SlideShare a Scribd company logo
1 of 29
LECTURE 8 - DETERMINATION OF
OWN EMPLOYMENT BY
CONTRACTOR
YONG BOON XIONG - 0321754
YONG SEEN YEE - 0315883
DETERMINATION OF OWN EMPLOYMENT BY
CONTRACTOR
Clause 26.1 states that the Contractor MAY
determine his own employment if the Employer
defaults in any of the following, where the Employer:
 Cl 26.1(a) – Fails to pay the certified amount within the Period
of Honouring Certificates.
 Cl 26.1(b) – Interferes the issues of any Certificates.
 Cl 26.1(c) – Fails to nominate a succeeding Architect or
Consultant.
 Cl 26.1(d) – Suspends the work for a continuous period of
time exceeding the stated Period of Delay in Appendix.
CLAUSE 26.1(A) – EMPLOYER FAILED TO PAY
CERTIFIED AMOUNT
 Clause 30.1 – The Employer shall pay the Contractor the certified
sum within the Period of Honouring Certificate stated in
Appendix.
 Failure to pay = Breach of Contract
 The Contractor will be entitled to determine his own employment.
 Amount due on any certificate is subjected to deduction:
 Clause 22.1 – Liquidated Damages
 Clause 30.4 – Set-off
 However, the Employer has to inform the Contractor before
making any deduction to the amount in Certificate.
CLAUSE 26.1(B) – EMPLOYER INTERFERES
WITH ANY CERTIFICATE
 The Architect is required to act FAIRLY and WITHOUT BIAS.
 If the Employer interferes in the issuance of certificates such
as instructing the Architect to:
 delay the issuance of certificate or
 reduce the certified amount,
 The Contractor is entitled to determine his own employment
under Clause 26.1(b).
CLAUSE 26.1(C) – EMPLOYER FAILS TO APPOINT A
SUCCEEDING ARCHITECT/CONSULTANT
 Failure to appoint a replacement Person within a reasonable
time = Breach of express term of the contract.
 The Contractor must be able to establish the following to
prove the Employer is on default:
 The Architect or Consultant ceasing to act in that capacity.
 The failure of Employer to nominate a successor; and
 Such failure to confirm beyond the time period stated in the contract,
28 days.
 However, the Employer may request for an extension if he is
unable to find a replacement.
CLAUSE 26.1(D) – THE WORKS IS
SUSPENDED
 For the Contractor to determine his employment under Clause
26.1(d), he must prove the following:
 There was a suspension.
 The suspension exceeds a continuous period stated in the Period of
Delay in Appendix.
 The suspension must be due to one/more of the following events:
 AI issued by the Architect under Clause 1.4, 21.1 and 21.4.
 Architect’s inability to provide all necessary information requested by the
Contractor to carry out the Works.
 Contractor not having in due time the necessary for AI for the expenditure of PC
and Provisional Sum.
 Delay by works not forming part of Contract, e.g. Employer’s tradesmen.
 Opening up for inspection and test which later is found to be in accordance
with the contract.
PROCEDURE FOR DETERMINATION BY
CONTRACTOR
Under clause 26.2, the contractor must:
 Comply meticulously with the time table stated in
contract.
 Ensure that such notice must not be given
unreasonably or vexatious.
2-STEPS PROCEDURE FOR DETERMINATION
STEP 1:
 Issue written Notice of Default to Employer
 Employer has 14 Days to rectify the default
 Should Employer fails or neglect to act, then the
Contractor can trigger the next stage of the
determination process.
STEP 2:
 Issue actual written Notice of Determination within ten (10)
Days to determine his own employment.
 Vacate the Site
 To request for the date of inspection on site to jointly record
extent of work done and materials delivered.
 Submit final account
 Check final account and advise Employer. Any disputes from
Employer must be raised within 3 Months.
 Employer must submit their disagreement within 3 Months.
Besides, the Employer has 3 Months to refer the
disagreement on the final account to arbitration
 Clause 26.2 does not stipulate any option for the
revocation of the determination and resumption of
works. If such reinstatement were to arise, this has
to be effected through a separate agreement by
mutual consent of both parties.
AUTOMATIC DETERMINATION (CLAUSE 26.3)
If the Employer :
 Insolvent
 making a composition or arrangement with his
creditors
 Winding up order made
 Voluntary winding up
 Having a liquidator/receiver/manager of his
business of undertaking duly appointed by the
court; or
 Company taken over by holders of debentures
RIGHTS AND DUTIES OF EMPLOYER/CONTRACTOR
AFTER DETERMINATION (CLAUSE 26.4)
 Vacate the Site
 Demobilize all workers and remove all temporary
buildings, construction plants, and tools on the Site
 Employer must pay for loss and/or expense
suffered by the contractor
 Put a lien over any unfixed goods and materials
which are unpaid
 Strictly to the contractual procedures laid down in
Contract.
