Challenging Glass 2 – Conference on Architectural and Structural Applications of Glass,
Bos, Louter, Veer (Eds.), TU Delft, May 2010.
Copyright © with the authors. All rights reserved.
A new Façade Concept for an Existing
Office Building
Iris Maniatis, Barbara Siebert
Ingenieurbüro Dr. Siebert – Consulting Engineers, Munich, Germany,
ima@ing-siebert.de, www.ing-siebert.de
In this paper a case study is presented relating to the redesign of an office building
dating from the 1960s. Especially the detailing and the structural complexity of
designing the new double skin façade are described. The building consists of a two-
storey podium topped by a nine-storey tower, the overall height is 40m above
ground level. In order to optimise the building's energy efficiency and present the
public a modern appearance the whole building is completely renovated. The
existing building envelope which mainly consisted of prefabricated concrete
elements was dismantled and is now replaced by a transparent floor to floor double
skin façade. Within the renovation two new storeys (12th and 13th floor) are added.
Keywords: redesign, double skin facade, structural detailing
1. Introduction
Rising energy costs and amendments to regulations have strengthened the society's
awareness of energy saving measures. In order to reduce CO2 emissions many buildings
dating from the 1960s and 1970s are being now refurbished. They scarcely comply with
the stricter building standards introduced in recent years and very often need to be
renovated not only in terms of energy efficiency but also in terms of fire protection and
functionality.
Retrofitting existing buildings is very often even more complex than designing new
ones as the remaining structure has to be included in the design concept and in many
cases compromises have to be made to meet standards and requirements.
In this paper a case study is presented relating to the redesign of an office building
dating from the 1960s. This example shows the creative potential but also the
complexity that lies in the renewal of older buildings. Especially the detailing and the
structural complexity of designing the new double skin façade are described.
Built in 1969 the building complex accommodating a bank company sets an important
accent within the city centre of Rosenheim, which is a medium size town in Germany.
The building consists of a two-storey podium topped by a nine-storey tower, the overall
height is 40m above ground level. In order to optimise the building's energy efficiency
and present the public a modern appearance the whole building is completely renovated.
The existing building envelope which mainly consisted of prefabricated concrete
elements was dismantled (Figure 1a, b) and is now replaced by a transparent floor to
floor double skin façade Within the renovation two new storeys (12th and 13th floor)
Challenging Glass 2
are added. The overall office area is 4000m2. The energy consumption will be reduced
from 400 kWh/m2 to 100 kWh/m2 which is a reduction of 75%.
Figure 1a, b: Dismantling of the Concrete Façade Elements.
The design of the office building dating from the 1960s as well as the redesign was
planned by Schleburg Architects, Rosenheim. The floor plan of the nine-storey tower
has a rectangular shape having a size of approximately 22.5m x 13m. The outer façade
is suspended from steel fins which are mounted on the concrete floors. The dominating
glazing parts of the secondary façade have a size of 2.5m x 2.5m, in the 11th floor the
glazing height increases to 4.3m. The inner part of the facade consists of an insulated
wooden cladding with linear supported floor to floor double glazed systems. Whereas
the outer screen consists of glass panels which are locally supported by clamps along
their edges.
2. Design of the Double Skin Façade
2.1. Glazing
The dominating glazing parts of the secondary façade have a size of 2.5m x 2.5m, in the
11th floor the glazing height increases to 4.3m. The glass panels are supported by
clamps along their edges. The glass set-up consists of 2 x 10mm laminated heat
strengthened glass and in the corner areas of 2 x 12mm laminated heat strengthened
glass.
The glass panels are visually broken up by openable louvres which are 0.55m high and
1.25m wide, they are linearly supported along their short edges and have a glass set-up
of 2 x 8mm laminated annealed glass. The louvers are used for natural ventilation and
will also open in case of any smoke emission. Figure 2 shows the elevation of the
façade.
The wind loads were determined based on a wind study which was carried out for the
double skin façade.
[A new Façade Concept for an Existing Office Building]
As the gap between outer and inner façade is to be accessible for cleaning and
maintenance the outer façade has to resist also impact loads. Therefore besides the
structural analysis impact tests had to be carried out (see section 3).
For the louvers also additional requirements regarding remaining load carrying capacity
after glass breakage had to be taken into consideration. This was necessary as the open
louvers having an inclination more than 10° are classified as an overhead glazing. The
testing is described in section 3. For the secondary glazing of the façade a special permit
from the authorities was needed.
Figure 2: Elevation of the Façade.
2.2. Supporting Structure and Detailing
The outer façade is suspended from steel fins which are fixed to the concrete slabs by
anchors (Figure 3). The steel fin itself consists of welded flat steel plates (Figure 4).
When designing the supporting elements the main problem was the connection to the
concrete structure. Due to the poor concrete quality dating from the 1960s and
insufficient reinforcement at the slab edges it was necessary to fix the anchors at defined
