SlideShare a Scribd company logo
PMP EXAM
SAMPLE Q & A
You are part of a cross-functional development team piloting an adaptive approach to project
management in an organization that has traditionally used a predictive approach. You realize that
you have to tailor the template of the schedule management plan.
Which of the following components of the template are you likely to tailor the most?
A. The rules of performance measurement, the summary milestones, and the key deliverables
B. The organizational procedures links, the units of measure, and the project organization charts
C. The schedule model development, the release and iteration length, and the reporting formats
D. The project schedule model maintenance, the level of accuracy, and the level of precision
HINT: To eliminate some choices, look for items that are not components of the schedule
management plan.
Question
The correct answer is C.
The question suggests you are carrying out the Plan Schedule Management process. The
schedule management plan is the primary output of this process. The schedule management
plan establishes the criteria and the activities for developing, monitoring, and controlling the
schedule. Of the choices presented, only the schedule model development, the release and
iteration length, and the reporting formats are components of the schedule management plan.
All three of these components would merit significant tailoring to reflect an adaptive approach to
project management. The project schedule model development specifies the scheduling
methodology and the scheduling tool used to develop the schedule model.
Answer
For an adaptive approach, the schedule model will be a selected series of activities needed to
complete a high-priority subset of the project scope that can deliver value quickly. The release
and iteration length determine the time-boxed events that must be completed and how long it
will take to release the iteration. The reporting formats will be driven by the adaptive schedule
model and the iteration length.
The other answer choices contain components that are not part of the schedule management
plan.
Answer
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.

More Related Content

Similar to Free PMP Exam Sample Question

PMI Project Management Associate (CAPM) Certification | Study Guide
PMI Project Management Associate (CAPM) Certification | Study GuidePMI Project Management Associate (CAPM) Certification | Study Guide
PMI Project Management Associate (CAPM) Certification | Study Guide
Meghna Arora
 
Project Management Framework automation for Project and Portfolio Management ...
Project Management Framework automation for Project and Portfolio Management ...Project Management Framework automation for Project and Portfolio Management ...
Project Management Framework automation for Project and Portfolio Management ...
PMILebanonChapter
 
Pm 0010 introduction to project management
Pm 0010   introduction to project managementPm 0010   introduction to project management
Pm 0010 introduction to project management
smumbahelp
 
ASAP-01 Implementaion.pptx
ASAP-01 Implementaion.pptxASAP-01 Implementaion.pptx
ASAP-01 Implementaion.pptx
Ashraf206702
 
SAP Organization Change Management
SAP Organization Change ManagementSAP Organization Change Management
SAP Organization Change ManagementFred Asher, Ph.D.
 
Sanitized Knowledge Transfer Deliverable:Rapid Process Change Tutorial
Sanitized Knowledge Transfer Deliverable:Rapid Process Change TutorialSanitized Knowledge Transfer Deliverable:Rapid Process Change Tutorial
Sanitized Knowledge Transfer Deliverable:Rapid Process Change Tutorialguesta83e9d
 
A project portfolio management capability framework
A project portfolio management capability frameworkA project portfolio management capability framework
A project portfolio management capability framework
Robert Greca, PMP, SA
 
ALM Assessment Program
ALM Assessment ProgramALM Assessment Program
ALM Assessment Program
Steve Lange
 
Requirement NumberRequirement DescriptionPriority (High, Mediu.docx
Requirement NumberRequirement DescriptionPriority (High, Mediu.docxRequirement NumberRequirement DescriptionPriority (High, Mediu.docx
Requirement NumberRequirement DescriptionPriority (High, Mediu.docx
heunice
 
Project Management MethodologiesPPMP20009Week 10 LectureDr.docx
Project Management MethodologiesPPMP20009Week 10 LectureDr.docxProject Management MethodologiesPPMP20009Week 10 LectureDr.docx
Project Management MethodologiesPPMP20009Week 10 LectureDr.docx
briancrawford30935
 
MIS Project management
MIS Project managementMIS Project management
MIS Project management
Josephine Claire
 
PgMP Panel Review (3/3)
PgMP Panel Review (3/3)PgMP Panel Review (3/3)
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
Wadhwani Foundation
 
Pm0011 project planning and scheduling
Pm0011   project planning and schedulingPm0011   project planning and scheduling
Pm0011 project planning and schedulingsmumbahelp
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
David Pedreno
 
