SlideShare a Scribd company logo
1 of 40
Download to read offline
BY
KHALIL Y. A.
POWER DISTRIBUTION LOSS
CAPACITOR INSTALLATION/RE-CONDUCTORING
AUGUST, 2019
Objectives
▰At the end of this session, participants should be able
to;
▰ 1) Explain and illustrate the use of NEPLAN to simulate
insertion of capacitor to reduce losses in a model of
distribution network.
▰ 2) Simulate the effect of re-conductoring to reduce losses
▰ 3) Use the above concepts in their networks for load
reduction actions/investment schedules
2
Learning methods
Power point presentation
Open Discussions –
Share experiences
Exercises – Individuals/Groups
Case Studies/simulations
4
Recap –
10 Common Causes of
Technical Losses
1. Location of the source and MV/LV substations far from the centre of gravity of the
load they supply
2. Influence zone of grid substations and MV/LV substations is too wide
3. Insufficient number of grid substations and MV/LV substations
4. Transformers for grid substations and MV/LV substations undersized or oversized
5. MV and LV lines are overloaded
6. MV and LV lines are too long
7. Use of inappropriate sections
8. No compensation of reactive current
9. Unequal distribution of loads on the phases
10.N/O points are selected in a suboptimal way
5
Recap(2) –
10 Key Actions to reduce
Technical losses
1. Installation of capacitor banks
2. Replacement of conductors
3. Restructuring of the MV networks
4. Additional substations (grid S/S or distribution S/S)
5. Use of high efficiency transformers
6. Phase rebalancing on LV feeders
7. Optimisation of N/O points
8. Demand Side Management
9. Load Management
10.Optimal network planning
11.Optimal tariff allocation for reactive consumption
Page 6
Project
Highlights
1. Effects of Installation of capacitor banks
2. Effects of Replacement (upgrade) of conductors
Introduction
Page 7
Project
Highlights
Connection of Capacitors
• Capacitors can be classified as
Series or Parallel according to the
type of Connection they have.
• Series Capacitors are connected in
series with lines, to compensate for
inductive reactance.
• Shunt Capacitors are connected in
parallel with lines to compensate for
reactive power or current required
by an inductive load.
Page 8
Project
Highlights
Objectives of connecting capacitor
• Capacitors are used for the
following purposes:
– Reduce losses (kW – kWh).
– Improve power factor.
– Improve voltage profile.
– Reduce loading of distribution feeders.
Page 9
Project
Highlights
Series and shunt compensation
Page 10
Project
Highlights
Series and shunt compensation
• Consider a simple 33 kV radial line
transmitting power by an overhead
system to a lagging power factor
load.
• The sending-and receiving-end
conditions will be examined for each of
three cases;
– Without capacitor
– With shunt capacitor
– With series capacitor
Page 11
Project
Highlights
CASE A
Page 12
Project
Highlights
CASE A (2)
Page 13
Project
Highlights
CASE B
Page 14
Project
Highlights
CASE B (2)
Page 15
Project
Highlights
CASE C
Page 16
Project
Highlights
SUMMARY OF RESULTS
• The main conclusions are:
• (i) Both shunt and series capacitors
reduce the voltage drop, and also
the kVAr demand at source of
supply
• (ii) Shunt capacitors reduce the line
power losses by reducing the
receiving-end current.
Page 17
Project
Highlights
SUMMARY OF RESULTS (2)
Page 18
Project
Highlights
TABLE OF RESULTS
Page 19
Project
Highlights
Page 20
Project
Highlights
Methods of locating and sizing capacitor
• By Feeder Modelling
• By Inspection
• By Using Software
Page 21
Project
Highlights
Re-open project network 1
Page 22
Project
Highlights
Reopen project network 1
Page 23
Project
Highlights
OPEN THE MODELLED NETWORK IN
NEPLAN
• Highlighted Bus with problemNetwork/Area/Zone PLosses
kW
QLosses
kVAr
PLoad
kW
QLoad
kVAr
PGen
kW
QGen
kVAr
PImport
