CPUC Utilities Safety and Reliability Branch 1
General Orders 95, 128, & 165
Rules for Construction and Maintenance of
Overhead and Underground Electric
Supply and Communication Systems
CPUC Utilities Safety and Reliability Branch 2
Scope of Class
• Provide general
knowledge of the GOs
• Provide details of
common infractions
CPUC Utilities Safety and Reliability Branch 3
Utilities Safety and Reliability Branch
• Engineers in LA, SF and
Sacramento
• Overhead/Under-ground
electric lines.
• Propane/natural gas
pipelines -- utilities,
master-meters
• Investigate incidents-On
Call
CPUC Utilities Safety and Reliability Branch 4
Utilities Safety and Reliability Branch
• Jurisdiction
– Investor Owned
– Co-op
– CATV
– Municipal (Polk vs. City of Los Angeles)
CPUC Utilities Safety and Reliability Branch 5
Current Orders
• G.O. 95
– Overhead Line
Construction
• G. O. 128
– Underground Line
Construction
• G. O. 165
– Inspection
Requirements (Electric
Supply Only)
CPUC Utilities Safety and Reliability Branch 6
Development of GOs
• 1911 State legislature enacted laws to
regulate erection and maintenance of poles
and lines for overhead construction.
• 1915 Railroad Commission assigned to
inspect overhead construction.
• 1922 RR Commission issued GO 64, rules
for overhead construction.
CPUC Utilities Safety and Reliability Branch 7
Development (Cont.)
• RR Commission revised GO 64 and issued
GO 64-A in 1929
• GO 95 issued in 1941, from GO 64-A
• GO 128 issued in 1967
• GO 165 issued in 1997
CPUC Utilities Safety and Reliability Branch 8
Changes
• Any person may petition the Commission
under Public Utilities Code Section 1708.5
to adopt, amend, or repeal a regulation.
– General Order 95/128 rules committee meets
regularly to address rule changes, prior to
submitting to the CPUC
– CPUC staff reviews General Orders
periodically to determine if changes are needed
CPUC Utilities Safety and Reliability Branch 9
Other Documents
• Penal Code Section 385
• Title 25 HCD (Electric design for MHP)
• Cal-OSHA Title 8 Electric Safety Orders
• National Electrical Safety Code
• Company’s requirements
• Polk vs City of Los Angeles
CPUC Utilities Safety and Reliability Branch 10
General Order 95
• Rules for Overhead
Electric Line
Construction
CPUC Utilities Safety and Reliability Branch 11
General Order 95
• Sections
• Change list
• Decision No. 34884
GO 95
GO 95
CPUC Utilities Safety and Reliability Branch 12
Browsing G.O. 95
• Section I
– Purpose of G.O. 95 (Rule 11)
– Grandfathering (Rules 12.3 and 12.4)
• Section II
– Definitions
CPUC Utilities Safety and Reliability Branch 13
Requirements for All Lines
• Section III and IV
– Suitable design and
good maintenance
– Proper grounding
– Clearances
– Strength requirements
CPUC Utilities Safety and Reliability Branch 14
Requirements for Electric Lines
• Sections V and VI
– Detailed construction
requirements for
electric supply lines
– Tower and extra high
voltage line
CPUC Utilities Safety and Reliability Branch 15
Trolleys and Electric Railroads
• Sections VII
– Detailed construction
requirements for
Trolley Lines
– Detailed construction
and inspection
requirements Third
Rail Lines
– New GO for 25 kV
Electric Railroads
CPUC Utilities Safety and Reliability Branch 16
Requirements for
Communication Lines
• Section VIII
• Details for
construction of
Communication Lines
CPUC Utilities Safety and Reliability Branch 17
Joint Poles or Poles Jointly Used
• Section IX
– Mutual agreement
– Must use most stringent requirements
– Must use preceding rules, but some
modifications are permitted and described
CPUC Utilities Safety and Reliability Branch 18
Line Crossings, Line Conflicts and
Lines Over Railroad Tracks.
• Section X
– Extra precautions for lines crossing each other
or where conflicts may occur.
• Section XI
– Extra precautions for supply or
communications lines over railroad tracks
CPUC Utilities Safety and Reliability Branch 19
Appendices
A. Loading Districts
B. Mechanical and Loading Data
C. Sags
D. Communication Line Construction
E. Clearance of Poles, Towers, and
Structures from RR Tracks and Tree
Trimming(!)
CPUC Utilities Safety and Reliability Branch 20
Appendices (Cont.)
F. Typical problems
G. Illustrative Diagrams
H. Settlement Agreement
CPUC Utilities Safety and Reliability Branch 21
Rule numbering
• Example 1: Rule 54.7
Climbing Space and Rule
84.7
• Example 2: Rule 92.1-F5
CPUC Utilities Safety and Reliability Branch 22
General Order 95
• Definitions
• General Provisions
CPUC Utilities Safety and Reliability Branch 23
Definitions in Section II
CPUC Utilities Safety and Reliability Branch 24
Antenna
• Antenna means a
device for emitting
and/or receiving radio
frequency signals.
CPUC Utilities Safety and Reliability Branch 25
Climbing Space
• Space reserved along
the surface of a pole or
structure to permit
ready access for
linemen to equipment
and conductors located
on the pole
CPUC Utilities Safety and Reliability Branch 26
Communication Circuits
• For public or private
communication service.
Operate at less than 400
Volts to ground , or
750 V between any two
points on circuit.
Transmitted power is
less than 150 watts.
CPUC Utilities Safety and Reliability Branch 27
Supply Circuits
• Transmit a supply of
electrical energy
• Class E at very high
voltage >300,000V
• Class H circuits are
<300,000 but > 5000V
• Class L circuits are <
5000V
CPUC Utilities Safety and Reliability Branch 28
Service Drops
• Conductors strung
between a pole line
and a building, a
structure or meter
pole.
CPUC Utilities Safety and Reliability Branch 29
Guy
• Tension member, solid
or stranded wire used
to withstand an
unbalanced force on a
pole, cross arm or
other overhead
structure
CPUC Utilities Safety and Reliability Branch 30
Lead Wires
• Jumpers, bridle wires,
transposition wires,
taps
• Connect line
conductors to the
equipment and
apparatus or other line
conductors on same
overhead structure.
CPUC Utilities Safety and Reliability Branch 31
Conductor
• Material suitable for
carrying electric
current such as wire,
cable or bus bar
• Material for
transmitting light
(fiber optics)
CPUC Utilities Safety and Reliability Branch 32
Risers
• Conductors which
extend below the
ground line and are
generally installed on
the surfaces of poles.
CPUC Utilities Safety and Reliability Branch 33
Runs
vertical or lateral
conductors supported in
coverings or casings on
overhead line structures,
or insulated
communication
conductors supported
along surfaces of poles or
cross arms.
CPUC Utilities Safety and Reliability Branch 34
Cross Arm
• Horizontal support
attached to poles or
structures, generally at
right angle to the
conductor supported
CPUC Utilities Safety and Reliability Branch 35
Guard Arm
• A Cross Arm installed
above and
approximately parallel
to a messenger, cable
or conductor
CPUC Utilities Safety and Reliability Branch 36
Joint Use of Poles or Poles Jointly Used
• Poles or structures
occupied by circuits of
different ownership or by
two or more of the
following classes of
circuits of the same
ownership
– Communications circuits
for public use
– Railway or trolley circuits
– Supply circuits other than
trolley circuits
CPUC Utilities Safety and Reliability Branch 37
General Provisions
General Order 95
CPUC Utilities Safety and Reliability Branch 38
Emergency Installation
(Rule 12.5)
• During Emergency conditions the requirements of
General Order 95 may be deferred.
• Shall be removed, replaced or relocated as soon as
practical
• The requirements of Rule 37 for supply
conductors should not be waived
• Facilities shall not be installed with a safety factor
of less than unity.
CPUC Utilities Safety and Reliability Branch 39
Third Party Nonconformance
(Rule 12.6)
• When a third party causes a condition on or
near a utility facility that does not conform
with this Order, the utility shall be allowed
reasonable time to address the condition
• While addressing this condition, the utility
is in conformance with the Order
CPUC Utilities Safety and Reliability Branch 40
Investigation of Accidents
(Rule 17)
• Each owner or operator of supply lines shall
establish procedures for the investigation of major
accidents and failures for the purpose of
determining the causes and minimizing the
possibility of recurrence.
– Incidents associated with utility facilities which cause
property damage estimated at or about the time of the
incident to be more than $50,000
– Incidents resulting from electrical contact which cause
personal injury which require hospitalization overnight,
or result in death
CPUC Utilities Safety and Reliability Branch 41
Design, Construction and Maintenance
(Rule 31.1)
• Constructed, and
maintained for their
intended use
• Work should be done
in accordance with
accepted good practice
for the given local
conditions
CPUC Utilities Safety and Reliability Branch 42
Inspection
