SlideShare a Scribd company logo
1 of 19
W. Bollingerfehr – 09/2016
US/D Workshop
Washington, USA, Sept. 7-9, 2016
1
NEA/IAEA Workshop on Operational Safety:
- Summary of Presentations and Discussions -
Wilhelm Bollingerfehr
DBE TECHNOLOGY GmbH
Washington, DC
September 7-9, 2016
W. Bollingerfehr – 09/2016
US/D Workshop
Washington, USA, Sept. 7-9, 2016
2
Contents
• Background
• Objectives of the Workshop
• Workshop Format
• Workshop Summary and Future Challenges
W. Bollingerfehr – 09/2016
US/D Workshop
Washington, USA, Sept. 7-9, 2016
3
Background
For decades, geological disposal programmes
 focussed on long-term safety,
As programmes have matured:
 aspects related to engineering feasibility and operational safety
have received increasing attention.
 It has become apparent that operating a repository safelty for
many decades is a challenging undertaking,
 as is demonstrating operational safety at a level of detail
adequate to license such operations.
W. Bollingerfehr – 09/2016
US/D Workshop
Washington, USA, Sept. 7-9, 2016
4
Common Disposal Concepts
 Deep geological repositories will be
sited, designed, constructed, operated
and closed to isolate RW from the
accessible biosphere;
 Surface operations are as important as
activities in the underground (UG);
infrastructure like shafts and/or ramps
that connects the UG with the surface;
 Deep geological repositories may
remain operational for long period
(up to 100 yrs), may be expanded if
needed;
 ALARA and the defence-in-depth
strategy along with engineered
barriers are often applied to
minimize exposure risks.
W. Bollingerfehr – 09/2016
US/D Workshop
Washington, USA, Sept. 7-9, 2016
5
Repository Operations
 Surface facilities: typical processes
include waste acceptance, encapsulation
of conditioned waste; inspection, and
canister preparation / acceptance for
transfer to UG disposal;
 Ready packages are transferred in
shielded transfer cask;
 Emplacement of disposal canisters in UG
boreholes or cells;
 Exposure to workers and the public
during the operational phase is likely
similar as in other nuclear facilities.
Shielded driver cabin – locomotive
(Ondraf/Niras)
W. Bollingerfehr – 09/2016
US/D Workshop
Washington, USA, Sept. 7-9, 2016
6
Motivation for a Common Workshop
Both the NEA and the IAEA have long recognised the importance
of operational safety. Projects and work initiatives have been
carried out with different work scopes and objectives to address
various operational safety issues. For instance,
 The NEA IGSC created the Expert Group on Operational Safety
(EGOS) in 2013 to develop the best operating practices and the
optimal design provisions of geological repositories.
 IAEA had launched the GEOSAF Project in 2008 (a forum to
exchange ideas and experience on the development and review
of safety cases for geological disposal facilities).
 Consequentially a common workshop was initiated to share
information and experiences (NEA-OECD-headquarters in
Paris, July 2016)
W. Bollingerfehr – 09/2016
US/D Workshop
Washington, USA, Sept. 7-9, 2016
7
Objectives of the Workshop
 Explore how implementers address operational safety in
developing geological repositories for radioactive waste
disposal,
 Identify effective and practical design alternatives used to
achieve operational safety in geological repositories,
 Evaluate the adequacy and comprehensiveness of the existing
regulatory framework guiding implementers in addressing
operational safety in geological repositories and
 Identify areas and topics that require further work.
W. Bollingerfehr – 09/2016
US/D Workshop
Washington, USA, Sept. 7-9, 2016
8
Workshop Format
The workshop focuses on three key topics:
1) technical design aspects, e.g. fire risk management, on-site
transportation and emplacement;
2) repository regulatory framework and requirements; and
3) radiological protection issues in DGR,
each one consisting of introducing presentations followed by small
group discussions (guided by specific questions).
 45 Participants from 15 countries attended the Workshop, and
representatives from NEA and IAEA
W. Bollingerfehr – 09/2016
US/D Workshop
Washington, USA, Sept. 7-9, 2016
9
Worshop Summary and Future Challenges
1. Regulatory Environment
2. System design and Controls
3. Operational safety assessment and risk management
4. Monitoring and compliance control
5. Safety Culture
W. Bollingerfehr – 09/2016
US/D Workshop
Washington, USA, Sept. 7-9, 2016
10
1. Regulatory Environment
 Demonstrating compliance with a wide range of relevant
regulations and coordinating the work of multiple regulatory
bodies, and
 Building and adapting a regulatory system with clear
responsibilities of all involved regulatory bodies. It is also crucial
to maintain regulatory competence;
 Resolving the current lack of international guidance specifically
focussed on the operational safety of geological repositories and
investigating the possibility of integrating harmonising national
regulations;
 Preparing for an emergency situation.
W. Bollingerfehr – 09/2016
US/D Workshop
Washington, USA, Sept. 7-9, 2016
11
2. System Design and Controls 1/2
 dealing, e.g. through the development of waste acceptance
criteria, with the often wide range of waste types that can
arise over periods of decades, some of which give rise to
specific safety concerns (e.g. produce gases)
 striking a suitable balance between prevention of incidents
and accidents on the one hand and detection/mitigation on
the other,
 including “resilience” in design, i.e. the ability to respond /
recover effectively in the event of an incident or accident,
W. Bollingerfehr – 09/2016
US/D Workshop
Washington, USA, Sept. 7-9, 2016
12
2. System Design and Controls 2/2
 managing possible conflicts in safety requirements (e.g.
between fire safety requirements and provision of a good
working environment during normal operations when
planning ventilation systems) and, more generally, between
construction/operational safety and long-term safety, and
 implementing a system of change management during the
operational period, (must be properly documented for
transparency and also they can give rise to unforeseen
operational safety issues.
W. Bollingerfehr – 09/2016
US/D Workshop
Washington, USA, Sept. 7-9, 2016
13
Example: System Design and Controls
Iterative process of design development, with feedback from operational and long-term
safety assessments to design requirements or premises,
(as envisioned by SKB and Posiva)
W. Bollingerfehr – 09/2016
US/D Workshop
Washington, USA, Sept. 7-9, 2016
14
3. Operational Safety Assessment and Risk Management
 investigating the possibility to develop standardised high-
level approaches, e.g. to fire risk management,
 better justifying certain key model assumptions, e.g.
regarding the temperature and duration of fires,
 ensuring waste retrieval operations, if needed, can be
carried out safely in such a way that guarantees
safeguards and security, and
 promoting completeness in evaluating risks or hazards and
the ranges of potential consequences.
W. Bollingerfehr – 09/2016
US/D Workshop
Washington, USA, Sept. 7-9, 2016
15
4. Monitoring and Compliance Control 1/2
 clarifying regulatory expectations on monitoring at each
licencing stage,
 demonstrating and maintaining the reliability of monitoring
equipment,
 clarifying the extent to which equipment for monitoring
during the operational phase needs to be removed,
 identifying the role, nature and conditions for post-
operational monitoring,
W. Bollingerfehr – 09/2016
US/D Workshop
Washington, USA, Sept. 7-9, 2016
16
4. Monitoring and Compliance Control 2/2
 developing “safety envelopes” that define the ranges of
parameter values that are consistent with safety,
 clarifying what actions to take if parameter values that are
monitored are outside their respective safety envelopes
(including circumstances in which waste packages should
be retrieved), and
 clarifying the roles of underground research laboratories
and “pilot facilities” with regard to monitoring .
W. Bollingerfehr – 09/2016
US/D Workshop
Washington, USA, Sept. 7-9, 2016
17
5. Safety Culture
 maintaining the main focus of the organization on safety
over a period of many decades (e.g. continual support from
management, maintaining staff competence, preserving
corporate memory, etc),
 ensuring that schedules and cost concerns do not
compromise safety,
 resolving possible cultural differences between
construction personnel (miners) and operations personnel,
and
 demonstrating an adequate safety culture to stakeholders.
W. Bollingerfehr – 09/2016
US/D Workshop
Washington, USA, Sept. 7-9, 2016
18
Acknowlegements
Many Thanks to:
 NEA and IAEA as initiators and organizers of the workshop
 Workshop Programme Committee
 Chairpersons and rapporteurs
 Participants for presentations and discussions
 Paul Smith: Draft summary report
W. Bollingerfehr – 09/2016
US/D Workshop
Washington, USA, Sept. 7-9, 2016
19
Thank you
for your attention.

