MINING DESIGN GUIDELINE | MDG 41
Guideline for fluid power system safety at mines
Comments close 31 October 2015.
Comments should be forward to: consult.minsafety@industry.nsw.gov.au
2
MINING DESIGN GUIDELINE | MDG 41
The guide for fluid power systems safety at mines MDG41 has
undergone an update in line with WHS requirements and
industry feedback. It focuses on risk management & mitigation
controls to be considered, along with competency and
operational guidance. MDG41 now also incorporates links to
other relevant data and historical incident reporting along with
exposure frequency for more meaningful Risk Assessments.
3
MINING DESIGN GUIDELINE | MDG 41
This document provides an industry benchmark for engineering
standards and fit-for-purpose equipment. This document was
compiled to formulate a management system approach for the
safe use of fluid power systems in mines. Use it for guidance
when assessing the safety aspects of fluid power systems. This
document is not intended to be a compliance document, it is
intended only to highlight risks and possible risk controls for
consideration.
4
MINING DESIGN GUIDELINE | MDG 41
1.3 Application
This guideline applies to all fluid power systems on plant in mines.
It should be used for all mining plant such as longwalls, mobile plant (open cut and underground mines), development equipment,
fixed installations, compressed air systems, etc.
This guideline should be considered when:
a) undertaking risk assessments
b) designing, manufacturing, altering and/or supplying fluid power systems (new or previously used)
c) installing or commissioning fluid power systems on a mine site
d) operating or using fluid power systems
e) maintaining, repairing, or overhauling, fluid power systems
f) site contracts are being considered
g) introducing fluid power systems to a mine on the first occasion
h) reviewing the adequacy of risk controls following an incident
i) assessing/auditing existing standards and practices.
5
MINING DESIGN GUIDELINE | MDG 41
1.4.1 Applicable legislation
Principal safety legislation for mines includes:
a) Work Health and Safety Act 2011, (WHS Act).
b) Work Health and Safety Regulation 2011, (WHS Regulation).
c) Work Health and Safety (Mines) Act 2014, (WHS (Mines) Act).
d) Work Health and Safety (Mines) Regulation, (WHS (Mines) Regulation).
Details of the legislation can be found at www.legislation.nsw.gov.au/
6
MINING DESIGN GUIDELINE | MDG 41
1.5.16 Reasonably practicable
That which is (or was at a particular time) reasonably able to be done to ensure health and safety, taking into account and
weighing up all relevant matters including:
a) the likelihood of the hazard or the risk concerned occurring
b) the degree of harm that might result from the hazard or the risk
c) what the person concerned knows, or reasonably should know, about the hazard or risk, and ways of eliminating or
minimizing the risk
d) the availability and suitability of ways to eliminate or minimise the risk
e) after assessing the extent of the risk and the available ways of eliminating or minimising the risk, the cost associated with
available ways of eliminating or minimising the risk, including whether the cost is grossly disproportionate to the risk.
In considering what is reasonably practicable, first consider what can be done, what is possible in the circumstances for
ensuring health and safety. Then consider whether it is reasonable in the circumstances to do all that is possible. This means
what can be done should be done unless it is reasonable in the circumstances to do something less.
7
MINING DESIGN GUIDELINE | MDG 41 RISK BASED CONSIDERATIONS
8
Review of past incidents
People in control of fluid power systems should provide the plant designer with details of relevant incidents and include
these in the plant safety file.
9
The most likely area for people to be struck with fluid is around the hands/fingers, face and arm/forearm areas. This is reflected in
both the 6 year period and the last 12 months and is consistent with people working on or in close proximity to hydraulic failures.
10
Operation Type 2007 2008 2009 2010 2011 2012 2013 Total
Underground 1 1 1 1 0 0 3 7
Surface 0 1 0 0 0 1 0 2
Total 1 2 1 1 0 1 3 9
Circumstances of 56(1)(o) escape of fluid incidents with 55(a)(v) fluid injection injuries
a) Outbye: A brain pump blockage in the delivery line and air pressurised, releasing fluid pressure which struck a person in the
leg. (deputy, permanent employee, pumping duties).
b) Coal handling plant: A painter was cleaning an airless spray gun which injected fluid into his finger. (painter [operator]
contractor employee, surface painting duties, injected in finger).
c) Development unit: Employees were cable bolting and the cable bolt tensioner pipe ruptured due to intensification.
(contractor employee supervisor, secondary bolting operations, struck in the hand – fingers)
d) Longwall: A staple was removed from a pressurised inter chock hose which released fluid injecting the employee in his
hand. (fitter, maintenance duties, hand)
e) Open cut: A contractor was cleaning equipment using pressure water cleaner and he cleaned the blocked nozzle with his
hand which injected water into his finger. (contractor, cleaning operations, injected in finger).
f) Open cut: Fitter received a high pressure grease injury to left upper chest when pressure was retained in grease system
when removing a component on excavator. (fitter, permanent employee, chest)
g) Development unit: A contract operator received an injection of hydraulic oil to his right forearm from a blown hose while
operating R/H inner bolting rig on a continuous miner. He went to remove the dolly from the drill motor and as he reached to
remove the dolly a hydraulic hose burst hitting him. (miner, contractor, arm/forearm)
h) Outbye: A contract fitter while attempting to identify a blown hose was moving hoses out of the way with his left hand and
operating a hydraulic lever with his right hand when he received an oil injection to his left hand ring finger. (Fitter, contractor,
hands and fingers). This injury also resulted in loss of consciousness.
i) Outbye: A Mineworker was cleaning mud around a QDS tongue retract hose on an LHD in order to identify a suspected oil
leak. He asked the LHD operator to activate the function while he had his hand near the damaged hose resulting in an oil
injection which required surgery. (miner, permanent employee, hands and fingers)
11
MINING DESIGN GUIDELINE | MDG 41
Work health and Safety Legislation
2.1.2 General duties in relation plant
A person conducting a business or undertaking (PCBU) has a primary duty of care under section 19 of the WHS Act to ensure,
so far as is reasonably practicable, that workers and other people are not exposed to health and safety risks arising from the
business or undertaking. This duty includes ensuring, so far as is reasonably practicable:
•the provision and maintenance of safe plant and structures
•the provision and maintenance of safe systems of work
•the safe use, handling and storage of plant and structures
•the provision of any information, training, instruction and supervision that is necessary to protect all persons from risks to their
health and safety arising from work carried out as part of the conduct of the business or undertaking.
In meeting this duty at a mine, a PCBU must manage risks to health and safety associated with mining operations at the mine in
accordance with part 3.1 of the WHS Regulation and clause 9 of the WHS (Mines) Regulation 2014:
•ensuring that a risk assessment is conducted by a person who is competent to conduct the particular risk assessment having
regard to the nature of the hazard
•identifying all reasonably foreseeable hazards
•eliminate risks to health and safety so far as is reasonably practicable
•if it is not reasonably practicable to eliminate risks to health and safety – minimise risks so far as reasonably practicable in accordance with
the hierarchy of risk control measures
12
MINING DESIGN GUIDELINE | MDG 41
2.4 Plant safety file
Safety-related aspects of fluid power systems should be fully documented. These records should be maintained in a plant safety
file that covers the lifecycle of the system. The plant safety file should be created by the designer and maintained by the person
