SlideShare a Scribd company logo
1 of 28
Download to read offline
THE VALUE
OF PROJECT
RISK MANAGEMENT
WEDNESDAY FEBRUARY 25, 2015
0
100
ProjectPredictability
Risk Implementation Maturity
 Improve project delivery
 Improve communications
 Better balance strategic
needs with capital planning
Goal for Today
Discuss Value of Applying Risk Management to Projects
PMA CONSULTANTS LLC | 2
Agenda
Introductions
What is project risk
Intro to project risk management
The value of risk management
Deploying a risk management process
PMA CONSULTANTS LLC | 3
INTRODUCTIONS
PMA CONSULTANTS LLC | 4
Presenters
• Dax Ponce de Leon, PMP, LEED AP BD+C
– 12 years experience in project management, project controls, planning, scheduling,
risk management
• Dane McBaine, PMP, LEED AP
– 11 years experience, including in risk management process on large capital program
• Herschel Baxi, PMP, LEED AP
– 20 years experience, including in deployment of risk management process on large
capital program
PMA CONSULTANTS LLC | 5
About PMA Consultants
Top 50 ENR Program /
Construction Management Firm
Specializing in owner
representation, project
controls, claims management,
and project risk management Projects in rail, ports, aviation, infrastructure, oil/gas,
pharmaceutical, higher education
RISK EXPERIENCE
PMA CONSULTANTS LLC | 6
15YEARS
250RISK ASSESSMENTS
$50BPROJECT VALUE
WHAT IS PROJECT RISK
PMA CONSULTANTS LLC | 7
Project Risk
Uncertain events that, if occurring, have an impact on
one or more project objectives such as scope,
schedule, cost, and quality
Project risk collectively causes fluctuation in capital
expenditure and forecasting
SOURCE: PMBOK 5TH ED. PMA CONSULTANTS LLC | 8
How Does Risk Affect Projects?
REASONS FOR COST OVERRUN
60%
55%
40%
36%
32%
19%
6%
4%
2%
26%
0% 10% 20% 30% 40% 50% 60% 70%
Material Price Escalation
Poorly Defined Scope
Contractual Disputes
Time Delay
Design Creep
Achieving Productivities
Lack of Approvals
Weather
Industrial Relations
Other
REASONS FOR SCHEDULE DELAY
57%
57%
36%
34%
21%
17%
15%
13%
2%
19%
0% 10% 20% 30% 40% 50% 60%
Poorly Defined Scope
Design Creep
Lack of Approvals
Contractual Disputes
Weather
Time Delay
Achieving Productivities
Material Price Escalation
Commissioning Process
Other
SOURCE: KPMG GLOBAL CONSTRUCTION SURVEY 2008 PMA CONSULTANTS LLC | 9
Risk Response Strategies
PMA CONSULTANTS LLC | 10
INTRO TO PROJECT RISK
MANAGEMENT
PMA CONSULTANTS LLC | 11
Project Risk Management Process
PMA CONSULTANTS LLC | 12
PROJECT
COMMUNICATION
Risk
Management
Planning
Review Process
Risk
Identification
Risk
Quantification
Risk Response
Planning
Summarize
Risk Monitoring
& Control
Comprehensive strategy
for identifying and
controlling risk on a
project
Identify Prioritize Model
Summarize
SimulateRange
 Possible risks &
response plans
 Critical & risk-
sensitive
sequences
 Cost breakdown,
variables,
distributions
 Activity durations
 Cost variables: scope,
price, productivity
 PertMaster,
NetRisk, @Risk
 Report, graphics, options
to mitigate risks
 Recommended
cost/schedule
contingencies
 Estimate issues,
possible risks,
response plans
Review
 Scope, assumptions
 Schedules, estimates
 Execution Plans &
strategy
Risk
Management
Plan
QUALITATIVE RISK ANALYSIS QUANTITATIVE RISK ANALYSIS
PMA CONSULTANTS LLC | 13
Typical Risk Assessment Process
Results of Quantitative Cost Risk Analysis
Objective: evaluate likelihood of completing project within a certain cost
Current project estimate (MM) $10
Methodology: Cost Risk Analysis
Likelihood of completion at $10MM 10%
Project cost for 90% confidence (MM) $15
Output: project contingency informs capital planning
New project contingency (MM) $5
PMA CONSULTANTS LLC | 14
Results of Quantitative Schedule Risk Analysis
Objective: evaluate likelihood of completing project within a certain time
Current project schedule (months) 24
Methodology: Schedule Risk Analysis
Likelihood of completion in 24 months 24%
Project duration for 90% confidence (months) 28