kW
QImport
kVAr
PTransformerLosses kW QTransformerLosses kVAr IImport A PLineLosses kW VRegmaxHT
%
VRegminHT
%
QLineLosses
kVAr
Network 425.4 545 5000 0 5425.4 545 5425.4 545 42.5 422.6 0 382.9 0 0 122.4
Default Area 425.4 545 5000 0 5425.4 545 0 0 42.5 422.6 0 382.9 0 0 122.4
Page 24
Project
Highlights
Bus with problem corrected with Capacitor
installed
Network/Area/Zone PLosses
kW
QLosses
kVAr
PLoad
kW
QLoad
kVAr
PGen
kW
QGen
kVAr
PImport
kW
QImport
kVAr
PTransformerLosses kW QTransformerLosses kVAr IImport A PLineLosses kW VRegmaxHT
%
VRegminHT
%
QLineLosses
kVAr
Network 445.2 570.5 5000 0 5445.2 -1259.7 5445.2 -1259.7 44.6 444 0 400.6 0 0 126.5
Default Area 445.2 570.5 5000 0 5445.2 -1259.7 0 0 44.6 444 0 400.6 0 0 126.5
Page 25
Project
Highlights
Create a new subvariant
2
1
Page 26
Project
Highlights
Create a new subvariant
Page 27
Project
Highlights
Create a new subvariant
1
2
Page 28
Project
Highlights
1) EXERCISE 5: Insert a capacitor bank
1
2
3
Page 29
Project
Highlights
1) Insert a capacitor bank
1
Relier le condensateur
au bus
2
Page 30
Project
Highlights
1) Insert a capacitor bank
Launch Loadflow
and compare the
results
How has the capacitor bank
helped to reduce losses?
Page 31
Compare the
results
2) Replacement (Upgrade) of
conductors
▰ By using the higher the cross-section
area of conductor / cables the losses
will be lower but the same time cost
will be high so by forecasting the
future load an optimum balance
between investment cost and
network losses should be
maintained.
▰ R = ꝭ*L
CSA
Page 33
Project
Highlights
2) Replacement of conductors
1. Create a new variant (remp_conduc)
2. Change the conductor type for line 1-2
(AGS117)
3. Launch a load balancing and compare
losses
2) EXERCISE 6: Replacement of conductors
Page 34
Project
Highlights
2) Replacement of conductors
Page 35
Project
Highlights
OPEN THE MODELLED NETWORK IN
NEPLAN
• Highlighted Bus with problem with conductor of – ACSR
ANT (190A rating)Network/Area/Zone PLosses
kW
QLosses
kVAr
PLoad
kW
QLoad
kVAr
PGen
kW
QGen
kVAr
PImport
kW
QImport
kVAr
PTransformerLosses kW QTransformerLosses kVAr IImport A PLineLosses kW VRegmaxHT
%
VRegminHT
%
QLineLosses
kVAr
Network 425.4 545 5000 0 5425.4 545 5425.4 545 42.5 422.6 0 382.9 0 0 122.4
Default Area 425.4 545 5000 0 5425.4 545 0 0 42.5 422.6 0 382.9 0 0 122.4
Page 36
Project
Highlights
Replacement of conductor
• A conductor with 190A replaced with another
AGS (291A rating), Capacitor isolated, the
result converged.
Network/Area/Zone PLosses
kW
QLosses
kVAr
PLoad
kW
QLoad kVAr PGen
kW
QGen
kVAr
PImport
kW
QImport
kVAr
PTransformerLosses
kW
QTransformerLosses
kVAr
IImport A PLineLosses kW VRegmaxHT
%
VRegminHT
%
QLineLosses
kVAr
Network 239.2 493.2 5000 0 5239.2 493.2 5239.2 493.2 39.6 393.6 0 199.6 0 0 99.5
Default Area 239.2 493.2 5000 0 5239.2 493.2 0 0 39.6 393.6 0 199.6 0 0 99.5
When does it make sense to
replace conductors (from an
economic point of view?
Page 37
Compare the
results
Questions…
Reactions
Personal experiences
38
REFERENCES
• Power Loss Reduction Technologies presentation; Power
System Analysis Tool (PSAT), DNV KEMA Academy,
2013
• NAPTIN training presentation on Power loss
Management, NAPTIN 2018
• Power Loss Calculation Training of Trainers (ToT)
presentations, June 2019, Daniel D’Hoop, Gopa-
Intec/GIZ @ VRA Academy, Akuse, Ghana.
• Capacitor sizing and Location in Distribution Network, by
Dr Gers M. Juan, 2013, Gers USA consulting Engineers.
• A Turnaround Story! ON THE AGGREGATE
TECHNICAL AND COMMERCIAL (AT&C) LOSS
REDUCTION FROM 53% TO 15% IN DELHI AREA
ACHIEVED IN 8 YEARS BY NDPL (NORTH DELHI
POWER LIMITED) By Ajai Nirula .
• Reducing Technical and Non-Technical losses in the
Power sector,
Background Paper for the World Bank Group Energy Sec
tor Strategy, July 2009
40
THANKS FOR LISTENING

