informed NEO 
to stop the work. 
3. SEPCO has to decide the 
1. Conveyor Erection Balance. 
2. Belt Laying & Jointing Balance. 
3. Moving Head Installation & paddle 
Feeder Commissioning Balance. 
4. Chute (2 nos) & Skirt Board 
Erection & alignment Balance. 
4 1D 1400 303.5 205.52 150.00 73 contractor.
CONVEYOR 2ABCD STATUS / BALANCE WORK 
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 
Conveyor 2A 
Conveyor 2B 
Conveyor 2C 
Conveyor 2D 
Completed 
Balance 
Sno. Conveyor 
Belt 
Width 
(mm) 
Conveyor 
Length 
(mtr) 
Total 
Weight 
(MT) 
Progress 
(MT) 
progress 
(%) 
Status/ Balance work 
Expected 
Days 
Remarks 
1 2A 1800 188 138.61 138.61 100 Completed 
2 2B 1800 202 142.90 142.90 100 Completed 
3 2C 1800 202 142.90 130.00 91 
1. Belt Jointing Balance. 
2. Drive alignment & Cooling Water 
piping Balance. 
3. Chute (2 nos) & Skirt Board 
Erection & alignment Balance. 
7 
1. PETRON scope, SEPCO 
has to give clearence. 
4 2D 1800 188 138.61 130.00 94 
1. Belt Jointing Balance. 
2. Drive alignment & Cooling Water 
piping Balance. 
3. Chute (2 nos) & Skirt Board 
Erection & alignment Balance.
CONVEYOR 3ABCD STATUS / BALANCE WORK 
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 
Conveyor 3A 
Conveyor 3B 
Conveyor 3C 
Conveyor 3D 
Completed 
Balance 
Sno. Conveyor 
Belt 
Width 
(mm) 
Conveyor 
Length 
(mtr) 
Total 
Weight 
(MT) 
Progress 
(MT) 
progress 
(%) 
Status/ Balance work 
Expected 
Days 
Remarks 
1 3A 1400 93.95 52.06 52.06 100 Completed 
2 3B 1400 93.95 52.06 52.06 100 Completed 
3 3C 1400 93.95 60.62 59.00 97 
1. Belt Belt Jointing Balance. 
2. Drive alignment & Cooling Water 
piping Balance. 
3. Chute (2 nos) & Skirt Board 
Erection & alignment Balance. 
7 
1. PETRON scope, SEPCO 
has to give clearence. 
4 3D 1400 93.95 60.62 59.00 97 
1. Belt Jointing Balance. 
2. Drive alignment & Cooling Water 
piping Balance. 
3. Chute (2 nos) & Skirt Board 
Erection & alignment Balance.
CONVEYOR 4ABCD STATUS / BALANCE WORK 
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 
Conveyor 4A 
Conveyor 4B 
Conveyor 4C 
Conveyor 4D 
Completed 
Balance 
Sno. Conveyor 
Belt 
Width 
(mm) 
Conveyor 
Length 
(mtr) 
Total 
Weight 
(MT) 
Progress 
(MT) 
progress 
(%) 
Status/ Balance work 
Expected 
Days 
Remarks 
1 4A 1400 122.75 51.84 51.84 100 Completed 
2 4B 1400 122.75 57.05 57.05 100 Completed 
3 4C 1400 122.75 57.05 56.00 98 
1. Belt Jointing Balance. 
2. Drive alignment Balance. 
7 
1. PETRON scope, SEPCO has 
to give clearence. 
4 4D 1400 122.75 51.84 50.00 96 
1. Belt Jointing Balance. 
2. Drive alignment Balance.
CONVEYOR 5ABCD STATUS / BALANCE WORK 
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 
Conveyor 5A 
Conveyor 5B 
Conveyor 5C 
Conveyor 5D 
Completed 
Balance 
Sno. Conveyor 
Belt 
Width 
(mm) 
Conveyor 
Length 
(mtr) 
Total 
Weight 
(MT) 
Progress 
(MT) 
progress 
(%) 
Status/ Balance work 
Expected 
Days 
Remarks 
1 5A 1400 122.75 51.84 51.84 100 Completed 
2 5B 1400 122.75 57.05 57.05 100 Completed 
3 5C 1400 122.75 57.05 56.00 98 
1. Belt Jointing Balance. 
2. Drive alignment Balance. 
3. Chute (4 nos) & Skirt Board 
Erection & alignment Balance. 
7 
1. PETRON scope, SEPCO has 
to give clearence. 
4 5D 1400 122.75 51.84 50.00 96 
1. Belt Jointing Balance. 
2. Drive alignment Balance. 
3. Chute (4 nos) & Skirt Board 
Erection & alignment Balance.
CONVEYOR 6ABCD STATUS / BALANCE WORK 
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 
Conveyor 6A 
Conveyor 6B 
Conveyor 6C 
Conveyor 6D 
Completed 
Balance 
Sno. Conveyor 
Belt 
Width 
(mm) 
Conveyor 
Length 
(mtr) 
Total 
Weight 
(MT) 
Progress 
(MT) 
progress 
(%) 
Status/ Balance work 
Expected 
Days 
Remarks 
1 6A 1400 76.25 46.33 46.33 100 Completed 
2 6B 1400 76.25 48.86 48.86 100 Completed 
3 6C 1400 69.25 48.86 47.00 96 
1. Belt Jointing Balance. 
2. Drive alignment Balance. 
3. Chute (2 nos) & Skirt Board 
Erection & alignment Balance. 
7 
1. PETRON scope, SEPCO 
