SlideShare a Scribd company logo
1 of 21
Download to read offline
Bob Prieto, Fluor Page 1 11/29/2011
Program Management Audit Checklist
Prepared by: Bob Prieto
Senior Vice President
Fluor
March 27, 2008
This audit checklist is designed to complement other owner, program manager and
contractually required audit checklists. The purpose of this checklist is to ensure that
continued focus is paid on achieving the strategic business outcomes that the program is
intended to address.
Bob Prieto, Fluor Page 2 11/29/2011
Program Management Audit Checklist
Audit Element Owner’s Focus Program Manager’s
Focus
Program Plan Does formal program plan
exist?
Is program plan being
utilizing and maintained up
to date?
Are Owner and Program
Manager efforts aligned
with this plan?
Are projects and program
management organizational
elements aligned with the
program plan?
Is Program Manager
utilizing and maintaining an
up to date Program Plan in
the management of his
activities?
Are projects and program
management organizational
elements utilizing and
maintaining an up to date
plan?
Bob Prieto, Fluor Page 3 11/29/2011
Program Management Audit Checklist
Audit Element Owner’s Focus Program Manager’s
Focus
Stakeholder Management Have all Stakeholder’s at
the Program level been
identified?
Does a Stakeholder
Management plan exist; are
responsibilities apportioned
between Owner, Program
Manager and respective
Projects; and being utilized
and maintained up to date?
Does a Stakeholder
Management plan exist;
responsibilities apportioned
between Owner and
Program Manager; and
being utilized and
maintained up to date?
Do the individual projects
have stakeholder
management and third
party interface plans in
place, are they being
utilized and maintained up
to date?
Bob Prieto, Fluor Page 4 11/29/2011
Program Management Audit Checklist
Audit Element Owner’s Focus Program Manager’s
Focus
Communications Plan Does external
communications plan exist
and is it being
implemented?
Is a comprehensive internal
Communication Plan in
place and being adequately
implemented across all
projects?
Has Program Manager
developed and
implemented a robust
internal communications
plan?
Have individual projects put
in place and required
project level communication
plans and taken steps to
implement any
communication
requirements assigned to
them by the internal
program Communication
Plan.
Bob Prieto, Fluor Page 5 11/29/2011
Program Management Audit Checklist
Audit Element Owner’s Focus Program Manager’s
Focus
Program Management Have key strategic
business objectives been
clearly communicated in a
consistent way to the
Owner’s and Program
Manager’s team?
Have program goals and
strategic business
objectives been
incorporated into each of
the framework processes?
Have the key elements of a
coherent program
management strategy been
established?
a. Program monitoring and
measurement plan &
methodology (key metrics)
b. Program status reporting
structure & process
c. Change Management
plan
d. Issues Management
process
e. Risk Management Plan
Are framework processes
providing the Program
Manager with the
necessary tools and
information to manage and
track overall program
progress; are cross cutting
trends being adequately
identified, analyzed and
managed?
Has the Program Manager
implemented all required
framework processes and
are those processes
producing the desired
outcomes?
Are project level
management systems in
place and providing
required programmatic data
in a timely way; are project
level management systems
being adequately used to
accomplish project level
activities?
Bob Prieto, Fluor Page 6 11/29/2011
Program Management Audit Checklist
Audit Element Owner’s Focus Program Manager’s
Focus
Program Scheduling &
Tracking
Are external factors
sufficiently reflected in the
overall program schedule?
Are external factors
reflected in the overall
program schedule being
actively managed by the
Program Management
organization?
Are identified risk factors
being actively managed
and tracked by the Owner’s
organization or Program
Manager as appropriate?
Are identified risk factors
being actively managed
and tracked by the Program
Management organization
or projects, as appropriate?
Is Program Manager
adequately identifying
systemic program issues
affecting schedule and
recommending corrective or
risk limiting actions?
Are the organizational
elements of the Program
Manager adequately
identifying, analyzing and
recommending and
implementing corrective
action for systemic risks?
Are projects adequately
identifying issues affecting
schedule and taking
corrective actions?
Are program and project
level milestones being
adequately tracked and
managed?
Have activity relationships
and interdependencies
within tasks and across
projects been adequately
identified?
Are changes in deliverable
commitments agreed to by
all affected groups &
individuals?
Bob Prieto, Fluor Page 7 11/29/2011
Program Management Audit Checklist
Audit Element Owner’s Focus Program Manager’s
Focus
Program Status
Reporting
Is program status reviewed
with Program Manager at
appropriate intervals?
a. Overall status
b. Program performance
(achievements &
milestones)
c. Open issues
d. Risks
e. Action items
f. Cost & time performance
against plan
g. Quality metrics
h. Involvement by ALL
relevant Owner’s
organizational elements.
Is project status reviewed
with senior management of
projects at appropriate
intervals?
a. Overall status
b. Project performance
(achievements &
milestones)
c. Open issues
d. Risks
e. Action items
f. Cost & time performance
against plan
g. Quality metrics
h. Change Impact
Assessment
i. Interface management
j. Involvement by all
relevant Program Manager
organizational elements
Have adequate procedures
been put in place for project
coordination and status
reporting across project
boundaries by the Program
Manager?
Bob Prieto, Fluor Page 8 11/29/2011
Program Management Audit Checklist
Audit Element Owner’s Focus Program Manager’s
Focus
Program Budget &
Forecast
Do Program estimates
reflect both risks associated
with quantity uncertainties
as well as possible risk
events?
Are program activity
budgets clearly assigned
within the Program
Manager’s organization?
Are risk allocation and
management
responsibilities between the
Owner and Program
Manager clearly defined?
Are risk pools
comprehensively defined
and actively managed? Are
systemic cost drivers being
adequately tracked?
Is the Program Manager
adequately managing risk
pools within his purview?
Are projects accurately
measuring progress and
adequately forecasting
trends and opportunities for
cost savings?
Bob Prieto, Fluor Page 9 11/29/2011
Program Management Audit Checklist
Audit Element Owner’s Focus Program Manager’s
Focus
Risk Management Is an up to date Program
wide risk assessment in
place at the Owner’s level?
Is the Program Manager’s
risk assessment and
management process being
adequately implemented
and is it providing timely
actionable information for
the Program Manager and
Owner?
Is the Program Manager’s
risk assessment and
management process being
adequately implemented
and is it providing timely
actionable information for
the Program Manager and
Owner?
Are significant changes in
risk posture or the
emergence of new risks
being adequately identified
across all projects and
program management
activities being actively
managed and tracked?
Are significant changes in
risk posture or the
emergence of new risks
being adequately identified
by the Program Manager,
managed and tracked?
Are significant changes in
risk posture or the
emergence of new risks
being adequately identified
by projects, managed and
tracked?
Bob Prieto, Fluor Page 10 11/29/2011
Program Management Audit Checklist
Audit Element Owner’s Focus Program Manager’s
Focus
Quality Management Does the program have a
‘Quality Culture’?
Has the program quality
culture been adequately
flowed down to projects and
key suppliers?
Does the Program Manager
have a Quality Plan
covering all Policies,
Guidelines and
Procedures?
Are quality related policies,
guidelines and procedures
clearly communicated,
trained, implemented and
assured?
Quality Assurance Has an overall Quality
Assurance Plan been
developed and
implemented by the
Program Manager for the
program in accordance with
program needs and
contract requirements?
Has the programmatic
quality assurance program
been translated into specific
quality plans for all
elements of the program
management organization
as well as for individual
projects and key supply
chain activities?
Is the implemented Quality
Assurance program
supporting the meeting of
the strategic business
objectives defined?
Are quality programs
implemented at the project
level providing timely
identification and mitigation
of quality affecting issues?
Are programmatic quality
findings and lessons
learned being effectively
incorporated into new
planned activities and
transmitted across all
projects in a timely
manner?
Bob Prieto, Fluor Page 11 11/29/2011
Program Management Audit Checklist
Audit Element Owner’s Focus Program Manager’s
Focus
Management Procedures Does the Program Manager
have in place and is he
implementing a
comprehensive and
integrated set of
management procedures
that provide assurance of
achievement of the
program’s strategic
business objectives?
Are all elements of the
program management
organization implementing
established management
procedures? Are these
procedures providing
adequate control of
program activities and will
they support the delivery of
strategic business
objectives?
Are the implemented
procedures being
comprehensively applied
across all framework
processes?
Have projects and key
suppliers put in place the
necessary procedures to
manage their work efforts
and provide sufficient
management information to
the Program Manager to
facilitate overall program
management? Are the
procedures being
effectively implemented and
are they causing the
required results?
Are resources applied by
the program manager
adequately forecast,
