Rajesh Prasad Singh
Prepared by:
Collection of Waste Water
• From place of origin to place of treatment or
disposal(Sewerage System)
• What are collected
– Domestic wastewater
– Industrial wastewater
– Infiltration/inflow
– Storm water
Types of Collection System
1)Sanitary wastewater system
2)Combined sanitary and storm water collection system
3)Storm water collection system
Choice of System
Combined System Separate system
Volume of water reaching WWTP High
Sewer size Large
Self cleansing velocity during dry period
LOW, so deposits of solid in the sewer
Initial investment HIGH
Low
Smaller size
Basis of design is the required self
cleansing velocity
Low
Combined Sewer
Water
Quality
Standards
for Various
uses
Design Criteria for KathmanduValley
The design flow of the interceptor and collector sewers are to
be adopted as follows.
Design flow of Interceptor/Collector sewer = DS x PF + NDS
+ IN
Design flow of Branch sewer and laterals = DS x PF + NDS + IN + SW
Where, DS = domestic sewage
• NDS = Non domestic sewage
• PF = Peak factor
• IN = Infiltration
• SW = Storm water
Steps in Sewer Design
• Survey and General Investigation
– Precise levels indicating the topography
– Subsoil investigation
– Location of treatment works
– Existing features of the town
– Type of land use
– Population and population density
– Discharge point of the water body with HFL
– One meter contour map
– Existing utilities to be mapped in the layout plan
• System Pattern of Sewerage Layout
– Interceptor pattern
– Zone pattern
– Fan Pattern
– Radial Pattern
• Design Period
Minimum 30 years
• Population
– Use census data
– Real count
– Make projection of future population
– Use population densities where there is possibility of growth in the
future
Wastewater Generation
• Domestic Wastewater
– 100 lpcd up to the year 2020 and 120 lpcd in the year 2030
– 80% of the water consumption becoming sewage flow("Manual on
Sewerage and Sewage Treatment”, Ministry of Urban Development,
November 2013)
Nondomestic Wastewater
wastewater generated from various
industries and commercial establishments
10% of domestic wastewater
Infiltration
infiltration value shall be limited to a
maximum of 10% of the design value of the
sewage flow
Storm Water
Q = CIA
where, Q = storm water flow in m3/s; C = runoff
coefficient or impermeability factor;
I = intensity of rainfall in m/s; and
A=catchment area or drainage area in m2
Runoff Coefficient(C)
Land Use
Runoff
Coefficient
Land Use
Runoff
Coefficient
Lawns:
Sandy soil, flat, 2% 0.05 - 0.10
Business: Sandy soil, avg., 2-7% 0.10 - 0.15
Downtown area 0.70 - 0.95 Sandy soil, steep, 7% 0.15 - 0.20
Neighborhood area 0.50 - 0.70 Heavy soil, flat, 2% 0.13 - 0.17
Heavy soil, avg., 2-7% 0.18 - 0.22
Heavy soil, steep, 7% 0.25 - 0.35
Agricultural land:
Bare packed soil
Smooth 0.30 - 0.60
Rough 0.20 - 0.50
Residential (urban): Cultivated rows
Single family area 0.30 - 0.50 Heavy soil, no crop 0.30 - 0.60
Multi-units, detached 0.40 - 0.60 Heavy soil, with crop 0.20 - 0.50
Multi-units, attached 0.60 - 0.75 Sandy soil, no crop 0.20 - 0.40
Residential (suburban) 0.25 - 0.40 Sandy soil, with crop 0.10 - 0.25
Apartment areas 0.50 - 0.70 Pasture
Heavy soil 0.15 - 0.45
Sandy soil 0.05 - 0.25
Woodlands 0.05 - 0.25
Streets:
Industrial Asphaltic 0.70 - 0.95
Light areas 0.50 - 0.80 Concrete 0.80 - 0.95
Heavy areas 0.60 - 0.90 Brick 0.70 - 0.85
Parks, cemeteries 0.10 - 0.25 Unimproved areas 0.10 - 0.30
Playgrounds 0.20 - 0.35 Drives and walks 0.75 - 0.85
Railroad yards 0.20 - 0.40 Roofs 0.75 - 0.95
Coefficients
Rainfall Intensity
0
50
100
150
200
250
300
350
0 20 40 60 80 100 120 140 160 180
RainfalIntensity(mm/hr)
Time of Concentration (min)
Rainfall Intensity - Duration - Frequency Curves
Kathmandu Valley
2-year 5-year 10-year 25-year 50-year 100-year
Flow Velocity
• Self Cleaning Velocity
– The minimum velocity at which no solids get deposited in the invert
of the sewer is called self-cleaning velocity. For the design purposes
the self- cleaning velocity has considered as 0.6 m/sec (source:
American Society of Civil Engineers, ASCE).
• The minimum velocity to cause the scouring of the suspension
of solids heavier than the sewage or liquid which carry them is
determined by the following Shield formula:
V =
8k
f
ρs−ρ
ρ
g × d
Where, V = Velocity of flow
k = Characteristics of solids (0.04 -0.06)
• f = Darcy’s coefficient of friction, 0.03
Specific gravity of the solids particles in the
sewage. Its value is between 1.2 and 2.65.
• Specific gravity of the liquid = 1
• g = Acceleration due to gravity
• d = diameter of the particles.
• From the above formula, it is clear that heavier and
sticky solids require velocity for their cleaning.
=
Minimum Velocity
The minimum velocity of 0.6 and 0.8 m/s at the peak flow is
recommended for separate flow and combined/storm water
sewer respectively
Maximum Velocity
The maximum velocity of 3.0 m/sec has been recommended.
Froude number should be less than 1.0 so that supercritical flow
is avoided at the peak flow.
Design Formula
• Design practice is to use Manning’s Formula for open channel
flow and the Hazen Williams and Darcy-Weisbach formulae for
closed conduit or pressure flow (Source: Manual on Sewerage
and Sewage Treatment (Third Edition), Ministry of Urban
Development, November 2013).
The manning's formula is given by the following equation.
V =
1
n
× R
2
3 × S
1
2
Q =
1
n
× A × R
2
3 × S
1
2
Where;
Q = discharge in m3/s
S = slope of hydraulic gradient
R = hydraulic radius in m
A = cross sectional area of flow
V= velocity in m/s
n = Manning’s coefficient of roughness
Roughness Coefficient
Manning roughness coefficients for concrete and HDPE pipes are
recommended as 0.013 and 0.009 respectively
Minimum Sewer Diameter
200 mm for collector, branch and lateral sewers 400 mm for
interceptor sewers
Ruling Gradient
CWWMP recommends a minimum sewer gradient of 1 in 200
Depth of Flow in Sewer
Sewers will be designed in such a way that the depth of flow in
the sewer at peak flow is not more than 0.8 times the diameter
of the sewer i.e. d/D ≤ 0.8
Pipe Features
Pipe Material and Joints
In principle all pipes to be used in the main sewer network
are proposed to be reinforced concrete cement RCC pipes with
spigot and socket ends, jointed through rubber gaskets. RCC
pipes shall be manufactured as per NS80/2042 and IS 458:2003
medium duty, non pressure pipes. The jointing shall be Rubber
Ring Joint (RRJ) type and the rubber gasket to be provided shall
be as per NS, NP3 or exceptionally NP4 RCC (Hume) pipes for
sewer lines as applicable.
Pipe Cover
The minimum cover above the crests of the sewer pipe is to be 1.0 m
Width of Trench
• For diameter up to 450mm, the bottom pipe width of trench shall be
OD+45cm
• For diameter above 450 mm, the bottom width of trench shall be
OD+60cm
• For house connection, the bottom width of trench shall be not less than
OD+30cm
Where OD = outside diameter of pipe
Bedding
Table 3-2: Categories of Bedding
Category
Description Abbreviation
Type 1 Granular bedding GRB
Type 2 Plain Cement Concrete M20 PCCB
Type 3 Reinforced Cement Concrete 0.4%
reinforcement M20
RCCB 0.4
Type 4 Reinforced Cement Concrete 1.0%
reinforcement M20
RCCB 1.0
Type 5
"Arch" bedding for PE pipes including the
combination of anti-flotation precast RCC
blocks every 3m and type 1 bedding in current
sections
ARCH / Type 1
Table 3.3
The proposed bedding type for various pipe materials at different
depths are specified in Table 3-3 and Table 3-4.
Pipe
NP3 -RRJ
Type 1 Type 2 Type 3 Type 4 Type 5
ND OD GRB PCCB RCCB 0.4 RCCB
1.0
ARCH
200 0.26 0-4m 5. m >5m
IfRequired
NotApplicable
250 0.31 0-4m 4-5m >5m
300 0.38 0-4m 4-5m >5m
350 0.50 0-4m 4-5m >5m
400 0.55 0-4m 4-5m >5m
450 0.60 0-4m 4-5m >5m
500 0.65 0-5m 5-6m >6m
600 0.77 0-5m 5-6m >6m
700 0.87 0-5m 5-6m >6m
800 0.99 0-5m 5-6m >6m
900 1.10 0-5m 5-6m >6m
1000 1.23
Not
Applicable
0-7m >7m
1200 1.44 0-7m >7m
1500 1.78 0-7m >7m