More Related Content

What's hot

Power quality improvement of distributed generation integrated ne
Power quality improvement of distributed generation integrated nePower quality improvement of distributed generation integrated ne
Power quality improvement of distributed generation integrated neNagaraj Madival
 
Flexibility of Power System (Sources of flexibility & flexibility markets)
Flexibility of Power System (Sources of flexibility & flexibility markets)Flexibility of Power System (Sources of flexibility & flexibility markets)
Flexibility of Power System (Sources of flexibility & flexibility markets)Bilal Amjad
 
Webinar - Distributed and Renewable Power Generation
Webinar - Distributed and Renewable Power GenerationWebinar - Distributed and Renewable Power Generation
Webinar - Distributed and Renewable Power GenerationWPICPE
 
Renewable energy and grid integration energy transition
Renewable energy and grid integration   energy transitionRenewable energy and grid integration   energy transition
Renewable energy and grid integration energy transitionNarinporn Malasri
 
Engage with...Network Rail
Engage with...Network RailEngage with...Network Rail
Engage with...Network RailKTN
 
Renewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectRenewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectPartha Deb
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)IJERD Editor
 
Power Distribution Overview
Power Distribution OverviewPower Distribution Overview
Power Distribution OverviewHIMADRI BANERJI
 
Energy Storage | Fuel Security , Presented at Energy Institute, London
Energy Storage | Fuel Security , Presented at Energy Institute, LondonEnergy Storage | Fuel Security , Presented at Energy Institute, London
Energy Storage | Fuel Security , Presented at Energy Institute, LondonRebecca Markillie
 
Impacts of Distributed Generation on Power Quality
Impacts of Distributed Generation on Power QualityImpacts of Distributed Generation on Power Quality
Impacts of Distributed Generation on Power QualityParth Patel
 
Integration of Renewable Energy Sources
Integration of Renewable Energy SourcesIntegration of Renewable Energy Sources
Integration of Renewable Energy SourcesSandeep Kaushal
 
Distributed generation placement
Distributed generation placementDistributed generation placement
Distributed generation placementreza shahbazi
 
Power Grid and development in India
Power Grid and development in IndiaPower Grid and development in India
Power Grid and development in IndiaSandipan Chakraborty
 
Photovoltaic Grid Parity Monitor for Residential Consumers - Issue 3b
Photovoltaic Grid Parity Monitor for Residential Consumers - Issue 3bPhotovoltaic Grid Parity Monitor for Residential Consumers - Issue 3b
Photovoltaic Grid Parity Monitor for Residential Consumers - Issue 3bLeonardo ENERGY
 
Power distribution, operation and maintenance of comilla palli bidyut samity 1
Power distribution, operation and maintenance of comilla palli bidyut samity 1Power distribution, operation and maintenance of comilla palli bidyut samity 1
Power distribution, operation and maintenance of comilla palli bidyut samity 1Kawsar Ahmed
 
