SlideShare a Scribd company logo
1 of 97
Download to read offline
Corporate Presentation Merging with Technologies
Smart Metro Rail Project (2017)
3
India Culture Golden ERA
Trains in India /Move Smart/Keep Moving
Aab Hum Sudherenge
Need for automation ..
• Enhancement of safety
• Enhance passenger convenience
• Minimum manning to reduce operational
costs
• Improve efficiency of operations &
maintenance
• Optimising sectional capacity and energy
efficient operation
• Minimum maintenance time for ensuring
higher availability
Areas of automation
• Signaling system & Train Control
• Telecommunication System
• Rolling Stock
• Automatic Fare Collection System
• Traction and Power control
• Fire detection and Mitigation System
• Building Management Systems
• Lifts and Escalators
• Automation of maintenance and depot machinery
• Automation of training
METRO OPTIONS
Straddle type monorail
Suspended monorail
Tramways Bus Rapid Transit System
Metro Train
• India Plan To have METRO RAIL Connectivity with all Major Cities
• Building and Infra Facilities
• Station Buildings Ground/Upper/Under Ground
• Networking and Communication
• Power Grid + DG+Solar+Wind+UPS
• Parking Management
• Passenger Information Systems(Display)
• Building Management Systems
• DEPOT and Sub Station 11KV-66KV
• Signal and Traffic
• Water Storage and Distribution Management
• Link With Major Bus Station/Railway Station Plan for Airport
SMART METRO RAIL Project India
by JMV LPS LTD
Systems
Systems
Systems
Systems
• The origin of railway signaling dates back to 1856 when John
Saxby received the first patent for interlocking switches and
signals
14
• Electricalbased solutions: train detection, signals, switching & interlockings
• Cab signalling systems for advanced signalling information onboard and for
automatic train stops when passing red signals.
• Traffic management from centralised control centre.
15
• Train position is reported to Operational Control Centre (OCC) by radio
communication.
• OCC calculates maximum speed dynamically and sends it back to the
train.
• Trackside equipment is reduced to minimum.
16
ATP
TDMS
ATO
ATC
DMI
Phw
RS
TIMS
Radio
DMC
(Head)
ATP
TDMS
ATO
ATC
Phw
RS
Radio
DMC
(Tail)
DMI
AntennaPick-up
coil
Pick-up
coil
Antenna
TC
Train Borne Architecture
TIMS
Train borne Equipment
 Pick up Coil
 Beacon antenna
 Odometer
 DMI
 Train borne ATC cubicle
 SCS (Safety Cut Out Switch)
 SCS counter
 ATC selector switch
 DMI fan power supply status indicator
 ATP MCBs
OCC Building
SCADA DISPLAY AND CONTROL SCREEN IN OCC BUILDING
Communication System
21
COMMUNICATION SYSTEM
Communication System
 Fibre Optic Transmission System (FOTS)
 Telephone System (EPABX & Direct Lines)
 Radio System (TETRA)
 Broad Band Radio System (BBRS)
 Closed Circuit Television System (CCTV) & Video Analytics
 Automatic Passenger Information Display System (PIDS)
 Public Address system (PAS)
 Master Clock System
 Telecom- Supervisory Control and Data Acquisition (T-
SCADA)
CCTV
Central Surveillance Room
Operational Security/Passengers Information
Communication System
Passenger Address & Information System (PA/PIS)
Contract:2RS-DM 25
 Public Address (PA) to Passenger including.
 Live announcement to all passengers by OCC via Train Radio.
 Broadcasting of pre-recorded announcement based on real time
information
• Door Messages for all Stations.
• Station Messages for particular Station.
• Special & Emergency Messages.
 manual broadcasting by Train Driver.
 Emergency passenger announcement on the Train by Operation
Control centre (OCC) via Train Radio System.
 Destination & Train number indicator on Front Cab head.
Automation in Rolling Stock
Contract:2RS-DM 26
FUNCTIONS OF TMS
Sample display screen for Door operating status
Automation in Rolling Stock
Customer Care – Station Level
Customer Care Office is for providing services such as Card / Token
refund/replacement, ticket adjustment by operator to passenger,
Collection of penalty.
Remaining Value Checking Terminal
(RVCT)
The RVCT for checking balance and the validity of a ticket.
Ticket Topping-up outlets
•Ticket Office Machines (TOM)
•Ticket Vending Machines (TVM)
•SBI ATM
•SBI Netbanking
•BMRCL website
•Mobile Phone banking
•Airtel Money service & Airtel retail
Network for any service provider phone
Automatic Gates
AFC Gates (Automatic Gates)
• Permit one passenger per ticket to enter and exit the system
• Deduct correct fare from Stored Value Tickets
• Prevent exit of over-stayed / over-travelled /invalid tickets
• Ticket shown on right hand side
• Children below 3 ft to be taken in front
and close
Emergency Trip System provided at all Metro Station Platforms
Automation of Safety Systems - Fire Detection & Mitigation
Fire Alarm Control Panel Manual Call Point
Smoke cum heat detectorManual Call Point Strobe
Automation in Lifts and escalators
Automation in control of Electrical Installations at Stations -
Building Management System
Automation in control of Electrical Installations at Stations -
Building Management System
Automation in control of Electrical Installations at Stations - Building
Management System
Rolling Stock and Equipments
Integrated Power Development
Scheme (IPDS)
• An integrated scheme for urban areas covering:
• •S art Meteri g a d Ta per-proof meters at homes
• •I frastru ture upgradation in urban areas -
Comprehensive sub transmission & distribution
• •U dergrou d a li g & GIS Su statio s i de sely
populated areas
• •IT i ple e tatio for etter usto er ser i e
• •Solar i stallatio s like rooftop solar pa els also
covered
• •Outlay of Rs. , crores
Traction Power Supply System
• 66 kV System
• Receiving Substations 66/33kV
• 33 kV Cable Distribution System
• Auxiliary Substations - 33kV / 415V
• Traction Substations – 33kV / 750 V dc
• 750 V DC Third Rail System
• Earthing, Bonding and Stray Current Mitigation & Monitoring
System
• SCADA and ETS system
38
Network Configuration
66kV/33kV RSS Locations
‘A’ Peenya
RSS
‘B’
Baiyapanhalli
RSS
‘C’
Puttenhalli
RSS
‘D’
Mysore Road
RSS (GIS)
Nelamangala 400kV /
220kV (RTPS, Nagajhari,
Sharavati etc.
400 kV HVDC
Kolar / Talcher
220 kV
400 kV
400 kV
Peenya
GSS
Hoody GSS
HAL GSS
66 kV
66 kV
66 kV
220 kV
66 kV
400 kV
400 kV / 220
kV Somanahalli
220 kV RR
Nagar SS
220 kV
Subramaniump
ura SS
Khoday
GSS
220 kV 220 kV
66 kV 66 kV
66 kV
66 kV
220 kV
220 kV
400 kV
66 kV
220 kV
400 kV
V Valley
GSS
REMC
O SS
39
Panoramic view of the RSS and Switchyard
Auxiliary Sub Station (ASS) – 33 kV/415 V
Electrical Loads of Metro Stations fed from
Auxiliary Sub Station
• Lighting and signages
• Power Supply to equipment installed in Operational Rooms
• Air conditioners of Operational Rooms – Station Control Room,
Signaling Equipment Room, Telecom Equipment Room, UPS and
Battery Room
• Lifts & Escalators
• Pumps for fire mitigation and water supply to toilets
• Ventilation fans of Sub Stations
• Fire Alarm and Detection System
500 kVA Transformer in a Typical ASS
Traction Substations – 33 kV / 750 V dc
Function : 33 kV stepped down to 2 X 292 V and rectified to 750 V dc for feeding to third rail
2850 kVA Rectifier Transformer Rectifier
DC Panels SCD/Over Voltage Protection Device
SCADA (SUPERVISORY CONTROL AND
DATA ACQUISITION) SYSTEM
Purpose : to monitor and control
• receiving/distribution of power at 66kv
and 33kv
• Auxiliary power for all auxiliary
equipments at the stations
• Traction power for powering the rolling
stock
Automation of Depot Machinery
Under floor pit wheel lathe Mobile Lifting jack
Auto Wash Plant
Pit Jacks
Remote Controlled
Electric Bogie Tractor
Portable Battery Topping
Up Cart
Potable Traction Motor
Dust remover
Maintenance &Precausion
Sikhana to Padega Hi Follow NBC2016
External/Internal Surge Source
LIGHTNING STRIKE DAMAGE
Sources for Extra Current /Voltages from different areas……
 Signal Surges Generation due
direct lightning
 Switching operations of
heavy duty machines like
motors, lifts, AC units,
refrigerator, welding machine
etc.
 Ground Potential Rise
Short Circuit due Wire/ Cables
Problems due to Direct or In-Direct Electrical Installation.
Switching actions
Switching actions occur almost everywhere
where work is done with electrical energy.
Especially vulnerable are areas in which large
inductive loads are switched, for example:
• Motors
• Transformers
• Chokes
• Climate control installations
• Welding equipment
• Long light strings
Effects: Overvoltages (surges) on network lines
Cause: High current steepnesses on switching actions
lead to transient surges (overvoltages) on the mains
wiring.
Direct strike on a low-voltage overhead line
The preconditions for a direct strike on a low-
voltage overhead line are not the same as for
direct strikes on high-voltage overhead lines.
The fundamental difference is in the proximity
to the building, which permits the conduction of
partial lightning currents.
Effects: Partial lightning currents and voltage surges
in the low-voltage network.
Cause: the amplitude of the lightning impulse
current
The 100% of lightning energy breaks down as
follows:
a) 50% of the lightning current will flow through
the ground
b) 50% of the lightning current will flow over the
connected metal parts out of the building:
• about 10% to the water pipe (metal)
• about 10% to the gas pipe (metal)
• about 10% to the oil pipe (metal tank)
• about 10% to the sewage pipe
• a out % to the po er supplier’s i o i g feed
• max. 5% or 5 kA shared across all data lines
50 %
50 %
Equipotential bonding for lightning protection according IEC 61024-
1 and IEC 61312-1; IEC62305
In India & Sri Lanka Only Chance is Power Line
Approximately 50 % of Total Lightning Current has
to be diverted to Power lines
More Picture
Fire Component Level
Solar PV Power Plant
Fire Accident in Chemical & Process Plant
Reason Lose Contact Earthing Disorder and Lightning
An Arcing Fault is the flow of current through
the air between phase conductors or phase
conductors and neutral or ground. Concentrated
radiant energy is released at the point of arcing
an a small amount of time resulting
in Extremely High Temperature.
Follow Safety in Electrical Instalation Shocks
Earthing Design and Require Result
• For substation Large Power below 1.00Ohm
• For substation Small Power below 2.00Ohm
• SCADA/TELECOM and AutomationFor substation Large
Power below 0.50Ohm
• Tower and Other Structure between 8-15Ohm
• Lightning Surge Protection 50KA below 5Ohm or 100KA
between 8-15Ohm
• Follow Standard IEC /IEEE
• Recommended use of Hybrid Metal to Protect from Theft
Copper Clad Steel/Alumineum Clad Copper
• Exothermeic weld IEEE 837
Surge in Systems and Result
Surge in DC Application
