Coefficient of Thermal Expansion and their Importance.pptx
GPL - HT Network - 25.10.21.ppt
1. High Voltage (69 kV) Network Operational Review
(Demerara & Berbice Interconnected Transmission Network)
2. Introduction
Aim
To improvethe resilience of the transmissionnetwork (69 KV) of DBIS;
Objectives
Network voltage level stability issue – Reasons / control features;
Operationof generatingstations – Normal & Power failure restorationPeriod;
Level of reactive power (MVAR) and regulationwith reference;
StudyPeriod: August - September 2021
GPLlookingforwardshort term measureson priority;
Longterm programinpipeline, mainly installationof CapacitorBanks,new SCADA station;
Highercapacitygeneratorsintegrationto meet growingelectricity demand;
3. Transmission Network (69 KV)
Based on the collected information, Load flow in the HT network is ~65 MW
5. Demerara : Power Generation
Location Generation Unit Installed Capacity,
MW
Operating load,
MW
Mode of
Operation
Actual
Operation
Remark
Garden of Eden
DP # 1
#5 DA 3.0
#6 DA 4.0 3.9 0.9 pf lag
#1 DG 5.5 5.4 SD-VD SD - PF 0.93 pf lag (14.0 KV)
#2 DG 5.5 5.1 SD-VD SD - PF 0.91 pf lag (14.0 KV)
#3 DG 5.5 3.8 SD-PF KW-PF 0.83 pf lag (14.2 KV)
#4 DG 5.5 5.0 KW-PF KW-PF 0.88 pf lag (14.2 KV)
Kingston (DP # 2) #1 DG 5.5 5.3 KW-PF KW-PF 0.94 pf lag
#2 DG 5.5 5.2 SD-PF KW-PF 0.94 pf lag
#3 DG 5.5 5.3 SD-PF KW-PF 0.94 pf lag
#4 DG 5.5 5.2 KW-PF KW-PF 0.94 pf lag
Kingston (DP # 3) #1 DG 6.9 6.0 SD-PF SD-PF 0.83 pf
#2 DG 6.9 4.0 KW-PF kW - PF
#3 DG 6.9 6.85 SD-PF kW - PF 0.84 pf
#4 DG 7.8 7.6 SD-PF SD-PF 0.84 pf
#5 DG 7.8 7.6 SD-PF SD-PF 0.84 pf
Vreed-En-Hoop
(DP # 4)
#2 DG 8.7 5.7 ICM - Voltage ICM - Voltage 0.90 pf
#3 DG 8.7 5.8 ICM - Voltage ICM - Voltage 0.88 pf
Sophia 3 X CAT 2 X 1.6 3.0
Giftland DG I X 2.0
Total 108.6 90.75±2
Variation in Power factor at 13.8 KV bus w.r.t generators’ operation
6. Berbice : Power Generation
Location Generation Unit Installed Capacity Operating load, MW Remark
MW MW
Cane field #3 DA 4.0 4.0
#8 CAT 1.5 1.5
#9 CAT 1.0
#11 CAT 1.6 1.6
2 X 1.6
Onverwagt #1 CAT 1.6 2.3
#2 CAT 1.6 1.4
#12 CAT 0.8
#14 CAT 0.8
#17 CAT 1.6 1.4
Skeldon /
PPDI 5 #2 DG 2.5 2.5
#3 DG 2.5 2.5
Total 18.7 17.2
Most of the generators operate to full capacity; Total generation : 110 ± 2 MW
The mode of operation of a few generators were different from the actual defined operating procedures
- It is suggested to report variation in the mode of operation in the daily report (PPDI to GPL)
Reasons for lower power factor at DP # 3 can be reviewed
7. Transmission Network – Transformers
Substation Make Rating of
Transformer, MVA
Voltage, KV Impendence, % Status
Demerara Region
Garden of Eden (G) ABB 16.8 69 / 13.8 8.10 Damaged
Westinghouse 16.8 69 / 13.8 11.59
Westinghouse 16.8 69 / 13.8 11.59
Golden Grove Dachi 10.0 69 / 13.8 11.42
Dachi 10.0 69 / 13.8 11.18
Sophia Old ABB 16.8 69 / 13.8 8.10 Damaged
Westinghouse 16.8 69 / 13.8 11.59 OFF