(Rule 31.2)
• Systems shall be inspected by the operator
frequently and thoroughly for the purpose of
insuring that they are in good condition so
as to conform with these rules.
• This rule does not specify time intervals,
that is left up to the operator.
CPUC Utilities Safety and Reliability Branch 43
Cooperation to Avoid Conflicts
(Rule 31.4)
• Cooperation to Avoid Conflicts
• Notice to other utilities when construction
or reconstruction may create line conflict
in ADVANCE
CPUC Utilities Safety and Reliability Branch 44
Abandoned lines
(Rule 31.6)
• Lines or portions of lines abandoned shall
be removed by their owners to avoid public
nuisance or hazard
• Lines that are permanently abandoned shall
be defined as those lines that are determined
by their owner to have no foreseeable future
use.
CPUC Utilities Safety and Reliability Branch 45
General Arrangements of Lines
(Rule 32)
• Where two or more systems are concerned in any
clearance, that owner or operator who last in point of
time constructs or erects facilities, shall establish the
clearance required in these rules from other facilities
which have been erected previously.
• Where supply and communication circuits or supply
circuits of different voltage classifications are
involved in crossings, conflicts or joint use, the higher
voltage circuit shall in general be carried at the higher
level.
CPUC Utilities Safety and Reliability Branch 46
Ground and Neutrals
(Rule 33)
• Treat common neutral like a phase conductor
• Rule need not apply to overhead lightning
protection wires on metal structures or grounded
wood structures.
• The grounding of the neutral or any other
conductor is permitted only for the purposes of
stabilization and protection, not for use as a return
conductor.
CPUC Utilities Safety and Reliability Branch 47
Ground or Earth as a Conductor
Rule 33.2
• Ground or earth shall not be used as a
normal return or circuit conductor.
• The neutral or any other conductor is
permitted to be grounded only for the
purposes of stabilization and protection.
• “Stray” Voltage
CPUC Utilities Safety and Reliability Branch 48
Foreign attachments
(Rule 34)
• Nothing in these rules shall
be construed as permitting
the unauthorized attachment
... of antennas, signs, posters,
banners, decoration, wires,
lighting fixtures, guys, ropes
and other such equipment
foreign to the purposes of
overhead electric line
construction.
CPUC Utilities Safety and Reliability Branch 49
Tree Trimming
(Rule 35)
• Where overhead wires
pass through trees, a
reasonable amount of
tree trimming shall be
done in order that the
wires may clear
branches and foliage
CPUC Utilities Safety and Reliability Branch 50
Tree Trimming
(Rule 35)
• The minimum clearances are established in
Table 1, Case 13 for vegetation and Supply
lines operating above 750 volts.
• When a Communication Line or Supply
Line operating at less than 750 volts, shows
strain or evidences abrasion from tree
contact, the condition shall be corrected.
CPUC Utilities Safety and Reliability Branch 51
Clearances of Wires Above Ground
(Rule 37, Table 1)
• Rule 37, allows
modifications of
certain values in Table
1 for:
– Temperature
– Loading (Rule 43)
– Other conditions
• Define how to
measure values in
respective tables
CPUC Utilities Safety and Reliability Branch 52
Clearances of Wires Above Ground
(Rule 37, Table 1)
• Table 1
– Breaks overhead facilities into 7 categories
– Gives clearances for 14 different conditions
– Has over 50 footnotes for the table
CPUC Utilities Safety and Reliability Branch 53
Service Drop Clearances (Cont)
CPUC Utilities Safety and Reliability Branch 54
Clearances of Wires from other Wires
(Rule 38 & Table 2)
• Table 2
– Breaks overhead facilities into 11 categories
– Gives clearances for 21 different conditions
– Has over 40 footnotes for the table
CPUC Utilities Safety and Reliability Branch 55
Clearances of Wires from Signs
(Rule 39, Table 2A)
• Rule 39, allows
modifications of
values in Table 2A
for:
– Temperature
– Loading (Rule 43)
• Define how to
measure values in
respective tables
CPUC Utilities Safety and Reliability Branch 56
Safety Factors
(Section IV)
• Grade of Construction (Rule 42, Table 3)
• Light or Heavy Loading (Rule 43)
• Safety Factor Can Be Determined (Rule 44)
– Table 4 Lists safety factor at time of installation
– Rule 44.2 allows for “2/3” reduction of values
in Table 4 (due to deterioration) but in no case
may safety factor fall below “1”
CPUC Utilities Safety and Reliability Branch 57
Setting of Poles
(Rule 49.1-C)
• Table 6 shows
minimum depths
• If soil is not firm,
deeper setting or
special methods
• Unguyed pole subject
to strain or at corners
should be set deeper
CPUC Utilities Safety and Reliability Branch 58
Setting of Poles
(Rule 49.1-C)
• Poles are branded, to
determine how deeply
they are set:
– <50ft, brand is 10 ft
– >55 ft, brand is 14 ft
• A 10% reduction in
the pole setting depth
is allowed due to:
– Ground Erosion
– Excavation
CPUC Utilities Safety and Reliability Branch 59
Service Drop Covering
(Rule 49.4-C7a)
• Service drop conductors must be covered
with the equivalent of standard double braid
weatherproofing or of a design authorized
for use by the Commission.
CPUC Utilities Safety and Reliability Branch 60
High Voltage Signs
(Rule 51.6)
• Poles and cross arms
carrying conductors of
more than 750V shall
be marked High
Voltage
• Signs must be secure,
legible and clearly
distinguishable.
CPUC Utilities Safety and Reliability Branch 61
Risers and Runs
(Rules 54.6, 74.6 & 84.6)
• Ground wires of
supply circuits must
be protected by
suitable covering in
good repair throughout
their length.
• Lateral runs must be
covered to outer
position of conductor
CPUC Utilities Safety and Reliability Branch 62
Service Drop Clearance from Buildings
(Rules 54.8 & 84.8)
• Horizontal clearances for Supply Service
Drops from doors and windows – 3 feet
• Communication Service Drops
– Buildings on the premises served – no
minimum but can not touch
– Buildings on other premises – 8 feet
• Except: Roofs whose slope exceeds 9 inches of rise
per 12 inches of run or the service drop does not
overhang the building by more than 6 feet
CPUC Utilities Safety and Reliability Branch 63
Guy Marker
(Rules 56.9, 66.7, 86.9)
• Anchor guys are
required to be marked
by securely attached
markers and in good
repair
CPUC Utilities Safety and Reliability Branch 64
Rule 94
• 94.1 Definition
• 94.2 Maintenance and Inspection
• 94.3 General Requirements
• 94.4 Clearances
• 94.5 Marking
• 94.6 De-energizing
• Exceptions
CPUC Utilities Safety and Reliability Branch 65
Rule 94 Continued
94.5 Marking
A. No antenna owner or operator shall install an antenna
on a joint use pole unless such installation is subject to
an agreement with the pole owner(s) that includes
marking requirements that are substantially similar to
and achieve at least the same safety standards as those
set forth in Appendix H to GO 95.
B. Joint use poles shall be marked with a sign for each
antenna installation as follows:
1) Identification of the antenna operator
2) A 24-hour contact number of antenna operator for
Emergency or Information
3) Unique identifier of the antenna installation.
CPUC Utilities Safety and Reliability Branch 66
Rule 94 Continued
94.6 De-energizing
No antenna owner or operator shall install an
antenna on a joint use pole unless such installation is
subject to an agreement with the pole owner(s) that
includes de-energizing protocols that are
substantially similar to and achieve at least the same
safety standards as those set forth in Appendix H to
GO 95.
CPUC Utilities Safety and Reliability Branch 67
General Order 128
• Rules for Construction
of Underground
Electric Supply and
Communication
Systems
CPUC Utilities Safety and Reliability Branch 68
General Order 128
• Sections
• Change list
• Decision No. 73195
GO 95
GO
128
CPUC Utilities Safety and Reliability Branch 69
Browsing G.O. 128
• Section I
– Purpose of G.O. 128 (Rule 11)
– Grandfathering (Rules 12.3 and 12.4)
• Section II
– Definitions
CPUC Utilities Safety and Reliability Branch 70
Requirements for Supply Systems
• Section III
– Clearance and Depths
– Explosion Protection
– Guarding Live Parts
CPUC Utilities Safety and Reliability Branch 71
Requirements for Communication Systems
• Section IV
– Clearance and Depths
– Explosion Protection
– Guarding Live Parts
– Police, Fire Alarm, and Traffic Control Circuits
CPUC Utilities Safety and Reliability Branch 72
Appendices
• Appendix A
– Summary of Dimensions, Clearances, and Depth
Requirements
• Appendix B
– Typical Illustrative Diagrams of Rules
• Appendix C
– Clearance from Railroad Tracks
• Appendix D
– Excerpts from Public Utilities Code
CPUC Utilities Safety and Reliability Branch 73
General Order 128
• Definitions
• General Provisions
CPUC Utilities Safety and Reliability Branch 74
