Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Capacitor installation and re conductoring
1. BY
KHALIL Y. A.
POWER DISTRIBUTION LOSS
CAPACITOR INSTALLATION/RE-CONDUCTORING
AUGUST, 2019
2. Objectives
▰At the end of this session, participants should be able
to;
▰ 1) Explain and illustrate the use of NEPLAN to simulate
insertion of capacitor to reduce losses in a model of
distribution network.
▰ 2) Simulate the effect of re-conductoring to reduce losses
▰ 3) Use the above concepts in their networks for load
reduction actions/investment schedules
2
3. Learning methods
Power point presentation
Open Discussions –
Share experiences
Exercises – Individuals/Groups
Case Studies/simulations
4. 4
Recap –
10 Common Causes of
Technical Losses
1. Location of the source and MV/LV substations far from the centre of gravity of the
load they supply
2. Influence zone of grid substations and MV/LV substations is too wide
3. Insufficient number of grid substations and MV/LV substations
4. Transformers for grid substations and MV/LV substations undersized or oversized
5. MV and LV lines are overloaded
6. MV and LV lines are too long
7. Use of inappropriate sections
8. No compensation of reactive current
9. Unequal distribution of loads on the phases
10.N/O points are selected in a suboptimal way
5. 5
Recap(2) –
10 Key Actions to reduce
Technical losses
1. Installation of capacitor banks
2. Replacement of conductors
3. Restructuring of the MV networks
4. Additional substations (grid S/S or distribution S/S)
5. Use of high efficiency transformers
6. Phase rebalancing on LV feeders
7. Optimisation of N/O points
8. Demand Side Management
9. Load Management
10.Optimal network planning
11.Optimal tariff allocation for reactive consumption
7. Page 7
Project
Highlights
Connection of Capacitors
• Capacitors can be classified as
Series or Parallel according to the
type of Connection they have.
• Series Capacitors are connected in
series with lines, to compensate for
inductive reactance.
• Shunt Capacitors are connected in
parallel with lines to compensate for
reactive power or current required
by an inductive load.
8. Page 8
Project
Highlights
Objectives of connecting capacitor
• Capacitors are used for the
following purposes:
– Reduce losses (kW – kWh).
– Improve power factor.
– Improve voltage profile.
– Reduce loading of distribution feeders.
10. Page 10
Project
Highlights
Series and shunt compensation
• Consider a simple 33 kV radial line
transmitting power by an overhead
system to a lagging power factor
load.
• The sending-and receiving-end
conditions will be examined for each of
three cases;
– Without capacitor
– With shunt capacitor
– With series capacitor
16. Page 16
Project
Highlights
SUMMARY OF RESULTS
• The main conclusions are:
• (i) Both shunt and series capacitors
reduce the voltage drop, and also
the kVAr demand at source of
supply
• (ii) Shunt capacitors reduce the line
power losses by reducing the
receiving-end current.
31. How has the capacitor bank
helped to reduce losses?
Page 31
Compare the
results
32. 2) Replacement (Upgrade) of
conductors
▰ By using the higher the cross-section
area of conductor / cables the losses
will be lower but the same time cost
will be high so by forecasting the
future load an optimum balance
between investment cost and
network losses should be
maintained.
▰ R = ꝭ*L
CSA
33. Page 33
Project
Highlights
2) Replacement of conductors
1. Create a new variant (remp_conduc)
2. Change the conductor type for line 1-2
(AGS117)
3. Launch a load balancing and compare
losses
2) EXERCISE 6: Replacement of conductors
39. REFERENCES
• Power Loss Reduction Technologies presentation; Power
System Analysis Tool (PSAT), DNV KEMA Academy,
2013
• NAPTIN training presentation on Power loss
Management, NAPTIN 2018
• Power Loss Calculation Training of Trainers (ToT)
presentations, June 2019, Daniel D’Hoop, Gopa-
Intec/GIZ @ VRA Academy, Akuse, Ghana.
• Capacitor sizing and Location in Distribution Network, by
Dr Gers M. Juan, 2013, Gers USA consulting Engineers.
• A Turnaround Story! ON THE AGGREGATE
TECHNICAL AND COMMERCIAL (AT&C) LOSS
REDUCTION FROM 53% TO 15% IN DELHI AREA
ACHIEVED IN 8 YEARS BY NDPL (NORTH DELHI
POWER LIMITED) By Ajai Nirula .
• Reducing Technical and Non-Technical losses in the
Power sector,
Background Paper for the World Bank Group Energy Sec
tor Strategy, July 2009