SlideShare a Scribd company logo
1 of 14
7th US/German Workshop on Salt Repository
Research, Design, and Operation
WIPP Recovery and Lessons Learned
Tammy Reynolds – Deputy Project Manager
Nuclear Waste Partnership LLC
Washington, DC
September 7-9, 2016
WIPP Recovery and Lessons Learned
Background
 The Waste Isolation Pilot Plant (WIPP), located in New Mexico began construction in the
early 1980’s
 Receipt and disposal of Contact Handled (CH) waste began in March 1999
 Receipt and disposal of Remote Handled (RH) waste began in January 2007
 Between March 1999 and February 2014, WIPP safely and compliantly:
Received 11, 894 shipments and disposed the waste in the u/g,
90,627 cubic meters of CH TRU waste,
357 cubic meters of RH TRU waste
 In February 2014, WIPP operations were paused when a fire and a radiological event
occurred in the underground
 Recovery from the events is in progress and planned to be complete by the end of calendar
year 2016. Commencement of waste emplacement activities will begin as soon as it is safe
to do so.
2
WIPP Recovery and Lessons Learned
Fire Event
 February 5, 2014 a fire occurred in the u/g involving a salt haul truck
 86 workers in the u/g at the time of the fire were safely evacuated
 Investigated by both DOE and NWP
 DOE Accident Investigation Report issued on March 13, 2014
Radiological Event
 February 14, 2014 an exothermic reaction involving the mixture of the organic materials (absorbent
and/or neutralizer) and nitrate salts occurred inside a drum.
 Pressurization of the drum, failure of the drum locking ring, and displacement of the drum lid
 TRU waste propelled from the drum up into the polypropylene magnesium oxide (MgO) super
sacks on top of the containers and onto adjacent waste containers.
(Note: MgO is an assurance feature to ensure consistent and favorable chemical conditions are
maintained in the brines after final facility closure by reacting with any carbon dioxide produced
by the decay of organic carbon in the waste and waste emplacement materials.)
 Radiological Continuous Air Monitor (CAM) alarm received; ventilation interlocked to filtration
mode
 Small amount of leakage bypassed the HEPA filters and released into the atmosphere
 DOE Accident Investigation Report Phase I (response to the event) – issued on April 22, 2014
 DOE Accident Investigation Report Phase II (cause of the event) – issued on April 16, 2015 3
WIPP Recovery and Lessons Learned
Lessons Learned
 Nuclear Facility vs Mine Culture
 Although WIPP is a nuclear facility, there was a mining culture in place vs a nuclear culture
 Difference in expectations between waste handling and non-waste handling vehicles
(combustible buildup, manual vs auto fire detection/suppression)
 Operability and recognition of impaired critical safety equipment
 Fire protection program not adequately implemented at the WIPP facility
 No controls or programs in place for control of combustible materials or maintaining of fire
protection support systems
 Maintenance program not effectively implemented
– Combustible buildup on salt haul truck; chaining open ventilation doors; inoperable
ventilation fans; inoperable mine phones, obscured evacuation reflectors, disabling of
auto fire suppressions system; no overall method to understand status and impact of
impaired mine safety related equipment
 Mindset of production over maintenance based on complex wide priorities to accelerate
shipments from generator sites in support of individual site milestones and regulatory agreements
4
WIPP Recovery and Lessons Learned
Lessons Learned
 Training and drill programs
 Emergency management/preparedness and response programs not effectively implemented
 Limited drills, inadequate donning of self-rescuers or SCSRs during training or drills,
or hands on training with portable fire extinguishers
 Inconsistencies between u/g fire response procedures and drills/training
(shifting ventilation during evacuation)
 Expectations and capabilities of the Facility Shift Manager to manage all aspects of an
emergency or abnormal event
 CMR response (evaluation and protective actions) was less than adequate
 Identified problems with communications and alarms during the fire/evacuation
delaying egress
 National TRU Program not robust enough to identify incompatible waste
 Communications to the community and regulatory stakeholders was not timely
 Ensures trust is maintained rather than rebuilding that trust
5
WIPP Recovery and Lessons Learned
6
WIPP Recovery Managed as a Project
• Baseline established
• Scope, schedule, cost and risks reflected in the recovery baseline
• Primavera detailed schedule developed
• Progress tracked in Plan of the Day and Plan of the Week meetings
• Critical Path calculated on weekly basis
WIPP Recovery and Lessons Learned
7
Radiological and Ground Control Recovery
 Radiological release event in February 2014
 Prevented underground access for several
months; required “catch-up” bolting in areas
that had not been maintained during that period
 Created radiologically contaminated areas –
complicating all operations including bolting and
other ground control
 Ground control catchup efforts in the radiological
clean areas is complete. Ground control efforts are
now focused in the radiologically contaminated areas
 180K sq. ft. has been recovered and are
unrestricted
 130K sq. ft actively being worked
 50K sq. ft. “Restricted”
 10K sq. ft. “Prohibited
 Nominal bolt failure rate 40/week
 Bolt installation rate 110/week based on 11
shifts of bolting/week
WIPP Recovery and Lessons Learned
8
Facility/Equipment Improvements
 New Emergency Operating Center (EOC)
 Remodeled training facility
 U/G Ventilation fan reliability improvements
 Hybrid bolters
 Maintenance backlog reduction
 Interim Ventilation System
Program Improvements
 Fire Protection Program Plan
 DSA Revision 5 Implemented (STD 3009-2014)
 Increased training for fire response and 10X increase in drills
New Emergency
Operations Center
Hybrid Bolting Machine Combustible Control ZoneNew Equipment
WIPP Recovery and Lessons Learned
9
Enhanced Underground Safety
 New underground notification system
 U/G combustible reduction
 U/G localized fire suppression systems
 Vehicle auto fire suppression systems
 Improved mine stability and ground control
Aggressive Culture Change
 Leadership Academy
 Leaders Forum
 Focus on Values, Expectations, and Standards
Notification System Vehicle Fire Suppression
WIPP Recovery and Lessons Learned
10
 Phase I - Interim Ventilation System
 Two HEPA skids and fan units
 114,000 cfm of airflow
 Doubles the existing 60k cfm capacity
 Ensures adequate air flow at the waste face
for resumption of waste emplacement
 Increase airflow for ground control and
maintenance operations
 Phase II – Supplemental Ventilation
 Reconfiguring mine circuits and additional fans
 180,000 cfm airflow
 Phase III – Permanent Ventilation System
 Design and construct a new (permanent)
ventilation system
 Capable to provide 420,000 cfm
WIPP Recovery and Lessons Learned
11
National TRU Program
 DOE released the Enhanced National TRU Program Plan (June 2016)
 DOE placed HOLD on certifying TRU waste for shipment to WIPP
until new requirements are met
WIPP Recovery and Lessons Learned
12
National TRU Program – Moving Forward
 Re-Certification of Generator Sites
 Specific requirements for Previously Certified Waste
 Chemical Compatibility Evaluation
 Enhanced Acceptable Knowledge
 Evaluation of oxidizing chemicals
 Generator Site Technical Reviews
WIPP Recovery and Lessons Learned
13
Prioritization of Shipments:
 Initial focus of WIPP will be emplacement of waste currently in the Waste
Handling Building
 TRU site DOE Field Managers and DOE Headquarters met in August to begin the
discussion of TRU waste shipping priorities
WIPP Recovery and Lessons Learned
14
Incident Response
Investigation
U/G Recovery and Resumption of Ground Control (Bolting)
Isolation of Panel 6 and Panel 7, Room 7
Equipment Procurements and Upgrades
Interim Ventilation System
Authorization to Proceed – Commence Waste Emplacement Operations
DSA Revision and Implementation
Cold Operations
Management Self Assessment
Safety Management Program Improvements
Contractor Operational Readiness Review
DOE Operational Readiness Review – Regulator Concurrence