Definitions
CPUC Utilities Safety and Reliability Branch 75
Manhole
• A subsurface
enclosure in an
underground system
containing working
space large enough for
a person to enter
CPUC Utilities Safety and Reliability Branch 76
Handhole
• A permanent opening in the route of an
underground system, usually smaller than a
manhole, with a removable top and
affording access to cable runs and
associated apparatus
CPUC Utilities Safety and Reliability Branch 77
Cover
• The radial distance between the surface of an
underground cable or conduit and grade.
CPUC Utilities Safety and Reliability Branch 78
Inspection
(Rule 17.2)
• Systems shall be inspected by the operator
frequently and thoroughly for the purpose of
insuring that they are in good condition so
as to conform with these rules.
• This rule does not specify time intervals,
that is left up to the operator.
• Same as Rule 31.2 of General Order 95
CPUC Utilities Safety and Reliability Branch 79
Location Information
(Rule 17.7)
• Each party operating or owning facilities
shall, upon request, provide information as
to location of its underground facilities to
any other party contemplating underground
construction, or work, in the vicinity
thereof.
• Government Code Sections 4216-4216.9
CPUC Utilities Safety and Reliability Branch 80
Identification
(Rule 17.8)
• Manholes, handholes ,
subsurface and self-
contained surface-
mounted equipment
enclosures shall be
marked as to ownership to
facilitate identification by
persons authorized to
work therein and by other
persons performing work
in their vicinity.
CPUC Utilities Safety and Reliability Branch 81
Investigation of Accidents
(Rule 18)
• Each owner or operator of supply lines shall establish
procedures for the investigation of major accidents and
failures for the purpose of determining the causes and
minimizing the possibility of recurrence.
– Incidents associated with utility facilities which cause property
damage estimated at or about the time of the incident to be more
than $50,000
– Incidents resulting from electrical contact which cause personal
injury which require hospitalization overnight, or result in death
• Same as Rule 17, of General Order 95
CPUC Utilities Safety and Reliability Branch 82
Design, Construction and Maintenance
(Rule 17.1)
• Constructed, and
maintained for their
intended use
• Work should be done in
accordance with accepted
good practice for the
given local conditions
• Same as Rule 31.1, of
General Order 95
CPUC Utilities Safety and Reliability Branch 83
APPENDIX A Tables 1 & 2
• Table 1 - Clearance and Depth
Requirements for Supply and
Communication Systems
• Table 2 - Miscellaneous Dimensions and
Clearance Requirements for Supply and
Communication Systems
CPUC Utilities Safety and Reliability Branch 84
Covers
(Rules 32.7 & 42.7)
• Covers of subsurface enclosures must:
– Be secured in place
– Withstand the forces that they will be subject to
– Require a tool to open
CPUC Utilities Safety and Reliability Branch 85
Guarding Live Parts
(34.3-B)
• Surface mounted equipment containing live
parts shall be installed such that a wire or
other material, cannot be passed into the
enclosure when closed.
CPUC Utilities Safety and Reliability Branch 86
Locking –Padmounted
(Rule 34.3-C)
• Padmounted
equipment shall be
made secure against
entry by unauthorized
person by:
– Locks
– Suitable means
CPUC Utilities Safety and Reliability Branch 87
General Order 165
• Inspection Cycles
for
Electric Distribution
Facilities
CPUC Utilities Safety and Reliability Branch 88
General Order 165
I. Purpose
II. Applicability
III. Definitions
IV. Standards for
Inspection, Record-
keeping, and Reporting
Appendix A
GO 165
CPUC Utilities Safety and Reliability Branch 89
Purpose
• The purpose of this General Order is to establish
minimum requirements for electric distribution
facilities, regarding:
– maximum allowable inspection cycle lengths
– condition rating
– scheduling and performance of corrective action,
– record-keeping, and
– reporting
CPUC Utilities Safety and Reliability Branch 90
Applicability
• Section II, States GO 165
applies:
– PG&E
– PacifiCorp
– SDG&E
– SP&P
– SCE
• Decision 97-03-070
– Requested comments
concerning the application of
GO 165 to Municipals and
Publicly Owned Electric
Utilities
• Decision 98-03-036
– GO 165 applies to Municipals
and Publicly Owned Electric
Utilities
• Decision 98-10-059
– Denied CMUA’s request to
rehear decision
• Decision 99-12-052
– Denied CMUA’s request to
modify 98-03-036
CPUC Utilities Safety and Reliability Branch 91
Definitions
• "Urban" shall be defined as those areas with a
population of more than 1,000 persons per square
mile as determined by the United States Bureau of
the Census.
• "Rural" shall be defined as those areas with a
population of less than 1,000 persons per square
mile as determined by the United States Bureau of
the Census.
CPUC Utilities Safety and Reliability Branch 92
Definitions
• "Patrol" shall be defined as a simple visual inspection, of
applicable utility equipment and structures, that is designed
to identify obvious structural problems and hazards.
Patrols may be carried out in the course of other company
business.
• "Detailed" inspection shall be defined as one where
individual pieces of equipment and structures are carefully
examined, visually and through use of routine diagnostic
test, as appropriate, and (if practical and if useful
information can be so gathered) opened, and the condition
of each rated and recorded.
CPUC Utilities Safety and Reliability Branch 93
Definitions
• "Intrusive" inspection is defined as one involving
movement of soil, taking samples for analysis,
and/or using more sophisticated diagnostic tools
beyond visual inspections or instrument reading.
• "Corrective Action" shall be defined as
maintenance, repair, or replacement of utility
equipment and structures so that they function
properly and safely.
CPUC Utilities Safety and Reliability Branch 94
Standards for Inspection, Record-
keeping, and Reporting
• Each utility shall conduct inspections of its
distribution facilities, as necessary, but in
no case may the period between inspections
(measured in years) exceed the time
specified in the table.
CPUC Utilities Safety and Reliability Branch 95
Standards for Inspection, Record-
keeping, and Reporting
• For all inspections, within a reasonable period,
company records shall specify:
– The circuit, area, or equipment inspected
– The name of the inspector, the date of the inspection
– Any problems identified during each inspection
– A scheduled date of corrective action.
– For detailed and intrusive inspections, companies shall
also rate the condition of inspected equipment.
– Upon completion of corrective action, company records
will show the nature of the work, the date, and the
identity of persons performing the work.
CPUC Utilities Safety and Reliability Branch 96
Standards for Inspection, Record-
keeping, and Reporting
• Each utility shall file annual reports for every following year by no
later than July 1. The report shall identify:
– The number of facilities, by type which have been inspected during the
previous period.
– Identify those facilities which were scheduled for inspection but which
were not inspected
– The total and percentage breakdown of equipment rated at each condition
rating level, including that equipment determined to be in need of
corrective action.
– Present the total and percentage of equipment which was and was not
corrected during the reporting period.
– The percentage of equipment in need of corrective action, but with a
scheduled date beyond the reporting period, classified by the amount of
time remaining before the scheduled action.
– All of the above information shall be presented for each type of facility
identified in the attached table and shall be aggregated by district.
2020------------Wood poles which passed intrusive inspection
1010xx21Wood Poles over 15 years which have not been subject to intrusive inspection
------xx21Wood Poles under 15 years
------xx21Streetlighting
------5521Overhead Conductor and Cables
------5521Padmounted
------3321Underground
------5521Overhead
Regulators/Capacitors
------5521Padmounted
------3321Underground
------5521Overhead
Switching/Protective Devices
------5521Padmounted
------3321Underground
------5521Overhead
Transformers
RuralUrbanRuralUrbanRuralUrban
IntrusiveDetailedPatrol
Table
CPUC Utilities Safety and Reliability Branch 98
Enforcement
• Only the Commission can levy fines
• We rely on utility’s desire to have a good
system
• Collegial Approach
• What about Communication Utilities?
CPUC Utilities Safety and Reliability Branch 99
Current Utilities Safety and Reliability
Branch Issues
• Communications
Enforcement
• Substations
• Wireless Antenna Rule
• New GO for 25 kV
Electric Railroads