Ch23
Ch23Ch23
Week_10_Term_Paper_ANS_1429096.docxRunning head Agile Project.docx
Week_10_Term_Paper_ANS_1429096.docxRunning head Agile Project.docxWeek_10_Term_Paper_ANS_1429096.docxRunning head Agile Project.docx
Week_10_Term_Paper_ANS_1429096.docxRunning head Agile Project.docx
philipnelson29183
 
Process Improvement in Software Engineering SE25
Process Improvement in Software Engineering SE25Process Improvement in Software Engineering SE25
Process Improvement in Software Engineering SE25koolkampus
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
David Pedreno
 
Rational Unified Process(Rup)
Rational Unified Process(Rup)Rational Unified Process(Rup)
Rational Unified Process(Rup)pawanonline83
 

Similar to Free PMP Exam Sample Question (20)

PMI Project Management Associate (CAPM) Certification | Study Guide
PMI Project Management Associate (CAPM) Certification | Study GuidePMI Project Management Associate (CAPM) Certification | Study Guide
PMI Project Management Associate (CAPM) Certification | Study Guide
 
Project Management Framework automation for Project and Portfolio Management ...
Project Management Framework automation for Project and Portfolio Management ...Project Management Framework automation for Project and Portfolio Management ...
Project Management Framework automation for Project and Portfolio Management ...
 
Pm 0010 introduction to project management
Pm 0010   introduction to project managementPm 0010   introduction to project management
Pm 0010 introduction to project management
 
ASAP-01 Implementaion.pptx
ASAP-01 Implementaion.pptxASAP-01 Implementaion.pptx
ASAP-01 Implementaion.pptx
 
SAP Organization Change Management
SAP Organization Change ManagementSAP Organization Change Management
SAP Organization Change Management
 
Sanitized Knowledge Transfer Deliverable:Rapid Process Change Tutorial
Sanitized Knowledge Transfer Deliverable:Rapid Process Change TutorialSanitized Knowledge Transfer Deliverable:Rapid Process Change Tutorial
Sanitized Knowledge Transfer Deliverable:Rapid Process Change Tutorial
 
A project portfolio management capability framework
A project portfolio management capability frameworkA project portfolio management capability framework
A project portfolio management capability framework
 
ALM Assessment Program
ALM Assessment ProgramALM Assessment Program
ALM Assessment Program
 
Requirement NumberRequirement DescriptionPriority (High, Mediu.docx
Requirement NumberRequirement DescriptionPriority (High, Mediu.docxRequirement NumberRequirement DescriptionPriority (High, Mediu.docx
Requirement NumberRequirement DescriptionPriority (High, Mediu.docx
 
Project Management MethodologiesPPMP20009Week 10 LectureDr.docx
Project Management MethodologiesPPMP20009Week 10 LectureDr.docxProject Management MethodologiesPPMP20009Week 10 LectureDr.docx
Project Management MethodologiesPPMP20009Week 10 LectureDr.docx
 
MIS Project management
MIS Project managementMIS Project management
MIS Project management
 
PgMP Panel Review (3/3)
PgMP Panel Review (3/3)PgMP Panel Review (3/3)
PgMP Panel Review (3/3)
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Pm0011 project planning and scheduling
Pm0011   project planning and schedulingPm0011   project planning and scheduling
Pm0011 project planning and scheduling
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
 
Ch23
Ch23Ch23
Ch23
 
Week_10_Term_Paper_ANS_1429096.docxRunning head Agile Project.docx
Week_10_Term_Paper_ANS_1429096.docxRunning head Agile Project.docxWeek_10_Term_Paper_ANS_1429096.docxRunning head Agile Project.docx
Week_10_Term_Paper_ANS_1429096.docxRunning head Agile Project.docx
 
Process Improvement in Software Engineering SE25
Process Improvement in Software Engineering SE25Process Improvement in Software Engineering SE25
Process Improvement in Software Engineering SE25
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
 
Rational Unified Process(Rup)
Rational Unified Process(Rup)Rational Unified Process(Rup)
Rational Unified Process(Rup)
 

More from OSP International LLC

Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
OSP International LLC
 
Free CAPM Exam Sample Question for the Week
Free CAPM Exam Sample Question for the WeekFree CAPM Exam Sample Question for the Week
Free CAPM Exam Sample Question for the Week
OSP International LLC
 