has to give clearence. 
4 6D 1400 69.25 46.33 45.00 97 
1. Belt Jointing Balance. 
2. Drive alignment Balance. 
3. Chute (2 nos) & Skirt Board 
Erection & alignment Balance.
CONVEYOR 7ABCD STATUS / BALANCE WORK 
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 
Conveyor 7A 
Conveyor 7B 
Conveyor 7C 
Conveyor 7D 
Completed 
Balance 
Sno. Conveyor 
Belt 
Width 
(mm) 
Conveyor 
Length 
(mtr) 
Total 
Weight 
(MT) 
Progress 
(MT) 
progress 
(%) 
Status/ Balance work 
Expected 
Days 
Remarks 
1 7A 1400 622.441 230.25 230.25 100 Completed 
2 7B 1400 624.254 225.60 225.60 100 Completed 
3 7C 1400 626.741 229.21 177.00 77 
1. Belt Laying & Jointing Balance. 
2. Conveyor, Drive alignment & 
Cooling Water piping Balance. 
3. Chute (2 nos) & Skirt Board 
Erection & alignment Balance. 
20 
1. PETRON scope, SEPCO 
has to give clearence. 
4 7D 1400 625.629 228.61 160.00 70 
1. Belt Laying & Jointing Balance. 
2. Conveyor, Drive alignment & 
Cooling Water piping Balance. 
3. Chute (2 nos) & Skirt Board 
Erection & alignment Balance.
CONVEYOR 8ABCD STATUS / BALANCE WORK 
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 
Conveyor 8A 
Conveyor 8B 
Conveyor 8C 
Conveyor 8D 
Completed 
Balance 
Sno. Conveyor 
Belt 
Width 
(mm) 
Conveyor 
Length 
(mtr) 
Total 
Weight 
(MT) 
Progress 
(MT) 
progress 
(%) 
Status/ Balance work 
Expected 
Days 
Remarks 
1 8A 1400 281.32 85.04 85.04 100 Completed 
2 8B 1400 284.82 84.88 84.88 100 Completed 
3 8C 1400 1400 152.45 0.00 0 
1. 80% structural work completed, 
balance work will compl after the 
MPH erection. 
2. Deck Sheeting & flooring Balance. 
3. Drive, Chutes & conveyor will 
compl. After MPH erection. 
90 
1. Work was under NEO 
scope. 
2. SEPCO has informed 
NEO to stop the work. 
3. SEPCO has to decide the 
contractor. 
4. Critical work: Require 
T7 for structural work as 
well as mechanical work 
4 8D 1400 1400 152.45 0.00 0 
1. 80% structural work completed, 
balance work will compl after the 
MPH erection. 
2. Deck Sheeting & flooring Balance. 
3. Drive, Chutes & conveyor will 
compl. After MPH erection.
CONVEYOR 10AB STATUS / BALANCE WORK 
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 
Conveyor 10A 
Conveyor 10B 
Completed 
Balance 
Sno. Conveyor 
Belt 
Width 
(mm) 
Conveyor 
Length 
(mtr) 
Total 
Weight 
(MT) 
Progress 
(MT) 
progress 
(%) 
Status/ Balance work 
Expected 
Days 
Remarks 
1 10A 1400 161.35 592.70 592.70 100 Completed 
2 10B 1400 161.35 592.70 592.70 100 Completed
CONVEYOR 12,13 &14 STATUS / BALANCE WORK 
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 
Conveyor 12 
Conveyor 13 
Conveyor 14 
Completed 
Balance 
Sno. Conveyor 
Belt 
Width 
(mm) 
Conveyor 
Length 
(mtr) 
Total 
Weight 
(MT) 
Progress 
(MT) 
progress 
(%) 
Status/ Balance work 
Expected 
Days 
Remarks 
1 12 1400 482 145.03 145.03 100 Completed 
2 13 1400 482 145.03 145.03 100 Completed 
3 14 1400 482 145.03 0.00 0 
1. Civil foundation(300 Mtrs) 
balance. 
2. Conveyor Work not Started. 
3. Chute Work Balance. 
40 
1. Civil has to give front. 
2. PETRON scope, SEPCO has 
to give clearance.
CONVEYOR 11AB STATUS / BALANCE WORK 
Conveyor 11A Completed 
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 
Conveyor 11B 
Balance 
Sno. Conveyor 
Belt 
Width 
(mm) 
Conveyor 
Length 
(mtr) 
Total 
Weight 
(MT) 
Progress 
(MT) 
progress 
(%) 
Status/ Balance work 
Expected 
Days 
Remarks 
1 11A 1400 278.20 139.12 139.12 100 Completed 
1. Completed but need 
restoration for Unit # 1. 
2. Critical work: Require 
MPH +41mtr floor from 
unit#1 to 6 for mechanical 
work. 
2 11B 1400 278.20 139.12 139.12 100 Completed 
Conveyor 11A (Restoration) Completed 
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 
Conveyor 11B (Restoration) 
Unit#6 Unit#5 Unit#4 Unit#3 Unit#2 Unit#1 
FEEDING FEEDING FEEDING FEEDING FEEDING FEEDING 
Balance 
Conveyor 9 CD feeding Unit #4, 5 & 6 Conveyor 11 AB feeding Unit #1, 2 & 3 
8CD 10AB