controlled and tracked to
assure program efficiency?
Are management resources
applied at the project level
adequate to manage the
assigned tasks
successfully?
Have the personnel with the
necessary skills and
competence been identified
and has agreement for their
participation in the program
been reached?
Have the projects been
resourced with the requisite
number of skilled personnel
consistent with overall
program and contract
requirements?
Does the detailed program
work plan match the
complexity of tasks with the
capabilities of personnel?
Is the project work plan
sufficiently detailed,
resourced and measured to
assure progress in
accordance with project
requirements is being
achieved?
Has appropriate allowance
been made for the effect of
Has adequate allowance
been made for mobilization,
Bob Prieto, Fluor Page 12 11/29/2011
the learning curve on all
personnel joining the
program who do not have
the required prior project
execution methodology
(program management)
industry, functional &
technical expertise?
interfaces and
demobilization?
Are project team members
committed full-time?
Bob Prieto, Fluor Page 13 11/29/2011
Program Management Audit Checklist
Audit Element Owner’s Focus Program Manager’s
Focus
Design & Analysis Are requirements & design
standards in place?
Have design standards
been promulgated and
design changes controlled
to promote the maximum
standardization possible on
a programmatic basis?
Are required design QA
programs being
implemented by the
program manager?
Are specifications clearly
traceable from physical
design to logical
requirements?
Have programmatic efforts
related to standardization,
modularization and
increased focus on
constructability been
sufficiently realized?
Do the design specification
documents reference:
a. Purpose / scope?
b. Requirements
specifications?
c. Modularized or other
standard components
d. Technical environment
specification?
e. Constraints and
interfaces?
f. Commissioning, startup
and testing requirements?
Have design elements of
the program utilized
qualified designers and
checkers?
Are design QA and QC
activities sufficiently
documented?
Bob Prieto, Fluor Page 14 11/29/2011
Program Management Audit Checklist
Audit Element Owner’s Focus Program Manager’s
Focus
Construction Are intermediate
construction milestones
being met?
Have the
interaction/interference
between all projects been
adequately reflected on the
master program schedule?
Is the quality of construction
consistent with the
program’s strategic
business objectives?
Has due consideration
been given to supply chain
delivery times and changing
logistical requirements?
Is construction productivity
being enhanced throughout
the program through use of
standardization,
simplification of details and
application of programmatic
type contracts?
Are construction activities
for individual projects well
planned, crews adequately
prepared and equipped for
the tasks to be undertaken
each day and have site or
task safety hazards been
adequately communicated
and necessary protective
measures taken?
Is construction productivity
assessed at the project
level and programmatically
assessed across like
activities?
Are lessons learned within
the program being
transferred back across all
projects?
Bob Prieto, Fluor Page 15 11/29/2011
Program Management Audit Checklist
Audit Element Owner’s Focus Program Manager’s
Focus
Operations &
Maintenance
Do adequate operations
procedures exist?
Have commissioning and
over activities been
adequately planned;
Owner’s interfaces clearly
defined and project level
requirement fully
addressed?
Are Maintenance Metrics
defined and in place?
Are responsibilities for
warranty management pre-
and post-commissioning
well defined and adequately
managed?
Is there an improvement
program in place?
Is there a warranty
management program in-
place for the post
commissioning period?
Bob Prieto, Fluor Page 16 11/29/2011
Program Management Audit Checklist
Audit Element Owner’s Focus Program Manager’s
Focus
Financial Integrity Are financial management
controls in place to ensure
the integrity of financial
operations, disbursement of
funds, payment to vendors,
management of escrow and
reserve accounts,
maintenance of insurance,
accounting for capital
assets and in-process
materials, and other
financial activities
conducted by the Owner or
the Program Manager on
behalf of the Owner?
Are financial systems and
controls, including external
audit functions fully in place
and adequately staffed with
qualified staff?
Have required financial
audit activities been fully
carried out?
Have audits of vendor,
contractor and other
supplier pay records and
documentation been carried
out and to the extent
required have similar sub-
tier activities been audited
for compliance with any
such requirements?
Have all audit findings been
communicated as
appropriate and
subsequently satisfactorily
closed out?
Have all identified
corrective actions been
taken?
Has all supporting
documentation required by
the Owner been completed
and archived as
appropriate?
Are open claims and
disputes tracked, resolved
in a timely manner and
closed out?
Bob Prieto, Fluor Page 17 11/29/2011
Program Management Audit Checklist
Audit Element Owner’s Focus Program Manager’s
Focus
Contract Management Has Owner’s organization
and Program Manager
efficiently all contract
administration processes
between them so as not to
impact overall program
performance?
Have each of the following
contract management
activities occurred for
projects and suppliers
agreements?
• Evaluate contractor
performance or
deliverables.
• Verify and document
evidence of actual or
potential performance
problems, constructive
changes, or other
deviations.
• Determine potential
impact of technical issues
on cost, schedule, and
delivery; and
investigate/resolve rationale
for potential or actual
delays.
• Specify technical criteria
for the quality of the
product, in-process test
procedures and test
points, and acceptance
criteria through engineering
analysis.
• Assess performance,
quality, and other technical
issues and provide
technical evaluation
to contracts for adjustment
to, modification of, or
compliance with the
contract.
Bob Prieto, Fluor Page 18 11/29/2011
Program Management Audit Checklist
Audit Element Owner’s Focus Program Manager’s
Focus
Contract Management
(continued)
Have each of the following
contract management
activities occurred for
projects and suppliers
agreements?
• Analyze performance data
for trends and issues.
Resolve issues in data
quality and performance
quality.
• Monitor the risk
management process to
identify technical risk, as
well as cost, schedule,
and performance risk.
• Review change proposals
and alterations impacts on
cost and schedule to
ensure that adequate
funding is available and that
schedules imposed in the
contract are not affected.
• Review requests for
waivers and deviations from
contractor and field
activities to determine the
impact on system reliability
and performance, as well
as on cost and schedule.
• Review change proposals
for need, technical
adequacy of design,
consistency with program
objectives, impact on
operations, producibility,
quality and similar
programmatic concerns;
and ensure that proposed
changes are within the
scope of the
contract.
.
Bob Prieto, Fluor Page 19 11/29/2011
Program Management Audit Checklist
Audit Element Owner’s Focus Program Manager’s
Focus
Contract Management
(continued)
Have each of the following
contract management
activities occurred for
projects and suppliers
agreements?
• Conduct a cost-benefit
analysis of the Value
Engineering Change
Proposal
• Participate in design
review planning meetings,
in the event of potential
impact to the contract (e.g.,
constructive change
clauses, etc.) and conduct
design reviews.
• Support baseline reviews
process.
• Track corrective actions
and interfaces with the
contractor during project
reviews until they are
complete.
• Ensure compliance with
the configuration
management requirements
of the contract and
consistency with the
acquisition strategy, such
as the decision to buy data
rights or other strategies to
ensure that a second
source can build the
hardware.
Bob Prieto, Fluor Page 20 11/29/2011
Program Management Audit Checklist
Audit Element Owner’s Focus Program Manager’s
Focus
Contract Management
(continued)
Have all necessary contract
close-out activities
occurred? These include:
• Assess the impact of stop
work orders on contractor
performance of the
technical and programmatic
requirements. Recommend
stop work when contractor
deficiencies are expected to
result in delivery of
nonconforming technical
products. Evaluate
contractor proposals to stop
work for technical reasons.
• Ensure that engineering
contractors are responsible
for the professional quality,
technical accuracy, and
coordination of all services
required under their
contracts and that
firms are held liable for
costs resulting from errors
or deficiencies in designs
furnished under its contract.
• Settle all outstanding
claims, issues or disputes;
respond to contractor
claims for additional money
or contract adjustment, and
determine if it constitutes a
payable claim.
• Verify that the contract is
physically complete through
physical and functional
configuration audits.
Bob Prieto, Fluor Page 21 11/29/2011
Program Management Audit Checklist
Audit Element Owner’s Focus Program Manager’s
Focus
Contract Management
(continued)
Have each of the following
contract management
activities occurred for
projects and suppliers
agreements?
• Obtain all forms, reports,
and clearances required at
closeout from both Owner
and contractor activities,
and ensure that they have
met all applicable terms
and conditions for closeout.
• Make final payment
• Prepare contract
completion documentation.
• Assist Owner in identifying
or settling unresolved
issues, such as
performance issues,
unresolved Value
Engineering Change
Proposals, etc.
• Dispose of surplus
property property that the
Owner does not wish to
retain.