More Related Content

What's hot

27 task f fluid inclusion and movement in tight rocks wang sand2017-4132 pe...
27 task f   fluid inclusion and movement in tight rocks wang sand2017-4132 pe...27 task f   fluid inclusion and movement in tight rocks wang sand2017-4132 pe...
27 task f fluid inclusion and movement in tight rocks wang sand2017-4132 pe...leann_mays
 
25 herold 20160830 retrieval final
25 herold 20160830 retrieval final25 herold 20160830 retrieval final
25 herold 20160830 retrieval finalleann_mays
 
06 sevougian fe ps sand2016 8441-c rev2
06 sevougian fe ps sand2016 8441-c rev206 sevougian fe ps sand2016 8441-c rev2
06 sevougian fe ps sand2016 8441-c rev2leann_mays
 
Untangling the Web of Confusion Around the ASTM E1527-13 Phase I Standard
Untangling the Web of Confusion Around the ASTM E1527-13 Phase I StandardUntangling the Web of Confusion Around the ASTM E1527-13 Phase I Standard
Untangling the Web of Confusion Around the ASTM E1527-13 Phase I StandardEDR
 
43 international collaboration skb ebs task force overview jove-colon sand2...
43 international collaboration skb ebs task force   overview jove-colon sand2...43 international collaboration skb ebs task force   overview jove-colon sand2...
43 international collaboration skb ebs task force overview jove-colon sand2...leann_mays
 
27 kuhlman sand2016 8647 c hydrologic-modeling-v2
27 kuhlman sand2016 8647 c hydrologic-modeling-v227 kuhlman sand2016 8647 c hydrologic-modeling-v2
27 kuhlman sand2016 8647 c hydrologic-modeling-v2leann_mays
 
PIOGA/MSC Observations/Questions on PA DEP Radiation in Shale Drilling Study
PIOGA/MSC Observations/Questions on PA DEP Radiation in Shale Drilling StudyPIOGA/MSC Observations/Questions on PA DEP Radiation in Shale Drilling Study
PIOGA/MSC Observations/Questions on PA DEP Radiation in Shale Drilling StudyMarcellus Drilling News
 
28 voelzke sorenson issues of ageing sand2016 8277 c
28 voelzke sorenson issues of ageing sand2016 8277 c28 voelzke sorenson issues of ageing sand2016 8277 c
28 voelzke sorenson issues of ageing sand2016 8277 cleann_mays
 
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...Society of Petroleum Engineers
 
The New Era of National Ambient Air Quality Standards
The New Era of National Ambient Air Quality StandardsThe New Era of National Ambient Air Quality Standards
The New Era of National Ambient Air Quality StandardsAll4 Inc.
 
10 sfwst – disposal in argillite r&d barrier material degradation and int...
10 sfwst – disposal in argillite r&d barrier material degradation and int...10 sfwst – disposal in argillite r&d barrier material degradation and int...
10 sfwst – disposal in argillite r&d barrier material degradation and int...leann_mays
 
2014 Real Estate Inst (Otte Roek).PPTX
2014 Real Estate Inst (Otte Roek).PPTX2014 Real Estate Inst (Otte Roek).PPTX
2014 Real Estate Inst (Otte Roek).PPTXKatie Roek
 
Phase I Environmental Site Assessment Training Seminar
Phase I Environmental Site Assessment Training SeminarPhase I Environmental Site Assessment Training Seminar
Phase I Environmental Site Assessment Training SeminarBrandon Trate
 
Adams, Justin Resume
Adams, Justin Resume Adams, Justin Resume
Adams, Justin Resume justin adams
 

What's hot (19)

27 task f fluid inclusion and movement in tight rocks wang sand2017-4132 pe...
27 task f   fluid inclusion and movement in tight rocks wang sand2017-4132 pe...27 task f   fluid inclusion and movement in tight rocks wang sand2017-4132 pe...
27 task f fluid inclusion and movement in tight rocks wang sand2017-4132 pe...
 