More Related Content

What's hot

Final year project
Final year projectFinal year project
Final year projectRohitMeshram15
 
Caterpillar cat ec20 k ec25k forklift lift trucks service repair manual sna3e...
Caterpillar cat ec20 k ec25k forklift lift trucks service repair manual sna3e...Caterpillar cat ec20 k ec25k forklift lift trucks service repair manual sna3e...
Caterpillar cat ec20 k ec25k forklift lift trucks service repair manual sna3e...fjjskekdmnsme
 
Caterpillar cat ec20 k ec25k forklift lift trucks service repair manual sna3e...
Caterpillar cat ec20 k ec25k forklift lift trucks service repair manual sna3e...Caterpillar cat ec20 k ec25k forklift lift trucks service repair manual sna3e...
Caterpillar cat ec20 k ec25k forklift lift trucks service repair manual sna3e...fjjsekkmdmes
 
Virtual baja 2016 17355 alpha college of engg. and tech._presentation.ppt
Virtual baja 2016 17355 alpha college of engg. and tech._presentation.pptVirtual baja 2016 17355 alpha college of engg. and tech._presentation.ppt
Virtual baja 2016 17355 alpha college of engg. and tech._presentation.pptIshan Mehta
 
Belt Weigh feeder short presentation By Shubham saxena
Belt Weigh feeder short presentation By Shubham saxena Belt Weigh feeder short presentation By Shubham saxena
Belt Weigh feeder short presentation By Shubham saxena Shubham Saxena
 
Design, Analysis and fabrication of ATV (All Terrain Vehicle) for the event B...
Design, Analysis and fabrication of ATV (All Terrain Vehicle) for the event B...Design, Analysis and fabrication of ATV (All Terrain Vehicle) for the event B...
Design, Analysis and fabrication of ATV (All Terrain Vehicle) for the event B...vinay kumar
 
Team Traxion'15 - Virtual Baja 2015 Presentation
Team Traxion'15 - Virtual Baja 2015 PresentationTeam Traxion'15 - Virtual Baja 2015 Presentation
Team Traxion'15 - Virtual Baja 2015 PresentationDhamodharan V
 
ASME HPVC 2017, LNMIIT jaipur, ACETII-II , Aloha college of Eng. & Tech.
ASME HPVC 2017, LNMIIT jaipur, ACETII-II , Aloha college of Eng. & Tech. ASME HPVC 2017, LNMIIT jaipur, ACETII-II , Aloha college of Eng. & Tech.
ASME HPVC 2017, LNMIIT jaipur, ACETII-II , Aloha college of Eng. & Tech. Ishan Mehta
 
Savage-Suspension-Report-Final
Savage-Suspension-Report-FinalSavage-Suspension-Report-Final
Savage-Suspension-Report-FinalTing-Hung Yu
 
Virtual baja 2016 17227 tezpur university_presentation
Virtual baja 2016 17227 tezpur university_presentationVirtual baja 2016 17227 tezpur university_presentation
Virtual baja 2016 17227 tezpur university_presentationBishal Purkayastha
 
Team Kashpiers "Baja 2013"
Team Kashpiers "Baja 2013"Team Kashpiers "Baja 2013"
Team Kashpiers "Baja 2013"Mohit Mahaldar
 
Virtual BAJA 2015_(16190)_(Team Prayog)_PRESENTATION
Virtual BAJA 2015_(16190)_(Team Prayog)_PRESENTATION Virtual BAJA 2015_(16190)_(Team Prayog)_PRESENTATION
Virtual BAJA 2015_(16190)_(Team Prayog)_PRESENTATION Anubhav Maheshwari
 
secciones Paralelo.pdf
secciones Paralelo.pdfsecciones Paralelo.pdf
secciones Paralelo.pdfDarsonSobrino2
 
BAJA SAE INDIA 2015
BAJA SAE INDIA 2015BAJA SAE INDIA 2015
BAJA SAE INDIA 2015Vaibhav porwal
 
TSCO-THERMO FISHER
TSCO-THERMO FISHERTSCO-THERMO FISHER
TSCO-THERMO FISHERTechno Service
 
National Go-kart Championship (NGKC, ISNEE) 2014
National Go-kart Championship (NGKC, ISNEE) 2014National Go-kart Championship (NGKC, ISNEE) 2014
National Go-kart Championship (NGKC, ISNEE) 2014Vaibhav porwal
 
96745 Team Gearedup2012
96745 Team Gearedup201296745 Team Gearedup2012
96745 Team Gearedup2012saddamjean
 

What's hot (18)

Final year project
Final year projectFinal year project
Final year project
 
Caterpillar cat ec20 k ec25k forklift lift trucks service repair manual sna3e...
Caterpillar cat ec20 k ec25k forklift lift trucks service repair manual sna3e...Caterpillar cat ec20 k ec25k forklift lift trucks service repair manual sna3e...
Caterpillar cat ec20 k ec25k forklift lift trucks service repair manual sna3e...
 
Caterpillar cat ec20 k ec25k forklift lift trucks service repair manual sna3e...
Caterpillar cat ec20 k ec25k forklift lift trucks service repair manual sna3e...Caterpillar cat ec20 k ec25k forklift lift trucks service repair manual sna3e...
Caterpillar cat ec20 k ec25k forklift lift trucks service repair manual sna3e...
 
