SlideShare a Scribd company logo
1 of 16
PRESENTERS
     RAHMAT ALI                    SU/10-001-074081
     NASIRUDDIN                    SU/10-001-074075
     NUMAN NAZIR                   SU/10-001-074122

      SARHAD UNIVERSITY OF SCIENCE & INFORMATION TECHNOLOGY
                         PESHAWAR
                                        DATE: 22 Dec,2012
INTRODUCTION
The construction of a new
railway is a huge project
and each mile required
Rs.15 to 20 million
depending upon:

 The topography of area

Standard of construction

And some other features
Why we construct a new
railway lines?
 The need of constructing new railway line arises
 because of one or more consideration such as:
 Political reason.
 Development of backward areas.
 To connect new trade centers.
 To shorten the existing rail link etc.
Preliminary investigations for a new
railway line
Traffic survey:
 It includes detail
study of traffic
condition:
  • Possible traffic
    the railway line
    carry.
  • Standard of
    railway line.
  • Promising traffic
    the railway line
    will carry.
Preliminary investigations for a new
 railway line
Reconnaissance
survey:
This survey consists of a rapid
and rough investigation of the
area by using equipments of
survey:
Such as
   Prismatic compass
   Binocular
   pedometer
   Geodimeter
for measurement upto 80 km
distance during day and night
Use of laser etc
Distance upto 70 km can be
measured using laser.
Preliminary investigations
for a new railway line
Preliminary survey:
This survey consists of a detailed
instrumental examination of the
route to be selected in order to
estimate the cost of the proposed
railway line
By using:
Total station
Tachometer
Dumpy level etc.
Final location survey
Once a decision has been taken for a particular railway line to
be constructed a final location survey is done
Instruments used are the same as in the case of preliminary
survey
 Alignment is fully staked.
More detailed project report is prepared.
All working drawings are prepared.
Modern surveying
techniques
It includes:
   Satellite imagery
   Aerial photographs
   Contour maps
   Digital modeling.
   Photogrammetric
    modeling sheets
CONSTRUCTION OF NEW RAILWAY LINES
• Once the survey completed then construction
  works begin
• It includes
 Land acquisition
 Earthwork and bridges
 Station building, staff quarters
 Ballasting of tracks
CONSTRUCTION OF NEW RAILWAY LINES
 Land acquisition:
 It includes:
     Width of formation.

   Side slopes.

   Width of berms.

   Borrow pits.
CONSTRUCTION OF NEW RAILWAY LINES

Earth work for formation:
   The height of earth work depends on the high flood level.
   Mechanically compaction is done generally by sheep foot
    roller.
CONSTRUCTION OF NEW RAILWAY LINES
Bridges construction:
  Bridges increased the cost of the railway project.
  Bridges may be:
     Reinforced cement slab bridges.
     Steel bridges etc.
CONSTRUCTION OF NEW RAILWAY LINES
Track laying:
Once the formation is ready then
just track laying are required.

It consists:
Laying of ballast
Laying of sleepers and rails
 Fastenings
PLATE LAYING METHODS

1) Tram line method:
A temporary line laid
by the side of proposed
track.
Modification of this
method is the “side
method”.
Side method are
applicable when the
service road is parallel to
the track
PLATE LAYING METHODS

2) American method:
 Rails and sleepers are
first assembled and then
taken to the site.
At site track panels are
then unloaded either
manually or with the help
of cranes
For concrete sleepers
generally cranes are used.
Engineering surveys and construction of new lines

More Related Content

What's hot

Geometric Design of highway
Geometric Design of highway Geometric Design of highway
Geometric Design of highway RAMPRASAD KUMAWAT
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )mohit kumar panchal
 
Rail gauges & rail sections Railway Engineering
Rail gauges & rail sections  Railway EngineeringRail gauges & rail sections  Railway Engineering
Rail gauges & rail sections Railway EngineeringLatif Hyder Wadho
 
Highway construction PPT
Highway construction PPTHighway construction PPT
Highway construction PPTVikas Sukhwal
 
Introduction to railway engineering
Introduction to railway engineeringIntroduction to railway engineering
Introduction to railway engineeringSatyapal Singh
 
Traffic Volume Studies
Traffic Volume StudiesTraffic Volume Studies
Traffic Volume StudiesMd Tanvir Alam
 
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTUVATSAL PATEL
 
Overtaking sight distance
Overtaking sight distanceOvertaking sight distance
Overtaking sight distanceAglaia Connect
 