More Related Content

What's hot

Project Quality Management - PMBOK
Project Quality Management - PMBOKProject Quality Management - PMBOK
Project Quality Management - PMBOKArief Rahmana
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)Anand Subramaniam
 
TBO PMO Model
TBO PMO ModelTBO PMO Model
TBO PMO Modeltholtz11
 
Risk and issue management
Risk and issue managementRisk and issue management
Risk and issue managementThomas Petite
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management FundamentalsNishant Munjal
 
What is Program Management - An Overview
What is Program Management - An OverviewWhat is Program Management - An Overview
What is Program Management - An OverviewYolanda Williams
 
PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality managementejlp12
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Jeremy Jay Lim
 
Prince2 explained in 30mins
Prince2 explained in 30minsPrince2 explained in 30mins
Prince2 explained in 30minsILX Group
 
PgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint PresentationPgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint PresentationOsama Zarzour
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and TechniquesMaRS Discovery District
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementKris Kimmerle
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasMazen Zbib
 
Project Management
Project ManagementProject Management
Project ManagementMark Roman
 
Project management
Project managementProject management
Project managementJay Raval
 

What's hot (20)

Program Management Deployment Concept Consulting
Program Management Deployment Concept ConsultingProgram Management Deployment Concept Consulting
Program Management Deployment Concept Consulting
 
Overview of Program Management
Overview of Program ManagementOverview of Program Management
Overview of Program Management
 
Project Quality Management - PMBOK
Project Quality Management - PMBOKProject Quality Management - PMBOK
Project Quality Management - PMBOK
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
 
TBO PMO Model
TBO PMO ModelTBO PMO Model
TBO PMO Model
 
Risk and issue management
Risk and issue managementRisk and issue management
Risk and issue management
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
What is Program Management - An Overview
What is Program Management - An OverviewWhat is Program Management - An Overview
What is Program Management - An Overview
 
Pmo final 1
Pmo final 1Pmo final 1
Pmo final 1
 
PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality management
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)
 
Prince2 explained in 30mins
Prince2 explained in 30minsPrince2 explained in 30mins
Prince2 explained in 30mins
 
PgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint PresentationPgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint Presentation
 
project management
project managementproject management
project management
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areas
 
PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?
 