Virtual baja 2016 17355 alpha college of engg. and tech._presentation.ppt
Virtual baja 2016 17355 alpha college of engg. and tech._presentation.pptVirtual baja 2016 17355 alpha college of engg. and tech._presentation.ppt
Virtual baja 2016 17355 alpha college of engg. and tech._presentation.ppt
 
Belt Weigh feeder short presentation By Shubham saxena
Belt Weigh feeder short presentation By Shubham saxena Belt Weigh feeder short presentation By Shubham saxena
Belt Weigh feeder short presentation By Shubham saxena
 
Design, Analysis and fabrication of ATV (All Terrain Vehicle) for the event B...
Design, Analysis and fabrication of ATV (All Terrain Vehicle) for the event B...Design, Analysis and fabrication of ATV (All Terrain Vehicle) for the event B...
Design, Analysis and fabrication of ATV (All Terrain Vehicle) for the event B...
 
Team Traxion'15 - Virtual Baja 2015 Presentation
Team Traxion'15 - Virtual Baja 2015 PresentationTeam Traxion'15 - Virtual Baja 2015 Presentation
Team Traxion'15 - Virtual Baja 2015 Presentation
 
ASME HPVC 2017, LNMIIT jaipur, ACETII-II , Aloha college of Eng. & Tech.
ASME HPVC 2017, LNMIIT jaipur, ACETII-II , Aloha college of Eng. & Tech. ASME HPVC 2017, LNMIIT jaipur, ACETII-II , Aloha college of Eng. & Tech.
ASME HPVC 2017, LNMIIT jaipur, ACETII-II , Aloha college of Eng. & Tech.
 
Savage-Suspension-Report-Final
Savage-Suspension-Report-FinalSavage-Suspension-Report-Final
Savage-Suspension-Report-Final
 
Virtual baja 2016 17227 tezpur university_presentation
Virtual baja 2016 17227 tezpur university_presentationVirtual baja 2016 17227 tezpur university_presentation
Virtual baja 2016 17227 tezpur university_presentation
 
Team Kashpiers "Baja 2013"
Team Kashpiers "Baja 2013"Team Kashpiers "Baja 2013"
Team Kashpiers "Baja 2013"
 
Virtual BAJA 2015_(16190)_(Team Prayog)_PRESENTATION
Virtual BAJA 2015_(16190)_(Team Prayog)_PRESENTATION Virtual BAJA 2015_(16190)_(Team Prayog)_PRESENTATION
Virtual BAJA 2015_(16190)_(Team Prayog)_PRESENTATION
 
secciones Paralelo.pdf
secciones Paralelo.pdfsecciones Paralelo.pdf
secciones Paralelo.pdf
 
BAJA SAE INDIA 2015
BAJA SAE INDIA 2015BAJA SAE INDIA 2015
BAJA SAE INDIA 2015
 
TSCO-THERMO FISHER
TSCO-THERMO FISHERTSCO-THERMO FISHER
TSCO-THERMO FISHER
 
National Go-kart Championship (NGKC, ISNEE) 2014
National Go-kart Championship (NGKC, ISNEE) 2014National Go-kart Championship (NGKC, ISNEE) 2014
National Go-kart Championship (NGKC, ISNEE) 2014
 
Cke900 1 f-spec
Cke900 1 f-specCke900 1 f-spec
Cke900 1 f-spec
 
96745 Team Gearedup2012
96745 Team Gearedup201296745 Team Gearedup2012
96745 Team Gearedup2012
 

Viewers also liked

Coal Handling Plants....
Coal Handling Plants....Coal Handling Plants....
Coal Handling Plants....Vipul Sinha
 
Best ppt on Presentation on Coal handling plant
Best ppt on Presentation on Coal handling plantBest ppt on Presentation on Coal handling plant
Best ppt on Presentation on Coal handling plantRonak Thakare
 
Coal Handling Plant ( CHP )
Coal Handling Plant ( CHP )Coal Handling Plant ( CHP )
Coal Handling Plant ( CHP )SHRIKANT KHATING
 
Presentation on coal handling systems
Presentation on coal handling systemsPresentation on coal handling systems
Presentation on coal handling systemsArnab Chakraborty
 
Coal handling plant
Coal handling plantCoal handling plant
Coal handling plantRohit Khatri
 
Chp in presentation
Chp in presentationChp in presentation
Chp in presentationrajkumar_sm
 
Coal and Ash Handling
Coal and Ash HandlingCoal and Ash Handling
Coal and Ash HandlingVanita Thakkar
 
Chpppt 100617141038-phpapp01
Chpppt 100617141038-phpapp01Chpppt 100617141038-phpapp01
Chpppt 100617141038-phpapp01Aashutosh Rathore
 
NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')
NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')
NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')Tejasvi Anant
 
6 weeks it on ntpc
6 weeks it on ntpc 6 weeks it on ntpc
6 weeks it on ntpc Uttam Kumar
 
COAL HANDLING PLANT
COAL  HANDLING PLANTCOAL  HANDLING PLANT
COAL HANDLING PLANTpulak126
 
Coal Handling Plant
Coal Handling PlantCoal Handling Plant
Coal Handling PlantAshrant Dass
 
THERMAL POWER STATION PPT.
THERMAL POWER STATION PPT.THERMAL POWER STATION PPT.
THERMAL POWER STATION PPT.Anish Anand
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plantfoxycrow
 
THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)Baibhav Saha
 
Best ppt on thermal power station working
Best ppt on thermal power station workingBest ppt on thermal power station working
Best ppt on thermal power station workingRonak Thakare
 
Mormugao port ppt
Mormugao port pptMormugao port ppt
Mormugao port pptGAURAV SHARMA
 

Viewers also liked (20)

Coal Handling Plants....
Coal Handling Plants....Coal Handling Plants....
Coal Handling Plants....
 