Energy Management and the Evolution of Intelligent Motor Control and Drives @...
Energy Management and the Evolution of Intelligent Motor Control and Drives @...Energy Management and the Evolution of Intelligent Motor Control and Drives @...
Energy Management and the Evolution of Intelligent Motor Control and Drives @...ARC Advisory Group
 
System Level Data and Technology Requirements of REV
System Level Data and Technology Requirements of REV System Level Data and Technology Requirements of REV
System Level Data and Technology Requirements of REV Smarter Grid Solutions
 

What's hot (20)

Power quality improvement of distributed generation integrated ne
Power quality improvement of distributed generation integrated nePower quality improvement of distributed generation integrated ne
Power quality improvement of distributed generation integrated ne
 
Flexibility of Power System (Sources of flexibility & flexibility markets)
Flexibility of Power System (Sources of flexibility & flexibility markets)Flexibility of Power System (Sources of flexibility & flexibility markets)
Flexibility of Power System (Sources of flexibility & flexibility markets)
 
Webinar - Distributed and Renewable Power Generation
Webinar - Distributed and Renewable Power GenerationWebinar - Distributed and Renewable Power Generation
Webinar - Distributed and Renewable Power Generation
 
Renewable energy and grid integration energy transition
Renewable energy and grid integration   energy transitionRenewable energy and grid integration   energy transition
Renewable energy and grid integration energy transition
 
Engage with...Network Rail
Engage with...Network RailEngage with...Network Rail
Engage with...Network Rail
 
Renewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectRenewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot Project
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 
Power Distribution Overview
Power Distribution OverviewPower Distribution Overview
Power Distribution Overview
 
Energy Storage | Fuel Security , Presented at Energy Institute, London
Energy Storage | Fuel Security , Presented at Energy Institute, LondonEnergy Storage | Fuel Security , Presented at Energy Institute, London
Energy Storage | Fuel Security , Presented at Energy Institute, London
 
Impacts of Distributed Generation on Power Quality
Impacts of Distributed Generation on Power QualityImpacts of Distributed Generation on Power Quality
Impacts of Distributed Generation on Power Quality
 
Integration of Renewable Energy Sources
Integration of Renewable Energy SourcesIntegration of Renewable Energy Sources
Integration of Renewable Energy Sources
 
Distributed generation placement
Distributed generation placementDistributed generation placement
Distributed generation placement
 
Power Grid and development in India
Power Grid and development in IndiaPower Grid and development in India
Power Grid and development in India
 
Blackout
BlackoutBlackout
Blackout
 
Photovoltaic Grid Parity Monitor for Residential Consumers - Issue 3b
Photovoltaic Grid Parity Monitor for Residential Consumers - Issue 3bPhotovoltaic Grid Parity Monitor for Residential Consumers - Issue 3b
Photovoltaic Grid Parity Monitor for Residential Consumers - Issue 3b
 
Power distribution, operation and maintenance of comilla palli bidyut samity 1
Power distribution, operation and maintenance of comilla palli bidyut samity 1Power distribution, operation and maintenance of comilla palli bidyut samity 1
Power distribution, operation and maintenance of comilla palli bidyut samity 1
 
Energy Management and the Evolution of Intelligent Motor Control and Drives @...
Energy Management and the Evolution of Intelligent Motor Control and Drives @...Energy Management and the Evolution of Intelligent Motor Control and Drives @...
Energy Management and the Evolution of Intelligent Motor Control and Drives @...
 
System Level Data and Technology Requirements of REV
System Level Data and Technology Requirements of REV System Level Data and Technology Requirements of REV
System Level Data and Technology Requirements of REV
 
Availability Based Tariff and UI charges
Availability Based Tariff and UI chargesAvailability Based Tariff and UI charges
Availability Based Tariff and UI charges
 
Smart grid system using fpga
Smart grid system using fpgaSmart grid system using fpga
Smart grid system using fpga
 

Similar to Capacitor installation and re conductoring

Power Factor correction of Toitskraal 11kV feeder
Power Factor correction of Toitskraal 11kV feederPower Factor correction of Toitskraal 11kV feeder
Power Factor correction of Toitskraal 11kV feederKruger Greyvenstein
 