O and d study
O and d studyO and d study
O and d studymeetmksvs
 
Introduction to highway engineering
Introduction to highway engineeringIntroduction to highway engineering
Introduction to highway engineeringAavani Thampi
 
Traffic assignment
Traffic assignmentTraffic assignment
Traffic assignmentMNIT,JAIPUR
 
Transportation engineering
Transportation engineeringTransportation engineering
Transportation engineeringKHUSHBU SHAH
 
Role of transportation in Development
Role of transportation in DevelopmentRole of transportation in Development
Role of transportation in DevelopmentMalvika Jaishal
 

What's hot (20)

Trip generation
Trip generation Trip generation
Trip generation
 
Geometric Design of highway
Geometric Design of highway Geometric Design of highway
Geometric Design of highway
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )
 
Rail gauges & rail sections Railway Engineering
Rail gauges & rail sections  Railway EngineeringRail gauges & rail sections  Railway Engineering
Rail gauges & rail sections Railway Engineering
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
PERMANANT WAY
PERMANANT WAYPERMANANT WAY
PERMANANT WAY
 
Cross section of road
Cross section of roadCross section of road
Cross section of road
 
Highway construction PPT
Highway construction PPTHighway construction PPT
Highway construction PPT
 
Unit 3
Unit 3Unit 3
Unit 3
 
Introduction to railway engineering
Introduction to railway engineeringIntroduction to railway engineering
Introduction to railway engineering
 
Traffic Volume Studies
Traffic Volume StudiesTraffic Volume Studies
Traffic Volume Studies
 
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
 
Overtaking sight distance
Overtaking sight distanceOvertaking sight distance
Overtaking sight distance
 
O and d study
O and d studyO and d study
O and d study
 
Introduction to highway engineering
Introduction to highway engineeringIntroduction to highway engineering
Introduction to highway engineering
 
Traffic assignment
Traffic assignmentTraffic assignment
Traffic assignment
 
Transportation engineering
Transportation engineeringTransportation engineering
Transportation engineering
 
Role of transportation in Development
Role of transportation in DevelopmentRole of transportation in Development
Role of transportation in Development
 
Highway drainage
Highway drainageHighway drainage
Highway drainage
 

Similar to Engineering surveys and construction of new lines

Surveys & alignment of Railway Engineering
Surveys & alignment of Railway EngineeringSurveys & alignment of Railway Engineering
Surveys & alignment of Railway EngineeringLatif Hyder Wadho
 
Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)Saksham Bhutani
 
06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultransConsultrans, S.A.
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Crosstown TO
 
4.engineering surveys
4.engineering surveys4.engineering surveys
4.engineering surveysMani Vel
 
Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptxashish502848
 
Minor project ppt1.pdf
Minor project ppt1.pdfMinor project ppt1.pdf
Minor project ppt1.pdfAnshuRaj51911
 
Unit 1:- HIGHWAY DEVELOPMENT AND PLANNING
Unit 1:- HIGHWAY DEVELOPMENT AND PLANNINGUnit 1:- HIGHWAY DEVELOPMENT AND PLANNING
Unit 1:- HIGHWAY DEVELOPMENT AND PLANNINGRNRANGANATH
 
Needs Study of North Dakota Roads and Bridges Status Report
Needs Study of North Dakota Roads and Bridges Status ReportNeeds Study of North Dakota Roads and Bridges Status Report
Needs Study of North Dakota Roads and Bridges Status ReportUGPTI
 
Chapter 2 highway route surveys and locationaa
Chapter 2 highway route surveys and locationaaChapter 2 highway route surveys and locationaa
Chapter 2 highway route surveys and locationaaBashaFayissa1
 
Presentation_for_Road.pptx
Presentation_for_Road.pptxPresentation_for_Road.pptx
Presentation_for_Road.pptxSantoshKapse9
 
Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...JumpingJaq
 
Design Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway AlignmentDesign Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway AlignmentIRJET Journal
 

Similar to Engineering surveys and construction of new lines (20)

Surveys & alignment of Railway Engineering
Surveys & alignment of Railway EngineeringSurveys & alignment of Railway Engineering
Surveys & alignment of Railway Engineering
 
Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)
 
06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
 
4.engineering surveys
4.engineering surveys4.engineering surveys
4.engineering surveys
 
Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptx
 
Highway Projects
Highway Projects Highway Projects
Highway Projects
 
Minor project ppt1.pdf
Minor project ppt1.pdfMinor project ppt1.pdf
Minor project ppt1.pdf
 
