The document describes a sample PMP exam question regarding decomposing a system testing work package when project details are still unknown. The best approach is to: 1) Decompose the system development work package now as details are available 2) Decompose the system testing work package later when more information is available from the partially completed system development 3) This rolling wave planning approach delays decomposition of uncertain future work packages until additional details emerge, as is described in the question's answer.