CONTRACTOR’S RIGHTS AND REMEDIES NOT
PREJUDICED (CLAUSE 26.7)
 The contractor can determine his own employment
either:
a. under the contract (clause 26.1), or
b. under common law.
 If the Contractor chooses to determine under the
contract and if such determination was eventually found
to be invalid, then he is bound by the contract
provisions.
 He cannot then resort to the common law rights of
determination as an alternative cause of action.
 Malayan Flour Sdn Bhd v Raja Lope & Tan Co & Anor
(1998) 6 MLJ 377.
 TUTORIAL QUESTIONS
QUESTION 1:
 If the project is suspended by the Employer for
more than 3 months due to design change, what
are the remedies available to the Contractor.
Discuss the conditions whereby the Contractor is
entitled to determine his Own Employment.
REMEDIES AVAILABLE TO THE CONTRACTOR
 Under Clause 24.1,
 The Contractor is entitled to claim for loss and expenses caused
by matters affecting the regular progress of the Works.
 Clause 24.3(c) states suspension of Works in compliance with AI as
matters affecting the regular progress of the Works.
 Under Clause 23.1,
 The Contractor is entitled to claim for extension of time.
 Clause 23.8(g) states compliance with AI under Clause 21.4
(Postponement of works) as the Relevant Events for EoT Claim.
 Under Clause 26.1(d),
 When the uncompleted Works is suspended for a continuous period
of time exceeding Period of Delay stated in the Appendix,
 The Contractor is entitled to determine his own employment
 For the Contractor to determine his employment under Clause
26.1(d), he must prove the following:
 There was a suspension.
 The suspension exceeds a continuous period stated in the Period of
Delay in Appendix.
 The suspension must be due to one/more of the following events:
 AI issued by the Architect under Clause 1.4, 21.1 and 21.4.
 Architect’s inability to provide all necessary information requested by the
Contractor to carry out the Works.
 Contractor not having in due time the necessary for AI for the expenditure of PC
and Provisional Sum.
 Delay by works not forming part of Contract, e.g. Employer’s tradesmen.
 Opening up for inspection and test which later is found to be in accordance
with the contract.
 QUESTION 2:
Discuss the checklist before the Contractor determine
his own employment. What is the procedure required
under PAM 2006 for determination of Contractor’s
Own Employment?
Under clause 26.2, the contractor must:
 Comply meticulously with the time table stated in
contract.
 Ensure that such notice must not be given
unreasonably or vexatious.
STEP 1:
 Issue written Notice of Default to Employer
 Employer has 14 Days to rectify the default
 Should Employer fails or neglect to act, then the
Contractor can trigger the next stage of the
determination process.
STEP 2:
 Issue actual written Notice of Determination within ten
(10) Days to determine his own employment.
 Vacate the Site
 To request for the date of inspection on site to jointly
record extent of work done and materials delivered.
 Submit final account
 Check final account and advise Employer. Any disputes
from Employer must be raised within 3 Months.
 Employer must submit their disagreement within 3
Months. Besides, the Employer has 3 Months to refer
the disagreement on the final account to arbitration
QUESTION 3:
 What happen if the Architect resigns from the
project and there is no replacement for 4 months?
 Architect is the person who responsible for
supervising the work on site.
 If the architect resigns, and no one can supervising
the work on site. The contractor must stop work.
 The contractor can terminate his own employment
where the whole project is suspended for a
continuous period of time exceeding the period
stated in the Period of Delay (if none is stated 3
months) in Appendix
 ADDITIONAL QUESTIONS
QUESTION 1:
What is the different situation between the employer
determinate the contractor’s employment and the
contractor determinate his own employment when the
contractor submit final account to QS ?
Answer:
 If the employer determinate the contractor’s
employment due to the contractor’s fault. The QS
will only issue the final account only after the
remaining works is completed by second (NEW)
contractor.
 If the contractor determinate his own employment
due to the employer’s fault. The QS will issue the
final account to the contactor. In this situation, the
contractor NO NEED wait after remaining works is
completed by second (NEW) contractor.
QUESTION 2:
Can the Contractor determine his own employment if
the Employer make deduction in the Interim
Certificate?
Answer:
 Yes, the Contractor may determine his own
employment under Clause 26.1(a).
 Unless the Employer made deduction based on the
following, which he is entitled to:
1.) Clause 22.1 – Liquidated Damages
2.) Clause 30.4 – Set-Off
THANK YOU