Best ppt on Presentation on Coal handling plant
Best ppt on Presentation on Coal handling plantBest ppt on Presentation on Coal handling plant
Best ppt on Presentation on Coal handling plant
 
Coal Handling Plant ( CHP )
Coal Handling Plant ( CHP )Coal Handling Plant ( CHP )
Coal Handling Plant ( CHP )
 
coal handling plant
coal handling plantcoal handling plant
coal handling plant
 
Presentation on coal handling systems
Presentation on coal handling systemsPresentation on coal handling systems
Presentation on coal handling systems
 
Coal handling plant
Coal handling plantCoal handling plant
Coal handling plant
 
Chp in presentation
Chp in presentationChp in presentation
Chp in presentation
 
Coal and Ash Handling
Coal and Ash HandlingCoal and Ash Handling
Coal and Ash Handling
 
Chpppt 100617141038-phpapp01
Chpppt 100617141038-phpapp01Chpppt 100617141038-phpapp01
Chpppt 100617141038-phpapp01
 
NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')
NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')
NTPC KORBA CHHATTISGARH coal to electricity by tejasvi anant (tan 90')
 
6 weeks it on ntpc
6 weeks it on ntpc 6 weeks it on ntpc
6 weeks it on ntpc
 
COAL HANDLING PLANT
COAL  HANDLING PLANTCOAL  HANDLING PLANT
COAL HANDLING PLANT
 
Coal Handling Plant
Coal Handling PlantCoal Handling Plant
Coal Handling Plant
 
THERMAL POWER STATION PPT.
THERMAL POWER STATION PPT.THERMAL POWER STATION PPT.
THERMAL POWER STATION PPT.
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)
 
Best ppt on thermal power station working
Best ppt on thermal power station workingBest ppt on thermal power station working
Best ppt on thermal power station working
 
Kstps ppt
Kstps pptKstps ppt
Kstps ppt
 
Mormugao port ppt
Mormugao port pptMormugao port ppt
Mormugao port ppt
 
Chp
ChpChp
Chp
 

Similar to coal handling plant

PM Performamnec report- Jan'23.pptx
PM Performamnec report- Jan'23.pptxPM Performamnec report- Jan'23.pptx
PM Performamnec report- Jan'23.pptxsantosh509014
 
COOP training-Bokhari
COOP training-BokhariCOOP training-Bokhari
COOP training-BokhariAssad Bokhari
 
Site Surveying Report 2 (Traversing)
Site Surveying Report 2 (Traversing)Site Surveying Report 2 (Traversing)
Site Surveying Report 2 (Traversing)Haziq1511
 
Proposal Wide Blower No.1 & 2 with inverter
Proposal Wide Blower No.1 & 2  with inverterProposal Wide Blower No.1 & 2  with inverter
Proposal Wide Blower No.1 & 2 with inverterRidhoIrawan12
 
Anant project work
Anant project workAnant project work
Anant project workRajat Dixit
 
1st Presentation NAME 338
1st Presentation NAME 338 1st Presentation NAME 338
1st Presentation NAME 338 Kifayath Chowdhury
 
NAME 338 , Presentation 1
NAME 338 , Presentation 1NAME 338 , Presentation 1
NAME 338 , Presentation 1Kifayath Chowdhury
 
Mitsubishi ac servos melservo j4 solutions vertical form, fill & seal
Mitsubishi ac servos melservo j4 solutions vertical form, fill & sealMitsubishi ac servos melservo j4 solutions vertical form, fill & seal
Mitsubishi ac servos melservo j4 solutions vertical form, fill & sealDien Ha The
 
Mitsubishi ac servos melservo j4 solutions vertical form, fill & seal-die...
Mitsubishi ac servos melservo j4 solutions vertical form, fill & seal-die...Mitsubishi ac servos melservo j4 solutions vertical form, fill & seal-die...
Mitsubishi ac servos melservo j4 solutions vertical form, fill & seal-die...Dien Ha The
 
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)hepemod733
 
Hoisting equipment inspection presentation
Hoisting equipment inspection presentationHoisting equipment inspection presentation
Hoisting equipment inspection presentationIndra Biswakarma
 
Presentation on Industrial Attachment of Mosharaf Group
Presentation on Industrial Attachment of Mosharaf GroupPresentation on Industrial Attachment of Mosharaf Group
Presentation on Industrial Attachment of Mosharaf GroupMuhammad Abdulla-Al-Sufian
 
Igo50-Product-Guide.pdf
Igo50-Product-Guide.pdfIgo50-Product-Guide.pdf
Igo50-Product-Guide.pdfkredis1
 