More Related Content

What's hot

IRC_Poster_WFTPElectrical_Final
IRC_Poster_WFTPElectrical_FinalIRC_Poster_WFTPElectrical_Final
IRC_Poster_WFTPElectrical_Final
Michael Bardwell
 
Nav Topic 4 hf communication system
Nav Topic 4 hf communication systemNav Topic 4 hf communication system
Nav Topic 4 hf communication system
Izah Asmadi
 
CE Power NERC Compliance
CE Power NERC ComplianceCE Power NERC Compliance
CE Power NERC Compliance
Brian V. Wilson
 
Iai controller overview_specsheet
Iai controller overview_specsheetIai controller overview_specsheet
Iai controller overview_specsheet
Electromate
 
Nav Topic 6 pa system
Nav Topic 6 pa systemNav Topic 6 pa system
Nav Topic 6 pa system
Izah Asmadi
 
Iai ether cat_pcon_acon_specsheet
Iai ether cat_pcon_acon_specsheetIai ether cat_pcon_acon_specsheet
Iai ether cat_pcon_acon_specsheet
Electromate
 

What's hot (20)

Tems investigation 16.3.2 connectable devices
Tems investigation 16.3.2   connectable devicesTems investigation 16.3.2   connectable devices
Tems investigation 16.3.2 connectable devices
 
IRJET- Wireless Monitoring of Distribution Tranformer and Inform to Electrica...
IRJET- Wireless Monitoring of Distribution Tranformer and Inform to Electrica...IRJET- Wireless Monitoring of Distribution Tranformer and Inform to Electrica...
IRJET- Wireless Monitoring of Distribution Tranformer and Inform to Electrica...
 
fault detection of transformer using GSM,,,,by YASASWINI.KAGITHALA
fault detection of transformer using GSM,,,,by YASASWINI.KAGITHALAfault detection of transformer using GSM,,,,by YASASWINI.KAGITHALA
fault detection of transformer using GSM,,,,by YASASWINI.KAGITHALA
 
Mobile tower site, Nimay Giri
Mobile tower site, Nimay GiriMobile tower site, Nimay Giri
Mobile tower site, Nimay Giri
 
IRC_Poster_WFTPElectrical_Final
IRC_Poster_WFTPElectrical_FinalIRC_Poster_WFTPElectrical_Final
IRC_Poster_WFTPElectrical_Final
 
Nav Topic 4 hf communication system
Nav Topic 4 hf communication systemNav Topic 4 hf communication system
Nav Topic 4 hf communication system
 
CE Power NERC Compliance
CE Power NERC ComplianceCE Power NERC Compliance
CE Power NERC Compliance
 
Dmcr lte trial feature
Dmcr lte trial featureDmcr lte trial feature
Dmcr lte trial feature
 
Report its
Report itsReport its
Report its
 
Umts system architecture
Umts system architectureUmts system architecture
Umts system architecture
 
Iai controller overview_specsheet
Iai controller overview_specsheetIai controller overview_specsheet
Iai controller overview_specsheet
 
IRJET- A New Load Frequency Control Method of Multi-Area Power System Via the...
IRJET- A New Load Frequency Control Method of Multi-Area Power System Via the...IRJET- A New Load Frequency Control Method of Multi-Area Power System Via the...
IRJET- A New Load Frequency Control Method of Multi-Area Power System Via the...
 
HBC-radiomatic India Pvt. Ltd, Pune, Radio Control
HBC-radiomatic India Pvt. Ltd, Pune, Radio ControlHBC-radiomatic India Pvt. Ltd, Pune, Radio Control
HBC-radiomatic India Pvt. Ltd, Pune, Radio Control
 
Nav Topic 6 pa system
Nav Topic 6 pa systemNav Topic 6 pa system
Nav Topic 6 pa system
 
Iai ether cat_pcon_acon_specsheet
Iai ether cat_pcon_acon_specsheetIai ether cat_pcon_acon_specsheet
Iai ether cat_pcon_acon_specsheet
 
Connectable devices tems investigation 15.3
Connectable devices tems investigation 15.3Connectable devices tems investigation 15.3
Connectable devices tems investigation 15.3
 
Umts signal flow
Umts signal flowUmts signal flow
Umts signal flow
 
Vhf station
Vhf stationVhf station
Vhf station
 
Drive test from a t z (part 3)-actix
Drive test from a t z (part 3)-actixDrive test from a t z (part 3)-actix
Drive test from a t z (part 3)-actix
 
Bts commissioning (alcatel lucent)
Bts commissioning (alcatel lucent)Bts commissioning (alcatel lucent)
Bts commissioning (alcatel lucent)
 

Similar to CPUC - General Orders 95, 128 & 165

Artificial lift forum ul 1741 presentation - final
Artificial lift forum   ul 1741 presentation - finalArtificial lift forum   ul 1741 presentation - final
Artificial lift forum ul 1741 presentation - final
Ron Henderson
 
2005 16 autumn_wiring_matters__complete_no_adverts
2005 16 autumn_wiring_matters__complete_no_adverts2005 16 autumn_wiring_matters__complete_no_adverts
2005 16 autumn_wiring_matters__complete_no_adverts
Khalid Sithari
 