More Related Content

What's hot

Partial possession-by-employer-29052017-finalized (1)
Partial possession-by-employer-29052017-finalized (1)Partial possession-by-employer-29052017-finalized (1)
Partial possession-by-employer-29052017-finalized (1)Tee Joanne
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerKai Yun Pang
 
PP2 final report
PP2 final reportPP2 final report
PP2 final reportArissa Loh
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 이환
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC ContractKai Yun Pang
 
Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Arissa Loh
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
PP2 presentation
PP2 presentationPP2 presentation
PP2 presentationYong Sy
 
Substitute and vicarious_performance
Substitute and vicarious_performanceSubstitute and vicarious_performance
Substitute and vicarious_performanceHafizul Mukhlis
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentHaziq1511
 
07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-dericSyafiq Zariful
 
Law relating-to-payment
Law relating-to-paymentLaw relating-to-payment
Law relating-to-paymentArthur Wilson
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalKai Yun Pang
 
CL Final Report
CL Final ReportCL Final Report
CL Final ReportMelvin Lim
 

What's hot (20)

Partial possession-by-employer-29052017-finalized (1)
Partial possession-by-employer-29052017-finalized (1)Partial possession-by-employer-29052017-finalized (1)
Partial possession-by-employer-29052017-finalized (1)
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by Employer
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
 
Cl compilation
Cl compilationCl compilation
Cl compilation
 
PP2 final report
PP2 final reportPP2 final report
PP2 final report
 
Pp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangPp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyang
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
PP2 presentation
PP2 presentationPP2 presentation
PP2 presentation
 
Substitute and vicarious_performance
Substitute and vicarious_performanceSubstitute and vicarious_performance
Substitute and vicarious_performance
 
Pp2 final report
Pp2 final reportPp2 final report
Pp2 final report
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group Assignment
 
07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric
 
Site possession
Site possessionSite possession
Site possession
 
Defects liability
Defects liabilityDefects liability
Defects liability
 
Law relating-to-payment
Law relating-to-paymentLaw relating-to-payment
Law relating-to-payment
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost Appraisal
 
CL Final Report
CL Final ReportCL Final Report
CL Final Report
 

Similar to Lecture 8-determination-of-own-employment-by

Pp2 coursework 1 p10
Pp2 coursework 1 p10 Pp2 coursework 1 p10
Pp2 coursework 1 p10 Farah Sham
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
PP2 Seminar Presentation
PP2 Seminar PresentationPP2 Seminar Presentation
PP2 Seminar Presentationashleyyeap
 
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptxssuser6d14e4
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
Preserving Your Bottom Line
Preserving Your Bottom LinePreserving Your Bottom Line
Preserving Your Bottom LineCallPM
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation Lin Hui
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractAvinash Kumar Gupta
 
Pp2 assignment
Pp2 assignmentPp2 assignment
Pp2 assignmentfareezsham
 
Construction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual ClaimsConstruction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual ClaimsYee Len Wan
 
Suspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxSuspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxNathannielGonzales1
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - QuestionKai Yun Pang
 

Similar to Lecture 8-determination-of-own-employment-by (20)

Pp2 coursework 1 p10
Pp2 coursework 1 p10 Pp2 coursework 1 p10
Pp2 coursework 1 p10
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 
PP2 Seminar Presentation
PP2 Seminar PresentationPP2 Seminar Presentation
PP2 Seminar Presentation
 
Seminar p8x
Seminar p8xSeminar p8x
Seminar p8x
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
PP2 COMPILCATION
PP2 COMPILCATIONPP2 COMPILCATION
PP2 COMPILCATION
 
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx
257883989-Claim-in-Red-Book-FIdic-Presentation-ver03.pptx
 
Cl report final
Cl report finalCl report final
Cl report final
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Preserving Your Bottom Line
Preserving Your Bottom LinePreserving Your Bottom Line
Preserving Your Bottom Line
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction Contract
 
Pp2 assignment
Pp2 assignmentPp2 assignment
Pp2 assignment
 
Construction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual ClaimsConstruction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual Claims
 
Suspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxSuspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptx
 
Pp2 p7
Pp2   p7Pp2   p7
Pp2 p7
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - Question
 

More from seenyeeyong

Community service 2017 (1)
Community service 2017 (1)Community service 2017 (1)
Community service 2017 (1)seenyeeyong
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice IIseenyeeyong
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice IIseenyeeyong
 
Measurement Presentation
Measurement PresentationMeasurement Presentation
Measurement Presentationseenyeeyong
 
software assignment
software assignmentsoftware assignment
software assignmentseenyeeyong
 
ECA Presentation slide
ECA Presentation slideECA Presentation slide
ECA Presentation slideseenyeeyong
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practiceseenyeeyong
 