More Related Content

What's hot

Apec workshop 2 presentation 13 r wright apec-gccsi engineering disclipines...
Apec workshop 2 presentation 13  r wright apec-gccsi  engineering disclipines...Apec workshop 2 presentation 13  r wright apec-gccsi  engineering disclipines...
Apec workshop 2 presentation 13 r wright apec-gccsi engineering disclipines...Global CCS Institute
 
29 reed synergies
29 reed synergies29 reed synergies
29 reed synergiesleann_mays
 
02 highlights from integrated waste management system analyses, storage and t...
02 highlights from integrated waste management system analyses, storage and t...02 highlights from integrated waste management system analyses, storage and t...
02 highlights from integrated waste management system analyses, storage and t...leann_mays
 
11 spent fuel matrix degradation and canister corrosion quantifying the effec...
11 spent fuel matrix degradation and canister corrosion quantifying the effec...11 spent fuel matrix degradation and canister corrosion quantifying the effec...
11 spent fuel matrix degradation and canister corrosion quantifying the effec...leann_mays
 
31 session corrosion of spent nuclear fuel canisters bryan sand2017 5541 pe
31 session  corrosion of spent nuclear fuel canisters bryan sand2017 5541 pe31 session  corrosion of spent nuclear fuel canisters bryan sand2017 5541 pe
31 session corrosion of spent nuclear fuel canisters bryan sand2017 5541 peleann_mays
 
27 kuhlman sand2016 8647 c hydrologic-modeling-v2
27 kuhlman sand2016 8647 c hydrologic-modeling-v227 kuhlman sand2016 8647 c hydrologic-modeling-v2
27 kuhlman sand2016 8647 c hydrologic-modeling-v2leann_mays
 
Waste Confidence Rule Project Presentation for UM NERS 531
Waste Confidence Rule Project Presentation for UM NERS 531Waste Confidence Rule Project Presentation for UM NERS 531
Waste Confidence Rule Project Presentation for UM NERS 531Doug Kripke
 
Monitoring measuring and verification, Gonzalo Zambrano, University of Alberta
Monitoring measuring and verification, Gonzalo Zambrano, University of AlbertaMonitoring measuring and verification, Gonzalo Zambrano, University of Alberta
Monitoring measuring and verification, Gonzalo Zambrano, University of AlbertaGlobal CCS Institute
 
Le Trench DISPONET INTRO
Le Trench  DISPONET INTRO Le Trench  DISPONET INTRO
Le Trench DISPONET INTRO Peter ORMAI
 
EXIT SPEECH FOR BANGLADESH
EXIT SPEECH FOR BANGLADESHEXIT SPEECH FOR BANGLADESH
EXIT SPEECH FOR BANGLADESHPeter ORMAI
 
DISPOSAL CONCEPTS and OPTIONS
DISPOSAL CONCEPTS and OPTIONS DISPOSAL CONCEPTS and OPTIONS
DISPOSAL CONCEPTS and OPTIONS Peter ORMAI
 