Free PMP Exam Sample Question for the Week
Free PMP Exam Sample Question for the WeekFree PMP Exam Sample Question for the Week
Free PMP Exam Sample Question for the Week
OSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
OSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
OSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
OSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
OSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
OSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
OSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
OSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
OSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
OSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
OSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
OSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
OSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
OSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
OSP International LLC
 
Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!
OSP International LLC
 
Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!
OSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
OSP International LLC
 

More from OSP International LLC (20)

Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free CAPM Exam Sample Question for the Week
Free CAPM Exam Sample Question for the WeekFree CAPM Exam Sample Question for the Week
Free CAPM Exam Sample Question for the Week
 
Free PMP Exam Sample Question for the Week
Free PMP Exam Sample Question for the WeekFree PMP Exam Sample Question for the Week
Free PMP Exam Sample Question for the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!
 
Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 

Recently uploaded

Protected Workmen required today for growth
Protected Workmen required today for growthProtected Workmen required today for growth
Protected Workmen required today for growth
rivaraj2711
 
Founder-Game Director Workshop (Session 1)
Founder-Game Director  Workshop (Session 1)Founder-Game Director  Workshop (Session 1)
Founder-Game Director Workshop (Session 1)
Amir H. Fassihi
 
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
tdt5v4b
 
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
juniourjohnstone
 
Senior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdfSenior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdf
Jim Smith
 
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish GermanCV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
EUS+ Management & Consulting Excellence
 
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
tdt5v4b
 
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
tdt5v4b
 
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
William (Bill) H. Bender, FCSI
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
Muhammad Adil Jamil
 
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
tdt5v4b
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
gcljeuzdu
 
TCS AI for Business Study – Key Findings
TCS AI for Business Study – Key FindingsTCS AI for Business Study – Key Findings
TCS AI for Business Study – Key Findings
Tata Consultancy Services
 
W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
William (Bill) H. Bender, FCSI
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
akaash13
 
Case Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of ManagementCase Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of Management
A. F. M. Rubayat-Ul Jannat
 

Recently uploaded (16)

Protected Workmen required today for growth
Protected Workmen required today for growthProtected Workmen required today for growth
Protected Workmen required today for growth
 
Founder-Game Director Workshop (Session 1)
Founder-Game Director  Workshop (Session 1)Founder-Game Director  Workshop (Session 1)
Founder-Game Director Workshop (Session 1)
 
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
 
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
 
Senior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdfSenior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdf
 
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish GermanCV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
 
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
 
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
 
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
 
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
 
TCS AI for Business Study – Key Findings
TCS AI for Business Study – Key FindingsTCS AI for Business Study – Key Findings
TCS AI for Business Study – Key Findings
 
W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
 
Case Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of ManagementCase Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of Management
 

Free PMP Exam Sample Question

  • 2. You are part of a cross-functional development team piloting an adaptive approach to project management in an organization that has traditionally used a predictive approach. You realize that you have to tailor the template of the schedule management plan. Which of the following components of the template are you likely to tailor the most? A. The rules of performance measurement, the summary milestones, and the key deliverables B. The organizational procedures links, the units of measure, and the project organization charts C. The schedule model development, the release and iteration length, and the reporting formats D. The project schedule model maintenance, the level of accuracy, and the level of precision HINT: To eliminate some choices, look for items that are not components of the schedule management plan. Question
  • 3. The correct answer is C. The question suggests you are carrying out the Plan Schedule Management process. The schedule management plan is the primary output of this process. The schedule management plan establishes the criteria and the activities for developing, monitoring, and controlling the schedule. Of the choices presented, only the schedule model development, the release and iteration length, and the reporting formats are components of the schedule management plan. All three of these components would merit significant tailoring to reflect an adaptive approach to project management. The project schedule model development specifies the scheduling methodology and the scheduling tool used to develop the schedule model. Answer
  • 4. For an adaptive approach, the schedule model will be a selected series of activities needed to complete a high-priority subset of the project scope that can deliver value quickly. The release and iteration length determine the time-boxed events that must be completed and how long it will take to release the iteration. The reporting formats will be driven by the adaptive schedule model and the iteration length. The other answer choices contain components that are not part of the schedule management plan. Answer
  • 5. All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.