in control of the fluid power system. The plant safety file should contain the following information:
a) design specifications, performance and operational conditions
b) design documentation
c) installation requirements
d) hazard identification and risk assessment documents
e) risk control methods
f) identification of all safety-critical systems and their safety category or integrity level
g) consultation records
h) commissioning and test results
i) maintenance records, safety inspections and test reports
j) change of procedures, monitoring, audit and review reports
k) reports of accidents and safety statistics
l) fluid system alterations.
The records should be stored and maintained in such a way that they are readily retrievable and protected against damage,
deterioration or loss. A plant safety file may not necessarily be one complete document, and may refer to where the information
can be obtained.
13
MINING DESIGN GUIDELINE | MDG 41
3.3 Fluid power systems design
3.3.1 General
Fluid power systems should be designed and components selected to provide safe operation over the intended design lifecycle
of the systems.
Seals and sealing devices should be compatible with the fluid used, adjacent materials, working conditions and environment.
Fluid systems should be designed to minimise excessive heat generation.
3.3.2 Rated working pressure
To avoid pressurised fluids escaping into the environment, fluid power system components should have appropriate factors of
safety on the rated working pressure to bursting pressure.
Hose assemblies should have a factor of safety of at least 4:1.
Adaptor fittings should have a factor of safety of at least:
a) 4:1 on rated working pressure to catastrophic failure of the adaptor or fitting
b) 2.5:1 on the rated working pressure to yield or deformation of the component.
Other fluid power components, such as cylinders, valves, actuators or similar should have a factor of safety of at least 2.5:1.
Where the above safety factors are reduced, appropriate engineering analysis and/or cycle and endurance testing should be
carried out and documented. ISO 7751 provides guidance.
Energy conversion components such as pumps, motors, cylinders, gas charged accumulators, reservoirs, etc should be
designed in accordance with ISO 4413 & ISO 4414
14
15
MINING DESIGN GUIDELINE | MDG 41
3.7.6.2 Staple type fittings
Staple lock connections are a legacy longwall technology, which need be managed with appropriate
control measures to be implemented for continued use. Staples are not recommended above those
pressures nominated in DIN 20043, BS 6537 and SAE J1467. All staple life expectancy is limited by
cyclic loading (cyclic fatigue). This information should be included in suppliers data.
People have suffered fatal injuries from the withdrawal of a staple type fittings when the fitting
inadvertently or unknowingly remained under pressure. For this reason, consideration should be given
to alternative to staple type fittings when designing new fluid power systems. Staple fittings should only
be used when there is no other reasonably practicable alternative fitting.
Unlike some other fittings, a staple fitting does not leak and gives no indication there is pressurised
fluid in the system when the staple is being removed. Once the staple is removed full pressure and flow
will expel from the fitting.
There are alternate non staple/pin connections available cannot be disconnected under pressure that
may be suitable.
16
MINING DESIGN GUIDELINE | MDG 41
3.3.4 Protection from uncontrolled escape of pressurised fluids
The design should minimise the risk of injury to operators and maintenance personnel from the uncontrolled escape of
pressurised fluids. Controls must be provided in accordance with the hierarchy of controls, refer 2.1.2.
Consideration should be given to:
a) routing hoses, pipes and pressurised components away from high risk areas, or otherwise as far away as is possible
b) use of protective fixed guards to prevent escaped fluids entering work areas
c) use of devices to divert or disperse the escaped fluid
d) providing means to detect a potential component failure before it occurs
e) providing means for effective isolation, energy dissipation and verification, refer Clause 3.6.
It is not considered acceptable to solely rely on PPE in high-risk areas.
3.7.2.8 Hose assembly energy diffusion devices
Where hoses are in a high-risk area and there is no other means to provide protection from the uncontrolled escape of
pressurised fluids, a hose assembly energy diffusion device may be appropriate if an unacceptable residual risk remains for
potential harm to people.
Diffusion devices may limit inspection for damage and hose deterioration.
When used – the hose assembly energy diffusion device should be able to diffuse the energy in the hydraulic fluid, to a level
where fluid injection will not occur provision should be made for the safe routine inspection of the hose contained within the
diffusion device. Inspection of hose assemblies should be undertaken with the sleeves removed
Diffusion sleeves are required to be a loose fit over the hose to redirect the energy of any ejected fluid. Covering layers of
spiral guarding may negate the effectiveness of the sleeve the sleeve should be manufactured from high abrasion, ozone,
heat resistant material and should be suitably attached in underground coal mines this sleeve should be fire resistant.
17
MINING DESIGN GUIDELINE | MDG 41
3.7.2.10 Fire resistance
All hydraulic hose assemblies should be fire resistant unless the hose is in a low risk fire area.
Fire resistance hoses should be tested in accordance with AS 1180-10B or ISO 8030 and the average duration of
the flaming and glowing should not exceed 30 seconds.
MDG 3608 provides guidance on FRAS in underground coal mines.
6.2 Hydraulic Hose
• Hydraulic hose is used in underground coal mines shall be constructed of materials that meet the following
requirements.
6.2.1.1 Fire Resistance
• When tested in accordance with ISO 8030, meets the requirements of ISO 6805:1994 Clause 15.
6.2.1.2 Electrical Resistance
• When tested in accordance with ISO 8031,meets the requirements of ISO 6805:1994 Clause 14.
18
MINING DESIGN GUIDELINE | MDG 41
3.7.3.3 Effective service life
In order to maximise the effective service life of hose assembly, design and installation should be carried out in accordance with
SAE J1273 or ISO 17165-2. Poor design of installation standards is a predominate factor in effective service life
In addition consideration should be given to:
a) external cover protection that may be exposed to abrasion or impact damage
b) shielding to protect hose assemblies from heat sources such as engine manifolds, exhausts, turbos etc
c) accidental damage caused by: falling rock, vehicle collision, tensile load, shear load, crushing, fire
d) mechanical loads – vibration, tensile, shear
e) corrosive spillage, molten metal, pressure surge
f) corrosion of end fittings (alkalinity / acidic water) / Coal (sulphur)
g) heat generated internally and externally to the hose assembly
h) refer hose life degradation (ref S-N studies) ACARP C17020
i) working fluid temperature, velocity and contamination.
19
MINING DESIGN GUIDELINE | MDG 41
3.7.3.4 Hose and hose assembly shelf life and storage
Storage and age control can affect hose life. The following should be considered:
a) A system of age control should be implemented to ensure hose assemblies are used prior to shelf life expiration.
b) Hose and hose assemblies should be stored in accordance with ISO 8331.
c) Storage areas should be relatively cool and dark, as well as free of dust, dirt, dampness and mildew.
d) Hose and hose assemblies can be adversely affected by temperature, humidity, ozone, sunlight, ultraviolet light, oils,
solvents, corrosive liquids, and fumes, acids and alkalis, insects, rodents, sharp edges and abrasive surfaces, electric or
strong magnetic fields, mould and fungi, and radioactive materials.
e) Storage of tested hose assemblies should be limited to two years from inspection, refer to SAE J1273 Clause 9.1.c.
f) Hose assembly stored for more than two years, should be visually inspected and proof tested or follow manufacturer’s