One-Page Red Hill SI RA modeling Omaha feb13
One-Page Red Hill SI RA modeling Omaha feb13One-Page Red Hill SI RA modeling Omaha feb13
One-Page Red Hill SI RA modeling Omaha feb13Jeffrey Hart
 
K5 4 Wells Portal Success Story
K5 4 Wells Portal Success StoryK5 4 Wells Portal Success Story
K5 4 Wells Portal Success StoryDaljit Brar
 
Andrew Gorman resume 2015
Andrew Gorman resume 2015Andrew Gorman resume 2015
Andrew Gorman resume 2015Andrew Gorman
 
20191113 jbfs presentation final
20191113 jbfs presentation final20191113 jbfs presentation final
20191113 jbfs presentation finalecowatchers
 
LLW challenges and developments FINAL pptx
LLW challenges and developments FINAL pptxLLW challenges and developments FINAL pptx
LLW challenges and developments FINAL pptxPeter ORMAI
 
25 decovalex 2019 geochemical and reactive transport evaluations with relevan...
25 decovalex 2019 geochemical and reactive transport evaluations with relevan...25 decovalex 2019 geochemical and reactive transport evaluations with relevan...
25 decovalex 2019 geochemical and reactive transport evaluations with relevan...leann_mays
 
Stormwater Webinar 11 14 12 Final
Stormwater Webinar 11 14 12 FinalStormwater Webinar 11 14 12 Final
Stormwater Webinar 11 14 12 Finalaearles
 
Improving Reservoir Simulation Modeling with Seismic Attributes
Improving Reservoir Simulation Modeling with Seismic Attributes Improving Reservoir Simulation Modeling with Seismic Attributes
Improving Reservoir Simulation Modeling with Seismic Attributes Society of Petroleum Engineers
 

What's hot (20)

Apec workshop 2 presentation 13 r wright apec-gccsi engineering disclipines...
Apec workshop 2 presentation 13  r wright apec-gccsi  engineering disclipines...Apec workshop 2 presentation 13  r wright apec-gccsi  engineering disclipines...
Apec workshop 2 presentation 13 r wright apec-gccsi engineering disclipines...
 
29 reed synergies
29 reed synergies29 reed synergies
29 reed synergies
 
02 highlights from integrated waste management system analyses, storage and t...
02 highlights from integrated waste management system analyses, storage and t...02 highlights from integrated waste management system analyses, storage and t...
02 highlights from integrated waste management system analyses, storage and t...
 
11 spent fuel matrix degradation and canister corrosion quantifying the effec...
11 spent fuel matrix degradation and canister corrosion quantifying the effec...11 spent fuel matrix degradation and canister corrosion quantifying the effec...
11 spent fuel matrix degradation and canister corrosion quantifying the effec...
 
31 session corrosion of spent nuclear fuel canisters bryan sand2017 5541 pe
31 session  corrosion of spent nuclear fuel canisters bryan sand2017 5541 pe31 session  corrosion of spent nuclear fuel canisters bryan sand2017 5541 pe
31 session corrosion of spent nuclear fuel canisters bryan sand2017 5541 pe
 
27 kuhlman sand2016 8647 c hydrologic-modeling-v2
27 kuhlman sand2016 8647 c hydrologic-modeling-v227 kuhlman sand2016 8647 c hydrologic-modeling-v2
27 kuhlman sand2016 8647 c hydrologic-modeling-v2
 
Waste Confidence Rule Project Presentation for UM NERS 531
Waste Confidence Rule Project Presentation for UM NERS 531Waste Confidence Rule Project Presentation for UM NERS 531
Waste Confidence Rule Project Presentation for UM NERS 531
 
Monitoring measuring and verification, Gonzalo Zambrano, University of Alberta
Monitoring measuring and verification, Gonzalo Zambrano, University of AlbertaMonitoring measuring and verification, Gonzalo Zambrano, University of Alberta
Monitoring measuring and verification, Gonzalo Zambrano, University of Alberta
 
Le Trench DISPONET INTRO
Le Trench  DISPONET INTRO Le Trench  DISPONET INTRO
Le Trench DISPONET INTRO
 
EXIT SPEECH FOR BANGLADESH
EXIT SPEECH FOR BANGLADESHEXIT SPEECH FOR BANGLADESH
EXIT SPEECH FOR BANGLADESH
 
DISPOSAL CONCEPTS and OPTIONS
DISPOSAL CONCEPTS and OPTIONS DISPOSAL CONCEPTS and OPTIONS
DISPOSAL CONCEPTS and OPTIONS
 
One-Page Red Hill SI RA modeling Omaha feb13
One-Page Red Hill SI RA modeling Omaha feb13One-Page Red Hill SI RA modeling Omaha feb13
One-Page Red Hill SI RA modeling Omaha feb13
 
K5 4 Wells Portal Success Story
K5 4 Wells Portal Success StoryK5 4 Wells Portal Success Story
K5 4 Wells Portal Success Story
 
Andrew Gorman resume 2015
Andrew Gorman resume 2015Andrew Gorman resume 2015
Andrew Gorman resume 2015
 
20191113 jbfs presentation final
20191113 jbfs presentation final20191113 jbfs presentation final
20191113 jbfs presentation final
 
LLW challenges and developments FINAL pptx
LLW challenges and developments FINAL pptxLLW challenges and developments FINAL pptx
LLW challenges and developments FINAL pptx
 
25 decovalex 2019 geochemical and reactive transport evaluations with relevan...
25 decovalex 2019 geochemical and reactive transport evaluations with relevan...25 decovalex 2019 geochemical and reactive transport evaluations with relevan...
25 decovalex 2019 geochemical and reactive transport evaluations with relevan...
 