Project Management
Project ManagementProject Management
Project Management
 
Project management
Project managementProject management
Project management
 

Viewers also liked

101 Free Online Marketing Resources For Entrepreneurs
101 Free Online Marketing Resources For Entrepreneurs101 Free Online Marketing Resources For Entrepreneurs
101 Free Online Marketing Resources For EntrepreneursFit Small Business
 
Technical Marketing is the Price of Admission
Technical Marketing is the Price of AdmissionTechnical Marketing is the Price of Admission
Technical Marketing is the Price of AdmissionMichael King
 
Iso 9001 2015 audit checklist
Iso 9001 2015 audit checklistIso 9001 2015 audit checklist
Iso 9001 2015 audit checklistHamid Ali
 
How to Audit Your Incident Response Plan
How to Audit Your Incident Response PlanHow to Audit Your Incident Response Plan
How to Audit Your Incident Response PlanResilient Systems
 
Summer Training Presentation On HMT Machine Tools Ltd
Summer Training Presentation On HMT Machine Tools LtdSummer Training Presentation On HMT Machine Tools Ltd
Summer Training Presentation On HMT Machine Tools LtdPuneet Parihar
 
Capex audit checklist
Capex audit checklistCapex audit checklist
Capex audit checklistDushyant Jadav
 
Website Audit Checklist
Website Audit ChecklistWebsite Audit Checklist
Website Audit ChecklistTim Bourgeois
 
Predictive Analytics: Context and Use Cases
Predictive Analytics: Context and Use CasesPredictive Analytics: Context and Use Cases
Predictive Analytics: Context and Use CasesKimberley Mitchell
 
security-checklist-database
security-checklist-databasesecurity-checklist-database
security-checklist-databaseMohsen B
 
Web site int audit checklist intent
Web site int audit checklist intentWeb site int audit checklist intent
Web site int audit checklist intentmartinbusiness
 
IS Audit Checklist- by Software development company in india
IS Audit Checklist- by Software development company in indiaIS Audit Checklist- by Software development company in india
IS Audit Checklist- by Software development company in indiaiFour Consultancy
 
Ch12 - Organisation theory design and change gareth jones
Ch12 - Organisation theory design and change gareth jonesCh12 - Organisation theory design and change gareth jones
Ch12 - Organisation theory design and change gareth jonesAnkit Kesri
 
13 information system audit of banks
13 information system audit of banks13 information system audit of banks
13 information system audit of banksspandane
 
Computer networking
Computer networkingComputer networking
Computer networkingChinmoy Jena
 
Landforms 60 - PowerPoint - Version 2
Landforms 60 - PowerPoint - Version 2Landforms 60 - PowerPoint - Version 2
Landforms 60 - PowerPoint - Version 2Yaryalitsa
 
Information System audit
Information System auditInformation System audit
Information System auditPratapchandra
 
Iso Process Audit Training
Iso Process Audit TrainingIso Process Audit Training
Iso Process Audit Trainingsrmortensen
 
Integrated treasury management in banks
Integrated treasury management in banksIntegrated treasury management in banks
Integrated treasury management in banksSahas Patil
 
Audit Checklist for Information Systems
Audit Checklist for Information SystemsAudit Checklist for Information Systems
Audit Checklist for Information SystemsAhmad Tariq Bhatti
 
Entrepreneurship And Business Management
Entrepreneurship And Business ManagementEntrepreneurship And Business Management
Entrepreneurship And Business ManagementProf Parameshwar P Iyer
 

Viewers also liked (20)

101 Free Online Marketing Resources For Entrepreneurs
101 Free Online Marketing Resources For Entrepreneurs101 Free Online Marketing Resources For Entrepreneurs
101 Free Online Marketing Resources For Entrepreneurs
 
Technical Marketing is the Price of Admission
Technical Marketing is the Price of AdmissionTechnical Marketing is the Price of Admission
Technical Marketing is the Price of Admission
 
Iso 9001 2015 audit checklist
Iso 9001 2015 audit checklistIso 9001 2015 audit checklist
Iso 9001 2015 audit checklist
 
How to Audit Your Incident Response Plan
How to Audit Your Incident Response PlanHow to Audit Your Incident Response Plan
How to Audit Your Incident Response Plan
 
Summer Training Presentation On HMT Machine Tools Ltd
Summer Training Presentation On HMT Machine Tools LtdSummer Training Presentation On HMT Machine Tools Ltd
Summer Training Presentation On HMT Machine Tools Ltd
 
Capex audit checklist
Capex audit checklistCapex audit checklist
Capex audit checklist
 
Website Audit Checklist
Website Audit ChecklistWebsite Audit Checklist
Website Audit Checklist
 
Predictive Analytics: Context and Use Cases
Predictive Analytics: Context and Use CasesPredictive Analytics: Context and Use Cases
Predictive Analytics: Context and Use Cases
 
security-checklist-database
security-checklist-databasesecurity-checklist-database
security-checklist-database
 
Web site int audit checklist intent
Web site int audit checklist intentWeb site int audit checklist intent
Web site int audit checklist intent
 
IS Audit Checklist- by Software development company in india
IS Audit Checklist- by Software development company in indiaIS Audit Checklist- by Software development company in india
IS Audit Checklist- by Software development company in india
 
Ch12 - Organisation theory design and change gareth jones
Ch12 - Organisation theory design and change gareth jonesCh12 - Organisation theory design and change gareth jones
Ch12 - Organisation theory design and change gareth jones
 
13 information system audit of banks
13 information system audit of banks13 information system audit of banks
13 information system audit of banks
 