Output: project cash flow informs capital planning
Revised schedule contingency (months) 4
Adjust project cash flow for additional 6 months
PMA CONSULTANTS LLC | 15
Distribution of Project Completion Date
The project schedule deterministic
date of 16-Sep-14 is in the 24th
percentile of the simulation results
PMA CONSULTANTS LLC | 16
A Risk-Focused Mindset Improves Project Delivery
 Clarity in scope assumptions
 Better estimates
 Better schedules
 Improved project controls
Project Document Review
 Focus on project agenda
 Recognition and
transparency in project
challenges
 Early risk warnings and
mitigation strategies
 Brainstorming and
innovative solutions
 Risk Register as a project
team’s tool
 Key stakeholders to the table
Qualitative Assessment
 Risk-based, quantified
project contingencies
 Support to project change
management
Quantitative Analysis
PMA CONSULTANTS LLC | 17
THE VALUE OF
RISK MANAGEMENT
PMA CONSULTANTS LLC | 18
Project Contingency and Capital Planning
Source: Flyvbjerg, B. - Survival of the Unfittest, 2009 PMA CONSULTANTS LLC | 19
45%
34%
20%
0%
10%
20%
30%
40%
50%
RailBridges and TunnelsRoad
Average Cost Overrun
Budget overruns contingency,
which impacts capital planning
In any given period, inadequate or
excessive capital dollars are reserved
Risk Workshops – Multiple Benefits
TRANSPARENCY
COLLABORATION
ACTION
 Early risk warnings
and opportunities
 Improves other
project management
processes
 Improves project
communication
 Collaborative
problem solving
 Include all
stakeholders
 No agenda other
than project success
 Added transparency
in project challenges
Probabilistic 
Simulation is only 
one component
PMA CONSULTANTS LLC | 20
Service
Provider
External
Stakeholders
Senior
Management
Business
Units
Project Risk Management Improves Communications
• Risk process – transparent,
collaborative, proactive
• Funding requests include clear view
of risks, impacts, and mitigation
strategies
PMA CONSULTANTS LLC | 21
The Bottom Line - Improved Capital Planning
Strategic
Capital
Needs
Annual
Capital
Forecast
Judicious
Capital
Reserves
Reasonable
Annual
Spreads
Capital Project
Contingencies
Based on Cost
Risk Analysis
Project Cash
Flow Based
on Schedule
Risk Analysis
PMA CONSULTANTS LLC | 22
DEPLOYING A RISK
MANAGEMENT PROCESS
PMA CONSULTANTS LLC | 23
Need For A Flexible Project Risk Management Process
PMA CONSULTANTS LLC | 24
Gradual change in
processes and
organization
Tailored to project size,
type, complexity
Need not be expensive!
Phased Scalable
Deploying A Risk Management Program
Risk Management
is implemented
piecemeal
Nurture Risk
Management
processes
Risk Management
becomes a
mature project
management
process
Start
here
“Low-hanging fruits”
Look for quick successes
PMA CONSULTANTS LLC | 25
Independent Analyst vs. Self-Performed by ProjectTeam
• Independent Analyst can bring
– Unbiased perspective
– Outside perspective
– Cold-eyed review of project plan
– Standard process
• Usually, project members are willing to share concerns
more openly with an independent analyst
• In collaboration with project team, can help to identify
challenges
PMA CONSULTANTS LLC | 26
Leveraging An Independent Analyst
Facilitate risk
assessments on larger,
complex projects
Drive adoption of
qualitative risk analysis
within project teams
(develop & maintain
risk registers)
Design, implement,
and hand-off a
comprehensive risk
management process
which is phased,
scalable, and robust
1 2 3
PMA CONSULTANTS LLC | 27
Value of Applying a Project Risk Management Process
Strategic
Capital
Needs
Annual
Capital
Forecast
Judicious
Capital
Reserves
Reasonable
Annual
Spreads
Transparent, scalable,
collaborative risk
management process
improves project
predictability
Funding requests include
clear view of risks,
impacts, and mitigation
strategies
Balanced capital plans
0
100
ProjectPredictability
Risk Implementation Maturity
PMA CONSULTANTS LLC | 28
Service
Provider
External
Stakeholders
Senior
Management
Business
Units