25 herold 20160830 retrieval final
25 herold 20160830 retrieval final25 herold 20160830 retrieval final
25 herold 20160830 retrieval final
 
06 sevougian fe ps sand2016 8441-c rev2
06 sevougian fe ps sand2016 8441-c rev206 sevougian fe ps sand2016 8441-c rev2
06 sevougian fe ps sand2016 8441-c rev2
 
Untangling the Web of Confusion Around the ASTM E1527-13 Phase I Standard
Untangling the Web of Confusion Around the ASTM E1527-13 Phase I StandardUntangling the Web of Confusion Around the ASTM E1527-13 Phase I Standard
Untangling the Web of Confusion Around the ASTM E1527-13 Phase I Standard
 
43 international collaboration skb ebs task force overview jove-colon sand2...
43 international collaboration skb ebs task force   overview jove-colon sand2...43 international collaboration skb ebs task force   overview jove-colon sand2...
43 international collaboration skb ebs task force overview jove-colon sand2...
 
27 kuhlman sand2016 8647 c hydrologic-modeling-v2
27 kuhlman sand2016 8647 c hydrologic-modeling-v227 kuhlman sand2016 8647 c hydrologic-modeling-v2
27 kuhlman sand2016 8647 c hydrologic-modeling-v2
 
PIOGA/MSC Observations/Questions on PA DEP Radiation in Shale Drilling Study
PIOGA/MSC Observations/Questions on PA DEP Radiation in Shale Drilling StudyPIOGA/MSC Observations/Questions on PA DEP Radiation in Shale Drilling Study
PIOGA/MSC Observations/Questions on PA DEP Radiation in Shale Drilling Study
 
28 voelzke sorenson issues of ageing sand2016 8277 c
28 voelzke sorenson issues of ageing sand2016 8277 c28 voelzke sorenson issues of ageing sand2016 8277 c
28 voelzke sorenson issues of ageing sand2016 8277 c
 
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
 
Don Lawton (CMC Research Institutes) - Monitoring Conformance and Containment...
Don Lawton (CMC Research Institutes) - Monitoring Conformance and Containment...Don Lawton (CMC Research Institutes) - Monitoring Conformance and Containment...
Don Lawton (CMC Research Institutes) - Monitoring Conformance and Containment...
 
Don Lawton (CMC) at UKCCSRC-CMC Workshop, 20-21 April 2015
Don Lawton (CMC) at UKCCSRC-CMC Workshop, 20-21 April 2015Don Lawton (CMC) at UKCCSRC-CMC Workshop, 20-21 April 2015
Don Lawton (CMC) at UKCCSRC-CMC Workshop, 20-21 April 2015
 
Sand2018 0581 o metadata for presentations 011918 lac
Sand2018 0581 o metadata for presentations 011918 lacSand2018 0581 o metadata for presentations 011918 lac
Sand2018 0581 o metadata for presentations 011918 lac
 
Bell Creek, USA
Bell Creek, USABell Creek, USA
Bell Creek, USA
 
The New Era of National Ambient Air Quality Standards
The New Era of National Ambient Air Quality StandardsThe New Era of National Ambient Air Quality Standards
The New Era of National Ambient Air Quality Standards
 
10 sfwst – disposal in argillite r&d barrier material degradation and int...
10 sfwst – disposal in argillite r&d barrier material degradation and int...10 sfwst – disposal in argillite r&d barrier material degradation and int...
10 sfwst – disposal in argillite r&d barrier material degradation and int...
 
2014 Real Estate Inst (Otte Roek).PPTX
2014 Real Estate Inst (Otte Roek).PPTX2014 Real Estate Inst (Otte Roek).PPTX
2014 Real Estate Inst (Otte Roek).PPTX
 
Phase I Environmental Site Assessment Training Seminar
Phase I Environmental Site Assessment Training SeminarPhase I Environmental Site Assessment Training Seminar
Phase I Environmental Site Assessment Training Seminar
 
Adams, Justin Resume
Adams, Justin Resume Adams, Justin Resume
Adams, Justin Resume
 
JRyan2014
JRyan2014JRyan2014
JRyan2014
 

Viewers also liked

16 wolters lux fluid dynamic processes
16 wolters lux fluid dynamic processes16 wolters lux fluid dynamic processes
16 wolters lux fluid dynamic processesleann_mays
 
27 kuhlman basin scale density-dependent groundwate sand2016-9236 a
27 kuhlman basin scale density-dependent groundwate sand2016-9236 a27 kuhlman basin scale density-dependent groundwate sand2016-9236 a
27 kuhlman basin scale density-dependent groundwate sand2016-9236 aleann_mays
 
22 hesse capillary controls
22 hesse capillary controls22 hesse capillary controls
22 hesse capillary controlsleann_mays
 
21a discussion wieczorek plugging and sealing
21a discussion wieczorek plugging and sealing21a discussion wieczorek plugging and sealing
21a discussion wieczorek plugging and sealingleann_mays
 
25 herold impact of retrieval requirements
25 herold impact of retrieval requirements 25 herold impact of retrieval requirements
25 herold impact of retrieval requirements leann_mays
 
18 wieczorek dopas
18 wieczorek dopas18 wieczorek dopas
18 wieczorek dopasleann_mays
 
08 bollingerfehr nea and iaea workshop
08 bollingerfehr nea and iaea workshop08 bollingerfehr nea and iaea workshop
08 bollingerfehr nea and iaea workshopleann_mays
 
19 herold 20160830 elsa final
19 herold 20160830 elsa final19 herold 20160830 elsa final
19 herold 20160830 elsa finalleann_mays
 