Surge Protection use Recommendation
v
JMV LPS Products
Copper Cladded Conductor For Electrical
Installation
The Copper Clad Steel Grounding Conductor is made up of steel with the coating of 99.99% pure copper. These
conductors/ wires
or strands are equipped with the strength of steel with the conductivity and copper with the better corrosion
resistance property. The concentric copper cladding is metallurgic ally bonded to a steel core through a continuous,
solid cladding process using pressure rolling for primary bonding. The copper cladding
thickness remains constant surrounding steel. We use different steel grades for the steel core result in Dead Soft
Annealed, High strength and Extra High Strength Characteristics.
The Copper Clad Steel Wire yields a composite conductivity of 21%, 30% and 40% IACS, and available in Annealed
and Hard drawn. We are delivering products with varied conductivity and tensile strength as per the customer need.
Further, the wire can be processed to be silver plated or tinned copper clad steel wire.
Most Efficient JointProcess
It is efficient and superior to all existing surface –to-surface
mechanical retention connectors.
What is Exothermic Welding System?
Copper to Bi-Metal and Alumenium
Types of Exothermic Joints:
Possible to join any bi metal except aluminum
Exothermic welding is a process of making maintain free highly molecular bonding process is superior in
performance connection to any known mechanical or compression-type surface-to-surface contact connector.
Exothermic weld connections provide current carrying (fusing) capacity equal to that of the conductor and will
not deteriorate with age.
 It offers Electrical connections between two or more copper to copper and copper to steel conductors.
 Highly portable method as it does not require any external power source or heat source, so it can be done
almost anywhere.
 It provides strong permanent molecular bond among metallic conductors that cannot loosen and further will
not deteriorate with age.
 Connection does not corrode with time and it offers permanent conductivity.
Copper Clad Steel Solid ROD and Conductor
LIGHTNING FORMATION
Facts about Lightning
• A strike can average 100 million volts of electricity
• Current of up to 200,000 amperes
• Can generate 54,000 oF
• 10/350MicroSec/50KA Fault Current/Discharge in
Nano Sec
Protection
Earthing Design100KA Fault Current/Joints Exothermic
/Flexible Down Conductor with Shortest Route &
Less Corner
• Lightning Protection Standard use in India
(IS2309 Now IEC 62305-5)NBC2016
Working Principle Angullar No Compromise with Design
Max Protection 30Mtrs from One
No Product warrenty from Manufacturer
High Maintenance Require
NFC17-102(2011) Now Europeon Standard(ESE LA)
Working Principle Radius Compromise with Design
Possible with Increasing Qty of ESE
Max Protection 109 Mtrs Radius from One
Manufacturing Warrenty and Test Certificate for Products
Available
Maintenance on Call Basis
Lightning Risk assessment Study is actually the measure of risk of a lightning strike and
probability of damages. As Per IEC62305-2.
All these calculations are based on:
lightning strike density in that particular area (provided by OMV i.e. Ng = 8),
Danger for people,
Occupation coefficient of structure,
Relative location of site,
Fire Risk,
Associated services,
Electrical Lines,
Lightning Protection Level,
Surge Arrestor and
Dimensions of installation.
Lighting Strike Density (Ng)
It is the measure of lightning strikes per kilometre square per year in the particular area.
Higher the lighting strike density, higher the probability of lightning strike which needs higher level of lightning protection level.
Danger for People (h)
It is the factor of presence of people and panic in the building in case of a lightning strike
No particular danger 1
Low panic level(<=2 floors, < 100 persons 2
Medium risk of panic (< 1000 persons) 5
Difficult to evacuate (disabled people, hospitals) 5
High risk of panic (> 1000 persons) 10
Hazard for surroundings or environment 20
Contamination of surroundings or environment 50
Occupancy Coefficient (Lf1)
It is the risk reduction factor with respect to theoccupancy of the building / installation. For example, loss due to lighting strike is higher in hospital as compared to a store / warehouse.
Structure unoccupied 0.1
Structure normally occupied 0.01
Relative Location of Site (Cd)
It is the risk reduction factor with respect to the location and surrounding of the building / installation. For example, chance of lighting strike is minimized if the building is near to a high tower.
Structure surrounded by higher objects or trees 0.25
Structure surrounded by similar or lower objects 0.5
Isolated structure-No other objects nearby 1
Isolated structure on top of a hill or a hillock 2
Fire Risk (rf)
It is the risk reduction factor with respect to the flammability of the material present in the building / installation. For example, in case of lighting strike, loss will be very high at a gas station as compare to the cement store.
Explosion 1
High 0.1
Ordinary 0.01
Low 0.001
Lightning Risk Calcuator as per IEC6305
LIGHTNING RISK ASSESSMENT CALCULATIONS
Building / Installation : KTC Tower
Building ID No. KTC, Mall Road
LIGHTNING DENSITY Ng= 8
STRUCTURE
Length L(m) L= 12
Width W(m) W= 15
Height H(m) Hi= 10
Chimney/Tower height (m) T= 2
DANGER FOR PEOPLE h= No particular danger
OCCUPATION OF THE STRUCTURE Lf1= Structure normally occupied
LIGHTNING CONDUCTOR Pd= Protection Level IV
Electrical Line Ai= Underground
RELATIVE LOCATION OF THE STRUCTURE Cd= Structure surrounded by higher objects or trees
FIRE RISK rf= Low
SERVICE Lf2= Gas, water
SURGE ARRESTOR Pi= None
RESULTS OF THE RISK ASSESSMENT
Risk of human loss R1= ACCEPTABLE
Risk of loss of service R2= ACCEPTABLE
Risk of loss of cultural heritage R3= ACCEPTABLE
PASSIVE PROTECTION SYSTEM
The Simple Rod air terminal is composed from a metallic rod with 2 to 8 m height dominating
the structure to protect, and linked to 2 down conductors minimum, and 2 earthing systems.
The protection radius ensured by this air terminal which is limited to 30 m more or less
(Protection level IV, height = 60 m), especially dedicated to the protection of small structures or
areas like to ers, hi eys, ta ks, ater to er, a te a asts… The EN -3 standard
describes the installation procedure for these air terminals.
13 Simple Rods, 13 down conductors, and 13 earthing systems are necessary to ensure the
protection below :
The meshed cage protection is composed from a meshing in roof surface and in the front face around the
uildi g. Surrou di g the roof surfa e, a d o high poi ts, apture poi ts are positio ed. A o du tors’
network is placed at the outer perimeter of the roof. This network is completed by transverse conductors.
The size of the meshing is 5 to meters, and depends on the efficiency needed for the protection. On the
front face of the building, the down conductors are linked at the top to the meshing of the roof. And, down,
to specific earthing systems. The distance between two conductors is 10 to 25 meters, and depend on the
efficiency needed for the protection. The EN 62305-3 describes the installation procedure for this method.
Generally, this method is heavy and expensive, due to the complexity of the structures to protect.
26 capture points, 26 down conductors and a grounded loop earthing system are necessaries to ensure the
protection of the structure here below :
The catenary wires protection is a method closed to the meshed cage principle, because it is
constituted with meshing of the conductors far from the structure to protect, to avoid any
contact with lightning current.
Catenary wires are located over the structure to protect, connected to down conductors and
specific earthing systems. The width of the meshing and distance between the down conductors
must respect the same rules as for the meshed cage. The EN 62305-3 describes the installation
procedure for this method.
Generally, this method is heavy and expensive, due to the complexity of the structures to
protect.
The ESE air terminal is a terminal which enables to generate artificially an upward leader earlier than a
simple rod, with an ionization system, in order to establish a special impact on its point. The capture of the
lightning strike being faster than a simple rod, this technology enables to benefit from larger protection
areas, ensuring protection for large dimensions structures.
The ge erated prote tio radius depe ds o the early strea er e issio alue of the air ter i al Δt i µs ,
its height, and the efficiency of the protection. The protection radius ensured by this type of air terminal is
120 m (Protection level IV, height = 60 m , early streamer emission time 60µs) The NFC 17-102 standard
describes the installation procedure for this type of air terminal.
The installation of this type of air terminal is easy and cheaper than other technologies. It can protect whole
buildings with one E.S.E. air terminal. It enables the protection of a structure and its environment, the
protection of opened areas and well integrate in the architecture of a structure without aesthetic alteration.
1 ESE, 2 down conductors and 2 earthing systems are necessary to ensure the protection below :
Installation
ESE AT with radius protection form 32 mtr to 107 mtr.
DMC Insulator .
GI/FRP Mast .
Down Conductor Copper / Copper Cadmium
Cable 70 sq. mm
Copper Bonded Ground Earthing
Step – 1
Step – 2
Step – 3
Joint all phase wire/ cable with the help of
crimping tools and lugs
Fixed the separation sheet between all wires/
cables
Close the filled Silicon enclosure from top and
bottom , complete installation is done.
Thimble
Separation Sheet
Gel / Silicon
Features :
Provides cable with cable connections and jointing wires in switchboard / electric boxes Being a jelly it can be
easily fit into molds of any shape and size.
Helps in safeguarding electrical connections and also protects electrical connection joints from catching fire, sparking
and leakage current.
Eradicates all the possibilities of fire, electric shocks and sparks, etc. causes due to improper electrical connection
joints and safeguards structure, equipment and person.
Offers safety to your electrical joints from ageing, corrosion, moisture and also observes leakage current.
Advantages :
Nontoxic
Insulating
Highly reliable operation
Maintenance Free
Repairable
Cost Effective
High repeat value
Elasticity
Shape retention
JMV’s Clients
Neeraj Saini – 9910398538
Rahul Verma – 9910398535
Manav Chandra - 9910398999
manav@jmv.co.in

