SlideShare a Scribd company logo
1 of 17
Engineering Surveys and
Construction of New Lines
Mr MANIVEL M
FACULTY,CIVIL ENGINEERING
SCHOOL OF TECHNOLOGY
PANDIT DEENDAYAL PETROLEUM UNIVERSITY
GANDHINAGAR
Introduction
The construction of a new railway line is a
capital-intensive project and each kilometre of
a new railway line costs in the range of Rs 6 to
10 million depending upon the topography of
the area, the standard of construction, and
such other features. It is, therefore, natural
that a lot of thought be given when making a
final decision as to whether a new railway line
is at all necessary or not.
Need for Construction of a New
Railway Line
The need for construction of a new railway line arises
because of one or more of the following
considerations.
(a) Strategic reasons It is sometimes necessary to
extend the existing railway line to a new point of
strategic importance so that the defence forces can
move quickly to the some areas in case of any
emergency such as the threat of war.
(b) Political reasons A new line sometimes becomes
necessary to serve the political needs of the country,
for example, the railway line from Pathankot to
Jammu.
(c) Development of backward areas Railway lines are
sometimes constructed to develop backward areas.
Experience has shown that once railway
communication is available, backward areas develop
very fast. The Assam rail link can be classified in this
category.
(d) To connect new trade centres Sometimes new trade
centres are connected with railway lines for the quick
transportation of goods between two trade centres or
from the point of production to the point of
consumption.
(e) To shorten the existing rail link: The existing
routes between two important points may be
longer than required. New railway lines are
constructed on a shorter alignment in such
cases. A short route is not only economical,
but also helps in the faster movement of goods
and passengers. The Konkan Railway is a
typical example.
Types of Surveys
The following types of surveys are normally
conducted:
(a) Traffic survey
(b) Reconnaissance survey
(c) Preliminary survey
(d) Final location survey
(a) Traffic survey
Traffic survey includes a detailed study of the
traffic conditions in the area with a view to
determine the
Most promising route for the railway in the
area,
Possible traffic the railway line will carry, and
Standard of railway line to be followed.
Traffic survey consists of an economic study of the area keeping in mind the
following considerations, information on which should be collected in detail:
(a) Human resources
(b) Agricultural and mineral resources
(c) Pattern of trade and commerce
(d) Industries located and projected
(e) Prospects of tourist traffic
(f) Existing transport facilities
(g) Locations of important government and private offices
(h) Planning for economic development of the area
• The traffic survey team should make an assessment of the
traffic likely to be carried by to the new line. While
carrying out the survey, details of traffic likely to be
offered by various government organizations, public
bodies, or private enterprises should be gathered
Survey Instruments
Prismatic compass - To get magnetic bearings of
the proposed alignment.
Aneroid barometer - To ensure relative heights
of various points.
Abney level or hand level or clinometer - To
measure the gradients or angles of slopes.
Binocular - To view the physical features.
Pedometer - To get an idea of the total length
traversed while walking.
Reconnaissance Survey
This survey consists of a rapid and rough
investigation of the area with a view to determine
the technical feasibility of the proposal as well as
the rough cost of one or more alternatives to the
new line. The reconnaissance survey (RECCE) is
normally based on contoured survey maps and
other data already available without carrying out
detailed investigations in the field. With the help
of the maps, different alternative alignments of
the new line are studied.
Preliminary Survey
The preliminary survey consists of a detailed
instrumental examination of the route to be
selected as a result of the reconnaissance
survey in order to estimate the cost of the
proposed railway line. Based on the
preliminary and traffic survey reports, the
railway administration decides whether or not
the proposed railway line is to be constructed.
Instruments for Preliminary Survey
(a) Theodolite for traversing and pegging the
centre line
(b) Tacheometer for plotting the main features
(c) Dumpy level for taking the longitudinal and
cross levels
(d) Plane table for getting details of various
features
(e) Prismatic compass for measuring the
magnetic bearings of a particular alignment
Final Location Survey
Once a decision has been taken for a particular
railway line to be constructed, a final location
survey is done. The instruments used are
generally the same as in the case of the
preliminary survey. Final location survey is
done to prepare working details and make
accurate cost estimates in certain cases.
The principal differences between the preliminary
survey and the final survey are as follows.
(a) In the final location survey, the alignment is
fully staked with the help of a theodolite,
whereas it is not obligatory to do so in the case
of preliminary survey.
(b) In the final location survey, a more detailed
project report is prepared and submitted.
(c) All working drawings are prepared in the final
location survey.
The following tasks are carried out in the final location survey.
(a) The centre line is fully marked by pegs at 20
m. At each 100 m, a large peg should be used.
(b) Masonry pillars are built at tangent points of
curves and along the centre line at intervals of
500 m.
(c) Longitudinal and cross levelling is done to
ascertain the final gradient of the alignment.
All gradients are compensated for curves.
(d) The sites for station yards are fully
demarcated.
In the final location survey, the following set of drawings is
prepared.
(a) General map of the country traversed by the
project at a scale of about 20 km to 1 cm
(b) Index map, scale about 2.5 km to 1 cm
(c) Index plan and sections
(d) Detailed plans and sections
(e) Plans and cross section
(f) Plans of station yards
(g) Detailed drawings of structures
(h) Plans of junction arrangements
• Thanks