08 kuhnlenz first results of the kosina project
08 kuhnlenz first results of the kosina project08 kuhnlenz first results of the kosina project
08 kuhnlenz first results of the kosina projectleann_mays
 
03 wolf safety case
03 wolf safety case03 wolf safety case
03 wolf safety caseleann_mays
 
02 orrell international perspectives
02 orrell international perspectives02 orrell international perspectives
02 orrell international perspectivesleann_mays
 
12 reedlunn reinvestigation into closure
12 reedlunn reinvestigation into closure12 reedlunn reinvestigation into closure
12 reedlunn reinvestigation into closureleann_mays
 
26 gunter deep borehole disposal
26 gunter deep borehole disposal26 gunter deep borehole disposal
26 gunter deep borehole disposalleann_mays
 
17 popp minkley teutschenthal
17 popp   minkley teutschenthal17 popp   minkley teutschenthal
17 popp minkley teutschenthalleann_mays
 
Sand2016 7915 c contributed images on template 081616
Sand2016 7915 c contributed images on template 081616Sand2016 7915 c contributed images on template 081616
Sand2016 7915 c contributed images on template 081616leann_mays
 
09 reynolds wipp recovery and lessons learned
09 reynolds wipp recovery and lessons learned09 reynolds wipp recovery and lessons learned
09 reynolds wipp recovery and lessons learnedleann_mays
 
24a kuhlman percolation discussion
24a kuhlman percolation discussion24a kuhlman percolation discussion
24a kuhlman percolation discussionleann_mays
 

Viewers also liked (20)

16 wolters lux fluid dynamic processes
16 wolters lux fluid dynamic processes16 wolters lux fluid dynamic processes
16 wolters lux fluid dynamic processes
 
27 kuhlman basin scale density-dependent groundwate sand2016-9236 a
27 kuhlman basin scale density-dependent groundwate sand2016-9236 a27 kuhlman basin scale density-dependent groundwate sand2016-9236 a
27 kuhlman basin scale density-dependent groundwate sand2016-9236 a
 
7th us german workshop photos sand2016 9820 w
7th us german workshop photos sand2016 9820 w7th us german workshop photos sand2016 9820 w
7th us german workshop photos sand2016 9820 w
 
22 hesse capillary controls
22 hesse capillary controls22 hesse capillary controls
22 hesse capillary controls
 
21a discussion wieczorek plugging and sealing
21a discussion wieczorek plugging and sealing21a discussion wieczorek plugging and sealing
21a discussion wieczorek plugging and sealing
 
25 herold impact of retrieval requirements
25 herold impact of retrieval requirements 25 herold impact of retrieval requirements
25 herold impact of retrieval requirements
 
18 wieczorek dopas
18 wieczorek dopas18 wieczorek dopas
18 wieczorek dopas
 
08 bollingerfehr nea and iaea workshop
08 bollingerfehr nea and iaea workshop08 bollingerfehr nea and iaea workshop
08 bollingerfehr nea and iaea workshop
 
19 herold 20160830 elsa final
19 herold 20160830 elsa final19 herold 20160830 elsa final
19 herold 20160830 elsa final
 
Salt group shots
Salt group shotsSalt group shots
Salt group shots
 
08 kuhnlenz first results of the kosina project
08 kuhnlenz first results of the kosina project08 kuhnlenz first results of the kosina project
08 kuhnlenz first results of the kosina project
 
03 wolf safety case
03 wolf safety case03 wolf safety case
03 wolf safety case
 
02 orrell international perspectives
02 orrell international perspectives02 orrell international perspectives
02 orrell international perspectives
 
12 reedlunn reinvestigation into closure
12 reedlunn reinvestigation into closure12 reedlunn reinvestigation into closure
12 reedlunn reinvestigation into closure
 
26 gunter deep borehole disposal
26 gunter deep borehole disposal26 gunter deep borehole disposal
26 gunter deep borehole disposal
 
17 popp minkley teutschenthal
17 popp   minkley teutschenthal17 popp   minkley teutschenthal
17 popp minkley teutschenthal
 
24 hammer zulauf us german_2016
24 hammer zulauf us german_201624 hammer zulauf us german_2016
24 hammer zulauf us german_2016
 
Sand2016 7915 c contributed images on template 081616
Sand2016 7915 c contributed images on template 081616Sand2016 7915 c contributed images on template 081616
Sand2016 7915 c contributed images on template 081616
 
09 reynolds wipp recovery and lessons learned
09 reynolds wipp recovery and lessons learned09 reynolds wipp recovery and lessons learned
09 reynolds wipp recovery and lessons learned
 
24a kuhlman percolation discussion
24a kuhlman percolation discussion24a kuhlman percolation discussion
24a kuhlman percolation discussion
 

Similar to 07 bollingerfehr nea iaea_workshop

Zahir - Technical Safety - 2017
Zahir - Technical Safety - 2017Zahir - Technical Safety - 2017
Zahir - Technical Safety - 2017Zahir Patel
 
6 - A Risk Analysis Framework for Offshore Wind Turbines - Gkoumas
6 - A Risk Analysis Framework for Offshore Wind Turbines - Gkoumas6 - A Risk Analysis Framework for Offshore Wind Turbines - Gkoumas
6 - A Risk Analysis Framework for Offshore Wind Turbines - GkoumasStroNGER2012
 
03 wolf safety case german approach
03 wolf safety case german approach03 wolf safety case german approach
03 wolf safety case german approachleann_mays
 
Safety for offshore structure
Safety for offshore structureSafety for offshore structure
Safety for offshore structureOFFSHORE VN
 
Tubine foundation design
Tubine foundation designTubine foundation design
Tubine foundation designniketmahajan
 
Safety Assurance and Certification: Current Practices, Challenges, and Brains...
Safety Assurance and Certification: Current Practices, Challenges, and Brains...Safety Assurance and Certification: Current Practices, Challenges, and Brains...
Safety Assurance and Certification: Current Practices, Challenges, and Brains...Roberto Natella
 
Hector M Morales Safety Resume
Hector M Morales Safety ResumeHector M Morales Safety Resume
Hector M Morales Safety ResumeMorales Hector
 