Stormwater Webinar 11 14 12 Final
Stormwater Webinar 11 14 12 FinalStormwater Webinar 11 14 12 Final
Stormwater Webinar 11 14 12 Final
 
Improving Reservoir Simulation Modeling with Seismic Attributes
Improving Reservoir Simulation Modeling with Seismic Attributes Improving Reservoir Simulation Modeling with Seismic Attributes
Improving Reservoir Simulation Modeling with Seismic Attributes
 
George Stosur
George StosurGeorge Stosur
George Stosur
 

Similar to 09 reynolds 7th salt workshop (trr)

Case Study – WIPP Radiological Release NSE 515 11212018 .docx
Case Study – WIPP Radiological Release NSE 515 11212018 .docxCase Study – WIPP Radiological Release NSE 515 11212018 .docx
Case Study – WIPP Radiological Release NSE 515 11212018 .docxdrennanmicah
 
09 reynolds wipp recovery and lessons learned
09 reynolds wipp recovery and lessons learned09 reynolds wipp recovery and lessons learned
09 reynolds wipp recovery and lessons learnedleann_mays
 
Exploitation of Source Rock Hydrocarbons through Propane Stimulation
Exploitation of Source Rock Hydrocarbons through Propane StimulationExploitation of Source Rock Hydrocarbons through Propane Stimulation
Exploitation of Source Rock Hydrocarbons through Propane StimulationecorpStim
 
Urban Water Quality Issues
Urban Water Quality IssuesUrban Water Quality Issues
Urban Water Quality Issuesnacaa
 
Lake Ontario Waterkeeper's submissions for Pickering Waste Management Facilit...
Lake Ontario Waterkeeper's submissions for Pickering Waste Management Facilit...Lake Ontario Waterkeeper's submissions for Pickering Waste Management Facilit...
Lake Ontario Waterkeeper's submissions for Pickering Waste Management Facilit...LOWaterkeeper
 
LauraEngells_FinalPresentation
LauraEngells_FinalPresentationLauraEngells_FinalPresentation
LauraEngells_FinalPresentationLaura Engells
 
1.-Landfill-basics.pdf
1.-Landfill-basics.pdf1.-Landfill-basics.pdf
1.-Landfill-basics.pdfMartinP31
 
DarlingtonRefurb_PerfomanceReport_July2014
DarlingtonRefurb_PerfomanceReport_July2014DarlingtonRefurb_PerfomanceReport_July2014
DarlingtonRefurb_PerfomanceReport_July2014Piyush Sharma
 
uk_fifth_national_report_compliance_obligations_joint_convention_safety_spent...
uk_fifth_national_report_compliance_obligations_joint_convention_safety_spent...uk_fifth_national_report_compliance_obligations_joint_convention_safety_spent...
uk_fifth_national_report_compliance_obligations_joint_convention_safety_spent...Phillip Hudson
 
Regulatory Update 2015
Regulatory Update 2015Regulatory Update 2015
Regulatory Update 2015Jane Besch
 

Similar to 09 reynolds 7th salt workshop (trr) (20)

Case Study – WIPP Radiological Release NSE 515 11212018 .docx
Case Study – WIPP Radiological Release NSE 515 11212018 .docxCase Study – WIPP Radiological Release NSE 515 11212018 .docx
Case Study – WIPP Radiological Release NSE 515 11212018 .docx
 
21 WIPP recovery and Operational Safety
21 WIPP recovery and Operational Safety21 WIPP recovery and Operational Safety
21 WIPP recovery and Operational Safety
 
09 reynolds wipp recovery and lessons learned
09 reynolds wipp recovery and lessons learned09 reynolds wipp recovery and lessons learned
09 reynolds wipp recovery and lessons learned
 
Exploitation of Source Rock Hydrocarbons through Propane Stimulation
Exploitation of Source Rock Hydrocarbons through Propane StimulationExploitation of Source Rock Hydrocarbons through Propane Stimulation
Exploitation of Source Rock Hydrocarbons through Propane Stimulation
 
project resume
project resumeproject resume
project resume
 
Regulation of Landfill in Ireland
Regulation of Landfill in IrelandRegulation of Landfill in Ireland
Regulation of Landfill in Ireland
 
The Pueblo Plant: A Year in Review 2013
The Pueblo Plant: A Year in Review 2013The Pueblo Plant: A Year in Review 2013
The Pueblo Plant: A Year in Review 2013
 
CAMS GA Aerosols
CAMS GA  AerosolsCAMS GA  Aerosols
CAMS GA Aerosols
 
ADBA Spring Regulatory Forum - May 2016
ADBA Spring Regulatory Forum - May 2016ADBA Spring Regulatory Forum - May 2016
ADBA Spring Regulatory Forum - May 2016
 
SPW_51_23
SPW_51_23SPW_51_23
SPW_51_23
 
Utah's Air quality Program
Utah's Air quality ProgramUtah's Air quality Program
Utah's Air quality Program
 
Urban Water Quality Issues
Urban Water Quality IssuesUrban Water Quality Issues
Urban Water Quality Issues
 
Lake Ontario Waterkeeper's submissions for Pickering Waste Management Facilit...
Lake Ontario Waterkeeper's submissions for Pickering Waste Management Facilit...Lake Ontario Waterkeeper's submissions for Pickering Waste Management Facilit...
Lake Ontario Waterkeeper's submissions for Pickering Waste Management Facilit...
 