More Related Content

What's hot

Geometric design of highway
Geometric design of highwayGeometric design of highway
Geometric design of highwayJunaid Jamadar
 
Fittings and Fastenings of Rails.pdf
Fittings and Fastenings of Rails.pdfFittings and Fastenings of Rails.pdf
Fittings and Fastenings of Rails.pdfTVijayaGowri
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossingssrinivas2036
 
Highway Development & Planning
Highway Development & PlanningHighway Development & Planning
Highway Development & PlanningRitom Debnath
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )mohit kumar panchal
 
Elements of road x-section
Elements of road x-section Elements of road x-section
Elements of road x-section Rana Ibrahim
 
O and d study
O and d studyO and d study
O and d studymeetmksvs
 
Highway Cross-sectional Elements
Highway Cross-sectional ElementsHighway Cross-sectional Elements
Highway Cross-sectional ElementsAkshathaBhandary
 
Traffic volume
Traffic volumeTraffic volume
Traffic volumePENKI RAMU
 
IRC Method of Signal Design
IRC Method of Signal DesignIRC Method of Signal Design
IRC Method of Signal DesignVijai Krishnan V
 
Highway Engineering topics
Highway Engineering topicsHighway Engineering topics
Highway Engineering topicsShubham Sadh
 
Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptxBalpreetSingh47890
 
Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)Civil Zone
 
Station and Yards in Indian Railway
Station and Yards in Indian RailwayStation and Yards in Indian Railway
Station and Yards in Indian RailwayArbaz Kazi
 
Railways for urban transportation
Railways for urban transportationRailways for urban transportation
Railways for urban transportationgayathrysatheesan1
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossingshiranrathva
 
Railway Engineering- Basic Introduction
Railway Engineering- Basic IntroductionRailway Engineering- Basic Introduction
Railway Engineering- Basic IntroductionBathla Tuition Centre
 
Rail fastenings and joints
Rail fastenings and jointsRail fastenings and joints
Rail fastenings and jointsDeven Diran
 

What's hot (20)

Geometric design of highway
Geometric design of highwayGeometric design of highway
Geometric design of highway
 
Fittings and Fastenings of Rails.pdf
Fittings and Fastenings of Rails.pdfFittings and Fastenings of Rails.pdf
Fittings and Fastenings of Rails.pdf
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
 
Highway Development & Planning
Highway Development & PlanningHighway Development & Planning
Highway Development & Planning
 
Intersection,types
Intersection,typesIntersection,types
Intersection,types
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )
 
Elements of road x-section
Elements of road x-section Elements of road x-section
Elements of road x-section
 
O and d study
O and d studyO and d study
O and d study
 
Highway Cross-sectional Elements
Highway Cross-sectional ElementsHighway Cross-sectional Elements
Highway Cross-sectional Elements
 
Traffic volume
Traffic volumeTraffic volume
Traffic volume
 
IRC Method of Signal Design
IRC Method of Signal DesignIRC Method of Signal Design
IRC Method of Signal Design
 
Intersection designs ppt
Intersection designs pptIntersection designs ppt
Intersection designs ppt
 
Highway Engineering topics
Highway Engineering topicsHighway Engineering topics
Highway Engineering topics
 
Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptx
 
Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)
 
Station and Yards in Indian Railway
Station and Yards in Indian RailwayStation and Yards in Indian Railway
Station and Yards in Indian Railway
 