Similar to 07 bollingerfehr nea iaea_workshop (20)

INCASS Newsletter_8
INCASS Newsletter_8INCASS Newsletter_8
INCASS Newsletter_8
 
M2 sf 17sn010303011-sand2017-1057r
M2 sf 17sn010303011-sand2017-1057rM2 sf 17sn010303011-sand2017-1057r
M2 sf 17sn010303011-sand2017-1057r
 
6x process
6x process6x process
6x process
 
Zahir - Technical Safety - 2017
Zahir - Technical Safety - 2017Zahir - Technical Safety - 2017
Zahir - Technical Safety - 2017
 
6 - A Risk Analysis Framework for Offshore Wind Turbines - Gkoumas
6 - A Risk Analysis Framework for Offshore Wind Turbines - Gkoumas6 - A Risk Analysis Framework for Offshore Wind Turbines - Gkoumas
6 - A Risk Analysis Framework for Offshore Wind Turbines - Gkoumas
 
M4 sf 18sn010303061 8th us german 020918 lac reduced sand2018-1339r
M4 sf 18sn010303061 8th us german 020918 lac reduced sand2018-1339rM4 sf 18sn010303061 8th us german 020918 lac reduced sand2018-1339r
M4 sf 18sn010303061 8th us german 020918 lac reduced sand2018-1339r
 
03 wolf safety case german approach
03 wolf safety case german approach03 wolf safety case german approach
03 wolf safety case german approach
 
INCASS Newsletter_10
INCASS Newsletter_10INCASS Newsletter_10
INCASS Newsletter_10
 
Safety for offshore structure
Safety for offshore structureSafety for offshore structure
Safety for offshore structure
 
Tubine foundation design
Tubine foundation designTubine foundation design
Tubine foundation design
 
Te 1484 web
Te 1484 webTe 1484 web
Te 1484 web
 
Alan Smith NSC update for IAEA - Oct '17.pptx
Alan Smith NSC update for IAEA - Oct '17.pptxAlan Smith NSC update for IAEA - Oct '17.pptx
Alan Smith NSC update for IAEA - Oct '17.pptx
 
Rbi final report
Rbi final reportRbi final report
Rbi final report
 
Lauren A. Blakley
Lauren A. BlakleyLauren A. Blakley
Lauren A. Blakley
 
INCASS-Newsletter_9
INCASS-Newsletter_9INCASS-Newsletter_9
INCASS-Newsletter_9
 
Eugenia valsami jones university of birmingham
Eugenia valsami jones   university of birminghamEugenia valsami jones   university of birmingham
Eugenia valsami jones university of birmingham
 
Reduced size m3 ft 15sn08180210 hansen
Reduced size m3 ft 15sn08180210 hansenReduced size m3 ft 15sn08180210 hansen
Reduced size m3 ft 15sn08180210 hansen
 
Minisymposium
MinisymposiumMinisymposium
Minisymposium
 
Safety Assurance and Certification: Current Practices, Challenges, and Brains...
Safety Assurance and Certification: Current Practices, Challenges, and Brains...Safety Assurance and Certification: Current Practices, Challenges, and Brains...
Safety Assurance and Certification: Current Practices, Challenges, and Brains...
 
Hector M Morales Safety Resume
Hector M Morales Safety ResumeHector M Morales Safety Resume
Hector M Morales Safety Resume
 

More from leann_mays

13 ensa enun 32 p rail cask transport tests start june 2017 mcconnell sand201...
13 ensa enun 32 p rail cask transport tests start june 2017 mcconnell sand201...13 ensa enun 32 p rail cask transport tests start june 2017 mcconnell sand201...
13 ensa enun 32 p rail cask transport tests start june 2017 mcconnell sand201...leann_mays
 
03 dry cask simulator experiments for cfd validation durbin sand2017 4330 c
03 dry cask simulator experiments for cfd validation durbin sand2017 4330 c03 dry cask simulator experiments for cfd validation durbin sand2017 4330 c
03 dry cask simulator experiments for cfd validation durbin sand2017 4330 cleann_mays
 
17 laboratory testing approach for intermediate scale borehole heater test mi...
17 laboratory testing approach for intermediate scale borehole heater test mi...17 laboratory testing approach for intermediate scale borehole heater test mi...
17 laboratory testing approach for intermediate scale borehole heater test mi...leann_mays
 
07 international collaboration activities in disposal r and d relevance to r ...
07 international collaboration activities in disposal r and d relevance to r ...07 international collaboration activities in disposal r and d relevance to r ...
07 international collaboration activities in disposal r and d relevance to r ...leann_mays
 
59 an example of a regional geologic evaluation of argillite for disposal of ...
59 an example of a regional geologic evaluation of argillite for disposal of ...59 an example of a regional geologic evaluation of argillite for disposal of ...
59 an example of a regional geologic evaluation of argillite for disposal of ...leann_mays
 
51 update on the fifth worldwide review international approaches for nuclear ...
51 update on the fifth worldwide review international approaches for nuclear ...51 update on the fifth worldwide review international approaches for nuclear ...
51 update on the fifth worldwide review international approaches for nuclear ...leann_mays
 
49 collaboration with swedish deep drilling project dobson lbnl
49 collaboration with swedish deep drilling project dobson lbnl49 collaboration with swedish deep drilling project dobson lbnl
49 collaboration with swedish deep drilling project dobson lbnlleann_mays
 
46 collaboration with clausthal germany on coupled thm modeling rutqvist lbnl
46 collaboration with clausthal germany on coupled thm modeling rutqvist lbnl46 collaboration with clausthal germany on coupled thm modeling rutqvist lbnl
46 collaboration with clausthal germany on coupled thm modeling rutqvist lbnlleann_mays
 
34 ciscc susceptibility and cgr testing sindelar srnl sti-2017-00323
34 ciscc susceptibility and cgr testing sindelar srnl sti-2017-0032334 ciscc susceptibility and cgr testing sindelar srnl sti-2017-00323
34 ciscc susceptibility and cgr testing sindelar srnl sti-2017-00323leann_mays
 