recommendations.
g) Hose assemblies with hose older than five years (five years or greater post cure date) should be re-proof tested (see
3.8.7.1) and hose assemblies with hose older than eight years should be discarded unless otherwise recommended by
the hose manufacturer. After successfully retesting, the hose assemblies should be clearly remarked.
20
MINING DESIGN GUIDELINE | MDG 41
3.7.6.1 General
Hose ends should not be interchanged and should be properly matched to the hose based on proven type test result.
Only select hose ends compatible with the hose for the application. The fitting and hose manufacturer’s recommendations
should be strictly followed.
21
MINING DESIGN GUIDELINE | MDG 41
3.9.7 Operation and maintenance instructions
Operation and maintenance manuals should be provided. These manuals should contain the following information categorised
in appropriate sections:
a) Recommended maintenance requirements to maintain the fluid system in a safe operating condition.
b) Recommended inspection and tests, to check if the equipment is safe to operate.
c) Identification of any hazards involved in maintaining and operating the equipment.
d) Identification of all high risk areas.
e) Energy isolation, dissipation and control procedures.
f) Safe work procedures to carry out maintenance on the system, including setting of controls.
g) Protective equipment requirements.
h) Trouble shooting guide.
i) Safe handling and disposal of fluids.
j) Recommended spares.
22
MINING DESIGN GUIDELINE | MDG 41
4.1 Manufacture and assembly - of fluid power systems and components
Manufacturers and assemblers of fluid power systems and components should use the design specifications provided by
the designer. Clause 193 of the WHS Regulation imposes specific duties on the manufacturer of plant.
The following should be considered in the manufacture and assembly of fluid power systems and components:
• Specific conditions relating to the method of manufacture.
• Instructions for fitting or refitting plant parts and their location on other components of the plant or their housings
where errors could be made when installing the plant.
• Instruction where hot or cold parts or material may create a hazard.
• Specifications of material.
• Schematic diagrams.
• Specifications for proprietary items e.g. electric motors.
• Component specifications including drawings and tolerances.
• Assembly drawings.
• Assembly procedures including specific tools or equipment to be used.
• Manufacturing processes e.g, requirements for crimping.
• Details of hazards presented by materials during manufacturing.
• Safety outcomes
Any alterations during the manufacturing / assembly phase of a fluid power systems is considered a design change in
which designers obligations apply.
23
MINING DESIGN GUIDELINE | MDG 41
7.1.1 Competence
All people associated with the maintenance of the fluid power system (including contractors) should be competent to safely
carry out work on the fluid system.
Some relevant competencies include:
•MEM18052B Maintain fluid power systems for mobile plant
•Minimum Bend Radius
•Minimum Bend Radius AURTTA3013 Repair hydraulic systems
Competence of maintenance personnel should include:
a)system functional requirements and operating parameters
b)troubleshooting and individual component testing
c)safe energy isolation and dissipation in accordance with the mines isolation management plan
d)electrical / fluid power interfaces and control circuitry
e)hose management
f)importance of cleanliness
g)energy isolation process in particular hazardous activity isolation.
Specific competence on energy isolation should be carried out on large and complex fluid power systems such as longwall roof
supports.
24
MINING DESIGN GUIDELINE | MDG 41
7.1.4 Safe working with fluid power systems:
When working with fluid power systems:
• Never feel for leaks
• Never vent hydraulic fluid to atmosphere unless it is safely controlled, such as into collection drums/trays or through a
diffuser
• Never disconnect any line that has not been de-energised and tested for de-energisation
• Always apply energy isolation procedures, refer to clause 3.6.
A typical model for safely performing maintenance is illustrated in the figure below:
25
MINING DESIGN GUIDELINE | MDG 41
7.2 Isolation and energy dissipation
The mine will have an energy isolation management plan, refer to MDG 40
This plan will include:
a)an energy isolation process used for the de-energisation of all energies
b)an assessment process for people who need to demonstrate competence
c)identified specific isolation processes for high risk activities
d)emergency management
e)training.
All safe work methods should identify energy isolation, dissipation and verification requirements.
MDG 40 offers guidance on the requirements for energy isolation management.
26
MINING DESIGN GUIDELINE | MDG 41
3.6.1 General
In the performance of many lifecycle tasks such as installation, repair, service, component replacement, maintenance and
disassembly it is imperative to have isolation and energy dissipation considered in the design of the fluid power system.
Isolation valves should not be installed in the return circuit of a hydraulic system as they provide a means for pressure
intensification if left closed.
The design risk assessment should consider effective means of energy isolation, dissipation and verification of fluid power
hazards. This should include:
a) identification of all energy sources to prevent a release of energy, (such as stored fluid power, gravity, (suspended
loads), springs, electrical) and / or prevent unintended activation or movement of equipment
b) provision of a means to isolate all identified energy sources to prevent a possible state change. This includes purpose
designed isolation devices that are lockable.
c) provision of a means to safely dissipate fluid. If used as part of the isolation process a dissipation device should be a
purpose-designed dissipation devices and lockable.
d) provision of a system that verifies that pressure has been dissipated. (Test for dead or safe state)
e) clear identification of all isolation and dissipation points
f) provision of safe work methods for the use of the isolation, dissipation and verification devices. Should include removal
and restoration of energy.
g) information on required people competence to isolate, diffuse and verify isolation.
27
MINING DESIGN GUIDELINE | MDG 41
7.6 Hose assembly management
7.6.1 General
A hose management plan should be developed, implemented and maintained (refer to clause 7.5 and clause 3.7.12). The hose
management plan should be established and maintained in consultation with all stakeholders, including site management,
maintenance and suppliers. The hose management plan should be integral with the mines maintenance system and the site
specific maintenance strategies.
A hose management program will reduce equipment downtime, maintain peak operating performance, and reduce the risk for
personal injury and/or property damage.
The hose management plan should include:
• A database of the range of hose assemblies on the mine site
• A maintenance schedule such that all hose assemblies are inspected at a frequency as required for their risk to safety and
equipment operation, refer Work Health and Safety (Mines) Regulation 2014 Section 13 and Schedule 2.
• Discarded hose assemblies or hoses with no known history (e.g. longwall, monorail, AFC/BSL hoses) not being reinstalled
unless tested and certified in accordance with clause 3.7.11.1 Individual Hose assembly proof testing. If reinstalled, the
hoses being cleaned and labelled in readiness for reuse. This is not intended to include the disconnection and reconnection
for operational or maintenance purposes.
• Hose failure mode analysis.
28
MINING DESIGN GUIDELINE | MDG 41
MDG41 is not a Hose & fitting standard
MDG41 is not a Compliance document
29
MINING DESIGN GUIDELINE | MDG 41
Guideline for fluid power system safety at mines
Focuses on risk management & mitigation controls to be
considered, along with competency and operational guidance.
MDG41 now also incorporates links to other relevant data and
historical incident reporting along with exposure frequency for
more meaningful Risk Assessments.
30
Thank you