Railways for urban transportation
Railways for urban transportationRailways for urban transportation
Railways for urban transportation
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
 
Railway Engineering- Basic Introduction
Railway Engineering- Basic IntroductionRailway Engineering- Basic Introduction
Railway Engineering- Basic Introduction
 
Rail fastenings and joints
Rail fastenings and jointsRail fastenings and joints
Rail fastenings and joints
 

Similar to 4.engineering surveys

Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptxashish502848
 
Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)Saksham Bhutani
 
1_Highway Engg-Ch.1 Introduction_full.pdf
1_Highway Engg-Ch.1 Introduction_full.pdf1_Highway Engg-Ch.1 Introduction_full.pdf
1_Highway Engg-Ch.1 Introduction_full.pdfShivamKumar423966
 
Surveys & alignment of Railway Engineering
Surveys & alignment of Railway EngineeringSurveys & alignment of Railway Engineering
Surveys & alignment of Railway EngineeringLatif Hyder Wadho
 
Alignment Survey | Track Alignment | Civil TechMate
Alignment Survey | Track Alignment | Civil TechMateAlignment Survey | Track Alignment | Civil TechMate
Alignment Survey | Track Alignment | Civil TechMateCivil TechMate
 
ROAD NETWORKING AND SURVEYING
ROAD NETWORKING AND SURVEYINGROAD NETWORKING AND SURVEYING
ROAD NETWORKING AND SURVEYINGmanashkedia098
 
Design Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway AlignmentDesign Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway AlignmentIRJET Journal
 
3.alignment of railway lines
3.alignment of railway lines3.alignment of railway lines
3.alignment of railway linesMani Vel
 
What are the areas in Transportation Engineering, where Civil Eng.pdf
 What are the areas in Transportation Engineering, where Civil Eng.pdf What are the areas in Transportation Engineering, where Civil Eng.pdf
What are the areas in Transportation Engineering, where Civil Eng.pdfadmaniimran
 
VTU exam Question Paper with Solution of 18CV56 HIGHWAY ENGINEERING Jan-2021-...
VTU exam Question Paper with Solution of 18CV56 HIGHWAY ENGINEERING Jan-2021-...VTU exam Question Paper with Solution of 18CV56 HIGHWAY ENGINEERING Jan-2021-...
VTU exam Question Paper with Solution of 18CV56 HIGHWAY ENGINEERING Jan-2021-...pogeto1115
 
Optimum Cost Analysis For Selecting Best Suited Flexible Pavement Road Type F...
Optimum Cost Analysis For Selecting Best Suited Flexible Pavement Road Type F...Optimum Cost Analysis For Selecting Best Suited Flexible Pavement Road Type F...
Optimum Cost Analysis For Selecting Best Suited Flexible Pavement Road Type F...IRJET Journal
 
Engineering surveys and construction of new lines
Engineering surveys and construction of new linesEngineering surveys and construction of new lines
Engineering surveys and construction of new linesNasir Uddin
 
06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultransConsultrans, S.A.
 
Tunnel Presentation (1).pptx
Tunnel Presentation (1).pptxTunnel Presentation (1).pptx
Tunnel Presentation (1).pptxseifelsaie2
 
Minor project ppt1.pdf
Minor project ppt1.pdfMinor project ppt1.pdf
Minor project ppt1.pdfAnshuRaj51911
 

Similar to 4.engineering surveys (20)

Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptx
 
Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)
 
1_Highway Engg-Ch.1 Introduction_full.pdf
1_Highway Engg-Ch.1 Introduction_full.pdf1_Highway Engg-Ch.1 Introduction_full.pdf
1_Highway Engg-Ch.1 Introduction_full.pdf
 
Surveys & alignment of Railway Engineering
Surveys & alignment of Railway EngineeringSurveys & alignment of Railway Engineering
Surveys & alignment of Railway Engineering
 
Railway engineering part2
Railway engineering part2Railway engineering part2
Railway engineering part2
 
Alignment Survey | Track Alignment | Civil TechMate
Alignment Survey | Track Alignment | Civil TechMateAlignment Survey | Track Alignment | Civil TechMate
Alignment Survey | Track Alignment | Civil TechMate
 
ROAD NETWORKING AND SURVEYING
ROAD NETWORKING AND SURVEYINGROAD NETWORKING AND SURVEYING
ROAD NETWORKING AND SURVEYING
 
Design Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway AlignmentDesign Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway Alignment
 