More Related Content

What's hot

Introduction on indian codes as applied in electrical design
Introduction on indian codes as applied in electrical designIntroduction on indian codes as applied in electrical design
Introduction on indian codes as applied in electrical designAsif Eqbal
 
A solution to remote detection of illegal electricity.
A solution to remote detection of illegal electricity.A solution to remote detection of illegal electricity.
A solution to remote detection of illegal electricity.Praveen Kumar
 
Wireless power theft monitoring
Wireless power theft monitoringWireless power theft monitoring
Wireless power theft monitoringBiswajit Pratihari
 
Track 2 session 6 - st dev con 2016 - wireless charging technologies
Track 2   session 6 - st dev con 2016 - wireless charging technologies Track 2   session 6 - st dev con 2016 - wireless charging technologies
Track 2 session 6 - st dev con 2016 - wireless charging technologies ST_World
 
An application of Power Line Communication
An application of Power Line CommunicationAn application of Power Line Communication
An application of Power Line CommunicationSujit Nayak
 
Project paper
Project paperProject paper
Project paperchigongo
 
possible emc slides
possible emc slidespossible emc slides
possible emc slidesWissam Fawaz
 
A Solution to remote detection of illegal electricity
A Solution to remote detection of illegal electricityA Solution to remote detection of illegal electricity
A Solution to remote detection of illegal electricityAhmed Aslam
 
Automation of load using mobile phone.
Automation of load using mobile phone.Automation of load using mobile phone.
Automation of load using mobile phone.Justin Rams
 
Ppt power theft identification and detection using gsm
Ppt power theft identification and detection using gsmPpt power theft identification and detection using gsm
Ppt power theft identification and detection using gsmradha krishna
 
EE-55 Power Cables Testing & Fault Location
EE-55 Power Cables Testing & Fault LocationEE-55 Power Cables Testing & Fault Location
EE-55 Power Cables Testing & Fault LocationRina Florentes
 
Wireless charge share between two mobiles
Wireless charge share between two mobilesWireless charge share between two mobiles
Wireless charge share between two mobilesMOHITH Royal
 
wireless energy meter monitoring with automatic tariff calculation ppt
wireless energy meter monitoring with automatic tariff calculation pptwireless energy meter monitoring with automatic tariff calculation ppt
wireless energy meter monitoring with automatic tariff calculation pptsheefa kauser
 
Regulatory Best Practices
Regulatory Best PracticesRegulatory Best Practices
Regulatory Best Practiceschaman12
 
Power line communication
Power line communicationPower line communication
Power line communicationAhmad AL CHAMI
 

What's hot (20)

Report its
Report itsReport its
Report its
 
Introduction on indian codes as applied in electrical design
Introduction on indian codes as applied in electrical designIntroduction on indian codes as applied in electrical design
Introduction on indian codes as applied in electrical design
 
A solution to remote detection of illegal electricity.
A solution to remote detection of illegal electricity.A solution to remote detection of illegal electricity.
A solution to remote detection of illegal electricity.
 