Computer networking
Computer networkingComputer networking
Computer networking
 
Landforms 60 - PowerPoint - Version 2
Landforms 60 - PowerPoint - Version 2Landforms 60 - PowerPoint - Version 2
Landforms 60 - PowerPoint - Version 2
 
Information System audit
Information System auditInformation System audit
Information System audit
 
Iso Process Audit Training
Iso Process Audit TrainingIso Process Audit Training
Iso Process Audit Training
 
Integrated treasury management in banks
Integrated treasury management in banksIntegrated treasury management in banks
Integrated treasury management in banks
 
Audit Checklist for Information Systems
Audit Checklist for Information SystemsAudit Checklist for Information Systems
Audit Checklist for Information Systems
 
Entrepreneurship And Business Management
Entrepreneurship And Business ManagementEntrepreneurship And Business Management
Entrepreneurship And Business Management
 

Similar to Program management audit checklist

Project Planning Checklist
Project Planning ChecklistProject Planning Checklist
Project Planning ChecklistAnand Subramaniam
 
Program management - Fundamentals
Program management   - FundamentalsProgram management   - Fundamentals
Program management - FundamentalsJulen Mohanty
 
Program management for goup1
Program management for goup1Program management for goup1
Program management for goup1Mohammed Al_busailiy
 
New Techniques to Elevate QA to Program Assurance
New Techniques to Elevate QA to Program AssuranceNew Techniques to Elevate QA to Program Assurance
New Techniques to Elevate QA to Program AssuranceSusan Schanta
 
Program management scope management
Program management   scope managementProgram management   scope management
Program management scope managementJulen Mohanty
 
Project-Review-Checklist.docx
Project-Review-Checklist.docxProject-Review-Checklist.docx
Project-Review-Checklist.docxAddisu15
 
Program governance Structure
Program governance StructureProgram governance Structure
Program governance StructureSaurabh Sardesai
 
Program Management
Program ManagementProgram Management
Program ManagementRajnish Anand
 
Pg mp study notes (updated)
Pg mp study notes (updated)Pg mp study notes (updated)
Pg mp study notes (updated)Adil Elhaj, PfMP
 
Introduction-to-Project-Management systems
Introduction-to-Project-Management systemsIntroduction-to-Project-Management systems
Introduction-to-Project-Management systemsAbshirAhmed8
 
software project management software engineering.pptx
software project management software engineering.pptxsoftware project management software engineering.pptx
software project management software engineering.pptx05sheetalkumari
 
Project Management vs. Program Management: Strategies for Transition Success
Project Management vs. Program Management: Strategies for Transition SuccessProject Management vs. Program Management: Strategies for Transition Success
Project Management vs. Program Management: Strategies for Transition SuccessRuffin Veal and Associates, Inc.
 
Standardforprogrammanagementchanges 090328223505 Phpapp02
Standardforprogrammanagementchanges 090328223505 Phpapp02Standardforprogrammanagementchanges 090328223505 Phpapp02
Standardforprogrammanagementchanges 090328223505 Phpapp02Gee
 
A Guide to Software Development Manager Responsibilities.pdf
A Guide to Software Development Manager Responsibilities.pdfA Guide to Software Development Manager Responsibilities.pdf
A Guide to Software Development Manager Responsibilities.pdfLaura Miller
 
Efficacy of Project Management,
Efficacy of Project Management, Efficacy of Project Management,
Efficacy of Project Management, Assignment Studio
 

Similar to Program management audit checklist (20)

Project Planning Checklist
Project Planning ChecklistProject Planning Checklist
Project Planning Checklist
 
Program management - Fundamentals
Program management   - FundamentalsProgram management   - Fundamentals
Program management - Fundamentals
 
Program management for goup1
Program management for goup1Program management for goup1
Program management for goup1
 
New Techniques to Elevate QA to Program Assurance
New Techniques to Elevate QA to Program AssuranceNew Techniques to Elevate QA to Program Assurance
New Techniques to Elevate QA to Program Assurance
 
Program management scope management
Program management   scope managementProgram management   scope management
Program management scope management
 
Project-Review-Checklist.docx
Project-Review-Checklist.docxProject-Review-Checklist.docx
Project-Review-Checklist.docx
 
Program governance Structure
Program governance StructureProgram governance Structure
Program governance Structure
 
Program Management
Program ManagementProgram Management
Program Management
 
Pg mp study notes (updated)
Pg mp study notes (updated)Pg mp study notes (updated)
Pg mp study notes (updated)
 
Project Health Check
Project Health CheckProject Health Check
Project Health Check
 
PgMP - Introduction to Program Management
PgMP -  Introduction to Program ManagementPgMP -  Introduction to Program Management
PgMP - Introduction to Program Management
 
Introduction-to-Project-Management systems
Introduction-to-Project-Management systemsIntroduction-to-Project-Management systems
Introduction-to-Project-Management systems
 
Model of Programs.pptx
Model of Programs.pptxModel of Programs.pptx
Model of Programs.pptx
 
software project management software engineering.pptx
software project management software engineering.pptxsoftware project management software engineering.pptx
software project management software engineering.pptx
 
Project Management vs. Program Management: Strategies for Transition Success
Project Management vs. Program Management: Strategies for Transition SuccessProject Management vs. Program Management: Strategies for Transition Success
Project Management vs. Program Management: Strategies for Transition Success
 
Standardforprogrammanagementchanges 090328223505 Phpapp02
Standardforprogrammanagementchanges 090328223505 Phpapp02Standardforprogrammanagementchanges 090328223505 Phpapp02
Standardforprogrammanagementchanges 090328223505 Phpapp02
 
Program management 2
Program management 2Program management 2
Program management 2
 
Lfa
LfaLfa
Lfa
 
A Guide to Software Development Manager Responsibilities.pdf
A Guide to Software Development Manager Responsibilities.pdfA Guide to Software Development Manager Responsibilities.pdf
A Guide to Software Development Manager Responsibilities.pdf
 
Efficacy of Project Management,
Efficacy of Project Management, Efficacy of Project Management,
Efficacy of Project Management,
 

More from Bob Prieto

Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Bob Prieto
 
Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startupBob Prieto
 
Deeper look at the physics of projects
Deeper look at the physics of projectsDeeper look at the physics of projects
Deeper look at the physics of projectsBob Prieto
 