ABB 16.8 69 / 13.8 8.10
New Georgetown Dachi 16.7 69 / 13.8 11.19
Dachi 16.7 69 / 13.8 11.10
Kingston (G) Sunbelt 35.0 69 / 13.8 10.66
Crompton Greeves 35.0 69 / 13.8 10.90
Vreed-en-Hoop Dachi 2 X 20.0 69 / 13.8 11.29 OFF (TR#1)
Edinburgh Dachi 10.0 69 / 13.8 11.27
Good Hope Crompton greaves 35.0 69 / 13.8 10.90
Columbia Dachi 16.7 69 / 13.8 11.12
Onverwagt Dachi 16.7 69 / 13.8 11.04
Barbice Region
Canefield (G) Dachi 16.7 69 / 13.8 11.09
No 53 Village Federal pioneer 16.7 69 / 13.8 10.90
Skeldon Dachi 16.7 69 / 13.8 11.09
Few transformers are with off load tap changers; Old transformers are being operated in fixed transformation ratio
8. 69 kV Transmission lines data analysis
− Coming 'IN' or Import + going 'OUT' or Export
TL name
Point 1 Point 2 Voltage difference Current difference
MW PF %Uunb %Iunb MW PF %Uunb %Iunb Uab Ubc Uca IA IB IC
TL-1: GOE - Golden Grove -7.78 -0.96
TL-2: Sophia - Golden Grove -3.04 -0.88 1.9 8.6 4.04 0.99 1.7 11.2 -533 -833 -740 7.1 2.3 7.7
TL-3: GOE - Golden Grove 8.03 -0.96
TL-4: New Sophia - Golden
Grove -2.94 -0.87 1.9 8.8 3.99 0.99 1.7 10.3 -624 -922 -830 7.4 2.1 6.9
TL-5: Kingston - Sophia 29.28 0.92 1.9 7.4 -27.56 -0.93 1.9 7.3 -3465 -3486 -3605 -3.4 -3.0 -3.6
TL-6: Kingston - Vreed-en-
hoop -4.92 -0.96 1.8 35.8 4.99 0.94 1.9 33.2 -100 -16 67 1.7 0.5 0.3
TL-7: Vreed-en-hoop -
Edinburgh 7.73 0.88 1.9 12.1 -7.69 -0.87 2.2 12.5 -823 -489 -520 1.1 1.5 0.6
TL-10: Sophia - New
Georgetown 12.4 0.94 2.0 7.1
TL-12: Sophia - New Sophia 3.82 0.73 1.9 19.3 -3.80 -0.73 2.0 19.7 15 42 111 -0.1 -0.1 -0.3
TL-13: Sophia - New Sophia 4.81 0.97 2.0 11.8 -5.14 -0.97 2.0 12.0 2664 2796 2713 1.5 1.3 1.1
TL-16: New Sophia - Good
Hope 11.8 0.87 2.0 15.0 -11.71 -0.87 2.3 15.0 -968 -649 -594 0.4 0.5 0.4
TL-17: Good Hope - Columbia 1.17 0.92 2.4 35.5 -1.35 -0.90 2.2 29.8 -238 -499 -313 3.2 3.3 3.8
TL-20: Columbia - Onverwagt -2.51 -0.97 2.2 35.7 2.59 1.00 1.8 39.4 521 12 247 0.2 -0.4 2.3
TL-21: Onverwagt - Canefield -1.94
9. 69 kV Transmission lines data analysis
Voltages at the transmission line ends are found to be below 65 kV, i.e. as low as 63 kV;
- Less than the standard value mentioned in the GPL electricity grid code;
Voltage drop in TL # 5, 13 are very high even though the line length is small;
Unbalance voltage for all the 69 kV transmission lines varies from 1.7% to 2.3%;
In some of the feeders (namely TL # 6, 12, 13, 17 & 20), unbalanced currents are found
varying dynamically from 10% to 80%;
All the transmission lines are loaded in the range of 1% to 40%;
- TL # 5 is loaded around 40%, and all other lines are loaded less than 25%.
International standards (e.g., EN-50160 and the IEC 1000-3-x series) give limits for the
unbalance ratio of < 2% for low voltage and medium voltage systems, and <1% for high
voltage, measured as 10 min intervals, with an instantaneous maximum of 4%.
Current unbalance should be < 5% for high voltage networks.