Wireless power theft monitoring
Wireless power theft monitoringWireless power theft monitoring
Wireless power theft monitoring
 
Power line communication
Power line communicationPower line communication
Power line communication
 
Track 2 session 6 - st dev con 2016 - wireless charging technologies
Track 2   session 6 - st dev con 2016 - wireless charging technologies Track 2   session 6 - st dev con 2016 - wireless charging technologies
Track 2 session 6 - st dev con 2016 - wireless charging technologies
 
An application of Power Line Communication
An application of Power Line CommunicationAn application of Power Line Communication
An application of Power Line Communication
 
POWER LINE COMMUNICATION
POWER LINE COMMUNICATIONPOWER LINE COMMUNICATION
POWER LINE COMMUNICATION
 
Project paper
Project paperProject paper
Project paper
 
possible emc slides
possible emc slidespossible emc slides
possible emc slides
 
A Solution to remote detection of illegal electricity
A Solution to remote detection of illegal electricityA Solution to remote detection of illegal electricity
A Solution to remote detection of illegal electricity
 
Automation of load using mobile phone.
Automation of load using mobile phone.Automation of load using mobile phone.
Automation of load using mobile phone.
 
Tariff Metering
Tariff MeteringTariff Metering
Tariff Metering
 
Power Line communication
Power Line communicationPower Line communication
Power Line communication
 
Ppt power theft identification and detection using gsm
Ppt power theft identification and detection using gsmPpt power theft identification and detection using gsm
Ppt power theft identification and detection using gsm
 
EE-55 Power Cables Testing & Fault Location
EE-55 Power Cables Testing & Fault LocationEE-55 Power Cables Testing & Fault Location
EE-55 Power Cables Testing & Fault Location
 
Wireless charge share between two mobiles
Wireless charge share between two mobilesWireless charge share between two mobiles
Wireless charge share between two mobiles
 
wireless energy meter monitoring with automatic tariff calculation ppt
wireless energy meter monitoring with automatic tariff calculation pptwireless energy meter monitoring with automatic tariff calculation ppt
wireless energy meter monitoring with automatic tariff calculation ppt
 
Regulatory Best Practices
Regulatory Best PracticesRegulatory Best Practices
Regulatory Best Practices
 
Power line communication
Power line communicationPower line communication
Power line communication
 

Similar to Metro rail project in india year 2017

Electrical And Electronic Equipments used in DMRC At Intelligence Platforms
Electrical And Electronic Equipments used in DMRCAt Intelligence PlatformsElectrical And Electronic Equipments used in DMRCAt Intelligence Platforms
Electrical And Electronic Equipments used in DMRC At Intelligence PlatformsPoojaKumari762
 
Scada presentation
Scada presentationScada presentation
Scada presentationAmit Kumar
 
Extra high voltage long ac transmission lines
Extra high voltage long ac transmission linesExtra high voltage long ac transmission lines
Extra high voltage long ac transmission linesShivagee Raj
 
20BEE042 5th semester Internship PPT.pptx
20BEE042 5th semester Internship PPT.pptx20BEE042 5th semester Internship PPT.pptx
20BEE042 5th semester Internship PPT.pptxSumitRajput83
 
Residual current monitorning (rcm) prevent electrical fire &amp; hazards
Residual current monitorning (rcm) prevent electrical fire &amp; hazardsResidual current monitorning (rcm) prevent electrical fire &amp; hazards
Residual current monitorning (rcm) prevent electrical fire &amp; hazardsMessung Electrical Engineering
 
Industrial Training PPT-Divyansh Khelani.pptx
Industrial Training PPT-Divyansh Khelani.pptxIndustrial Training PPT-Divyansh Khelani.pptx
Industrial Training PPT-Divyansh Khelani.pptxDivyanshKhelani1
 
INTERNSHIP REPORT (FINAL)
INTERNSHIP REPORT (FINAL)INTERNSHIP REPORT (FINAL)
INTERNSHIP REPORT (FINAL)Sindhuja Balaji
 
Power Line Carrier Communication
Power Line Carrier CommunicationPower Line Carrier Communication
Power Line Carrier CommunicationNeha Gethe
 
ibrahim saleh c v (1)
ibrahim saleh c v (1)ibrahim saleh c v (1)
ibrahim saleh c v (1)Ibrahim saleh
 
ibrahim saleh c v (1)
ibrahim saleh c v (1)ibrahim saleh c v (1)
ibrahim saleh c v (1)Ibrahim saleh
 
Power line carrier communication(with awesome animation work)
Power line carrier communication(with awesome animation work)Power line carrier communication(with awesome animation work)
Power line carrier communication(with awesome animation work)Mohit Agarwal
 
Techno Quest - Profile
Techno Quest -  ProfileTechno Quest -  Profile
Techno Quest - Profilekrunaldesai20
 
RTD FasTracks - INCOSE Colorado Front Range Chapter Presentation - Dec, 2014
RTD FasTracks - INCOSE Colorado Front Range Chapter Presentation - Dec, 2014RTD FasTracks - INCOSE Colorado Front Range Chapter Presentation - Dec, 2014
RTD FasTracks - INCOSE Colorado Front Range Chapter Presentation - Dec, 2014INCOSE Colorado Front Range Chapter
 
3 p strategy sems 10-v4
3 p strategy  sems 10-v43 p strategy  sems 10-v4
3 p strategy sems 10-v4guestec6b92bb
 
SICAM FCM – Feeder Condition Monitor
SICAM FCM – Feeder Condition MonitorSICAM FCM – Feeder Condition Monitor
SICAM FCM – Feeder Condition Monitorashwini reliserv
 
Sro Project Brief
Sro Project BriefSro Project Brief
Sro Project Briefenergyvijay
 
Distribution System Automation
 Distribution System Automation  Distribution System Automation
Distribution System Automation Adithya Ballaji
 
Avoiding Cyberterrorism Threats Inside Hydraulic Power Generation Plants
Avoiding Cyberterrorism Threats Inside Hydraulic Power Generation PlantsAvoiding Cyberterrorism Threats Inside Hydraulic Power Generation Plants
Avoiding Cyberterrorism Threats Inside Hydraulic Power Generation PlantsManuel Santander
 

Similar to Metro rail project in india year 2017 (20)

Electrical And Electronic Equipments used in DMRC At Intelligence Platforms
Electrical And Electronic Equipments used in DMRCAt Intelligence PlatformsElectrical And Electronic Equipments used in DMRCAt Intelligence Platforms
Electrical And Electronic Equipments used in DMRC At Intelligence Platforms
 
Scada presentation
Scada presentationScada presentation
Scada presentation
 
RVNL_Report_ppt
RVNL_Report_pptRVNL_Report_ppt
RVNL_Report_ppt
 
Extra high voltage long ac transmission lines
Extra high voltage long ac transmission linesExtra high voltage long ac transmission lines
Extra high voltage long ac transmission lines
 
20BEE042 5th semester Internship PPT.pptx
20BEE042 5th semester Internship PPT.pptx20BEE042 5th semester Internship PPT.pptx
20BEE042 5th semester Internship PPT.pptx
 
Residual current monitorning (rcm) prevent electrical fire &amp; hazards
Residual current monitorning (rcm) prevent electrical fire &amp; hazardsResidual current monitorning (rcm) prevent electrical fire &amp; hazards
Residual current monitorning (rcm) prevent electrical fire &amp; hazards
 
Industrial Training PPT-Divyansh Khelani.pptx
Industrial Training PPT-Divyansh Khelani.pptxIndustrial Training PPT-Divyansh Khelani.pptx
Industrial Training PPT-Divyansh Khelani.pptx
 