Estimating tender presentation
Estimating tender presentation Estimating tender presentation
Estimating tender presentation seenyeeyong
 
Estimating seminar presentation
Estimating seminar presentationEstimating seminar presentation
Estimating seminar presentationseenyeeyong
 

More from seenyeeyong (9)

Community service 2017 (1)
Community service 2017 (1)Community service 2017 (1)
Community service 2017 (1)
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice II
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice II
 
Measurement Presentation
Measurement PresentationMeasurement Presentation
Measurement Presentation
 
software assignment
software assignmentsoftware assignment
software assignment
 
ECA Presentation slide
ECA Presentation slideECA Presentation slide
ECA Presentation slide
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practice
 
Estimating tender presentation
Estimating tender presentation Estimating tender presentation
Estimating tender presentation
 
Estimating seminar presentation
Estimating seminar presentationEstimating seminar presentation
Estimating seminar presentation
 

Recently uploaded

VIP Call Girls Service Shamshabad Hyderabad Call +91-8250192130
VIP Call Girls Service Shamshabad Hyderabad Call +91-8250192130VIP Call Girls Service Shamshabad Hyderabad Call +91-8250192130
VIP Call Girls Service Shamshabad Hyderabad Call +91-8250192130Suhani Kapoor
 
Low Rate Call Girls Nagpur Esha Call 7001035870 Meet With Nagpur Escorts
Low Rate Call Girls Nagpur Esha Call 7001035870 Meet With Nagpur EscortsLow Rate Call Girls Nagpur Esha Call 7001035870 Meet With Nagpur Escorts
Low Rate Call Girls Nagpur Esha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
VIP Call Girls Service Secunderabad Hyderabad Call +91-8250192130
VIP Call Girls Service Secunderabad Hyderabad Call +91-8250192130VIP Call Girls Service Secunderabad Hyderabad Call +91-8250192130
VIP Call Girls Service Secunderabad Hyderabad Call +91-8250192130Suhani Kapoor
 
(ASHA) Sb Road Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(ASHA) Sb Road Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(ASHA) Sb Road Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(ASHA) Sb Road Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Affordable PriceD Call Girls In Crowne Plaza Greater Noida 8377877756 Short 2...
Affordable PriceD Call Girls In Crowne Plaza Greater Noida 8377877756 Short 2...Affordable PriceD Call Girls In Crowne Plaza Greater Noida 8377877756 Short 2...
Affordable PriceD Call Girls In Crowne Plaza Greater Noida 8377877756 Short 2...dollysharma2066
 
(PRIYANKA) Katraj Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune E...
(PRIYANKA) Katraj Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune E...(PRIYANKA) Katraj Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune E...
(PRIYANKA) Katraj Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune E...ranjana rawat
 
ΦΑΓΗΤΟ ΤΕΛΕΙΟ ΞΞΞΞΞΞΞ ΞΞΞΞΞΞ ΞΞΞΞ ΞΞΞΞ Ξ
ΦΑΓΗΤΟ ΤΕΛΕΙΟ ΞΞΞΞΞΞΞ ΞΞΞΞΞΞ ΞΞΞΞ ΞΞΞΞ ΞΦΑΓΗΤΟ ΤΕΛΕΙΟ ΞΞΞΞΞΞΞ ΞΞΞΞΞΞ ΞΞΞΞ ΞΞΞΞ Ξ
ΦΑΓΗΤΟ ΤΕΛΕΙΟ ΞΞΞΞΞΞΞ ΞΞΞΞΞΞ ΞΞΞΞ ΞΞΞΞ Ξlialiaskou00
 
College Call Girls Nashik Ria 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Ria 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Ria 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Ria 7001305949 Independent Escort Service Nashikranjana rawat
 
Call Girls Laxmi Nagar Delhi reach out to us at ☎ 9711199012
Call Girls Laxmi Nagar Delhi reach out to us at ☎ 9711199012Call Girls Laxmi Nagar Delhi reach out to us at ☎ 9711199012
Call Girls Laxmi Nagar Delhi reach out to us at ☎ 9711199012rehmti665
 
Chocolate Milk Flavorful Indulgence to RD UHT Innovations.pptx
Chocolate Milk Flavorful Indulgence to RD UHT Innovations.pptxChocolate Milk Flavorful Indulgence to RD UHT Innovations.pptx
Chocolate Milk Flavorful Indulgence to RD UHT Innovations.pptxRD Food
 
VIP Russian Call Girls in Cuttack Deepika 8250192130 Independent Escort Servi...
VIP Russian Call Girls in Cuttack Deepika 8250192130 Independent Escort Servi...VIP Russian Call Girls in Cuttack Deepika 8250192130 Independent Escort Servi...
VIP Russian Call Girls in Cuttack Deepika 8250192130 Independent Escort Servi...Suhani Kapoor
 