More Related Content

Viewers also liked (20)

Nmdl final project express-kate schild
Nmdl final project express-kate schildNmdl final project express-kate schild
Nmdl final project express-kate schild
 
Smart Grid Analytics
Smart Grid AnalyticsSmart Grid Analytics
Smart Grid Analytics
 
Australian Renewable Energy Mapping Infrastructure
Australian Renewable Energy Mapping InfrastructureAustralian Renewable Energy Mapping Infrastructure
Australian Renewable Energy Mapping Infrastructure
 
Opportunities for wind energy in NSW
Opportunities for wind energy in NSWOpportunities for wind energy in NSW
Opportunities for wind energy in NSW
 
Mitosis plant & animal
Mitosis plant & animalMitosis plant & animal
Mitosis plant & animal
 
Raheel Iqbal
Raheel IqbalRaheel Iqbal
Raheel Iqbal
 
Mte penyertaan
Mte penyertaanMte penyertaan
Mte penyertaan
 
О блоге и об авторе
О блоге и об автореО блоге и об авторе
О блоге и об авторе
 
DeepaPriyaJ
DeepaPriyaJDeepaPriyaJ
DeepaPriyaJ
 
2014 Regulatory Team Work
2014 Regulatory Team Work2014 Regulatory Team Work
2014 Regulatory Team Work
 
Preview radar systems david howell
Preview radar systems   david howellPreview radar systems   david howell
Preview radar systems david howell
 
NinaLulu.HRjob
NinaLulu.HRjobNinaLulu.HRjob
NinaLulu.HRjob
 
Sijil 2
Sijil 2Sijil 2
Sijil 2
 
Muscular system
Muscular systemMuscular system
Muscular system
 
Cooperative Drilling
Cooperative DrillingCooperative Drilling
Cooperative Drilling
 
Clean Energy Finance Corporation
Clean Energy Finance CorporationClean Energy Finance Corporation
Clean Energy Finance Corporation
 
cancell this presentation.
cancell this presentation.cancell this presentation.
cancell this presentation.
 
Ti apresentation pepin
Ti apresentation pepinTi apresentation pepin
Ti apresentation pepin
 
Mte penghargaan
Mte penghargaanMte penghargaan
Mte penghargaan
 
Perkenalan diri
Perkenalan diriPerkenalan diri
Perkenalan diri
 

Similar to Mdg 41 review - Gary Nauer

A handbook for safety and health in small scale
A handbook for safety and health in small scaleA handbook for safety and health in small scale
A handbook for safety and health in small scaleIDHAMUKI
 
Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...Khalid Abdel Naser Abdel Rahim
 
Risk analysis and environmental hazard management
Risk analysis and environmental hazard managementRisk analysis and environmental hazard management
Risk analysis and environmental hazard managementeSAT Publishing House
 
Dam construction safety management (group 2, 7th reporter)
Dam construction safety management (group 2, 7th reporter)Dam construction safety management (group 2, 7th reporter)
Dam construction safety management (group 2, 7th reporter)Jefferson Pura Basista
 
Australian elevator association hand book
Australian elevator association hand bookAustralian elevator association hand book
Australian elevator association hand bookLutfi Ismail
 
The management of health and safety of construction sites in accra
The management of health and safety of construction sites in accraThe management of health and safety of construction sites in accra
The management of health and safety of construction sites in accraAlexander Decker
 
Safety complete
Safety completeSafety complete
Safety completeLwj Welson
 
Facility Upgrade V2
Facility Upgrade V2Facility Upgrade V2
Facility Upgrade V2Rose Buot
 
öZlem özkiliç makale - en
öZlem özkiliç  makale - enöZlem özkiliç  makale - en
öZlem özkiliç makale - enÖzlem ÖZKILIÇ
 
Safety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxSafety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxalutarep1
 
Safety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxSafety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxalutarep1
 
Knowledge Based System (Expert System) : Equipment Safety Control & Management
Knowledge Based System (Expert System) : Equipment Safety Control & ManagementKnowledge Based System (Expert System) : Equipment Safety Control & Management
Knowledge Based System (Expert System) : Equipment Safety Control & ManagementAmr El-Ganainy
 
Industrial safety
Industrial safetyIndustrial safety
Industrial safetypsc2015
 

Similar to Mdg 41 review - Gary Nauer (20)

A handbook for safety and health in small scale
A handbook for safety and health in small scaleA handbook for safety and health in small scale
A handbook for safety and health in small scale
 
Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...
 
Risk analysis and environmental hazard management
Risk analysis and environmental hazard managementRisk analysis and environmental hazard management
Risk analysis and environmental hazard management
 
Dam construction safety management (group 2, 7th reporter)
Dam construction safety management (group 2, 7th reporter)Dam construction safety management (group 2, 7th reporter)
Dam construction safety management (group 2, 7th reporter)
 
Changing world of maintenance - AXYS Consulting
Changing world of maintenance - AXYS ConsultingChanging world of maintenance - AXYS Consulting
Changing world of maintenance - AXYS Consulting
 
Class 4-osha-1994-cdm
Class 4-osha-1994-cdmClass 4-osha-1994-cdm
Class 4-osha-1994-cdm
 
Procedure for Hazard Identification and Risk Assessment in Wastewater Treatme...
Procedure for Hazard Identification and Risk Assessment in Wastewater Treatme...Procedure for Hazard Identification and Risk Assessment in Wastewater Treatme...
Procedure for Hazard Identification and Risk Assessment in Wastewater Treatme...
 
Australian elevator association hand book
Australian elevator association hand bookAustralian elevator association hand book
Australian elevator association hand book
 
The management of health and safety of construction sites in accra
The management of health and safety of construction sites in accraThe management of health and safety of construction sites in accra
The management of health and safety of construction sites in accra
 
Safety complete
Safety completeSafety complete
Safety complete
 
Facility Upgrade V2
Facility Upgrade V2Facility Upgrade V2
Facility Upgrade V2
 
öZlem özkiliç makale - en
öZlem özkiliç  makale - enöZlem özkiliç  makale - en
öZlem özkiliç makale - en
 
Safety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxSafety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptx
 
Safety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxSafety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptx
 
05 reviewing your SMS
05 reviewing your SMS05 reviewing your SMS
05 reviewing your SMS
 
Intro to safety
Intro to safetyIntro to safety
Intro to safety
 
Intro to safety
Intro to safetyIntro to safety
Intro to safety
 
guide-tunnelling.pdf
guide-tunnelling.pdfguide-tunnelling.pdf
guide-tunnelling.pdf
 
Knowledge Based System (Expert System) : Equipment Safety Control & Management
Knowledge Based System (Expert System) : Equipment Safety Control & ManagementKnowledge Based System (Expert System) : Equipment Safety Control & Management
Knowledge Based System (Expert System) : Equipment Safety Control & Management
 
Industrial safety
Industrial safetyIndustrial safety
Industrial safety
 

More from NSW Environment and Planning

06. how the regulator communicates with the industry
06. how the regulator communicates with the industry06. how the regulator communicates with the industry
06. how the regulator communicates with the industryNSW Environment and Planning
 
Fires on mobile plant refuelling (Ross Stutchbury)
Fires on mobile plant refuelling (Ross Stutchbury)Fires on mobile plant refuelling (Ross Stutchbury)
Fires on mobile plant refuelling (Ross Stutchbury)NSW Environment and Planning
 