More Related Content

What's hot

Risk management plan
Risk management planRisk management plan
Risk management plan
Kashif Mastan
 
Presentation manage risk
Presentation manage riskPresentation manage risk
Presentation manage risk
Michael Curtis
 
Qualitative & Quantitative Analysis
Qualitative & Quantitative AnalysisQualitative & Quantitative Analysis
Qualitative & Quantitative Analysis
Alin Veronika
 
Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)
Serdar Temiz
 

What's hot (20)

Risk management plan
Risk management planRisk management plan
Risk management plan
 
Construction Risk Summit "benefit and pits of Construction Risk Management"
Construction Risk Summit   "benefit and pits of Construction Risk Management"Construction Risk Summit   "benefit and pits of Construction Risk Management"
Construction Risk Summit "benefit and pits of Construction Risk Management"
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
Risk management
Risk managementRisk management
Risk management
 
Qualitative risk analysis
Qualitative risk analysisQualitative risk analysis
Qualitative risk analysis
 
Risk strategies presentation
Risk strategies presentationRisk strategies presentation
Risk strategies presentation
 
Risk management poster
Risk management posterRisk management poster
Risk management poster
 
12. Project Risk Management
12. Project Risk Management12. Project Risk Management
12. Project Risk Management
 
Advanced program management risk mitigation and management
Advanced program management   risk mitigation and managementAdvanced program management   risk mitigation and management
Advanced program management risk mitigation and management
 
Presentation manage risk
Presentation manage riskPresentation manage risk
Presentation manage risk
 
STRIDE Standard Process for RISK
STRIDE Standard Process for RISKSTRIDE Standard Process for RISK
STRIDE Standard Process for RISK
 
Project risk management: Techniques and strategies
Project risk management: Techniques and strategiesProject risk management: Techniques and strategies
Project risk management: Techniques and strategies
 
Qualitative & Quantitative Analysis
Qualitative & Quantitative AnalysisQualitative & Quantitative Analysis
Qualitative & Quantitative Analysis
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best Practices
 
PROJECT RISK MANAGEMENT ... complete training materials and others at www.ga...
PROJECT RISK MANAGEMENT ...  complete training materials and others at www.ga...PROJECT RISK MANAGEMENT ...  complete training materials and others at www.ga...
PROJECT RISK MANAGEMENT ... complete training materials and others at www.ga...
 
Stephen Ward: Performance uncertainty management is a more effective approach...
Stephen Ward: Performance uncertainty management is a more effective approach...Stephen Ward: Performance uncertainty management is a more effective approach...
Stephen Ward: Performance uncertainty management is a more effective approach...
 
Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)
 
112 risk management
112 risk management112 risk management
112 risk management
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Project Management Risks Review
Project Management Risks ReviewProject Management Risks Review
Project Management Risks Review
 

Viewers also liked

Risk & Risk Management
Risk & Risk ManagementRisk & Risk Management
Risk & Risk Management
ansula
 
Risk mangement
Risk mangementRisk mangement
Risk mangement
college
 
Project Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K SinhaProject Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K Sinha
Pankaj K Sinha
 

Viewers also liked (18)

Project risk and value in supply chain management
Project risk and value in supply chain managementProject risk and value in supply chain management
Project risk and value in supply chain management
 
Certified Ethical Hacking - Book Summary
Certified Ethical Hacking - Book SummaryCertified Ethical Hacking - Book Summary
Certified Ethical Hacking - Book Summary
 
Ceh v5 module 22 penetration testing
Ceh v5 module 22 penetration testingCeh v5 module 22 penetration testing
Ceh v5 module 22 penetration testing
 
Pert master risk analysis tool
Pert master   risk analysis toolPert master   risk analysis tool
Pert master risk analysis tool
 
Value at risk
Value at riskValue at risk
Value at risk
 
2017 | E-Brochure | PMP® Fast Track (4 Days) | Project Management Training - ...
2017 | E-Brochure | PMP® Fast Track (4 Days) | Project Management Training - ...2017 | E-Brochure | PMP® Fast Track (4 Days) | Project Management Training - ...
2017 | E-Brochure | PMP® Fast Track (4 Days) | Project Management Training - ...
 