(SUNAINA) Call Girls Alandi Road ( 7001035870 ) HI-Fi Pune Escorts Service
(SUNAINA) Call Girls Alandi Road ( 7001035870 ) HI-Fi Pune Escorts Service(SUNAINA) Call Girls Alandi Road ( 7001035870 ) HI-Fi Pune Escorts Service
(SUNAINA) Call Girls Alandi Road ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
High Class Call Girls Nashik Priya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Priya 7001305949 Independent Escort Service NashikHigh Class Call Girls Nashik Priya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Priya 7001305949 Independent Escort Service Nashikranjana rawat
 
(办理学位证)加州大学圣塔芭芭拉分校毕业证成绩单原版一比一
(办理学位证)加州大学圣塔芭芭拉分校毕业证成绩单原版一比一(办理学位证)加州大学圣塔芭芭拉分校毕业证成绩单原版一比一
(办理学位证)加州大学圣塔芭芭拉分校毕业证成绩单原版一比一Fi sss
 
Russian Call Girls Nashik Riddhi 7001305949 Independent Escort Service Nashik
Russian Call Girls Nashik Riddhi 7001305949 Independent Escort Service NashikRussian Call Girls Nashik Riddhi 7001305949 Independent Escort Service Nashik
Russian Call Girls Nashik Riddhi 7001305949 Independent Escort Service Nashikranjana rawat
 
Dubai Call Girls Drilled O525547819 Call Girls Dubai (Raphie)
Dubai Call Girls Drilled O525547819 Call Girls Dubai (Raphie)Dubai Call Girls Drilled O525547819 Call Girls Dubai (Raphie)
Dubai Call Girls Drilled O525547819 Call Girls Dubai (Raphie)kojalkojal131
 
VIP Call Girls Nagpur Krisha Call 7001035870 Meet With Nagpur Escorts
VIP Call Girls Nagpur Krisha Call 7001035870 Meet With Nagpur EscortsVIP Call Girls Nagpur Krisha Call 7001035870 Meet With Nagpur Escorts
VIP Call Girls Nagpur Krisha Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Low Rate Call Girls Nashik Mahima 7001305949 Independent Escort Service Nashik
Low Rate Call Girls Nashik Mahima 7001305949 Independent Escort Service NashikLow Rate Call Girls Nashik Mahima 7001305949 Independent Escort Service Nashik
Low Rate Call Girls Nashik Mahima 7001305949 Independent Escort Service Nashikranjana rawat
 
Call Girl Nashik Khushi 7001305949 Independent Escort Service Nashik
Call Girl Nashik Khushi 7001305949 Independent Escort Service NashikCall Girl Nashik Khushi 7001305949 Independent Escort Service Nashik
Call Girl Nashik Khushi 7001305949 Independent Escort Service Nashikranjana rawat
 

Recently uploaded (20)

VIP Call Girls Service Shamshabad Hyderabad Call +91-8250192130
VIP Call Girls Service Shamshabad Hyderabad Call +91-8250192130VIP Call Girls Service Shamshabad Hyderabad Call +91-8250192130
VIP Call Girls Service Shamshabad Hyderabad Call +91-8250192130
 
Low Rate Call Girls Nagpur Esha Call 7001035870 Meet With Nagpur Escorts
Low Rate Call Girls Nagpur Esha Call 7001035870 Meet With Nagpur EscortsLow Rate Call Girls Nagpur Esha Call 7001035870 Meet With Nagpur Escorts
Low Rate Call Girls Nagpur Esha Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Secunderabad Hyderabad Call +91-8250192130
VIP Call Girls Service Secunderabad Hyderabad Call +91-8250192130VIP Call Girls Service Secunderabad Hyderabad Call +91-8250192130
VIP Call Girls Service Secunderabad Hyderabad Call +91-8250192130
 
(ASHA) Sb Road Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(ASHA) Sb Road Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(ASHA) Sb Road Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(ASHA) Sb Road Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Affordable PriceD Call Girls In Crowne Plaza Greater Noida 8377877756 Short 2...
Affordable PriceD Call Girls In Crowne Plaza Greater Noida 8377877756 Short 2...Affordable PriceD Call Girls In Crowne Plaza Greater Noida 8377877756 Short 2...
Affordable PriceD Call Girls In Crowne Plaza Greater Noida 8377877756 Short 2...
 
(PRIYANKA) Katraj Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune E...
(PRIYANKA) Katraj Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune E...(PRIYANKA) Katraj Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune E...
(PRIYANKA) Katraj Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune E...
 