Frank resume 20150707
Frank resume 20150707Frank resume 20150707
Frank resume 20150707
 
Jim.CV.July 16 (1)
Jim.CV.July 16 (1)Jim.CV.July 16 (1)
Jim.CV.July 16 (1)
 
LauraEngells_FinalPresentation
LauraEngells_FinalPresentationLauraEngells_FinalPresentation
LauraEngells_FinalPresentation
 
1.-Landfill-basics.pdf
1.-Landfill-basics.pdf1.-Landfill-basics.pdf
1.-Landfill-basics.pdf
 
DarlingtonRefurb_PerfomanceReport_July2014
DarlingtonRefurb_PerfomanceReport_July2014DarlingtonRefurb_PerfomanceReport_July2014
DarlingtonRefurb_PerfomanceReport_July2014
 
uk_fifth_national_report_compliance_obligations_joint_convention_safety_spent...
uk_fifth_national_report_compliance_obligations_joint_convention_safety_spent...uk_fifth_national_report_compliance_obligations_joint_convention_safety_spent...
uk_fifth_national_report_compliance_obligations_joint_convention_safety_spent...
 
Regulatory Update 2015
Regulatory Update 2015Regulatory Update 2015
Regulatory Update 2015
 

More from leann_mays

43 international collaboration skb ebs task force overview jove-colon sand2...
43 international collaboration skb ebs task force   overview jove-colon sand2...43 international collaboration skb ebs task force   overview jove-colon sand2...
43 international collaboration skb ebs task force overview jove-colon sand2...leann_mays
 
27 task f fluid inclusion and movement in tight rocks wang sand2017-4132 pe...
27 task f   fluid inclusion and movement in tight rocks wang sand2017-4132 pe...27 task f   fluid inclusion and movement in tight rocks wang sand2017-4132 pe...
27 task f fluid inclusion and movement in tight rocks wang sand2017-4132 pe...leann_mays
 
13 ensa enun 32 p rail cask transport tests start june 2017 mcconnell sand201...
13 ensa enun 32 p rail cask transport tests start june 2017 mcconnell sand201...13 ensa enun 32 p rail cask transport tests start june 2017 mcconnell sand201...
13 ensa enun 32 p rail cask transport tests start june 2017 mcconnell sand201...leann_mays
 
03 dry cask simulator experiments for cfd validation durbin sand2017 4330 c
03 dry cask simulator experiments for cfd validation durbin sand2017 4330 c03 dry cask simulator experiments for cfd validation durbin sand2017 4330 c
03 dry cask simulator experiments for cfd validation durbin sand2017 4330 cleann_mays
 
17 laboratory testing approach for intermediate scale borehole heater test mi...
17 laboratory testing approach for intermediate scale borehole heater test mi...17 laboratory testing approach for intermediate scale borehole heater test mi...
17 laboratory testing approach for intermediate scale borehole heater test mi...leann_mays
 
10 sfwst – disposal in argillite r&d barrier material degradation and int...
10 sfwst – disposal in argillite r&d barrier material degradation and int...10 sfwst – disposal in argillite r&d barrier material degradation and int...
10 sfwst – disposal in argillite r&d barrier material degradation and int...leann_mays
 
07 international collaboration activities in disposal r and d relevance to r ...
07 international collaboration activities in disposal r and d relevance to r ...07 international collaboration activities in disposal r and d relevance to r ...
07 international collaboration activities in disposal r and d relevance to r ...leann_mays
 
59 an example of a regional geologic evaluation of argillite for disposal of ...
59 an example of a regional geologic evaluation of argillite for disposal of ...59 an example of a regional geologic evaluation of argillite for disposal of ...
59 an example of a regional geologic evaluation of argillite for disposal of ...leann_mays
 
51 update on the fifth worldwide review international approaches for nuclear ...
51 update on the fifth worldwide review international approaches for nuclear ...51 update on the fifth worldwide review international approaches for nuclear ...
51 update on the fifth worldwide review international approaches for nuclear ...leann_mays
 
49 collaboration with swedish deep drilling project dobson lbnl
49 collaboration with swedish deep drilling project dobson lbnl49 collaboration with swedish deep drilling project dobson lbnl
49 collaboration with swedish deep drilling project dobson lbnlleann_mays
 
46 collaboration with clausthal germany on coupled thm modeling rutqvist lbnl
46 collaboration with clausthal germany on coupled thm modeling rutqvist lbnl46 collaboration with clausthal germany on coupled thm modeling rutqvist lbnl
46 collaboration with clausthal germany on coupled thm modeling rutqvist lbnlleann_mays
 
34 ciscc susceptibility and cgr testing sindelar srnl sti-2017-00323
34 ciscc susceptibility and cgr testing sindelar srnl sti-2017-0032334 ciscc susceptibility and cgr testing sindelar srnl sti-2017-00323
34 ciscc susceptibility and cgr testing sindelar srnl sti-2017-00323leann_mays
 