Ce hv6 module 57 computer forensics and incident handling
Ce hv6 module 57 computer forensics and incident handlingCe hv6 module 57 computer forensics and incident handling
Ce hv6 module 57 computer forensics and incident handling
 
Pmp risk management
Pmp risk managementPmp risk management
Pmp risk management
 
Introduction To Value At Risk
Introduction To Value At RiskIntroduction To Value At Risk
Introduction To Value At Risk
 
Incident Response: Don't Mess It Up, Here's How To Get It Right
Incident Response: Don't Mess It Up, Here's How To Get It RightIncident Response: Don't Mess It Up, Here's How To Get It Right
Incident Response: Don't Mess It Up, Here's How To Get It Right
 
Feasibility study about Poultry Business
Feasibility study about Poultry BusinessFeasibility study about Poultry Business
Feasibility study about Poultry Business
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Feasibility Study (Water Refilling Station)
Feasibility Study (Water Refilling Station)Feasibility Study (Water Refilling Station)
Feasibility Study (Water Refilling Station)
 
Risk & Risk Management
Risk & Risk ManagementRisk & Risk Management
Risk & Risk Management
 
Risk mangement
Risk mangementRisk mangement
Risk mangement
 
Risk management
Risk managementRisk management
Risk management
 
Project Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K SinhaProject Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K Sinha
 
Risk Management Framework
Risk Management FrameworkRisk Management Framework
Risk Management Framework
 

Similar to The Value of Project Risk Management

Raid based approach for efficient project management in a pragmatic way towar...
Raid based approach for efficient project management in a pragmatic way towar...Raid based approach for efficient project management in a pragmatic way towar...
Raid based approach for efficient project management in a pragmatic way towar...
Phanindra Kishore
 

Similar to The Value of Project Risk Management (20)

16 Risk-final- V Imp.ppt
16 Risk-final- V Imp.ppt16 Risk-final- V Imp.ppt
16 Risk-final- V Imp.ppt
 
Simple approach to managing preparedness projects
Simple approach to managing preparedness projectsSimple approach to managing preparedness projects
Simple approach to managing preparedness projects
 
Risk Management
Risk Management Risk Management
Risk Management
 
Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...
 Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen... Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...
Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...
 
Андрій Мудрий «Risk managemnt: Welcome to Risk World»
Андрій Мудрий «Risk managemnt: Welcome to Risk World»Андрій Мудрий «Risk managemnt: Welcome to Risk World»
Андрій Мудрий «Risk managemnt: Welcome to Risk World»
 
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaOnline PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
 
Strategic PMO - Align Projects to Corporate Strategy
Strategic PMO - Align Projects to Corporate StrategyStrategic PMO - Align Projects to Corporate Strategy
Strategic PMO - Align Projects to Corporate Strategy
 
9. Risk.ppt
9. Risk.ppt9. Risk.ppt
9. Risk.ppt
 
9. Risk.ppt
9. Risk.ppt9. Risk.ppt
9. Risk.ppt
 
9. Risk.ppt
9. Risk.ppt9. Risk.ppt
9. Risk.ppt
 
9. Risk.ppt
9. Risk.ppt9. Risk.ppt
9. Risk.ppt
 
project managment.ppt
project managment.pptproject managment.ppt
project managment.ppt
 
9. Risk.ppt
9. Risk.ppt9. Risk.ppt
9. Risk.ppt
 
9. Risk.ppt
9. Risk.ppt9. Risk.ppt
9. Risk.ppt
 
9. Risk.ppt
9. Risk.ppt9. Risk.ppt
9. Risk.ppt
 
Portfolio, programme and project risk (Peter Campbell)
Portfolio, programme and project risk (Peter Campbell)Portfolio, programme and project risk (Peter Campbell)
Portfolio, programme and project risk (Peter Campbell)
 