Depth Of Trench
Trench Depth = Ground Level – Invert Level + Pipe Thickness + H1
Where, H1 is related to thetype of bedding
H2 and H3 are related to the pipe diameter
H4 is related to the type of bedding
H5 depend of the bedding arrangements and the surface reinstatement
H6 is defined by the characteristics of the surface finishing
H2 + H3 is equal to the outside diameter of the pipe
The concrete cradle depth varies from 0 to H1+H2+H3+H4 depending on the type of bedding.
Density of Population
Size of
town,population
Density of population per
hectare
Upto 5,000
5,000-20,000
20,000-50,000
50,000-100,000
Above 100,000
75-150
150-250
250-300
300-350
350-1000
Carrying Capacity of Domestic Sewer
• Prospective population
• Drinking Water Supply quantity(consider 80% of the water
supply per day) multiplied by Peak Factor
Contributory
Population
Peak Factor
Up to 20,000
20,000-50,000
50,000-7,50,000
Above 7,50,000
3.5
2.5
2.25
2.0
Flow depth in sewer
• Due to ventilation in waste water flow, sewers are not
designed to run full
• Recommended Depth of Flow in Sewers
Size of Sewer Depth of Flow
Upto 400 mm dia
400mm-900mm dia
Larger than 900mmdia
½ depth
2/3 depth
¾ depth
Minimum Size of Sewer
Minimum size of public sewer shall be 150mm dia but
in practice 200mm dia is recommended
Minimum And Maximum Velocity
Sewer should constructed with gradients which
produce Self Cleansing Velocities sufficient to carry
forward all solids and avoid settlements. A minimum
velocity of 0.6m/sec at design peak flow in the sewer
is recommended subject to a minimum velocity of
0.6m/sec for Present Peak Flows.The maximum
velocity to be permitted is of the order of 3m/sec
Manholes
Purpose of manholes
cleaning, inspection and maintenance of sewer line
Location of manholes
gradient change
pipe size change
bends
regular interval as per specification
Construction Material
• Manholes are generally constructed in circular shape. The manholes are in brick masonry
walls with plastered inside, RC concrete bottom and top slab with cover and finished with a
benching. Alternatively small size masonry manholes can be rectangular for easy
construction
• Where the water table is high and the pipe sewer is laid in open field or along the side of
the drain, the RCC circular manholes would be constructed to avoid any leakages into or out
the manholes. The RCC cast in situ or precast manholes will be used in the interceptor and
collector sewers as these are proposed to be laid along the bank of the river. RCC precast or
cast in situ manholes are recommended for large size sewers where space is sufficient for its
construction. If possible brick masonry manholes are planned for narrow streets where the
construction of RCC manholes is difficult and RCC cast in situ or precast manholes are
proposed for main roads or for heavy traffic roads. Precast manholes should be made
watertight by providing rubber gasket at the joints. Masonry manholes are limited to 2 m
depth for pipes of 200-450 mm.
Manhole Cover Levels
• The final level of manholes would be depending on site condition,
and therefore the final levels will be finalized during the execution
time. However, generally the following values may be considered;
• Paved areas cover level = final paved level.
• Landscaped areas cover level = final ground level +0.1m.
• Open, unpaved areas cover level = final ground level +0.25m or as
instructed by the Engineer during construction.
• Manhole covers with frame with a minimum clear opening of 600
mm
Manhole Size and Shape
Table 3-7: Recommended Manhole Size
Depth to Pipe Soffit from Cover
Level
Largest Pipe in Manhole Circular Diameter of Manhole Wall Thickness
Manhole Type
(m) (mm) (mm) (mm)
< 3 200-450 900 150 Type I RCC
3 - 6 200-450 1200 200 Type II RCC
< 5 500-1000 1500 200 Type III RCC
5 - 8 500-1000 1500 250 Type IV RCC
< 5 1200 1800 200 Type V RCC
5 - 8 1200 1800 250 Type VI RCC
< 5 1400-1600 2400 200 Type VII RCC
5 - 8 1400-1600 2400 250 Type VIII RCC
Thank you
Collection of Waste Water
• From place of origin to place of treatment or disposal(Sewerage
System)
• What are collected
• Domestic wastewater
• Industrial wastewater
• Infiltration/inflow
• Storm water
Types of Collection System
1)Sanitary wastewater system
2)Combined sanitary and storm water collection system
3)Storm water collection system
Choice of System
Combined System Separate system
Volume of water reaching WWTP High
Sewer size Large
Self cleansing velocity during dry period
LOW, so deposits of solid in the sewer
Initial investment HIGH
Low
Smaller size
Basis of design is the required self
cleansing velocity
Low
Combined Sewer
Water
Quality
Standards
for Various
uses
Design Criteria for KathmanduValley
The design flow of the interceptor and collector sewers are to be
adopted as follows.
Design flow of Interceptor/Collector sewer = DS x PF + NDS + IN
Design flow of Branch sewer and laterals = DS x PF + NDS + IN + SW
Where, DS = domestic sewage
• NDS = Non domestic sewage
• PF = Peak factor
• IN = Infiltration
• SW = Storm water
Steps in Sewer Design
• Survey and General Investigation
• Precise levels indicating the topography
• Subsoil investigation
• Location of treatment works
• Existing features of the town
• Type of land use
• Population and population density
• Discharge point of the water body with HFL
• One meter contour map
• Existing utilities to be mapped in the layout plan
• System Pattern of Sewerage Layout
• Interceptor pattern
• Zone pattern
• Fan Pattern
• Radial Pattern
• Design Period
Minimum 30 years
• Population
• Use census data
• Real count
• Make projection of future population
• Use population densities where there is possibility of growth in the future
Wastewater Generation
• Domestic Wastewater
• 100 lpcd up to the year 2020 and 120 lpcd in the year 2030
• 80% of the water consumption becoming sewage flow("Manual on Sewerage
and Sewage Treatment”, Ministry of Urban Development, November 2013)
Nondomestic Wastewater
wastewater generated from various industries
and commercial establishments
10% of domestic wastewater
Infiltration
infiltration value shall be limited to a maximum
of 10% of the design value of the sewage flow
Storm Water
Q = CIA
where, Q = storm water flow in m3/s; C = runoff
coefficient or impermeability factor;
I = intensity of rainfall in m/s; and
A=catchment area or drainage area in m2
Runoff Coefficient(C)
Land Use
Runoff
Coefficient
Land Use
Runoff
Coefficient
Lawns:
Sandy soil, flat, 2% 0.05 - 0.10
Business: Sandy soil, avg., 2-7% 0.10 - 0.15
Downtown area 0.70 - 0.95 Sandy soil, steep, 7% 0.15 - 0.20
Neighborhood area 0.50 - 0.70 Heavy soil, flat, 2% 0.13 - 0.17
Heavy soil, avg., 2-7% 0.18 - 0.22
Heavy soil, steep, 7% 0.25 - 0.35
Agricultural land:
Bare packed soil
Smooth 0.30 - 0.60
Rough 0.20 - 0.50
Residential (urban): Cultivated rows
Single family area 0.30 - 0.50 Heavy soil, no crop 0.30 - 0.60
Multi-units, detached 0.40 - 0.60 Heavy soil, with crop 0.20 - 0.50
Multi-units, attached 0.60 - 0.75 Sandy soil, no crop 0.20 - 0.40
Residential (suburban) 0.25 - 0.40 Sandy soil, with crop 0.10 - 0.25
Apartment areas 0.50 - 0.70 Pasture
Heavy soil 0.15 - 0.45
Sandy soil 0.05 - 0.25
Woodlands 0.05 - 0.25
Streets:
Industrial Asphaltic 0.70 - 0.95
Light areas 0.50 - 0.80 Concrete 0.80 - 0.95
Heavy areas 0.60 - 0.90 Brick 0.70 - 0.85
Parks, cemeteries 0.10 - 0.25 Unimproved areas 0.10 - 0.30
Playgrounds 0.20 - 0.35 Drives and walks 0.75 - 0.85
Railroad yards 0.20 - 0.40 Roofs 0.75 - 0.95
Coefficients
Rainfall Intensity
0
50
100
150
200
250
300
350
0 20 40 60 80 100 120 140 160 180
RainfalIntensity(mm/hr)
Time of Concentration (min)
Rainfall Intensity - Duration - Frequency Curves
Kathmandu Valley
2-year 5-year 10-year 25-year 50-year 100-year
Flow Velocity
• Self Cleaning Velocity
• The minimum velocity at which no solids get deposited in the invert of the
sewer is called self-cleaning velocity. For the design purposes the self-