33 residual stress simulation and experimental stress replication of mock up ...
33 residual stress simulation and experimental stress replication of mock up ...33 residual stress simulation and experimental stress replication of mock up ...
33 residual stress simulation and experimental stress replication of mock up ...leann_mays
 
32 field test at maine yankee independent spent fuel storage instillation gor...
32 field test at maine yankee independent spent fuel storage instillation gor...32 field test at maine yankee independent spent fuel storage instillation gor...
32 field test at maine yankee independent spent fuel storage instillation gor...leann_mays
 
30 fe heater test at mont terri rutqvist lbnl
30 fe heater test at mont terri rutqvist lbnl30 fe heater test at mont terri rutqvist lbnl
30 fe heater test at mont terri rutqvist lbnlleann_mays
 
29 international collaboration in disposal research fs experiment at mont ter...
29 international collaboration in disposal research fs experiment at mont ter...29 international collaboration in disposal research fs experiment at mont ter...
29 international collaboration in disposal research fs experiment at mont ter...leann_mays
 
28 international collaboration in disposal research mont terri project birkho...
28 international collaboration in disposal research mont terri project birkho...28 international collaboration in disposal research mont terri project birkho...
28 international collaboration in disposal research mont terri project birkho...leann_mays
 
27b potential hot bent collaboration zheng v0 lbnl
27b potential hot bent collaboration zheng v0 lbnl27b potential hot bent collaboration zheng v0 lbnl
27b potential hot bent collaboration zheng v0 lbnlleann_mays
 
27a febex dp collaboration overview and related sfwst r and d activities zhen...
27a febex dp collaboration overview and related sfwst r and d activities zhen...27a febex dp collaboration overview and related sfwst r and d activities zhen...
27a febex dp collaboration overview and related sfwst r and d activities zhen...leann_mays
 
24 upscaling of heater tests in bure rutqvist lbnl
24 upscaling of heater tests in bure rutqvist lbnl24 upscaling of heater tests in bure rutqvist lbnl
24 upscaling of heater tests in bure rutqvist lbnlleann_mays
 

More from leann_mays (20)

43 international collaboration skb ebs task force overview jove-colon sand2...
43 international collaboration skb ebs task force   overview jove-colon sand2...43 international collaboration skb ebs task force   overview jove-colon sand2...
43 international collaboration skb ebs task force overview jove-colon sand2...
 
27 task f fluid inclusion and movement in tight rocks wang sand2017-4132 pe...
27 task f   fluid inclusion and movement in tight rocks wang sand2017-4132 pe...27 task f   fluid inclusion and movement in tight rocks wang sand2017-4132 pe...
27 task f fluid inclusion and movement in tight rocks wang sand2017-4132 pe...
 
13 ensa enun 32 p rail cask transport tests start june 2017 mcconnell sand201...
13 ensa enun 32 p rail cask transport tests start june 2017 mcconnell sand201...13 ensa enun 32 p rail cask transport tests start june 2017 mcconnell sand201...
13 ensa enun 32 p rail cask transport tests start june 2017 mcconnell sand201...
 
03 dry cask simulator experiments for cfd validation durbin sand2017 4330 c
03 dry cask simulator experiments for cfd validation durbin sand2017 4330 c03 dry cask simulator experiments for cfd validation durbin sand2017 4330 c
03 dry cask simulator experiments for cfd validation durbin sand2017 4330 c
 
17 laboratory testing approach for intermediate scale borehole heater test mi...
17 laboratory testing approach for intermediate scale borehole heater test mi...17 laboratory testing approach for intermediate scale borehole heater test mi...
17 laboratory testing approach for intermediate scale borehole heater test mi...
 
10 sfwst – disposal in argillite r&d barrier material degradation and int...
10 sfwst – disposal in argillite r&d barrier material degradation and int...10 sfwst – disposal in argillite r&d barrier material degradation and int...
10 sfwst – disposal in argillite r&d barrier material degradation and int...
 
07 international collaboration activities in disposal r and d relevance to r ...
07 international collaboration activities in disposal r and d relevance to r ...07 international collaboration activities in disposal r and d relevance to r ...
07 international collaboration activities in disposal r and d relevance to r ...
 
59 an example of a regional geologic evaluation of argillite for disposal of ...
59 an example of a regional geologic evaluation of argillite for disposal of ...59 an example of a regional geologic evaluation of argillite for disposal of ...
59 an example of a regional geologic evaluation of argillite for disposal of ...
 
51 update on the fifth worldwide review international approaches for nuclear ...
51 update on the fifth worldwide review international approaches for nuclear ...51 update on the fifth worldwide review international approaches for nuclear ...
51 update on the fifth worldwide review international approaches for nuclear ...
 
49 collaboration with swedish deep drilling project dobson lbnl
49 collaboration with swedish deep drilling project dobson lbnl49 collaboration with swedish deep drilling project dobson lbnl
49 collaboration with swedish deep drilling project dobson lbnl
 
46 collaboration with clausthal germany on coupled thm modeling rutqvist lbnl
46 collaboration with clausthal germany on coupled thm modeling rutqvist lbnl46 collaboration with clausthal germany on coupled thm modeling rutqvist lbnl
46 collaboration with clausthal germany on coupled thm modeling rutqvist lbnl
 
34 ciscc susceptibility and cgr testing sindelar srnl sti-2017-00323
34 ciscc susceptibility and cgr testing sindelar srnl sti-2017-0032334 ciscc susceptibility and cgr testing sindelar srnl sti-2017-00323
34 ciscc susceptibility and cgr testing sindelar srnl sti-2017-00323
 
33 residual stress simulation and experimental stress replication of mock up ...
33 residual stress simulation and experimental stress replication of mock up ...33 residual stress simulation and experimental stress replication of mock up ...
33 residual stress simulation and experimental stress replication of mock up ...
 