Igo50 Self Erecting Tower Cranes Product-Guide.pdf
Igo50 Self Erecting Tower Cranes Product-Guide.pdfIgo50 Self Erecting Tower Cranes Product-Guide.pdf
Igo50 Self Erecting Tower Cranes Product-Guide.pdfCompass Equipment
 
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...paws21610697
 
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...uddksemd8ud
 
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...f7djidksmd3e
 
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...f8uuseijdkmd3e
 
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...jdjkskmikdkmd
 

Similar to coal handling plant (20)

PM Performamnec report- Jan'23.pptx
PM Performamnec report- Jan'23.pptxPM Performamnec report- Jan'23.pptx
PM Performamnec report- Jan'23.pptx
 
COOP training-Bokhari
COOP training-BokhariCOOP training-Bokhari
COOP training-Bokhari
 
Site Surveying Report 2 (Traversing)
Site Surveying Report 2 (Traversing)Site Surveying Report 2 (Traversing)
Site Surveying Report 2 (Traversing)
 
Proposal Wide Blower No.1 & 2 with inverter
Proposal Wide Blower No.1 & 2  with inverterProposal Wide Blower No.1 & 2  with inverter
Proposal Wide Blower No.1 & 2 with inverter
 
Anant project work
Anant project workAnant project work
Anant project work
 
1st Presentation NAME 338
1st Presentation NAME 338 1st Presentation NAME 338
1st Presentation NAME 338
 
NAME 338 , Presentation 1
NAME 338 , Presentation 1NAME 338 , Presentation 1
NAME 338 , Presentation 1
 
Mitsubishi ac servos melservo j4 solutions vertical form, fill & seal
Mitsubishi ac servos melservo j4 solutions vertical form, fill & sealMitsubishi ac servos melservo j4 solutions vertical form, fill & seal
Mitsubishi ac servos melservo j4 solutions vertical form, fill & seal
 
Mitsubishi ac servos melservo j4 solutions vertical form, fill & seal-die...
Mitsubishi ac servos melservo j4 solutions vertical form, fill & seal-die...Mitsubishi ac servos melservo j4 solutions vertical form, fill & seal-die...
Mitsubishi ac servos melservo j4 solutions vertical form, fill & seal-die...
 
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
 
Traversing
TraversingTraversing
Traversing
 
Hoisting equipment inspection presentation
Hoisting equipment inspection presentationHoisting equipment inspection presentation
Hoisting equipment inspection presentation
 
Presentation on Industrial Attachment of Mosharaf Group
Presentation on Industrial Attachment of Mosharaf GroupPresentation on Industrial Attachment of Mosharaf Group
Presentation on Industrial Attachment of Mosharaf Group
 
Igo50-Product-Guide.pdf
Igo50-Product-Guide.pdfIgo50-Product-Guide.pdf
Igo50-Product-Guide.pdf
 
Igo50 Self Erecting Tower Cranes Product-Guide.pdf
Igo50 Self Erecting Tower Cranes Product-Guide.pdfIgo50 Self Erecting Tower Cranes Product-Guide.pdf
Igo50 Self Erecting Tower Cranes Product-Guide.pdf
 
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
 
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
 
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
 
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
 
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
Caterpillar Cat 966K Wheel Loader (Prefix TFS) Service Repair Manual (TFS0000...
 

Recently uploaded

chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 

Recently uploaded (20)

chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 

coal handling plant

  • 1. A PRESENTATION ON COAL HANDLING PLANT
  • 2. 6-CD 5ABCD 4-CD 3-CD SR-3 C-14 1-EF TT-5 CRH TT-6 TT-8 Unit#6 Unit#5 Unit#4 Unit#3 Unit#2 Unit#1 6-AB 7-AB TT-4 TT-3 4-AB TT-2 TT-7 TT-9 3-AB TT-1 TT-0 1-AB 2-AB 8-AB 10-AB 11-AB SR-1 C-12 Track Hopper- 1 & 2 8-CD 1-CD 2-CD 7-CD 9-CD SR-2 C-13 WT-1&2 COAL HANDLING SYSTEM WASTE WATER TREATMENT
  • 3. Track Hopper-2 1-EF TT-5 CRH TT-6 TT-8 Unit#6 Unit#5 Unit#4 Unit#3 Unit#2 Unit#1 6-AB 7-AB TT-4 5-AB TT-3 4-AB TT-2 TT-7 TT-9 3-AB TT-1 TT-0 1-AB 2-AB 8-AB 10-AB 11-AB SR-1 C-12 WT- 2 WT- 1 Track Hopper-1 OPERATION OF COAL HANDLING PLANT WASTE WATER TREATMENT Note: Two streams are running for feeding of bunker of Unit # 3 & 4, by this only we are able to feed in bunker of unit#2 by commissioning of Plough discharger.
  • 4. STACKER RECLAIMER OPERATION STACKING RECLAIMING
  • 5. TT-5 CRH TT-6 TT-8 Unit#6 Unit#5 Unit#4 Unit#3 Unit#2 Unit#1 TT-4 TT-3 4ABCD TT-2 TT-7 TT-9 TT-1 TT-0 11-AB SR-3 C-14 Track Hopper- 1 & 2 1-CD 2ABCD 9-CD SR-2 C-13 WT-1&2 BALANCE CHP STRUCTURAL WASTE WATER TREATMENT 3ABCD 5ABCD 6ABCD 7ABCD 8CD Erection Completed 1 gallery Erection Balance MPH +41m Erection Balance Note:
  • 6. TT-5 CRH TT-6 TT-8 Unit#6 Unit#5 Unit#4 Unit#3 Unit#2 Unit#1 TT-4 TT-3 TT-2 TT-7 TT-9 TT-1 TT-0 11-AB SR-3 C-14 Track Hopper- 1 & 2 8-CD 1-CD 6-CD 5ABCD 4-CD 3-CD 2-CD 7-CD 9-CD SR-2 C-13 WT-1&2 BALANCE CHP MECHANICAL WASTE WATER TREATMENT
  • 7. CONVEYOR 1ABCD STATUS / BALANCE WORK 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Conveyor 1A Conveyor 1B Conveyor 1C Conveyor 1D Completed Balance Sno. Conveyor Belt Width (mm) Conveyor Length (mtr) Total Weight (MT) Progress (MT) progress (%) Status/ Balance work Expected Days Remarks 1 1A 1400 303.5 205.52 205.52 100 Completed 2 1B 1400 303.5 205.52 205.52 100 Completed 3 1C 1400 303.5 205.52 170.00 83 1. Conveyor Erection Balance. 2. Belt Laying & Jointing Balance. 3. Moving Head & paddle Feeder Commissioning Balance. 4. Chute (2 nos) & Skirt Board Erection & alignment Balance. 70 1. Work was under NEO scope. 2. SEPCO has informed NEO to stop the work. 3. SEPCO has to decide the 1. Conveyor Erection Balance. 2. Belt Laying & Jointing Balance. 3. Moving Head Installation & paddle Feeder Commissioning Balance. 4. Chute (2 nos) & Skirt Board Erection & alignment Balance. 4 1D 1400 303.5 205.52 150.00 73 contractor.
  • 8. CONVEYOR 2ABCD STATUS / BALANCE WORK 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Conveyor 2A Conveyor 2B Conveyor 2C Conveyor 2D Completed Balance Sno. Conveyor Belt Width (mm) Conveyor Length (mtr) Total Weight (MT) Progress (MT) progress (%) Status/ Balance work Expected Days Remarks 1 2A 1800 188 138.61 138.61 100 Completed 2 2B 1800 202 142.90 142.90 100 Completed 3 2C 1800 202 142.90 130.00 91 1. Belt Jointing Balance. 2. Drive alignment & Cooling Water piping Balance. 3. Chute (2 nos) & Skirt Board Erection & alignment Balance. 7 1. PETRON scope, SEPCO has to give clearence. 4 2D 1800 188 138.61 130.00 94 1. Belt Jointing Balance. 2. Drive alignment & Cooling Water piping Balance. 3. Chute (2 nos) & Skirt Board Erection & alignment Balance.
  • 9. CONVEYOR 3ABCD STATUS / BALANCE WORK 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Conveyor 3A Conveyor 3B Conveyor 3C Conveyor 3D Completed Balance Sno. Conveyor Belt Width (mm) Conveyor Length (mtr) Total Weight (MT) Progress (MT) progress (%) Status/ Balance work Expected Days Remarks 1 3A 1400 93.95 52.06 52.06 100 Completed 2 3B 1400 93.95 52.06 52.06 100 Completed 3 3C 1400 93.95 60.62 59.00 97 1. Belt Belt Jointing Balance. 2. Drive alignment & Cooling Water piping Balance. 3. Chute (2 nos) & Skirt Board Erection & alignment Balance. 7 1. PETRON scope, SEPCO has to give clearence. 4 3D 1400 93.95 60.62 59.00 97 1. Belt Jointing Balance. 2. Drive alignment & Cooling Water piping Balance. 3. Chute (2 nos) & Skirt Board Erection & alignment Balance.
  • 10. CONVEYOR 4ABCD STATUS / BALANCE WORK 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Conveyor 4A Conveyor 4B Conveyor 4C Conveyor 4D Completed Balance Sno. Conveyor Belt Width (mm) Conveyor Length (mtr) Total Weight (MT) Progress (MT) progress (%) Status/ Balance work Expected Days Remarks 1 4A 1400 122.75 51.84 51.84 100 Completed 2 4B 1400 122.75 57.05 57.05 100 Completed 3 4C 1400 122.75 57.05 56.00 98 1. Belt Jointing Balance. 2. Drive alignment Balance. 7 1. PETRON scope, SEPCO has to give clearence. 4 4D 1400 122.75 51.84 50.00 96 1. Belt Jointing Balance. 2. Drive alignment Balance.