Mobile plant rollovers and collisions (Bill McGlynn)
Mobile plant rollovers and collisions (Bill McGlynn)Mobile plant rollovers and collisions (Bill McGlynn)
Mobile plant rollovers and collisions (Bill McGlynn)NSW Environment and Planning
 
Electrical performance presentation (Craig Harris)
Electrical performance presentation (Craig Harris)Electrical performance presentation (Craig Harris)
Electrical performance presentation (Craig Harris)NSW Environment and Planning
 
Where do I stand for fire protection on mobile and transportable equipment an...
Where do I stand for fire protection on mobile and transportable equipment an...Where do I stand for fire protection on mobile and transportable equipment an...
Where do I stand for fire protection on mobile and transportable equipment an...NSW Environment and Planning
 
Demolition of a former mine site - Luke Egan and David Wood
Demolition of a former mine site - Luke Egan and David WoodDemolition of a former mine site - Luke Egan and David Wood
Demolition of a former mine site - Luke Egan and David WoodNSW Environment and Planning
 

More from NSW Environment and Planning (20)

12 Small mines report card 2020
12 Small mines report card 202012 Small mines report card 2020
12 Small mines report card 2020
 
11 occupational hygiene monitoring of dust
11 occupational hygiene monitoring of dust11 occupational hygiene monitoring of dust
11 occupational hygiene monitoring of dust
 
13 explosives awareness
13 explosives awareness13 explosives awareness
13 explosives awareness
 
10 incident reporting to the regulator 2020
10 incident reporting to the regulator 202010 incident reporting to the regulator 2020
10 incident reporting to the regulator 2020
 
08 dust safety and health surveillance
08 dust safety and health surveillance08 dust safety and health surveillance
08 dust safety and health surveillance
 
07 feedback and consultation
07 feedback and consultation07 feedback and consultation
07 feedback and consultation
 
06. how the regulator communicates with the industry
06. how the regulator communicates with the industry06. how the regulator communicates with the industry
06. how the regulator communicates with the industry
 
04. slinging and lifting equipment
04. slinging and lifting equipment04. slinging and lifting equipment
04. slinging and lifting equipment
 
Control focused inspection tools (Mark Smith)
Control focused inspection tools (Mark Smith)Control focused inspection tools (Mark Smith)
Control focused inspection tools (Mark Smith)
 
Central assessment unit CAU(Steve Bentham)
Central assessment unit CAU(Steve Bentham)Central assessment unit CAU(Steve Bentham)
Central assessment unit CAU(Steve Bentham)
 
Autonomous mining equipment (Owen Barry)
Autonomous mining equipment (Owen Barry)Autonomous mining equipment (Owen Barry)
Autonomous mining equipment (Owen Barry)
 
Fires on mobile plant refuelling (Ross Stutchbury)
Fires on mobile plant refuelling (Ross Stutchbury)Fires on mobile plant refuelling (Ross Stutchbury)
Fires on mobile plant refuelling (Ross Stutchbury)
 
Mobile plant rollovers and collisions (Bill McGlynn)
Mobile plant rollovers and collisions (Bill McGlynn)Mobile plant rollovers and collisions (Bill McGlynn)
Mobile plant rollovers and collisions (Bill McGlynn)
 
Metropolitan colliery gas (Dave Gordon)
Metropolitan colliery gas (Dave Gordon)Metropolitan colliery gas (Dave Gordon)
Metropolitan colliery gas (Dave Gordon)
 
Airborne dust update (Mark Shepherd)
Airborne dust update (Mark Shepherd)Airborne dust update (Mark Shepherd)
Airborne dust update (Mark Shepherd)
 
Emergency planning (Matt U'Brien)
Emergency planning (Matt U'Brien)Emergency planning (Matt U'Brien)
Emergency planning (Matt U'Brien)
 
Electrical performance presentation (Craig Harris)
Electrical performance presentation (Craig Harris)Electrical performance presentation (Craig Harris)
Electrical performance presentation (Craig Harris)
 
Where do I stand for fire protection on mobile and transportable equipment an...
Where do I stand for fire protection on mobile and transportable equipment an...Where do I stand for fire protection on mobile and transportable equipment an...
Where do I stand for fire protection on mobile and transportable equipment an...
 
The culture of hydraulic safety - Kyle Probert
The culture of hydraulic safety - Kyle ProbertThe culture of hydraulic safety - Kyle Probert
The culture of hydraulic safety - Kyle Probert
 
Demolition of a former mine site - Luke Egan and David Wood
Demolition of a former mine site - Luke Egan and David WoodDemolition of a former mine site - Luke Egan and David Wood
Demolition of a former mine site - Luke Egan and David Wood
 

Recently uploaded

High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...narwatsonia7
 
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...Suhani Kapoor
 
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfYHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfyalehistoricalreview
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...ResolutionFoundation
 
Club of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationClub of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationEnergy for One World
 
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...narwatsonia7
 
history of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhistory of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhellokittymaearciaga
 
Take action for a healthier planet and brighter future.
Take action for a healthier planet and brighter future.Take action for a healthier planet and brighter future.
Take action for a healthier planet and brighter future.Christina Parmionova
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...Suhani Kapoor
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28JSchaus & Associates
 
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...Suhani Kapoor
 
(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书mbetknu
 
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service BangaloreCall Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalorenarwatsonia7
 
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012rehmti665
 
Panet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRILPanet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRILChristina Parmionova
 
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...ankitnayak356677
 
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls ServiceCall Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Servicenarwatsonia7
 
Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Christina Parmionova
 
(办)McGill毕业证怎么查学位证书
(办)McGill毕业证怎么查学位证书(办)McGill毕业证怎么查学位证书
(办)McGill毕业证怎么查学位证书mbetknu
 

Recently uploaded (20)

High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
High Class Call Girls Bangalore Komal 7001305949 Independent Escort Service B...
 
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
 
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdfYHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
YHR Fall 2023 Issue (Joseph Manning Interview) (2).pdf
 
Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...Precarious profits? Why firms use insecure contracts, and what would change t...
Precarious profits? Why firms use insecure contracts, and what would change t...
 
Club of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological CivilizationClub of Rome: Eco-nomics for an Ecological Civilization
Club of Rome: Eco-nomics for an Ecological Civilization
 
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
Call Girls Service Race Course Road Just Call 7001305949 Enjoy College Girls ...
 
history of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptxhistory of 1935 philippine constitution.pptx
history of 1935 philippine constitution.pptx
 
Take action for a healthier planet and brighter future.
Take action for a healthier planet and brighter future.Take action for a healthier planet and brighter future.
Take action for a healthier planet and brighter future.
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28
 
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
VIP Call Girls Doodh Bowli ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With R...
 
(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书(怎样办)Sherbrooke毕业证本科/硕士学位证书
(怎样办)Sherbrooke毕业证本科/硕士学位证书
 
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service BangaloreCall Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
Call Girls Bangalore Saanvi 7001305949 Independent Escort Service Bangalore
 
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
Call Girls Connaught Place Delhi reach out to us at ☎ 9711199012
 
Panet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRILPanet vs.Plastics - Earth Day 2024 - 22 APRIL
Panet vs.Plastics - Earth Day 2024 - 22 APRIL
 
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
Greater Noida Call Girls 9711199012 WhatsApp No 24x7 Vip Escorts in Greater N...
 