INTERNSHIP REPORT (FINAL)
INTERNSHIP REPORT (FINAL)INTERNSHIP REPORT (FINAL)
INTERNSHIP REPORT (FINAL)
 
Power Line Carrier Communication
Power Line Carrier CommunicationPower Line Carrier Communication
Power Line Carrier Communication
 
ibrahim saleh c v (1)
ibrahim saleh c v (1)ibrahim saleh c v (1)
ibrahim saleh c v (1)
 
ibrahim saleh c v (1)
ibrahim saleh c v (1)ibrahim saleh c v (1)
ibrahim saleh c v (1)
 
Power line carrier communication(with awesome animation work)
Power line carrier communication(with awesome animation work)Power line carrier communication(with awesome animation work)
Power line carrier communication(with awesome animation work)
 
Techno Quest - Profile
Techno Quest -  ProfileTechno Quest -  Profile
Techno Quest - Profile
 
RTD FasTracks - INCOSE Colorado Front Range Chapter Presentation - Dec, 2014
RTD FasTracks - INCOSE Colorado Front Range Chapter Presentation - Dec, 2014RTD FasTracks - INCOSE Colorado Front Range Chapter Presentation - Dec, 2014
RTD FasTracks - INCOSE Colorado Front Range Chapter Presentation - Dec, 2014
 
3 p strategy sems 10-v4
3 p strategy  sems 10-v43 p strategy  sems 10-v4
3 p strategy sems 10-v4
 
SICAM FCM – Feeder Condition Monitor
SICAM FCM – Feeder Condition MonitorSICAM FCM – Feeder Condition Monitor
SICAM FCM – Feeder Condition Monitor
 
Sro Project Brief
Sro Project BriefSro Project Brief
Sro Project Brief
 
Distribution System Automation
 Distribution System Automation  Distribution System Automation
Distribution System Automation
 
CEA Regulations.pptx
CEA Regulations.pptxCEA Regulations.pptx
CEA Regulations.pptx
 
Avoiding Cyberterrorism Threats Inside Hydraulic Power Generation Plants
Avoiding Cyberterrorism Threats Inside Hydraulic Power Generation PlantsAvoiding Cyberterrorism Threats Inside Hydraulic Power Generation Plants
Avoiding Cyberterrorism Threats Inside Hydraulic Power Generation Plants
 

More from Mahesh Chandra Manav

The Ministry of Road Transport and Highways with Electric Vehicle Charging an...
The Ministry of Road Transport and Highways with Electric Vehicle Charging an...The Ministry of Road Transport and Highways with Electric Vehicle Charging an...
The Ministry of Road Transport and Highways with Electric Vehicle Charging an...Mahesh Chandra Manav
 
Building Automation,Networking & Communication Presentation by LVS 2022.pdf
Building Automation,Networking & Communication Presentation by LVS 2022.pdfBuilding Automation,Networking & Communication Presentation by LVS 2022.pdf
Building Automation,Networking & Communication Presentation by LVS 2022.pdfMahesh Chandra Manav
 
National green building code 2021 india kaya kool hey hum by link vue system
National green building code 2021 india  kaya kool hey hum by link vue systemNational green building code 2021 india  kaya kool hey hum by link vue system
National green building code 2021 india kaya kool hey hum by link vue systemMahesh Chandra Manav
 
Lightning it's not joke kills or destry only safety first
Lightning it's not joke kills or destry only safety firstLightning it's not joke kills or destry only safety first
Lightning it's not joke kills or destry only safety firstMahesh Chandra Manav
 
Electric vehicle charging information. by linkvue system
Electric vehicle charging   information. by linkvue systemElectric vehicle charging   information. by linkvue system
Electric vehicle charging information. by linkvue systemMahesh Chandra Manav
 
Solar power and our application (2)
Solar power and our application (2)Solar power and our application (2)
Solar power and our application (2)Mahesh Chandra Manav
 
Electrical Failure ,Short Circuit Reason Cables and Termination
Electrical Failure ,Short Circuit Reason Cables and TerminationElectrical Failure ,Short Circuit Reason Cables and Termination
Electrical Failure ,Short Circuit Reason Cables and TerminationMahesh Chandra Manav
 
High speed electric sky pods for passenger and cargo presentation by link vue
High speed electric sky pods for passenger and cargo presentation by link vueHigh speed electric sky pods for passenger and cargo presentation by link vue
High speed electric sky pods for passenger and cargo presentation by link vueMahesh Chandra Manav
 
Presentation for power plant 2021 by link vue system
Presentation for power plant 2021 by link vue systemPresentation for power plant 2021 by link vue system
Presentation for power plant 2021 by link vue systemMahesh Chandra Manav
 
Building management system from link vue system
Building management system  from link vue systemBuilding management system  from link vue system
Building management system from link vue systemMahesh Chandra Manav
 
Safe you and your team from corona virus 2021 by link vue system
Safe you and your team from corona virus 2021 by link vue  systemSafe you and your team from corona virus 2021 by link vue  system
Safe you and your team from corona virus 2021 by link vue systemMahesh Chandra Manav
 
Electric bus best public transport(hum safar)
Electric bus best public transport(hum safar)Electric bus best public transport(hum safar)
Electric bus best public transport(hum safar)Mahesh Chandra Manav
 
India great intiative a carbon free silent road transportaion electric vehicle
India great intiative a carbon free silent road transportaion electric vehicleIndia great intiative a carbon free silent road transportaion electric vehicle
India great intiative a carbon free silent road transportaion electric vehicleMahesh Chandra Manav
 
Plug&Socket for All Equipment's&System from Link Vue
Plug&Socket for All Equipment's&System from Link VuePlug&Socket for All Equipment's&System from Link Vue
Plug&Socket for All Equipment's&System from Link VueMahesh Chandra Manav
 
Platform touch voltage protection membrane system and other railways buildin...
Platform touch voltage protection membrane system  and other railways buildin...Platform touch voltage protection membrane system  and other railways buildin...
Platform touch voltage protection membrane system and other railways buildin...Mahesh Chandra Manav
 
Aaab Khela HOBO a Dead Man Walking
Aaab Khela HOBO a Dead Man WalkingAaab Khela HOBO a Dead Man Walking
Aaab Khela HOBO a Dead Man WalkingMahesh Chandra Manav
 
Link vue system pvt ltd Offer Electrical Safety and Building Automation
Link vue system pvt ltd  Offer Electrical Safety and Building AutomationLink vue system pvt ltd  Offer Electrical Safety and Building Automation
Link vue system pvt ltd Offer Electrical Safety and Building AutomationMahesh Chandra Manav
 
Electric vehicle and charging infra by link vue system
Electric vehicle and charging infra by link vue systemElectric vehicle and charging infra by link vue system
Electric vehicle and charging infra by link vue systemMahesh Chandra Manav
 
Follow Electrical Safety ,Networking andAutomation (Guide)
Follow Electrical Safety ,Networking andAutomation (Guide)Follow Electrical Safety ,Networking andAutomation (Guide)
Follow Electrical Safety ,Networking andAutomation (Guide)Mahesh Chandra Manav
 

More from Mahesh Chandra Manav (20)

The Ministry of Road Transport and Highways with Electric Vehicle Charging an...
The Ministry of Road Transport and Highways with Electric Vehicle Charging an...The Ministry of Road Transport and Highways with Electric Vehicle Charging an...
The Ministry of Road Transport and Highways with Electric Vehicle Charging an...
 