cleaning velocity has considered as 0.6 m/sec (source: American Society of
Civil Engineers, ASCE).
• The minimum velocity to cause the scouring of the suspension of
solids heavier than the sewage or liquid which carry them is
determined by the following Shield formula:
V =
8k
f
ρs−ρ
ρ
g × d
Where, V = Velocity of flow
k = Characteristics of solids (0.04 -0.06)
• f = Darcy’s coefficient of friction, 0.03
Specific gravity of the solids particles in the
sewage. Its value is between 1.2 and 2.65.
• Specific gravity of the liquid = 1
• g = Acceleration due to gravity
• d = diameter of the particles.
• From the above formula, it is clear that heavier and sticky
solids require velocity for their cleaning.
=
Minimum Velocity
The minimum velocity of 0.6 and 0.8 m/s at the peak flow is
recommended for separate flow and combined/storm water sewer
respectively
Maximum Velocity
The maximum velocity of 3.0 m/sec has been recommended. Froude
number should be less than 1.0 so that supercritical flow is avoided at
the peak flow.
Design Formula
• Design practice is to use Manning’s Formula for open channel flow
and the Hazen Williams and Darcy-Weisbach formulae for closed
conduit or pressure flow (Source: Manual on Sewerage and Sewage
Treatment (Third Edition), Ministry of Urban Development, November
2013).
The manning's formula is given by the following equation.
V =
1
n
× R
2
3 × S
1
2
Q =
1
n
× A × R
2
3 × S
1
2
Where;
Q = discharge in m3/s
S = slope of hydraulic gradient
R = hydraulic radius in m
A = cross sectional area of flow
V= velocity in m/s
n = Manning’s coefficient of roughness
Roughness Coefficient
Manning roughness coefficients for concrete and HDPE pipes are
recommended as 0.013 and 0.009 respectively
Minimum Sewer Diameter
200 mm for collector, branch and lateral sewers 400 mm for
interceptor sewers
Ruling Gradient
CWWMP recommends a minimum sewer gradient of 1 in 200
Depth of Flow in Sewer
Sewers will be designed in such a way that the depth of flow in the
sewer at peak flow is not more than 0.8 times the diameter of the
sewer i.e. d/D ≤ 0.8
Pipe Features
Pipe Material and Joints
In principle all pipes to be used in the main sewer network are
proposed to be reinforced concrete cement RCC pipes with spigot and
socket ends, jointed through rubber gaskets. RCC pipes shall be
manufactured as per NS80/2042 and IS 458:2003 medium duty, non
pressure pipes. The jointing shall be Rubber Ring Joint (RRJ) type and
the rubber gasket to be provided shall be as per NS, NP3 or
exceptionally NP4 RCC (Hume) pipes for sewer lines as applicable.
Pipe Cover
The minimum cover above the crests of the sewer pipe is to be 1.0 m
Width of Trench
• For diameter up to 450mm, the bottom pipe width of trench shall be
OD+45cm
• For diameter above 450 mm, the bottom width of trench shall be
OD+60cm
• For house connection, the bottom width of trench shall be not less than
OD+30cm
Where OD = outside diameter of pipe
Bedding
Table 3-2: Categories of Bedding
Category
Description Abbreviation
Type 1 Granular bedding GRB
Type 2 Plain Cement Concrete M20 PCCB
Type 3 Reinforced Cement Concrete 0.4%
reinforcement M20
RCCB 0.4
Type 4 Reinforced Cement Concrete 1.0%
reinforcement M20
RCCB 1.0
Type 5
"Arch" bedding for PE pipes including the
combination of anti-flotation precast RCC
blocks every 3m and type 1 bedding in current
sections
ARCH / Type 1
Table 3.3
The proposed bedding type for various pipe materials at different
depths are specified in Table 3-3 and Table 3-4.
Pipe
NP3 -RRJ
Type 1 Type 2 Type 3 Type 4 Type 5
ND OD GRB PCCB RCCB 0.4 RCCB
1.0
ARCH
200 0.26 0-4m 5. m >5m
IfRequired
NotApplicable
250 0.31 0-4m 4-5m >5m
300 0.38 0-4m 4-5m >5m
350 0.50 0-4m 4-5m >5m
400 0.55 0-4m 4-5m >5m
450 0.60 0-4m 4-5m >5m
500 0.65 0-5m 5-6m >6m
600 0.77 0-5m 5-6m >6m
700 0.87 0-5m 5-6m >6m
800 0.99 0-5m 5-6m >6m
900 1.10 0-5m 5-6m >6m
1000 1.23
Not
Applicable
0-7m >7m
1200 1.44 0-7m >7m
1500 1.78 0-7m >7m
Depth Of Trench
Trench Depth = Ground Level – Invert Level + Pipe Thickness + H1
Where, H1 is related to thetype of bedding
H2 and H3 are related to the pipe diameter
H4 is related to the type of bedding
H5 depend of the bedding arrangements and the surface reinstatement
H6 is defined by the characteristics of the surface finishing
H2 + H3 is equal to the outside diameter of the pipe
The concrete cradle depth varies from 0 to H1+H2+H3+H4 depending on the type of bedding.
Density of Population
Size of
town,population
Density of population per
hectare
Upto 5,000
5,000-20,000
20,000-50,000
50,000-100,000
Above 100,000
75-150
150-250
250-300
300-350
350-1000
Carrying Capacity of Domestic Sewer
• Prospective population
• Drinking Water Supply quantity(consider 80% of the water supply per
day) multiplied by Peak Factor
Contributory
Population
Peak Factor
Up to 20,000
20,000-50,000
50,000-7,50,000
Above 7,50,000
3.5
2.5
2.25
2.0
Flow depth in sewer
• Due to ventilation in waste water flow, sewers are not designed to run
full
• Recommended Depth of Flow in Sewers
Size of Sewer Depth of Flow
Upto 400 mm dia
400mm-900mm dia
Larger than 900mmdia
½ depth
2/3 depth
¾ depth
Minimum Size of Sewer
Minimum size of public sewer shall be 150mm dia but
in practice 200mm dia is recommended
Minimum And Maximum Velocity
Sewer should constructed with gradients which
produce Self Cleansing Velocities sufficient to carry
forward all solids and avoid settlements. A minimum
velocity of 0.6m/sec at design peak flow in the sewer
is recommended subject to a minimum velocity of
0.6m/sec for Present Peak Flows.The maximum
velocity to be permitted is of the order of 3m/sec
Manholes
Purpose of manholes
cleaning, inspection and maintenance of sewer line
Location of manholes
gradient change
pipe size change
bends
regular interval as per specification
Construction Material
• Manholes are generally constructed in circular shape. The manholes are in brick masonry
walls with plastered inside, RC concrete bottom and top slab with cover and finished
with a benching. Alternatively small size masonry manholes can be rectangular for easy
construction
• Where the water table is high and the pipe sewer is laid in open field or along the side of
the drain, the RCC circular manholes would be constructed to avoid any leakages into or
out the manholes. The RCC cast in situ or precast manholes will be used in the
interceptor and collector sewers as these are proposed to be laid along the bank of the
river. RCC precast or cast in situ manholes are recommended for large size sewers where
space is sufficient for its construction. If possible brick masonry manholes are planned
for narrow streets where the construction of RCC manholes is difficult and RCC cast in
situ or precast manholes are proposed for main roads or for heavy traffic roads. Precast
manholes should be made watertight by providing rubber gasket at the joints. Masonry
manholes are limited to 2 m depth for pipes of 200-450 mm.
Manhole Cover Levels
• The final level of manholes would be depending on site condition,
and therefore the final levels will be finalized during the execution
time. However, generally the following values may be considered;
• Paved areas cover level = final paved level.
• Landscaped areas cover level = final ground level +0.1m.
• Open, unpaved areas cover level = final ground level +0.25m or as
instructed by the Engineer during construction.
• Manhole covers with frame with a minimum clear opening of 600 mm
Manhole Size and Shape
Table 3-7: Recommended Manhole Size
Depth to Pipe Soffit from Cover
Level
Largest Pipe in Manhole Circular Diameter of Manhole Wall Thickness
Manhole Type
(m) (mm) (mm) (mm)
< 3 200-450 900 150 Type I RCC
3 - 6 200-450 1200 200 Type II RCC
< 5 500-1000 1500 200 Type III RCC
5 - 8 500-1000 1500 250 Type IV RCC
< 5 1200 1800 200 Type V RCC
5 - 8 1200 1800 250 Type VI RCC
< 5 1400-1600 2400 200 Type VII RCC
5 - 8 1400-1600 2400 250 Type VIII RCC
Thank you