ΦΑΓΗΤΟ ΤΕΛΕΙΟ ΞΞΞΞΞΞΞ ΞΞΞΞΞΞ ΞΞΞΞ ΞΞΞΞ Ξ
ΦΑΓΗΤΟ ΤΕΛΕΙΟ ΞΞΞΞΞΞΞ ΞΞΞΞΞΞ ΞΞΞΞ ΞΞΞΞ ΞΦΑΓΗΤΟ ΤΕΛΕΙΟ ΞΞΞΞΞΞΞ ΞΞΞΞΞΞ ΞΞΞΞ ΞΞΞΞ Ξ
ΦΑΓΗΤΟ ΤΕΛΕΙΟ ΞΞΞΞΞΞΞ ΞΞΞΞΞΞ ΞΞΞΞ ΞΞΞΞ Ξ
 
College Call Girls Nashik Ria 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Ria 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Ria 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Ria 7001305949 Independent Escort Service Nashik
 
Call Girls Laxmi Nagar Delhi reach out to us at ☎ 9711199012
Call Girls Laxmi Nagar Delhi reach out to us at ☎ 9711199012Call Girls Laxmi Nagar Delhi reach out to us at ☎ 9711199012
Call Girls Laxmi Nagar Delhi reach out to us at ☎ 9711199012
 
Chocolate Milk Flavorful Indulgence to RD UHT Innovations.pptx
Chocolate Milk Flavorful Indulgence to RD UHT Innovations.pptxChocolate Milk Flavorful Indulgence to RD UHT Innovations.pptx
Chocolate Milk Flavorful Indulgence to RD UHT Innovations.pptx
 
VIP Russian Call Girls in Cuttack Deepika 8250192130 Independent Escort Servi...
VIP Russian Call Girls in Cuttack Deepika 8250192130 Independent Escort Servi...VIP Russian Call Girls in Cuttack Deepika 8250192130 Independent Escort Servi...
VIP Russian Call Girls in Cuttack Deepika 8250192130 Independent Escort Servi...
 
(SUNAINA) Call Girls Alandi Road ( 7001035870 ) HI-Fi Pune Escorts Service
(SUNAINA) Call Girls Alandi Road ( 7001035870 ) HI-Fi Pune Escorts Service(SUNAINA) Call Girls Alandi Road ( 7001035870 ) HI-Fi Pune Escorts Service
(SUNAINA) Call Girls Alandi Road ( 7001035870 ) HI-Fi Pune Escorts Service
 
High Class Call Girls Nashik Priya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Priya 7001305949 Independent Escort Service NashikHigh Class Call Girls Nashik Priya 7001305949 Independent Escort Service Nashik
High Class Call Girls Nashik Priya 7001305949 Independent Escort Service Nashik
 
(办理学位证)加州大学圣塔芭芭拉分校毕业证成绩单原版一比一
(办理学位证)加州大学圣塔芭芭拉分校毕业证成绩单原版一比一(办理学位证)加州大学圣塔芭芭拉分校毕业证成绩单原版一比一
(办理学位证)加州大学圣塔芭芭拉分校毕业证成绩单原版一比一
 
Russian Call Girls Nashik Riddhi 7001305949 Independent Escort Service Nashik
Russian Call Girls Nashik Riddhi 7001305949 Independent Escort Service NashikRussian Call Girls Nashik Riddhi 7001305949 Independent Escort Service Nashik
Russian Call Girls Nashik Riddhi 7001305949 Independent Escort Service Nashik
 
Dubai Call Girls Drilled O525547819 Call Girls Dubai (Raphie)
Dubai Call Girls Drilled O525547819 Call Girls Dubai (Raphie)Dubai Call Girls Drilled O525547819 Call Girls Dubai (Raphie)
Dubai Call Girls Drilled O525547819 Call Girls Dubai (Raphie)
 
VIP Call Girls Nagpur Krisha Call 7001035870 Meet With Nagpur Escorts
VIP Call Girls Nagpur Krisha Call 7001035870 Meet With Nagpur EscortsVIP Call Girls Nagpur Krisha Call 7001035870 Meet With Nagpur Escorts
VIP Call Girls Nagpur Krisha Call 7001035870 Meet With Nagpur Escorts
 
Low Rate Call Girls Nashik Mahima 7001305949 Independent Escort Service Nashik
Low Rate Call Girls Nashik Mahima 7001305949 Independent Escort Service NashikLow Rate Call Girls Nashik Mahima 7001305949 Independent Escort Service Nashik
Low Rate Call Girls Nashik Mahima 7001305949 Independent Escort Service Nashik
 
9953330565 Low Rate Call Girls In Sameypur-Bodli Delhi NCR
9953330565 Low Rate Call Girls In Sameypur-Bodli Delhi NCR9953330565 Low Rate Call Girls In Sameypur-Bodli Delhi NCR
9953330565 Low Rate Call Girls In Sameypur-Bodli Delhi NCR
 