locations which were able to resist these additional loads (Figure 5). The gap between
anchor and drill hole was filled with a suitable mortar to avoid any slip.
Challenging Glass 2
Figure 3: Vertical Section Steel Fin.
Figure 4: Installed Steel Fin. Figure 5: Steel Fins are fixed to the Concrete Floor by
Anchors.
[A new Façade Concept for an Existing Office Building]
Furthermore complex supporting details had to be developed to transfer the compressive
forces locally into a defined area of the concrete edge (Figure 6a). To guarantee a
uniform load distribution additionally the gaps between the steel sections and the
concrete were filled with a high strength grout (Figure 6b).
The supporting elements were modeled by means of finite element analysis (Figure 7,
Figure 8).
Figure 6a, b: Load Application into the Slab Edge.
Figure 7: FEA model. Figure 8: Max. deformation.
3. Testing
3.1. Introduction
The design of this complex façade structure should not only be based on numerical
simulation therefore full scale tests of the supporting elements were carried out to be
able to evaluate the FEA-model in a qualified way (section 3.2).
As the gap between outer and inner façade is to be accessible for cleaning and
maintenance the outer façade functions as a barrier and has to resist also impact loads.
Therefore for the glazing of the outer skin impact tests were required according to
TRAV [7] (section 3.3).
high strength
grout
Challenging Glass 2
Finally the post-breakage performance of the openable louvres was determined (section
3.4). This was necessary as the open louvers having an inclination more than 10° are
classified as an overhead glazing and a safe post-failure behaviour in the event of
breakage for people beneath has to be guaranteed.
3.2. Deformation of the Outer Skin
Goal of these tests was to verify that there are no significant deformations or any slip of
the façade supporting elements induced by dead, wind and traffic loads. The tests were
carried out in full scale on site.
The loads where applied step by step starting with the characteristic values. Finally the
design values were applied. For each load step the horizontal and vertical deformation
was determined (Figure 9).
Figure 9 Test set-up. Figure 10: Load application.
The loads were simulated by cement bags (Figure 10) and fixed to the location of load
application by steel cables and deflection pulleys. The exact load value was determined
by force transducers.
The following maximum deformations were determined: horizontal direction 1.3mm
and vertical direction 5.0mm. These values matched very well with the calculated
values of the structural analysis. In the tests no slip of the supporting structure was
determined.
3.3. Impact Resistance
For the glazing of the secondary façade impact tests according to German TRAV [7]
were performed using a standard pendulum according to EN 12600. A drop height of
900mm was used. The tests were carried out in full scale in the laboratory (Figure 11).
The impact body hit the specimen on points that caused maximum glass and support
damage. After an impact at the corner of the specimen the laminated glass broke (Figure
12), but as the impact body did not penetrate the laminated glass and no dangerous glass
fragments fell down the test was passed.
[A new Façade Concept for an Existing Office Building]
Figure 11: Test set-up. Figure 12: Damaged glass specimen.
3.4. Post-breakage performance
To determine the post-breakage performance of the louvres (Figure 3) the laminated
glass specimen were placed horizontally and loaded by half of the service load (Figure
13). With the load still applied all the sheets of the laminated glass panel were fractured
at several locations by means of a hole punch and a hammer. The tests were carried out
successfully: Within 24 hours the specimen did not slide from the supports and no
dangerous glass fragments fell down (Figure 14).
Figure 13 Test set-up with loading
Figure 14: Specimen after testing.
4. Conclusion
Retrofitting existing buildings is very often even more complex than designing new
ones as the remaining structure has to be included in the design concept and in many
cases compromises have to be made to meet standards and requirements.
Challenging Glass 2
Redesigning this office building the main problem was the connection of the façade
supporting elements to the existing concrete structure. Due to the poor concrete quality
dating from the 1960s and insufficient reinforcement at the slab edges it was necessary
to design special joints and fix the anchors at defined locations which were able to resist
these additional loads.
Moreover for the outer glass skin besides the structural analysis additional requirements
such as resistance against human impact and post-breakage performance were
demanded from the building authorities.
Although redesigning the building was very complex, by improving the energy
efficiency and present the public a modern appearance the renovation of the building
was very successfully (Figure 15a, b).
Figure 15a, b: New double skin facade
5. References
[1] DIN 18800-1: 1990-11 Steel structures: design and construction.
[2] DIN 1055-3: 2006-03 Action on structures: self-weight and imposed load in building.
[3] DIN 1055-4: 2005-03 Action on structures: wind loads.
[4] DIN 1055-5: 2005-07 Action on structures : snow loads and ice loads.
[5] Technische Regeln für die Verwendung von linienförmig gelagerten Verglasungen (TRLV), final version
August 2006.
[6] Technische Regeln für die Bemessung und die Ausführung punktförmig gelagerter Verglasungen (TRPV),
final version August 2006.
[7] Technische Regeln für die Verwendung von absturzsichernden Verglasungen (TRAV), version January
2003.

