From Wikipedia:
A BOM is a list of the raw materials, sub-assemblies,
intermediate assemblies, sub-components, parts, and the
quantities of each needed to manufacture a finished product.
© OpenBOM, 2018 (Newman Cloud Inc.)
Product structure is a hierarchy of product parent-child
relationships. Usually a tree or graph representation of
relationships between parts and assemblies representing
product itself.
What will we consider in this webinar
We will be setting aside the Wiki & formal definitions for now and asking this
question…. Will a consumer of your BOM deliver the correct product and what
level of completeness is required to do so?
© OpenBOM, 2018 (Newman Cloud Inc.)
Value
Maturity and completeness
Parts list
Consider BOM completeness as a spectrum
Maturity and completeness
Parts list, literally
a list of parts
Sub Levels
and Structure
Costs, Labor,
shipping, etc
Part
Configurations
Roll ups &
calculations
The
Configurable or
200% BOM
Production
Planning
BOM
Manuf
Process
© OpenBOM, 2018 (Newman Cloud Inc.)
Globe Skateboards ™ From Webinar #2
Wheel 1
Wheel 2
Wheel 3
Skateboard S100
Screw 1-4
Skateboard
S100
Deck Assy Axle Assy x2
Nut x2
Wheel x2
© OpenBOM, 2018 (Newman Cloud Inc.)
Wheel Board Axle Screw
Axle x1
Screws x8
Tape x2.5
Deck
Deck
Thoughtful Design….. From Webinar #2
© OpenBOM, 2018 (Newman Cloud Inc.)
Globe™ is adding a new Tony Hawk limited edition
skateboard based on the S100
Skateboard S100 Skateboard S100-TH
Tony Hawk
limited edition
*Different deck and wheels
© OpenBOM, 2018 (Newman Cloud Inc.)
Part
Number
Quantity Description Cost Extended
Cost
PN10 4 Part1 $10 $40
PN20 5 Part2 $20 $100
L15 .2 Labor $15 $3
Part
Number
Description Cost SB-CFG Quantity
On Hand
PN10 Part1 $10 S100,
S100-TH
10
PN20 Part2 $20 S100 20
PN30 Part3 $30 S100-TH 30
L15 Labor $15 S100,
S100-TH
---
Part
Number
Quantity Description Cost Extended
Cost
PN10 4 Part1 $10 $40
PN30 5 Part3 $30 $150
L15 .25 Labor $15 $3.75
Ex. BOM2 @S100-TH
Ex. BOM1 @S100
Skateboard Item
Master/Catalog/Inventory
© OpenBOM, 2018 (Newman Cloud Inc.)
Added the notion of configuration to our
item master from Webinar #2 as the
CFG property
Live...
- Review Skateboard Catalog and SB-CFG property
- Add SB-CFG for the 100-TH Deck
- Update the Skateboard BOM
- In the BOM, add the additional items needed for the -TH
- Create a BOM View for the S100 and S100-TH
- View the BOM as the S100 - no changes
- View the BOM as the S100-TH - is it complete?
- Change the cost of the -TH wheel in the Catalog
- Observe the change in the S100-TH view and not the S100
- Add shipping box to Catalog that will show in BOTH BOMs
- Go to Flatten
- Export PDF with filter on
© OpenBOM, 2018 (Newman Cloud Inc.)
© OpenBOM, 2018 (Newman Cloud Inc.)
Value
Maturity and completeness
Parts The “Thoughtful design from webinar #2”
Sufficient to
manufacture
List
Parts list,
literally a list
of parts
Sub Levels and
Structure
Costs, Labor,
shipping, etc
Part
Configurations
Roll ups &
calculations
The Configurable
or 200% BOM
Production
Planning
Manuf
Process
BOM Completeness and Maturity
More…..
Autodesk PLM blog - What should be included on the Bill of Materials
OpenBOM blog - What is a BOM? https://www.openbom.com/blog/what-is-bom-bill-of-materials
BeyondPLM blog http://beyondplm.com/2016/12/09/plm-multi-level-bom-vs-product-structure-lets-sort/
Arena PLM - Managing multi-level BOMs
Questions??
© OpenBOM, 2018 (Newman Cloud Inc.)
Questions?
Please type into the webinar panel or send to support@openbom.com
More information at www.openbom.com
© OpenBOM, 2018 (Newman Cloud Inc.)

BOM vs Product Structure

  • 1.
    BOM vs. ProductStructure Steve Hess Director of User Experience, OpenBOM stevehess@openbom.com Wednesday September 11, 2019 © OpenBOM, 2018 (Newman Cloud Inc.)