33 residual stress simulation and experimental stress replication of mock up ...
33 residual stress simulation and experimental stress replication of mock up ...33 residual stress simulation and experimental stress replication of mock up ...
33 residual stress simulation and experimental stress replication of mock up ...leann_mays
 
32 field test at maine yankee independent spent fuel storage instillation gor...
32 field test at maine yankee independent spent fuel storage instillation gor...32 field test at maine yankee independent spent fuel storage instillation gor...
32 field test at maine yankee independent spent fuel storage instillation gor...leann_mays
 
30 fe heater test at mont terri rutqvist lbnl
30 fe heater test at mont terri rutqvist lbnl30 fe heater test at mont terri rutqvist lbnl
30 fe heater test at mont terri rutqvist lbnlleann_mays
 
29 international collaboration in disposal research fs experiment at mont ter...
29 international collaboration in disposal research fs experiment at mont ter...29 international collaboration in disposal research fs experiment at mont ter...
29 international collaboration in disposal research fs experiment at mont ter...leann_mays
 
28 international collaboration in disposal research mont terri project birkho...
28 international collaboration in disposal research mont terri project birkho...28 international collaboration in disposal research mont terri project birkho...
28 international collaboration in disposal research mont terri project birkho...leann_mays
 
27b potential hot bent collaboration zheng v0 lbnl
27b potential hot bent collaboration zheng v0 lbnl27b potential hot bent collaboration zheng v0 lbnl
27b potential hot bent collaboration zheng v0 lbnlleann_mays
 
27a febex dp collaboration overview and related sfwst r and d activities zhen...
27a febex dp collaboration overview and related sfwst r and d activities zhen...27a febex dp collaboration overview and related sfwst r and d activities zhen...
27a febex dp collaboration overview and related sfwst r and d activities zhen...leann_mays
 
25 decovalex 2019 geochemical and reactive transport evaluations with relevan...
25 decovalex 2019 geochemical and reactive transport evaluations with relevan...25 decovalex 2019 geochemical and reactive transport evaluations with relevan...
25 decovalex 2019 geochemical and reactive transport evaluations with relevan...leann_mays
 
24 upscaling of heater tests in bure rutqvist lbnl
24 upscaling of heater tests in bure rutqvist lbnl24 upscaling of heater tests in bure rutqvist lbnl
24 upscaling of heater tests in bure rutqvist lbnlleann_mays
 
23 international collaboration in disposal research decovalex 2019 birkholzer...
23 international collaboration in disposal research decovalex 2019 birkholzer...23 international collaboration in disposal research decovalex 2019 birkholzer...
23 international collaboration in disposal research decovalex 2019 birkholzer...leann_mays
 
22 international collaboration in disposal research introduction birkholzer lbnl
22 international collaboration in disposal research introduction birkholzer lbnl22 international collaboration in disposal research introduction birkholzer lbnl
22 international collaboration in disposal research introduction birkholzer lbnlleann_mays
 

More from leann_mays (20)

13 ensa enun 32 p rail cask transport tests start june 2017 mcconnell sand201...
13 ensa enun 32 p rail cask transport tests start june 2017 mcconnell sand201...13 ensa enun 32 p rail cask transport tests start june 2017 mcconnell sand201...
13 ensa enun 32 p rail cask transport tests start june 2017 mcconnell sand201...
 
03 dry cask simulator experiments for cfd validation durbin sand2017 4330 c
03 dry cask simulator experiments for cfd validation durbin sand2017 4330 c03 dry cask simulator experiments for cfd validation durbin sand2017 4330 c
03 dry cask simulator experiments for cfd validation durbin sand2017 4330 c
 
17 laboratory testing approach for intermediate scale borehole heater test mi...
17 laboratory testing approach for intermediate scale borehole heater test mi...17 laboratory testing approach for intermediate scale borehole heater test mi...
17 laboratory testing approach for intermediate scale borehole heater test mi...
 
07 international collaboration activities in disposal r and d relevance to r ...
07 international collaboration activities in disposal r and d relevance to r ...07 international collaboration activities in disposal r and d relevance to r ...
07 international collaboration activities in disposal r and d relevance to r ...
 
59 an example of a regional geologic evaluation of argillite for disposal of ...
59 an example of a regional geologic evaluation of argillite for disposal of ...59 an example of a regional geologic evaluation of argillite for disposal of ...
59 an example of a regional geologic evaluation of argillite for disposal of ...
 
51 update on the fifth worldwide review international approaches for nuclear ...
51 update on the fifth worldwide review international approaches for nuclear ...51 update on the fifth worldwide review international approaches for nuclear ...
51 update on the fifth worldwide review international approaches for nuclear ...
 
49 collaboration with swedish deep drilling project dobson lbnl
49 collaboration with swedish deep drilling project dobson lbnl49 collaboration with swedish deep drilling project dobson lbnl
49 collaboration with swedish deep drilling project dobson lbnl
 
46 collaboration with clausthal germany on coupled thm modeling rutqvist lbnl
46 collaboration with clausthal germany on coupled thm modeling rutqvist lbnl46 collaboration with clausthal germany on coupled thm modeling rutqvist lbnl
46 collaboration with clausthal germany on coupled thm modeling rutqvist lbnl
 
34 ciscc susceptibility and cgr testing sindelar srnl sti-2017-00323
34 ciscc susceptibility and cgr testing sindelar srnl sti-2017-0032334 ciscc susceptibility and cgr testing sindelar srnl sti-2017-00323
34 ciscc susceptibility and cgr testing sindelar srnl sti-2017-00323
 
33 residual stress simulation and experimental stress replication of mock up ...
33 residual stress simulation and experimental stress replication of mock up ...33 residual stress simulation and experimental stress replication of mock up ...
33 residual stress simulation and experimental stress replication of mock up ...
 
32 field test at maine yankee independent spent fuel storage instillation gor...
32 field test at maine yankee independent spent fuel storage instillation gor...32 field test at maine yankee independent spent fuel storage instillation gor...
32 field test at maine yankee independent spent fuel storage instillation gor...
 