More Related Content

What's hot

Aluminium formwork(t 4 a)
Aluminium formwork(t 4 a)Aluminium formwork(t 4 a)
Aluminium formwork(t 4 a)
w ss
 
Scs – A World Of Possibilities R New
Scs – A World Of Possibilities R NewScs – A World Of Possibilities R New
Scs – A World Of Possibilities R New
neerajtri
 
Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3
Yee Len Wan
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction Industry
Abhishek Shah
 

What's hot (20)

Blockwork system
Blockwork systemBlockwork system
Blockwork system
 
Building construction 02
Building construction 02Building construction 02
Building construction 02
 
Types of modern construction formwork
Types of modern construction formwork Types of modern construction formwork
Types of modern construction formwork
 
Building Construction II - Project 1
Building Construction II - Project 1Building Construction II - Project 1
Building Construction II - Project 1
 
Bcon
BconBcon
Bcon
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction technique
 
A Case Study of Existing Institutional Building for Assessment and Repair (VJ...
A Case Study of Existing Institutional Building for Assessment and Repair (VJ...A Case Study of Existing Institutional Building for Assessment and Repair (VJ...
A Case Study of Existing Institutional Building for Assessment and Repair (VJ...
 
Formwork seminar 2
Formwork seminar 2Formwork seminar 2
Formwork seminar 2
 
vacation work report 2
vacation work report 2vacation work report 2
vacation work report 2
 
Advance Formwork System (PERI FORMWORK SYSTEM)
Advance Formwork System (PERI FORMWORK SYSTEM)Advance Formwork System (PERI FORMWORK SYSTEM)
Advance Formwork System (PERI FORMWORK SYSTEM)
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Aluminium formwork(t 4 a)
Aluminium formwork(t 4 a)Aluminium formwork(t 4 a)
Aluminium formwork(t 4 a)
 
Com flor manual
Com flor manualCom flor manual
Com flor manual
 
Bus shelter report
Bus shelter reportBus shelter report
Bus shelter report
 
Scs – A World Of Possibilities R New
Scs – A World Of Possibilities R NewScs – A World Of Possibilities R New
Scs – A World Of Possibilities R New
 
Ertf
ErtfErtf
Ertf
 
Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3Construction Technology III (Group Assignment) - Semester 3
Construction Technology III (Group Assignment) - Semester 3
 
Building Construction 2 - Project 1 - Temporary Bus Shelter
Building Construction 2 - Project 1 - Temporary Bus ShelterBuilding Construction 2 - Project 1 - Temporary Bus Shelter
Building Construction 2 - Project 1 - Temporary Bus Shelter
 
Different types of damages that have been observed in masonry buildings durin...
Different types of damages that have been observed in masonry buildings durin...Different types of damages that have been observed in masonry buildings durin...
Different types of damages that have been observed in masonry buildings durin...
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction Industry
 

Similar to A new facade concept for an existing office building

Design Appraisal report
Design Appraisal reportDesign Appraisal report
Design Appraisal report
Conor Meaney
 
B tech individual report
B tech individual reportB tech individual report
B tech individual report
ong93
 
BTECHN PROJECT 2 Final report (GROUP)
BTECHN PROJECT 2 Final report (GROUP)BTECHN PROJECT 2 Final report (GROUP)
BTECHN PROJECT 2 Final report (GROUP)
ong93
 

Similar to A new facade concept for an existing office building (20)

Design Appraisal report
Design Appraisal reportDesign Appraisal report
Design Appraisal report
 
B tech individual report
B tech individual reportB tech individual report
B tech individual report
 