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls ServiceCall Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
 
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.Action Toolkit - Earth Day 2024 - April 22nd.
Action Toolkit - Earth Day 2024 - April 22nd.
 
(办)McGill毕业证怎么查学位证书
(办)McGill毕业证怎么查学位证书(办)McGill毕业证怎么查学位证书
(办)McGill毕业证怎么查学位证书
 

Mdg 41 review - Gary Nauer

  • 1. 1 MINING DESIGN GUIDELINE | MDG 41 Guideline for fluid power system safety at mines Comments close 31 October 2015. Comments should be forward to: consult.minsafety@industry.nsw.gov.au
  • 2. 2 MINING DESIGN GUIDELINE | MDG 41 The guide for fluid power systems safety at mines MDG41 has undergone an update in line with WHS requirements and industry feedback. It focuses on risk management & mitigation controls to be considered, along with competency and operational guidance. MDG41 now also incorporates links to other relevant data and historical incident reporting along with exposure frequency for more meaningful Risk Assessments.
  • 3. 3 MINING DESIGN GUIDELINE | MDG 41 This document provides an industry benchmark for engineering standards and fit-for-purpose equipment. This document was compiled to formulate a management system approach for the safe use of fluid power systems in mines. Use it for guidance when assessing the safety aspects of fluid power systems. This document is not intended to be a compliance document, it is intended only to highlight risks and possible risk controls for consideration.
  • 4. 4 MINING DESIGN GUIDELINE | MDG 41 1.3 Application This guideline applies to all fluid power systems on plant in mines. It should be used for all mining plant such as longwalls, mobile plant (open cut and underground mines), development equipment, fixed installations, compressed air systems, etc. This guideline should be considered when: a) undertaking risk assessments b) designing, manufacturing, altering and/or supplying fluid power systems (new or previously used) c) installing or commissioning fluid power systems on a mine site d) operating or using fluid power systems e) maintaining, repairing, or overhauling, fluid power systems f) site contracts are being considered g) introducing fluid power systems to a mine on the first occasion h) reviewing the adequacy of risk controls following an incident i) assessing/auditing existing standards and practices.
  • 5. 5 MINING DESIGN GUIDELINE | MDG 41 1.4.1 Applicable legislation Principal safety legislation for mines includes: a) Work Health and Safety Act 2011, (WHS Act). b) Work Health and Safety Regulation 2011, (WHS Regulation). c) Work Health and Safety (Mines) Act 2014, (WHS (Mines) Act). d) Work Health and Safety (Mines) Regulation, (WHS (Mines) Regulation). Details of the legislation can be found at www.legislation.nsw.gov.au/
  • 6. 6 MINING DESIGN GUIDELINE | MDG 41 1.5.16 Reasonably practicable That which is (or was at a particular time) reasonably able to be done to ensure health and safety, taking into account and weighing up all relevant matters including: a) the likelihood of the hazard or the risk concerned occurring b) the degree of harm that might result from the hazard or the risk c) what the person concerned knows, or reasonably should know, about the hazard or risk, and ways of eliminating or minimizing the risk d) the availability and suitability of ways to eliminate or minimise the risk e) after assessing the extent of the risk and the available ways of eliminating or minimising the risk, the cost associated with available ways of eliminating or minimising the risk, including whether the cost is grossly disproportionate to the risk. In considering what is reasonably practicable, first consider what can be done, what is possible in the circumstances for ensuring health and safety. Then consider whether it is reasonable in the circumstances to do all that is possible. This means what can be done should be done unless it is reasonable in the circumstances to do something less.
  • 7. 7 MINING DESIGN GUIDELINE | MDG 41 RISK BASED CONSIDERATIONS
  • 8. 8 Review of past incidents People in control of fluid power systems should provide the plant designer with details of relevant incidents and include these in the plant safety file.
  • 9. 9 The most likely area for people to be struck with fluid is around the hands/fingers, face and arm/forearm areas. This is reflected in both the 6 year period and the last 12 months and is consistent with people working on or in close proximity to hydraulic failures.
  • 10. 10 Operation Type 2007 2008 2009 2010 2011 2012 2013 Total Underground 1 1 1 1 0 0 3 7 Surface 0 1 0 0 0 1 0 2 Total 1 2 1 1 0 1 3 9 Circumstances of 56(1)(o) escape of fluid incidents with 55(a)(v) fluid injection injuries a) Outbye: A brain pump blockage in the delivery line and air pressurised, releasing fluid pressure which struck a person in the leg. (deputy, permanent employee, pumping duties). b) Coal handling plant: A painter was cleaning an airless spray gun which injected fluid into his finger. (painter [operator] contractor employee, surface painting duties, injected in finger). c) Development unit: Employees were cable bolting and the cable bolt tensioner pipe ruptured due to intensification. (contractor employee supervisor, secondary bolting operations, struck in the hand – fingers) d) Longwall: A staple was removed from a pressurised inter chock hose which released fluid injecting the employee in his hand. (fitter, maintenance duties, hand) e) Open cut: A contractor was cleaning equipment using pressure water cleaner and he cleaned the blocked nozzle with his hand which injected water into his finger. (contractor, cleaning operations, injected in finger). f) Open cut: Fitter received a high pressure grease injury to left upper chest when pressure was retained in grease system when removing a component on excavator. (fitter, permanent employee, chest) g) Development unit: A contract operator received an injection of hydraulic oil to his right forearm from a blown hose while operating R/H inner bolting rig on a continuous miner. He went to remove the dolly from the drill motor and as he reached to remove the dolly a hydraulic hose burst hitting him. (miner, contractor, arm/forearm) h) Outbye: A contract fitter while attempting to identify a blown hose was moving hoses out of the way with his left hand and operating a hydraulic lever with his right hand when he received an oil injection to his left hand ring finger. (Fitter, contractor, hands and fingers). This injury also resulted in loss of consciousness. i) Outbye: A Mineworker was cleaning mud around a QDS tongue retract hose on an LHD in order to identify a suspected oil leak. He asked the LHD operator to activate the function while he had his hand near the damaged hose resulting in an oil injection which required surgery. (miner, permanent employee, hands and fingers)
  • 11. 11 MINING DESIGN GUIDELINE | MDG 41 Work health and Safety Legislation 2.1.2 General duties in relation plant A person conducting a business or undertaking (PCBU) has a primary duty of care under section 19 of the WHS Act to ensure, so far as is reasonably practicable, that workers and other people are not exposed to health and safety risks arising from the business or undertaking. This duty includes ensuring, so far as is reasonably practicable: •the provision and maintenance of safe plant and structures •the provision and maintenance of safe systems of work •the safe use, handling and storage of plant and structures •the provision of any information, training, instruction and supervision that is necessary to protect all persons from risks to their health and safety arising from work carried out as part of the conduct of the business or undertaking. In meeting this duty at a mine, a PCBU must manage risks to health and safety associated with mining operations at the mine in accordance with part 3.1 of the WHS Regulation and clause 9 of the WHS (Mines) Regulation 2014: •ensuring that a risk assessment is conducted by a person who is competent to conduct the particular risk assessment having regard to the nature of the hazard •identifying all reasonably foreseeable hazards •eliminate risks to health and safety so far as is reasonably practicable •if it is not reasonably practicable to eliminate risks to health and safety – minimise risks so far as reasonably practicable in accordance with the hierarchy of risk control measures