10. Malfunctioning of SCADA
SCADA measurements at Golden Grove end of 69 kV transmission lines, TL # 2 & 4 are not
working. The same value is being shown for 24 hours for many days.
Date
Average kW/hour
Line # 1 Line # 2 Line # 3 Line # 4
Sending end
Receiving
end
Sending end Receiving end Sending end Receiving end Sending end Receiving end
01-09-2021 No data 7.79 2.81 4.04 No data 8.03 4.54 3.99
02-09-2021 No data 7.79 4.64 4.04 No data 8.03 3.68 3.99
03-09-2021 No data 7.79 2.82 4.04 No data 8.03 2.79 3.99
04-09-2021 No data 7.79 1.73 4.04 No data 8.03 4.11 3.99
05-09-2021 No data 7.79 2.53 4.04 No data 8.03 2.51 3.99
06-09-2021 No data 7.79 3.61 4.04 No data 8.03 3.63 3.99
07-09-2021 No data 7.79 4.66 4.04 No data 8.03 2.92 3.99
08-09-2021 No data 7.79 3.76 4.04 No data 8.03 3.73 3.99
09-09-2021 No data 7.79 3.21 4.04 No data 8.03 5.12 3.99
10-09-2021 No data 7.79 3.21 4.04 No data 8.03 3.13 3.99
11-09-2021 No data 7.79 3.4 4.04 No data 8.03 2.56 3.99
12-09-2021 No data 7.79 4.1 4.04 No data 8.03 3.88 3.99
13-09-2021 No data 7.79 2.83 4.04 No data 8.03 2.85 3.99
14-09-2021 No data 7.79 3.67 4.04 No data 8.03 2.96 3.99
15-09-2021 No data 7.79 2.93 4.04 No data 8.03 4.86 3.99
16-09-2021 No data 7.79 2.99 4.04 No data 8.03 4.64 3.99
17-09-2021 No data 7.79 5.73 4.04 No data 8.03 1.92 3.99
18-09-2021 No data 7.79 1.14 4.04 No data 8.03 1.34 3.99
19-09-2021 No data 7.79 2.31 4.04 No data 8.03 2.35 3.99
11. Substation : Kingston
Installed transformers 2 X 35 MVA;
DP 2 and DP 3 interconnected;
Total power generation : 53 MW (21 + 32)
DP 3 : Generators 1/2/3 connected feeder B1F1 connected to Step-up transformer 13.8 / 69 KV;
: Generators 4/5 connected with submarine cable 69 KV
Load flow through transformers 36 – 42 MW;
Position G 1/2/3 G 4 /5
Generation end
voltage
14.07 / 14.32 /
13.95
14.03 / 14.28 /
13.91
HT Voltage
levels
66.5/68.7/67.9 66.5/68.7/67.9
Line # 2
(66.2 kV, 68.4
kV, 67.6 kV)
Line # 5
(63.5 kV, 65.7
kV, 64.8 kV)
12. Verified Energy Losses between Kingston to Sophia – Line 5
Total daily energy transmitted by L5 line : 705 MWh
Energy lost during transmission : 37.8 MWh (> 2.0 MW during peak hour)
Percentage of Energy loss : 5.4%
Substation : Kingston
14. Substation : Vreed-En-Hoop
Currently, a project was initiated to shift 20 MVA transformer from Vreed-en-hoop to Edinburgh (to
replace with the existing 10 MVA transformer)
Installed transformers 2 X 20 MVA; Operational 1 X 20 MVA;
Total Generation at Vreed-En-Hoop : 11.5 – 13.5 kW (each 5.7 – 6.7 MW)
F1 directly to transmission Edinburgh : 6.4 – 8.7 MW (at pf 0.88)
West Bank Distribution feeders 13.8 KV bus : 5.0 MW
Position G 2 G 3
Generation end voltage 14.0 / 14.2 / 13.9 13.9 / 14.2 / 13.9
HT Voltage levels (Line # 7) 66.7 / 68.89 /68.24
HT voltage at Edinburgh 65.9 / 68.49 / 67.7
Step down transformer at Edinburgh : 1 X 10 MVA
Mid Night load (19.00 – 24.00 PM) : 8.7 MW at 0.87 : 10 MVA Fully loaded
(around 108% during peak hours)
16. 13.8 kV distribution feeder data analysis
Description
Feeder-1 Feeder-2 Feeder-3 Feeder-4
%Vunb %Iunb MW %Vunb %Iunb MW %Vunb %Iunb MW %Vunb %Iunb MW
Vreed-en-hoop 1.0 10.9 3.3
Edinburgh 2.4 21.9 2.6 2.5 25.0 4.5 2.4 20.1 1.5
Good Hope 2.3 28.2 1.9 2.1 20.9 3.3 2.3 31.5 2.3 2.2 31.4 4.5
Columbia 1.9 14.5 1.8 1.7 9.3 2.2
Onverwagt 1.4 9.6 0.6 1.3 13.9 -1.2
Canefield-Corentyne
No.53 Village-Corentyne
Skeldon
Garden of Eden
Golden Grove 1.7 6.2 4.1 1.8 18.8 4.0
Kingston
Sophia upgraded
New Georgetown
• Total no. of 13.8 kV feeders = ~50
• No. of feeders where data is available : 14
• Edinburgh and Good Hope feeders have large voltage and current unbalances.