Ijsrp p3928
Ijsrp p3928Ijsrp p3928
Ijsrp p3928
 
Detail behind the proposal
Detail behind the proposalDetail behind the proposal
Detail behind the proposal
 
IBS design proposal of apartment
IBS design proposal of apartmentIBS design proposal of apartment
IBS design proposal of apartment
 
2327
23272327
2327
 
Prefabricated panels
Prefabricated panelsPrefabricated panels
Prefabricated panels
 
A long span structure in Romania Full paper balint karoly
A long span structure in Romania Full paper balint karolyA long span structure in Romania Full paper balint karoly
A long span structure in Romania Full paper balint karoly
 
5th batch.pptx
5th batch.pptx5th batch.pptx
5th batch.pptx
 
BTECHN PROJECT 2 Final report (GROUP)
BTECHN PROJECT 2 Final report (GROUP)BTECHN PROJECT 2 Final report (GROUP)
BTECHN PROJECT 2 Final report (GROUP)
 
IRJET- A Study on Seismic Analysis of RC Framed Structures on Varying Slo...
IRJET-  	  A Study on Seismic Analysis of RC Framed Structures on Varying Slo...IRJET-  	  A Study on Seismic Analysis of RC Framed Structures on Varying Slo...
IRJET- A Study on Seismic Analysis of RC Framed Structures on Varying Slo...
 
Influence of Modeling Masonry Infill on Seismic Performance of Multi-Storeyed...
Influence of Modeling Masonry Infill on Seismic Performance of Multi-Storeyed...Influence of Modeling Masonry Infill on Seismic Performance of Multi-Storeyed...
Influence of Modeling Masonry Infill on Seismic Performance of Multi-Storeyed...
 
Behaviour of reinforced concrete frame with in fill walls under seismic loads...
Behaviour of reinforced concrete frame with in fill walls under seismic loads...Behaviour of reinforced concrete frame with in fill walls under seismic loads...
Behaviour of reinforced concrete frame with in fill walls under seismic loads...
 
Glass beams
Glass beamsGlass beams
Glass beams
 
Lateral Load Analysis of Shear Wall and Concrete Braced Multi-Storeyed R.C Fr...
Lateral Load Analysis of Shear Wall and Concrete Braced Multi-Storeyed R.C Fr...Lateral Load Analysis of Shear Wall and Concrete Braced Multi-Storeyed R.C Fr...
Lateral Load Analysis of Shear Wall and Concrete Braced Multi-Storeyed R.C Fr...
 
Lateral Load Analysis of Shear Wall and Concrete Braced Multi-Storeyed R.C Fr...
Lateral Load Analysis of Shear Wall and Concrete Braced Multi-Storeyed R.C Fr...Lateral Load Analysis of Shear Wall and Concrete Braced Multi-Storeyed R.C Fr...
Lateral Load Analysis of Shear Wall and Concrete Braced Multi-Storeyed R.C Fr...
 
Seismic Performance Evaluation of Multi-Storeyed R C Framed Structural System...
Seismic Performance Evaluation of Multi-Storeyed R C Framed Structural System...Seismic Performance Evaluation of Multi-Storeyed R C Framed Structural System...
Seismic Performance Evaluation of Multi-Storeyed R C Framed Structural System...
 
Dynamic Analysis of Soft Storey Frame with Isolators
Dynamic Analysis of Soft Storey Frame with IsolatorsDynamic Analysis of Soft Storey Frame with Isolators
Dynamic Analysis of Soft Storey Frame with Isolators
 
Tokyo Sky Tree
Tokyo Sky TreeTokyo Sky Tree
Tokyo Sky Tree
 
The Advanced Facade Technology – CCF
The Advanced Facade Technology – CCFThe Advanced Facade Technology – CCF
The Advanced Facade Technology – CCF
 

Recently uploaded

Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Recently uploaded (20)

Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 

A new facade concept for an existing office building

  • 1. Challenging Glass 2 – Conference on Architectural and Structural Applications of Glass, Bos, Louter, Veer (Eds.), TU Delft, May 2010. Copyright © with the authors. All rights reserved. A new Façade Concept for an Existing Office Building Iris Maniatis, Barbara Siebert Ingenieurbüro Dr. Siebert – Consulting Engineers, Munich, Germany, ima@ing-siebert.de, www.ing-siebert.de In this paper a case study is presented relating to the redesign of an office building dating from the 1960s. Especially the detailing and the structural complexity of designing the new double skin façade are described. The building consists of a two- storey podium topped by a nine-storey tower, the overall height is 40m above ground level. In order to optimise the building's energy efficiency and present the public a modern appearance the whole building is completely renovated. The existing building envelope which mainly consisted of prefabricated concrete elements was dismantled and is now replaced by a transparent floor to floor double skin façade. Within the renovation two new storeys (12th and 13th floor) are added. Keywords: redesign, double skin facade, structural detailing 1. Introduction Rising energy costs and amendments to regulations have strengthened the society's awareness of energy saving measures. In order to reduce CO2 emissions many buildings dating from the 1960s and 1970s are being now refurbished. They scarcely comply with the stricter building standards introduced in recent years and very often need to be renovated not only in terms of energy efficiency but also in terms of fire protection and functionality. Retrofitting existing buildings is very often even more complex than designing new ones as the remaining structure has to be included in the design concept and in many cases compromises have to be made to meet standards and requirements. In this paper a case study is presented relating to the redesign of an office building dating from the 1960s. This example shows the creative potential but also the complexity that lies in the renewal of older buildings. Especially the detailing and the structural complexity of designing the new double skin façade are described. Built in 1969 the building complex accommodating a bank company sets an important accent within the city centre of Rosenheim, which is a medium size town in Germany. The building consists of a two-storey podium topped by a nine-storey tower, the overall height is 40m above ground level. In order to optimise the building's energy efficiency and present the public a modern appearance the whole building is completely renovated. The existing building envelope which mainly consisted of prefabricated concrete elements was dismantled (Figure 1a, b) and is now replaced by a transparent floor to floor double skin façade Within the renovation two new storeys (12th and 13th floor)
  • 2. Challenging Glass 2 are added. The overall office area is 4000m2. The energy consumption will be reduced from 400 kWh/m2 to 100 kWh/m2 which is a reduction of 75%. Figure 1a, b: Dismantling of the Concrete Façade Elements. The design of the office building dating from the 1960s as well as the redesign was planned by Schleburg Architects, Rosenheim. The floor plan of the nine-storey tower has a rectangular shape having a size of approximately 22.5m x 13m. The outer façade is suspended from steel fins which are mounted on the concrete floors. The dominating glazing parts of the secondary façade have a size of 2.5m x 2.5m, in the 11th floor the glazing height increases to 4.3m. The inner part of the facade consists of an insulated wooden cladding with linear supported floor to floor double glazed systems. Whereas the outer screen consists of glass panels which are locally supported by clamps along their edges. 2. Design of the Double Skin Façade 2.1. Glazing The dominating glazing parts of the secondary façade have a size of 2.5m x 2.5m, in the 11th floor the glazing height increases to 4.3m. The glass panels are supported by clamps along their edges. The glass set-up consists of 2 x 10mm laminated heat strengthened glass and in the corner areas of 2 x 12mm laminated heat strengthened glass. The glass panels are visually broken up by openable louvres which are 0.55m high and 1.25m wide, they are linearly supported along their short edges and have a glass set-up of 2 x 8mm laminated annealed glass. The louvers are used for natural ventilation and will also open in case of any smoke emission. Figure 2 shows the elevation of the façade. The wind loads were determined based on a wind study which was carried out for the double skin façade.
  • 3. [A new Façade Concept for an Existing Office Building] As the gap between outer and inner façade is to be accessible for cleaning and maintenance the outer façade has to resist also impact loads. Therefore besides the structural analysis impact tests had to be carried out (see section 3). For the louvers also additional requirements regarding remaining load carrying capacity after glass breakage had to be taken into consideration. This was necessary as the open louvers having an inclination more than 10° are classified as an overhead glazing. The testing is described in section 3. For the secondary glazing of the façade a special permit from the authorities was needed. Figure 2: Elevation of the Façade. 2.2. Supporting Structure and Detailing The outer façade is suspended from steel fins which are fixed to the concrete slabs by anchors (Figure 3). The steel fin itself consists of welded flat steel plates (Figure 4). When designing the supporting elements the main problem was the connection to the concrete structure. Due to the poor concrete quality dating from the 1960s and insufficient reinforcement at the slab edges it was necessary to fix the anchors at defined locations which were able to resist these additional loads (Figure 5). The gap between anchor and drill hole was filled with a suitable mortar to avoid any slip.