Electrical & MEP Design - Study material.pdf
Electrical & MEP Design - Study material.pdfElectrical & MEP Design - Study material.pdf
Electrical & MEP Design - Study material.pdf
sureshrajan38
 
INTERNSHIP REPORT (FINAL)
INTERNSHIP REPORT (FINAL)INTERNSHIP REPORT (FINAL)
INTERNSHIP REPORT (FINAL)
Sindhuja Balaji
 

Similar to CPUC - General Orders 95, 128 & 165 (20)

CEA Regulations.pptx
CEA Regulations.pptxCEA Regulations.pptx
CEA Regulations.pptx
 
EIT_Presentation
EIT_PresentationEIT_Presentation
EIT_Presentation
 
Central electricity authority regulations wikipedia
Central electricity authority regulations   wikipediaCentral electricity authority regulations   wikipedia
Central electricity authority regulations wikipedia
 
Nec and oesc-1
Nec and oesc-1Nec and oesc-1
Nec and oesc-1
 
Artificial lift forum ul 1741 presentation - final
Artificial lift forum   ul 1741 presentation - finalArtificial lift forum   ul 1741 presentation - final
Artificial lift forum ul 1741 presentation - final
 
4143813.ppt
4143813.ppt4143813.ppt
4143813.ppt
 
Electrical Lessons learned
Electrical Lessons learnedElectrical Lessons learned
Electrical Lessons learned
 
Final_NFE,May23-Lenin-CEA-Safety- Regulations PPT.pptx
Final_NFE,May23-Lenin-CEA-Safety- Regulations PPT.pptxFinal_NFE,May23-Lenin-CEA-Safety- Regulations PPT.pptx
Final_NFE,May23-Lenin-CEA-Safety- Regulations PPT.pptx
 
Metro rail project in india year 2017
Metro rail project in india year 2017Metro rail project in india year 2017
Metro rail project in india year 2017
 
Selective Coordination
Selective CoordinationSelective Coordination
Selective Coordination
 
2005 16 autumn_wiring_matters__complete_no_adverts
2005 16 autumn_wiring_matters__complete_no_adverts2005 16 autumn_wiring_matters__complete_no_adverts
2005 16 autumn_wiring_matters__complete_no_adverts
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and Standards
 
Electrical & MEP Design - Study material.pdf
Electrical & MEP Design - Study material.pdfElectrical & MEP Design - Study material.pdf
Electrical & MEP Design - Study material.pdf
 
Overhead & Underground Electric Safety Webinar Presented by Amprobe
Overhead & Underground Electric Safety Webinar Presented by AmprobeOverhead & Underground Electric Safety Webinar Presented by Amprobe
Overhead & Underground Electric Safety Webinar Presented by Amprobe
 
INTERNSHIP REPORT (FINAL)
INTERNSHIP REPORT (FINAL)INTERNSHIP REPORT (FINAL)
INTERNSHIP REPORT (FINAL)
 
2311 s5500 checkout &amp; comm. of elec. equip, rev. a 8
2311 s5500 checkout &amp; comm. of elec. equip, rev. a 82311 s5500 checkout &amp; comm. of elec. equip, rev. a 8
2311 s5500 checkout &amp; comm. of elec. equip, rev. a 8
 
2311 s5500 checkout &amp; comm. of elec. equip, rev. a 8
2311 s5500 checkout &amp; comm. of elec. equip, rev. a 82311 s5500 checkout &amp; comm. of elec. equip, rev. a 8
2311 s5500 checkout &amp; comm. of elec. equip, rev. a 8
 
switchgear and protection.pdf
switchgear and protection.pdfswitchgear and protection.pdf
switchgear and protection.pdf
 
Eat105 Chapter 1
Eat105 Chapter 1Eat105 Chapter 1
Eat105 Chapter 1
 
Exploring IEEE-C37.246-2017 Guide -Presenatation.pdf
Exploring IEEE-C37.246-2017 Guide -Presenatation.pdfExploring IEEE-C37.246-2017 Guide -Presenatation.pdf
Exploring IEEE-C37.246-2017 Guide -Presenatation.pdf
 

More from michaeljmack

Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systems
michaeljmack
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrush
michaeljmack
 
Building information modeling
Building information modelingBuilding information modeling
Building information modeling
michaeljmack
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protection
michaeljmack
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systems
michaeljmack
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spaces
michaeljmack
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708
michaeljmack
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distribution
michaeljmack
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulator
michaeljmack
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Shedding
michaeljmack
 

More from michaeljmack (20)

Auburn, NY - 200 Years of History 1793-1993
Auburn, NY - 200 Years of History  1793-1993Auburn, NY - 200 Years of History  1793-1993
Auburn, NY - 200 Years of History 1793-1993
 
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 YearbookAuburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 Yearbook
 
Auburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 YearbookAuburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbook
 
Surge Protection
Surge ProtectionSurge Protection
Surge Protection
 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systems
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flash
 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgear
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrush
 
Building information modeling
Building information modelingBuilding information modeling
Building information modeling
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protection
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systems
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spaces
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distribution
 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performance
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulator
 
Facts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind PlantsFacts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind Plants
 
Power Plant Horror Stories
Power Plant Horror StoriesPower Plant Horror Stories
Power Plant Horror Stories
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Shedding
 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentals
 

Recently uploaded

Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 

Recently uploaded (20)