3.alignment of railway lines
3.alignment of railway lines3.alignment of railway lines
3.alignment of railway lines
 
Unit 5
Unit 5Unit 5
Unit 5
 
What are the areas in Transportation Engineering, where Civil Eng.pdf
 What are the areas in Transportation Engineering, where Civil Eng.pdf What are the areas in Transportation Engineering, where Civil Eng.pdf
What are the areas in Transportation Engineering, where Civil Eng.pdf
 
VTU exam Question Paper with Solution of 18CV56 HIGHWAY ENGINEERING Jan-2021-...
VTU exam Question Paper with Solution of 18CV56 HIGHWAY ENGINEERING Jan-2021-...VTU exam Question Paper with Solution of 18CV56 HIGHWAY ENGINEERING Jan-2021-...
VTU exam Question Paper with Solution of 18CV56 HIGHWAY ENGINEERING Jan-2021-...
 
Optimum Cost Analysis For Selecting Best Suited Flexible Pavement Road Type F...
Optimum Cost Analysis For Selecting Best Suited Flexible Pavement Road Type F...Optimum Cost Analysis For Selecting Best Suited Flexible Pavement Road Type F...
Optimum Cost Analysis For Selecting Best Suited Flexible Pavement Road Type F...
 
Engineering surveys and construction of new lines
Engineering surveys and construction of new linesEngineering surveys and construction of new lines
Engineering surveys and construction of new lines
 
06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans
 
Road construction
Road constructionRoad construction
Road construction
 
Drawing And Report
Drawing And Report Drawing And Report
Drawing And Report
 
Tunnel Presentation (1).pptx
Tunnel Presentation (1).pptxTunnel Presentation (1).pptx
Tunnel Presentation (1).pptx
 
Minor project ppt1.pdf
Minor project ppt1.pdfMinor project ppt1.pdf
Minor project ppt1.pdf
 
20320130406022 2
20320130406022 220320130406022 2
20320130406022 2
 

More from Mani Vel

1.introduction
1.introduction1.introduction
1.introductionMani Vel
 
11.track junctions and layouts
11.track junctions and layouts11.track junctions and layouts
11.track junctions and layoutsMani Vel
 
5.track or permanent way and track stresses
5.track or permanent way and track stresses5.track or permanent way and track stresses
5.track or permanent way and track stressesMani Vel
 
1.railway engnieering
1.railway engnieering1.railway engnieering
1.railway engnieeringMani Vel
 
Railway Engineering - Geometric design of track
Railway Engineering - Geometric design of trackRailway Engineering - Geometric design of track
Railway Engineering - Geometric design of trackMani Vel
 
Railway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevationRailway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevationMani Vel
 
Road signs
Road signsRoad signs
Road signsMani Vel
 

More from Mani Vel (7)

1.introduction
1.introduction1.introduction
1.introduction
 
11.track junctions and layouts
11.track junctions and layouts11.track junctions and layouts
11.track junctions and layouts
 
5.track or permanent way and track stresses
5.track or permanent way and track stresses5.track or permanent way and track stresses
5.track or permanent way and track stresses
 
1.railway engnieering
1.railway engnieering1.railway engnieering
1.railway engnieering
 
Railway Engineering - Geometric design of track
Railway Engineering - Geometric design of trackRailway Engineering - Geometric design of track
Railway Engineering - Geometric design of track
 
Railway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevationRailway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevation
 
Road signs
Road signsRoad signs
Road signs
 

Recently uploaded

EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIkoyaldeepu123
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 

Recently uploaded (20)

EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AI
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 