  • 4. Challenging Glass 2 Figure 3: Vertical Section Steel Fin. Figure 4: Installed Steel Fin. Figure 5: Steel Fins are fixed to the Concrete Floor by Anchors.
  • 5. [A new Façade Concept for an Existing Office Building] Furthermore complex supporting details had to be developed to transfer the compressive forces locally into a defined area of the concrete edge (Figure 6a). To guarantee a uniform load distribution additionally the gaps between the steel sections and the concrete were filled with a high strength grout (Figure 6b). The supporting elements were modeled by means of finite element analysis (Figure 7, Figure 8). Figure 6a, b: Load Application into the Slab Edge. Figure 7: FEA model. Figure 8: Max. deformation. 3. Testing 3.1. Introduction The design of this complex façade structure should not only be based on numerical simulation therefore full scale tests of the supporting elements were carried out to be able to evaluate the FEA-model in a qualified way (section 3.2). As the gap between outer and inner façade is to be accessible for cleaning and maintenance the outer façade functions as a barrier and has to resist also impact loads. Therefore for the glazing of the outer skin impact tests were required according to TRAV [7] (section 3.3). high strength grout
  • 6. Challenging Glass 2 Finally the post-breakage performance of the openable louvres was determined (section 3.4). This was necessary as the open louvers having an inclination more than 10° are classified as an overhead glazing and a safe post-failure behaviour in the event of breakage for people beneath has to be guaranteed. 3.2. Deformation of the Outer Skin Goal of these tests was to verify that there are no significant deformations or any slip of the façade supporting elements induced by dead, wind and traffic loads. The tests were carried out in full scale on site. The loads where applied step by step starting with the characteristic values. Finally the design values were applied. For each load step the horizontal and vertical deformation was determined (Figure 9). Figure 9 Test set-up. Figure 10: Load application. The loads were simulated by cement bags (Figure 10) and fixed to the location of load application by steel cables and deflection pulleys. The exact load value was determined by force transducers. The following maximum deformations were determined: horizontal direction 1.3mm and vertical direction 5.0mm. These values matched very well with the calculated values of the structural analysis. In the tests no slip of the supporting structure was determined. 3.3. Impact Resistance For the glazing of the secondary façade impact tests according to German TRAV [7] were performed using a standard pendulum according to EN 12600. A drop height of 900mm was used. The tests were carried out in full scale in the laboratory (Figure 11). The impact body hit the specimen on points that caused maximum glass and support damage. After an impact at the corner of the specimen the laminated glass broke (Figure 12), but as the impact body did not penetrate the laminated glass and no dangerous glass fragments fell down the test was passed.
  • 7. [A new Façade Concept for an Existing Office Building] Figure 11: Test set-up. Figure 12: Damaged glass specimen. 3.4. Post-breakage performance To determine the post-breakage performance of the louvres (Figure 3) the laminated glass specimen were placed horizontally and loaded by half of the service load (Figure 13). With the load still applied all the sheets of the laminated glass panel were fractured at several locations by means of a hole punch and a hammer. The tests were carried out successfully: Within 24 hours the specimen did not slide from the supports and no dangerous glass fragments fell down (Figure 14). Figure 13 Test set-up with loading Figure 14: Specimen after testing. 4. Conclusion Retrofitting existing buildings is very often even more complex than designing new ones as the remaining structure has to be included in the design concept and in many cases compromises have to be made to meet standards and requirements.
  • 8. Challenging Glass 2 Redesigning this office building the main problem was the connection of the façade supporting elements to the existing concrete structure. Due to the poor concrete quality dating from the 1960s and insufficient reinforcement at the slab edges it was necessary to design special joints and fix the anchors at defined locations which were able to resist these additional loads. Moreover for the outer glass skin besides the structural analysis additional requirements such as resistance against human impact and post-breakage performance were demanded from the building authorities. Although redesigning the building was very complex, by improving the energy efficiency and present the public a modern appearance the renovation of the building was very successfully (Figure 15a, b). Figure 15a, b: New double skin facade 5. References [1] DIN 18800-1: 1990-11 Steel structures: design and construction. [2] DIN 1055-3: 2006-03 Action on structures: self-weight and imposed load in building. [3] DIN 1055-4: 2005-03 Action on structures: wind loads. [4] DIN 1055-5: 2005-07 Action on structures : snow loads and ice loads. [5] Technische Regeln für die Verwendung von linienförmig gelagerten Verglasungen (TRLV), final version August 2006. [6] Technische Regeln für die Bemessung und die Ausführung punktförmig gelagerter Verglasungen (TRPV), final version August 2006. [7] Technische Regeln für die Verwendung von absturzsichernden Verglasungen (TRAV), version January 2003.