More Related Content

What's hot

Collection and estimation of sewage
Collection and estimation of sewageCollection and estimation of sewage
Collection and estimation of sewageBibhabasu Mohanty
 
Design of sewerage system
Design of sewerage systemDesign of sewerage system
Design of sewerage systemManoj Mota
 
Design of sewerage collection system and cost estimation
Design of sewerage collection system and cost estimationDesign of sewerage collection system and cost estimation
Design of sewerage collection system and cost estimationVijay Kumar
 
Water demand/Waterrequirements
Water demand/Waterrequirements Water demand/Waterrequirements
Water demand/Waterrequirements dhavalsshah
 
Water distribution network design and analysis
Water distribution network design and analysisWater distribution network design and analysis
Water distribution network design and analysisAna Debbarma
 
water supply Project theory
water supply Project theorywater supply Project theory
water supply Project theoryMadhav Parajuli
 
Collection of sewage & estimation of its discharge
Collection of sewage & estimation of its dischargeCollection of sewage & estimation of its discharge
Collection of sewage & estimation of its dischargeRajdip Bhdaraka
 
sewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenancesewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenanceManish Goyal
 
Design and construction of sewer
Design and construction of sewer Design and construction of sewer
Design and construction of sewer SitalParajuli
 
Estimating sewage discharge and peak drainage discharge
Estimating sewage discharge and peak drainage dischargeEstimating sewage discharge and peak drainage discharge
Estimating sewage discharge and peak drainage dischargeAnkit Gola
 
Water and Waste Water Engineering
Water and Waste Water EngineeringWater and Waste Water Engineering
Water and Waste Water EngineeringAditya Mistry
 
Water Supply and Sewerage Design
Water Supply and Sewerage DesignWater Supply and Sewerage Design
Water Supply and Sewerage DesignJeremy Molayem
 

What's hot (20)

Collection and estimation of sewage
Collection and estimation of sewageCollection and estimation of sewage
Collection and estimation of sewage
 
Design of sewerage system
Design of sewerage systemDesign of sewerage system
Design of sewerage system
 
Design of sewerage collection system and cost estimation
Design of sewerage collection system and cost estimationDesign of sewerage collection system and cost estimation
Design of sewerage collection system and cost estimation
 
Water resource engineering project list
Water resource engineering project listWater resource engineering project list
Water resource engineering project list
 
Water demand/Waterrequirements
Water demand/Waterrequirements Water demand/Waterrequirements
Water demand/Waterrequirements
 
Water distribution network design and analysis
Water distribution network design and analysisWater distribution network design and analysis
Water distribution network design and analysis
 
water supply Project theory
water supply Project theorywater supply Project theory
water supply Project theory
 
Collection of sewage & estimation of its discharge
Collection of sewage & estimation of its dischargeCollection of sewage & estimation of its discharge
Collection of sewage & estimation of its discharge
 
sewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenancesewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenance
 
Water demand
Water demandWater demand
Water demand
 
Design and construction of sewer
Design and construction of sewer Design and construction of sewer
Design and construction of sewer
 
Hydraulics of water Distribution System
 Hydraulics of water Distribution System Hydraulics of water Distribution System
Hydraulics of water Distribution System
 
Low Cost Sanitation Systems
Low Cost Sanitation SystemsLow Cost Sanitation Systems
Low Cost Sanitation Systems
 
Estimating sewage discharge and peak drainage discharge
Estimating sewage discharge and peak drainage dischargeEstimating sewage discharge and peak drainage discharge
Estimating sewage discharge and peak drainage discharge
 
Water and Waste Water Engineering
Water and Waste Water EngineeringWater and Waste Water Engineering
Water and Waste Water Engineering
 
02 water demand
02 water demand02 water demand
02 water demand
 
L 4 wastewater flow rates
L 4 wastewater flow ratesL 4 wastewater flow rates
L 4 wastewater flow rates
 
Hydraulicdesignofsewer
HydraulicdesignofsewerHydraulicdesignofsewer
Hydraulicdesignofsewer
 
Water Supply and Sewerage Design
Water Supply and Sewerage DesignWater Supply and Sewerage Design
Water Supply and Sewerage Design
 
Water resource engineering project list 2
Water resource engineering project list 2Water resource engineering project list 2
Water resource engineering project list 2
 

Similar to Sewer Design

L6 - DESIGN OF SEWERGAE SYSTEMS.pptx
L6 - DESIGN OF SEWERGAE SYSTEMS.pptxL6 - DESIGN OF SEWERGAE SYSTEMS.pptx
L6 - DESIGN OF SEWERGAE SYSTEMS.pptxPRACHI DESSAI
 
Sewage treatment plant design calculation
Sewage treatment plant design calculationSewage treatment plant design calculation
Sewage treatment plant design calculationSharifah Ain
 
5-Runoff computation (2).ppt
5-Runoff computation (2).ppt5-Runoff computation (2).ppt
5-Runoff computation (2).pptJohnAyele
 