  • 11. CONVEYOR 5ABCD STATUS / BALANCE WORK 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Conveyor 5A Conveyor 5B Conveyor 5C Conveyor 5D Completed Balance Sno. Conveyor Belt Width (mm) Conveyor Length (mtr) Total Weight (MT) Progress (MT) progress (%) Status/ Balance work Expected Days Remarks 1 5A 1400 122.75 51.84 51.84 100 Completed 2 5B 1400 122.75 57.05 57.05 100 Completed 3 5C 1400 122.75 57.05 56.00 98 1. Belt Jointing Balance. 2. Drive alignment Balance. 3. Chute (4 nos) & Skirt Board Erection & alignment Balance. 7 1. PETRON scope, SEPCO has to give clearence. 4 5D 1400 122.75 51.84 50.00 96 1. Belt Jointing Balance. 2. Drive alignment Balance. 3. Chute (4 nos) & Skirt Board Erection & alignment Balance.
  • 12. CONVEYOR 6ABCD STATUS / BALANCE WORK 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Conveyor 6A Conveyor 6B Conveyor 6C Conveyor 6D Completed Balance Sno. Conveyor Belt Width (mm) Conveyor Length (mtr) Total Weight (MT) Progress (MT) progress (%) Status/ Balance work Expected Days Remarks 1 6A 1400 76.25 46.33 46.33 100 Completed 2 6B 1400 76.25 48.86 48.86 100 Completed 3 6C 1400 69.25 48.86 47.00 96 1. Belt Jointing Balance. 2. Drive alignment Balance. 3. Chute (2 nos) & Skirt Board Erection & alignment Balance. 7 1. PETRON scope, SEPCO has to give clearence. 4 6D 1400 69.25 46.33 45.00 97 1. Belt Jointing Balance. 2. Drive alignment Balance. 3. Chute (2 nos) & Skirt Board Erection & alignment Balance.
  • 13. CONVEYOR 7ABCD STATUS / BALANCE WORK 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Conveyor 7A Conveyor 7B Conveyor 7C Conveyor 7D Completed Balance Sno. Conveyor Belt Width (mm) Conveyor Length (mtr) Total Weight (MT) Progress (MT) progress (%) Status/ Balance work Expected Days Remarks 1 7A 1400 622.441 230.25 230.25 100 Completed 2 7B 1400 624.254 225.60 225.60 100 Completed 3 7C 1400 626.741 229.21 177.00 77 1. Belt Laying & Jointing Balance. 2. Conveyor, Drive alignment & Cooling Water piping Balance. 3. Chute (2 nos) & Skirt Board Erection & alignment Balance. 20 1. PETRON scope, SEPCO has to give clearence. 4 7D 1400 625.629 228.61 160.00 70 1. Belt Laying & Jointing Balance. 2. Conveyor, Drive alignment & Cooling Water piping Balance. 3. Chute (2 nos) & Skirt Board Erection & alignment Balance.
  • 14. CONVEYOR 8ABCD STATUS / BALANCE WORK 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Conveyor 8A Conveyor 8B Conveyor 8C Conveyor 8D Completed Balance Sno. Conveyor Belt Width (mm) Conveyor Length (mtr) Total Weight (MT) Progress (MT) progress (%) Status/ Balance work Expected Days Remarks 1 8A 1400 281.32 85.04 85.04 100 Completed 2 8B 1400 284.82 84.88 84.88 100 Completed 3 8C 1400 1400 152.45 0.00 0 1. 80% structural work completed, balance work will compl after the MPH erection. 2. Deck Sheeting & flooring Balance. 3. Drive, Chutes & conveyor will compl. After MPH erection. 90 1. Work was under NEO scope. 2. SEPCO has informed NEO to stop the work. 3. SEPCO has to decide the contractor. 4. Critical work: Require T7 for structural work as well as mechanical work 4 8D 1400 1400 152.45 0.00 0 1. 80% structural work completed, balance work will compl after the MPH erection. 2. Deck Sheeting & flooring Balance. 3. Drive, Chutes & conveyor will compl. After MPH erection.
  • 15. CONVEYOR 10AB STATUS / BALANCE WORK 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Conveyor 10A Conveyor 10B Completed Balance Sno. Conveyor Belt Width (mm) Conveyor Length (mtr) Total Weight (MT) Progress (MT) progress (%) Status/ Balance work Expected Days Remarks 1 10A 1400 161.35 592.70 592.70 100 Completed 2 10B 1400 161.35 592.70 592.70 100 Completed
  • 16. CONVEYOR 12,13 &14 STATUS / BALANCE WORK 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Conveyor 12 Conveyor 13 Conveyor 14 Completed Balance Sno. Conveyor Belt Width (mm) Conveyor Length (mtr) Total Weight (MT) Progress (MT) progress (%) Status/ Balance work Expected Days Remarks 1 12 1400 482 145.03 145.03 100 Completed 2 13 1400 482 145.03 145.03 100 Completed 3 14 1400 482 145.03 0.00 0 1. Civil foundation(300 Mtrs) balance. 2. Conveyor Work not Started. 3. Chute Work Balance. 40 1. Civil has to give front. 2. PETRON scope, SEPCO has to give clearance.
  • 17. CONVEYOR 11AB STATUS / BALANCE WORK Conveyor 11A Completed 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Conveyor 11B Balance Sno. Conveyor Belt Width (mm) Conveyor Length (mtr) Total Weight (MT) Progress (MT) progress (%) Status/ Balance work Expected Days Remarks 1 11A 1400 278.20 139.12 139.12 100 Completed 1. Completed but need restoration for Unit # 1. 2. Critical work: Require MPH +41mtr floor from unit#1 to 6 for mechanical work. 2 11B 1400 278.20 139.12 139.12 100 Completed Conveyor 11A (Restoration) Completed 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Conveyor 11B (Restoration) Unit#6 Unit#5 Unit#4 Unit#3 Unit#2 Unit#1 FEEDING FEEDING FEEDING FEEDING FEEDING FEEDING Balance Conveyor 9 CD feeding Unit #4, 5 & 6 Conveyor 11 AB feeding Unit #1, 2 & 3 8CD 10AB