4.engineering surveys

  • 1. Engineering Surveys and Construction of New Lines Mr MANIVEL M FACULTY,CIVIL ENGINEERING SCHOOL OF TECHNOLOGY PANDIT DEENDAYAL PETROLEUM UNIVERSITY GANDHINAGAR
  • 2. Introduction The construction of a new railway line is a capital-intensive project and each kilometre of a new railway line costs in the range of Rs 6 to 10 million depending upon the topography of the area, the standard of construction, and such other features. It is, therefore, natural that a lot of thought be given when making a final decision as to whether a new railway line is at all necessary or not.
  • 3. Need for Construction of a New Railway Line The need for construction of a new railway line arises because of one or more of the following considerations. (a) Strategic reasons It is sometimes necessary to extend the existing railway line to a new point of strategic importance so that the defence forces can move quickly to the some areas in case of any emergency such as the threat of war. (b) Political reasons A new line sometimes becomes necessary to serve the political needs of the country, for example, the railway line from Pathankot to Jammu.
  • 4. (c) Development of backward areas Railway lines are sometimes constructed to develop backward areas. Experience has shown that once railway communication is available, backward areas develop very fast. The Assam rail link can be classified in this category. (d) To connect new trade centres Sometimes new trade centres are connected with railway lines for the quick transportation of goods between two trade centres or from the point of production to the point of consumption.
  • 5. (e) To shorten the existing rail link: The existing routes between two important points may be longer than required. New railway lines are constructed on a shorter alignment in such cases. A short route is not only economical, but also helps in the faster movement of goods and passengers. The Konkan Railway is a typical example.
  • 6. Types of Surveys The following types of surveys are normally conducted: (a) Traffic survey (b) Reconnaissance survey (c) Preliminary survey (d) Final location survey
  • 7. (a) Traffic survey Traffic survey includes a detailed study of the traffic conditions in the area with a view to determine the Most promising route for the railway in the area, Possible traffic the railway line will carry, and Standard of railway line to be followed.
  • 8. Traffic survey consists of an economic study of the area keeping in mind the following considerations, information on which should be collected in detail: (a) Human resources (b) Agricultural and mineral resources (c) Pattern of trade and commerce (d) Industries located and projected (e) Prospects of tourist traffic (f) Existing transport facilities (g) Locations of important government and private offices (h) Planning for economic development of the area • The traffic survey team should make an assessment of the traffic likely to be carried by to the new line. While carrying out the survey, details of traffic likely to be offered by various government organizations, public bodies, or private enterprises should be gathered
  • 9. Survey Instruments Prismatic compass - To get magnetic bearings of the proposed alignment. Aneroid barometer - To ensure relative heights of various points. Abney level or hand level or clinometer - To measure the gradients or angles of slopes. Binocular - To view the physical features. Pedometer - To get an idea of the total length traversed while walking.
  • 10. Reconnaissance Survey This survey consists of a rapid and rough investigation of the area with a view to determine the technical feasibility of the proposal as well as the rough cost of one or more alternatives to the new line. The reconnaissance survey (RECCE) is normally based on contoured survey maps and other data already available without carrying out detailed investigations in the field. With the help of the maps, different alternative alignments of the new line are studied.
  • 11. Preliminary Survey The preliminary survey consists of a detailed instrumental examination of the route to be selected as a result of the reconnaissance survey in order to estimate the cost of the proposed railway line. Based on the preliminary and traffic survey reports, the railway administration decides whether or not the proposed railway line is to be constructed.
  • 12. Instruments for Preliminary Survey (a) Theodolite for traversing and pegging the centre line (b) Tacheometer for plotting the main features (c) Dumpy level for taking the longitudinal and cross levels (d) Plane table for getting details of various features (e) Prismatic compass for measuring the magnetic bearings of a particular alignment
  • 13. Final Location Survey Once a decision has been taken for a particular railway line to be constructed, a final location survey is done. The instruments used are generally the same as in the case of the preliminary survey. Final location survey is done to prepare working details and make accurate cost estimates in certain cases.
  • 14. The principal differences between the preliminary survey and the final survey are as follows. (a) In the final location survey, the alignment is fully staked with the help of a theodolite, whereas it is not obligatory to do so in the case of preliminary survey. (b) In the final location survey, a more detailed project report is prepared and submitted. (c) All working drawings are prepared in the final location survey.
  • 15. The following tasks are carried out in the final location survey. (a) The centre line is fully marked by pegs at 20 m. At each 100 m, a large peg should be used. (b) Masonry pillars are built at tangent points of curves and along the centre line at intervals of 500 m. (c) Longitudinal and cross levelling is done to ascertain the final gradient of the alignment. All gradients are compensated for curves. (d) The sites for station yards are fully demarcated.
  • 16. In the final location survey, the following set of drawings is prepared. (a) General map of the country traversed by the project at a scale of about 20 km to 1 cm (b) Index map, scale about 2.5 km to 1 cm (c) Index plan and sections (d) Detailed plans and sections (e) Plans and cross section (f) Plans of station yards (g) Detailed drawings of structures (h) Plans of junction arrangements