Collection of sewage &amp; estimation of its discharge
Collection of sewage &amp; estimation of its dischargeCollection of sewage &amp; estimation of its discharge
Collection of sewage &amp; estimation of its dischargeRajdip Bhdaraka
 
Water supply chapter 6 (Water Treatment)
Water supply chapter 6 (Water Treatment)Water supply chapter 6 (Water Treatment)
Water supply chapter 6 (Water Treatment)Safal Poudel
 
Anexo sobre-riego-por-aspersion
Anexo sobre-riego-por-aspersionAnexo sobre-riego-por-aspersion
Anexo sobre-riego-por-aspersionmartinatorafer
 
Hydraulic Design of Sprinkler System,
Hydraulic Design of Sprinkler System, Hydraulic Design of Sprinkler System,
Hydraulic Design of Sprinkler System, Suyog Khose
 
LARGE SCALE INSTALLATION OF SUBSURFACE DRAINAGE SYSTEM
LARGE SCALE INSTALLATION OF SUBSURFACE DRAINAGE SYSTEM LARGE SCALE INSTALLATION OF SUBSURFACE DRAINAGE SYSTEM
LARGE SCALE INSTALLATION OF SUBSURFACE DRAINAGE SYSTEM Tushar Dholakia
 
Estimation of storm sewage
Estimation of storm sewageEstimation of storm sewage
Estimation of storm sewagesidrarashiddar
 
Planning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptxPlanning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptxssuser0a41e6
 
Planning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptxPlanning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptxMathewHany1
 
Treatment of wastewater
Treatment of wastewaterTreatment of wastewater
Treatment of wastewaterArpit Budania
 
Report work on retaining wall
Report work on retaining wallReport work on retaining wall
Report work on retaining wallvikas Meena
 
Technical design-of-rwh (2)
Technical design-of-rwh (2)Technical design-of-rwh (2)
Technical design-of-rwh (2)ABood Al-ghamdy
 
Lectre 1- Real INTRO and SEWER DESIGFN.pptx
Lectre 1- Real INTRO and SEWER DESIGFN.pptxLectre 1- Real INTRO and SEWER DESIGFN.pptx
Lectre 1- Real INTRO and SEWER DESIGFN.pptxAsnelTiffa
 

Similar to Sewer Design (20)

Sewerage design
Sewerage designSewerage design
Sewerage design
 
Sewerage System
Sewerage SystemSewerage System
Sewerage System
 
L6 - DESIGN OF SEWERGAE SYSTEMS.pptx
L6 - DESIGN OF SEWERGAE SYSTEMS.pptxL6 - DESIGN OF SEWERGAE SYSTEMS.pptx
L6 - DESIGN OF SEWERGAE SYSTEMS.pptx
 
Sewage treatment plant design calculation
Sewage treatment plant design calculationSewage treatment plant design calculation
Sewage treatment plant design calculation
 
5-Runoff computation (2).ppt
5-Runoff computation (2).ppt5-Runoff computation (2).ppt
5-Runoff computation (2).ppt
 
Collection of sewage &amp; estimation of its discharge
Collection of sewage &amp; estimation of its dischargeCollection of sewage &amp; estimation of its discharge
Collection of sewage &amp; estimation of its discharge
 
Ch2.ppt
Ch2.pptCh2.ppt
Ch2.ppt
 
Water supply chapter 6 (Water Treatment)
Water supply chapter 6 (Water Treatment)Water supply chapter 6 (Water Treatment)
Water supply chapter 6 (Water Treatment)
 
Anexo sobre-riego-por-aspersion
Anexo sobre-riego-por-aspersionAnexo sobre-riego-por-aspersion
Anexo sobre-riego-por-aspersion
 
WATERSHED CATCHMENT.pptx
WATERSHED CATCHMENT.pptxWATERSHED CATCHMENT.pptx
WATERSHED CATCHMENT.pptx
 
Hydraulic Design of Sprinkler System,
Hydraulic Design of Sprinkler System, Hydraulic Design of Sprinkler System,
Hydraulic Design of Sprinkler System,
 
LARGE SCALE INSTALLATION OF SUBSURFACE DRAINAGE SYSTEM
LARGE SCALE INSTALLATION OF SUBSURFACE DRAINAGE SYSTEM LARGE SCALE INSTALLATION OF SUBSURFACE DRAINAGE SYSTEM
LARGE SCALE INSTALLATION OF SUBSURFACE DRAINAGE SYSTEM
 
designing simple drainage system.pptx
designing simple drainage system.pptxdesigning simple drainage system.pptx
designing simple drainage system.pptx
 
Estimation of storm sewage
Estimation of storm sewageEstimation of storm sewage
Estimation of storm sewage
 
Planning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptxPlanning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptx
 
Planning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptxPlanning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptx
 
Treatment of wastewater
Treatment of wastewaterTreatment of wastewater
Treatment of wastewater
 
Report work on retaining wall
Report work on retaining wallReport work on retaining wall
Report work on retaining wall
 
Technical design-of-rwh (2)
Technical design-of-rwh (2)Technical design-of-rwh (2)
Technical design-of-rwh (2)
 
Lectre 1- Real INTRO and SEWER DESIGFN.pptx
Lectre 1- Real INTRO and SEWER DESIGFN.pptxLectre 1- Real INTRO and SEWER DESIGFN.pptx
Lectre 1- Real INTRO and SEWER DESIGFN.pptx
 

Recently uploaded

Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 

Recently uploaded (20)

Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 

Sewer Design

  • 2. Collection of Waste Water • From place of origin to place of treatment or disposal(Sewerage System) • What are collected – Domestic wastewater – Industrial wastewater – Infiltration/inflow – Storm water
  • 3. Types of Collection System 1)Sanitary wastewater system 2)Combined sanitary and storm water collection system 3)Storm water collection system
  • 4. Choice of System Combined System Separate system Volume of water reaching WWTP High Sewer size Large Self cleansing velocity during dry period LOW, so deposits of solid in the sewer Initial investment HIGH Low Smaller size Basis of design is the required self cleansing velocity Low
  • 5.
  • 8. Design Criteria for KathmanduValley The design flow of the interceptor and collector sewers are to be adopted as follows. Design flow of Interceptor/Collector sewer = DS x PF + NDS + IN Design flow of Branch sewer and laterals = DS x PF + NDS + IN + SW Where, DS = domestic sewage • NDS = Non domestic sewage • PF = Peak factor • IN = Infiltration • SW = Storm water
  • 9.
  • 10.
  • 11. Steps in Sewer Design • Survey and General Investigation – Precise levels indicating the topography – Subsoil investigation – Location of treatment works – Existing features of the town – Type of land use – Population and population density – Discharge point of the water body with HFL
  • 12. – One meter contour map – Existing utilities to be mapped in the layout plan
  • 13. • System Pattern of Sewerage Layout – Interceptor pattern – Zone pattern – Fan Pattern – Radial Pattern • Design Period Minimum 30 years
  • 14. • Population – Use census data – Real count – Make projection of future population – Use population densities where there is possibility of growth in the future
  • 15. Wastewater Generation • Domestic Wastewater – 100 lpcd up to the year 2020 and 120 lpcd in the year 2030 – 80% of the water consumption becoming sewage flow("Manual on Sewerage and Sewage Treatment”, Ministry of Urban Development, November 2013)
  • 16. Nondomestic Wastewater wastewater generated from various industries and commercial establishments 10% of domestic wastewater Infiltration infiltration value shall be limited to a maximum of 10% of the design value of the sewage flow
  • 17. Storm Water Q = CIA where, Q = storm water flow in m3/s; C = runoff coefficient or impermeability factor; I = intensity of rainfall in m/s; and A=catchment area or drainage area in m2
  • 18. Runoff Coefficient(C) Land Use Runoff Coefficient Land Use Runoff Coefficient Lawns: Sandy soil, flat, 2% 0.05 - 0.10 Business: Sandy soil, avg., 2-7% 0.10 - 0.15 Downtown area 0.70 - 0.95 Sandy soil, steep, 7% 0.15 - 0.20 Neighborhood area 0.50 - 0.70 Heavy soil, flat, 2% 0.13 - 0.17 Heavy soil, avg., 2-7% 0.18 - 0.22 Heavy soil, steep, 7% 0.25 - 0.35 Agricultural land: Bare packed soil Smooth 0.30 - 0.60 Rough 0.20 - 0.50 Residential (urban): Cultivated rows Single family area 0.30 - 0.50 Heavy soil, no crop 0.30 - 0.60 Multi-units, detached 0.40 - 0.60 Heavy soil, with crop 0.20 - 0.50 Multi-units, attached 0.60 - 0.75 Sandy soil, no crop 0.20 - 0.40 Residential (suburban) 0.25 - 0.40 Sandy soil, with crop 0.10 - 0.25 Apartment areas 0.50 - 0.70 Pasture Heavy soil 0.15 - 0.45 Sandy soil 0.05 - 0.25 Woodlands 0.05 - 0.25 Streets: Industrial Asphaltic 0.70 - 0.95 Light areas 0.50 - 0.80 Concrete 0.80 - 0.95 Heavy areas 0.60 - 0.90 Brick 0.70 - 0.85 Parks, cemeteries 0.10 - 0.25 Unimproved areas 0.10 - 0.30 Playgrounds 0.20 - 0.35 Drives and walks 0.75 - 0.85 Railroad yards 0.20 - 0.40 Roofs 0.75 - 0.95 Coefficients
  • 19. Rainfall Intensity 0 50 100 150 200 250 300 350 0 20 40 60 80 100 120 140 160 180 RainfalIntensity(mm/hr) Time of Concentration (min) Rainfall Intensity - Duration - Frequency Curves Kathmandu Valley 2-year 5-year 10-year 25-year 50-year 100-year
  • 20. Flow Velocity • Self Cleaning Velocity – The minimum velocity at which no solids get deposited in the invert of the sewer is called self-cleaning velocity. For the design purposes the self- cleaning velocity has considered as 0.6 m/sec (source: American Society of Civil Engineers, ASCE).
  • 21. • The minimum velocity to cause the scouring of the suspension of solids heavier than the sewage or liquid which carry them is determined by the following Shield formula: V = 8k f ρs−ρ ρ g × d
  • 22. Where, V = Velocity of flow k = Characteristics of solids (0.04 -0.06) • f = Darcy’s coefficient of friction, 0.03 Specific gravity of the solids particles in the sewage. Its value is between 1.2 and 2.65. • Specific gravity of the liquid = 1 • g = Acceleration due to gravity • d = diameter of the particles. • From the above formula, it is clear that heavier and sticky solids require velocity for their cleaning. =
  • 23. Minimum Velocity The minimum velocity of 0.6 and 0.8 m/s at the peak flow is recommended for separate flow and combined/storm water sewer respectively Maximum Velocity The maximum velocity of 3.0 m/sec has been recommended. Froude number should be less than 1.0 so that supercritical flow is avoided at the peak flow.
  • 24. Design Formula • Design practice is to use Manning’s Formula for open channel flow and the Hazen Williams and Darcy-Weisbach formulae for closed conduit or pressure flow (Source: Manual on Sewerage and Sewage Treatment (Third Edition), Ministry of Urban Development, November 2013).
  • 25. The manning's formula is given by the following equation. V = 1 n × R 2 3 × S 1 2 Q = 1 n × A × R 2 3 × S 1 2 Where; Q = discharge in m3/s S = slope of hydraulic gradient R = hydraulic radius in m A = cross sectional area of flow V= velocity in m/s n = Manning’s coefficient of roughness
  • 26. Roughness Coefficient Manning roughness coefficients for concrete and HDPE pipes are recommended as 0.013 and 0.009 respectively Minimum Sewer Diameter 200 mm for collector, branch and lateral sewers 400 mm for interceptor sewers
  • 27. Ruling Gradient CWWMP recommends a minimum sewer gradient of 1 in 200 Depth of Flow in Sewer Sewers will be designed in such a way that the depth of flow in the sewer at peak flow is not more than 0.8 times the diameter of the sewer i.e. d/D ≤ 0.8
  • 28. Pipe Features Pipe Material and Joints In principle all pipes to be used in the main sewer network are proposed to be reinforced concrete cement RCC pipes with spigot and socket ends, jointed through rubber gaskets. RCC pipes shall be manufactured as per NS80/2042 and IS 458:2003 medium duty, non pressure pipes. The jointing shall be Rubber Ring Joint (RRJ) type and the rubber gasket to be provided shall be as per NS, NP3 or exceptionally NP4 RCC (Hume) pipes for sewer lines as applicable.
  • 29. Pipe Cover The minimum cover above the crests of the sewer pipe is to be 1.0 m Width of Trench • For diameter up to 450mm, the bottom pipe width of trench shall be OD+45cm • For diameter above 450 mm, the bottom width of trench shall be OD+60cm • For house connection, the bottom width of trench shall be not less than OD+30cm Where OD = outside diameter of pipe
  • 30. Bedding Table 3-2: Categories of Bedding Category Description Abbreviation Type 1 Granular bedding GRB Type 2 Plain Cement Concrete M20 PCCB Type 3 Reinforced Cement Concrete 0.4% reinforcement M20 RCCB 0.4 Type 4 Reinforced Cement Concrete 1.0% reinforcement M20 RCCB 1.0 Type 5 "Arch" bedding for PE pipes including the combination of anti-flotation precast RCC blocks every 3m and type 1 bedding in current sections ARCH / Type 1
  • 31. Table 3.3 The proposed bedding type for various pipe materials at different depths are specified in Table 3-3 and Table 3-4. Pipe NP3 -RRJ Type 1 Type 2 Type 3 Type 4 Type 5 ND OD GRB PCCB RCCB 0.4 RCCB 1.0 ARCH 200 0.26 0-4m 5. m >5m IfRequired NotApplicable 250 0.31 0-4m 4-5m >5m 300 0.38 0-4m 4-5m >5m 350 0.50 0-4m 4-5m >5m 400 0.55 0-4m 4-5m >5m 450 0.60 0-4m 4-5m >5m 500 0.65 0-5m 5-6m >6m 600 0.77 0-5m 5-6m >6m 700 0.87 0-5m 5-6m >6m 800 0.99 0-5m 5-6m >6m 900 1.10 0-5m 5-6m >6m 1000 1.23 Not Applicable 0-7m >7m 1200 1.44 0-7m >7m 1500 1.78 0-7m >7m