  • 2.
    This webinar isNOT a deep dive into BOM or database theory. This is a “No Marketing” environment! This webinar IS a thoughtful discussion about the level of BOM detail required to build your product. © OpenBOM, 2018 (Newman Cloud Inc.)
  • 3.
    From Wikipedia: A BOMis a list of the raw materials, sub-assemblies, intermediate assemblies, sub-components, parts, and the quantities of each needed to manufacture a finished product. © OpenBOM, 2018 (Newman Cloud Inc.) Product structure is a hierarchy of product parent-child relationships. Usually a tree or graph representation of relationships between parts and assemblies representing product itself.
  • 4.
    What will weconsider in this webinar We will be setting aside the Wiki & formal definitions for now and asking this question…. Will a consumer of your BOM deliver the correct product and what level of completeness is required to do so? © OpenBOM, 2018 (Newman Cloud Inc.) Value Maturity and completeness Parts list
  • 5.
    Consider BOM completenessas a spectrum Maturity and completeness Parts list, literally a list of parts Sub Levels and Structure Costs, Labor, shipping, etc Part Configurations Roll ups & calculations The Configurable or 200% BOM Production Planning BOM Manuf Process © OpenBOM, 2018 (Newman Cloud Inc.)
  • 6.
    Globe Skateboards ™From Webinar #2 Wheel 1 Wheel 2 Wheel 3 Skateboard S100 Screw 1-4 Skateboard S100 Deck Assy Axle Assy x2 Nut x2 Wheel x2 © OpenBOM, 2018 (Newman Cloud Inc.) Wheel Board Axle Screw Axle x1 Screws x8 Tape x2.5 Deck Deck
  • 7.
    Thoughtful Design….. FromWebinar #2 © OpenBOM, 2018 (Newman Cloud Inc.)
  • 8.
    Globe™ is addinga new Tony Hawk limited edition skateboard based on the S100 Skateboard S100 Skateboard S100-TH Tony Hawk limited edition *Different deck and wheels © OpenBOM, 2018 (Newman Cloud Inc.)
  • 9.
    Part Number Quantity Description CostExtended Cost PN10 4 Part1 $10 $40 PN20 5 Part2 $20 $100 L15 .2 Labor $15 $3 Part Number Description Cost SB-CFG Quantity On Hand PN10 Part1 $10 S100, S100-TH 10 PN20 Part2 $20 S100 20 PN30 Part3 $30 S100-TH 30 L15 Labor $15 S100, S100-TH --- Part Number Quantity Description Cost Extended Cost PN10 4 Part1 $10 $40 PN30 5 Part3 $30 $150 L15 .25 Labor $15 $3.75 Ex. BOM2 @S100-TH Ex. BOM1 @S100 Skateboard Item Master/Catalog/Inventory © OpenBOM, 2018 (Newman Cloud Inc.) Added the notion of configuration to our item master from Webinar #2 as the CFG property
  • 10.
    Live... - Review SkateboardCatalog and SB-CFG property - Add SB-CFG for the 100-TH Deck - Update the Skateboard BOM - In the BOM, add the additional items needed for the -TH - Create a BOM View for the S100 and S100-TH - View the BOM as the S100 - no changes - View the BOM as the S100-TH - is it complete? - Change the cost of the -TH wheel in the Catalog - Observe the change in the S100-TH view and not the S100 - Add shipping box to Catalog that will show in BOTH BOMs - Go to Flatten - Export PDF with filter on © OpenBOM, 2018 (Newman Cloud Inc.)
  • 11.
    © OpenBOM, 2018(Newman Cloud Inc.) Value Maturity and completeness Parts The “Thoughtful design from webinar #2” Sufficient to manufacture List Parts list, literally a list of parts Sub Levels and Structure Costs, Labor, shipping, etc Part Configurations Roll ups & calculations The Configurable or 200% BOM Production Planning Manuf Process BOM Completeness and Maturity
  • 12.
    More….. Autodesk PLM blog- What should be included on the Bill of Materials OpenBOM blog - What is a BOM? https://www.openbom.com/blog/what-is-bom-bill-of-materials BeyondPLM blog http://beyondplm.com/2016/12/09/plm-multi-level-bom-vs-product-structure-lets-sort/ Arena PLM - Managing multi-level BOMs Questions?? © OpenBOM, 2018 (Newman Cloud Inc.)
  • 13.
    Questions? Please type intothe webinar panel or send to support@openbom.com More information at www.openbom.com © OpenBOM, 2018 (Newman Cloud Inc.)