You are tailoring the schedule management plan template for a project using an adaptive approach instead of a predictive approach. The components you will tailor the most are the schedule model development, release and iteration length, and reporting formats. These directly relate to developing an adaptive schedule model with time-boxed iterations and reporting tailored to the new iterative approach. The other answer choices contain components that are not part of the schedule management plan.