  • 32. Depth Of Trench Trench Depth = Ground Level – Invert Level + Pipe Thickness + H1 Where, H1 is related to thetype of bedding H2 and H3 are related to the pipe diameter H4 is related to the type of bedding H5 depend of the bedding arrangements and the surface reinstatement H6 is defined by the characteristics of the surface finishing H2 + H3 is equal to the outside diameter of the pipe The concrete cradle depth varies from 0 to H1+H2+H3+H4 depending on the type of bedding.
  • 33.
  • 34. Density of Population Size of town,population Density of population per hectare Upto 5,000 5,000-20,000 20,000-50,000 50,000-100,000 Above 100,000 75-150 150-250 250-300 300-350 350-1000
  • 35. Carrying Capacity of Domestic Sewer • Prospective population • Drinking Water Supply quantity(consider 80% of the water supply per day) multiplied by Peak Factor Contributory Population Peak Factor Up to 20,000 20,000-50,000 50,000-7,50,000 Above 7,50,000 3.5 2.5 2.25 2.0
  • 36. Flow depth in sewer • Due to ventilation in waste water flow, sewers are not designed to run full • Recommended Depth of Flow in Sewers Size of Sewer Depth of Flow Upto 400 mm dia 400mm-900mm dia Larger than 900mmdia ½ depth 2/3 depth ¾ depth
  • 37.
  • 38. Minimum Size of Sewer Minimum size of public sewer shall be 150mm dia but in practice 200mm dia is recommended Minimum And Maximum Velocity Sewer should constructed with gradients which produce Self Cleansing Velocities sufficient to carry forward all solids and avoid settlements. A minimum velocity of 0.6m/sec at design peak flow in the sewer is recommended subject to a minimum velocity of 0.6m/sec for Present Peak Flows.The maximum velocity to be permitted is of the order of 3m/sec
  • 39. Manholes Purpose of manholes cleaning, inspection and maintenance of sewer line Location of manholes gradient change pipe size change bends regular interval as per specification
  • 40. Construction Material • Manholes are generally constructed in circular shape. The manholes are in brick masonry walls with plastered inside, RC concrete bottom and top slab with cover and finished with a benching. Alternatively small size masonry manholes can be rectangular for easy construction • Where the water table is high and the pipe sewer is laid in open field or along the side of the drain, the RCC circular manholes would be constructed to avoid any leakages into or out the manholes. The RCC cast in situ or precast manholes will be used in the interceptor and collector sewers as these are proposed to be laid along the bank of the river. RCC precast or cast in situ manholes are recommended for large size sewers where space is sufficient for its construction. If possible brick masonry manholes are planned for narrow streets where the construction of RCC manholes is difficult and RCC cast in situ or precast manholes are proposed for main roads or for heavy traffic roads. Precast manholes should be made watertight by providing rubber gasket at the joints. Masonry manholes are limited to 2 m depth for pipes of 200-450 mm.
  • 41. Manhole Cover Levels • The final level of manholes would be depending on site condition, and therefore the final levels will be finalized during the execution time. However, generally the following values may be considered; • Paved areas cover level = final paved level. • Landscaped areas cover level = final ground level +0.1m. • Open, unpaved areas cover level = final ground level +0.25m or as instructed by the Engineer during construction. • Manhole covers with frame with a minimum clear opening of 600 mm
  • 42. Manhole Size and Shape Table 3-7: Recommended Manhole Size Depth to Pipe Soffit from Cover Level Largest Pipe in Manhole Circular Diameter of Manhole Wall Thickness Manhole Type (m) (mm) (mm) (mm) < 3 200-450 900 150 Type I RCC 3 - 6 200-450 1200 200 Type II RCC < 5 500-1000 1500 200 Type III RCC 5 - 8 500-1000 1500 250 Type IV RCC < 5 1200 1800 200 Type V RCC 5 - 8 1200 1800 250 Type VI RCC < 5 1400-1600 2400 200 Type VII RCC 5 - 8 1400-1600 2400 250 Type VIII RCC
  • 44. Collection of Waste Water • From place of origin to place of treatment or disposal(Sewerage System) • What are collected • Domestic wastewater • Industrial wastewater • Infiltration/inflow • Storm water
  • 45. Types of Collection System 1)Sanitary wastewater system 2)Combined sanitary and storm water collection system 3)Storm water collection system
  • 46. Choice of System Combined System Separate system Volume of water reaching WWTP High Sewer size Large Self cleansing velocity during dry period LOW, so deposits of solid in the sewer Initial investment HIGH Low Smaller size Basis of design is the required self cleansing velocity Low
  • 47.
  • 50. Design Criteria for KathmanduValley The design flow of the interceptor and collector sewers are to be adopted as follows. Design flow of Interceptor/Collector sewer = DS x PF + NDS + IN Design flow of Branch sewer and laterals = DS x PF + NDS + IN + SW Where, DS = domestic sewage • NDS = Non domestic sewage • PF = Peak factor • IN = Infiltration • SW = Storm water
  • 51.
  • 52.
  • 53. Steps in Sewer Design • Survey and General Investigation • Precise levels indicating the topography • Subsoil investigation • Location of treatment works • Existing features of the town • Type of land use • Population and population density • Discharge point of the water body with HFL
  • 54. • One meter contour map • Existing utilities to be mapped in the layout plan
  • 55. • System Pattern of Sewerage Layout • Interceptor pattern • Zone pattern • Fan Pattern • Radial Pattern • Design Period Minimum 30 years
  • 56. • Population • Use census data • Real count • Make projection of future population • Use population densities where there is possibility of growth in the future
  • 57. Wastewater Generation • Domestic Wastewater • 100 lpcd up to the year 2020 and 120 lpcd in the year 2030 • 80% of the water consumption becoming sewage flow("Manual on Sewerage and Sewage Treatment”, Ministry of Urban Development, November 2013)
  • 58. Nondomestic Wastewater wastewater generated from various industries and commercial establishments 10% of domestic wastewater Infiltration infiltration value shall be limited to a maximum of 10% of the design value of the sewage flow
  • 59. Storm Water Q = CIA where, Q = storm water flow in m3/s; C = runoff coefficient or impermeability factor; I = intensity of rainfall in m/s; and A=catchment area or drainage area in m2
  • 60. Runoff Coefficient(C) Land Use Runoff Coefficient Land Use Runoff Coefficient Lawns: Sandy soil, flat, 2% 0.05 - 0.10 Business: Sandy soil, avg., 2-7% 0.10 - 0.15 Downtown area 0.70 - 0.95 Sandy soil, steep, 7% 0.15 - 0.20 Neighborhood area 0.50 - 0.70 Heavy soil, flat, 2% 0.13 - 0.17 Heavy soil, avg., 2-7% 0.18 - 0.22 Heavy soil, steep, 7% 0.25 - 0.35 Agricultural land: Bare packed soil Smooth 0.30 - 0.60 Rough 0.20 - 0.50 Residential (urban): Cultivated rows Single family area 0.30 - 0.50 Heavy soil, no crop 0.30 - 0.60 Multi-units, detached 0.40 - 0.60 Heavy soil, with crop 0.20 - 0.50 Multi-units, attached 0.60 - 0.75 Sandy soil, no crop 0.20 - 0.40 Residential (suburban) 0.25 - 0.40 Sandy soil, with crop 0.10 - 0.25 Apartment areas 0.50 - 0.70 Pasture Heavy soil 0.15 - 0.45 Sandy soil 0.05 - 0.25 Woodlands 0.05 - 0.25 Streets: Industrial Asphaltic 0.70 - 0.95 Light areas 0.50 - 0.80 Concrete 0.80 - 0.95 Heavy areas 0.60 - 0.90 Brick 0.70 - 0.85 Parks, cemeteries 0.10 - 0.25 Unimproved areas 0.10 - 0.30 Playgrounds 0.20 - 0.35 Drives and walks 0.75 - 0.85 Railroad yards 0.20 - 0.40 Roofs 0.75 - 0.95 Coefficients
  • 61. Rainfall Intensity 0 50 100 150 200 250 300 350 0 20 40 60 80 100 120 140 160 180 RainfalIntensity(mm/hr) Time of Concentration (min) Rainfall Intensity - Duration - Frequency Curves Kathmandu Valley 2-year 5-year 10-year 25-year 50-year 100-year
  • 62. Flow Velocity • Self Cleaning Velocity • The minimum velocity at which no solids get deposited in the invert of the sewer is called self-cleaning velocity. For the design purposes the self- cleaning velocity has considered as 0.6 m/sec (source: American Society of Civil Engineers, ASCE).