457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptx
 

CPUC - General Orders 95, 128 & 165

  • 1. CPUC Utilities Safety and Reliability Branch 1 General Orders 95, 128, & 165 Rules for Construction and Maintenance of Overhead and Underground Electric Supply and Communication Systems
  • 2. CPUC Utilities Safety and Reliability Branch 2 Scope of Class • Provide general knowledge of the GOs • Provide details of common infractions
  • 3. CPUC Utilities Safety and Reliability Branch 3 Utilities Safety and Reliability Branch • Engineers in LA, SF and Sacramento • Overhead/Under-ground electric lines. • Propane/natural gas pipelines -- utilities, master-meters • Investigate incidents-On Call
  • 4. CPUC Utilities Safety and Reliability Branch 4 Utilities Safety and Reliability Branch • Jurisdiction – Investor Owned – Co-op – CATV – Municipal (Polk vs. City of Los Angeles)
  • 5. CPUC Utilities Safety and Reliability Branch 5 Current Orders • G.O. 95 – Overhead Line Construction • G. O. 128 – Underground Line Construction • G. O. 165 – Inspection Requirements (Electric Supply Only)
  • 6. CPUC Utilities Safety and Reliability Branch 6 Development of GOs • 1911 State legislature enacted laws to regulate erection and maintenance of poles and lines for overhead construction. • 1915 Railroad Commission assigned to inspect overhead construction. • 1922 RR Commission issued GO 64, rules for overhead construction.
  • 7. CPUC Utilities Safety and Reliability Branch 7 Development (Cont.) • RR Commission revised GO 64 and issued GO 64-A in 1929 • GO 95 issued in 1941, from GO 64-A • GO 128 issued in 1967 • GO 165 issued in 1997
  • 8. CPUC Utilities Safety and Reliability Branch 8 Changes • Any person may petition the Commission under Public Utilities Code Section 1708.5 to adopt, amend, or repeal a regulation. – General Order 95/128 rules committee meets regularly to address rule changes, prior to submitting to the CPUC – CPUC staff reviews General Orders periodically to determine if changes are needed
  • 9. CPUC Utilities Safety and Reliability Branch 9 Other Documents • Penal Code Section 385 • Title 25 HCD (Electric design for MHP) • Cal-OSHA Title 8 Electric Safety Orders • National Electrical Safety Code • Company’s requirements • Polk vs City of Los Angeles
  • 10. CPUC Utilities Safety and Reliability Branch 10 General Order 95 • Rules for Overhead Electric Line Construction
  • 11. CPUC Utilities Safety and Reliability Branch 11 General Order 95 • Sections • Change list • Decision No. 34884 GO 95 GO 95
  • 12. CPUC Utilities Safety and Reliability Branch 12 Browsing G.O. 95 • Section I – Purpose of G.O. 95 (Rule 11) – Grandfathering (Rules 12.3 and 12.4) • Section II – Definitions
  • 13. CPUC Utilities Safety and Reliability Branch 13 Requirements for All Lines • Section III and IV – Suitable design and good maintenance – Proper grounding – Clearances – Strength requirements
  • 14. CPUC Utilities Safety and Reliability Branch 14 Requirements for Electric Lines • Sections V and VI – Detailed construction requirements for electric supply lines – Tower and extra high voltage line
  • 15. CPUC Utilities Safety and Reliability Branch 15 Trolleys and Electric Railroads • Sections VII – Detailed construction requirements for Trolley Lines – Detailed construction and inspection requirements Third Rail Lines – New GO for 25 kV Electric Railroads
  • 16. CPUC Utilities Safety and Reliability Branch 16 Requirements for Communication Lines • Section VIII • Details for construction of Communication Lines
  • 17. CPUC Utilities Safety and Reliability Branch 17 Joint Poles or Poles Jointly Used • Section IX – Mutual agreement – Must use most stringent requirements – Must use preceding rules, but some modifications are permitted and described
  • 18. CPUC Utilities Safety and Reliability Branch 18 Line Crossings, Line Conflicts and Lines Over Railroad Tracks. • Section X – Extra precautions for lines crossing each other or where conflicts may occur. • Section XI – Extra precautions for supply or communications lines over railroad tracks
  • 19. CPUC Utilities Safety and Reliability Branch 19 Appendices A. Loading Districts B. Mechanical and Loading Data C. Sags D. Communication Line Construction E. Clearance of Poles, Towers, and Structures from RR Tracks and Tree Trimming(!)
  • 20. CPUC Utilities Safety and Reliability Branch 20 Appendices (Cont.) F. Typical problems G. Illustrative Diagrams H. Settlement Agreement
  • 21. CPUC Utilities Safety and Reliability Branch 21 Rule numbering • Example 1: Rule 54.7 Climbing Space and Rule 84.7 • Example 2: Rule 92.1-F5
  • 22. CPUC Utilities Safety and Reliability Branch 22 General Order 95 • Definitions • General Provisions
  • 23. CPUC Utilities Safety and Reliability Branch 23 Definitions in Section II
  • 24. CPUC Utilities Safety and Reliability Branch 24 Antenna • Antenna means a device for emitting and/or receiving radio frequency signals.
  • 25. CPUC Utilities Safety and Reliability Branch 25 Climbing Space • Space reserved along the surface of a pole or structure to permit ready access for linemen to equipment and conductors located on the pole
  • 26. CPUC Utilities Safety and Reliability Branch 26 Communication Circuits • For public or private communication service. Operate at less than 400 Volts to ground , or 750 V between any two points on circuit. Transmitted power is less than 150 watts.
  • 27. CPUC Utilities Safety and Reliability Branch 27 Supply Circuits • Transmit a supply of electrical energy • Class E at very high voltage >300,000V • Class H circuits are <300,000 but > 5000V • Class L circuits are < 5000V
  • 28. CPUC Utilities Safety and Reliability Branch 28 Service Drops • Conductors strung between a pole line and a building, a structure or meter pole.
  • 29. CPUC Utilities Safety and Reliability Branch 29 Guy • Tension member, solid or stranded wire used to withstand an unbalanced force on a pole, cross arm or other overhead structure
  • 30. CPUC Utilities Safety and Reliability Branch 30 Lead Wires • Jumpers, bridle wires, transposition wires, taps • Connect line conductors to the equipment and apparatus or other line conductors on same overhead structure.
  • 31. CPUC Utilities Safety and Reliability Branch 31 Conductor • Material suitable for carrying electric current such as wire, cable or bus bar • Material for transmitting light (fiber optics)
  • 32. CPUC Utilities Safety and Reliability Branch 32 Risers • Conductors which extend below the ground line and are generally installed on the surfaces of poles.
  • 33. CPUC Utilities Safety and Reliability Branch 33 Runs vertical or lateral conductors supported in coverings or casings on overhead line structures, or insulated communication conductors supported along surfaces of poles or cross arms.
  • 34. CPUC Utilities Safety and Reliability Branch 34 Cross Arm • Horizontal support attached to poles or structures, generally at right angle to the conductor supported
  • 35. CPUC Utilities Safety and Reliability Branch 35 Guard Arm • A Cross Arm installed above and approximately parallel to a messenger, cable or conductor
  • 36. CPUC Utilities Safety and Reliability Branch 36 Joint Use of Poles or Poles Jointly Used • Poles or structures occupied by circuits of different ownership or by two or more of the following classes of circuits of the same ownership – Communications circuits for public use – Railway or trolley circuits – Supply circuits other than trolley circuits
  • 37. CPUC Utilities Safety and Reliability Branch 37 General Provisions General Order 95
  • 38. CPUC Utilities Safety and Reliability Branch 38 Emergency Installation (Rule 12.5) • During Emergency conditions the requirements of General Order 95 may be deferred. • Shall be removed, replaced or relocated as soon as practical • The requirements of Rule 37 for supply conductors should not be waived • Facilities shall not be installed with a safety factor of less than unity.
  • 39. CPUC Utilities Safety and Reliability Branch 39 Third Party Nonconformance (Rule 12.6) • When a third party causes a condition on or near a utility facility that does not conform with this Order, the utility shall be allowed reasonable time to address the condition • While addressing this condition, the utility is in conformance with the Order
  • 40. CPUC Utilities Safety and Reliability Branch 40 Investigation of Accidents (Rule 17) • Each owner or operator of supply lines shall establish procedures for the investigation of major accidents and failures for the purpose of determining the causes and minimizing the possibility of recurrence. – Incidents associated with utility facilities which cause property damage estimated at or about the time of the incident to be more than $50,000 – Incidents resulting from electrical contact which cause personal injury which require hospitalization overnight, or result in death
  • 41. CPUC Utilities Safety and Reliability Branch 41 Design, Construction and Maintenance (Rule 31.1) • Constructed, and maintained for their intended use • Work should be done in accordance with accepted good practice for the given local conditions