30 fe heater test at mont terri rutqvist lbnl
30 fe heater test at mont terri rutqvist lbnl30 fe heater test at mont terri rutqvist lbnl
30 fe heater test at mont terri rutqvist lbnl
 
29 international collaboration in disposal research fs experiment at mont ter...
29 international collaboration in disposal research fs experiment at mont ter...29 international collaboration in disposal research fs experiment at mont ter...
29 international collaboration in disposal research fs experiment at mont ter...
 
28 international collaboration in disposal research mont terri project birkho...
28 international collaboration in disposal research mont terri project birkho...28 international collaboration in disposal research mont terri project birkho...
28 international collaboration in disposal research mont terri project birkho...
 
27b potential hot bent collaboration zheng v0 lbnl
27b potential hot bent collaboration zheng v0 lbnl27b potential hot bent collaboration zheng v0 lbnl
27b potential hot bent collaboration zheng v0 lbnl
 
27a febex dp collaboration overview and related sfwst r and d activities zhen...
27a febex dp collaboration overview and related sfwst r and d activities zhen...27a febex dp collaboration overview and related sfwst r and d activities zhen...
27a febex dp collaboration overview and related sfwst r and d activities zhen...
 
25 decovalex 2019 geochemical and reactive transport evaluations with relevan...
25 decovalex 2019 geochemical and reactive transport evaluations with relevan...25 decovalex 2019 geochemical and reactive transport evaluations with relevan...
25 decovalex 2019 geochemical and reactive transport evaluations with relevan...
 
24 upscaling of heater tests in bure rutqvist lbnl
24 upscaling of heater tests in bure rutqvist lbnl24 upscaling of heater tests in bure rutqvist lbnl
24 upscaling of heater tests in bure rutqvist lbnl
 
23 international collaboration in disposal research decovalex 2019 birkholzer...
23 international collaboration in disposal research decovalex 2019 birkholzer...23 international collaboration in disposal research decovalex 2019 birkholzer...
23 international collaboration in disposal research decovalex 2019 birkholzer...
 
22 international collaboration in disposal research introduction birkholzer lbnl
22 international collaboration in disposal research introduction birkholzer lbnl22 international collaboration in disposal research introduction birkholzer lbnl
22 international collaboration in disposal research introduction birkholzer lbnl
 

Recently uploaded

Science&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdfScience&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdfjimielynbastida
 
Build your next Gen AI Breakthrough - April 2024
Build your next Gen AI Breakthrough - April 2024Build your next Gen AI Breakthrough - April 2024
Build your next Gen AI Breakthrough - April 2024Neo4j
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksSoftradix Technologies
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024BookNet Canada
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024BookNet Canada
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentationphoebematthew05
 
Unlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power SystemsUnlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power SystemsPrecisely
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptxLBM Solutions
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 

Recently uploaded (20)

Hot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort Service
Hot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort ServiceHot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort Service
Hot Sexy call girls in Panjabi Bagh 🔝 9953056974 🔝 Delhi escort Service
 
Science&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdfScience&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdf
 
Build your next Gen AI Breakthrough - April 2024
Build your next Gen AI Breakthrough - April 2024Build your next Gen AI Breakthrough - April 2024
Build your next Gen AI Breakthrough - April 2024
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
Vulnerability_Management_GRC_by Sohang Sengupta.pptx
Vulnerability_Management_GRC_by Sohang Sengupta.pptxVulnerability_Management_GRC_by Sohang Sengupta.pptx
Vulnerability_Management_GRC_by Sohang Sengupta.pptx
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other Frameworks
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentation
 
Unlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power SystemsUnlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power Systems
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptx
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 