Unit 1:- HIGHWAY DEVELOPMENT AND PLANNING
Unit 1:- HIGHWAY DEVELOPMENT AND PLANNINGUnit 1:- HIGHWAY DEVELOPMENT AND PLANNING
Unit 1:- HIGHWAY DEVELOPMENT AND PLANNING
 
transportation
transportationtransportation
transportation
 
Needs Study of North Dakota Roads and Bridges Status Report
Needs Study of North Dakota Roads and Bridges Status ReportNeeds Study of North Dakota Roads and Bridges Status Report
Needs Study of North Dakota Roads and Bridges Status Report
 
Naveed Asif C.V Updated
Naveed Asif C.V UpdatedNaveed Asif C.V Updated
Naveed Asif C.V Updated
 
Chapter 2 highway route surveys and locationaa
Chapter 2 highway route surveys and locationaaChapter 2 highway route surveys and locationaa
Chapter 2 highway route surveys and locationaa
 
GOPAL
GOPALGOPAL
GOPAL
 
Railway.pdf
Railway.pdfRailway.pdf
Railway.pdf
 
PPT Estimate.pptx
PPT Estimate.pptxPPT Estimate.pptx
PPT Estimate.pptx
 
Presentation_for_Road.pptx
Presentation_for_Road.pptxPresentation_for_Road.pptx
Presentation_for_Road.pptx
 
Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...
 
Tes p-122.08-r0
Tes p-122.08-r0Tes p-122.08-r0
Tes p-122.08-r0
 
Design Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway AlignmentDesign Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway Alignment
 

Engineering surveys and construction of new lines

  • 1. PRESENTERS RAHMAT ALI SU/10-001-074081 NASIRUDDIN SU/10-001-074075 NUMAN NAZIR SU/10-001-074122 SARHAD UNIVERSITY OF SCIENCE & INFORMATION TECHNOLOGY PESHAWAR DATE: 22 Dec,2012
  • 2. INTRODUCTION The construction of a new railway is a huge project and each mile required Rs.15 to 20 million depending upon:  The topography of area Standard of construction And some other features
  • 3. Why we construct a new railway lines? The need of constructing new railway line arises because of one or more consideration such as: Political reason. Development of backward areas. To connect new trade centers. To shorten the existing rail link etc.
  • 4. Preliminary investigations for a new railway line Traffic survey: It includes detail study of traffic condition: • Possible traffic the railway line carry. • Standard of railway line. • Promising traffic the railway line will carry.
  • 5. Preliminary investigations for a new railway line Reconnaissance survey: This survey consists of a rapid and rough investigation of the area by using equipments of survey: Such as Prismatic compass Binocular pedometer Geodimeter for measurement upto 80 km distance during day and night Use of laser etc Distance upto 70 km can be measured using laser.
  • 6. Preliminary investigations for a new railway line Preliminary survey: This survey consists of a detailed instrumental examination of the route to be selected in order to estimate the cost of the proposed railway line By using: Total station Tachometer Dumpy level etc.
  • 7. Final location survey Once a decision has been taken for a particular railway line to be constructed a final location survey is done Instruments used are the same as in the case of preliminary survey  Alignment is fully staked. More detailed project report is prepared. All working drawings are prepared.
  • 8. Modern surveying techniques It includes: Satellite imagery Aerial photographs Contour maps Digital modeling. Photogrammetric modeling sheets
  • 9. CONSTRUCTION OF NEW RAILWAY LINES • Once the survey completed then construction works begin • It includes Land acquisition Earthwork and bridges Station building, staff quarters Ballasting of tracks
  • 10. CONSTRUCTION OF NEW RAILWAY LINES Land acquisition: It includes: Width of formation. Side slopes. Width of berms. Borrow pits.
  • 11. CONSTRUCTION OF NEW RAILWAY LINES Earth work for formation:  The height of earth work depends on the high flood level.  Mechanically compaction is done generally by sheep foot roller.
  • 12. CONSTRUCTION OF NEW RAILWAY LINES Bridges construction: Bridges increased the cost of the railway project. Bridges may be: Reinforced cement slab bridges. Steel bridges etc.
  • 13. CONSTRUCTION OF NEW RAILWAY LINES Track laying: Once the formation is ready then just track laying are required. It consists: Laying of ballast Laying of sleepers and rails  Fastenings
  • 14. PLATE LAYING METHODS 1) Tram line method: A temporary line laid by the side of proposed track. Modification of this method is the “side method”. Side method are applicable when the service road is parallel to the track
  • 15. PLATE LAYING METHODS 2) American method:  Rails and sleepers are first assembled and then taken to the site. At site track panels are then unloaded either manually or with the help of cranes For concrete sleepers generally cranes are used.