  • 42. CPUC Utilities Safety and Reliability Branch 42 Inspection (Rule 31.2) • Systems shall be inspected by the operator frequently and thoroughly for the purpose of insuring that they are in good condition so as to conform with these rules. • This rule does not specify time intervals, that is left up to the operator.
  • 43. CPUC Utilities Safety and Reliability Branch 43 Cooperation to Avoid Conflicts (Rule 31.4) • Cooperation to Avoid Conflicts • Notice to other utilities when construction or reconstruction may create line conflict in ADVANCE
  • 44. CPUC Utilities Safety and Reliability Branch 44 Abandoned lines (Rule 31.6) • Lines or portions of lines abandoned shall be removed by their owners to avoid public nuisance or hazard • Lines that are permanently abandoned shall be defined as those lines that are determined by their owner to have no foreseeable future use.
  • 45. CPUC Utilities Safety and Reliability Branch 45 General Arrangements of Lines (Rule 32) • Where two or more systems are concerned in any clearance, that owner or operator who last in point of time constructs or erects facilities, shall establish the clearance required in these rules from other facilities which have been erected previously. • Where supply and communication circuits or supply circuits of different voltage classifications are involved in crossings, conflicts or joint use, the higher voltage circuit shall in general be carried at the higher level.
  • 46. CPUC Utilities Safety and Reliability Branch 46 Ground and Neutrals (Rule 33) • Treat common neutral like a phase conductor • Rule need not apply to overhead lightning protection wires on metal structures or grounded wood structures. • The grounding of the neutral or any other conductor is permitted only for the purposes of stabilization and protection, not for use as a return conductor.
  • 47. CPUC Utilities Safety and Reliability Branch 47 Ground or Earth as a Conductor Rule 33.2 • Ground or earth shall not be used as a normal return or circuit conductor. • The neutral or any other conductor is permitted to be grounded only for the purposes of stabilization and protection. • “Stray” Voltage
  • 48. CPUC Utilities Safety and Reliability Branch 48 Foreign attachments (Rule 34) • Nothing in these rules shall be construed as permitting the unauthorized attachment ... of antennas, signs, posters, banners, decoration, wires, lighting fixtures, guys, ropes and other such equipment foreign to the purposes of overhead electric line construction.
  • 49. CPUC Utilities Safety and Reliability Branch 49 Tree Trimming (Rule 35) • Where overhead wires pass through trees, a reasonable amount of tree trimming shall be done in order that the wires may clear branches and foliage
  • 50. CPUC Utilities Safety and Reliability Branch 50 Tree Trimming (Rule 35) • The minimum clearances are established in Table 1, Case 13 for vegetation and Supply lines operating above 750 volts. • When a Communication Line or Supply Line operating at less than 750 volts, shows strain or evidences abrasion from tree contact, the condition shall be corrected.
  • 51. CPUC Utilities Safety and Reliability Branch 51 Clearances of Wires Above Ground (Rule 37, Table 1) • Rule 37, allows modifications of certain values in Table 1 for: – Temperature – Loading (Rule 43) – Other conditions • Define how to measure values in respective tables
  • 52. CPUC Utilities Safety and Reliability Branch 52 Clearances of Wires Above Ground (Rule 37, Table 1) • Table 1 – Breaks overhead facilities into 7 categories – Gives clearances for 14 different conditions – Has over 50 footnotes for the table
  • 53. CPUC Utilities Safety and Reliability Branch 53 Service Drop Clearances (Cont)
  • 54. CPUC Utilities Safety and Reliability Branch 54 Clearances of Wires from other Wires (Rule 38 & Table 2) • Table 2 – Breaks overhead facilities into 11 categories – Gives clearances for 21 different conditions – Has over 40 footnotes for the table
  • 55. CPUC Utilities Safety and Reliability Branch 55 Clearances of Wires from Signs (Rule 39, Table 2A) • Rule 39, allows modifications of values in Table 2A for: – Temperature – Loading (Rule 43) • Define how to measure values in respective tables
  • 56. CPUC Utilities Safety and Reliability Branch 56 Safety Factors (Section IV) • Grade of Construction (Rule 42, Table 3) • Light or Heavy Loading (Rule 43) • Safety Factor Can Be Determined (Rule 44) – Table 4 Lists safety factor at time of installation – Rule 44.2 allows for “2/3” reduction of values in Table 4 (due to deterioration) but in no case may safety factor fall below “1”
  • 57. CPUC Utilities Safety and Reliability Branch 57 Setting of Poles (Rule 49.1-C) • Table 6 shows minimum depths • If soil is not firm, deeper setting or special methods • Unguyed pole subject to strain or at corners should be set deeper
  • 58. CPUC Utilities Safety and Reliability Branch 58 Setting of Poles (Rule 49.1-C) • Poles are branded, to determine how deeply they are set: – <50ft, brand is 10 ft – >55 ft, brand is 14 ft • A 10% reduction in the pole setting depth is allowed due to: – Ground Erosion – Excavation
  • 59. CPUC Utilities Safety and Reliability Branch 59 Service Drop Covering (Rule 49.4-C7a) • Service drop conductors must be covered with the equivalent of standard double braid weatherproofing or of a design authorized for use by the Commission.
  • 60. CPUC Utilities Safety and Reliability Branch 60 High Voltage Signs (Rule 51.6) • Poles and cross arms carrying conductors of more than 750V shall be marked High Voltage • Signs must be secure, legible and clearly distinguishable.
  • 61. CPUC Utilities Safety and Reliability Branch 61 Risers and Runs (Rules 54.6, 74.6 & 84.6) • Ground wires of supply circuits must be protected by suitable covering in good repair throughout their length. • Lateral runs must be covered to outer position of conductor
  • 62. CPUC Utilities Safety and Reliability Branch 62 Service Drop Clearance from Buildings (Rules 54.8 & 84.8) • Horizontal clearances for Supply Service Drops from doors and windows – 3 feet • Communication Service Drops – Buildings on the premises served – no minimum but can not touch – Buildings on other premises – 8 feet • Except: Roofs whose slope exceeds 9 inches of rise per 12 inches of run or the service drop does not overhang the building by more than 6 feet
  • 63. CPUC Utilities Safety and Reliability Branch 63 Guy Marker (Rules 56.9, 66.7, 86.9) • Anchor guys are required to be marked by securely attached markers and in good repair
  • 64. CPUC Utilities Safety and Reliability Branch 64 Rule 94 • 94.1 Definition • 94.2 Maintenance and Inspection • 94.3 General Requirements • 94.4 Clearances • 94.5 Marking • 94.6 De-energizing • Exceptions
  • 65. CPUC Utilities Safety and Reliability Branch 65 Rule 94 Continued 94.5 Marking A. No antenna owner or operator shall install an antenna on a joint use pole unless such installation is subject to an agreement with the pole owner(s) that includes marking requirements that are substantially similar to and achieve at least the same safety standards as those set forth in Appendix H to GO 95. B. Joint use poles shall be marked with a sign for each antenna installation as follows: 1) Identification of the antenna operator 2) A 24-hour contact number of antenna operator for Emergency or Information 3) Unique identifier of the antenna installation.
  • 66. CPUC Utilities Safety and Reliability Branch 66 Rule 94 Continued 94.6 De-energizing No antenna owner or operator shall install an antenna on a joint use pole unless such installation is subject to an agreement with the pole owner(s) that includes de-energizing protocols that are substantially similar to and achieve at least the same safety standards as those set forth in Appendix H to GO 95.
  • 67. CPUC Utilities Safety and Reliability Branch 67 General Order 128 • Rules for Construction of Underground Electric Supply and Communication Systems
  • 68. CPUC Utilities Safety and Reliability Branch 68 General Order 128 • Sections • Change list • Decision No. 73195 GO 95 GO 128
  • 69. CPUC Utilities Safety and Reliability Branch 69 Browsing G.O. 128 • Section I – Purpose of G.O. 128 (Rule 11) – Grandfathering (Rules 12.3 and 12.4) • Section II – Definitions
  • 70. CPUC Utilities Safety and Reliability Branch 70 Requirements for Supply Systems • Section III – Clearance and Depths – Explosion Protection – Guarding Live Parts
  • 71. CPUC Utilities Safety and Reliability Branch 71 Requirements for Communication Systems • Section IV – Clearance and Depths – Explosion Protection – Guarding Live Parts – Police, Fire Alarm, and Traffic Control Circuits
  • 72. CPUC Utilities Safety and Reliability Branch 72 Appendices • Appendix A – Summary of Dimensions, Clearances, and Depth Requirements • Appendix B – Typical Illustrative Diagrams of Rules • Appendix C – Clearance from Railroad Tracks • Appendix D – Excerpts from Public Utilities Code