Call Girl Nashik Khushi 7001305949 Independent Escort Service Nashik
Call Girl Nashik Khushi 7001305949 Independent Escort Service NashikCall Girl Nashik Khushi 7001305949 Independent Escort Service Nashik
Call Girl Nashik Khushi 7001305949 Independent Escort Service Nashik
 

Lecture 8-determination-of-own-employment-by

  • 1. LECTURE 8 - DETERMINATION OF OWN EMPLOYMENT BY CONTRACTOR YONG BOON XIONG - 0321754 YONG SEEN YEE - 0315883
  • 2. DETERMINATION OF OWN EMPLOYMENT BY CONTRACTOR Clause 26.1 states that the Contractor MAY determine his own employment if the Employer defaults in any of the following, where the Employer:  Cl 26.1(a) – Fails to pay the certified amount within the Period of Honouring Certificates.  Cl 26.1(b) – Interferes the issues of any Certificates.  Cl 26.1(c) – Fails to nominate a succeeding Architect or Consultant.  Cl 26.1(d) – Suspends the work for a continuous period of time exceeding the stated Period of Delay in Appendix.
  • 3. CLAUSE 26.1(A) – EMPLOYER FAILED TO PAY CERTIFIED AMOUNT  Clause 30.1 – The Employer shall pay the Contractor the certified sum within the Period of Honouring Certificate stated in Appendix.  Failure to pay = Breach of Contract  The Contractor will be entitled to determine his own employment.  Amount due on any certificate is subjected to deduction:  Clause 22.1 – Liquidated Damages  Clause 30.4 – Set-off  However, the Employer has to inform the Contractor before making any deduction to the amount in Certificate.
  • 4. CLAUSE 26.1(B) – EMPLOYER INTERFERES WITH ANY CERTIFICATE  The Architect is required to act FAIRLY and WITHOUT BIAS.  If the Employer interferes in the issuance of certificates such as instructing the Architect to:  delay the issuance of certificate or  reduce the certified amount,  The Contractor is entitled to determine his own employment under Clause 26.1(b).
  • 5. CLAUSE 26.1(C) – EMPLOYER FAILS TO APPOINT A SUCCEEDING ARCHITECT/CONSULTANT  Failure to appoint a replacement Person within a reasonable time = Breach of express term of the contract.  The Contractor must be able to establish the following to prove the Employer is on default:  The Architect or Consultant ceasing to act in that capacity.  The failure of Employer to nominate a successor; and  Such failure to confirm beyond the time period stated in the contract, 28 days.  However, the Employer may request for an extension if he is unable to find a replacement.
  • 6. CLAUSE 26.1(D) – THE WORKS IS SUSPENDED  For the Contractor to determine his employment under Clause 26.1(d), he must prove the following:  There was a suspension.  The suspension exceeds a continuous period stated in the Period of Delay in Appendix.  The suspension must be due to one/more of the following events:  AI issued by the Architect under Clause 1.4, 21.1 and 21.4.  Architect’s inability to provide all necessary information requested by the Contractor to carry out the Works.  Contractor not having in due time the necessary for AI for the expenditure of PC and Provisional Sum.  Delay by works not forming part of Contract, e.g. Employer’s tradesmen.  Opening up for inspection and test which later is found to be in accordance with the contract.
  • 7. PROCEDURE FOR DETERMINATION BY CONTRACTOR Under clause 26.2, the contractor must:  Comply meticulously with the time table stated in contract.  Ensure that such notice must not be given unreasonably or vexatious.
  • 8. 2-STEPS PROCEDURE FOR DETERMINATION STEP 1:  Issue written Notice of Default to Employer  Employer has 14 Days to rectify the default  Should Employer fails or neglect to act, then the Contractor can trigger the next stage of the determination process.
  • 9. STEP 2:  Issue actual written Notice of Determination within ten (10) Days to determine his own employment.  Vacate the Site  To request for the date of inspection on site to jointly record extent of work done and materials delivered.  Submit final account  Check final account and advise Employer. Any disputes from Employer must be raised within 3 Months.  Employer must submit their disagreement within 3 Months. Besides, the Employer has 3 Months to refer the disagreement on the final account to arbitration
  • 10.  Clause 26.2 does not stipulate any option for the revocation of the determination and resumption of works. If such reinstatement were to arise, this has to be effected through a separate agreement by mutual consent of both parties.
  • 11. AUTOMATIC DETERMINATION (CLAUSE 26.3) If the Employer :  Insolvent  making a composition or arrangement with his creditors  Winding up order made  Voluntary winding up  Having a liquidator/receiver/manager of his business of undertaking duly appointed by the court; or  Company taken over by holders of debentures
  • 12. RIGHTS AND DUTIES OF EMPLOYER/CONTRACTOR AFTER DETERMINATION (CLAUSE 26.4)  Vacate the Site  Demobilize all workers and remove all temporary buildings, construction plants, and tools on the Site  Employer must pay for loss and/or expense suffered by the contractor  Put a lien over any unfixed goods and materials which are unpaid  Strictly to the contractual procedures laid down in Contract.