Morelia workshop presentation william ross
Morelia workshop presentation william rossMorelia workshop presentation william ross
Morelia workshop presentation william rossBenito Ortiz Bejar
 
POWER ELECTRONIC IN POWER SYSTEM KELAS.pptx
POWER ELECTRONIC IN POWER SYSTEM KELAS.pptxPOWER ELECTRONIC IN POWER SYSTEM KELAS.pptx
POWER ELECTRONIC IN POWER SYSTEM KELAS.pptxmasterunedo
 
Operational ANM Schmes in the UK and America
Operational ANM Schmes in the UK and AmericaOperational ANM Schmes in the UK and America
Operational ANM Schmes in the UK and AmericaSmarter Grid Solutions
 
Power Factor.ppt
Power Factor.pptPower Factor.ppt
Power Factor.pptVidya Sagar
 
20170727 angledc project, mvdc
20170727 angledc project, mvdc20170727 angledc project, mvdc
20170727 angledc project, mvdcChao Long
 
IRJET- A Novel Modified Switched Capacitor Nine Level Inverter Topology with ...
IRJET- A Novel Modified Switched Capacitor Nine Level Inverter Topology with ...IRJET- A Novel Modified Switched Capacitor Nine Level Inverter Topology with ...
IRJET- A Novel Modified Switched Capacitor Nine Level Inverter Topology with ...IRJET Journal
 
FCG & HCV - Performance analysis
FCG & HCV - Performance analysisFCG & HCV - Performance analysis
FCG & HCV - Performance analysisPranav Contractor
 
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...IJMERJOURNAL
 
POWER QUALITY IMPROVEMENT OF DISTRIBUTION GRID USING ULTRA CAPACITOR INTEGRAT...
POWER QUALITY IMPROVEMENT OF DISTRIBUTION GRID USING ULTRA CAPACITOR INTEGRAT...POWER QUALITY IMPROVEMENT OF DISTRIBUTION GRID USING ULTRA CAPACITOR INTEGRAT...
POWER QUALITY IMPROVEMENT OF DISTRIBUTION GRID USING ULTRA CAPACITOR INTEGRAT...IRJET Journal
 
Solving Energy Storage Challenges Offshore | Offshore Europe 2017
Solving Energy Storage Challenges Offshore | Offshore Europe 2017Solving Energy Storage Challenges Offshore | Offshore Europe 2017
Solving Energy Storage Challenges Offshore | Offshore Europe 2017Parker Hannifin Corporation
 
Ph.D. Defence on "High power medium voltage dc/dc converter technology for D...
 Ph.D. Defence on "High power medium voltage dc/dc converter technology for D... Ph.D. Defence on "High power medium voltage dc/dc converter technology for D...
Ph.D. Defence on "High power medium voltage dc/dc converter technology for D...CatalinGabrielDincan
 
Analysis for underground cable system, lakeside pokhara
Analysis for underground cable system, lakeside pokharaAnalysis for underground cable system, lakeside pokhara
Analysis for underground cable system, lakeside pokharaBishal Rimal
 
Dual-Active-Bridge Converter for Bi-Directional PV Micro Inverter Application...
Dual-Active-Bridge Converter for Bi-Directional PV Micro Inverter Application...Dual-Active-Bridge Converter for Bi-Directional PV Micro Inverter Application...
Dual-Active-Bridge Converter for Bi-Directional PV Micro Inverter Application...IRJET Journal
 
Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power
Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable PowerFeasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power
Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable PowerClean Energy Canada
 
Enterprise Europe Network | STORY CAES Demo | David Surplus
Enterprise Europe Network | STORY CAES Demo | David SurplusEnterprise Europe Network | STORY CAES Demo | David Surplus
Enterprise Europe Network | STORY CAES Demo | David SurplusInvest Northern Ireland
 
Final report of 220kv gss working model
Final report of 220kv gss working modelFinal report of 220kv gss working model
Final report of 220kv gss working modelgiriraj bairwa
 

Similar to Capacitor installation and re conductoring (20)