  • 73. CPUC Utilities Safety and Reliability Branch 73 General Order 128 • Definitions • General Provisions
  • 74. CPUC Utilities Safety and Reliability Branch 74 Definitions
  • 75. CPUC Utilities Safety and Reliability Branch 75 Manhole • A subsurface enclosure in an underground system containing working space large enough for a person to enter
  • 76. CPUC Utilities Safety and Reliability Branch 76 Handhole • A permanent opening in the route of an underground system, usually smaller than a manhole, with a removable top and affording access to cable runs and associated apparatus
  • 77. CPUC Utilities Safety and Reliability Branch 77 Cover • The radial distance between the surface of an underground cable or conduit and grade.
  • 78. CPUC Utilities Safety and Reliability Branch 78 Inspection (Rule 17.2) • Systems shall be inspected by the operator frequently and thoroughly for the purpose of insuring that they are in good condition so as to conform with these rules. • This rule does not specify time intervals, that is left up to the operator. • Same as Rule 31.2 of General Order 95
  • 79. CPUC Utilities Safety and Reliability Branch 79 Location Information (Rule 17.7) • Each party operating or owning facilities shall, upon request, provide information as to location of its underground facilities to any other party contemplating underground construction, or work, in the vicinity thereof. • Government Code Sections 4216-4216.9
  • 80. CPUC Utilities Safety and Reliability Branch 80 Identification (Rule 17.8) • Manholes, handholes , subsurface and self- contained surface- mounted equipment enclosures shall be marked as to ownership to facilitate identification by persons authorized to work therein and by other persons performing work in their vicinity.
  • 81. CPUC Utilities Safety and Reliability Branch 81 Investigation of Accidents (Rule 18) • Each owner or operator of supply lines shall establish procedures for the investigation of major accidents and failures for the purpose of determining the causes and minimizing the possibility of recurrence. – Incidents associated with utility facilities which cause property damage estimated at or about the time of the incident to be more than $50,000 – Incidents resulting from electrical contact which cause personal injury which require hospitalization overnight, or result in death • Same as Rule 17, of General Order 95
  • 82. CPUC Utilities Safety and Reliability Branch 82 Design, Construction and Maintenance (Rule 17.1) • Constructed, and maintained for their intended use • Work should be done in accordance with accepted good practice for the given local conditions • Same as Rule 31.1, of General Order 95
  • 83. CPUC Utilities Safety and Reliability Branch 83 APPENDIX A Tables 1 & 2 • Table 1 - Clearance and Depth Requirements for Supply and Communication Systems • Table 2 - Miscellaneous Dimensions and Clearance Requirements for Supply and Communication Systems
  • 84. CPUC Utilities Safety and Reliability Branch 84 Covers (Rules 32.7 & 42.7) • Covers of subsurface enclosures must: – Be secured in place – Withstand the forces that they will be subject to – Require a tool to open
  • 85. CPUC Utilities Safety and Reliability Branch 85 Guarding Live Parts (34.3-B) • Surface mounted equipment containing live parts shall be installed such that a wire or other material, cannot be passed into the enclosure when closed.
  • 86. CPUC Utilities Safety and Reliability Branch 86 Locking –Padmounted (Rule 34.3-C) • Padmounted equipment shall be made secure against entry by unauthorized person by: – Locks – Suitable means
  • 87. CPUC Utilities Safety and Reliability Branch 87 General Order 165 • Inspection Cycles for Electric Distribution Facilities
  • 88. CPUC Utilities Safety and Reliability Branch 88 General Order 165 I. Purpose II. Applicability III. Definitions IV. Standards for Inspection, Record- keeping, and Reporting Appendix A GO 165
  • 89. CPUC Utilities Safety and Reliability Branch 89 Purpose • The purpose of this General Order is to establish minimum requirements for electric distribution facilities, regarding: – maximum allowable inspection cycle lengths – condition rating – scheduling and performance of corrective action, – record-keeping, and – reporting
  • 90. CPUC Utilities Safety and Reliability Branch 90 Applicability • Section II, States GO 165 applies: – PG&E – PacifiCorp – SDG&E – SP&P – SCE • Decision 97-03-070 – Requested comments concerning the application of GO 165 to Municipals and Publicly Owned Electric Utilities • Decision 98-03-036 – GO 165 applies to Municipals and Publicly Owned Electric Utilities • Decision 98-10-059 – Denied CMUA’s request to rehear decision • Decision 99-12-052 – Denied CMUA’s request to modify 98-03-036
  • 91. CPUC Utilities Safety and Reliability Branch 91 Definitions • "Urban" shall be defined as those areas with a population of more than 1,000 persons per square mile as determined by the United States Bureau of the Census. • "Rural" shall be defined as those areas with a population of less than 1,000 persons per square mile as determined by the United States Bureau of the Census.
  • 92. CPUC Utilities Safety and Reliability Branch 92 Definitions • "Patrol" shall be defined as a simple visual inspection, of applicable utility equipment and structures, that is designed to identify obvious structural problems and hazards. Patrols may be carried out in the course of other company business. • "Detailed" inspection shall be defined as one where individual pieces of equipment and structures are carefully examined, visually and through use of routine diagnostic test, as appropriate, and (if practical and if useful information can be so gathered) opened, and the condition of each rated and recorded.
  • 93. CPUC Utilities Safety and Reliability Branch 93 Definitions • "Intrusive" inspection is defined as one involving movement of soil, taking samples for analysis, and/or using more sophisticated diagnostic tools beyond visual inspections or instrument reading. • "Corrective Action" shall be defined as maintenance, repair, or replacement of utility equipment and structures so that they function properly and safely.
  • 94. CPUC Utilities Safety and Reliability Branch 94 Standards for Inspection, Record- keeping, and Reporting • Each utility shall conduct inspections of its distribution facilities, as necessary, but in no case may the period between inspections (measured in years) exceed the time specified in the table.
  • 95. CPUC Utilities Safety and Reliability Branch 95 Standards for Inspection, Record- keeping, and Reporting • For all inspections, within a reasonable period, company records shall specify: – The circuit, area, or equipment inspected – The name of the inspector, the date of the inspection – Any problems identified during each inspection – A scheduled date of corrective action. – For detailed and intrusive inspections, companies shall also rate the condition of inspected equipment. – Upon completion of corrective action, company records will show the nature of the work, the date, and the identity of persons performing the work.
  • 96. CPUC Utilities Safety and Reliability Branch 96 Standards for Inspection, Record- keeping, and Reporting • Each utility shall file annual reports for every following year by no later than July 1. The report shall identify: – The number of facilities, by type which have been inspected during the previous period. – Identify those facilities which were scheduled for inspection but which were not inspected – The total and percentage breakdown of equipment rated at each condition rating level, including that equipment determined to be in need of corrective action. – Present the total and percentage of equipment which was and was not corrected during the reporting period. – The percentage of equipment in need of corrective action, but with a scheduled date beyond the reporting period, classified by the amount of time remaining before the scheduled action. – All of the above information shall be presented for each type of facility identified in the attached table and shall be aggregated by district.
  • 97. 2020------------Wood poles which passed intrusive inspection 1010xx21Wood Poles over 15 years which have not been subject to intrusive inspection ------xx21Wood Poles under 15 years ------xx21Streetlighting ------5521Overhead Conductor and Cables ------5521Padmounted ------3321Underground ------5521Overhead Regulators/Capacitors ------5521Padmounted ------3321Underground ------5521Overhead Switching/Protective Devices ------5521Padmounted ------3321Underground ------5521Overhead Transformers RuralUrbanRuralUrbanRuralUrban IntrusiveDetailedPatrol Table
  • 98. CPUC Utilities Safety and Reliability Branch 98 Enforcement • Only the Commission can levy fines • We rely on utility’s desire to have a good system • Collegial Approach • What about Communication Utilities?
  • 99. CPUC Utilities Safety and Reliability Branch 99 Current Utilities Safety and Reliability Branch Issues • Communications Enforcement • Substations • Wireless Antenna Rule • New GO for 25 kV Electric Railroads