• 13.8 kV distribution feeder level voltage at 'Sophia upgraded' substation is on the lower side, i.e., 13.4 kV.
Unbalance currents in the distribution feeders are the leading cause of increased voltage unbalance at the 13.8 kV level. It is also
affecting the voltage at generating units resulting in unbalanced power.
17. End user PQ analysis – Golden Grove to Diamond
18. End user PQ analysis – GWI Pouderoyen
Use of single phase transformer phase
wise are in place for voltage balance at
end user.
Different size of single phase transformers
are installed ( 2 X 50 KVA + 1 X 75 KVA)
19. Capacitor installation at Canefield substation
Shunt Capacitor
Installation Status
Transformer Tap Position
Onverwagt S/S Canefield S/S Village 53 S/S
Number of Taps 5 13 33
Before 5 13 30/33
After 3 5 20
Capcitor
bank
Status
Date:
23/09/20
21 Time:
69 kV line voltage
OFF 7:00 66.5 68.1 67.7 66.6 68.1 67.7
ON 19:00 70.1 71.5 71.3 70.1 71.5 71.4
L21
Onverwagt Canefield L22
Canefield Village 53
20. Distribution Feeders : Load balance
Some of the 13.8 kV distribution
feeders which are having high
unbalanced currents is shown in
above table along with number of
customers connected to the line and
the load it is carrying.
It is suggested to select two/three
distribution feeders and conduct a
survey to identify the type and
quantity of consumers
like a number of households,
hospitals,
schools,
street lights,
commercial buildings,
government offices etc.
Location Feeder Connected areas
Load,
MW
% unbalance
Number of
customers
Voltage Current
Edinburgh
substation
F1 Windsor Forest, Best
Village GAB
2.50 2.4 21.9 3496
F2 Parika, Zeelugt,
Philedelhia, Le Destin,
Lookout
4.10 2.5 25.0 11849
F3 1.41 2.4 20.1
Good
Hope
substation
F1 Success, Lusignan 1.90 2.3 28.2 7736
F2 3.30 2.1 20.9
F3 Enmore factory road,
Hope SAB
2.90 2.3 31.5 9819
F4 4.00 2.2 31.4
Golden
Grove
F3 Diamond 4.04 1.8 18.8 7609
Set a target to bring down the unbalance current below 15%
By physically balancing the loads among the three phases
equally.
Identifying loads that are contributing major unbalances in
the network
If required bifurcate residential and industrial loads by
drawing a separate transmission line.
21. Suggested Measures on Priority
L5: Sophia-Kingston 69kV line: High voltage drop observed which is around 3.5 kV
and power loss of around 2 MW;
High Voltage drop in L13: Sophia-New Sophia line (2.5 KV);
High unbalance currents observed in 69kV network – L6, L17, L20
- Total load on this lines = 8.5 MW
Improving the SCADA is very essential;
- Report - transmission limits and limits violations; energy losses.
New Industrial parks to be connected with separate feeders (without domestic loads)
Distribution feeders (13.8 KV) load balance activities to be taken-up with set target (say
unbalance currents to minimise < 15%),
TERI team committed to work with GPL - distribution team to minimise power quality issues.
Installation of capacitor bank to improve voltage important
Edinburgh substation : 10 MVAr
New Sophia substation : 15 MVAr