  • 13. CONTRACTOR’S RIGHTS AND REMEDIES NOT PREJUDICED (CLAUSE 26.7)  The contractor can determine his own employment either: a. under the contract (clause 26.1), or b. under common law.  If the Contractor chooses to determine under the contract and if such determination was eventually found to be invalid, then he is bound by the contract provisions.  He cannot then resort to the common law rights of determination as an alternative cause of action.  Malayan Flour Sdn Bhd v Raja Lope & Tan Co & Anor (1998) 6 MLJ 377.
  • 15. QUESTION 1:  If the project is suspended by the Employer for more than 3 months due to design change, what are the remedies available to the Contractor. Discuss the conditions whereby the Contractor is entitled to determine his Own Employment.
  • 16. REMEDIES AVAILABLE TO THE CONTRACTOR  Under Clause 24.1,  The Contractor is entitled to claim for loss and expenses caused by matters affecting the regular progress of the Works.  Clause 24.3(c) states suspension of Works in compliance with AI as matters affecting the regular progress of the Works.  Under Clause 23.1,  The Contractor is entitled to claim for extension of time.  Clause 23.8(g) states compliance with AI under Clause 21.4 (Postponement of works) as the Relevant Events for EoT Claim.  Under Clause 26.1(d),  When the uncompleted Works is suspended for a continuous period of time exceeding Period of Delay stated in the Appendix,  The Contractor is entitled to determine his own employment
  • 17.  For the Contractor to determine his employment under Clause 26.1(d), he must prove the following:  There was a suspension.  The suspension exceeds a continuous period stated in the Period of Delay in Appendix.  The suspension must be due to one/more of the following events:  AI issued by the Architect under Clause 1.4, 21.1 and 21.4.  Architect’s inability to provide all necessary information requested by the Contractor to carry out the Works.  Contractor not having in due time the necessary for AI for the expenditure of PC and Provisional Sum.  Delay by works not forming part of Contract, e.g. Employer’s tradesmen.  Opening up for inspection and test which later is found to be in accordance with the contract.
  • 18.  QUESTION 2: Discuss the checklist before the Contractor determine his own employment. What is the procedure required under PAM 2006 for determination of Contractor’s Own Employment?
  • 19. Under clause 26.2, the contractor must:  Comply meticulously with the time table stated in contract.  Ensure that such notice must not be given unreasonably or vexatious.
  • 20. STEP 1:  Issue written Notice of Default to Employer  Employer has 14 Days to rectify the default  Should Employer fails or neglect to act, then the Contractor can trigger the next stage of the determination process.
  • 21. STEP 2:  Issue actual written Notice of Determination within ten (10) Days to determine his own employment.  Vacate the Site  To request for the date of inspection on site to jointly record extent of work done and materials delivered.  Submit final account  Check final account and advise Employer. Any disputes from Employer must be raised within 3 Months.  Employer must submit their disagreement within 3 Months. Besides, the Employer has 3 Months to refer the disagreement on the final account to arbitration
  • 22. QUESTION 3:  What happen if the Architect resigns from the project and there is no replacement for 4 months?
  • 23.  Architect is the person who responsible for supervising the work on site.  If the architect resigns, and no one can supervising the work on site. The contractor must stop work.  The contractor can terminate his own employment where the whole project is suspended for a continuous period of time exceeding the period stated in the Period of Delay (if none is stated 3 months) in Appendix
  • 25. QUESTION 1: What is the different situation between the employer determinate the contractor’s employment and the contractor determinate his own employment when the contractor submit final account to QS ?
  • 26. Answer:  If the employer determinate the contractor’s employment due to the contractor’s fault. The QS will only issue the final account only after the remaining works is completed by second (NEW) contractor.  If the contractor determinate his own employment due to the employer’s fault. The QS will issue the final account to the contactor. In this situation, the contractor NO NEED wait after remaining works is completed by second (NEW) contractor.
  • 27. QUESTION 2: Can the Contractor determine his own employment if the Employer make deduction in the Interim Certificate?
  • 28. Answer:  Yes, the Contractor may determine his own employment under Clause 26.1(a).  Unless the Employer made deduction based on the following, which he is entitled to: 1.) Clause 22.1 – Liquidated Damages 2.) Clause 30.4 – Set-Off