  • 63. • The minimum velocity to cause the scouring of the suspension of solids heavier than the sewage or liquid which carry them is determined by the following Shield formula: V = 8k f ρs−ρ ρ g × d
  • 64. Where, V = Velocity of flow k = Characteristics of solids (0.04 -0.06) • f = Darcy’s coefficient of friction, 0.03 Specific gravity of the solids particles in the sewage. Its value is between 1.2 and 2.65. • Specific gravity of the liquid = 1 • g = Acceleration due to gravity • d = diameter of the particles. • From the above formula, it is clear that heavier and sticky solids require velocity for their cleaning. =
  • 65. Minimum Velocity The minimum velocity of 0.6 and 0.8 m/s at the peak flow is recommended for separate flow and combined/storm water sewer respectively Maximum Velocity The maximum velocity of 3.0 m/sec has been recommended. Froude number should be less than 1.0 so that supercritical flow is avoided at the peak flow.
  • 66. Design Formula • Design practice is to use Manning’s Formula for open channel flow and the Hazen Williams and Darcy-Weisbach formulae for closed conduit or pressure flow (Source: Manual on Sewerage and Sewage Treatment (Third Edition), Ministry of Urban Development, November 2013).
  • 67. The manning's formula is given by the following equation. V = 1 n × R 2 3 × S 1 2 Q = 1 n × A × R 2 3 × S 1 2 Where; Q = discharge in m3/s S = slope of hydraulic gradient R = hydraulic radius in m A = cross sectional area of flow V= velocity in m/s n = Manning’s coefficient of roughness
  • 68. Roughness Coefficient Manning roughness coefficients for concrete and HDPE pipes are recommended as 0.013 and 0.009 respectively Minimum Sewer Diameter 200 mm for collector, branch and lateral sewers 400 mm for interceptor sewers
  • 69. Ruling Gradient CWWMP recommends a minimum sewer gradient of 1 in 200 Depth of Flow in Sewer Sewers will be designed in such a way that the depth of flow in the sewer at peak flow is not more than 0.8 times the diameter of the sewer i.e. d/D ≤ 0.8
  • 70. Pipe Features Pipe Material and Joints In principle all pipes to be used in the main sewer network are proposed to be reinforced concrete cement RCC pipes with spigot and socket ends, jointed through rubber gaskets. RCC pipes shall be manufactured as per NS80/2042 and IS 458:2003 medium duty, non pressure pipes. The jointing shall be Rubber Ring Joint (RRJ) type and the rubber gasket to be provided shall be as per NS, NP3 or exceptionally NP4 RCC (Hume) pipes for sewer lines as applicable.
  • 71. Pipe Cover The minimum cover above the crests of the sewer pipe is to be 1.0 m Width of Trench • For diameter up to 450mm, the bottom pipe width of trench shall be OD+45cm • For diameter above 450 mm, the bottom width of trench shall be OD+60cm • For house connection, the bottom width of trench shall be not less than OD+30cm Where OD = outside diameter of pipe
  • 72. Bedding Table 3-2: Categories of Bedding Category Description Abbreviation Type 1 Granular bedding GRB Type 2 Plain Cement Concrete M20 PCCB Type 3 Reinforced Cement Concrete 0.4% reinforcement M20 RCCB 0.4 Type 4 Reinforced Cement Concrete 1.0% reinforcement M20 RCCB 1.0 Type 5 "Arch" bedding for PE pipes including the combination of anti-flotation precast RCC blocks every 3m and type 1 bedding in current sections ARCH / Type 1
  • 73. Table 3.3 The proposed bedding type for various pipe materials at different depths are specified in Table 3-3 and Table 3-4. Pipe NP3 -RRJ Type 1 Type 2 Type 3 Type 4 Type 5 ND OD GRB PCCB RCCB 0.4 RCCB 1.0 ARCH 200 0.26 0-4m 5. m >5m IfRequired NotApplicable 250 0.31 0-4m 4-5m >5m 300 0.38 0-4m 4-5m >5m 350 0.50 0-4m 4-5m >5m 400 0.55 0-4m 4-5m >5m 450 0.60 0-4m 4-5m >5m 500 0.65 0-5m 5-6m >6m 600 0.77 0-5m 5-6m >6m 700 0.87 0-5m 5-6m >6m 800 0.99 0-5m 5-6m >6m 900 1.10 0-5m 5-6m >6m 1000 1.23 Not Applicable 0-7m >7m 1200 1.44 0-7m >7m 1500 1.78 0-7m >7m
  • 74. Depth Of Trench Trench Depth = Ground Level – Invert Level + Pipe Thickness + H1 Where, H1 is related to thetype of bedding H2 and H3 are related to the pipe diameter H4 is related to the type of bedding H5 depend of the bedding arrangements and the surface reinstatement H6 is defined by the characteristics of the surface finishing H2 + H3 is equal to the outside diameter of the pipe The concrete cradle depth varies from 0 to H1+H2+H3+H4 depending on the type of bedding.
  • 75.
  • 76. Density of Population Size of town,population Density of population per hectare Upto 5,000 5,000-20,000 20,000-50,000 50,000-100,000 Above 100,000 75-150 150-250 250-300 300-350 350-1000
  • 77. Carrying Capacity of Domestic Sewer • Prospective population • Drinking Water Supply quantity(consider 80% of the water supply per day) multiplied by Peak Factor Contributory Population Peak Factor Up to 20,000 20,000-50,000 50,000-7,50,000 Above 7,50,000 3.5 2.5 2.25 2.0
  • 78. Flow depth in sewer • Due to ventilation in waste water flow, sewers are not designed to run full • Recommended Depth of Flow in Sewers Size of Sewer Depth of Flow Upto 400 mm dia 400mm-900mm dia Larger than 900mmdia ½ depth 2/3 depth ¾ depth
  • 79.
  • 80. Minimum Size of Sewer Minimum size of public sewer shall be 150mm dia but in practice 200mm dia is recommended Minimum And Maximum Velocity Sewer should constructed with gradients which produce Self Cleansing Velocities sufficient to carry forward all solids and avoid settlements. A minimum velocity of 0.6m/sec at design peak flow in the sewer is recommended subject to a minimum velocity of 0.6m/sec for Present Peak Flows.The maximum velocity to be permitted is of the order of 3m/sec
  • 81. Manholes Purpose of manholes cleaning, inspection and maintenance of sewer line Location of manholes gradient change pipe size change bends regular interval as per specification
  • 82. Construction Material • Manholes are generally constructed in circular shape. The manholes are in brick masonry walls with plastered inside, RC concrete bottom and top slab with cover and finished with a benching. Alternatively small size masonry manholes can be rectangular for easy construction • Where the water table is high and the pipe sewer is laid in open field or along the side of the drain, the RCC circular manholes would be constructed to avoid any leakages into or out the manholes. The RCC cast in situ or precast manholes will be used in the interceptor and collector sewers as these are proposed to be laid along the bank of the river. RCC precast or cast in situ manholes are recommended for large size sewers where space is sufficient for its construction. If possible brick masonry manholes are planned for narrow streets where the construction of RCC manholes is difficult and RCC cast in situ or precast manholes are proposed for main roads or for heavy traffic roads. Precast manholes should be made watertight by providing rubber gasket at the joints. Masonry manholes are limited to 2 m depth for pipes of 200-450 mm.
  • 83. Manhole Cover Levels • The final level of manholes would be depending on site condition, and therefore the final levels will be finalized during the execution time. However, generally the following values may be considered; • Paved areas cover level = final paved level. • Landscaped areas cover level = final ground level +0.1m. • Open, unpaved areas cover level = final ground level +0.25m or as instructed by the Engineer during construction. • Manhole covers with frame with a minimum clear opening of 600 mm
  • 84. Manhole Size and Shape Table 3-7: Recommended Manhole Size Depth to Pipe Soffit from Cover Level Largest Pipe in Manhole Circular Diameter of Manhole Wall Thickness Manhole Type (m) (mm) (mm) (mm) < 3 200-450 900 150 Type I RCC 3 - 6 200-450 1200 200 Type II RCC < 5 500-1000 1500 200 Type III RCC 5 - 8 500-1000 1500 250 Type IV RCC < 5 1200 1800 200 Type V RCC 5 - 8 1200 1800 250 Type VI RCC < 5 1400-1600 2400 200 Type VII RCC 5 - 8 1400-1600 2400 250 Type VIII RCC