Systems nature of large complex projects
Systems nature of large complex projectsSystems nature of large complex projects
Systems nature of large complex projectsBob Prieto
 
Governance of mega and giga programs
Governance of mega and giga programsGovernance of mega and giga programs
Governance of mega and giga programsBob Prieto
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryBob Prieto
 
Rethinking Interface Management
Rethinking Interface ManagementRethinking Interface Management
Rethinking Interface ManagementBob Prieto
 
Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsBob Prieto
 
Reversing Global Warming
Reversing Global WarmingReversing Global Warming
Reversing Global WarmingBob Prieto
 
Improving infrastructure project success
Improving infrastructure project successImproving infrastructure project success
Improving infrastructure project successBob Prieto
 
Large complex project success
Large complex project successLarge complex project success
Large complex project successBob Prieto
 
Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Bob Prieto
 
Decision Making Under Uncertainty
Decision Making Under UncertaintyDecision Making Under Uncertainty
Decision Making Under UncertaintyBob Prieto
 
Post Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasPost Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasBob Prieto
 
Debating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentDebating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentBob Prieto
 
Chapters 11 12 13
Chapters 11  12  13Chapters 11  12  13
Chapters 11 12 13Bob Prieto
 
Chapter 10
Chapter 10Chapter 10
Chapter 10Bob Prieto
 
Chapter 9
Chapter 9Chapter 9
Chapter 9Bob Prieto
 
Chapter 8
Chapter 8Chapter 8
Chapter 8Bob Prieto
 
Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Bob Prieto
 

More from Bob Prieto (20)

Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...
 
Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startup
 
Deeper look at the physics of projects
Deeper look at the physics of projectsDeeper look at the physics of projects
Deeper look at the physics of projects
 
Systems nature of large complex projects
Systems nature of large complex projectsSystems nature of large complex projects
Systems nature of large complex projects
 
Governance of mega and giga programs
Governance of mega and giga programsGovernance of mega and giga programs
Governance of mega and giga programs
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project delivery
 
Rethinking Interface Management
Rethinking Interface ManagementRethinking Interface Management
Rethinking Interface Management
 
Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction Projects
 
Reversing Global Warming
Reversing Global WarmingReversing Global Warming
Reversing Global Warming
 
Improving infrastructure project success
Improving infrastructure project successImproving infrastructure project success
Improving infrastructure project success
 
Large complex project success
Large complex project successLarge complex project success
Large complex project success
 
Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects
 
Decision Making Under Uncertainty
Decision Making Under UncertaintyDecision Making Under Uncertainty
Decision Making Under Uncertainty
 
Post Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasPost Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the Bahamas
 
Debating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentDebating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environment
 
Chapters 11 12 13
Chapters 11  12  13Chapters 11  12  13
Chapters 11 12 13
 
Chapter 10
Chapter 10Chapter 10
Chapter 10
 
Chapter 9
Chapter 9Chapter 9
Chapter 9
 
Chapter 8
Chapter 8Chapter 8
Chapter 8
 
Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7
 

Recently uploaded

Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
TechTACÂŽ CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTACÂŽ CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTACÂŽ CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTACÂŽ CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoĂŁo Esperancinha
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 

Recently uploaded (20)

Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
TechTACÂŽ CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTACÂŽ CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTACÂŽ CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTACÂŽ CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 