32 field test at maine yankee independent spent fuel storage instillation gor...
32 field test at maine yankee independent spent fuel storage instillation gor...32 field test at maine yankee independent spent fuel storage instillation gor...
32 field test at maine yankee independent spent fuel storage instillation gor...
 
30 fe heater test at mont terri rutqvist lbnl
30 fe heater test at mont terri rutqvist lbnl30 fe heater test at mont terri rutqvist lbnl
30 fe heater test at mont terri rutqvist lbnl
 
29 international collaboration in disposal research fs experiment at mont ter...
29 international collaboration in disposal research fs experiment at mont ter...29 international collaboration in disposal research fs experiment at mont ter...
29 international collaboration in disposal research fs experiment at mont ter...
 
28 international collaboration in disposal research mont terri project birkho...
28 international collaboration in disposal research mont terri project birkho...28 international collaboration in disposal research mont terri project birkho...
28 international collaboration in disposal research mont terri project birkho...
 
27b potential hot bent collaboration zheng v0 lbnl
27b potential hot bent collaboration zheng v0 lbnl27b potential hot bent collaboration zheng v0 lbnl
27b potential hot bent collaboration zheng v0 lbnl
 
27a febex dp collaboration overview and related sfwst r and d activities zhen...
27a febex dp collaboration overview and related sfwst r and d activities zhen...27a febex dp collaboration overview and related sfwst r and d activities zhen...
27a febex dp collaboration overview and related sfwst r and d activities zhen...
 
24 upscaling of heater tests in bure rutqvist lbnl
24 upscaling of heater tests in bure rutqvist lbnl24 upscaling of heater tests in bure rutqvist lbnl
24 upscaling of heater tests in bure rutqvist lbnl
 

Recently uploaded

Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsAndrey Dotsenko
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptxLBM Solutions
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentationphoebematthew05
 
Bluetooth Controlled Car with Arduino.pdf
Bluetooth Controlled Car with Arduino.pdfBluetooth Controlled Car with Arduino.pdf
Bluetooth Controlled Car with Arduino.pdfngoud9212
 
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024BookNet Canada
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraDeakin University
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 

Recently uploaded (20)

Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
The transition to renewables in India.pdf
The transition to renewables in India.pdfThe transition to renewables in India.pdf
The transition to renewables in India.pdf
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptx
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentation
 
Bluetooth Controlled Car with Arduino.pdf
Bluetooth Controlled Car with Arduino.pdfBluetooth Controlled Car with Arduino.pdf
Bluetooth Controlled Car with Arduino.pdf
 
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning era
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 

09 reynolds 7th salt workshop (trr)