07 bollingerfehr nea iaea_workshop

  • 1. W. Bollingerfehr – 09/2016 US/D Workshop Washington, USA, Sept. 7-9, 2016 1 NEA/IAEA Workshop on Operational Safety: - Summary of Presentations and Discussions - Wilhelm Bollingerfehr DBE TECHNOLOGY GmbH Washington, DC September 7-9, 2016
  • 2. W. Bollingerfehr – 09/2016 US/D Workshop Washington, USA, Sept. 7-9, 2016 2 Contents • Background • Objectives of the Workshop • Workshop Format • Workshop Summary and Future Challenges
  • 3. W. Bollingerfehr – 09/2016 US/D Workshop Washington, USA, Sept. 7-9, 2016 3 Background For decades, geological disposal programmes  focussed on long-term safety, As programmes have matured:  aspects related to engineering feasibility and operational safety have received increasing attention.  It has become apparent that operating a repository safelty for many decades is a challenging undertaking,  as is demonstrating operational safety at a level of detail adequate to license such operations.
  • 4. W. Bollingerfehr – 09/2016 US/D Workshop Washington, USA, Sept. 7-9, 2016 4 Common Disposal Concepts  Deep geological repositories will be sited, designed, constructed, operated and closed to isolate RW from the accessible biosphere;  Surface operations are as important as activities in the underground (UG); infrastructure like shafts and/or ramps that connects the UG with the surface;  Deep geological repositories may remain operational for long period (up to 100 yrs), may be expanded if needed;  ALARA and the defence-in-depth strategy along with engineered barriers are often applied to minimize exposure risks.
  • 5. W. Bollingerfehr – 09/2016 US/D Workshop Washington, USA, Sept. 7-9, 2016 5 Repository Operations  Surface facilities: typical processes include waste acceptance, encapsulation of conditioned waste; inspection, and canister preparation / acceptance for transfer to UG disposal;  Ready packages are transferred in shielded transfer cask;  Emplacement of disposal canisters in UG boreholes or cells;  Exposure to workers and the public during the operational phase is likely similar as in other nuclear facilities. Shielded driver cabin – locomotive (Ondraf/Niras)
  • 6. W. Bollingerfehr – 09/2016 US/D Workshop Washington, USA, Sept. 7-9, 2016 6 Motivation for a Common Workshop Both the NEA and the IAEA have long recognised the importance of operational safety. Projects and work initiatives have been carried out with different work scopes and objectives to address various operational safety issues. For instance,  The NEA IGSC created the Expert Group on Operational Safety (EGOS) in 2013 to develop the best operating practices and the optimal design provisions of geological repositories.  IAEA had launched the GEOSAF Project in 2008 (a forum to exchange ideas and experience on the development and review of safety cases for geological disposal facilities).  Consequentially a common workshop was initiated to share information and experiences (NEA-OECD-headquarters in Paris, July 2016)
  • 7. W. Bollingerfehr – 09/2016 US/D Workshop Washington, USA, Sept. 7-9, 2016 7 Objectives of the Workshop  Explore how implementers address operational safety in developing geological repositories for radioactive waste disposal,  Identify effective and practical design alternatives used to achieve operational safety in geological repositories,  Evaluate the adequacy and comprehensiveness of the existing regulatory framework guiding implementers in addressing operational safety in geological repositories and  Identify areas and topics that require further work.
  • 8. W. Bollingerfehr – 09/2016 US/D Workshop Washington, USA, Sept. 7-9, 2016 8 Workshop Format The workshop focuses on three key topics: 1) technical design aspects, e.g. fire risk management, on-site transportation and emplacement; 2) repository regulatory framework and requirements; and 3) radiological protection issues in DGR, each one consisting of introducing presentations followed by small group discussions (guided by specific questions).  45 Participants from 15 countries attended the Workshop, and representatives from NEA and IAEA
  • 9. W. Bollingerfehr – 09/2016 US/D Workshop Washington, USA, Sept. 7-9, 2016 9 Worshop Summary and Future Challenges 1. Regulatory Environment 2. System design and Controls 3. Operational safety assessment and risk management 4. Monitoring and compliance control 5. Safety Culture
  • 10. W. Bollingerfehr – 09/2016 US/D Workshop Washington, USA, Sept. 7-9, 2016 10 1. Regulatory Environment  Demonstrating compliance with a wide range of relevant regulations and coordinating the work of multiple regulatory bodies, and  Building and adapting a regulatory system with clear responsibilities of all involved regulatory bodies. It is also crucial to maintain regulatory competence;  Resolving the current lack of international guidance specifically focussed on the operational safety of geological repositories and investigating the possibility of integrating harmonising national regulations;  Preparing for an emergency situation.
  • 11. W. Bollingerfehr – 09/2016 US/D Workshop Washington, USA, Sept. 7-9, 2016 11 2. System Design and Controls 1/2  dealing, e.g. through the development of waste acceptance criteria, with the often wide range of waste types that can arise over periods of decades, some of which give rise to specific safety concerns (e.g. produce gases)  striking a suitable balance between prevention of incidents and accidents on the one hand and detection/mitigation on the other,  including “resilience” in design, i.e. the ability to respond / recover effectively in the event of an incident or accident,
  • 12. W. Bollingerfehr – 09/2016 US/D Workshop Washington, USA, Sept. 7-9, 2016 12 2. System Design and Controls 2/2  managing possible conflicts in safety requirements (e.g. between fire safety requirements and provision of a good working environment during normal operations when planning ventilation systems) and, more generally, between construction/operational safety and long-term safety, and  implementing a system of change management during the operational period, (must be properly documented for transparency and also they can give rise to unforeseen operational safety issues.
  • 13. W. Bollingerfehr – 09/2016 US/D Workshop Washington, USA, Sept. 7-9, 2016 13 Example: System Design and Controls Iterative process of design development, with feedback from operational and long-term safety assessments to design requirements or premises, (as envisioned by SKB and Posiva)
  • 14. W. Bollingerfehr – 09/2016 US/D Workshop Washington, USA, Sept. 7-9, 2016 14 3. Operational Safety Assessment and Risk Management  investigating the possibility to develop standardised high- level approaches, e.g. to fire risk management,  better justifying certain key model assumptions, e.g. regarding the temperature and duration of fires,  ensuring waste retrieval operations, if needed, can be carried out safely in such a way that guarantees safeguards and security, and  promoting completeness in evaluating risks or hazards and the ranges of potential consequences.
  • 15. W. Bollingerfehr – 09/2016 US/D Workshop Washington, USA, Sept. 7-9, 2016 15 4. Monitoring and Compliance Control 1/2  clarifying regulatory expectations on monitoring at each licencing stage,  demonstrating and maintaining the reliability of monitoring equipment,  clarifying the extent to which equipment for monitoring during the operational phase needs to be removed,  identifying the role, nature and conditions for post- operational monitoring,
  • 16. W. Bollingerfehr – 09/2016 US/D Workshop Washington, USA, Sept. 7-9, 2016 16 4. Monitoring and Compliance Control 2/2  developing “safety envelopes” that define the ranges of parameter values that are consistent with safety,  clarifying what actions to take if parameter values that are monitored are outside their respective safety envelopes (including circumstances in which waste packages should be retrieved), and  clarifying the roles of underground research laboratories and “pilot facilities” with regard to monitoring .
  • 17. W. Bollingerfehr – 09/2016 US/D Workshop Washington, USA, Sept. 7-9, 2016 17 5. Safety Culture  maintaining the main focus of the organization on safety over a period of many decades (e.g. continual support from management, maintaining staff competence, preserving corporate memory, etc),  ensuring that schedules and cost concerns do not compromise safety,  resolving possible cultural differences between construction personnel (miners) and operations personnel, and  demonstrating an adequate safety culture to stakeholders.
  • 18. W. Bollingerfehr – 09/2016 US/D Workshop Washington, USA, Sept. 7-9, 2016 18 Acknowlegements Many Thanks to:  NEA and IAEA as initiators and organizers of the workshop  Workshop Programme Committee  Chairpersons and rapporteurs  Participants for presentations and discussions  Paul Smith: Draft summary report
  • 19. W. Bollingerfehr – 09/2016 US/D Workshop Washington, USA, Sept. 7-9, 2016 19 Thank you for your attention.