Program management audit checklist

  • 1. Bob Prieto, Fluor Page 1 11/29/2011 Program Management Audit Checklist Prepared by: Bob Prieto Senior Vice President Fluor March 27, 2008 This audit checklist is designed to complement other owner, program manager and contractually required audit checklists. The purpose of this checklist is to ensure that continued focus is paid on achieving the strategic business outcomes that the program is intended to address.
  • 2. Bob Prieto, Fluor Page 2 11/29/2011 Program Management Audit Checklist Audit Element Owner’s Focus Program Manager’s Focus Program Plan Does formal program plan exist? Is program plan being utilizing and maintained up to date? Are Owner and Program Manager efforts aligned with this plan? Are projects and program management organizational elements aligned with the program plan? Is Program Manager utilizing and maintaining an up to date Program Plan in the management of his activities? Are projects and program management organizational elements utilizing and maintaining an up to date plan?
  • 3. Bob Prieto, Fluor Page 3 11/29/2011 Program Management Audit Checklist Audit Element Owner’s Focus Program Manager’s Focus Stakeholder Management Have all Stakeholder’s at the Program level been identified? Does a Stakeholder Management plan exist; are responsibilities apportioned between Owner, Program Manager and respective Projects; and being utilized and maintained up to date? Does a Stakeholder Management plan exist; responsibilities apportioned between Owner and Program Manager; and being utilized and maintained up to date? Do the individual projects have stakeholder management and third party interface plans in place, are they being utilized and maintained up to date?
  • 4. Bob Prieto, Fluor Page 4 11/29/2011 Program Management Audit Checklist Audit Element Owner’s Focus Program Manager’s Focus Communications Plan Does external communications plan exist and is it being implemented? Is a comprehensive internal Communication Plan in place and being adequately implemented across all projects? Has Program Manager developed and implemented a robust internal communications plan? Have individual projects put in place and required project level communication plans and taken steps to implement any communication requirements assigned to them by the internal program Communication Plan.
  • 5. Bob Prieto, Fluor Page 5 11/29/2011 Program Management Audit Checklist Audit Element Owner’s Focus Program Manager’s Focus Program Management Have key strategic business objectives been clearly communicated in a consistent way to the Owner’s and Program Manager’s team? Have program goals and strategic business objectives been incorporated into each of the framework processes? Have the key elements of a coherent program management strategy been established? a. Program monitoring and measurement plan & methodology (key metrics) b. Program status reporting structure & process c. Change Management plan d. Issues Management process e. Risk Management Plan Are framework processes providing the Program Manager with the necessary tools and information to manage and track overall program progress; are cross cutting trends being adequately identified, analyzed and managed? Has the Program Manager implemented all required framework processes and are those processes producing the desired outcomes? Are project level management systems in place and providing required programmatic data in a timely way; are project level management systems being adequately used to accomplish project level activities?
  • 6. Bob Prieto, Fluor Page 6 11/29/2011 Program Management Audit Checklist Audit Element Owner’s Focus Program Manager’s Focus Program Scheduling & Tracking Are external factors sufficiently reflected in the overall program schedule? Are external factors reflected in the overall program schedule being actively managed by the Program Management organization? Are identified risk factors being actively managed and tracked by the Owner’s organization or Program Manager as appropriate? Are identified risk factors being actively managed and tracked by the Program Management organization or projects, as appropriate? Is Program Manager adequately identifying systemic program issues affecting schedule and recommending corrective or risk limiting actions? Are the organizational elements of the Program Manager adequately identifying, analyzing and recommending and implementing corrective action for systemic risks? Are projects adequately identifying issues affecting schedule and taking corrective actions? Are program and project level milestones being adequately tracked and managed? Have activity relationships and interdependencies within tasks and across projects been adequately identified? Are changes in deliverable commitments agreed to by all affected groups & individuals?
  • 7. Bob Prieto, Fluor Page 7 11/29/2011 Program Management Audit Checklist Audit Element Owner’s Focus Program Manager’s Focus Program Status Reporting Is program status reviewed with Program Manager at appropriate intervals? a. Overall status b. Program performance (achievements & milestones) c. Open issues d. Risks e. Action items f. Cost & time performance against plan g. Quality metrics h. Involvement by ALL relevant Owner’s organizational elements. Is project status reviewed with senior management of projects at appropriate intervals? a. Overall status b. Project performance (achievements & milestones) c. Open issues d. Risks e. Action items f. Cost & time performance against plan g. Quality metrics h. Change Impact Assessment i. Interface management j. Involvement by all relevant Program Manager organizational elements Have adequate procedures been put in place for project coordination and status reporting across project boundaries by the Program Manager?
  • 8. Bob Prieto, Fluor Page 8 11/29/2011 Program Management Audit Checklist Audit Element Owner’s Focus Program Manager’s Focus Program Budget & Forecast Do Program estimates reflect both risks associated with quantity uncertainties as well as possible risk events? Are program activity budgets clearly assigned within the Program Manager’s organization? Are risk allocation and management responsibilities between the Owner and Program Manager clearly defined? Are risk pools comprehensively defined and actively managed? Are systemic cost drivers being adequately tracked? Is the Program Manager adequately managing risk pools within his purview? Are projects accurately measuring progress and adequately forecasting trends and opportunities for cost savings?
  • 9. Bob Prieto, Fluor Page 9 11/29/2011 Program Management Audit Checklist Audit Element Owner’s Focus Program Manager’s Focus Risk Management Is an up to date Program wide risk assessment in place at the Owner’s level? Is the Program Manager’s risk assessment and management process being adequately implemented and is it providing timely actionable information for the Program Manager and Owner? Is the Program Manager’s risk assessment and management process being adequately implemented and is it providing timely actionable information for the Program Manager and Owner? Are significant changes in risk posture or the emergence of new risks being adequately identified across all projects and program management activities being actively managed and tracked? Are significant changes in risk posture or the emergence of new risks being adequately identified by the Program Manager, managed and tracked? Are significant changes in risk posture or the emergence of new risks being adequately identified by projects, managed and tracked?
  • 10. Bob Prieto, Fluor Page 10 11/29/2011 Program Management Audit Checklist Audit Element Owner’s Focus Program Manager’s Focus Quality Management Does the program have a ‘Quality Culture’? Has the program quality culture been adequately flowed down to projects and key suppliers? Does the Program Manager have a Quality Plan covering all Policies, Guidelines and Procedures? Are quality related policies, guidelines and procedures clearly communicated, trained, implemented and assured? Quality Assurance Has an overall Quality Assurance Plan been developed and implemented by the Program Manager for the program in accordance with program needs and contract requirements? Has the programmatic quality assurance program been translated into specific quality plans for all elements of the program management organization as well as for individual projects and key supply chain activities? Is the implemented Quality Assurance program supporting the meeting of the strategic business objectives defined? Are quality programs implemented at the project level providing timely identification and mitigation of quality affecting issues? Are programmatic quality findings and lessons learned being effectively incorporated into new planned activities and transmitted across all projects in a timely manner?
  • 11. Bob Prieto, Fluor Page 11 11/29/2011 Program Management Audit Checklist Audit Element Owner’s Focus Program Manager’s Focus Management Procedures Does the Program Manager have in place and is he implementing a comprehensive and integrated set of management procedures that provide assurance of achievement of the program’s strategic business objectives? Are all elements of the program management organization implementing established management procedures? Are these procedures providing adequate control of program activities and will they support the delivery of strategic business objectives? Are the implemented procedures being comprehensively applied across all framework processes? Have projects and key suppliers put in place the necessary procedures to manage their work efforts and provide sufficient management information to the Program Manager to facilitate overall program management? Are the procedures being effectively implemented and are they causing the required results? Are resources applied by the program manager adequately forecast, controlled and tracked to assure program efficiency? Are management resources applied at the project level adequate to manage the assigned tasks successfully? Have the personnel with the necessary skills and competence been identified and has agreement for their participation in the program been reached? Have the projects been resourced with the requisite number of skilled personnel consistent with overall program and contract requirements? Does the detailed program work plan match the complexity of tasks with the capabilities of personnel? Is the project work plan sufficiently detailed, resourced and measured to assure progress in accordance with project requirements is being achieved? Has appropriate allowance been made for the effect of Has adequate allowance been made for mobilization,
