SlideShare a Scribd company logo
1 of 4
Download to read offline
PMP EXAM
SAMPLE Q & A
In a pharmaceutical project, human trials have been started. The CEO is thrilled about the success of the trials
up to this point. She announces that the size of the patient pool for the trials should double from the one
originally planned and results tracked in the new system launching this week.
What should the project manager do first?
A. Ramp up production to match the demand of the CEO
B. Consider what might be included in a change request
C. Adjust the scope baseline to reflect the increased trial size
D. Communicate the change in the scope to the project stakeholders
HINT: Does the project team have the approval to make changes?
Question
The correct answer is B.
Managing changes to the project by following the organization's change control process established for
the project is important in keeping the project under control and operating effectively.
Changes to scope, like in the scenario of doubling the size of the patient pool as well as tracking the results
in the new system, require evaluation, agreement, and approval. Who makes those approvals is up to the
project organization and its change management plans.
But before any changes are implemented or communicated, the change request must be submitted per
the project's procedure and approved by those authorized to do so.
A CEO's declaration of what should happen in the project does not substitute for the project's change
control procedures and the Perform Integrated Change Control process.
Answer
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.

More Related Content

Similar to PMP Exam Q & A

Relocation of Us headquarters Technology firmJi Pete.docx
Relocation of Us headquarters Technology firmJi Pete.docxRelocation of Us headquarters Technology firmJi Pete.docx
Relocation of Us headquarters Technology firmJi Pete.docx
carlt4
 
Relocation of Us headquarters Technology firmJi Pete.docx
Relocation of Us headquarters Technology firmJi Pete.docxRelocation of Us headquarters Technology firmJi Pete.docx
Relocation of Us headquarters Technology firmJi Pete.docx
debishakespeare
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1
Daniel Hucks
 
Change management
Change managementChange management
Change management
mehak1990
 

Similar to PMP Exam Q & A (20)

04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
Free PMP Exam Q & A
 Free PMP Exam Q & A Free PMP Exam Q & A
Free PMP Exam Q & A
 
PMP Exam Q & A
PMP Exam Q & APMP Exam Q & A
PMP Exam Q & A
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
Relocation of Us headquarters Technology firmJi Pete.docx
Relocation of Us headquarters Technology firmJi Pete.docxRelocation of Us headquarters Technology firmJi Pete.docx
Relocation of Us headquarters Technology firmJi Pete.docx
 
Relocation of Us headquarters Technology firmJi Pete.docx
Relocation of Us headquarters Technology firmJi Pete.docxRelocation of Us headquarters Technology firmJi Pete.docx
Relocation of Us headquarters Technology firmJi Pete.docx
 
Free PMP® Exam Sample Question
Free PMP® Exam Sample QuestionFree PMP® Exam Sample Question
Free PMP® Exam Sample Question
 
Free PMP® Exam Sample Question
Free PMP® Exam Sample QuestionFree PMP® Exam Sample Question
Free PMP® Exam Sample Question
 
Free PMP Exam Sample Question
Free PMP Exam Sample QuestionFree PMP Exam Sample Question
Free PMP Exam Sample Question
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1
 
#Perform Integrated Change Control (PICC) Process for PMP Exam - By SN Panig...
#Perform Integrated Change Control (PICC)  Process for PMP Exam - By SN Panig...#Perform Integrated Change Control (PICC)  Process for PMP Exam - By SN Panig...
#Perform Integrated Change Control (PICC) Process for PMP Exam - By SN Panig...
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
Free CAPM Exam Sample Question
Free CAPM Exam Sample QuestionFree CAPM Exam Sample Question
Free CAPM Exam Sample Question
 
CAPM Sample Q and A
CAPM Sample Q and ACAPM Sample Q and A
CAPM Sample Q and A
 
CAPM Sample Q and A
CAPM Sample Q and ACAPM Sample Q and A
CAPM Sample Q and A
 
Change management
Change managementChange management
Change management
 
Project Methodology - On The Fly
Project Methodology - On The FlyProject Methodology - On The Fly
Project Methodology - On The Fly
 

More from OSP International LLC

More from OSP International LLC (20)

Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free CAPM Exam Sample Question from the PM Exam Simulator
Free CAPM Exam Sample Question from the PM Exam SimulatorFree CAPM Exam Sample Question from the PM Exam Simulator
Free CAPM Exam Sample Question from the PM Exam Simulator
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question from The PM Exam Simulator
Free PMP Exam Sample Question from The PM Exam SimulatorFree PMP Exam Sample Question from The PM Exam Simulator
Free PMP Exam Sample Question from The PM Exam Simulator
 
Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!
 
Free PMP Exam Sample Question of the week
Free PMP Exam Sample Question of the weekFree PMP Exam Sample Question of the week
Free PMP Exam Sample Question of the week
 

Recently uploaded

Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
negromaestrong
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
heathfieldcps1
 

Recently uploaded (20)

Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIFood Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Role Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptxRole Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptx
 
Asian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptxAsian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptx
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 

PMP Exam Q & A

  • 2. In a pharmaceutical project, human trials have been started. The CEO is thrilled about the success of the trials up to this point. She announces that the size of the patient pool for the trials should double from the one originally planned and results tracked in the new system launching this week. What should the project manager do first? A. Ramp up production to match the demand of the CEO B. Consider what might be included in a change request C. Adjust the scope baseline to reflect the increased trial size D. Communicate the change in the scope to the project stakeholders HINT: Does the project team have the approval to make changes? Question
  • 3. The correct answer is B. Managing changes to the project by following the organization's change control process established for the project is important in keeping the project under control and operating effectively. Changes to scope, like in the scenario of doubling the size of the patient pool as well as tracking the results in the new system, require evaluation, agreement, and approval. Who makes those approvals is up to the project organization and its change management plans. But before any changes are implemented or communicated, the change request must be submitted per the project's procedure and approved by those authorized to do so. A CEO's declaration of what should happen in the project does not substitute for the project's change control procedures and the Perform Integrated Change Control process. Answer
  • 4. All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.