  • 12. 12 MINING DESIGN GUIDELINE | MDG 41 2.4 Plant safety file Safety-related aspects of fluid power systems should be fully documented. These records should be maintained in a plant safety file that covers the lifecycle of the system. The plant safety file should be created by the designer and maintained by the person in control of the fluid power system. The plant safety file should contain the following information: a) design specifications, performance and operational conditions b) design documentation c) installation requirements d) hazard identification and risk assessment documents e) risk control methods f) identification of all safety-critical systems and their safety category or integrity level g) consultation records h) commissioning and test results i) maintenance records, safety inspections and test reports j) change of procedures, monitoring, audit and review reports k) reports of accidents and safety statistics l) fluid system alterations. The records should be stored and maintained in such a way that they are readily retrievable and protected against damage, deterioration or loss. A plant safety file may not necessarily be one complete document, and may refer to where the information can be obtained.
  • 13. 13 MINING DESIGN GUIDELINE | MDG 41 3.3 Fluid power systems design 3.3.1 General Fluid power systems should be designed and components selected to provide safe operation over the intended design lifecycle of the systems. Seals and sealing devices should be compatible with the fluid used, adjacent materials, working conditions and environment. Fluid systems should be designed to minimise excessive heat generation. 3.3.2 Rated working pressure To avoid pressurised fluids escaping into the environment, fluid power system components should have appropriate factors of safety on the rated working pressure to bursting pressure. Hose assemblies should have a factor of safety of at least 4:1. Adaptor fittings should have a factor of safety of at least: a) 4:1 on rated working pressure to catastrophic failure of the adaptor or fitting b) 2.5:1 on the rated working pressure to yield or deformation of the component. Other fluid power components, such as cylinders, valves, actuators or similar should have a factor of safety of at least 2.5:1. Where the above safety factors are reduced, appropriate engineering analysis and/or cycle and endurance testing should be carried out and documented. ISO 7751 provides guidance. Energy conversion components such as pumps, motors, cylinders, gas charged accumulators, reservoirs, etc should be designed in accordance with ISO 4413 & ISO 4414
  • 14. 14
  • 15. 15 MINING DESIGN GUIDELINE | MDG 41 3.7.6.2 Staple type fittings Staple lock connections are a legacy longwall technology, which need be managed with appropriate control measures to be implemented for continued use. Staples are not recommended above those pressures nominated in DIN 20043, BS 6537 and SAE J1467. All staple life expectancy is limited by cyclic loading (cyclic fatigue). This information should be included in suppliers data. People have suffered fatal injuries from the withdrawal of a staple type fittings when the fitting inadvertently or unknowingly remained under pressure. For this reason, consideration should be given to alternative to staple type fittings when designing new fluid power systems. Staple fittings should only be used when there is no other reasonably practicable alternative fitting. Unlike some other fittings, a staple fitting does not leak and gives no indication there is pressurised fluid in the system when the staple is being removed. Once the staple is removed full pressure and flow will expel from the fitting. There are alternate non staple/pin connections available cannot be disconnected under pressure that may be suitable.
  • 16. 16 MINING DESIGN GUIDELINE | MDG 41 3.3.4 Protection from uncontrolled escape of pressurised fluids The design should minimise the risk of injury to operators and maintenance personnel from the uncontrolled escape of pressurised fluids. Controls must be provided in accordance with the hierarchy of controls, refer 2.1.2. Consideration should be given to: a) routing hoses, pipes and pressurised components away from high risk areas, or otherwise as far away as is possible b) use of protective fixed guards to prevent escaped fluids entering work areas c) use of devices to divert or disperse the escaped fluid d) providing means to detect a potential component failure before it occurs e) providing means for effective isolation, energy dissipation and verification, refer Clause 3.6. It is not considered acceptable to solely rely on PPE in high-risk areas. 3.7.2.8 Hose assembly energy diffusion devices Where hoses are in a high-risk area and there is no other means to provide protection from the uncontrolled escape of pressurised fluids, a hose assembly energy diffusion device may be appropriate if an unacceptable residual risk remains for potential harm to people. Diffusion devices may limit inspection for damage and hose deterioration. When used – the hose assembly energy diffusion device should be able to diffuse the energy in the hydraulic fluid, to a level where fluid injection will not occur provision should be made for the safe routine inspection of the hose contained within the diffusion device. Inspection of hose assemblies should be undertaken with the sleeves removed Diffusion sleeves are required to be a loose fit over the hose to redirect the energy of any ejected fluid. Covering layers of spiral guarding may negate the effectiveness of the sleeve the sleeve should be manufactured from high abrasion, ozone, heat resistant material and should be suitably attached in underground coal mines this sleeve should be fire resistant.
  • 17. 17 MINING DESIGN GUIDELINE | MDG 41 3.7.2.10 Fire resistance All hydraulic hose assemblies should be fire resistant unless the hose is in a low risk fire area. Fire resistance hoses should be tested in accordance with AS 1180-10B or ISO 8030 and the average duration of the flaming and glowing should not exceed 30 seconds. MDG 3608 provides guidance on FRAS in underground coal mines. 6.2 Hydraulic Hose • Hydraulic hose is used in underground coal mines shall be constructed of materials that meet the following requirements. 6.2.1.1 Fire Resistance • When tested in accordance with ISO 8030, meets the requirements of ISO 6805:1994 Clause 15. 6.2.1.2 Electrical Resistance • When tested in accordance with ISO 8031,meets the requirements of ISO 6805:1994 Clause 14.
  • 18. 18 MINING DESIGN GUIDELINE | MDG 41 3.7.3.3 Effective service life In order to maximise the effective service life of hose assembly, design and installation should be carried out in accordance with SAE J1273 or ISO 17165-2. Poor design of installation standards is a predominate factor in effective service life In addition consideration should be given to: a) external cover protection that may be exposed to abrasion or impact damage b) shielding to protect hose assemblies from heat sources such as engine manifolds, exhausts, turbos etc c) accidental damage caused by: falling rock, vehicle collision, tensile load, shear load, crushing, fire d) mechanical loads – vibration, tensile, shear e) corrosive spillage, molten metal, pressure surge f) corrosion of end fittings (alkalinity / acidic water) / Coal (sulphur) g) heat generated internally and externally to the hose assembly h) refer hose life degradation (ref S-N studies) ACARP C17020 i) working fluid temperature, velocity and contamination.
  • 19. 19 MINING DESIGN GUIDELINE | MDG 41 3.7.3.4 Hose and hose assembly shelf life and storage Storage and age control can affect hose life. The following should be considered: a) A system of age control should be implemented to ensure hose assemblies are used prior to shelf life expiration. b) Hose and hose assemblies should be stored in accordance with ISO 8331. c) Storage areas should be relatively cool and dark, as well as free of dust, dirt, dampness and mildew. d) Hose and hose assemblies can be adversely affected by temperature, humidity, ozone, sunlight, ultraviolet light, oils, solvents, corrosive liquids, and fumes, acids and alkalis, insects, rodents, sharp edges and abrasive surfaces, electric or strong magnetic fields, mould and fungi, and radioactive materials. e) Storage of tested hose assemblies should be limited to two years from inspection, refer to SAE J1273 Clause 9.1.c. f) Hose assembly stored for more than two years, should be visually inspected and proof tested or follow manufacturer’s recommendations. g) Hose assemblies with hose older than five years (five years or greater post cure date) should be re-proof tested (see 3.8.7.1) and hose assemblies with hose older than eight years should be discarded unless otherwise recommended by the hose manufacturer. After successfully retesting, the hose assemblies should be clearly remarked.