  • 1. 7th US/German Workshop on Salt Repository Research, Design, and Operation WIPP Recovery and Lessons Learned Tammy Reynolds – Deputy Project Manager Nuclear Waste Partnership LLC Washington, DC September 7-9, 2016
  • 2. WIPP Recovery and Lessons Learned Background  The Waste Isolation Pilot Plant (WIPP), located in New Mexico began construction in the early 1980’s  Receipt and disposal of Contact Handled (CH) waste began in March 1999  Receipt and disposal of Remote Handled (RH) waste began in January 2007  Between March 1999 and February 2014, WIPP safely and compliantly: Received 11, 894 shipments and disposed the waste in the u/g, 90,627 cubic meters of CH TRU waste, 357 cubic meters of RH TRU waste  In February 2014, WIPP operations were paused when a fire and a radiological event occurred in the underground  Recovery from the events is in progress and planned to be complete by the end of calendar year 2016. Commencement of waste emplacement activities will begin as soon as it is safe to do so. 2
  • 3. WIPP Recovery and Lessons Learned Fire Event  February 5, 2014 a fire occurred in the u/g involving a salt haul truck  86 workers in the u/g at the time of the fire were safely evacuated  Investigated by both DOE and NWP  DOE Accident Investigation Report issued on March 13, 2014 Radiological Event  February 14, 2014 an exothermic reaction involving the mixture of the organic materials (absorbent and/or neutralizer) and nitrate salts occurred inside a drum.  Pressurization of the drum, failure of the drum locking ring, and displacement of the drum lid  TRU waste propelled from the drum up into the polypropylene magnesium oxide (MgO) super sacks on top of the containers and onto adjacent waste containers. (Note: MgO is an assurance feature to ensure consistent and favorable chemical conditions are maintained in the brines after final facility closure by reacting with any carbon dioxide produced by the decay of organic carbon in the waste and waste emplacement materials.)  Radiological Continuous Air Monitor (CAM) alarm received; ventilation interlocked to filtration mode  Small amount of leakage bypassed the HEPA filters and released into the atmosphere  DOE Accident Investigation Report Phase I (response to the event) – issued on April 22, 2014  DOE Accident Investigation Report Phase II (cause of the event) – issued on April 16, 2015 3
  • 4. WIPP Recovery and Lessons Learned Lessons Learned  Nuclear Facility vs Mine Culture  Although WIPP is a nuclear facility, there was a mining culture in place vs a nuclear culture  Difference in expectations between waste handling and non-waste handling vehicles (combustible buildup, manual vs auto fire detection/suppression)  Operability and recognition of impaired critical safety equipment  Fire protection program not adequately implemented at the WIPP facility  No controls or programs in place for control of combustible materials or maintaining of fire protection support systems  Maintenance program not effectively implemented – Combustible buildup on salt haul truck; chaining open ventilation doors; inoperable ventilation fans; inoperable mine phones, obscured evacuation reflectors, disabling of auto fire suppressions system; no overall method to understand status and impact of impaired mine safety related equipment  Mindset of production over maintenance based on complex wide priorities to accelerate shipments from generator sites in support of individual site milestones and regulatory agreements 4
  • 5. WIPP Recovery and Lessons Learned Lessons Learned  Training and drill programs  Emergency management/preparedness and response programs not effectively implemented  Limited drills, inadequate donning of self-rescuers or SCSRs during training or drills, or hands on training with portable fire extinguishers  Inconsistencies between u/g fire response procedures and drills/training (shifting ventilation during evacuation)  Expectations and capabilities of the Facility Shift Manager to manage all aspects of an emergency or abnormal event  CMR response (evaluation and protective actions) was less than adequate  Identified problems with communications and alarms during the fire/evacuation delaying egress  National TRU Program not robust enough to identify incompatible waste  Communications to the community and regulatory stakeholders was not timely  Ensures trust is maintained rather than rebuilding that trust 5
  • 6. WIPP Recovery and Lessons Learned 6 WIPP Recovery Managed as a Project • Baseline established • Scope, schedule, cost and risks reflected in the recovery baseline • Primavera detailed schedule developed • Progress tracked in Plan of the Day and Plan of the Week meetings • Critical Path calculated on weekly basis
  • 7. WIPP Recovery and Lessons Learned 7 Radiological and Ground Control Recovery  Radiological release event in February 2014  Prevented underground access for several months; required “catch-up” bolting in areas that had not been maintained during that period  Created radiologically contaminated areas – complicating all operations including bolting and other ground control  Ground control catchup efforts in the radiological clean areas is complete. Ground control efforts are now focused in the radiologically contaminated areas  180K sq. ft. has been recovered and are unrestricted  130K sq. ft actively being worked  50K sq. ft. “Restricted”  10K sq. ft. “Prohibited  Nominal bolt failure rate 40/week  Bolt installation rate 110/week based on 11 shifts of bolting/week
  • 8. WIPP Recovery and Lessons Learned 8 Facility/Equipment Improvements  New Emergency Operating Center (EOC)  Remodeled training facility  U/G Ventilation fan reliability improvements  Hybrid bolters  Maintenance backlog reduction  Interim Ventilation System Program Improvements  Fire Protection Program Plan  DSA Revision 5 Implemented (STD 3009-2014)  Increased training for fire response and 10X increase in drills New Emergency Operations Center Hybrid Bolting Machine Combustible Control ZoneNew Equipment
  • 9. WIPP Recovery and Lessons Learned 9 Enhanced Underground Safety  New underground notification system  U/G combustible reduction  U/G localized fire suppression systems  Vehicle auto fire suppression systems  Improved mine stability and ground control Aggressive Culture Change  Leadership Academy  Leaders Forum  Focus on Values, Expectations, and Standards Notification System Vehicle Fire Suppression
  • 10. WIPP Recovery and Lessons Learned 10  Phase I - Interim Ventilation System  Two HEPA skids and fan units  114,000 cfm of airflow  Doubles the existing 60k cfm capacity  Ensures adequate air flow at the waste face for resumption of waste emplacement  Increase airflow for ground control and maintenance operations  Phase II – Supplemental Ventilation  Reconfiguring mine circuits and additional fans  180,000 cfm airflow  Phase III – Permanent Ventilation System  Design and construct a new (permanent) ventilation system  Capable to provide 420,000 cfm
  • 11. WIPP Recovery and Lessons Learned 11 National TRU Program  DOE released the Enhanced National TRU Program Plan (June 2016)  DOE placed HOLD on certifying TRU waste for shipment to WIPP until new requirements are met
  • 12. WIPP Recovery and Lessons Learned 12 National TRU Program – Moving Forward  Re-Certification of Generator Sites  Specific requirements for Previously Certified Waste  Chemical Compatibility Evaluation  Enhanced Acceptable Knowledge  Evaluation of oxidizing chemicals  Generator Site Technical Reviews
  • 13. WIPP Recovery and Lessons Learned 13 Prioritization of Shipments:  Initial focus of WIPP will be emplacement of waste currently in the Waste Handling Building  TRU site DOE Field Managers and DOE Headquarters met in August to begin the discussion of TRU waste shipping priorities
  • 14. WIPP Recovery and Lessons Learned 14 Incident Response Investigation U/G Recovery and Resumption of Ground Control (Bolting) Isolation of Panel 6 and Panel 7, Room 7 Equipment Procurements and Upgrades Interim Ventilation System Authorization to Proceed – Commence Waste Emplacement Operations DSA Revision and Implementation Cold Operations Management Self Assessment Safety Management Program Improvements Contractor Operational Readiness Review DOE Operational Readiness Review – Regulator Concurrence