Managing risk as Opportunity
Managing risk as OpportunityManaging risk as Opportunity
Managing risk as Opportunity
 
All About PMI - RMP Certification
All About PMI - RMP CertificationAll About PMI - RMP Certification
All About PMI - RMP Certification
 
Raid based approach for efficient project management in a pragmatic way towar...
Raid based approach for efficient project management in a pragmatic way towar...Raid based approach for efficient project management in a pragmatic way towar...
Raid based approach for efficient project management in a pragmatic way towar...
 
Planning
PlanningPlanning
Planning
 

More from PMA Consultants

More from PMA Consultants (20)

Practical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital ProjectsPractical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital Projects
 
Project Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons LearntProject Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons Learnt
 
PANDEMIC RESILIENTSCHOOLS
PANDEMIC RESILIENTSCHOOLSPANDEMIC RESILIENTSCHOOLS
PANDEMIC RESILIENTSCHOOLS
 
BioPharma Projects: Essentials in Project Controls
BioPharma Projects: Essentials in Project ControlsBioPharma Projects: Essentials in Project Controls
BioPharma Projects: Essentials in Project Controls
 
How to Implement a Project Management Information System
How to Implement a Project Management Information SystemHow to Implement a Project Management Information System
How to Implement a Project Management Information System
 
Top Five Metrics for Measuring Schedule Reliability
Top Five Metrics for Measuring Schedule ReliabilityTop Five Metrics for Measuring Schedule Reliability
Top Five Metrics for Measuring Schedule Reliability
 
What are the disadvantages of Gantt charts?
What are the disadvantages of Gantt charts?What are the disadvantages of Gantt charts?
What are the disadvantages of Gantt charts?
 
BIM and VDC for Megaproject Construction Projects
BIM and VDC for Megaproject Construction ProjectsBIM and VDC for Megaproject Construction Projects
BIM and VDC for Megaproject Construction Projects
 
Setting up Filters & Layouts in P6
Setting up Filters & Layouts in P6Setting up Filters & Layouts in P6
Setting up Filters & Layouts in P6
 
How to Choose a Project Delivery Method
How to Choose a Project Delivery MethodHow to Choose a Project Delivery Method
How to Choose a Project Delivery Method
 
Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry Klanac
 
Project Controls Processes
Project Controls ProcessesProject Controls Processes
Project Controls Processes
 
Work Breakdown Structure Planning in NetPoint
Work Breakdown Structure Planning in NetPointWork Breakdown Structure Planning in NetPoint
Work Breakdown Structure Planning in NetPoint
 
How to Import/Export a Schedule between NetPoint and Microsft Excel
How to Import/Export a Schedule between NetPoint and Microsft ExcelHow to Import/Export a Schedule between NetPoint and Microsft Excel
How to Import/Export a Schedule between NetPoint and Microsft Excel
 
Smarter Planning with Microsoft Excel
Smarter Planning with Microsoft ExcelSmarter Planning with Microsoft Excel
Smarter Planning with Microsoft Excel
 
In Pursuit of Reliable Schedules
In Pursuit of Reliable SchedulesIn Pursuit of Reliable Schedules
In Pursuit of Reliable Schedules
 
Leveraging NetPoint & Excel for Template-Based Project Planning
Leveraging NetPoint & Excel for Template-Based Project PlanningLeveraging NetPoint & Excel for Template-Based Project Planning
Leveraging NetPoint & Excel for Template-Based Project Planning
 
Risk 2196 Removing the Early-Dates Bias in CPM Risk Analysis
Risk 2196 Removing the Early-Dates Bias in CPM Risk AnalysisRisk 2196 Removing the Early-Dates Bias in CPM Risk Analysis
Risk 2196 Removing the Early-Dates Bias in CPM Risk Analysis
 
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
 
P6 tips tricks-client
P6 tips tricks-clientP6 tips tricks-client
P6 tips tricks-client
 

Recently uploaded

DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 

Recently uploaded (20)

DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 

The Value of Project Risk Management

  • 1. THE VALUE OF PROJECT RISK MANAGEMENT WEDNESDAY FEBRUARY 25, 2015
  • 2. 0 100 ProjectPredictability Risk Implementation Maturity  Improve project delivery  Improve communications  Better balance strategic needs with capital planning Goal for Today Discuss Value of Applying Risk Management to Projects PMA CONSULTANTS LLC | 2
  • 3. Agenda Introductions What is project risk Intro to project risk management The value of risk management Deploying a risk management process PMA CONSULTANTS LLC | 3
  • 5. Presenters • Dax Ponce de Leon, PMP, LEED AP BD+C – 12 years experience in project management, project controls, planning, scheduling, risk management • Dane McBaine, PMP, LEED AP – 11 years experience, including in risk management process on large capital program • Herschel Baxi, PMP, LEED AP – 20 years experience, including in deployment of risk management process on large capital program PMA CONSULTANTS LLC | 5
  • 6. About PMA Consultants Top 50 ENR Program / Construction Management Firm Specializing in owner representation, project controls, claims management, and project risk management Projects in rail, ports, aviation, infrastructure, oil/gas, pharmaceutical, higher education RISK EXPERIENCE PMA CONSULTANTS LLC | 6 15YEARS 250RISK ASSESSMENTS $50BPROJECT VALUE
  • 7. WHAT IS PROJECT RISK PMA CONSULTANTS LLC | 7
  • 8. Project Risk Uncertain events that, if occurring, have an impact on one or more project objectives such as scope, schedule, cost, and quality Project risk collectively causes fluctuation in capital expenditure and forecasting SOURCE: PMBOK 5TH ED. PMA CONSULTANTS LLC | 8
  • 9. How Does Risk Affect Projects? REASONS FOR COST OVERRUN 60% 55% 40% 36% 32% 19% 6% 4% 2% 26% 0% 10% 20% 30% 40% 50% 60% 70% Material Price Escalation Poorly Defined Scope Contractual Disputes Time Delay Design Creep Achieving Productivities Lack of Approvals Weather Industrial Relations Other REASONS FOR SCHEDULE DELAY 57% 57% 36% 34% 21% 17% 15% 13% 2% 19% 0% 10% 20% 30% 40% 50% 60% Poorly Defined Scope Design Creep Lack of Approvals Contractual Disputes Weather Time Delay Achieving Productivities Material Price Escalation Commissioning Process Other SOURCE: KPMG GLOBAL CONSTRUCTION SURVEY 2008 PMA CONSULTANTS LLC | 9
  • 10. Risk Response Strategies PMA CONSULTANTS LLC | 10
  • 11. INTRO TO PROJECT RISK MANAGEMENT PMA CONSULTANTS LLC | 11
  • 12. Project Risk Management Process PMA CONSULTANTS LLC | 12 PROJECT COMMUNICATION Risk Management Planning Review Process Risk Identification Risk Quantification Risk Response Planning Summarize Risk Monitoring & Control Comprehensive strategy for identifying and controlling risk on a project
  • 13. Identify Prioritize Model Summarize SimulateRange  Possible risks & response plans  Critical & risk- sensitive sequences  Cost breakdown, variables, distributions  Activity durations  Cost variables: scope, price, productivity  PertMaster, NetRisk, @Risk  Report, graphics, options to mitigate risks  Recommended cost/schedule contingencies  Estimate issues, possible risks, response plans Review  Scope, assumptions  Schedules, estimates  Execution Plans & strategy Risk Management Plan QUALITATIVE RISK ANALYSIS QUANTITATIVE RISK ANALYSIS PMA CONSULTANTS LLC | 13 Typical Risk Assessment Process
  • 14. Results of Quantitative Cost Risk Analysis Objective: evaluate likelihood of completing project within a certain cost Current project estimate (MM) $10 Methodology: Cost Risk Analysis Likelihood of completion at $10MM 10% Project cost for 90% confidence (MM) $15 Output: project contingency informs capital planning New project contingency (MM) $5 PMA CONSULTANTS LLC | 14
  • 15. Results of Quantitative Schedule Risk Analysis Objective: evaluate likelihood of completing project within a certain time Current project schedule (months) 24 Methodology: Schedule Risk Analysis Likelihood of completion in 24 months 24% Project duration for 90% confidence (months) 28 Output: project cash flow informs capital planning Revised schedule contingency (months) 4 Adjust project cash flow for additional 6 months PMA CONSULTANTS LLC | 15