Power Factor correction of Toitskraal 11kV feeder
Power Factor correction of Toitskraal 11kV feederPower Factor correction of Toitskraal 11kV feeder
Power Factor correction of Toitskraal 11kV feeder
 
Morelia workshop presentation william ross
Morelia workshop presentation william rossMorelia workshop presentation william ross
Morelia workshop presentation william ross
 
POWER ELECTRONIC IN POWER SYSTEM KELAS.pptx
POWER ELECTRONIC IN POWER SYSTEM KELAS.pptxPOWER ELECTRONIC IN POWER SYSTEM KELAS.pptx
POWER ELECTRONIC IN POWER SYSTEM KELAS.pptx
 
Operational ANM Schmes in the UK and America
Operational ANM Schmes in the UK and AmericaOperational ANM Schmes in the UK and America
Operational ANM Schmes in the UK and America
 
Power Factor.ppt
Power Factor.pptPower Factor.ppt
Power Factor.ppt
 
powerfactor.pdf
powerfactor.pdfpowerfactor.pdf
powerfactor.pdf
 
Ssfcl
SsfclSsfcl
Ssfcl
 
20170727 angledc project, mvdc
20170727 angledc project, mvdc20170727 angledc project, mvdc
20170727 angledc project, mvdc
 
IRJET- A Novel Modified Switched Capacitor Nine Level Inverter Topology with ...
IRJET- A Novel Modified Switched Capacitor Nine Level Inverter Topology with ...IRJET- A Novel Modified Switched Capacitor Nine Level Inverter Topology with ...
IRJET- A Novel Modified Switched Capacitor Nine Level Inverter Topology with ...
 
FCG & HCV - Performance analysis
FCG & HCV - Performance analysisFCG & HCV - Performance analysis
FCG & HCV - Performance analysis
 
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
Voltage Profile Improvement using Switched Capacitors: Case of Single Wire Ea...
 
POWER QUALITY IMPROVEMENT OF DISTRIBUTION GRID USING ULTRA CAPACITOR INTEGRAT...
POWER QUALITY IMPROVEMENT OF DISTRIBUTION GRID USING ULTRA CAPACITOR INTEGRAT...POWER QUALITY IMPROVEMENT OF DISTRIBUTION GRID USING ULTRA CAPACITOR INTEGRAT...
POWER QUALITY IMPROVEMENT OF DISTRIBUTION GRID USING ULTRA CAPACITOR INTEGRAT...
 
P1111143901
P1111143901P1111143901
P1111143901
 
Solving Energy Storage Challenges Offshore | Offshore Europe 2017
Solving Energy Storage Challenges Offshore | Offshore Europe 2017Solving Energy Storage Challenges Offshore | Offshore Europe 2017
Solving Energy Storage Challenges Offshore | Offshore Europe 2017
 
Ph.D. Defence on "High power medium voltage dc/dc converter technology for D...
 Ph.D. Defence on "High power medium voltage dc/dc converter technology for D... Ph.D. Defence on "High power medium voltage dc/dc converter technology for D...
Ph.D. Defence on "High power medium voltage dc/dc converter technology for D...
 
Analysis for underground cable system, lakeside pokhara
Analysis for underground cable system, lakeside pokharaAnalysis for underground cable system, lakeside pokhara
Analysis for underground cable system, lakeside pokhara
 
Dual-Active-Bridge Converter for Bi-Directional PV Micro Inverter Application...
Dual-Active-Bridge Converter for Bi-Directional PV Micro Inverter Application...Dual-Active-Bridge Converter for Bi-Directional PV Micro Inverter Application...
Dual-Active-Bridge Converter for Bi-Directional PV Micro Inverter Application...
 
Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power
Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable PowerFeasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power
Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power
 
Enterprise Europe Network | STORY CAES Demo | David Surplus
Enterprise Europe Network | STORY CAES Demo | David SurplusEnterprise Europe Network | STORY CAES Demo | David Surplus
Enterprise Europe Network | STORY CAES Demo | David Surplus
 
Final report of 220kv gss working model
Final report of 220kv gss working modelFinal report of 220kv gss working model
Final report of 220kv gss working model
 

Recently uploaded

Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...gurkirankumar98700
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024The Digital Insurer
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 

Recently uploaded (20)

Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 

Capacitor installation and re conductoring

  • 1. BY KHALIL Y. A. POWER DISTRIBUTION LOSS CAPACITOR INSTALLATION/RE-CONDUCTORING AUGUST, 2019
  • 2. Objectives ▰At the end of this session, participants should be able to; ▰ 1) Explain and illustrate the use of NEPLAN to simulate insertion of capacitor to reduce losses in a model of distribution network. ▰ 2) Simulate the effect of re-conductoring to reduce losses ▰ 3) Use the above concepts in their networks for load reduction actions/investment schedules 2
  • 3. Learning methods Power point presentation Open Discussions – Share experiences Exercises – Individuals/Groups Case Studies/simulations
  • 4. 4 Recap – 10 Common Causes of Technical Losses 1. Location of the source and MV/LV substations far from the centre of gravity of the load they supply 2. Influence zone of grid substations and MV/LV substations is too wide 3. Insufficient number of grid substations and MV/LV substations 4. Transformers for grid substations and MV/LV substations undersized or oversized 5. MV and LV lines are overloaded 6. MV and LV lines are too long 7. Use of inappropriate sections 8. No compensation of reactive current 9. Unequal distribution of loads on the phases 10.N/O points are selected in a suboptimal way
  • 5. 5 Recap(2) – 10 Key Actions to reduce Technical losses 1. Installation of capacitor banks 2. Replacement of conductors 3. Restructuring of the MV networks 4. Additional substations (grid S/S or distribution S/S) 5. Use of high efficiency transformers 6. Phase rebalancing on LV feeders 7. Optimisation of N/O points 8. Demand Side Management 9. Load Management 10.Optimal network planning 11.Optimal tariff allocation for reactive consumption
  • 6. Page 6 Project Highlights 1. Effects of Installation of capacitor banks 2. Effects of Replacement (upgrade) of conductors Introduction
  • 7. Page 7 Project Highlights Connection of Capacitors • Capacitors can be classified as Series or Parallel according to the type of Connection they have. • Series Capacitors are connected in series with lines, to compensate for inductive reactance. • Shunt Capacitors are connected in parallel with lines to compensate for reactive power or current required by an inductive load.
  • 8. Page 8 Project Highlights Objectives of connecting capacitor • Capacitors are used for the following purposes: – Reduce losses (kW – kWh). – Improve power factor. – Improve voltage profile. – Reduce loading of distribution feeders.
  • 10. Page 10 Project Highlights Series and shunt compensation • Consider a simple 33 kV radial line transmitting power by an overhead system to a lagging power factor load. • The sending-and receiving-end conditions will be examined for each of three cases; – Without capacitor – With shunt capacitor – With series capacitor
  • 16. Page 16 Project Highlights SUMMARY OF RESULTS • The main conclusions are: • (i) Both shunt and series capacitors reduce the voltage drop, and also the kVAr demand at source of supply • (ii) Shunt capacitors reduce the line power losses by reducing the receiving-end current.