Building Automation,Networking & Communication Presentation by LVS 2022.pdf
Building Automation,Networking & Communication Presentation by LVS 2022.pdfBuilding Automation,Networking & Communication Presentation by LVS 2022.pdf
Building Automation,Networking & Communication Presentation by LVS 2022.pdf
 
National green building code 2021 india kaya kool hey hum by link vue system
National green building code 2021 india  kaya kool hey hum by link vue systemNational green building code 2021 india  kaya kool hey hum by link vue system
National green building code 2021 india kaya kool hey hum by link vue system
 
Lightning it's not joke kills or destry only safety first
Lightning it's not joke kills or destry only safety firstLightning it's not joke kills or destry only safety first
Lightning it's not joke kills or destry only safety first
 
Electric vehicle charging information. by linkvue system
Electric vehicle charging   information. by linkvue systemElectric vehicle charging   information. by linkvue system
Electric vehicle charging information. by linkvue system
 
Solar power and our application (2)
Solar power and our application (2)Solar power and our application (2)
Solar power and our application (2)
 
Electrical Failure ,Short Circuit Reason Cables and Termination
Electrical Failure ,Short Circuit Reason Cables and TerminationElectrical Failure ,Short Circuit Reason Cables and Termination
Electrical Failure ,Short Circuit Reason Cables and Termination
 
High speed electric sky pods for passenger and cargo presentation by link vue
High speed electric sky pods for passenger and cargo presentation by link vueHigh speed electric sky pods for passenger and cargo presentation by link vue
High speed electric sky pods for passenger and cargo presentation by link vue
 
Presentation for power plant 2021 by link vue system
Presentation for power plant 2021 by link vue systemPresentation for power plant 2021 by link vue system
Presentation for power plant 2021 by link vue system
 
Building management system from link vue system
Building management system  from link vue systemBuilding management system  from link vue system
Building management system from link vue system
 
Safe you and your team from corona virus 2021 by link vue system
Safe you and your team from corona virus 2021 by link vue  systemSafe you and your team from corona virus 2021 by link vue  system
Safe you and your team from corona virus 2021 by link vue system
 
Electric bus best public transport(hum safar)
Electric bus best public transport(hum safar)Electric bus best public transport(hum safar)
Electric bus best public transport(hum safar)
 
War is not a Solution
War is not a SolutionWar is not a Solution
War is not a Solution
 
India great intiative a carbon free silent road transportaion electric vehicle
India great intiative a carbon free silent road transportaion electric vehicleIndia great intiative a carbon free silent road transportaion electric vehicle
India great intiative a carbon free silent road transportaion electric vehicle
 
Plug&Socket for All Equipment's&System from Link Vue
Plug&Socket for All Equipment's&System from Link VuePlug&Socket for All Equipment's&System from Link Vue
Plug&Socket for All Equipment's&System from Link Vue
 
Platform touch voltage protection membrane system and other railways buildin...
Platform touch voltage protection membrane system  and other railways buildin...Platform touch voltage protection membrane system  and other railways buildin...
Platform touch voltage protection membrane system and other railways buildin...
 
Aaab Khela HOBO a Dead Man Walking
Aaab Khela HOBO a Dead Man WalkingAaab Khela HOBO a Dead Man Walking
Aaab Khela HOBO a Dead Man Walking
 
Link vue system pvt ltd Offer Electrical Safety and Building Automation
Link vue system pvt ltd  Offer Electrical Safety and Building AutomationLink vue system pvt ltd  Offer Electrical Safety and Building Automation
Link vue system pvt ltd Offer Electrical Safety and Building Automation
 
Electric vehicle and charging infra by link vue system
Electric vehicle and charging infra by link vue systemElectric vehicle and charging infra by link vue system
Electric vehicle and charging infra by link vue system
 
Follow Electrical Safety ,Networking andAutomation (Guide)
Follow Electrical Safety ,Networking andAutomation (Guide)Follow Electrical Safety ,Networking andAutomation (Guide)
Follow Electrical Safety ,Networking andAutomation (Guide)
 

Recently uploaded

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 

Recently uploaded (20)