  • 16. Distribution of Project Completion Date The project schedule deterministic date of 16-Sep-14 is in the 24th percentile of the simulation results PMA CONSULTANTS LLC | 16
  • 17. A Risk-Focused Mindset Improves Project Delivery  Clarity in scope assumptions  Better estimates  Better schedules  Improved project controls Project Document Review  Focus on project agenda  Recognition and transparency in project challenges  Early risk warnings and mitigation strategies  Brainstorming and innovative solutions  Risk Register as a project team’s tool  Key stakeholders to the table Qualitative Assessment  Risk-based, quantified project contingencies  Support to project change management Quantitative Analysis PMA CONSULTANTS LLC | 17
  • 18. THE VALUE OF RISK MANAGEMENT PMA CONSULTANTS LLC | 18
  • 19. Project Contingency and Capital Planning Source: Flyvbjerg, B. - Survival of the Unfittest, 2009 PMA CONSULTANTS LLC | 19 45% 34% 20% 0% 10% 20% 30% 40% 50% RailBridges and TunnelsRoad Average Cost Overrun Budget overruns contingency, which impacts capital planning In any given period, inadequate or excessive capital dollars are reserved
  • 20. Risk Workshops – Multiple Benefits TRANSPARENCY COLLABORATION ACTION  Early risk warnings and opportunities  Improves other project management processes  Improves project communication  Collaborative problem solving  Include all stakeholders  No agenda other than project success  Added transparency in project challenges Probabilistic  Simulation is only  one component PMA CONSULTANTS LLC | 20
  • 21. Service Provider External Stakeholders Senior Management Business Units Project Risk Management Improves Communications • Risk process – transparent, collaborative, proactive • Funding requests include clear view of risks, impacts, and mitigation strategies PMA CONSULTANTS LLC | 21
  • 22. The Bottom Line - Improved Capital Planning Strategic Capital Needs Annual Capital Forecast Judicious Capital Reserves Reasonable Annual Spreads Capital Project Contingencies Based on Cost Risk Analysis Project Cash Flow Based on Schedule Risk Analysis PMA CONSULTANTS LLC | 22
  • 23. DEPLOYING A RISK MANAGEMENT PROCESS PMA CONSULTANTS LLC | 23
  • 24. Need For A Flexible Project Risk Management Process PMA CONSULTANTS LLC | 24 Gradual change in processes and organization Tailored to project size, type, complexity Need not be expensive! Phased Scalable
  • 25. Deploying A Risk Management Program Risk Management is implemented piecemeal Nurture Risk Management processes Risk Management becomes a mature project management process Start here “Low-hanging fruits” Look for quick successes PMA CONSULTANTS LLC | 25
  • 26. Independent Analyst vs. Self-Performed by ProjectTeam • Independent Analyst can bring – Unbiased perspective – Outside perspective – Cold-eyed review of project plan – Standard process • Usually, project members are willing to share concerns more openly with an independent analyst • In collaboration with project team, can help to identify challenges PMA CONSULTANTS LLC | 26
  • 27. Leveraging An Independent Analyst Facilitate risk assessments on larger, complex projects Drive adoption of qualitative risk analysis within project teams (develop & maintain risk registers) Design, implement, and hand-off a comprehensive risk management process which is phased, scalable, and robust 1 2 3 PMA CONSULTANTS LLC | 27
  • 28. Value of Applying a Project Risk Management Process Strategic Capital Needs Annual Capital Forecast Judicious Capital Reserves Reasonable Annual Spreads Transparent, scalable, collaborative risk management process improves project predictability Funding requests include clear view of risks, impacts, and mitigation strategies Balanced capital plans 0 100 ProjectPredictability Risk Implementation Maturity PMA CONSULTANTS LLC | 28 Service Provider External Stakeholders Senior Management Business Units