  • 12. Bob Prieto, Fluor Page 12 11/29/2011 the learning curve on all personnel joining the program who do not have the required prior project execution methodology (program management) industry, functional & technical expertise? interfaces and demobilization? Are project team members committed full-time?
  • 13. Bob Prieto, Fluor Page 13 11/29/2011 Program Management Audit Checklist Audit Element Owner’s Focus Program Manager’s Focus Design & Analysis Are requirements & design standards in place? Have design standards been promulgated and design changes controlled to promote the maximum standardization possible on a programmatic basis? Are required design QA programs being implemented by the program manager? Are specifications clearly traceable from physical design to logical requirements? Have programmatic efforts related to standardization, modularization and increased focus on constructability been sufficiently realized? Do the design specification documents reference: a. Purpose / scope? b. Requirements specifications? c. Modularized or other standard components d. Technical environment specification? e. Constraints and interfaces? f. Commissioning, startup and testing requirements? Have design elements of the program utilized qualified designers and checkers? Are design QA and QC activities sufficiently documented?
  • 14. Bob Prieto, Fluor Page 14 11/29/2011 Program Management Audit Checklist Audit Element Owner’s Focus Program Manager’s Focus Construction Are intermediate construction milestones being met? Have the interaction/interference between all projects been adequately reflected on the master program schedule? Is the quality of construction consistent with the program’s strategic business objectives? Has due consideration been given to supply chain delivery times and changing logistical requirements? Is construction productivity being enhanced throughout the program through use of standardization, simplification of details and application of programmatic type contracts? Are construction activities for individual projects well planned, crews adequately prepared and equipped for the tasks to be undertaken each day and have site or task safety hazards been adequately communicated and necessary protective measures taken? Is construction productivity assessed at the project level and programmatically assessed across like activities? Are lessons learned within the program being transferred back across all projects?
  • 15. Bob Prieto, Fluor Page 15 11/29/2011 Program Management Audit Checklist Audit Element Owner’s Focus Program Manager’s Focus Operations & Maintenance Do adequate operations procedures exist? Have commissioning and over activities been adequately planned; Owner’s interfaces clearly defined and project level requirement fully addressed? Are Maintenance Metrics defined and in place? Are responsibilities for warranty management pre- and post-commissioning well defined and adequately managed? Is there an improvement program in place? Is there a warranty management program in- place for the post commissioning period?
  • 16. Bob Prieto, Fluor Page 16 11/29/2011 Program Management Audit Checklist Audit Element Owner’s Focus Program Manager’s Focus Financial Integrity Are financial management controls in place to ensure the integrity of financial operations, disbursement of funds, payment to vendors, management of escrow and reserve accounts, maintenance of insurance, accounting for capital assets and in-process materials, and other financial activities conducted by the Owner or the Program Manager on behalf of the Owner? Are financial systems and controls, including external audit functions fully in place and adequately staffed with qualified staff? Have required financial audit activities been fully carried out? Have audits of vendor, contractor and other supplier pay records and documentation been carried out and to the extent required have similar sub- tier activities been audited for compliance with any such requirements? Have all audit findings been communicated as appropriate and subsequently satisfactorily closed out? Have all identified corrective actions been taken? Has all supporting documentation required by the Owner been completed and archived as appropriate? Are open claims and disputes tracked, resolved in a timely manner and closed out?
  • 17. Bob Prieto, Fluor Page 17 11/29/2011 Program Management Audit Checklist Audit Element Owner’s Focus Program Manager’s Focus Contract Management Has Owner’s organization and Program Manager efficiently all contract administration processes between them so as not to impact overall program performance? Have each of the following contract management activities occurred for projects and suppliers agreements? • Evaluate contractor performance or deliverables. • Verify and document evidence of actual or potential performance problems, constructive changes, or other deviations. • Determine potential impact of technical issues on cost, schedule, and delivery; and investigate/resolve rationale for potential or actual delays. • Specify technical criteria for the quality of the product, in-process test procedures and test points, and acceptance criteria through engineering analysis. • Assess performance, quality, and other technical issues and provide technical evaluation to contracts for adjustment to, modification of, or compliance with the contract.
  • 18. Bob Prieto, Fluor Page 18 11/29/2011 Program Management Audit Checklist Audit Element Owner’s Focus Program Manager’s Focus Contract Management (continued) Have each of the following contract management activities occurred for projects and suppliers agreements? • Analyze performance data for trends and issues. Resolve issues in data quality and performance quality. • Monitor the risk management process to identify technical risk, as well as cost, schedule, and performance risk. • Review change proposals and alterations impacts on cost and schedule to ensure that adequate funding is available and that schedules imposed in the contract are not affected. • Review requests for waivers and deviations from contractor and field activities to determine the impact on system reliability and performance, as well as on cost and schedule. • Review change proposals for need, technical adequacy of design, consistency with program objectives, impact on operations, producibility, quality and similar programmatic concerns; and ensure that proposed changes are within the scope of the contract. .
  • 19. Bob Prieto, Fluor Page 19 11/29/2011 Program Management Audit Checklist Audit Element Owner’s Focus Program Manager’s Focus Contract Management (continued) Have each of the following contract management activities occurred for projects and suppliers agreements? • Conduct a cost-benefit analysis of the Value Engineering Change Proposal • Participate in design review planning meetings, in the event of potential impact to the contract (e.g., constructive change clauses, etc.) and conduct design reviews. • Support baseline reviews process. • Track corrective actions and interfaces with the contractor during project reviews until they are complete. • Ensure compliance with the configuration management requirements of the contract and consistency with the acquisition strategy, such as the decision to buy data rights or other strategies to ensure that a second source can build the hardware.
  • 20. Bob Prieto, Fluor Page 20 11/29/2011 Program Management Audit Checklist Audit Element Owner’s Focus Program Manager’s Focus Contract Management (continued) Have all necessary contract close-out activities occurred? These include: • Assess the impact of stop work orders on contractor performance of the technical and programmatic requirements. Recommend stop work when contractor deficiencies are expected to result in delivery of nonconforming technical products. Evaluate contractor proposals to stop work for technical reasons. • Ensure that engineering contractors are responsible for the professional quality, technical accuracy, and coordination of all services required under their contracts and that firms are held liable for costs resulting from errors or deficiencies in designs furnished under its contract. • Settle all outstanding claims, issues or disputes; respond to contractor claims for additional money or contract adjustment, and determine if it constitutes a payable claim. • Verify that the contract is physically complete through physical and functional configuration audits.
  • 21. Bob Prieto, Fluor Page 21 11/29/2011 Program Management Audit Checklist Audit Element Owner’s Focus Program Manager’s Focus Contract Management (continued) Have each of the following contract management activities occurred for projects and suppliers agreements? • Obtain all forms, reports, and clearances required at closeout from both Owner and contractor activities, and ensure that they have met all applicable terms and conditions for closeout. • Make final payment • Prepare contract completion documentation. • Assist Owner in identifying or settling unresolved issues, such as performance issues, unresolved Value Engineering Change Proposals, etc. • Dispose of surplus property property that the Owner does not wish to retain.