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 

Metro rail project in india year 2017

  • 1. Corporate Presentation Merging with Technologies Smart Metro Rail Project (2017)
  • 2.
  • 4. Trains in India /Move Smart/Keep Moving Aab Hum Sudherenge
  • 5. Need for automation .. • Enhancement of safety • Enhance passenger convenience • Minimum manning to reduce operational costs • Improve efficiency of operations & maintenance • Optimising sectional capacity and energy efficient operation • Minimum maintenance time for ensuring higher availability
  • 6. Areas of automation • Signaling system & Train Control • Telecommunication System • Rolling Stock • Automatic Fare Collection System • Traction and Power control • Fire detection and Mitigation System • Building Management Systems • Lifts and Escalators • Automation of maintenance and depot machinery • Automation of training
  • 7. METRO OPTIONS Straddle type monorail Suspended monorail Tramways Bus Rapid Transit System Metro Train
  • 8. • India Plan To have METRO RAIL Connectivity with all Major Cities • Building and Infra Facilities • Station Buildings Ground/Upper/Under Ground • Networking and Communication • Power Grid + DG+Solar+Wind+UPS • Parking Management • Passenger Information Systems(Display) • Building Management Systems • DEPOT and Sub Station 11KV-66KV • Signal and Traffic • Water Storage and Distribution Management • Link With Major Bus Station/Railway Station Plan for Airport
  • 9. SMART METRO RAIL Project India by JMV LPS LTD
  • 14. • The origin of railway signaling dates back to 1856 when John Saxby received the first patent for interlocking switches and signals 14
  • 15. • Electricalbased solutions: train detection, signals, switching & interlockings • Cab signalling systems for advanced signalling information onboard and for automatic train stops when passing red signals. • Traffic management from centralised control centre. 15
  • 16. • Train position is reported to Operational Control Centre (OCC) by radio communication. • OCC calculates maximum speed dynamically and sends it back to the train. • Trackside equipment is reduced to minimum. 16
  • 18. Train borne Equipment  Pick up Coil  Beacon antenna  Odometer  DMI  Train borne ATC cubicle  SCS (Safety Cut Out Switch)  SCS counter  ATC selector switch  DMI fan power supply status indicator  ATP MCBs
  • 19. OCC Building SCADA DISPLAY AND CONTROL SCREEN IN OCC BUILDING
  • 21. Communication System  Fibre Optic Transmission System (FOTS)  Telephone System (EPABX & Direct Lines)  Radio System (TETRA)  Broad Band Radio System (BBRS)  Closed Circuit Television System (CCTV) & Video Analytics  Automatic Passenger Information Display System (PIDS)  Public Address system (PAS)  Master Clock System  Telecom- Supervisory Control and Data Acquisition (T- SCADA)
  • 24. Passenger Address & Information System (PA/PIS) Contract:2RS-DM 25  Public Address (PA) to Passenger including.  Live announcement to all passengers by OCC via Train Radio.  Broadcasting of pre-recorded announcement based on real time information • Door Messages for all Stations. • Station Messages for particular Station. • Special & Emergency Messages.  manual broadcasting by Train Driver.  Emergency passenger announcement on the Train by Operation Control centre (OCC) via Train Radio System.  Destination & Train number indicator on Front Cab head. Automation in Rolling Stock
  • 25. Contract:2RS-DM 26 FUNCTIONS OF TMS Sample display screen for Door operating status Automation in Rolling Stock
  • 26. Customer Care – Station Level Customer Care Office is for providing services such as Card / Token refund/replacement, ticket adjustment by operator to passenger, Collection of penalty. Remaining Value Checking Terminal (RVCT) The RVCT for checking balance and the validity of a ticket.
  • 27. Ticket Topping-up outlets •Ticket Office Machines (TOM) •Ticket Vending Machines (TVM) •SBI ATM •SBI Netbanking •BMRCL website •Mobile Phone banking •Airtel Money service & Airtel retail Network for any service provider phone
  • 28. Automatic Gates AFC Gates (Automatic Gates) • Permit one passenger per ticket to enter and exit the system • Deduct correct fare from Stored Value Tickets • Prevent exit of over-stayed / over-travelled /invalid tickets • Ticket shown on right hand side • Children below 3 ft to be taken in front and close
  • 29. Emergency Trip System provided at all Metro Station Platforms
  • 30. Automation of Safety Systems - Fire Detection & Mitigation Fire Alarm Control Panel Manual Call Point Smoke cum heat detectorManual Call Point Strobe
  • 31. Automation in Lifts and escalators
  • 32. Automation in control of Electrical Installations at Stations - Building Management System
  • 33. Automation in control of Electrical Installations at Stations - Building Management System
  • 34. Automation in control of Electrical Installations at Stations - Building Management System
  • 35. Rolling Stock and Equipments
  • 36. Integrated Power Development Scheme (IPDS) • An integrated scheme for urban areas covering: • •S art Meteri g a d Ta per-proof meters at homes • •I frastru ture upgradation in urban areas - Comprehensive sub transmission & distribution • •U dergrou d a li g & GIS Su statio s i de sely populated areas • •IT i ple e tatio for etter usto er ser i e • •Solar i stallatio s like rooftop solar pa els also covered • •Outlay of Rs. , crores
  • 37. Traction Power Supply System • 66 kV System • Receiving Substations 66/33kV • 33 kV Cable Distribution System • Auxiliary Substations - 33kV / 415V • Traction Substations – 33kV / 750 V dc • 750 V DC Third Rail System • Earthing, Bonding and Stray Current Mitigation & Monitoring System • SCADA and ETS system 38
  • 38. Network Configuration 66kV/33kV RSS Locations ‘A’ Peenya RSS ‘B’ Baiyapanhalli RSS ‘C’ Puttenhalli RSS ‘D’ Mysore Road RSS (GIS) Nelamangala 400kV / 220kV (RTPS, Nagajhari, Sharavati etc. 400 kV HVDC Kolar / Talcher 220 kV 400 kV 400 kV Peenya GSS Hoody GSS HAL GSS 66 kV 66 kV 66 kV 220 kV 66 kV 400 kV 400 kV / 220 kV Somanahalli 220 kV RR Nagar SS 220 kV Subramaniump ura SS Khoday GSS 220 kV 220 kV 66 kV 66 kV 66 kV 66 kV 220 kV 220 kV 400 kV 66 kV 220 kV 400 kV V Valley GSS REMC O SS 39
  • 39. Panoramic view of the RSS and Switchyard
  • 40. Auxiliary Sub Station (ASS) – 33 kV/415 V Electrical Loads of Metro Stations fed from Auxiliary Sub Station • Lighting and signages • Power Supply to equipment installed in Operational Rooms • Air conditioners of Operational Rooms – Station Control Room, Signaling Equipment Room, Telecom Equipment Room, UPS and Battery Room • Lifts & Escalators • Pumps for fire mitigation and water supply to toilets • Ventilation fans of Sub Stations • Fire Alarm and Detection System
  • 41. 500 kVA Transformer in a Typical ASS
  • 42. Traction Substations – 33 kV / 750 V dc Function : 33 kV stepped down to 2 X 292 V and rectified to 750 V dc for feeding to third rail 2850 kVA Rectifier Transformer Rectifier DC Panels SCD/Over Voltage Protection Device
  • 43. SCADA (SUPERVISORY CONTROL AND DATA ACQUISITION) SYSTEM Purpose : to monitor and control • receiving/distribution of power at 66kv and 33kv • Auxiliary power for all auxiliary equipments at the stations • Traction power for powering the rolling stock
  • 44. Automation of Depot Machinery Under floor pit wheel lathe Mobile Lifting jack Auto Wash Plant Pit Jacks Remote Controlled Electric Bogie Tractor Portable Battery Topping Up Cart Potable Traction Motor Dust remover
  • 46. Sikhana to Padega Hi Follow NBC2016
  • 49.
  • 50.
  • 51.
  • 52. Sources for Extra Current /Voltages from different areas……  Signal Surges Generation due direct lightning  Switching operations of heavy duty machines like motors, lifts, AC units, refrigerator, welding machine etc.  Ground Potential Rise Short Circuit due Wire/ Cables
  • 53.
  • 54. Problems due to Direct or In-Direct Electrical Installation.
  • 55. Switching actions Switching actions occur almost everywhere where work is done with electrical energy. Especially vulnerable are areas in which large inductive loads are switched, for example: • Motors • Transformers • Chokes • Climate control installations • Welding equipment • Long light strings Effects: Overvoltages (surges) on network lines Cause: High current steepnesses on switching actions lead to transient surges (overvoltages) on the mains wiring.
  • 56. Direct strike on a low-voltage overhead line The preconditions for a direct strike on a low- voltage overhead line are not the same as for direct strikes on high-voltage overhead lines. The fundamental difference is in the proximity to the building, which permits the conduction of partial lightning currents. Effects: Partial lightning currents and voltage surges in the low-voltage network. Cause: the amplitude of the lightning impulse current
  • 57. The 100% of lightning energy breaks down as follows: a) 50% of the lightning current will flow through the ground b) 50% of the lightning current will flow over the connected metal parts out of the building: • about 10% to the water pipe (metal) • about 10% to the gas pipe (metal) • about 10% to the oil pipe (metal tank) • about 10% to the sewage pipe • a out % to the po er supplier’s i o i g feed • max. 5% or 5 kA shared across all data lines 50 % 50 % Equipotential bonding for lightning protection according IEC 61024- 1 and IEC 61312-1; IEC62305 In India & Sri Lanka Only Chance is Power Line Approximately 50 % of Total Lightning Current has to be diverted to Power lines
  • 58.
  • 61. Solar PV Power Plant
  • 62. Fire Accident in Chemical & Process Plant Reason Lose Contact Earthing Disorder and Lightning
  • 63. An Arcing Fault is the flow of current through the air between phase conductors or phase conductors and neutral or ground. Concentrated radiant energy is released at the point of arcing an a small amount of time resulting in Extremely High Temperature.
  • 64. Follow Safety in Electrical Instalation Shocks
  • 65. Earthing Design and Require Result • For substation Large Power below 1.00Ohm • For substation Small Power below 2.00Ohm • SCADA/TELECOM and AutomationFor substation Large Power below 0.50Ohm • Tower and Other Structure between 8-15Ohm • Lightning Surge Protection 50KA below 5Ohm or 100KA between 8-15Ohm • Follow Standard IEC /IEEE • Recommended use of Hybrid Metal to Protect from Theft Copper Clad Steel/Alumineum Clad Copper • Exothermeic weld IEEE 837
  • 66.
  • 67. Surge in Systems and Result
  • 68. Surge in DC Application
  • 69. Surge Protection use Recommendation
  • 70.
  • 71.