  • 20. Page 20 Project Highlights Methods of locating and sizing capacitor • By Feeder Modelling • By Inspection • By Using Software
  • 23. Page 23 Project Highlights OPEN THE MODELLED NETWORK IN NEPLAN • Highlighted Bus with problemNetwork/Area/Zone PLosses kW QLosses kVAr PLoad kW QLoad kVAr PGen kW QGen kVAr PImport kW QImport kVAr PTransformerLosses kW QTransformerLosses kVAr IImport A PLineLosses kW VRegmaxHT % VRegminHT % QLineLosses kVAr Network 425.4 545 5000 0 5425.4 545 5425.4 545 42.5 422.6 0 382.9 0 0 122.4 Default Area 425.4 545 5000 0 5425.4 545 0 0 42.5 422.6 0 382.9 0 0 122.4
  • 24. Page 24 Project Highlights Bus with problem corrected with Capacitor installed Network/Area/Zone PLosses kW QLosses kVAr PLoad kW QLoad kVAr PGen kW QGen kVAr PImport kW QImport kVAr PTransformerLosses kW QTransformerLosses kVAr IImport A PLineLosses kW VRegmaxHT % VRegminHT % QLineLosses kVAr Network 445.2 570.5 5000 0 5445.2 -1259.7 5445.2 -1259.7 44.6 444 0 400.6 0 0 126.5 Default Area 445.2 570.5 5000 0 5445.2 -1259.7 0 0 44.6 444 0 400.6 0 0 126.5
  • 28. Page 28 Project Highlights 1) EXERCISE 5: Insert a capacitor bank 1 2 3
  • 29. Page 29 Project Highlights 1) Insert a capacitor bank 1 Relier le condensateur au bus 2
  • 30. Page 30 Project Highlights 1) Insert a capacitor bank Launch Loadflow and compare the results
  • 31. How has the capacitor bank helped to reduce losses? Page 31 Compare the results
  • 32. 2) Replacement (Upgrade) of conductors ▰ By using the higher the cross-section area of conductor / cables the losses will be lower but the same time cost will be high so by forecasting the future load an optimum balance between investment cost and network losses should be maintained. ▰ R = ꝭ*L CSA
  • 33. Page 33 Project Highlights 2) Replacement of conductors 1. Create a new variant (remp_conduc) 2. Change the conductor type for line 1-2 (AGS117) 3. Launch a load balancing and compare losses 2) EXERCISE 6: Replacement of conductors
  • 35. Page 35 Project Highlights OPEN THE MODELLED NETWORK IN NEPLAN • Highlighted Bus with problem with conductor of – ACSR ANT (190A rating)Network/Area/Zone PLosses kW QLosses kVAr PLoad kW QLoad kVAr PGen kW QGen kVAr PImport kW QImport kVAr PTransformerLosses kW QTransformerLosses kVAr IImport A PLineLosses kW VRegmaxHT % VRegminHT % QLineLosses kVAr Network 425.4 545 5000 0 5425.4 545 5425.4 545 42.5 422.6 0 382.9 0 0 122.4 Default Area 425.4 545 5000 0 5425.4 545 0 0 42.5 422.6 0 382.9 0 0 122.4
  • 36. Page 36 Project Highlights Replacement of conductor • A conductor with 190A replaced with another AGS (291A rating), Capacitor isolated, the result converged. Network/Area/Zone PLosses kW QLosses kVAr PLoad kW QLoad kVAr PGen kW QGen kVAr PImport kW QImport kVAr PTransformerLosses kW QTransformerLosses kVAr IImport A PLineLosses kW VRegmaxHT % VRegminHT % QLineLosses kVAr Network 239.2 493.2 5000 0 5239.2 493.2 5239.2 493.2 39.6 393.6 0 199.6 0 0 99.5 Default Area 239.2 493.2 5000 0 5239.2 493.2 0 0 39.6 393.6 0 199.6 0 0 99.5
  • 37. When does it make sense to replace conductors (from an economic point of view? Page 37 Compare the results
  • 39. REFERENCES • Power Loss Reduction Technologies presentation; Power System Analysis Tool (PSAT), DNV KEMA Academy, 2013 • NAPTIN training presentation on Power loss Management, NAPTIN 2018 • Power Loss Calculation Training of Trainers (ToT) presentations, June 2019, Daniel D’Hoop, Gopa- Intec/GIZ @ VRA Academy, Akuse, Ghana. • Capacitor sizing and Location in Distribution Network, by Dr Gers M. Juan, 2013, Gers USA consulting Engineers. • A Turnaround Story! ON THE AGGREGATE TECHNICAL AND COMMERCIAL (AT&C) LOSS REDUCTION FROM 53% TO 15% IN DELHI AREA ACHIEVED IN 8 YEARS BY NDPL (NORTH DELHI POWER LIMITED) By Ajai Nirula . • Reducing Technical and Non-Technical losses in the Power sector, Background Paper for the World Bank Group Energy Sec tor Strategy, July 2009