  • 20. 20 MINING DESIGN GUIDELINE | MDG 41 3.7.6.1 General Hose ends should not be interchanged and should be properly matched to the hose based on proven type test result. Only select hose ends compatible with the hose for the application. The fitting and hose manufacturer’s recommendations should be strictly followed.
  • 21. 21 MINING DESIGN GUIDELINE | MDG 41 3.9.7 Operation and maintenance instructions Operation and maintenance manuals should be provided. These manuals should contain the following information categorised in appropriate sections: a) Recommended maintenance requirements to maintain the fluid system in a safe operating condition. b) Recommended inspection and tests, to check if the equipment is safe to operate. c) Identification of any hazards involved in maintaining and operating the equipment. d) Identification of all high risk areas. e) Energy isolation, dissipation and control procedures. f) Safe work procedures to carry out maintenance on the system, including setting of controls. g) Protective equipment requirements. h) Trouble shooting guide. i) Safe handling and disposal of fluids. j) Recommended spares.
  • 22. 22 MINING DESIGN GUIDELINE | MDG 41 4.1 Manufacture and assembly - of fluid power systems and components Manufacturers and assemblers of fluid power systems and components should use the design specifications provided by the designer. Clause 193 of the WHS Regulation imposes specific duties on the manufacturer of plant. The following should be considered in the manufacture and assembly of fluid power systems and components: • Specific conditions relating to the method of manufacture. • Instructions for fitting or refitting plant parts and their location on other components of the plant or their housings where errors could be made when installing the plant. • Instruction where hot or cold parts or material may create a hazard. • Specifications of material. • Schematic diagrams. • Specifications for proprietary items e.g. electric motors. • Component specifications including drawings and tolerances. • Assembly drawings. • Assembly procedures including specific tools or equipment to be used. • Manufacturing processes e.g, requirements for crimping. • Details of hazards presented by materials during manufacturing. • Safety outcomes Any alterations during the manufacturing / assembly phase of a fluid power systems is considered a design change in which designers obligations apply.
  • 23. 23 MINING DESIGN GUIDELINE | MDG 41 7.1.1 Competence All people associated with the maintenance of the fluid power system (including contractors) should be competent to safely carry out work on the fluid system. Some relevant competencies include: •MEM18052B Maintain fluid power systems for mobile plant •Minimum Bend Radius •Minimum Bend Radius AURTTA3013 Repair hydraulic systems Competence of maintenance personnel should include: a)system functional requirements and operating parameters b)troubleshooting and individual component testing c)safe energy isolation and dissipation in accordance with the mines isolation management plan d)electrical / fluid power interfaces and control circuitry e)hose management f)importance of cleanliness g)energy isolation process in particular hazardous activity isolation. Specific competence on energy isolation should be carried out on large and complex fluid power systems such as longwall roof supports.
  • 24. 24 MINING DESIGN GUIDELINE | MDG 41 7.1.4 Safe working with fluid power systems: When working with fluid power systems: • Never feel for leaks • Never vent hydraulic fluid to atmosphere unless it is safely controlled, such as into collection drums/trays or through a diffuser • Never disconnect any line that has not been de-energised and tested for de-energisation • Always apply energy isolation procedures, refer to clause 3.6. A typical model for safely performing maintenance is illustrated in the figure below:
  • 25. 25 MINING DESIGN GUIDELINE | MDG 41 7.2 Isolation and energy dissipation The mine will have an energy isolation management plan, refer to MDG 40 This plan will include: a)an energy isolation process used for the de-energisation of all energies b)an assessment process for people who need to demonstrate competence c)identified specific isolation processes for high risk activities d)emergency management e)training. All safe work methods should identify energy isolation, dissipation and verification requirements. MDG 40 offers guidance on the requirements for energy isolation management.
  • 26. 26 MINING DESIGN GUIDELINE | MDG 41 3.6.1 General In the performance of many lifecycle tasks such as installation, repair, service, component replacement, maintenance and disassembly it is imperative to have isolation and energy dissipation considered in the design of the fluid power system. Isolation valves should not be installed in the return circuit of a hydraulic system as they provide a means for pressure intensification if left closed. The design risk assessment should consider effective means of energy isolation, dissipation and verification of fluid power hazards. This should include: a) identification of all energy sources to prevent a release of energy, (such as stored fluid power, gravity, (suspended loads), springs, electrical) and / or prevent unintended activation or movement of equipment b) provision of a means to isolate all identified energy sources to prevent a possible state change. This includes purpose designed isolation devices that are lockable. c) provision of a means to safely dissipate fluid. If used as part of the isolation process a dissipation device should be a purpose-designed dissipation devices and lockable. d) provision of a system that verifies that pressure has been dissipated. (Test for dead or safe state) e) clear identification of all isolation and dissipation points f) provision of safe work methods for the use of the isolation, dissipation and verification devices. Should include removal and restoration of energy. g) information on required people competence to isolate, diffuse and verify isolation.
  • 27. 27 MINING DESIGN GUIDELINE | MDG 41 7.6 Hose assembly management 7.6.1 General A hose management plan should be developed, implemented and maintained (refer to clause 7.5 and clause 3.7.12). The hose management plan should be established and maintained in consultation with all stakeholders, including site management, maintenance and suppliers. The hose management plan should be integral with the mines maintenance system and the site specific maintenance strategies. A hose management program will reduce equipment downtime, maintain peak operating performance, and reduce the risk for personal injury and/or property damage. The hose management plan should include: • A database of the range of hose assemblies on the mine site • A maintenance schedule such that all hose assemblies are inspected at a frequency as required for their risk to safety and equipment operation, refer Work Health and Safety (Mines) Regulation 2014 Section 13 and Schedule 2. • Discarded hose assemblies or hoses with no known history (e.g. longwall, monorail, AFC/BSL hoses) not being reinstalled unless tested and certified in accordance with clause 3.7.11.1 Individual Hose assembly proof testing. If reinstalled, the hoses being cleaned and labelled in readiness for reuse. This is not intended to include the disconnection and reconnection for operational or maintenance purposes. • Hose failure mode analysis.
  • 28. 28 MINING DESIGN GUIDELINE | MDG 41 MDG41 is not a Hose & fitting standard MDG41 is not a Compliance document
  • 29. 29 MINING DESIGN GUIDELINE | MDG 41 Guideline for fluid power system safety at mines Focuses on risk management & mitigation controls to be considered, along with competency and operational guidance. MDG41 now also incorporates links to other relevant data and historical incident reporting along with exposure frequency for more meaningful Risk Assessments.