  • 72. v
  • 73.
  • 75. Copper Cladded Conductor For Electrical Installation The Copper Clad Steel Grounding Conductor is made up of steel with the coating of 99.99% pure copper. These conductors/ wires or strands are equipped with the strength of steel with the conductivity and copper with the better corrosion resistance property. The concentric copper cladding is metallurgic ally bonded to a steel core through a continuous, solid cladding process using pressure rolling for primary bonding. The copper cladding thickness remains constant surrounding steel. We use different steel grades for the steel core result in Dead Soft Annealed, High strength and Extra High Strength Characteristics. The Copper Clad Steel Wire yields a composite conductivity of 21%, 30% and 40% IACS, and available in Annealed and Hard drawn. We are delivering products with varied conductivity and tensile strength as per the customer need. Further, the wire can be processed to be silver plated or tinned copper clad steel wire.
  • 76. Most Efficient JointProcess It is efficient and superior to all existing surface –to-surface mechanical retention connectors.
  • 77. What is Exothermic Welding System? Copper to Bi-Metal and Alumenium Types of Exothermic Joints: Possible to join any bi metal except aluminum Exothermic welding is a process of making maintain free highly molecular bonding process is superior in performance connection to any known mechanical or compression-type surface-to-surface contact connector. Exothermic weld connections provide current carrying (fusing) capacity equal to that of the conductor and will not deteriorate with age.  It offers Electrical connections between two or more copper to copper and copper to steel conductors.  Highly portable method as it does not require any external power source or heat source, so it can be done almost anywhere.  It provides strong permanent molecular bond among metallic conductors that cannot loosen and further will not deteriorate with age.  Connection does not corrode with time and it offers permanent conductivity.
  • 78. Copper Clad Steel Solid ROD and Conductor
  • 79.
  • 81. Facts about Lightning • A strike can average 100 million volts of electricity • Current of up to 200,000 amperes • Can generate 54,000 oF • 10/350MicroSec/50KA Fault Current/Discharge in Nano Sec Protection Earthing Design100KA Fault Current/Joints Exothermic /Flexible Down Conductor with Shortest Route & Less Corner
  • 82. • Lightning Protection Standard use in India (IS2309 Now IEC 62305-5)NBC2016 Working Principle Angullar No Compromise with Design Max Protection 30Mtrs from One No Product warrenty from Manufacturer High Maintenance Require NFC17-102(2011) Now Europeon Standard(ESE LA) Working Principle Radius Compromise with Design Possible with Increasing Qty of ESE Max Protection 109 Mtrs Radius from One Manufacturing Warrenty and Test Certificate for Products Available Maintenance on Call Basis
  • 83. Lightning Risk assessment Study is actually the measure of risk of a lightning strike and probability of damages. As Per IEC62305-2. All these calculations are based on: lightning strike density in that particular area (provided by OMV i.e. Ng = 8), Danger for people, Occupation coefficient of structure, Relative location of site, Fire Risk, Associated services, Electrical Lines, Lightning Protection Level, Surge Arrestor and Dimensions of installation.
  • 84. Lighting Strike Density (Ng) It is the measure of lightning strikes per kilometre square per year in the particular area. Higher the lighting strike density, higher the probability of lightning strike which needs higher level of lightning protection level. Danger for People (h) It is the factor of presence of people and panic in the building in case of a lightning strike No particular danger 1 Low panic level(<=2 floors, < 100 persons 2 Medium risk of panic (< 1000 persons) 5 Difficult to evacuate (disabled people, hospitals) 5 High risk of panic (> 1000 persons) 10 Hazard for surroundings or environment 20 Contamination of surroundings or environment 50 Occupancy Coefficient (Lf1) It is the risk reduction factor with respect to theoccupancy of the building / installation. For example, loss due to lighting strike is higher in hospital as compared to a store / warehouse. Structure unoccupied 0.1 Structure normally occupied 0.01 Relative Location of Site (Cd) It is the risk reduction factor with respect to the location and surrounding of the building / installation. For example, chance of lighting strike is minimized if the building is near to a high tower. Structure surrounded by higher objects or trees 0.25 Structure surrounded by similar or lower objects 0.5 Isolated structure-No other objects nearby 1 Isolated structure on top of a hill or a hillock 2 Fire Risk (rf) It is the risk reduction factor with respect to the flammability of the material present in the building / installation. For example, in case of lighting strike, loss will be very high at a gas station as compare to the cement store. Explosion 1 High 0.1 Ordinary 0.01 Low 0.001
  • 85. Lightning Risk Calcuator as per IEC6305 LIGHTNING RISK ASSESSMENT CALCULATIONS Building / Installation : KTC Tower Building ID No. KTC, Mall Road LIGHTNING DENSITY Ng= 8 STRUCTURE Length L(m) L= 12 Width W(m) W= 15 Height H(m) Hi= 10 Chimney/Tower height (m) T= 2 DANGER FOR PEOPLE h= No particular danger OCCUPATION OF THE STRUCTURE Lf1= Structure normally occupied LIGHTNING CONDUCTOR Pd= Protection Level IV Electrical Line Ai= Underground RELATIVE LOCATION OF THE STRUCTURE Cd= Structure surrounded by higher objects or trees FIRE RISK rf= Low SERVICE Lf2= Gas, water SURGE ARRESTOR Pi= None RESULTS OF THE RISK ASSESSMENT Risk of human loss R1= ACCEPTABLE Risk of loss of service R2= ACCEPTABLE Risk of loss of cultural heritage R3= ACCEPTABLE
  • 87. The Simple Rod air terminal is composed from a metallic rod with 2 to 8 m height dominating the structure to protect, and linked to 2 down conductors minimum, and 2 earthing systems. The protection radius ensured by this air terminal which is limited to 30 m more or less (Protection level IV, height = 60 m), especially dedicated to the protection of small structures or areas like to ers, hi eys, ta ks, ater to er, a te a asts… The EN -3 standard describes the installation procedure for these air terminals. 13 Simple Rods, 13 down conductors, and 13 earthing systems are necessary to ensure the protection below :
  • 88. The meshed cage protection is composed from a meshing in roof surface and in the front face around the uildi g. Surrou di g the roof surfa e, a d o high poi ts, apture poi ts are positio ed. A o du tors’ network is placed at the outer perimeter of the roof. This network is completed by transverse conductors. The size of the meshing is 5 to meters, and depends on the efficiency needed for the protection. On the front face of the building, the down conductors are linked at the top to the meshing of the roof. And, down, to specific earthing systems. The distance between two conductors is 10 to 25 meters, and depend on the efficiency needed for the protection. The EN 62305-3 describes the installation procedure for this method. Generally, this method is heavy and expensive, due to the complexity of the structures to protect. 26 capture points, 26 down conductors and a grounded loop earthing system are necessaries to ensure the protection of the structure here below :
  • 89. The catenary wires protection is a method closed to the meshed cage principle, because it is constituted with meshing of the conductors far from the structure to protect, to avoid any contact with lightning current. Catenary wires are located over the structure to protect, connected to down conductors and specific earthing systems. The width of the meshing and distance between the down conductors must respect the same rules as for the meshed cage. The EN 62305-3 describes the installation procedure for this method. Generally, this method is heavy and expensive, due to the complexity of the structures to protect.
  • 90. The ESE air terminal is a terminal which enables to generate artificially an upward leader earlier than a simple rod, with an ionization system, in order to establish a special impact on its point. The capture of the lightning strike being faster than a simple rod, this technology enables to benefit from larger protection areas, ensuring protection for large dimensions structures. The ge erated prote tio radius depe ds o the early strea er e issio alue of the air ter i al Δt i µs , its height, and the efficiency of the protection. The protection radius ensured by this type of air terminal is 120 m (Protection level IV, height = 60 m , early streamer emission time 60µs) The NFC 17-102 standard describes the installation procedure for this type of air terminal. The installation of this type of air terminal is easy and cheaper than other technologies. It can protect whole buildings with one E.S.E. air terminal. It enables the protection of a structure and its environment, the protection of opened areas and well integrate in the architecture of a structure without aesthetic alteration. 1 ESE, 2 down conductors and 2 earthing systems are necessary to ensure the protection below :
  • 91. Installation ESE AT with radius protection form 32 mtr to 107 mtr. DMC Insulator . GI/FRP Mast . Down Conductor Copper / Copper Cadmium Cable 70 sq. mm Copper Bonded Ground Earthing
  • 92. Step – 1 Step – 2 Step – 3 Joint all phase wire/ cable with the help of crimping tools and lugs Fixed the separation sheet between all wires/ cables Close the filled Silicon enclosure from top and bottom , complete installation is done. Thimble Separation Sheet Gel / Silicon
  • 93. Features : Provides cable with cable connections and jointing wires in switchboard / electric boxes Being a jelly it can be easily fit into molds of any shape and size. Helps in safeguarding electrical connections and also protects electrical connection joints from catching fire, sparking and leakage current. Eradicates all the possibilities of fire, electric shocks and sparks, etc. causes due to improper electrical connection joints and safeguards structure, equipment and person. Offers safety to your electrical joints from ageing, corrosion, moisture and also observes leakage current. Advantages : Nontoxic Insulating Highly reliable operation Maintenance Free Repairable Cost Effective High repeat value Elasticity Shape retention
  • 94.
  • 95.
  • 97. Neeraj Saini – 9910398538 Rahul Verma – 9910398535 Manav Chandra - 9910398999 manav@jmv.co.in