SlideShare a Scribd company logo
1 of 11
Content
1) Introduction to Hong Kong Project (Western Harbor Crossing Construction)
2) Aims & Objectives
3) Work Breakdown Structure (WBS)
4) Sample of Tasks
5) Project Plan & Applying Predecessors
6) Gantt Chart
7) Network Diagram
8) Critical Path
9) CPM Analysis
10) PERT Analysis
11) Monte Carlo Simulation
12) Tornado Diagram
13) Monte Carlo Simulation new
14) Changes in Tornado
15) PERT Analysis new
16) Risk Registration
17) Conclusion
Introduction
• Kai Tak airport was outdated and located next to
numerous skyscrapers and mountains.
• New world class airport needed, no land to spare.
• Proposal to build new airport at sea by creating a
new island in south china sea.
• Western Harbor tunnel was built to relieve
growing traffic congestion on the two existing
harbour crossings.
Aims & Objectives
• Build a 2km long tunnel with an estimated average of 10 km of associated roads.
• To relieve growing traffic congestion on the two existing harbour crossings
• The whole tunnel is built with the required quality (able to withstand a 6 lane road).
• Contribute to the transport infrastructure
• Traffic Capacity designed to reach Maximum 180,000 vehicles per day
• Tunnel Length to reach 1,975 m between portals at West Kowloon Reclamation Area and Sai Ying Pun
• Speed Limit is at a maximum of 80 km/hr
• Design Life of Tunnel Structure is around 120 years
Work Breakdown Structure (WBS)
Tunnel
Feasibility Study/
Survey
Construction
Feasibility
Electrical
Feasibility
Engineering
Feasibility
Weather Survey
Traffic Survey
Project Site
Survey
Potential
Location
Staff, Equipment
& Approval
Equipment
Survey
Government
Approval
Financial
Approval
Hire Staff &
Equipment
Site Work
Main Site
Quarry
Preparation
Tunnel
Manufacture
Steel & Concrete
Structure
Storage
Preparation
Transportation
Batch 1
Batch 2
Batch 3
Installation/
Assembly
Batch 1
Batch 2
Batch 3
Infrastructure
Drainage
Ventilation
Electrical Work
Install Road
Completing
Inlet/Outlet
Toll Booths
Handover
Return
Equipment
Testing (Safety)
Inspection
Documentation &
Licensing
Project Sign Off
Project Plan (Gantt Chart)
Network Diagram
Critical Path
PERT Analysis
Conclusion
• The Monte Carlo simulation gives a completion probability of 47.2%
• The classical CPM analysis underestimated the completion probability
• Monte Carlo simulation was run with 10000 iterations to achieve a realistic value
• From the Monte Carlo simulation it has shows a 64.4% completion probability.
• Changes in Tornado
• Methods of increasing probability to finish within the set date:
• The tasks are to be minimised by handing over to a third party contractor
• Run certain tasks simultaneously however there are greater risks and costs involved
• Minimise duration of critical tasks by investing into greater tasks force.
Thank You

More Related Content

Similar to Tunnel Presentation (1).pptx

59323623 1943-g-g-001-r c
59323623 1943-g-g-001-r c59323623 1943-g-g-001-r c
59323623 1943-g-g-001-r chomeworkping4
 
Formulation of detailed project report(final)
Formulation of detailed project report(final)Formulation of detailed project report(final)
Formulation of detailed project report(final)Parag Chaubey
 
TRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdfTRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdfKARTHIKGOUD64
 
4.engineering surveys
4.engineering surveys4.engineering surveys
4.engineering surveysMani Vel
 
33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)Pablo Miguel Jurado
 
1915Canakkale Bridge
1915Canakkale Bridge1915Canakkale Bridge
1915Canakkale BridgeZeynepUla2
 
Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zachary Maddox
 
2015 excellence-infrastructure-summary-slides-en
2015 excellence-infrastructure-summary-slides-en2015 excellence-infrastructure-summary-slides-en
2015 excellence-infrastructure-summary-slides-enTeresa Elliott
 
CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)
CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)
CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)amr mahrous
 
2015 Excellence in Infrastructure Submissions
2015 Excellence in Infrastructure Submissions2015 Excellence in Infrastructure Submissions
2015 Excellence in Infrastructure SubmissionsAutodesk AEC
 
06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultransConsultrans, S.A.
 
Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptxBalpreetSingh47890
 
Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptxashish502848
 

Similar to Tunnel Presentation (1).pptx (20)

59323623 1943-g-g-001-r c
59323623 1943-g-g-001-r c59323623 1943-g-g-001-r c
59323623 1943-g-g-001-r c
 
CV - Ahmed Mounir
CV - Ahmed MounirCV - Ahmed Mounir
CV - Ahmed Mounir
 
Formulation of detailed project report(final)
Formulation of detailed project report(final)Formulation of detailed project report(final)
Formulation of detailed project report(final)
 
JUNDEE MAR TEJEDO
JUNDEE MAR TEJEDOJUNDEE MAR TEJEDO
JUNDEE MAR TEJEDO
 
TRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdfTRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdf
 
4.engineering surveys
4.engineering surveys4.engineering surveys
4.engineering surveys
 
33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
1915Canakkale Bridge
1915Canakkale Bridge1915Canakkale Bridge
1915Canakkale Bridge
 
Mahmoud Ahmed ElbadawyCV
Mahmoud Ahmed ElbadawyCVMahmoud Ahmed ElbadawyCV
Mahmoud Ahmed ElbadawyCV
 
new 5 tanmay_CV
new 5 tanmay_CV new 5 tanmay_CV
new 5 tanmay_CV
 
MERAJ UL HUDA CV
MERAJ UL HUDA CVMERAJ UL HUDA CV
MERAJ UL HUDA CV
 
Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01
 
TRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGYTRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGY
 
2015 excellence-infrastructure-summary-slides-en
2015 excellence-infrastructure-summary-slides-en2015 excellence-infrastructure-summary-slides-en
2015 excellence-infrastructure-summary-slides-en
 
CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)
CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)
CV_Amr Abdelhamid Mahrous (Update 20 Oct 2015)
 
2015 Excellence in Infrastructure Submissions
2015 Excellence in Infrastructure Submissions2015 Excellence in Infrastructure Submissions
2015 Excellence in Infrastructure Submissions
 
06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans
 
Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptx
 
Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptx
 

Recently uploaded

Air Compressor reciprocating single stage
Air Compressor reciprocating single stageAir Compressor reciprocating single stage
Air Compressor reciprocating single stageAbc194748
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadhamedmustafa094
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxmaisarahman1
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksMagic Marks
 
Bridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxBridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxnuruddin69
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesRAJNEESHKUMAR341697
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...HenryBriggs2
 

Recently uploaded (20)

Air Compressor reciprocating single stage
Air Compressor reciprocating single stageAir Compressor reciprocating single stage
Air Compressor reciprocating single stage
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic Marks
 
Bridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxBridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptx
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 

Tunnel Presentation (1).pptx

  • 1. Content 1) Introduction to Hong Kong Project (Western Harbor Crossing Construction) 2) Aims & Objectives 3) Work Breakdown Structure (WBS) 4) Sample of Tasks 5) Project Plan & Applying Predecessors 6) Gantt Chart 7) Network Diagram 8) Critical Path 9) CPM Analysis 10) PERT Analysis 11) Monte Carlo Simulation 12) Tornado Diagram 13) Monte Carlo Simulation new 14) Changes in Tornado 15) PERT Analysis new 16) Risk Registration 17) Conclusion
  • 2. Introduction • Kai Tak airport was outdated and located next to numerous skyscrapers and mountains. • New world class airport needed, no land to spare. • Proposal to build new airport at sea by creating a new island in south china sea. • Western Harbor tunnel was built to relieve growing traffic congestion on the two existing harbour crossings.
  • 3. Aims & Objectives • Build a 2km long tunnel with an estimated average of 10 km of associated roads. • To relieve growing traffic congestion on the two existing harbour crossings • The whole tunnel is built with the required quality (able to withstand a 6 lane road). • Contribute to the transport infrastructure • Traffic Capacity designed to reach Maximum 180,000 vehicles per day • Tunnel Length to reach 1,975 m between portals at West Kowloon Reclamation Area and Sai Ying Pun • Speed Limit is at a maximum of 80 km/hr • Design Life of Tunnel Structure is around 120 years
  • 4. Work Breakdown Structure (WBS) Tunnel Feasibility Study/ Survey Construction Feasibility Electrical Feasibility Engineering Feasibility Weather Survey Traffic Survey Project Site Survey Potential Location Staff, Equipment & Approval Equipment Survey Government Approval Financial Approval Hire Staff & Equipment Site Work Main Site Quarry Preparation Tunnel Manufacture Steel & Concrete Structure Storage Preparation Transportation Batch 1 Batch 2 Batch 3 Installation/ Assembly Batch 1 Batch 2 Batch 3 Infrastructure Drainage Ventilation Electrical Work Install Road Completing Inlet/Outlet Toll Booths Handover Return Equipment Testing (Safety) Inspection Documentation & Licensing Project Sign Off
  • 5.
  • 10. Conclusion • The Monte Carlo simulation gives a completion probability of 47.2% • The classical CPM analysis underestimated the completion probability • Monte Carlo simulation was run with 10000 iterations to achieve a realistic value • From the Monte Carlo simulation it has shows a 64.4% completion probability. • Changes in Tornado • Methods of increasing probability to finish within the set date: • The tasks are to be minimised by handing over to a third party contractor • Run certain tasks simultaneously however there are greater risks and costs involved • Minimise duration of critical tasks by investing into greater tasks force.